TESTING AND COMMISSIONING SHEET

ELECTRIC PASSENGER LIFT


1. DESCRIPTION

Building Name
Address
Machine Details
Elevator Type
Manufacturer

Traction Machine

7 - Sense
Gregory Road, Colombo 07.
L-5
Grearless Traction Machine
Mitsubishi Electric

Model No
Serial No
Control
Operation
Rated Load
Rated Speed
Door Type
Door Opening Size
Motor (kW)
Installation Drawing No.
Power Supply
Floors Served
Buffer Type
Car
Counter Weight

PM011SS
L1911141577
VVVF
825Kg
105 m/min
Center Opening
900mm (W) x 2100mm (H)
8.9 kW
400V / 3ph / 50Hz
B2, B1, G, 1, 2, 3, 4, 5, R
Spring, Hydraulic
Spring, Hydraulic

2. STATIC EXAMINATION

Does the Mechanical


Safety Gear Operate properly?

Yes

Does the brake sustain the car


With rated load plus 25%?

Yes

Does the phase failure device


Operate correctly?

Yes

3. LOAD TEST
Up

Load
%

Weight
(kg)

IS (A)

IR (A)

0
50
100

840

15.9

16.1

Speed
(m/min)

Down
Voltage
(V)

IS (A)

IR (A)

416

0.5

0.1

Speed
(m/min)

Voltage
(V)

418
Page 1 of 5

IS - Starting Current

IR - Running Current

4. DOOR TESTS

Door Opening Time

1.83 (s)

Door Closing Time

2.77 (s)

5. TIME DELAYS

Car Hold Delay

4.68 (s)

6. CONTROL CIRCUIT VOLTAGES

Full Load

24 V d.c

7. EARTHING

Is all the metal work enclosing


Conductors bonded to earth

Yes

Is the car connected to earth

Yes

8. GOVERNOR TRIPPING SPEED

Electrical

Up 2.18 m/s

Mechanical

2.27 m/s

Down 2.17 m/s

9. LIMIT SWITCHES

Does the terminal stopping devices


Operate satisfactorily?
Yes
Does the final limit switch operate
Satisfactorily?
Yes

10. CLEARANCES & RUNBY

Will the car clear all obstructions


When run on slow speed?

Yes
Page 2 of 5

Car top clearance

1200mm

Counterweight top clearance

1000mm

Bottom run by of car

190mm

Bottom run by of counterweight

90mm

11. CAR TOP CONTROL STATION

Speed up

20 m/min

Speed down

20 m/min

Is the operation of the car top


Control station correct?

Yes

12. FLOOR LEVELLING TESTS

With rated load in the car, the


maximum inaccuracy for any floor
in both directions
5mm

13. GENERAL

Is the load indication plate


fitted in the car

Yes

Has the machine room adequate


lighting for maintenance purposes ? No ; No any light available in lift shaft

14. ADDITIONAL FEATURES CHECK

Car Door Safety Edge

In Order

Ventilation Fan

In Order

Arrival Gong

In Order

Operation & indication of call


Page 3 of 5

buttons & indication panels

In Order

Emergency car light

In Order

Operation of Emergency
Rescue Device.

In Order

Operation of Interphone

No

Firemans Switch Operation

In Order

15. DECLARATION
We certify that on 10/09/2015 the equipment was thoroughly examined and found to be generally
complying with requirements except the snagging list (Annexure 01).

For Consultant:

Signature : ..............................................................
Name : .....................................................................
Date : .......................................................................

For Lift Contractor

Signature : ..............................................................
Name : .....................................................................
Date : .......................................................................

Page 4 of 5

Annexure - 01

SNAGGING LIST

1.Emergency/Maintenance lamps shall be fitted at each level of the lift shaft and lamps at
every other floor shall be battery backed.
2. A smoke detector shall be fitted on the soffit of the lift shaft and a remote indicator shall be
fitted at the entrance of the roof floor.
3.Link between the Fire alarm panel shall be established
4.All fixtures where protective coating damaged, shall be recoated with protective coating.
5.Interphone connection shall be established.

Page 5 of 5