EMPLOYER

ASHVI DEVELOPERS PRIVATE LIMITED

PROJECT

Strengthening & Construction of Residential Tower at Goregaon (West) Mumbai

TENDER FOR STRENGTHENING, RCC, STRUCTURAL, MEP AND FINISHES WORKS OF


RESIDENTIAL TOWER AT GOREGAON (WEST) MUMBAI FOR ASHVI DEVELOPERS
PRIVATE LIMITED
ADDENDUM 1 (Date 16 November 2013)

Sl. No Tender Reference Clause

Revision
Name of Employee shall be
M/s Ashvi Developers Private Limited,

1.

Vol I / Section 4 / Contract


Data Sheet

Ariisto House, N. S. Phadake Road,


Near East West Flyover, Andheri (East),
Mumbai 400 069.

2.

Vol I / Section 4 / Contract


Data Sheet

Contractor shall use DG as available at site at no cost to be paid to


Employer. Contractor to bear all operation and maintenance cost to
maintain the DG in good working condition and hand over to
Employer in good working condition after completion of work.

3.

Vol I / Section 5 / Appendix F

Revised Basic Rate Annexure

4.

Vol III / Section 8 / BOQ

Revised BOQ for Strengthening Work

5.

Pre-bid Meeting Queries

Clarification to pre-bid meeting queries.

6.

Submission Date

Signed and stamped hard copy of Tender Document in sealed


envelope to be submitted in Employer Office by 17:00 Hrs on
Tuesday, 26 November 2013.

Addendum 1

1of1Seal & Sign of Bidder

EMPLOYER - ASHVI DEVELOPERS PRIVATE LIMITED


PROJECT - Strengthening Construction of Residential Tower at Goregaon (West) Mumbai

BASIC RATE OF MATERIAL


Sr.No.

Description

Allowable
Wastage in
%

Unit

Basic Rate

BAG

300.00

2%

CEMENT-OPC

REINFORCEMENT STEEL - TMT Fe 500

MT

47,000.00

3%

REINFORCEMENT STEEL - TMT Fe 500

MT

50,000.00

5%

RUBBLE

Cum

800.00

5%

Concrete M60 (Including Pumping)

Cum

7,200.00

5%

Concrete M50 (Including Pumping)

Cum

6,607.00

5%

Concrete M40 (Including Pumping)

Cum

5,161.00

5%

Concrete M30 (Including Pumping)

Cum

5,039.00

5%

Concrete M25 (Including Pumping)

Cum

4,839.00

5%

10

Concrete M20 (Including Pumping)

Cum

4,550.00

5%

11

Concrete M15 (Including Pumping)

Cum

4,250.00

5%

12

Concrete M10 (Including Pumping)

Cum

3,800.00

5%

13

BRICKS (230x115x75)

no

5.25

5%

14

BRICKS (230x150x75)

no

10.50

5%

15

Solid blocks- 390x190x190mm

NOS

55.00

3%

16

Solid blocks- 390x190x150mm

NOS

36.00

3%

17

Solid blocks- 390x190x90mm

NOS

26.00

3%

18

Siporex blocks - 100x240x650mm

NOS

59.00

3%

19

Vitrified Tiles (600X600)

Sqm

538.00

5%

20

Vitrified Tiles (300 x 300)

Sqm

323.00

5%

21

Vitrified Tikes (800 x 800 )

Sqm

974.00

5%

22

Anti skid Ceramic Tiles (600x150)

Sqm

753.00

5%

23

Black Granite 20mm thick

Sqm

1,400.00

5%

24

Indian Marble18mm thick

Sqm

484.00

5%

25

Baroda green marble

Sqm

630.00

5%

26

Kota Stone

Sqm

410.00

5%

27

Composite Arificial Marble 18mmthick

sqm

2,400.00

5%

28

Glaas Mosaic Tiles

Sqm

8,614.00

5%

29

Vitrified Tiles (1000X1000)

Sqm

970.00

5%

30

Ceramic Tiles (300X300)

Sqm

323.00

5%

31

Ceramic Tiles (300X600)

Sqm

484.00

5%

Addendum1BasicRateAnnexure

Page1of3

SealSignofBidder

EMPLOYER - ASHVI DEVELOPERS PRIVATE LIMITED


PROJECT - Strengthening Construction of Residential Tower at Goregaon (West) Mumbai

BASIC RATE OF MATERIAL


Sr.No.

Description

Unit

Basic Rate

Wastage in
%

32

Glazed Tiles (200x300)

Sqm

284

5%

33

Texture Paint

Sqm

645

3%

34

Teak wood frame size 6"x21/2"

Cum

80,463

35

Teak wood frame size4""x21/2"

Cum

80,463

36

Red meranti wood size 4"x21/2"

Cum

35,761

37

Flush shutter 35mmthickwith commerical Veener finish with (ISI)

sqm

2,906

38

Flush shutter 45mmthick withcommerical Veener finish (2HR FIRE RATING)

sqm

4,540

39

Flush shutter 45mmthick with (1HR FIRE RATING)

sqm

3,850

40

Alumininum sliding window including fixing

sqm

3,770

41

Aluminium Window Toilet including fixing

sqm

2,690

42

S.S railing with glass including fixing

Rft

1,200

43

Gypsum ceiling board 12mmthick

SFT

17

44

Mortise handle with button dead lock

No

1,200

45

Mortise lock

No

1,300

46

Night Latch

No

968

47

Open Door closer

No

940

48

BRASS Butt Hinges 4"x1 1/2" Heavy Duty

No

296

49

Handle S.S 12"LONG

pair

750

50

S.S Railway type Hinge SIZE 125MM

No

125

51

S.S Railway type Hinge SIZE 100MM

No

88

52

HT Strands

KG

60

53

35mm thick Flush shutter with laminate finish

Sqm

2,906

54

Flush shutter 35mmthick with commerical Veener finish (2HR FIRE


RATING)

sqm

3,500

55

Aldrop Lock

No

300

Not
Applicable
Not
Applicable
Not
Applicable
Not
Applicable
Not
Applicable
Not
Applicable
Not
Applicable
Not
Applicable
Not
Applicable
2%
Not
Applicable
Not
Applicable
Not
Applicable
Not
Applicable
Not
Applicable
Not
Applicable
Not
Applicable
Not
Applicable
Not
Applicable
Not
Applicable
Not
Applicable
Not
Applicable

Employer will supply RMC, Steel and major finishing items along with MEP materials on a star rate basis as mentioned
above. Employer shall give all VAT bill to Contractor and it shall be consignee name in form of bid. Any increase or
decrease on the star rate will be in Employers account adjusted from RA Bill. Variation in the wastage is agreed by
Ariisto and bider. Employer will be liable to supply the fixed quantity according to the project and if any additional
quantity will be required to be procured by bidder for any reasons attributable to bidder and or on account of additional
wastage or for any other reasons it will be at the sole cost of bidder.
Above mentioned basic price of materials are the landed cost of materials at Project site including all taxes, duties,
cesses including VAT, Central & Local taxes, Loading, Transportation etc. complete. The unloading shall be factored in
the overall item rate.

Contractor should submit the Reconcilation Statement along with Running Account Bill (RA Bill). Contractor should take
all necessary care to see that wastage should not be exceeded % mentioned . If wastage exceeds by below mentioned
wastage %, cost of the extra wastage shall be recovered at 10% higher than supply rate and shall be deducted from
Running Bill. For Rolling Margin, Testing shall be done from every lot of steel of all diameter received at site and
wastage shall be calculated based on rolling margin
Bidder will submit list of materials with specifications as to quality and quantity as required on site at least one month in
advance to Employer. Such specifications shall be submitted along with the Price list and the vendor list. Employer
shall at its sole discretion either supply below or at par with the purchase rate or give consent to bidder for the

Addendum1BasicRateAnnexure

Page2of3

SealSignofBidder

EMPLOYER - ASHVI DEVELOPERS PRIVATE LIMITED


PROJECT - Strengthening Construction of Residential Tower at Goregaon (West) Mumbai

Formula for Basic price variation reimbursement is,


= [(Actual procurement price - Basic Price)] + Appropriate Tax, if applicable.

The Contractor, before procuring any item with base rate shall provide all documentary justification (three quotes) for
the base rate of materials. Final decision on supplier will be by Employer.

Addendum1BasicRateAnnexure

Page3of3

SealSignofBidder

Project: Ariisto Residential Tower


Loction: Goregaon, Mumbai
Client: Ashvi Developers Private Limited
TECHNICAL CLARIFICATION- CIVIL + FINISHES PACKAGE
Sr
No

Description

Raft

For introduction of additional columns as


per the drawings provided
PT Slab

Punchured Slab

New Slab & PT Beam Connection

Grade of Concrete

Addendum 1 - Pre-bid Queries Clarification

Reference
Scanned copy of ref drgs are attached

Scanned copy of ref drgs are attached

Queries

Clarification

Request you to provide the horizontal connection details


Not Required
between existing & new raft.

We understand from drawings that existing slab & beams are As per information PT bonding system is used and also we
are breaking only concrete not any reinforcement and tendon
PT. Kindly confirm the scope of destressing.
so no need of destressing.
After introducing additional columns, whether the punchered These additional columns are not crossing any tendon and
slab will be PT or not. Kindly confirm. If PT then kindly confirm also we are breaking only concrete not any reinforcement and
the scope of Re-stressing.
tendon so Re-stressing is not required
As per drawings, the beams are PT beams, so kindly provide New slab beams are coming at the back side of lift only so
the details of connection of new slab with existing PT beams. whereas old and new slab and beam connection is required
we will do epoxy grouting or equivalent.
From drawings we understand that the existing slab grade is M60 grade is used for column, for additional column we are
M40, whereas the grade of new concrete works is mentioned breaking concrete at junction. For new column and slab/beam
as M60 as per BOQ. Kindly provide the details of bonding in and raft provide Nitobond or equivalent for old and new
between
concrete bonding

Seal Sign of Bidder