You are on page 1of 13

Federal Register / Vol. 70, No.

249 / Thursday, December 29, 2005 / Proposed Rules 77101

(a) PWC are allowed in the following (3) Cape Lookout initiated reconsideration processes on
areas only when remaining five specific issues in the CAIR and
perpendicular to shore and operating at Access Location requested comment on those issues. In
flat-wake speed. this notice, EPA is announcing its
(i) Lighthouse A zone 300 feet north of the decision to reconsider one additional
(b) PWC use is not authorized for Area North. NPS dock at the light-
specific issue in the CAIR and is
recreational use parallel to the house ferry dock near
Milepost 41. requesting comment on that issue.
shoreline, but only for access to the The specific issue addressed in
following areas specifically for landing (ii) Lighthouse Sound-side beach 100 feet
Area South. south of the ‘‘summer today’s notice relates to the potential
purposes. kitchen’’ to 200 feet north impact of a recent D.C. Circuit Court
(c) In all cases, PWC have access to of the Cape Lookout Envi- decision, New York v. EPA, 413 F.3d 3
the sound side of the barrier islands ronmental Education Cen- (D.C. Cir. 2005), on the analysis used in
only. ter Dock. developing CAIR to identify highly cost-
(iii) Power Sound-side beach at Power effective emission reductions. This
(d) PWC are prohibited in all areas of Squadron Squadron Spit across from
the national seashore except for the court decision vacated the pollution
Spit. rock jetty to end of the spit
areas listed in paragraph (f) of this control project (PCP) exclusion in the
New Source Review (NSR) regulations
section. PWC are not allowed to beach (4) Shackleford Banks West End Access
(the exclusion allowed certain
on the oceanside. Sound-side beach at Shackleford Banks
environmentally beneficial PCPs to be
(e) The Superintendent may from Whale Creek west to Beaufort Inlet,
excluded from certain NSR
temporarily limit, restrict or terminate except the area between the Wade
requirements).
access to the areas designated for PWC Shores toilet facility and the passenger The EPA is seeking comment only on
use after taking into consideration ferry dock. the aspect of the CAIR specifically
public health and safety, natural and Dated: December 20, 2005. identified in this notice. We will not
cultural resource protection, and other respond to comments addressing other
Paul Hoffman,
management activities and objectives. provisions of the CAIR or any related
Acting Assistant Secretary, Fish and Wildlife
(f) PWC use is allowed only in the rulemakings.
and Parks.
locations specified in this paragraph. [FR Doc. E5–8003 Filed 12–28–05; 8:45 am] Comments must be received on
DATES:
BILLING CODE 4312–52–P
or before February 16, 2006. If
(1) North Core Banks: requested, a public hearing will be held
on January 17, 2006 in Washington, DC.
Access Location For additional information on a public
ENVIRONMENTAL PROTECTION
AGENCY hearing, see the SUPPLEMENTARY
(i) Ocracoke Wallace Channel dock to the
INFORMATION section of this preamble.
Inlet. demarcation line in
Ocracoke Inlet near Mile- 40 CFR Parts 51 and 96 ADDRESSES: Submit your comments,
post 1. identified by Docket ID No. EPA–HQ–
[EPA–HQ–OAR 2003–0053; FRL–8016–6]
(ii) Milepost Existing sound-side dock at OAR–2003–0053, by one of the
11B. mile post 11B approxi- Rule To Reduce Interstate Transport of following methods:
mately 4 miles north of
Fine Particulate Matter and Ozone • www.regulations.gov: Follow the
Long Point. on-line instructions for submitting
(iii) Long Point Ferry landing at the Long
(Clean Air Interstate Rule):
Supplemental Notice of comments. Attention Docket ID No.
Point Cabin area. EPA–HQ–OAR–2003–0053.
(iv) Old Drum Sound-side beach near Mile- Reconsideration
• E-mail: A-and-R-Docket@epa.gov.
Inlet. post 19 (as designated by AGENCY: Environmental Protection
signs), approximately 1⁄2
Attention Docket ID No. EPA–HQ–
mile north of Old Drum
Agency (EPA). OAR–2003–0053.
inlet (adjacent to the ACTION: Notice of reconsideration; • Fax: The fax number of the Air
cross-over route) encom- request for comment; notice of Docket is (202) 566–1741. Attention
passing approximately 50 opportunity for public hearing. Docket ID No. EPA–HQ–OAR–2003–
feet. 0053.
SUMMARY: On May 12, 2005, EPA • Mail: EPA Docket Center, EPA West
(2) South Core Banks: published in the Federal Register the (Air Docket), Attention Docket ID No.
final ‘‘Rule to Reduce Interstate EPA–HQ–OAR–2003–0053,
Access Location Transport of Fine Particulate Matter and Environmental Protection Agency,
Ozone’’ (Clean Air Interstate Rule or Mailcode: 6102T, 1200 Pennsylvania
(i) New Drum Sound-side beach near Mile- CAIR). The CAIR requires certain Ave., NW., Washington, DC 20460.
Inlet. post 23 (as designated by upwind States to reduce emissions of • Hand Delivery: EPA Docket Center
signs), approximately 1⁄4 nitrogen oxides (NOX) and/or sulfur (Air Docket), Attention Docket ID No.
mile long, beginning ap- dioxide (SO2) that significantly EPA–HQ–OAR–2003–0053,
proximately 1⁄2 mile south contribute to nonattainment of, or Environmental Protection Agency, 1301
of New Drum Inlet.
interfere with maintenance by, Constitution Avenue, NW., Room B102;
(ii) Great Is- Carly Dock at Great Island
land Access.. Camp, near Milepost 30
downwind States with respect to the Washington, DC. Such deliveries are
(noted as South Core fine particle (PM2.5) and/or 8-hour ozone only accepted during the Docket’s
wwhite on PROD1PC65 with PROPOSAL

Banks-Great Island on national ambient air quality standards normal hours of operation, and special
map). (NAAQS). Subsequently, EPA received arrangements should be made for
11 petitions for reconsideration of the deliveries of boxed information.
final rule. Through Federal Register Instructions: Direct your comments to
notices dated August 24, 2005 and Docket ID No. EPA–HQ–OAR–2003–
December 2, 2005, EPA previously 0053. EPA’s policy is that all comments

VerDate Aug<31>2005 17:50 Dec 28, 2005 Jkt 208001 PO 00000 Frm 00033 Fmt 4702 Sfmt 4702 E:\FR\FM\29DEP1.SGM 29DEP1
77102 Federal Register / Vol. 70, No. 249 / Thursday, December 29, 2005 / Proposed Rules

received will be included in the public this notice, please contact Meg Victor, morales.roberto@epa.gov, Docket ID No.
docket without change and may be U.S. EPA, Office of Atmospheric EPA–HQ–OAR–2003–0053.
made available online at http:// Programs, Clean Air Markets Division, 2. Tips for Preparing Your Comments.
www.regulations.gov, including any Mail Code 6204J, 1200 Pennsylvania When submitting comments, remember
personal information provided, unless Avenue, NW., Washington, DC 20460, to:
the comment includes information telephone (202) 343–9193, e-mail • Identify the rulemaking by docket
claimed to be Confidential Business address victor.meg@epa.gov. For legal number and other identifying
Information (CBI) or other information questions, please contact Sonja Rodman, information (subject heading, Federal
whose disclosure is restricted by statute. U.S. EPA, Office of General Counsel, Register date and page number).
Do not submit information that you Mail Code 2344A, 1200 Pennsylvania • Follow directions—The agency may
consider to be CBI or otherwise Avenue, NW., Washington, DC 20460, ask you to respond to specific questions
protected through www.regulations.gov telephone 202–564–4079, e-mail or organize comments by referencing a
or e-mail. The www.regulations.gov Web address rodman.sonja@epa.gov. For Code of Federal Regulations (CFR) part
site is an ‘‘anonymous access’’ system, information concerning a public or section number.
which means EPA will not know your hearing, please contact Jo Ann Allman, • Explain why you agree or disagree;
identity or contact information unless U.S. EPA, Office of Air Quality Planning suggest alternatives and substitute
you provide it in the body of your and Standards, Air Quality Strategies language for your requested changes.
comment. If you send an e-mail and Standards Division, Mail Code • Describe any assumptions and
comment directly to EPA without going C539–02, Research Triangle Park, NC provide any technical information and/
through www.regulations.gov your e- 27711, phone number (919) 541–1815, or data that you used.
mail address will be automatically e-mail address allman.joann@epa.gov. • If you estimate potential costs or
captured and included as part of the burdens, explain how you arrived at
SUPPLEMENTARY INFORMATION: your estimate in sufficient detail to
comment that is placed in the public
docket and made available on the General Information allow for it to be reproduced.
Internet. If you submit an electronic • Provide specific examples to
A. Does This Action Apply to Me? illustrate your concerns, and suggest
comment, EPA recommends that you
include your name and other contact The CAIR does not directly regulate alternatives.
emissions sources. Instead, it requires • Explain your views as clearly as
information in the body of your
States to develop, adopt, and submit possible, avoiding the use of profanity
comment and with any disk or CD ROM
State implementation plan (SIP) or personal threats.
you submit. If EPA cannot read your
• Make sure to submit your
comment due to technical difficulties revisions that would achieve the
comments by the comment period
and cannot contact you for clarification, necessary SO2 and NOX emissions
deadline identified.
EPA may not be able to consider your reductions, and leaves to the States the
comment. Electronic files should avoid task of determining how to obtain those Public Hearing
the use of special characters, any form reductions, including which entities to If requested, EPA will hold a public
of encryption, and be free of any defects regulate. hearing on today’s notice. The EPA will
or viruses. For additional information hold a hearing only if a party notifies
B. What Should I Consider as I Prepare
about EPA’s public docket visit the EPA EPA by January 10, 2006, expressing its
My Comments for EPA?
Docket Center homepage at http:// interest in presenting oral testimony on
www.epa.gov/epahome/dockets.htm. Note that general instructions for issues addressed in today’s notice. Any
For additional instructions on submitting comments are provided person may request a hearing by calling
submitting comments, go to the above under the ADDRESSES section. Jo Ann Allman at (919) 541–1815 before
SUPPLEMENTARY INFORMATION section of 1. Submitting CBI. Do not submit this 5 p.m. on January 10, 2006. Any person
this document. information to EPA through http:// who plans to attend the hearing should
Docket: All documents in the docket www.regulations.gov or e-mail. Clearly visit the EPA’s Web site at http://
are listed in the www.regulations.gov mark the part or all of the information www.epa.gov/cair or contact Jo Ann
index. Although listed in the index, that you claim to be CBI. For CBI Allman at (919) 541–1815 to learn if a
some information is not publicly information in a disk or CD ROM that hearing will be held.
available, e.g., CBI or other information you mail to EPA, mark the outside of the If a public hearing is held on today’s
whose disclosure is restricted by statute. disk or CD ROM as CBI and then notice, it will be held on January 17,
Certain other material, such as identify electronically within the disk or 2006 at EPA Headquarters, 1310 L Street
copyrighted material, will be publicly CD ROM the specific information that is (closest cross street is 13th Street), 1st
available only in hard copy. Publicly claimed as CBI. In addition to one floor conference rooms 152 and 154,
available docket materials are available complete version of the comment that Washington, DC. The closest Metro stop
either electronically in http:// includes information claimed as CBI, a is McPherson Square (Orange and Blue
www.regulations.gov or in hard copy at copy of the comment that does not lines)—take 14th Street/Franklin Square
the EPA Docket Center (Air Docket), contain the information claimed as CBI Exit. Because the hearing will be held at
EPA/DC, EPA West, Room B102, 1301 must be submitted for inclusion in the a U.S. Government facility, everyone
Constitution Ave., NW., Washington, public docket. Information so marked planning to attend should be prepared
DC. The Public Reading Room is open will not be disclosed except in to show valid picture identification to
from 8:30 a.m. to 4:30 p.m., Monday accordance with procedures set forth in the security staff in order to gain access
through Friday, excluding legal 40 CFR part 2. Send or deliver to the meeting room.
holidays. The telephone number for the
wwhite on PROD1PC65 with PROPOSAL

information identified as CBI only to the If held, the public hearing will begin
Public Reading Room is (202) 566–1744. following address: Roberto Morales, at 10 a.m. and end at 2 p.m. The hearing
FOR FURTHER INFORMATION CONTACT: For U.S. EPA, Office of Air Quality Planning will be limited to the subject matter of
general questions concerning today’s and Standards, Mail Code C404–02, this document. Oral testimony will be
action as well as questions concerning Research Triangle Park, NC 27711, limited to 5 minutes. The EPA
the analyses described in section III of telephone (919) 541–0880, e-mail at encourages commenters to provide

VerDate Aug<31>2005 16:10 Dec 28, 2005 Jkt 208001 PO 00000 Frm 00034 Fmt 4702 Sfmt 4702 E:\FR\FM\29DEP1.SGM 29DEP1
Federal Register / Vol. 70, No. 249 / Thursday, December 29, 2005 / Proposed Rules 77103

written versions of their oral testimonies Handling of Lime, Limestone, or FGD pursuant to section 307(d)(7)(B) of the
either electronically (on computer disk Waste After Installation of Dry or Wet CAA. Under this provision, the
or CD ROM) or in paper copy. The FGD Administrator is to initiate
8. Collateral Air Pollutant Emissions From
public hearing schedule, including the reconsideration proceedings if the
Units Switching From High to Low
list of speakers, will be posted on EPA’s Sulfur Coals petitioner can show that an objection is
Web site at http://www.epa.gov/cair. 9. Summary of Section III.B. of central relevance to the rule and that
Verbatim transcripts and written C. Potential Impact of NSR Permitting it was impracticable to raise the
statements will be included in the IV. Statutory and Executive Order Reviews objection to the rule within the public
rulemaking docket. A. Executive Order 12866: Regulatory comment period or that the grounds for
A public hearing would provide Planning and Review the objection arose after the public
interested parties the opportunity to B. Paperwork Reduction Act comment period but before the time for
present data, views, or arguments C. Regulatory Flexibility Act judicial review had run.
concerning issues addressed in today’s D. Unfunded Mandates Reform Act The EPA has already initiated a
E. Executive Order 13132: Federalism reconsideration process on five specific
notice. The EPA may ask clarifying F. Executive Order 13175: Consultation
questions during the oral presentations, aspects of the final CAIR. On August 24,
and Coordination With Indian Tribal
but would not respond to the Governments 2005 (70 FR 49708) and on December 2,
presentations or comments at that time. G. Executive Order 13045: Protection of 2005 (70 FR 72268), we published in the
Written statements and supporting Children From Environmental Health Federal Register notices announcing
information submitted during the and Safety Risks these decisions to reconsider specific
comment period will be considered H. Executive Order 13211: Actions That aspects of the CAIR and requesting
with the same weight as any oral Significantly Affect Energy Supply, comment on those issues. Today’s
comments and supporting information Distribution or Use notice announces EPA’s decision to
I. National Technology Transfer reconsider one additional issue raised in
presented at a public hearing. Advancement Act
All written comments must be a petition for reconsideration and
J. Executive Order 12898: Federal Actions
received by EPA on or before February requests comment on that additional
To Address Environmental Justice in
16, 2006. Because of the need to resolve Minority Populations and Low-Income issue.
the issues in this document in a timely Populations By a letter dated December 22, 2005
manner, EPA will not grant requests for we informed a petitioner of our intent
extensions of the public comment I. Background to grant reconsideration on an issue
period. On May 12, 2005, the EPA (Agency or addressed in their petition for
we) promulgated the final ‘‘Rule to reconsideration. We indicated in that
Availability of Related Information letter that we would initiate the
Reduce Interstate Transport of Fine
Documents related to the CAIR are Particulate Matter and Ozone’’ (Clean reconsideration process by publishing
available for inspection in Docket No. Air Interstate Rule or CAIR)(70 FR this notice.
EPA–HQ–OAR–2003–0053 at the 25162). As explained in the CAIR II. Today’s Action
address and times given above. The EPA preamble and summarized in our
has established a Web site for the CAIR December 2, 2005 reconsideration A. Grant of Reconsideration
at http://www.epa.gov/ notice (70 FR 72268), CAIR requires 28 In this notice, EPA is announcing its
cleanairinterstaterule or more simply States and the District of Columbia to decision to grant reconsideration on one
http://www.epa.gov/cair/. revise their State implementation plans issue raised in the petitions for
Outline (SIPs) to include control measures to reconsideration. This notice initiates
reduce emissions of SO2 and/or NOX. that reconsideration process and
I. Background
II. Today’s Action Sulfur dioxide is a precursor to PM2.5 requests comment on the issue to be
A. Grant of Reconsideration formation and NOX is a precursor to addressed. Given the intense public
B. Schedule for Reconsideration PM2.5 and ozone formation. By reducing interest in this rule, EPA has decided to
III. Impact on CAIR Analyses of DC Circuit upwind emissions of SO2 and NOX, provide this additional opportunity for
Decision in New York v. EPA CAIR will assist downwind PM2.5 and 8- public comment. At this time, however,
A. Background on New York v. EPA and its hour ozone nonattainment areas in EPA does not believe that any of the
Relationship to CAIR achieving the NAAQS. As also information submitted to date
B. Potential Impact of Collateral Pollutant demonstrates that EPA’s final decisions
described in the December 2005
Increases and Mitigation Measures
reconsideration notice, the CAIR was were erroneous or inappropriate.
1. Increases in Sulfuric Acid Emissions
From SCR Retrofits promulgated through a process that Therefore, we are not proposing any
2. Increases in Sulfuric Acid Emissions involved significant public participation modifications to the final CAIR.
From Wet FGD Retrofits in Combination (70 FR 72271). The issue on which EPA is requesting
With Switching to Higher Sulfur Coal Following publication of the final comment relates to the potential impact
3. Summary of Combinations of CAIR SCR CAIR on May 12, 2005, the of a recent judicial opinion on the
and/or FGD Retrofits and Coal Switches Administrator received eleven petitions highly cost-effective analysis prepared
That May Increase Sulfuric Acid requesting reconsideration of certain by EPA in developing the CAIR. This
Emissions aspects of the final rule. The complete
4. Technology Options Available for 0053–2193); Texas Commission on Environmental
Mitigating Sulfuric Acid Emission
petitions are available in the docket for
Quality (OAR–2003–0053–2212); Northern Indiana
Increases the CAIR.1 The petitions were filed Public Service Corporation (OAR–2003–0053–2194
5. Analysis of SO3/H2SO4 Mitigation Costs and 2213 (supplemental petition)); City of Amarillo,
1 Petitions for reconsideration were filed by: State
and Timing Impacts for CAIR SCR and/ Texas, El Paso Electric Company, Occidental
wwhite on PROD1PC65 with PROPOSAL

or Wet FGD Projects of North Carolina (OAR–2003–0053–2192); FPL Permian Ltd, and Southwestern Public Service
Group (OAR–2003–0053–2201); Florida Association Company d/b/a/ Xcel Energy (OAR–2003–0053–
6. Increases in Carbon Monoxide and of Electric Utilities (OAR–2003–0053–2200); 2196 and 2197 (attachment 1) and 2205–2207
Unburned Carbon (Solid Particulate) Entergy Corporation (OAR–2003–0053–2195 and (attachments 2–4)); Connecticut Business and
Emissions From Combustion Controls 2198 (attachment 1)); Massachusetts Department of Industry Ass’n (OAR–2003–0053–2203); and
7. Increases in Direct PM2.5 Resulting From Environmental Protection (OAR–2003–0053–2199); Minnesota Power, a division of ALLETE. Inc.
Fugitive Emissions From Storage or Integrated Waste Services Association (OAR–2003– (OAR–2003–0053–2212).

VerDate Aug<31>2005 16:10 Dec 28, 2005 Jkt 208001 PO 00000 Frm 00035 Fmt 4702 Sfmt 4702 E:\FR\FM\29DEP1.SGM 29DEP1
77104 Federal Register / Vol. 70, No. 249 / Thursday, December 29, 2005 / Proposed Rules

case, New York v. EPA, 413 F.3d 3 (D.C. for Certiorari with the United States potential impact of New York v. EPA on
Cir. 2005) was decided on June 24, Supreme Court has not yet run. The the CAIR cost-effectiveness
2005—after the final CAIR was analysis that follows looks at the determination and timing. This analysis
published but before the time for potential impact of the New York v. EPA indicates that some EGUs that install
judicial review of the rule had run. This decision. SO2 and/or NOX controls for CAIR may
issue is described in greater detail in The PCP exclusion provided a incur relatively minor additional costs
Section III of this notice. mechanism for sources to exclude and minor impacts on timing as a result
The EPA is requesting comment only certain environmentally beneficial PCPs of New York v. EPA, but these potential
on the issue specifically described in from the definition of ‘‘major impacts will neither affect the highly
Section III. We are not taking comment modification’’ under Prevention of cost-effective determination that the
on any other provisions in the CAIR or Significant Deterioration (PSD)/NSR 3 Agency made in CAIR nor impact the
otherwise reopening any other issues even though the PCP resulted in a timeframe for CAIR reductions. The
decided in the CAIR for reconsideration significant net emissions increase in a EPA’s analysis further shows that
or comment. collateral pollutant (e.g., increase in options exist that would allow units to
NOX from flaring VOCs). This exclusion meet the CAIR deadlines without
B. Schedule for Reconsideration
could only apply if the owner or changing plans to stagger PCP projects
For the issue addressed in this notice, operator, before beginning construction (sources will not be forced to install all
EPA expects to take final action on of the PCP, either provided notice to the PCPs at one time) and that the related
reconsideration by March 15, 2006. By Administrator (for certain projects listed costs would not alter the highly cost
that date, EPA will finalize the process in the regulations) or submitted a permit effective analysis done for the final
of reconsideration by issuing a final rule application to obtain approval to use the CAIR. The EPA invites comments on
or proposing a new approach. EPA also exclusion. If the exclusion were found this analysis and the potential impact of
expects, by March 15, 2006, to issue not to apply, the source would either the New York v. EPA decision on EPA’s
decisions on all remaining issues raised have to ensure that the PCP did not highly cost-effective determination.
in the petitions for reconsideration. result in a significant net emissions EPA’s analysis of this issue is
III. Impact on CAIR Analyses of DC increase in a collateral NSR-regulated summarized below and supplemental
Circuit Decision in New York v. EPA pollutant (and thus avoid NSR review), information is in the CAIR docket.
or apply for and receive a NSR permit In order to evaluate the petitioner’s
A. Background on New York v. EPA and for the project. Petitioner asks EPA to claim, the Agency examined the
Its Relationship to CAIR reconsider whether EPA’s highly cost potential for collateral increases in NSR-
One industry petitioner claims that a effective analysis ‘‘continues to be valid regulated air pollutants from the types
recent opinion of the DC Circuit raises given the court’s holding in [New York of NOX and SO2 controls on which EPA
questions about the sufficiency of EPA’s v. EPA].’’ More specifically, Petitioner based its CAIR cost-effectiveness
analysis prepared for the CAIR to claims that CAIR sources will need to go determination.4 The EPA identified
identify highly cost-effective emission through NSR permitting and that which of these technologies could have
reductions. The petitioner argues that additional time and financial costs will the potential to cause collateral
EPA should reconsider this analysis to be required for this permitting. increases in NSR-regulated air
take into account the potential impact of Petitioner does not specify which pollutants. The EPA then analyzed
the decision in New York v. EPA, 413 projects it believes might require NSR whether sources could mitigate any
F.3d 3 (D.C. Cir. 2005). This judicial permitting or what collateral increases such collateral increases to avoid NSR
opinion was issued on June 24, 2005— in NSR-regulated pollutants it expects. review and analyzed the cost and timing
after the final CAIR had been Petitioner also claims that additional impacts associated with potential
promulgated, but within the 60 days time will be necessary for NSR mitigation measures. The EPA
provided by CAA section 307(b) for permitting and that therefore the determined that projected collateral
filing of petitions for review.2 Among compliance deadlines of January 1, 2009 increases in NSR-regulated pollutants
other things, the opinion vacated a and 2010 are ‘‘in jeopardy.’’ Petitioner, that might be significant enough to
provision of the New Source Review however, does not ask EPA to trigger an NSR threshold could be
(NSR) regulations, commonly known as reconsider the 2009 and 2010 mitigated by many sources wishing to
the pollution control project (PCP) compliance deadlines. As noted above, avoid the NSR permitting process.
exclusion. All pending petitions for this notice grants reconsideration only However, some sources may not be able
rehearing of the case were denied by the on the issue of the impact of the New to ensure mitigation of all collateral
Court on December 9, 2005. The EPA’s York v. EPA decision on EPA’s highly increases. Therefore, the Agency also
request that the Court clarify its holding cost effective analysis. analyzed the impacts associated with
with regard to any retroactive effect of In developing the CAIR, EPA NSR permitting for these NOX and SO2
its ruling on the PCP issue was also conducted extensive analyses to identify pollution control projects.
denied. The Court determined that this highly cost-effective SO2 and NOX The EPA considered each of the NOX
clarification request was premature emissions reductions based on and SO2 control measures that were
because no specific retroactive controlling EGUs. These analyses are included in the CAIR cost-effectiveness
application of the provision was before explained in the preamble to the CAIR determination and found that the
the Court. The time for filing Petitions (70 FR 25202–25212). The EPA has following technologies may have the
reviewed the petition for potential to cause collateral increases in
2 CAA section 307(d)(7)(B) provides that the reconsideration and analyzed the air pollutants regulated under NSR:
Administrator shall convene a proceeding for combustion controls, selective catalytic
wwhite on PROD1PC65 with PROPOSAL

reconsideration if the person raising an objection 3 PSD is the part of the NSR program that applies
reduction (SCR), flue gas
can show that: it was impracticable to raise the to sources located in areas in attainment with the
objection during the period for public comment or NAAQS. Unless otherwise noted, in this notice, desulphurization (FGD), and fuel
the grounds for the objection arose after such period when we refer to the NSR program, NSR review,
but within the time specified for judicial review; NSR permitting or other NSR requirements, we are 4 All references to ‘‘collateral increases’’ in this

and the objection is of central relevance to the referring to both the NSR and PSD programs and document refer to potential collateral increases in
outcome of the rule. their respective requirements. NSR-regulated air pollutants.

VerDate Aug<31>2005 16:10 Dec 28, 2005 Jkt 208001 PO 00000 Frm 00036 Fmt 4702 Sfmt 4702 E:\FR\FM\29DEP1.SGM 29DEP1
Federal Register / Vol. 70, No. 249 / Thursday, December 29, 2005 / Proposed Rules 77105

switches to low sulfur coal. Many sulfuric acid mist—an NSR-regulated lower-sulfur coal use injected SO3 to
affected sources can choose to pollutant. bring the cold-side ESP performance
implement measures to mitigate the Sulfuric acid mist is also regulated back up. If such a unit installs SCR for
potential collateral emission increases under NSR as PM2.5 (a criteria CAIR, then the increased SO3 from the
(thereby obviating the need to undertake pollutant). Because PM2.5 is a criteria SCR would lessen or obviate the need
NSR analysis). pollutant, the NSR requirements vary for SO3 injection, and without the SO3
The Agency determined that some depending on the location of the unit injection there may be no net increase
cost increases will result from actions experiencing the emission increase, i.e., in sulfuric acid emissions.
that sources may take to mitigate whether the unit is located in a
collateral increases that result from nonattainment area. See further 2. Increases in Sulfuric Acid Emissions
CAIR control actions; however these discussion of the Agency’s analysis From Wet FGD Retrofits in Combination
impacts do not alter the final highly cost regarding permitting for these projects, With Switching to Higher Sulfur Coal
effective determination made in the below.
final CAIR. In addition, implementing Although SCR retrofits can lead to Many CAIR units are projected to
these control actions will not affect the increased sulfuric acid emissions, for install FGD to reduce SO2 emissions. As
feasibility of implementing the CAIR the following reasons EPA expects that discussed above, operation of dry or wet
reductions in the required timeframe. many units installing SCR for CAIR will FGD reduces SO3/H2SO4 emissions.
Further, if some sources apply for an not actually increase their sulfuric acid However, some units installing FGD for
NSR permit, the Agency believes that emissions and will therefore not incur CAIR may choose to switch to a higher
the impacts of NSR permitting will not any cost increase or timing burden sulfur coal at the time they install FGD.
affect the CAIR highly cost-effectiveness associated with collateral increases of Dry FGD reduces SO3/H2SO4
determination or the CAIR timeline. sulfuric acid: sufficiently to most likely mitigate any
Installing Both SCR and FGD. Many
Note that in today’s notice the Agency increase from the higher sulfur coal.
CAIR units that are expected to install
is not making any determination or Considering the lower SO3/H2SO4
SCR to reduce NOX emissions also are
prediction regarding what the specific removal efficiency of wet FGD,
expected to install flue gas
NSR requirements might be for such however, the potential exists for sulfuric
desulphurization (FGD) to reduce SO2
projects. acid emissions to increase from units
emissions, and FGD is also effective at
The EPA’s analysis for each of these that install wet FGD and switch to
reducing SO3/H2SO4 emissions. The two
NOX and SO2 controls is discussed most common types of FGD systems (on higher sulfur coal.
below and in a Technical Support which the Agency’s CAIR cost-
Document (TSD) available in the docket 3. Summary of Combinations of CAIR
effectiveness analysis was based) are a SCR and/or FGD Retrofits and Coal
entitled ‘‘Technical Support Document: lime-based spray dryer system (dry
Impact on CAIR Analyses of D.C. Circuit Switches That May Increase Sulfuric
FGD) and a limestone-based wet FGD
Decision in New York v. EPA.’’ Acid Emissions
system (wet FGD). Considering the
B. Potential Impact of Collateral effectiveness of FGD at mitigating The following table summarizes
Pollutant Increases and Mitigation SO3/H2SO4 emissions, the Agency combinations of SCR and/or FGD
Measures expects that a CAIR unit installing SCR control retrofits and coal switches that
and FGD at the same time would not may occur as a result of CAIR, and
1. Increases in Sulfuric Acid Emissions increase sulfuric acid emissions
From SCR Retrofits 5 identifies which of these combinations
significantly enough to trigger NSR. could lead to increases in sulfuric acid
Many CAIR units are projected to Note that some units may switch to a
higher sulfur coal when they install emissions significant enough to trigger
install selective catalytic reduction
FGD. The combination of installing SCR the NSR threshold.
(SCR) to reduce NOX emissions. The
SCR catalyst oxidizes a portion of the and dry FGD and switching to high
SO2 present in flue gas to SO3. The sulfur coal may not result in increased TABLE III–1.—COMBINATIONS OF CAIR
amount of SO3 added to the flue gas sulfuric acid because dry FGD is very SCR AND/OR FGD AND COAL
stream by SCR will be directly effective at mitigating SO3/H2SO4. SWITCHES THAT MAY INCREASE
proportional to the fuel sulfur content. However, installation of SCR in SULFURIC ACID EMISSIONS
(Note that SO2 is also oxidized to SO3 combination with wet FGD and a switch
in the boiler itself.) to high sulfur coal could result in a Combinations of SCR and/or Increase in
Some SO3 reacts with moisture in the significant net increase in sulfuric acid sulfuric acid
FGD and coal switches emissions?
flue gas to form sulfuric acid (H2SO4) emissions.
and exits the stack as sulfuric acid Switching to Lower Sulfur Coal with Install SCR ............................ Possible.
vapor. The Agency’s analysis for today’s SCR Retrofit. Some CAIR units that burn Install SCR and switch from No.
notice assumes that all sulfuric acid high sulfur coal may also choose to high to low sulfur coal.
emitted will be counted as emissions of switch to lower sulfur coal when Install SCR with wet FGD (no No.
installing SCR. For units switching from coal switch).
5 This SCR discussion is focused on the potential high to low sulfur coal and installing Install SCR with wet FGD Possible.
for sulfuric acid emission increases from SCR SCR, there would likely be no net and switch to higher sulfur
retrofits. Note that SCR conditions also favor a increase in sulfuric acid emissions. coal.
reaction between SO3 and ammonia that produces Ceasing to Inject SO3 with SCR Install wet FGD (no coal No.
ammonium bisulfate which condenses to form solid
PM, however the majority of this PM will be
Retrofit. Many CAIR units have cold- switch).
wwhite on PROD1PC65 with PROPOSAL

captured in the particulate control device installed side electrostatic precipitators (ESP) in Install wet FGD and switch to Possible.
at the unit. Any such increase in PM emissions place to control particulate matter higher sulfur coal.
would likely not be significant enough to trigger emissions. These control devices Install SCR and dry FGD ...... No.
NSR review, even when considered together with Install dry FGD ...................... No.
the small increase in PM emissions that could occur
perform better with SO3 present in the
from storage or handling lime, limestone, or FGD flue gas. Some units that have
waste (see discussion below). previously switched from higher-to

VerDate Aug<31>2005 16:10 Dec 28, 2005 Jkt 208001 PO 00000 Frm 00037 Fmt 4702 Sfmt 4702 E:\FR\FM\29DEP1.SGM 29DEP1
77106 Federal Register / Vol. 70, No. 249 / Thursday, December 29, 2005 / Proposed Rules

4. Technology Options Available for wet FGD will incur increased costs for units installing wet FGD alone and
Mitigating Sulfuric Acid Emission SO3/H2SO4 mitigation. switching to higher sulfur coal. The IPM
Increases Our cost analysis is based on the sensitivity analysis conservatively
assumption that each unit that retrofits assumes SO3/H2SO4 mitigation costs are
Several technology options are
SCR and/or wet FGD will install wet incurred by every unit projected to
available for mitigating sulfuric acid
ESPs for SO3/H2SO4 mitigation.7 The retrofit SCR and/or wet FGD. We note,
emission increases from CAIR retrofit
Agency believes that the choice of however, that based on EPA’s IPM
projects. These include:
SO3/H2SO4 mitigation method would modeling, for the first and second CAIR
• Injecting alkali materials into the
depend greatly on the specifics of the phases, respectively, only 16 percent
furnace;
affected sources, thus it is difficult to and 11 percent of total CAIR-affected
• Injecting alkali postfurnace;
predict control choices. For this cost generating capacity (i.e., capacity of
• Injecting ammonia;
analysis, EPA chose to model costs units in CAIR States with capacity
• Fuel switching (e.g., firing lower
based on wet ESP because we believe greater than 25 MW) are projected to
sulfur coal);
the costs of this technology are retrofit in any of these three
• Selecting specialized SCR catalyst
representative of the costs of combinations that might increase
with a low SO3 conversion rate;
technologies that sources might choose sulfuric acid emissions significantly to
• Installing wet ESP; and trigger the NSR threshold.
to install.
• Installing FGD. The EPA performed an IPM Also, it is possible that units that
The Agency anticipates that some sensitivity analysis in which we added inject SO3 to improve cold-side ESP
CAIR sources may choose to install costs for wet ESP to every unit that performance would cease injecting SO3
emerging multipollutant control installs SCR and/or wet FGD. We based after installing SCR which could result
technologies designed to reduce not this sensitivity analysis on the IPM in the net SO3 increase being
only SO2 and NOX but SO3 and other model run that includes the CAIR, Clean insufficient to trigger NSR (as discussed
pollutants as well. Generally, sources Air Mercury Rule (CAMR) and Clean above), however the Agency’s IPM
choosing to employ such technologies Air Visibility Rule (CAVR) sensitivity does not take into account
would do so if they found it to be requirements. Note that the IPM this possibility.
economical. Although EPA does not modeling for the final CAIR highly cost- Additionally, the IPM sensitivity
endorse the purchase or sale of any effectiveness determination does not model run overstates the cost impacts to
specific products and services include the CAMR and CAVR CAIR units because that modeling
mentioned, example multipollutant requirements. However, the Agency added SO3/sulfuric acid mitigation costs
technologies include: subsequently conducted IPM modeling for all units retrofitting SCR and/or wet
• Powerspan ECO Technology; and that reflects CAIR, CAMR and CAVR. FGD, including retrofits that are
• Mobotec USA Inc. ROTAMIX The IPM analysis discussed in today’s projected to occur prior to
System. notice (which examines the possible commencement of CAIR retrofits (the
5. Analysis of SO3/H2SO4 Mitigation cost impacts of SO3/H2SO4 mitigation) is Agency assumes that retrofits occurring
Costs and Timing Impacts for CAIR SCR based on the modeling that includes prior to 2007 do not result from CAIR,
and/or Wet FGD Projects CAIR, CAMR and CAVR because that but rather from existing programs such
modeling best reflects current as the title IV SO2 program and the NOX
Cost Modeling for SO3/H2SO4 SIP Call, however the IPM modeling
requirements.8
Controls. The Agency used the As noted above, this modeling—the does not account for this distinction).
Integrated Planning Model (IPM) 6 to SO3/H2SO4 mitigation IPM sensitivity Further, our analysis overstates the cost
provide an upper-end estimate of the modeling—overstates the possible cost impacts to CAIR units because the
possible cost impacts for CAIR units impacts to CAIR units for several modeling includes retrofits that occur in
that may install SO3/H2SO4 controls. reasons. As discussed above, only the the base case (without CAIR) and also
The EPA does not believe this analysis following three combinations of CAIR includes the CAMR and CAVR
provides a true estimate of the costs to SCR and/or wet FGD retrofits might requirements.
CAIR units of the NY v. EPA decision. increase sulfuric acid emissions Further, in the IPM sensitivity
Instead, EPA believes this analysis significantly to trigger the NSR analysis we assumed units would incur
significantly overstates the potential threshold: units installing SCR alone costs for year-round operation of wet
costs. However, because this analysis (without switching to lower sulfur coal); ESP in all CAIR States, including the
shows that even when the costs are units installing SCR with wet FGD and States that are only required to make
significantly overestimated they do not switching to higher sulfur coal; and, ozone season NOX reductions for CAIR.
impact the analyses done for the final Finally, the IPM sensitivity run
CAIR, EPA determined that a more 7 Although the Agency based this analysis on overstates the cost impacts because we
refined analysis was not necessary to installation of wet ESP, the Agency is not making added costs for wet ESP to each affected
address petitioner’s concerns. any determination or prediction regarding what the unit although SO3/H2SO4 mitigation
The EPA believes this analysis specific PSD/NSR requirements might be for these options are available that are less
projects.
overstates the likely true cost impact 8 The two model runs (the final CAIR modeling
expensive than wet ESP.
because, as explained below, it relies on or the subsequent modeling with CAMR and CAVR) Nonetheless, the Agency’s cost
several conservative assumptions. For use the same underlying base case assumptions in analysis assumed that every unit that is
example, we assumed that every unit the same modeling platform. In other words, the predicted to install SCR and/or wet FGD
that is projected to install SCR and/or two runs are based on identical assumptions for in the CAIR/CAMR/CAVR modeling
parameters such as (this is not an exhaustive list):
EGU inventory, fuel prices, impacts of the national will incur additional costs for year-
wwhite on PROD1PC65 with PROPOSAL

6 The IPM is a multiregional, dynamic, title IV SO2 program, NOX SIP program, State- round operation of a wet ESP, in order
deterministic linear programming model of the U.S. specific programs, and NSR settlements. Note that to provide an upper-end estimate of the
electric power sector. The Agency uses IPM to projected marginal costs for CAIR SO2 and NOX possible cost impacts of SO3/H2SO4
examine costs and, more broadly, analyze the reductions are about $100 per ton less in the CAIR/
projected impact of environmental polices on the CAMR/CAVR modeling than in the final CAIR mitigation.
electric power sector in the 48 contiguous States modeling, due to interactions between the three Table III–2 shows the results of this
and the District of Columbia. programs. analysis. It compares the SO2 and NOX

VerDate Aug<31>2005 16:10 Dec 28, 2005 Jkt 208001 PO 00000 Frm 00038 Fmt 4702 Sfmt 4702 E:\FR\FM\29DEP1.SGM 29DEP1
Federal Register / Vol. 70, No. 249 / Thursday, December 29, 2005 / Proposed Rules 77107

marginal costs in the SO3/H2SO4 modeling (Table III–2 also shows the sensitivity analysis, the costs of SO3/
mitigation sensitivity analysis to the marginal costs from the modeling that H2SO4 mitigation are reflected in the
marginal costs in the final CAIR included CAIR, CAMR and CAVR).9 In marginal costs of SO2 and NOX control.
TABLE III–2.—SO2 AND NOX ESTIMATED MARGINAL COST
[1999$ per ton] 1

SO2 Annual NOX Annual

2010 2015 2009 2015

CAIR modeling used in final CAIR cost-effectiveness analysis ...................................................... $700 $1,000 $1,300 $1,600
CAIR/CAMR/CAVR modeling .......................................................................................................... 600 900 1,200 1,500
Sensitivity analysis with SO3/H2SO4 mitigation (based on CAIR/CAMR/CAVR modeling) ............ 700 900 1,600 2,000
1 EPA IPM modeling is available in the docket. Projected costs are rounded to the nearest hundred dollars.

As shown in Table III–2, projected at the low end of the range of costs cited than wet ESP. For this boilermaker labor
SO2 marginal costs in the SO3/H2SO4 in the final CAIR highly cost- analysis, the Agency used the identical
mitigation sensitivity modeling are effectiveness determination (70 FR assumptions regarding boilermaker
lower than the SO2 marginal costs in the 25201–25204, 25208–25210). Thus, that availability factors (i.e., boilermaker
final CAIR modeling for 2015 and are determination is not affected by the sources, population, average annual
about the same as the costs in the final possible costs that may be incurred by work hours, activity periods, and duty
CAIR for 2010. This does not imply that units installing SO3/H2SO4 mitigation rates) that we used in the boilermaker
the added costs of SO3H2SO4 mitigation technologies. The Agency believes that analysis for the final CAIR. These
are so small as to have no effect on the average costs of SO2 and NOX control factors are defined in the final CAIR
marginal costs of SO2 reduction. Rather, also would not increase significantly boilermaker TSD.
the added costs of SO3/H2SO4 mitigation enough to impact the CAIR cost- For today’s notice, the Agency based
increase the SO2 marginal cost from the effectiveness determination, because the its boilermaker analysis on the
level in the CAIR/CAMR/CAVR run a projected marginal costs do not increase generating capacity that is projected to
small amount. As explained above, enough to impact the CAIR analysis. install NOX and SO2 controls that may
marginal cost levels in CAIR/CAMR/ The Agency discusses below its increase sulfuric acid emissions (the
CAVR modeling are lower than costs in evaluation of the feasibility of installing three combinations of SCR and/or wet
the modeling in the CAIR final SO3/H2SO4 mitigation measures, and the FGD retrofits and coal switches
rulemaking. In the SO3/H2SO4 impacts of NSR analysis. identified in Table III–1). The EPA
mitigation sensitivity analysis, the 2010 Feasibility and Timing Analysis. In its examined the capacity of retrofits that
cost is increased to about the level in CAIR analysis, the Agency evaluated the are projected to occur during the time
the final CAIR modeling, and the 2015 feasibility of installing projected SO2 period when CAIR retrofits would occur
cost increase is small enough that it is and NOX control retrofits in the CAIR for the two CAIR phases (i.e., during the
not apparent when the costs are timeframe. In particular, EPA examined years 2007 through 2015 inclusive).
rounded to the nearest hundred dollars. the availability of boilermaker labor to This analysis includes retrofits
Including the added costs of SO3/H2SO4 install retrofits during the period when projected to occur as result of the CAIR,
mitigation, the projected marginal costs the CAIR retrofits will occur and CAMR and CAVR policies as well as
of SO2 reduction under CAIR remain at determined that sufficient labor will be retrofits for base case policies (i.e.,
the lower end of the reference range of available (70 FR 25215–25225). The retrofits for existing regulatory
marginal costs cited in the Agency’s Agency’s CAIR analysis was discussed requirements such as the title IV SO2
CAIR cost-effectiveness determination. in detail in a TSD entitled ‘‘Boilermaker program and the NOX SIP Call) because
The range of marginal costs cited in Labor and Installation Timing some base case retrofits will occur
CAIR is $600 to $2,200 per ton of SO2 Analysis,’’ OAR–2003–0053–2092 during the time period 2007 through
removed (70 FR 25201–25204). (‘‘final CAIR boilermaker TSD’’). 2015.
As shown in Table III–2, projected The Agency has evaluated the In its analysis for the final CAIR, the
NOX marginal costs in the SO3/H2SO4 potential impacts on the CAIR timeline Agency determined that adequate
mitigation sensitivity are higher than from installation of SO3/H2SO4 boilermaker labor would be available to
the costs in the final CAIR modeling. mitigation technologies. Specifically, we complete the CAIR NOX and SO2 control
However, including the added costs of examined the impact of installing wet retrofits in the CAIR timeline, with
SO3/H2SO4 mitigation, the projected ESP on the availability of boilermaker sufficient contingency factors available
NOX marginal costs remain at the lower labor during the time when control to offset possible additional labor needs
end of the reference range of marginal retrofits will be installed for the two due to unforeseen events. In the final
costs cited in the Agency’s cost- CAIR phases. The EPA’s analysis CAIR, EPA considered a number of
effectiveness determination. The range assumed that units that might scenarios that included different
of marginal costs cited in CAIR is $2,000 experience sulfuric acid emission assumptions for boilermaker duty rates
to $19,600 per ton of annual NOX increases greater than the NSR threshold (i.e., the amount of time required for a
removed (70 FR 25208–25210). while incorporating NOX and/or SO2 boilermaker to install control
For the reasons discussed above, the controls for CAIR would choose to equipment), electricity demand and gas
Agency’s analysis likely overstates the install wet ESP, which is a conservative prices. In the most conservative scenario
wwhite on PROD1PC65 with PROPOSAL

cost impacts of SO3/H2SO4 mitigation. assumption because SO3/H2SO4 analyzed, EPA determined that there
Nonetheless, even with these projected mitigation measures are available that would be a 14 percent boilermaker labor
cost impacts, the marginal costs remain would require less boilermaker labor contingency (i.e., 14 percent more labor
9 As in the CAIR NFR (70 FR 25198), the Agency CAIR phases although the Phase I CAIR control levels were determined based on feasibility rather
reports cost effectiveness results for both of the than cost effectiveness.

VerDate Aug<31>2005 17:50 Dec 28, 2005 Jkt 208001 PO 00000 Frm 00039 Fmt 4702 Sfmt 4702 E:\FR\FM\29DEP1.SGM 29DEP1
77108 Federal Register / Vol. 70, No. 249 / Thursday, December 29, 2005 / Proposed Rules

would be available than the amount 6. Increases in Carbon Monoxide and controls and SCR. These sources have
required to install the controls). The Unburned Carbon (Solid Particulate) the option to use combustion control
boilermaker duty rates used for this case Emissions From Combustion Controls designs ensuring minimal CO and
were provided by a commenter on the Combustion controls that may be unburned carbon impacts, with SCR
CAIR, were well above the levels installed for CAIR to reduce NOX compensating for the possible reduced
determined to be appropriate in a emissions include low NOX burners performance of combustion controls.
detailed study conducted by EPA, and, (LNB) and overfire air (OFA). Both LNB Considering the potential of SCR
based on EPA’s investigations, reflected and OFA reduce NOX generation rates technology to provide 90 percent NOX
the worst-case assumptions for the by changing the combustion process. reduction with a minimum NOX rate of
boilermaker labor requirements Either one or both technologies may be 0.06 lb/MMBtu, most of these sources
associated with building air pollution installed on a generating unit to control would be able to use this strategy and
controls. If the boilermaker NOX emissions. Depending on the boiler avoid use of aggressive combustion
requirements are estimated using EPA’s design, these changes may result in an control designs.
boilermaker duty rates, the available increase in emissions of carbon The affected CAIR sources also have
contingency would be higher. monoxide (CO) and unburned carbon the option to use an advanced OFA
(solid particulate), although the system with the potential to achieve
The revised boilermaker labor high NOX reduction levels, with no
analysis that the Agency conducted for potential for increases significant
enough to trigger the NSR threshold increases in CO and unburned carbon
today’s notice, which takes into account levels. This technology utilizes rotating
boilermaker labor required to install wet exists only with the use of OFA
(because LNB does not affect the opposed fire air (ROFA) and has been
ESP, indicates that adequate installed or demonstrated at several
combustion process extensively).
boilermaker labor will be available even These emissions increases can be plants worldwide.15
considering the additional boilermakers minimized by using more modern The Agency believes that there will be
that may be needed to install the wet control designs and techniques.10 11 12 no increase in cost to CAIR units for
ESP. Considering the same assumptions These increases can also be minimized using good combustion practices to
that yielded a 14 percent contingency in by using less-aggressive OFA flow mitigate CO and unburned carbon
the final CAIR along with additional rates.13 The NOX removal efficiencies increases, because industry generally
boilermakers needed to install wet ESPs, for combustion controls assumed in uses such practices already.
EPA determined that there would be a EPA’s CAIR analysis are not Implementation of these practices
4 percent contingency. Again, if the aggressive.14 The Agency believes that would not affect the Agency’s CAIR
boilermaker requirements are estimated units projected to install combustion highly cost-effectiveness determination
using EPA’s boilermaker duty rates, the controls can opt for moderate levels of or the feasibility and timing analysis.
available contingency would be higher. OFA flow rates and still achieve the In addition, the implications of NSR
NOX reduction levels projected in our analysis for such units are relatively
This analysis is conservative in that it
CAIR analysis, without causing minor, as discussed further below.
assumes that in all cases where The Agency believes that the impacts
companies install equipment to mitigate significant increases in CO and
unburned carbon emissions. Therefore, of either mitigating the potential
SO3/H2SO4 increases, they install wet emission increases, or undertaking NSR
ESPs, which use more boilermakers given the conservative removal
efficiency assumptions in EPA’s original review for these units, are not
than other options such as sorbent substantial enough to affect the CAIR
injection. The remaining contingency analysis, there would be no additional
significant costs associated with highly cost-effective determination or
factors are still adequate (although the feasibility and timing analysis.
reduced). Thus, the NOX and SO2 mitigating CO emissions to avoid NSR
when combustion controls are added. Implications of NSR analysis for such
control retrofits projected to be installed units are discussed further below.
for CAIR can be completed in the Certain affected CAIR sources are
available time, even considering the projected to install both combustion 7. Increases in Direct PM2.5 Resulting
potential additional labor needs for From Fugitive Emissions From Storage
10 T. Steitz, et al., ‘‘Wall Fired Low NO Burner
SO3/H2SO4 mitigation. Note that any X or Handling of Lime, Limestone, or FGD
Evolution for Global NOX Compliance,’’ Foster
SO3/H2SO4 controls for CAIR projects Wheeler Web site, http://www.fwc.com/
Waste After Installation of Dry or Wet
can be retrofit concurrently with the publications/tech_papers/index.cfm# FGD
SO2 and NOX retrofits, and no 14905467952D7FCAFC2A5B206EAE10F0, Web site As discussed above, dry and wet FGD
accessed on September 30, 2005.
additional time would be needed. See 11 K. McCarthy, et al., ‘‘Improved Low NO Firing are effective SO3/H2SO4 mitigation
X
further discussion of timing in the Systems for Pulverized Coal Combustion,’’ Foster options. A separate consideration,
permitting section, below. Wheeler Web site, http://www.fwc.com/ however, is the potential for increased
publications/tech_papers/index.cfm# emissions of direct PM (including
Details of EPA’s revised boilermaker 14905467952D7FCAFC2A5B206EAE10F0, Web site
labor analysis are in a TSD in the docket accessed on September 30, 2005.
PM2.5) resulting from the storage and
entitled ‘‘Impact on CAIR Analyses of 12 ‘‘Reducing Emissions of Nitrogen Oxides Via handling of lime or limestone for the
D.C. Circuit Decision in New York v. Low-NOX Burner Technologies,’’ Clean Coal FGD and from hauling FGD waste.
EPA.’’ Technology, The Department of Energy, Topical The EPA believes that operation of
Report No. 5, September 1996. FGD will not result in significant
The Agency believes that the impacts 13 A. Kokkinos, et al., ‘‘B&W’s Experience
increases of emissions of direct PM
of mitigating the potential emission Reducing NOX Emissions in Tangentially-Fired
Boilers—2001 Update,’’ Power-Gen International (including PM2.5). Fugitive PM
increases, or undertaking NSR review 2001, December 11–13, 2001, Las Vegas, Nevada. emissions resulting from the storage and
wwhite on PROD1PC65 with PROPOSAL

for these units, are not substantial 14 The NO removal efficiency for each type of
X handling of lime or limestone and from
enough to alter the CAIR highly cost- combustion control used in EPA’s analysis for CAIR waste hauling associated with FGD
effective determination or the feasibility was estimated as an average of the reported
efficiencies for a large number of units equipped operation are minimal since most lime
and timing analysis. Implications of with these controls. In a unit equipped with both
NSR analysis for such units are LNB and OFA, LNB provides a greater part of the 15 MOBOTECUSA Web site, http://

discussed further below. overall NOX removal. www.mobotecusa.com/.

VerDate Aug<31>2005 17:50 Dec 28, 2005 Jkt 208001 PO 00000 Frm 00040 Fmt 4702 Sfmt 4702 E:\FR\FM\29DEP1.SGM 29DEP1
Federal Register / Vol. 70, No. 249 / Thursday, December 29, 2005 / Proposed Rules 77109

and limestone will be stored in covered 9. Summary of Section III.B. procurement) for the first phase of CAIR
structures with particulate controls, EPA’s IPM modeling predicts that control retrofits. The 22 months is based
lime and limestone will be transported some CAIR units will add controls with on the time from the CAIR promulgation
in covered vehicles, and particulate the potential to increase collateral date (March 10, 2005) until about 4
emissions mitigation techniques, emissions of NSR-regulated pollutants. months after the SIP submission date
including spraying near storage areas, However, the Agency has determined (about mid-January 2007).16 The New
hauling roads, and waste hauling trucks, that for each of the NOX and SO2 York v. EPA judicial decision was
will be employed. Fugitive emissions controls on which EPA based its CAIR issued on June 24, 2005. As a result of
could result from dust recirculation due highly cost-effectiveness determination, that decision, either CAIR sources will
to truck hauling, but these emissions are there are technology options available to need to mitigate emissions through one
also not significant enough to trigger of the various options discussed above,
mitigate potential collateral increases of
NSR. or they may choose to apply for NSR
NSR regulated pollutants such that
The Agency believes that the impacts permits. Sources that elect to obtain
of either mitigating these small potential many sources, looking to comply with
the CAIR requirements, would not NSR permits then would have almost 19
emission increases, or undertaking NSR months for NSR review for the first
review for these units, are not trigger NSR review for potential
collateral increases (however, some CAIR phase (from the date of the New
substantial enough to affect the CAIR York v. EPQ decision until about mid-
highly cost-effective determination or sources may not be able to ensure
mitigation of all collateral increases). January 2007). The Agency believes that
the feasibility and timing analysis. this is adequate time to perform NSR
Further, although some additional cost
8. Collateral Air Pollutant Emissions may be associated with mitigation review, as explained further below, thus
From Units Switching From High to measures, EPA’s analysis showed that the CAIR timeline would not be
Low Sulfur Coals these costs do not change the impacted.
conclusions of EPA’s highly cost- In the CAIR, the Agency determined
A switch from high-to low-sulfur highly cost-effective amounts of
coals is an option projected to be used effectiveness determination. In addition,
implementing these mitigation measures emission reductions based on modeled
by certain CAIR sources for SO2 control.
will not affect the feasibility of costs of SO2 and NOX mitigation, using
In some cases, modifications to the
implementing the CAIR reductions in IPM. The IPM cost modeling used in
existing equipment may become
the required timeframe. Options exist EPA’s analysis reflects the capital and
necessary to maintain compatibility
that would allow units to meet the CAIR operations and maintenance costs of
with the boiler and associated systems.
deadlines without changing plans to control technologies. The modeling does
One of the more common modifications
stagger PCP projects. For example, a not include costs associated with
required is the need to restore the
unit planning to install SCR first and permitting. Costs for permitting are
existing ESP performance, which may
FGD later could choose to use sorbent insignificant compared to costs of
be degraded due to the high-resistivity
ash generated from firing of low-sulfur injection technology to mitigate SO3/ constructing and operating these
coals (if ESP performance is not H2SO3 during the time between controls technologies.
restored, emissions of PM might installation of the SCR and the FGD. Prior to the D.C. Circuit decision to
increase). In general, use of a flue gas vacate the PCP provisions in the NSR
C. Potential Impact of NSR Permitting program, EGUs desiring to use the PCP
conditioning system fully restores the
ESP performance to levels obtained Although the above analysis shows exclusion were required to either
from firing of high-sulfur coals. that sources installing controls for CAIR provide notice to the Administrator (for
The impact of coal switching on the generally will have options to avoid certain projects listed in the regulations)
existing plant equipment would vary triggering NSR review for potential or submit a permit application to obtain
with the amount of switch. For example, collateral increases, EPA also analyzed approval to use the exclusion. This
if only a portion of the existing high- the potential impact on its CAIR process had requirements very similar
sulfur coal is replaced with the new analyses of sources whose projects to those that apply to sources subject to
low-sulfur coal, the impact may be could result in a net emissions increase NSR review. The basic steps for sources
minimal. Also, use of certain types of despite mitigative measures that might undergoing NSR review are:
low-sulfur coals may even have a be taken, and might therefore apply for a. Preparation of the permit
beneficial impact on some of the NSR- and obtain the necessary NSR permits to application and participation in any
regulated pollutants. For example, use address such increase. Accordingly, pre-permit application meetings;
of western sub-bituminous coals may EPA analyzed whether sources b. Issuance of permit application
result in a reduction in the CO and undergoing NSR permitting would have completeness determination by the
unburned carbon levels, because of the adequate time to obtain the regulatory agency;
high volatile contents of such coals. preconstruction permit and whether any c. Development and negotiation of the
In the CAIR analysis, EPA assumed controls required would impact EPA’s draft permit;
that the sources opting to switch to low- highly cost-effective analysis done for d. Opportunity for public notice and
sulfur coal would either select CAIR. The Agency intends to work with comment on the draft permit;
compatible coals or provide the States to quickly resolve any e. Response by the regulatory agency
modifications where required to avoid questions regarding permitting of CAIR to public comments; and
any adverse impacts on their boilers, pollution control projects, and will f. Possible administrative and judicial
including minimization of any increases provide technical assistance when appeals.
in air emissions. The EPA included requested to facilitate permitting. Of these steps, the bulk of the effort
is concentrated in the beginning steps
wwhite on PROD1PC65 with PROPOSAL

costs for such modifications in its In its analysis for the final CAIR, the
estimates for the CAIR implementation, Agency assumed that affected sources with the preparation of the permit
which were based on the coal switch would have about 22 months available 16 ‘‘Boilermaker Labor Analysis and Installation
experience for the power industry. for preconstruction activities (e.g., Timing,’’ March 2005, discusses the Agency’s
Therefore, no further analysis is permitting, planning, conceptual design, projected schedules for CAIR SCR and FGD retrofits
necessary. engineering, financing, and (OAR–2003–0053–2092).

VerDate Aug<31>2005 16:10 Dec 28, 2005 Jkt 208001 PO 00000 Frm 00041 Fmt 4702 Sfmt 4702 E:\FR\FM\29DEP1.SGM 29DEP1
77110 Federal Register / Vol. 70, No. 249 / Thursday, December 29, 2005 / Proposed Rules

application and collection and analysis the air quality in the vicinity of the result of the PCP. Special attention
of the data necessary to demonstrate affected source. Moreover, such data is would have been given in cases where
that the project would not present only required when the source’s a FLM had already identified adverse
problems with the NAAQS. The PCP emissions increase is predicted to impacts for an AQRV. In such cases, the
exclusion did not excuse a source from exceed the prescribed significant facility requesting the PCP exclusion
undergoing a similar analysis in order to monitoring value for that pollutant. See would have been expected to record and
obtain the PCP determination. 40 CFR 52.21(i)(5). Thus, sources consider any information that the FLM
Specifically, under the new source generally will not have to take the time had made available concerning the
review rules of 2002 (67 FR 80186), a to collect such data on their own when adverse effects, to help determine
source seeking to use the PCP it is required. In the few cases, if any, whether the pollutant impacts from the
provisions for one of the listed where it is the applicant’s burden to collateral emissions increase had the
technologies would automatically collect the data, we believe they will potential to cause further adverse
qualify for the exclusion if it could have adequate time to do so while the impacts.
demonstrate that there was no adverse overall project to comply with CAIR is If the requested PCP was included in
air quality impact, that is, if it would being developed without delaying the the list of projects presumed to be
not cause or contribute to a violation of necessary permit application. environmentally beneficial, the source
NAAQS or PSD increment, or adversely For sources that requested a PCP requesting the PCP exclusion would
impact an air quality related value exclusion from the list of approved have been allowed to begin construction
(AQRV), such as visibility, that had projects (67 FR 80246), the timeline on the PCP immediately upon
been identified for a Federal Class I area could have been very similar in submitting the required notice to the
by a Federal Land Manager (FLM). In duration to the one described above for reviewing authority. However, if the
performing the air quality analysis sources undergoing NSR review. The reviewing authority determined that the
under the PCP provision, the procedures projects included on the list were source did not qualify for a PCP
established for conducting air quality presumed to be environmentally exclusion, the source might have been
analysis in conjunction with typical beneficial based on the premise that the subject to a delay in the project or an
NSR permitting were used. As such, the source seeking the PCP exclusion would order to not undertake the project. If the
up front burden associated with design and operate the controls in a reviewing authority, upon receiving the
undergoing NSR review is comparable manner that would be consistent with notification of using the PCP exclusion,
to the burden to which a source proper industry, engineering, and determined that an air quality impacts
requesting a PCP exclusion would have reasonable practices, and that the source analysis was reasonably necessary, it
been subject. would minimize increases in collateral was entitled to request more
Once the permit application is pollutants within the physical information from the source, including
complete, whether processed as a PCP configuration and operational standards additional local or regional modeling.
exclusion request or as a formal PSD usually associated with the emissions Pollution control projects of the
permit application, the processing by control device or strategy. The source magnitude at issue here will require
the permitting authority usually does seeking the PCP exclusion would have large capital expenditures and
not take any longer under the formal been required to certify that this was significant engineering lead times. We
PSD process than under the previous true in the notification sent to the believe that in most cases, the internal
PCP exclusion process. Typically, in the reviewing authority. It is important to procedures within each company to
formal NSR permitting process, once the highlight that the environmentally request, approve, and allocate the
application is submitted to the beneficial determination for the listed necessary funding and then design and
permitting authority, there is a process projects was a presumption, and as construct the control equipment will be
during which the draft permit is such, it could be rebutted in cases in at least as long as the average permit
developed and published to give the which a reviewing authority determined application and approval process.
public an opportunity to comment on that a particular proposed PCP project Additional requirements that may
the draft permit. Depending on the would not be environmentally result from NSR review. As discussed in
comments received, some changes to the beneficial. previous sections, sources installing
draft permit may be made and a final Before a source requesting a PCP controls to comply with CAIR that
permit would then be issued to the exclusion could have begun actual experience collateral emissions
source. Based on the permitting construction of the PCP, it was required increases of some NSR regulated
authorities’ experience, this process to submit a notice to the reviewing pollutants likely would have requested
typically takes approximately six to authority that included the following a PCP exclusion. In particular, sulfuric
eight months. In the case of permits information (and depending on the acid mist emissions and CO emissions
issued for the construction of pollution reviewing authority’s requirements, this are the two pollutants expected to be of
control projects on CAIR units, we see information could have been submitted most interest.
no reason why the process should with a part 70, part 71 or other SIP- For emissions of CO, the Agency is
require a longer time period than is approved permit application such as a aware of previous PSD permits that have
normally required. minor NSR permit application): (1) A been processed by permitting
In addition, we do not believe that the description of project; (2) an analysis of authorities that demonstrated no
PSD requirement for submitting pre- the environmentally beneficial nature of NAAQS problems, while requiring no
application monitoring data will cause a the PCP, including a projection of additional add-on controls for the CO
delay in submitting the required PSD emissions increases and decreases emissions. The PSD permits given to
permit applications as the petitioner (speciated, using an appropriate these sources included Best Achievable
wwhite on PROD1PC65 with PROPOSAL

alleges. The relevant provision which emissions test for the emissions unit); Control Technology (BACT) emissions
requires the applicant to include 12 and (3) a demonstration that the project limits for CO where in most cases such
months of continuous ambient air will not have an adverse air quality limits did not previously exist. Most of
quality data allows applicants to rely on impact. Often, a screening model could these limits have been set at or near the
ambient air quality data that has already be used to estimate the ambient impacts level where the utility has historically
been collected and is representative of of the increase from the facility as a operated or was anticipated to operate.

VerDate Aug<31>2005 16:10 Dec 28, 2005 Jkt 208001 PO 00000 Frm 00042 Fmt 4702 Sfmt 4702 E:\FR\FM\29DEP1.SGM 29DEP1
Federal Register / Vol. 70, No. 249 / Thursday, December 29, 2005 / Proposed Rules 77111

This is the case because there is no provide sufficient offsets for the adversely affect in a material way the
technically feasible add-on control significantly lower potential increases economy, a sector of the economy,
technology for controlling CO emissions in direct PM fine emissions. As such, productivity, competition, jobs, the
from coal-fired boilers other than good we believe that the impact for environment, public health or safety, or
combustion practices. undergoing NSR review on these State, local, or tribal governments or
For emissions increases of sulfuric sources would be minimal, as described communities;
acid mist, NSR permitting analysis above. (2) create a serious inconsistency or
treats sulfuric acid mist as a NSR- For projects located in attainment otherwise interfere with an action taken
regulated pollutant and also as a areas, a situation similar to when a or planned by another agency;
component of PM2.5 (a criteria source is required to install controls for (3) materially alter the budgetary
pollutant). The Agency conducted an acid mist is expected. That is, when a impact of entitlements, grants, user fees,
analysis of the information available for source in an attainment area goes or loan programs or the rights and
EGUs that have undergone NSR review through NSR review for PM2.5 as a result obligations of recipients thereof; or
and that included a determination of of a collateral increase due to the (4) raise novel legal or policy issues
controls (BACT or Lowest Achievable addition of CAIR controls, we expect the arising out of legal mandates, the
Emission Rate (LAER)) for sulfuric acid required control technology to be President’s priorities, or the principles
mist. The analysis showed that similar, if not identical, to those listed set forth in the Executive Order.
pollution prevention measures (such as as available mitigation techniques for Pursuant to the terms of Executive
low sulfur fuel) and add-on controls sources wanting to avoid NSR review. Order 12866, OMB has determined that
(such as flue gas desulfurization or FGD) As such, we believe that the impact for this is not a significant regulatory
were cited in about two thirds of the undergoing NSR review on these action. This notice takes comment on an
determinations, while about one third sources would be minimal, as described aspect of the CAIR, but does not propose
resulted in no additional control. As above. any modifications.
previously stated, both switching to low In conclusion, the Agency believes B. Paperwork Reduction Act
sulfur coal and the use of FGD are that the impacts of choosing to
common techniques available for CAIR undertake NSR review for these units This action does not propose
units to minimize collateral emissions are not substantial enough to affect the information collection request
increases due to the installation of CAIR highly cost-effective requirements under the provisions of
CAIR-related controls. As a result, we determination or the feasibility and the Paperwork Reduction Act, 44 U.S.C.
expect that a source going through NSR timing analysis. 3501 et seq. Therefore, an information
for significant net emissions increases in The EPA generally does not believe collection request document is not
sulfuric acid mist due to CAIR controls that the PCP requirements under NSR required.
would be required to install technology will pose a problem. This is because Burden means the total time, effort, or
similar, if not identical, to those either companies will make control financial resources expended by persons
presented here as available mitigation decisions that will not result in to generate, maintain, retain, or disclose
techniques to avoid NSR review. collateral pollution increases or the NSR or provide information to or for a
Because sulfuric acid mist emissions process will not delay installation of Federal agency. This includes the time
are also a component of PM2.5, EPA also pollution controls. Even if there were a needed to review instructions; develop,
looked at what, if any, additional PM2.5 small number of cases in which NSR acquire, install, and utilize technology
controls would be required for sources requirements delayed control and systems for the purposes of
required to undergo NSR should a installations beyond the compliance collecting, validating, and verifying
significant emissions increase of PM2.5 dates for CAIR, EPA does not believe information, processing and
occur. For CAIR emissions units located that this would change its conclusions maintaining information, and disclosing
in non-attainment areas, we also believe about the cost effectiveness of the and providing information; adjust the
that the result of the LAER analysis for existing ways to comply with any
required emission reductions. The cost
these units will result in control previously applicable instructions and
effectiveness is not significantly
technologies similar, if not identical, to requirements; train personnel to be able
impacted because the trading
those listed as available mitigation to respond to a collection of
mechanisms within CAIR provide
techniques. In addition to the LAER information; search data sources;
flexibility if small numbers of sources
requirements, CAIR sources required to complete and review the collection of
are unable to install controls by the
meet nonattainment area NSR would be information; and transmit or otherwise
compliance deadlines.
required to obtain emissions reductions disclose the information.
to offsets their significant emissions IV. Statutory and Executive Order An agency may not conduct or
increase of PM2.5 emissions as part of Reviews sponsor, and a person is not required to
non-attainment NSR permit process. We respond to a collection of information
believe PM fine offsets will be widely A. Executive Order 12866: Regulatory
unless it displays a currently valid OMB
available for any of these projects Planning and Review
control number. The OMB control
located in non-attainment areas. In the Under Executive Order 12866 (58 FR numbers for EPA’s regulations in 40
PM Implementation Rule (70 FR 66042) 51735, October 4, 1993), the Agency CFR are listed in 40 CFR part 9.
we proposed to allow units to use must determine whether the regulatory
decreases in PM fine precursor action is ‘‘significant’’ and, therefore, C. Regulatory Flexibility Act
emissions as offsets for direct PM fine subject to Office of Management and The Regulatory Flexibility Act
emission increases. Units installing Budget (OMB) review and the generally requires an Agency to prepare
wwhite on PROD1PC65 with PROPOSAL

controls to comply with CAIR will have requirements of the Executive Order. a regulatory flexibility analysis of any
very large decreases in PM fine The Order defines ‘‘significant rule subject to notice and comment
precursors (SO2 and NOX). These regulatory action’’ as one that is likely rulemaking requirements under the
decreases are so large that we believe to result in a rule that may: Administrative Procedures Act or any
the decreases in PM fine precursor (1) Have an annual effect on the other statute unless the Agency certifies
emissions from other CAIR units will economy of $100 million or more or the rule will not have a significant

VerDate Aug<31>2005 16:10 Dec 28, 2005 Jkt 208001 PO 00000 Frm 00043 Fmt 4702 Sfmt 4702 E:\FR\FM\29DEP1.SGM 29DEP1
77112 Federal Register / Vol. 70, No. 249 / Thursday, December 29, 2005 / Proposed Rules

economic impact on a substantial any regulatory requirements that may relationship. Thus, Executive Order
number of small entities. Small entities significantly or uniquely affect small 13132 does not apply to this action.
include small businesses, small governments, including tribal
F. Executive Order 13175: Consultation
organizations, and small governmental governments, it must have developed,
and Coordination With Indian Tribal
jurisdictions. under section 203 of the UMRA, a small
For purposes of assessing the impacts Governments
government agency plan. The plan must
of today’s proposed rule on small provide for notifying potentially Executive Order 13175, entitled
entities, small entity is defined as: (1) A affected small governments, enabling ‘‘Consultation and Coordination with
small business that is a small industrial officials of affected small governments Indian Tribal Governments’’ (65 FR
entity as defined in the U.S. Small to have meaningful and timely input in 67249, November 9, 2000), requires EPA
Business Administration (SBA) size the development of EPA’s regulatory to develop an accountable process to
standards. (See 13 CFR part 121.); (2) a proposals with significant Federal ensure ‘‘meaningful and timely input by
governmental jurisdiction that is a intergovernmental mandates, and Tribal officials in the development of
government of a city, county, town, informing, educating, and advising regulatory policies that have Tribal
school district or special district with a small governments on compliance with implications.’’
population of less than 50,000; and (3) the regulatory requirements. For the same reasons stated in the
a small organization that is any not-for- final CAIR, today’s notice does not have
The EPA has determined that today’s
profit enterprise which is independently tribal implications as defined by
notice of reconsideration does not
owned and operated and is not Executive Order 13175. It does not have
contain a Federal mandate that may
dominant in its field. a substantial direct effect on one or
result in expenditures of $100 million or
After considering the economic more Indian Tribes, since no tribe has
more for State, local, and tribal
impacts of today’s proposed rule on implemented a federally-enforceable air
governments, in the aggregate, or the
small entities, I certify that this action quality management program under the
private sector in any 1 year. Today’s
will not have a significant economic CAA at this time. Furthermore, this
notice of reconsideration of the CAIR
impact on a substantial number of small action does not affect the relationship or
does not add new requirements that
entities. This notice does not impose distribution of power and
would increase the cost of the CAIR.
any requirements on small entities. We responsibilities between the Federal
Thus, today’s notice of reconsideration
are only announcing our decision to Government and Indian Tribes. The
is not subject to the requirements of
reconsider and request comment on a CAA and the Tribal Air Rule establish
sections 202 and 205 of the UMRA. In
specific issue in the CAIR. We continue the relationship of the Federal
addition, EPA has determined that
to be interested in the potential impacts Government and tribes in developing
today’s notice of reconsideration does
of the rule on small entities and plans to attain the NAAQS, and today’s
welcome comments on issues related to not significantly or uniquely affect small
notice does nothing to modify that
such impacts. governments because it contains no
relationship. Because this notice does
requirements that apply to such
not have tribal implications, Executive
D. Unfunded Mandates Reform Act governments or impose obligations
Order 13175 does not apply.
Title II of the Unfunded Mandates upon them. Therefore, today’s notice of If one assumes a tribe is implementing
Reform Act of 1995 (UMRA), Public reconsideration is not subject to section a tribal implementation plan, the CAIR
Law 104–4, establishes requirements for 203 of the UMRA. could have implications for that tribe,
Federal agencies to assess the effects of E. Executive Order 13132: Federalism but it would not impose substantial
their regulatory actions on State, local, direct costs upon the tribe, nor would it
and tribal governments and the private Executive Order 13132, entitled preempt tribal Law.
sector. Under section 202 of the UMRA, ‘‘Federalism’’ (64 FR 43255, August 10, Although Executive Order 13175 does
EPA generally must prepare a written 1999), requires EPA to develop an not apply to the CAIR or this notice of
statement, including a cost-benefit accountable process to ensure reconsideration of the CAIR, EPA
analysis, for proposed and final rules ‘‘meaningful and timely input by State consulted with tribal officials in
with ‘‘Federal mandates’’ that may and local officials in the development of developing the CAIR.
result in expenditures by State, local, regulatory policies that have federalism
and tribal governments, in the aggregate, implications.’’ ‘‘Policies that have G. Executive Order 13045: Protection of
or by the private sector, of $100 million federalism implications’’ is defined in Children From Environmental Health
or more in any 1 year. Before the Executive Order to include and Safety Risks
promulgating an EPA rule for which a regulations that have ‘‘substantial direct Executive Order 13045: ‘‘Protection of
written statement is needed, UMRA effects on the States, on the relationship Children From Environmental Health
section 205 generally requires EPA to between the National Government and and Safety Risks’’ (62 FR 19885, April
identify and consider a reasonable the States, or on the distribution of 23, 1997) applies to any rule that (1) is
number of regulatory alternatives and power and responsibilities among the determined to be ‘‘economically
adopt the least costly, most cost- various levels of government.’’ significant’’ as defined under Executive
effective, or least-burdensome This action does not have federalism Order 12866, and (2) concerns an
alternative that achieves the objectives implications. It would not have environmental health or safety risk that
of the rule. The provisions of section substantial direct effects on the States, EPA has reason to believe may have
205 do not apply when they are on the relationship between the disproportionate effect on children. If
inconsistent with applicable law. National Government and the States, or the regulatory action meets both criteria,
Moreover, section 205 allows EPA to on the distribution of power and the Agency must evaluate the
wwhite on PROD1PC65 with PROPOSAL

adopt an alternative other than the least- responsibilities among the various environmental health or safety effects of
costly, most cost-effective, or least- levels of government, as specified in the planned rule on children, and
burdensome alternative if the Executive Order 13132. The CAA explain why the planned regulation is
Administrator publishes with the final establishes the relationship between the preferable to other potentially effective
rule an explanation why that alternative Federal Government and the States, and and reasonably feasible alternatives
was not adopted. Before EPA establishes this action would not impact that considered by the Agency.

VerDate Aug<31>2005 16:10 Dec 28, 2005 Jkt 208001 PO 00000 Frm 00044 Fmt 4702 Sfmt 4702 E:\FR\FM\29DEP1.SGM 29DEP1
Federal Register / Vol. 70, No. 249 / Thursday, December 29, 2005 / Proposed Rules 77113

This notice is not subject to Executive exposure to hazards that are significant 2005. The following sections of
Order 13045 because it does not involve and that ‘‘appreciably exceed or is likely Michigan’s rules are affected: Part 3:
decisions on environmental health risks to appreciably exceed the risk or rate to Emission Limitations and
or safety risks that may the general population or to the Prohibitions—Particulate Matter; Part 4:
disproportionately affect children. The appropriate comparison group.’’ (EPA, Emission Limitations and
EPA believes that the emissions 1998). Prohibitions—Sulfur-bearing
reductions from the CAIR will further In accordance with Executive Order Compounds; Part 6: Emission
improve air quality and children’s 12898, the Agency has considered Limitations and Prohibitions—Existing
health. whether the CAIR may have Sources of Volatile Organic Compound
H. Executive Order 13211: Actions That disproportionate negative impacts on Emissions; Part 7: Emission Limitations
Significantly Affect Energy Supply, minority or low income populations. and Prohibitions—New Sources of
Distribution, or Use The EPA expects the CAIR to lead to Volatile Organic Compound Emissions;
reductions in air pollution and Part 9: Emission Limitations and
This rule is not subject to Executive exposures generally. Therefore, EPA Prohibitions—Miscellaneous; Part 10:
Order 13211, ‘‘Actions Concerning concluded that negative impacts to Intermittent Testing and Sampling; and
Regulations That Significantly Affect these sub-populations that appreciably Part 11: Continuous Emission
Energy Supply, Distribution, or Use’’ (66 exceed similar impacts to the general Monitoring. The revisions are primarily
FR 28355 (May 22, 2001)) because it is population are not expected. For the administrative changes and minor
not a significant regulatory action under same reasons, EPA is drawing the same corrections.
Executive Order 12866. conclusion for today’s notice to DATES: Comments must be received on
I. National Technology Transfer reconsider a certain aspect of the CAIR. or before January 30, 2006.
Advancement Act List of Subjects ADDRESSES: Submit comments,
Section 12(d) of the National identified by Docket ID No. EPA–R05–
Technology Transfer Advancement Act 40 CFR Part 51
OAR–2004–MI–0001, by one of the
of 1995, Public Law 104–113, section Administrative practice and following methods:
12(d) (15 U.S.C. 272 note) directs EPA procedure, Air pollution control, • http://www.regulations.gov: Follow
to use voluntary consensus standards in Intergovernmental relations, Nitrogen the on-line instructions for submitting
its regulatory activities unless to do so oxides, Ozone, Particulate matter, comments.
would be inconsistent with applicable Regional haze, Reporting and • E-mail: mooney.john@epa.gov.
law or otherwise impractical. Voluntary recordkeeping requirements, Sulfur • Fax: (312) 886–5824.
consensus standards are technical dioxide. • Mail: John M. Mooney, Chief,
standards (e.g., materials specifications, Criteria Pollutant Section, (AR–18J),
40 CFR Part 96 U.S. Environmental Protection Agency,
test methods, sampling procedures, and
business practices) that are developed or Administrative practice and 77 West Jackson Boulevard, Chicago,
adopted by voluntary consensus procedure, Air pollution control, Illinois 60604.
standards bodies. The National Electric utilities, Nitrogen oxides, • Hand Delivery: John M. Mooney,
Technology Transfer Advancement Act Reporting and recordkeeping Chief, Criteria Pollutant Section, (AR–
of 1995 directs EPA to provide requirements, Sulfur dioxide. 18J), U.S. Environmental Protection
Congress, through OMB, explanations Dated: December 22, 2005. Agency, 77 West Jackson Boulevard,
when the Agency decides not to use Stephen L. Johnson, 18th floor, Chicago, Illinois 60604. Such
available and applicable voluntary deliveries are only accepted during the
Administrator.
consensus standards. Regional Office’s normal hours of
[FR Doc. 05–24609 Filed 12–28–05; 8:45 am]
Today’s notice does not involve operation, and special arrangements
BILLING CODE 6560–50–P
technical standards. Therefore, the should be made for deliveries of boxed
National Technology Transfer and information. The Regional Office’s
Advancement Act of 1995 does not official hours of business are Monday
ENVIRONMENTAL PROTECTION
apply. through Friday, 8:30 a.m. to 4:30 p.m.
AGENCY
excluding Federal holidays.
J. Executive Order 12898: Federal
40 CFR Part 52 Instructions: Direct your comments to
Actions To Address Environmental
Docket ID No. EPA–R05–OAR–2004–
Justice in Minority Populations and [EPA–R05–OAR–2004–MI–0001; FRL–8016– MI–0001. EPA’s policy is that all
Low-Income Populations 4] comments received will be included in
Executive Order 12898, ‘‘Federal the public docket without change and
Actions to Address Environmental Approval and Promulgation of
may be made available online at
Justice in Minority Populations and Implementation Plans; Michigan
http://www.regulations.gov, including
Low-Income Populations,’’ requires AGENCY: Environmental Protection any personal information provided,
Federal agencies to consider the impact Agency (EPA). unless the comment includes
of programs, policies, and activities on ACTION: Proposed rule. information claimed to be Confidential
minority populations and low-income Business Information (CBI) or other
populations. According to EPA SUMMARY: The EPA is proposing to information whose disclosure is
guidance,17 agencies are to assess partially approve and partially restricted by statute. Do not submit
whether minority or low-income disapprove revisions to the Michigan information that you consider to be CBI
populations face risks or a rate of
wwhite on PROD1PC65 with PROPOSAL

State Implementation Plan (SIP). These or otherwise protected through http://


revisions were submitted to the EPA by www.regulations.gov or e-mail. The
17 U.S. Environmental Protection Agency, 1998.
the Michigan Department of http://www.regulations.gov Web site is
Guidance for Incorporating Environmental Justice
Concerns in EPA’s NEPA Compliance Analyses.
Environmental Quality (MDEQ) on an ‘‘anonymous access’’ system, which
Office of Federal Activities, Washington, DC, April, April 3, 2003, May 28, 2003, September means EPA will not know your identity
1998. 17, 2004, October 25, 2004 and June 8, or contact information unless you

VerDate Aug<31>2005 16:10 Dec 28, 2005 Jkt 208001 PO 00000 Frm 00045 Fmt 4702 Sfmt 4702 E:\FR\FM\29DEP1.SGM 29DEP1

You might also like