Professional Documents
Culture Documents
6600026167
002
JOB No. 11049D
41108
Site QC Manager
Construction manager
Result of Audits
Customer Satisfaction
Process Performance and Product Conformity
Preventive and Corrective Reports
Non Conformance Reports
QC Inspection & Surveillance Reports
QC Personnel Approval
8. Status of RFIs
9. Method Statements
10. Waivers
Page 1 of 6
Page 2 of 6
CUSTOMER FEEDBACK
NON-CONFORMANCE REPORTS
Review of the NCR reporting and register confirmed that in general NCRs
raised were relevant and justified, and their disposition was in timely manner.
(some structural item NCRs still awaiting for closure by sub-contractor Hidada
Ltd. While observing nature of NCRs, there are some items with recurring
nature which should be controlled viz. concrete curing, backfilling of trenches without required Field Density
Tests, mis-fabrication of structural items, hydro test leaking in RTR U/G piping
because of piping materials and workmanship of joint bonding, delivery of
civil materials to site without lab test reports especially marl, sub-base, base
coarse, sand and CMU.
(Attachment 3.0)
QC INSPECTION REPORTS
QC Inspection Reports forms part of surveillance, which were reviewed and
found that all inspection reports issued by MMG were recorded and most of
the findings were closed out in timely manner.
Attachment 4.0
QC PERSONNEL
QC Personnel approval verified and their tentative demobilization dates are
maintained.
Attachment 5.0
STATUS OF RFIs
Request For Inspection (RFI) log was reviewed by the QC Manager and
found that RFI status updated and maintained with their latest status (some
Civil RFIs are pending for test result from third party laboratory)
Attachment 6.0
Page 4 of 6
METHOD STATEMENT
Availability and approval of method statement for various construction
activities have been verified with Engineering control system and noticed that
some required method statements are still in-process. Engineering should
follow-up for approval of method statements. List of method statements under
various stages are attached for reference.
Attachment 7.0
WAIVERS
Management has verified with Engineering department for waivers raised for
specific activities in the project, it was noted that no waiver has been
requested till date.
TRAINING
Management has reviewed the training program rendered to skilled workers
especially RTR joint bonders, concrete group, structural steel erection group,
piping installation group and welders. Training was conducted on different
phases and documented.
Attachment 8.0
RESOURCE REQUIREMENT
Shortage of QC personnel raise concern. There is immediate requirement of
4 Civil QC Inspectors, 3 Piping QC Inspectors, 1 Valve Testing Inspector, 1
NDT Coordinator and 2 Computer Operators for welding data entry in PJCS.
There was concern over pending civil test reports from third party laboratory.
Site management is coordinating for speedy release of civil test reports to
clear RFI reports. Shortage of 2 civil third party lab and site technician.
Page 5 of 6
Prepared by:
Noted by:
REYNALDO A. DIMATATAC
Projects Area Director
Concurred by:
DEBASHISH TAPADAR
Quality Audit Manager
Page 6 of 6