Professional Documents
Culture Documents
Paper 2633V5-0
Introduction to measurement
Contents
Aims
Learning outcomes
1. Introduction
2. Taking off quantities
2.1 Group
2.2 Trade by trade
2.3 Scottish system
2.4 Traditional dimension paper
2.5 Brackets
2.6 Waste calculations
3. The use of a standard method of measurement
Appendix: Section 11, In-situ concrete works (NRM2)
Introduction to measurement
Aims
This paper aims to introduce you to the concept of measurement and its relationship
with the construction process and contract documentation.
Learning outcomes
After studying this paper you should be able to:
understand the purpose for which measurement is carried out at various stages
throughout the construction process.
Introduction to measurement
1 Introduction
The subject of measurement as a whole covers a wide field, and is a fundamental
study along with construction technology for all surveyors involved in
measurement and pricing. At this stage in your studies there is a need for a general
background of knowledge against which measurement can be set in perspective,
together with a need for selectivity and simplification in the matter presented for
preliminary study.
At this stage, it is perhaps pertinent to make some fundamental points:
The ultimate responsibility for the validity of measurement must rest with the
measurer, for although he may be constrained by conventions and rules of
measurement, he should never be totally constrained and must retain the
freedom to decide for himself whether he has satisfied the demands made of
him, whether he has produced an adequate tool for further use and whether he
has acted in the best interests of his client and the contractor.
The act of measurement and the processing of results into a communicable form for
use by others is time-consuming. Measurement is, however, only part of the skill of
the professional surveyor, whose real expertise rests in advising a prospective
building owner in all matters relating to the efficient use of his financial resources
during the construction process.
Introduction to measurement
2.1 Group
This is probably the most widely adopted system. The building is divided into its
functional parts or elements and these may then be subdivided according to
construction or location.
A typical list of elements would be:
Substructure
Frame
if one is applicable
External walls
Windows
Staircases
Roof
Internal walls
Doors
Internal finishes
Services
heating
ventilating
electrical
above ground
below ground
Upper floors
Drainage
External works
Introduction to measurement
The taker-off concentrates on one trade at a time and is therefore not distracted
by the requirements of other trades.
As soon as each section is taken off, the bill items can be prepared
immediately, which should save time in the final production of the document.
This system of taking off in final presentation order is useful for the preparation of
subcontractors bills and is essential when producing items of work to be rated by the
contractor and measured as the work proceeds (sometimes called schedule of rates).
Although many surveyors who adopt this system use the conventional type of takingoff paper, some north of England offices use specially ruled paper. There are several
different forms of ruling in use but the following is typical:
1
2/
4.00
5.25
3.50
3.00
1.50
Deduct
0.25
0.25
1.00
14.00 Room 1
15.75 Room 2
29.75
1.75 Beam Room 1
0.75 Beam Room 2
1.50 Lantern
4.00
25.75
26.00m
Columns
1
2
3
4
5
6
Use
Timesing
Length
Width
Depth
Squaring
Wastes and
references
Descriptions
written in full
across the columns
either above or
below the
dimensions
This approach is also readily adapted to spreadsheet use and entering into a computer.
Introduction to measurement
Traditional dimension paper is specially ruled A4. Each sheet is divided into two
parts, each part comprising four columns. The method of use is to write vertically
down the first half of the page and then down the second half. The description column
is the widest column and will also be used for preliminary calculations of the
dimensions required for an item (waste calculations). The dimensions are entered in
the centre column of the three narrow columns, usually in metres to two decimal
places. If there are more items with the same measurements for example 10 houses
being measured then the appropriate measurements may be multiplied by writing
the figure 10 in the timesing column.
The squaring column is for the product of any multiplication that may be required
(extending the dimensions).
Each sheet should be headed up with the reference to the work being measured and
the pages sequentially numbered.
Introduction to measurement
A cubic measurement
10.00m long
8.00m wide
2.00m high
10/5/ 10.00
8.00
2.00
A
cubic
item
multiplied by 5 for
one area and 10 for
furthur
identical
areas
A square measurenent
10.00m long
8.00m wide
Dotted on is a
term used to ass
more items of the
same size. A dot is
used in the
timesing column
10.00
A lineal measurement
10.00m long
A cubic
measurement
miltiplied by 7
.5/ 10.00
8.00
2.00
An enumerated item - 6
number of the item
Care should be
taken to ensure
that fractions are
written clearly and
cannot be confused
with 2 times 3
times.
5/ 10.00
8.00
A superficial item
multiplied by 5
2
/
3
10.00
8.00
2.00
A cubic
measurement
multiplied by two
thirds
Introduction to measurement
2.5 Brackets
It will be noticed, on the typical dimension sheet which follows (Example 2), that
there are some brackets drawn closely beside the line separating columns 3 and 4.
These brackets have a very important function, in that they bind together those
dimensions on the left with those descriptions on the right; without them the meaning
would be quite different in result.
Writers over the last few decades have given differing advice upon the use of this
bracket. The considered opinion of CEM is that it should be used for every item. If
this habit is acquired, there is little chance that errors and omissions will be made. But
if, as is sometimes advocated, it is used where there is plurality of dimensions, it has
been noticed that when speed has been increased many errors are made.
Remember at all stages of the work that clarity to a person other than the writer is
vital. A grasp of this will go a long way towards your success, and such fundamentals
as good figures, legible handwriting, recognisable abbreviations, ample explanatory
notes and orthodox procedure or system should follow as the logical expression of
this intention.
Introduction to measurement
11.35
20.15
width
8.400
2.600
11.000
0.345
15.300
4.500
19.800
0.345
11.345
20.145
Site preparation,
removal of topsoil
average 150mm thick
&
Retaining excavated
material on site,
topsoil, in temporary
spoil heap average
100m from excavation
0.15 =
1.45
2.30
Ddt
Removal of topsoil as
before
&
0.72
1.35
Ddt
Retaining topsoil in
temporary heaps
0.15 =
Notes:
Work
out
preliminary
dimentions first.
These are normally
to three decimal
places.
(Waste
calculations.)
Align descriptions
and dimensions.
The format and
content of the
description is
governed by the
standard method of
measurement (see
section on the use
of a standard
method of
measurement). The
ampesand is used
to save writing the
dimensions again.
The topsoil
excavation is
required to be
measured in square
metres whereas the
depositing is cubic
and this method is
the accepted short
cut to use.
Introduction to measurement
Overseas students should make notes throughout this module on the way their
standard method requires work to be measured and described. Look for explanatory
guides on the items for which clear direction is not given. NRMA identifies what is
deemed included in a measure or description. This may only be implied into some
standard methods and tradition should be investigated to ensure full understanding.
Introduction to measurement
1
2
3
4
In-situ concrete
Surface finishes to in-situ concrete
Formwork
Reinforcement
Designed joints in in-situ concrete
Accessories cast in to in-situ concrete
In-situ concrete sundries
11
Mandatory information to be
provided.
1
2
3
4
1 In filling voids.
2 In trench filling.
3 In any other situation: details
stated.
1 In blinding.
2 In structures.
1 In blinding.
2 In structures.
3 In staircases.
1 Any thickness.
1 300 thick.
2 > 300 thick.
1 300 thick.
2 > 300 thick.
m3
m3
m3
1 Mass concrete
2 Horizontal work
3 Sloping work 15
4 Sloping work > 15
Level two
Level one
Unit
Level three
8
9
10
11
12
Trowelling
Power floating
Hacking
Grinding
Any other surface treatment not left
to discretion of the contractor
m2
1 To top surfaces.
2 To faces.
3 To soffits.
1 Thickness stated.
m2
1 Application of surface
hardeners, sealers, dust
proofers, waterproofers,
carborundum grains or the like
shall be so described.
1 Curved.
2 Walls.
3 Beams.
4 Columns.
1 Sloping.
2 Falls.
3 Crossfalls.
1 Tops.
2 Soffits.
3 Curved.
Level three
1 Slabs.
1 Horizontal.
2 Sloping.
3 Vertical.
m
m3
1 In structures.
1 300 thick.
2 > 300 thick.
Level two
Level one
Unit
5 Vertical work
m2
17
18
19
20
21
Sides
Sides
Sides
Sides
Sides
m2
m
m2
Level one
1 Plain formwork.
2 Special finish formwork.
Unit
Formwork
1 Propping 3m high.
2 Propping over 3m but not
exceeding 4.5m high.
3 And thereafter in 1.5m stages.
Level two
Level three
Unit
1 15.
2 > 15.
m2
nr
31 Complex shapes
32 Wall kickers
1 Plain.
2 Suspended.
1 Dimensioned description or
diagram.
m2
nr
23 Extra over
Level three
m
m2
Level two
1 Vertical.
2 Battered one face.
3 Battered both faces.
Level one
1 Dimensioned description.
2 Nominal size stated.
3 Method of tensioning stated.
nr
m2
36 Pre/Post-tensioned members
37 Mesh
nr
Level one
Unit
Reinforcement
Straight.
Bent.
Curved.
Links.
1 Composite construction
described.
1 Chairs or stools.
2 Connectors.
1
2
3
4
Level two
Level three
m2
----m
----nr
1 Dimensioned description.
1 Dimensioned description.
2 total depth stated.
1 Horizontal.
2 Vertical.
3 Curved, radius stated.
Level three
Level two
38 Plain
39 Formed
40 Cut
Level one
Unit
nr
nr
44 Filling chases
Unit
42 Grouting
1 Dimensioned description.
Level one
1 Stanchion bases.
2 Grillages.
Level two
Level three