Professional Documents
Culture Documents
1
CDM Executive Board
page 1
B.
C.
D.
Environmental impacts
E.
Stakeholders comments
Annexes
The main purpose of the project activity is to establish a greenfield power plant using Empty Fruit
Bunches (EFB), an abundantly available palm oil mill biomass residue, as fuel and supply the net
electricity after inhouse consumption to the state electric grid for sale displacing fossil fuel dominated
grid electricity .
(a) Scenario existing prior to the start of the project activity
The project activity is a Greenfield power plant from renewable biomass.
The palm oil mills process Fresh Fruit Bunch (FFB) from palm plantations to produce Crude Palm Oil
(CPO) as the main product. In the process, a number of solid and liquid residues are produced as follows:
Solid biomass residues :
Liquid waste
:
Mesocarp fibre, Palm Kernel Shells and Empty Fruit Bunches (EFB).
Waste water generally known as Palm Oil Mill Effluent (POME).
S. D. Resources Sdn. Bhd. (Project Proponent) proposes to establish a greenfield 25 MW power plant
in Lahad Datu utilising EFB as fuel . The project proponent would also be establishing a new 120 ton /
hour palm oil mill in the same premises. Therefore most of the EFB required for the project activity
would be sourced from its own mill and the balance would be sourced from other palm oil mills. The
proposed palm oil mill is also a Greenfield project to be implemented in two phases.
Project Scenario
The project activity is installation of a new 25 MW power plant implemented in two phases as shown in
the table A-1:
Table A-1- Details of phases of the project activity
Phases
I phase
II phase
01 July, 2010
EFB is the biomass residue from the palm oil mill which is generally disposed in palm plantations and
allowed to decay in aerobic conditions. Other biomass residues of the palm oil mill such as mesocarp
fibre and palm kernel shells are good sources of energy and are generally used for energy generation
purposes.
EFB is produced at a rate 21- 23 % of FFB processed in the mill and disposed in the palm plantations and
subjected to aerobic decay. Therefore, EFB is abundantly available in Malaysia. But EFB had been a
difficult biomass to handle due to its high moisture content and bulky nature. The project proponent
proposes to utilise only the difficult EFB as fuel source. EFB would be combusted in a furnace and the
heat would be used in a boiler to produce high pressure steam. The steam is passed on to the turbine to
produce electricity. The net electricity after the parasitic load of the power plant would be exported to the
Sabah grid of Sabah Electricity Supply Berhad (SESB), the state electric utility in Sabah state of
Malaysia.
Pre project scenario: This is a Greenfield biomass based power project.
(b) Baseline scenario
The baseline scenario is that the power generated by the project activity would in the absence of the
project activity be generated by the power plants in the grid and biomass residues would in the absence of
the project activity be left to decay.
Reduction of greenhouse gases by the project activity
The project activity would supply the electricity to the East Coast grid of Sabah Electricity Supply
Berhad (SESB). The installed power capacity of Sabah grid as of 31 December 2006 is given in Table A2
Table A-2- Installed power capacity mix of Sabah grid
Available capacity 1
% share
226 MW
34.82 %
372 MW
57.32 %
51 MW
7.86 %
649 MW
100.00 %
Power source
Total
From the above table, it may be noticed that about 92.14% of the available capacity of the Sabah grid is
thermal generation with fossil fuel based sources and only 7.86 % of available capacity is from
hydropower. That is, the Sabah grid is powered predominantly by fossil fuels based generation. Hence,
the electricity supplied by the project activity would displace equivalent amount of electricity supplied
predominantly by fossil fuel based sources and associated CO2 emissions.
View of project participants on the contribution of project activity to sustainable development
Environmental sustainability
The project activity generates electricity from solid biomass wastes a renewable source of energy. The
project activity will lead to reduced disposal of waste products from the palm oil mills and increase the
utilisation of the energy content in wastes. The energy generation from a renewable source of energy
contributes for environmental sustainability.
Source : National Energy Balance 2006, Ministry of Energy, Water and Communications, Malaysia
Additionally, the project activity would prevent the methane emissions due to aerobic decay of EFB in
the palm plantations and produces electricity without much greenhouse gas (GHG) emissions.
Thus, the following environmental benefits are derived from the project activity:
Produces electricity from a renewable energy source.
Prevents methane emissions due to decay of EFB in the palm plantations.
Produces electricity without or very less GHG emissions.
Has very little negative impact on the environment.
The project activity would install necessary pollution control equipment to minimise the emissions of
particulates and other pollutants.
Social sustainability
The project activity would contribute for the following social benefits:
Contributes to meet Malaysia s Ninth Plan target of 350 MW generation from renewable energy
New employment oppurtunities for the local population improving the social living standards of
the local community
Improve the technical skills of staff in the operations and maintenance of an efficient electricity
generation plant
New jobs for skilled manpower during operation of the project activity
Increase in local business like transportation, maintenance, parts supply, food and other services
which would improve the social living standards of the local community
Economical sustainability
Decreasing the countrys dependence on imported and fast depleting fossil fuels for generation of
electricity
Improvement in local economic activity
During operation of the project, direct and indirect employment opportunities would be available
for the local community leading to economical benefits.
Savings in precious foreign exchange due to reduction in import of fuels.
Technological sustainability
The project activity would establish a 69 bar pressure boiler probably for the first time in palm oil
biomass power plant in Malaysia and therefore would employ a technically better system than
that of generally used in Malaysia.
The project activity would contribute for the countrys policy to promote the use of renewable
energy.
All the above would contribute for the sustainable development.
A.3.
Project participants:
Malaysia (Host)
No
United Kingdom
No
(*) In accordance with the CDM modalities and procedures, at the time of making the CDM-PDD
public at the stage of validation, a Party involved may or may not have provided its approval. At the
time of requesting registration, the approval by the Party (ies) involved is required.
A.4.
Host Party(ies):
A.4.1.2.
Malaysia
Region/State/Province etc.:
Sabah state
A.4.1.3.
City/Town/Community etc:
Lahad Datu
A.4.1.4.
Detail of physical location, including information allowing the
unique identification of this project activity (maximum one page):
The project activity would be located in the Kwantas complex in Lahad Datu town in Tawau
division in Sabah state in East Malaysia on the Borneo island. Lahad Datu is in eastern part of Sabah
state. Lahad Datu has an airport for domestic flights with connections to state capital Kota Kinabalu and
other parts of the country. The physical co ordinates of the location of the project activity are in 5 01
21 N latitude and 118 2142 E longitude
The location of the project activity is given in the following figures.
Sabah
state
Lahad Datu
Location of
the project
activity
(a)
Specification of Boiler
Capacity
Working pressure
Type
Temperature
Efficiency
Type of grate
Quantity of boiler
Make
:
:
:
:
:
:
:
:
75 ton / hour
69 bar
Water tube
485 C super heated steam
86%
Inclined vibrating grate combined with moving grate
2
Jinan, China
:
:
Working pressure
Voltage of generation
Quantity
:
:
:
25 MW
Fully Condensing, horizontal, impulse,
Multistage, axial flow and geared
69 bar
11 kV
1
Description
Installed capacity
Plant utilisation factor
Gross generation
Auxiliary consumption and
electricity supplied to the mill
Net electricity supplied to the grid
II phase
75%
85%
25 MW
A.4.4. Estimated amount of emission reductions over the chosen crediting period:
Table A- 4: The total GHG emission reductions in t CO2e over the crediting period
Years
Year 1
83,780
Year 2
128,297
Year 3
128,297
Year 4
128,297
Year 5
128,297
Year 6
128,297
Year 7
128,297
Year 8
128,297
Year 9
128,297
Year 10
128,297
1,238,454
10
123,845
Title and reference of the approved baseline methodology applied to the project activity:
Justification of the choice of the methodology and why it is applicable to the project activity
This consolidated methodology covers a number of different project types for power generation with
biomass residues.
The consolidated methodology ACM 0006 (version 06.2) has a number of applicability criteria discussed
in the table B.1 below.
Applicability criterion
biomass residues for fuel combustion, i.e. projects
that process the biomass residues prior to
combustion (e.g. esterification of waste oils)
In addition to the above, approved consolidated methodology ACM0006 - version 06.2 also specifies that
the project activity should comply with baseline scenario in Table 2 of the methodology.
As per table 2 of the methodology, the project activity fully complies with the scenario 2 as given below
in Table B -2:
Table B-2 Justification of scenario
Scenario 2 of Table 2
The project activity involves the installation of a
new biomass residue fired power plant at a site
where no power was generated prior to the
implementation of the project activity. The power
generated by the project plant is fed into the grid or
would in the absence of the project activity be
purchased form the grid. The biomass residues in
the absence of the project activity be dumped or
left to decay or burnt in an uncontrolled manner
without utilizing it for energy purposes. In case of
cogeneration plants, the heat would in the absence
of the project activity be generated in boilers fired
with fossil fuels, or by other means not involving
the biomass residues. This may apply, for example,
where prior to the project implementation heat has
been generated in boilers using fossil fuels.
Since all the applicability conditions of the methodology and the baseline scenario are fully met, this
methodology is applicable for the project activity.
B.3.
Description of how the sources and gases included in the project boundary
Table B.3: Sources and gases included in the project boundary
Baseline
Source
Grid electricity
generation
Heat generation
Gas
CO2
Included
CH4
Excluded
Justification / Explanation
Main emission source and calculated as per version 06.2
of ACM 0006.
For the purpose of simplification this is conservative.
N2O
Excluded
CO2
Excluded
CH4
Excluded
Not applicable
N2O
Excluded
Not applicable
Source
Uncontrolled
burning or decay
of biomass
residues
Gas
CO2
Excluded
CH4
Included
N2O
Excluded
CO2
Included
CH4
Excluded
N2O
Excluded
CO2
Included
CH4
Excluded
N2O
Excluded
CO2
Excluded
CH4
Included
N2O
Excluded
CO2
CH4
N2O
Waste water from CO2
the treatment of
biomass residues
CH4
Excluded
Project emissions
Off site
transportation of
biomass
Combustion of
biomass residues
for renewable
electricity and/or
heat generation
Storage of
biomass
N2O
Excluded
Excluded
Excluded
Justification / Explanation
Biomass is considered to be carbon neutral.
EFB are
Project boundary
The project boundary of the project activity is shown in Fig B-1.
Fig B - 1 Project boundary
Project Boundary
Fuel preparation
system
75 ton / hr Boilers
Steam
25 MW Turbine
To SESB Grid
To Consumers
B.4.
Description of how the baseline scenario is identified and description of the identified
baseline scenario:
The identification of the baseline scenario is in accordance to ACM 0006 (version 06.2) with
demonstration of additionality as per version 02.2 of the Combined tool to identify the baseline scenario
demonstrate additionality hereinafter referred to as Combined Additionality Tool.
The Combined Additionality Tool prescribes four steps to establish the baseline scenario and demonstrate
additionality:
STEP 1.
STEP 2.
STEP 3.
STEP 4.
The first and second steps would be used to identify the baseline scenario of the project activity.
STEP 1.
Step 1a.
Pursuant to the Combined Additionality Tool, project proponent shall identify all alternatives scenarios
that are available to the project proponent and that provide outputs or services with comparable quality,
properties and application areas as the proposed CDM project activity.
In applying Step 1 of the Combined Additionality Tool, ACM0006 (version 06.2) requires realistic and
credible alternatives should be separately determined regarding:
How power would be generated in the absence of the CDM project activity;
What would happen to the biomass residues in the absence of the project activity; and
In case of cogeneration projects: how the heat would be generated in the absence of the project
activity.
Since this is not a cogeneration project, baseline scenario for heat is not relevant and hence not identified
for heat.
The plausible baseline scenarios for power generation identified in ACM0006 (version 06.2) are set out
in Table B4 with comments and conclusion for each plausible baseline scenario discussed in the
corresponding right columns.
Table B.4: Realistic and credible alternatives for power generation:
Plausible
baseline
scenarios for
power
generation
Description
Comments
Realistic
and
credible
alternative?
(Yes/No)
Plausible
baseline
scenarios for
power
generation
P1
Description
Comments
P3
No
P4
Yes
P5
No.
P6
No.
P2
Realistic
and
credible
alternative?
(Yes/No)
Yes.
The proposed project activity not This could be an alternative but
undertaken as a CDM project
would not be a baseline scenario
activity.
as this option is economically
attractive as seen in subsequent
section.
No.
The continuation of power There is no existing power plant
generation in an existing biomass in the project site. Therefore,
residue fired power plant at the this is not a realistic alternative
project site, in the same
configuration, without retrofitting
and fired with the same type of
biomass residues as (co-)fired in
the project activity.
Plausible
baseline
scenarios for
power
generation
P7
P8
P9
Description
Comments
Realistic
and
credible
alternative?
(Yes/No)
No
No
No
Pursuant to Table B4, the realistic and credible alternatives identified for power generation are: P1 and
P4
B2
B3
Description
Comments
B4
B5
Realistic and
credible
alternative?
(Yes/No)
Yes
No.
No
No
No
Plausible
baseline
scenarios for
EFB
Description
B6
B7
B8
Comments
Realistic and
credible
alternative?
(Yes/No)
No
No
No
Danish Technical University, 2006: Ethanol potential for Empty Fruit Bunches pre-treated by Wet-Explosion
downloaded from www.eib.ptm.org.my
Plausible
baseline
scenarios for
EFB
Description
Comments
Realistic and
credible
alternative?
(Yes/No)
organic compost in
Malaysia
- Farmers mindset to use
organic compost as against
inorganic fertiliser
- Long distances of transport
of compost to the mills due
to remote location of the
mills
EFB to paper
There is no project operating
which
utilizes
EFB
to
manufacture paper although
researches are being undertaken
for such conversion.
This clearly shows that the
utilization of EFB to produce
compost or paper would not be
part of baseline scenario.
Pursuant to Table B.5A, the realistic and credible alternative identified for use of EFB is: B1
Sub-step 1b. Consistency with mandatory applicable laws and regulations
Baseline scenario B3 in Table B.5 refers to uncontrolled burning of biomass residues. This baseline
scenario is not in compliance with existing Malaysia legislation. Open burning of biomass residues is
prohibited according to The Malaysian Legislation Environment Quality Act 1974 (amended 2000).
Thus, these baseline scenarios have thus been disregarded as realistic and credible alternatives.
Following Step 1 of the Combined Additionality Tool i.e. Identification of alternative scenarios, the
following realistic and credible alternatives are identified:
For power
P1 and P4.
B1
Based on the above discussions, the most credible combinations of baseline scenarios are as follows:-
1.
Generation of power in the grid (P4) and biomass residues left to decay (B1) which is
consistent with Scenario 2 of Table 2: Combinations of project types and baseline scenarios
applicable to this methodology prescribed in ACM0006 (version 06.2) (Alternative 1);
2.
The proposed project activity not undertaken as a CDM project activity (P1 and B1)
(Alternative 2)
STEP 2.
Barrier analysis
This step serves to identify barriers and to assess which alternatives are prevented by barriers discussed in
Sub-step 2a below.
As prescribed in ACM0006 (version 06.2), the barrier analysis consists of two sub-steps namely:
Sub-step 2b:
Identify barriers that would prevent the implementation of alternative scenarios identified
in Step 1 above.
Eliminate alternative scenarios which are prevented by the identified barriers
Sub-step 2a.
Sub-step 2a:
Sub-step 2a requires the establishment of a complete list of realistic and credible barriers that may
prevent alternative scenarios to occur.
The complete list of realistic and credible barriers that may prevent implementation of alternative
scenarios are analysed as follows:
Investment barriers
Technology barriers
Lack of prevailing practice
Market barriers
Sub-step 2b.
This step identifies alternative scenarios which are prevented by at least one of the barriers listed in Substep 2a above and eliminate those alternative scenarios from further consideration.
Alternatives to power generation:
Out of the nine (9) alternatives to power generation analysed in Sub-step 1a and Sub-step 1 b above, only
alternative P1 and P4 can be considered as realistic and credible baseline scenarios and are subjected to
barrier analysis prescribed in Step 2.
Table B.6: Barrier analysis for alternatives to power generation
Barrier
P1:
Barrier
P1:
Investment
Erik Dugstad et al 2007: Options for implementation of the RE target in 9th Malaysia Plan. Page 3 Summary
Downloaded from www.eib.ptm.org.my
Barrier
P1:
No technology risk
Barrier
P1:
The grid connected electricity generation Power from the grid is the prevailing
projects is not a common practice in the practice
region.
There are about 112 palm oil mills and 9
palm oil refineries in Sabah state. Out of
these, only following 7 projects have
implemented / are implementing grid
connected palm oil biomass based
electricity generation projects and all
these projects are either registered as
CDM projects or under CDM validation:
i.
ii.
iii.
iv.
v.
vi.
Speech by The Minister for Energy Water and Communication Y.B. Dato' Sri Dr. Lim Keng Yaik at the National
Renewable Energy Forum 21/09/2006. Downloaded from www.ktak.gov.my
Barrier
P1:
Barrier
P1:
Market
It may be observed in Table B.5 that there are very significant barriers for the proposed project activity
to be undertaken not as a CDM project activity (P1) as compared to generation of power in the grid (P4).
It is well known that the generation of power in the grid has low technology, investment and market risks.
For the biomass type (EFB,) identified in Sub-step 1a and Sub-step 1b, only one alternative was
identified for each biomass type as discussed in Sub-step 1b. Thus, no barrier analysis was conducted in
relation to this alternative.
Outcome of Step 2b
From Sub-step 2a and Sub-step 2b, it is observed that Alternative 2 (P1 and B1) identified in Step 1
experiences significant barriers.
Following Sub-step 2b, alternatives scenario to the project activity that is not prevented by any barrier is
(Alternative 1):
P4 :
The generation of power in the grid and B1:
to decay under mainly aerobic conditions.
Alternative 1 is not prevented by any barrier and Alternative 2 faces significant barriers.
As per Additionality tool, if there is only one alternative scenario that s not prevented by any barrier
and this alternative is not the proposed project activity undertaken without being registered as CDM
project activity, then this alternative scenario is identified as the baseline scenario.
Thus, Alternative 1- P4 and B1 is the baseline scenario for the project activity.
Eco-Ideal Consulting & Mensilin Holdings, 2005: Barrier Analysis for the Supply Chain of Palm Oil Processing
Biomass (Empty Fruit Bunch) as Renewable Fuel. Page 43 Downloaded from www.eib.ptm.org.my
Thus, explanations using qualitative and quantitative arguments on how the registration of the CDM
project activity will alleviate the barriers that prevent the proposed project activity from occurring in the
absence of the CDM are set out below as per Combined Additionality Tool.
Qualitative arguments
As set out briefly in Step 2, the project activity experiences investment and technological barriers and
risks. The project activity would also face considerable financial barriers as explained in subsequent
section. The registration of the project activity as a CDM project activity allows the project proponent to
accept the inherent risks of the project activity arising from investment and technology risks. The income
from sale of CERs may also assist in overcoming the barriers posed by employment of new technology to
ensure the project activity is reasonably viable from commercial perspective.
In addition, it can be justified that CDM will help to overcome the major barriers based on the financial
contribution to the project activity. Such additional revenue also enables the project proponent to accept
risks associated with the inherent technological and investment risks of the project activity.
Quantitative arguments
From the quantitative viewpoint, the financial indicator set out below has been identified as most suitable
for the project type and decision making context:
Project internal rate of return (Project IRR)
In demonstrating how registration of the project activity as a CDM project activity will alleviate the
barriers that prevent the proposed project activity from occurring in the absence of the CDM, the Project
IRR of the project activity is calculated for further discussion.
The basic information for calculation of Project IRR is given below in Table B.7
Table B.7: Project IRR of the project activity without and with CDM registration
Parameters
Value
Data Source
25
Project proponent
100
Project proponent
8.5%
Project proponent
159,018
0.215
12
Budgeted
21
3.66 %
IRR Calculations
11.07%
IRR Calculations
The Project IRR was calculated as per latest Guidance on the Assessment of Investment Analysis version 02.1 of CDM EB 41. The internal rate of return of the project activity was calculated for 21
years ( 1 year construction period + 20 years operation period) which is also the term of Power Purchase
Agreement . The Project IRR is calculated to be 3.66 % for 21 years. The IRR for the project activity is 1.36 % for 10 years. The spreadsheet of IRR calculations are attached as Appendix- 1.
It may be seen that the returns from the project activity from the sale of electricity alone are very low.
This IRR is lower than the borrowing rate for the project which is 8.5 %. The latest Guidance on the
Assessment of Investment analysis suggests that commercial borrowing rate to be one of the benchmarks
for Project IRRs 7 . This is a very conservative benchmark as the calculations also includes equity
component where the rate of returns expected are generally higher than the lending rates. The project
activity would not be able to even service the debt component of the project with sale of electricity to the
grid. This has been one of the main reasons for many projects not coming up in Malaysia inspite of
availability of huge quantity of biomass in the country. In spite of Government initiative to promote
renewable energy, there has been a reluctance on the part of the electric utility to offer better prices to
facilitate establishment of such projects on a commercial scale as the purchase price offered by the
electric utility does not make the projects commercially viable.
The project activity is clearly not attractive economically and has a clear investment barrier.
1.1 Sensitivity analysis:
A sensitivity analysis with variations as suggested by Guidance on the Investment Analysis was carried
out as below:
1. Variations in Investment cost
2. Variations revenue from the project
As per guidance, sensitivity analysis for investment costs has to be carried out for the components that
constitute more than 20 % of the investment costs. In this case, the cost of boiler and turbine would
constitute for more than 20 % of the investment cost. These two items contribute for about 50 % of the
project cost. Therefore, the variation is considered for 50 % of the project cost with 10 % variation.
The project IRR with +10 and -10 % variations for variables listed above are presented in the Table B-8.
Table B-8 Project IRR without CDM revenues for various variations
S. No.
Parameters
Variation
1.
Variation
in
Investment costs
+10%
2.77 %
-10%
4.63 %
Variation in
revenues for the
project cost
+ 10%
10.33%
-10%
Negative
The results of the sensitivity analysis conducted confirm that the financial internal rate of return of the
project activity without CDM revenues is much lower than the benchmark of commercial borrowing rate.
It must be mentioned here that the commercial borrowing rate is a very conservative benchmark as the
project IRR calculations also has equity component and it is very unlikely that investors would invest in
the project with expectations to get returns as only that of commercial borrowing rates. In these
circumstances, an IRR of 12 % 8 is considered to be more appropriate indicator for Malaysia. It is hereby
requested that the IRR of the project activity to be compared with 12 % IRR as benchmark.
As explained above, the CDM would improve the IRR to the level above the commercial lending rate
making the project viable. Thus CDM would alleviate the barriers that exist for the proposed project
activity and that would prevent the proposed project activity from occurring. As per Combined
Additionality tool, next step is to proceed to Step 4 Common practice analysis.
Step 4:
Para 1, Page 21 of 28 of the report The IPP Investment Experience in Malaysia by Jeff Rector
Figure B.2: Distribution of fuels used in the total industrial sector in Malaysia, 2003.
(Source: National Energy Balance, PTM)
Figure B.2 depicts that the energy use in the industry in Malaysia is dominated by the use of fossil fuels.
Very few companies have been using biomass residue as fuel. Most of the biomass fuel used is PKS i.e.
cement industry whereas the use of EFB has been very limited (and mainly confined to CDM projects).
The statistics clearly set out that the use of biomass in industrial application is very limited in Malaysia
i.e. outside palm oil mills.
4.2. Similar project activities
There are about 112 palm oil mills and 9 palm oil refineries in Sabah state. Out of these, only following 7
projects have implemented / are implementing grid connected palm oil biomass based electricity
generation projects and all these projects are either registered as CDM projects or under CDM validation:
vii.
viii.
ix.
x.
xi.
xii.
Lahad Datu Edible Oil biomass steam and power plant -CDM Regn. No. 395
Sandakan Edible Oil biomass steam and power plant - CDM Regn. No. 402
Sahabat Empty Fruit Bunch Biomass -CDM Regn. No 288);
Kina Biopower plant - CDM Regn. No. 0385
Seguntor Bio energy plant CDM Regn. No. 0386.
Kunak Bio Energy Project (in process for registration as a CDM project activity)
It may be noted that just 4.59 % of the industries have implemented / are implementing grid connected
biomass based power projects and all these projects are implemented as CDM projects.
Therefore, it is clear the biomass based grid connected electricity generation plant is not common
business practice in Malaysia.
4.3 High pressure boiler
The project activity would employ boilers operating at 69 bar pressure which are very rarely used in
Malaysia. To the best of our knowledge, such high pressure boilers are being employed for the first time
for the combustion of palm oil industry biomass especially EFB.
Therefore, the project activity is clearly not a Business as Usual scenario.
With the above discussion, it may be concluded that the project activity is clearly additional.
B.5.
Description of how the anthropogenic emissions of GHG by sources are reduced below
those that would have occurred in the absence of the registered CDM project activity (assessment
and demonstration of additionality):
The basic demonstration of additionality is handled in the previous section by means of the Combined
Additionality Tool in section B4. This section is complementary to Section B4 and therefore, the
discussions are not repeated here as suggested by recent Guidelines for completing the PDD.
B.6.
Emission reductions:
B.6.1. Explanation of methodological choices:
The first methodological choice is to decide on the appropriate baseline methodology. In this PDD,
ACM0006 (version 06.2) was applied as the appropriate baseline methodology based on justification
discussed in Section B.2.
The second choice is the baseline scenario described in detail in Section B.4 above. The conclusion is that
this project should be evaluated under Scenario 2 of Table 2 of ACM 0006, (version 06.2).
This scenario is relevant since the project activity is a greenfield power plant where the baseline scenario
established in Section B.4 is Scenario 2 of Table 2 of ACM0006, (version 06.2) i.e.:
The means for transportation of biomass residues to the project site (e.g. vehicles);
All power plants connected physically to the electricity system that the CDM project power plant
is connected to. The spatial extent of the project electricity system, including issues related to the
calculation of the build margin (BM) and operating margin (OM), is further defined in the
Consolidated baseline methodology for grid-connected electricity generation from renewable
sources(ACM0002) 9 .
The site where the biomass residues would have been left for decay.
The emission reductions in the year, y, will be calculated using the formula (1) in the ACM0006 (version
06.2):
ERy
(1)
Where:
= Emissions reductions of the project activity during the year y in ton CO2/ year
ERy
ER electricity, y = Emission reductions due to displacement of electricity during the year y in ton CO2/year
ER heat,y
= Emission reductions due to displacement of heat during the year y in ton CO2/ year
BE biomass,y
PEy
Ly
PEy Ly
PEFF, CO2,y
PEEC,y
GWPCH4
CO2 emissions during the year y due to transport of the biomass to the project
plant in ton CO2 / year
CO2 emissions during the year y due to fossil fuels consumed in the project
activity in ton CO2 / year
CO2 emissions during the year y due to electricity consumption at the project site
that is attributable to the project activity (ton CO2/year)
Global Warming Potential for methane valid for the relevant commitment period
in ton CO2/ton CH4
=
=
PEBiomass, CH4,y
PE ww, CH4,y
CH4 emissions from the combustion of biomass during the year y in tCH4/ year.
CH4 emissions from waste water generated from the treatment of biomass
residues in year y (ton CH4/yr)
PET
BF T , k , y
TL
AVD
EF
km , CO 2 , y
(2a) of methodology
Where,
PETy
CO2 emissions during the year y due to transport of the biomass residues to the
project site (t CO2/year)
TLy
Average truck load of the trucks used (tons) during the year y
BFT,k,y
Quantity of biomass residue type k transported to the project site during the year
y (tons)
AVDy
Average round trip distance (from and to) between the biomass residue fuel
supply sites and the site of the project activity during the year y (km)
EFkm,CO2,y
Average CO2 emission factor for the trucks measured during the y (t CO2/km)
During start up of the power plant from cold condition. Cold condition is when the boiler is
switched off for long time and becomes completely cold
ii) Sometimes boiler may be switched off for short time and may still be in warm condition when
restarted again. Quantity of diesel required would be lesser than that required to start from cold
condition.
iii) Diesel would be required for boiler and pressure vessel inspection every year.
The CO2 emissions due to consumption of diesel would be calculated as per Tool to calculate project
or leakage CO2 emissions from fossil fuel combustion Version 1 as specified in the methodology.
As per tool, CO2 emissions from combustion of fossil fuels are calculated based on the quantity of fossil
fuel combusted and the CO2 emission coefficient of the fuel as follows:
PEFF,j,y
FCi.j.y
COEFi,y
Where:
PEFF,j,y
FCi,j,y
COEFi,y
i
are CO2 emissions from fossil fuel combustion in process j during the year y (tCO2 / yr);
is the quantity of fuel type i combusted in process j during the year y (mass or volume unit /
yr);
is the CO2 emission coefficient of fuel type i in year y (tCO2 / mass or volume unit);
are the fuel types combusted in process j during the year y.
Diesel is the fossil fuel consumed in the project activity for start up and during annual pressure vessel
inspection.
The CO2 emission co efficient of the diesel is calculated based on Option B in the tool as follows :
COEFi,y
NCVi,y
EFCO2,i,y
Where,
NCVi, y
is the net calorific value of the fuel type i used in the year y in GJ/ ton
EFCO2,i,y
is the CO2 emission factor of the fuel type i in year y in t CO2 / GJ.
As per the tool, the regional or national default value as per National Energy Balance could be used, if
available for these values.
As per latest National Energy Balance, 2005 issued by Ministry of Energy, Water and Communications,
Malaysia, the national default value is available for net calorific value of diesel oil which is 42.4960 GJ/
ton.
For CO2 emission factor of diesel, as per tool, latest IPCC default value at the upper limit of the
uncertainty at a 95% confidence interval as provided in Table 1.4 of Chapter 1 of Vol.2 (Energy) of the
2006 IPCC guidelines on National GHG Inventories would be adopted. The value for diesel is 0.0748
ton CO2/ GJ
Hence, COEF,i,y
Hence, PEFF,j,y
=
=
FCi.j.y
COEFi,y
FCi.j.y (ton) x
Project emissions from consumption of electricity from the grid are calculated based on the power
consumed by the project activity for the mechanical treatment of the biomass (fuel preparatory
equipment) and the emission factor of the grid, adjusted for transmission losses, using the following
formula:
PEEC,y = ECPJ,y x EFgrid,y x (1 + TDLy )
Where:
PEEC,y =
ECPJ,y =
EFgrid,y =
TDLy =
Project emissions from electricity consumption by the project activity during the year y
(ton CO2 /year);
Quantity of electricity consumed by the project activity for fuel preparation during the
year y (MWh / year);
CO2 Emission factor for the grid in year y (ton CO2/MWh)
Average technical transmission and distribution losses in the grid in year y for the voltage
level at which electricity is obtained from the grid at the project site
Quantity of biomass type k used as fuel in the project plant during the year y in a volume
or mass unit,
Net calorific value of the biomass type k in TJ/ ton of dry matter of biomass,
CH4 emission factor for the combustion of biomass in the project plant tons CH4 per TJ.
According to Table 4 :Default CH4 emission factors for combustion of biomass residues of ACM 0006
version 06.2, the default methane emission factor for other solid biomass residues is 30 kg/TJ with an
uncertainty level of 300 %. The conservativeness factor for uncertainly level above 150 % is 1.37.
Therefore, CH4 emission factor for solid biomass residues = 30 kg / TJ * 1.37
= 41.1 kg / TJ.
B.6.1.2. v) Methane emissions from waste water treatment (PEWW,CH4,y)
Small quantity of wastewater would be produced from the fuel preparatory system in the project activity.
This wastewater would be treated in closed anaerobic reactors along with the POME from the mill.
Methane generated from the closed anaerobic digesters would be destroyed in boilers or in flares.
Therefore, there would be no methane emissions from the waste water. Hence, the methane emissions
from wastewater are not estimated.
Therefore, Project emissions are,
PEy =
PETy + PEFF,CO2 y +
PEEC,y
GWPCH 4 * PE biomass, CH 4, y
(4)
Where:
ER electricity, y = Emission reductions due to displacement of electricity during the year y in tons of CO2 /
year
EGy
= Net quantity of electricity generation in the project activity during the year y in MWh
EF electricity, y = CO2 emission factor for the electricity displaced due to the project activity during the
year y in tons CO2/MWh
B.6.1.3.1 Determination of EF electricity, y
As per the approved methodology for scenario 2, the emission factor for the displacement of electricity of
a project activity with more than 15 MW should correspond to the grid emission factor (EF electricity, y= EF
grid, y) and EF grid, y should be calculated as follows:
If the power generation capacity of the project plant is more than 15 MW, EFgrid, y should be calculated
as a Combined Margin (CM) following guidance in the section Baselines in the Consolidated baseline
methodology for grid connected electricity generation from renewable sources (ACM0002). This
guidance is to be replaced with Tool to calculate the emission factor for electricity system (version
01.1).
The emission factor of the grid as per tool is given in Annex 3 Baseline information.
B.6.1.3.2. Determination of EGy
As per version 06.2 of ACM0006, for scenario 2, EGy corresponds to the net quantity of electricity
generation in the project plant (EGy = EG project plant)
Where,
EGy
= GWPCH4
BFpj,k,y
* NCVk
EF burning, CH4, k, y
In the absence of accurate information, the methodology suggests a default value of 0.0027 t CH4/ ton of
biomass for the product of NCVk and EF burning, CH4, k, y
As per methodology, the uncertainty of methane emission factor for uncontrolled burning of biomass is
more than 100 % and therefore the value of 0.0027 t CH4/ ton of biomass has to be adjusted with a
conservativeness factor of 0.73.
Hence,
NCVk *
EF burning, CH4, k, y
=
=
0.0027 * 0.73
0.001971 t CH4/ t biomass
Assessment of leakage:
As per methodology, where the baseline scenario is that the biomass residues are dumped or left to decay
or burnt in an uncontrolled manner without utilising for energy purposes, leakage has to be assessed to
demonstrate that the project activity does not increase the use of fossil fuel use.
Methodology suggests three options to assess leakage. Option 2 has been adopted due to availability of
direct data. As per option 2, it should be demonstrated that the quantity of available biomass is at least 25
% larger than the quantity of biomass residue that are utilized.
A radius of 50 km has been considered for assessment of leakage. Same distance of 50 kms has been
considered for transportation of biomass to the project site although actually distance could be lesser
during the operation of the project activity.
The names of the palm oil mills within a radius of 50 kms and their installed capacity is given in Table B9.
Table B-9 Details of palm oil mills within a radius of 50 kms and their installed capacity
S.No.
1.
60
2.
60
3.
60
4.
60
5.
60
6.
Tamaco Mill II
60
7.
45
8.
60
9.
60
10.
60
11.
60
12.
45
13.
60
14.
60
15.
S.D. Resources
120
Total
Assuming at least 6000 hours of operation of each mill, total FFB processed by the mills in the region
would be 5,580,000 tons of FFB/ year. There are no official statistics on the production and use of EFB,
so the total available amount of EFB has to be calculated. Quantity of EFB produced ranges from 21 23
%. An average value of 22 % is considered as EFB production. Further it is assumed that the annual
increase in FFB processed in Sabah will be 3.5% p.a. 10 . The escalation is not considered for leakage
estimates for conservatism.
The total quantity of FFB processed, EFB produced, demand for EFB and excess availability within 50
km radius is calculated and shown in Table B.10 below.
The demand for EFB is estimated through the number of potential CDM projects in the region. The CDM
projects considered are derived from the UNEP CDM-pipeline 11 . The CDM Pipeline contains a list of
all CDM projects that have either been uploaded for Global Stakeholder Process under validation or has
been submitted for registration at the UNFCCC.
In addition, save and except for consumption by CDM project activities, there is not any known use for
EFB in the region.
Table B.10: Calculation of leakage for biomass
Description
FFB processing capacity of palm oil mills in the region
Removing mill no. 11 as this is proposing CDM project with EFB (Mill
nos. 12 and 14 are proposing CDM projects mainly with mesocarp fibre)
FFB processed in balance mills
Number of operating hours of the mills
Total FFB processed
EFB processed at 22 %
EFB required for other projects within 50 km radius
Lahad Datu Edible Oils Sdn Bhd (Source : Registered PDD of the project
activity)
EFB available
EFB required for the project activity
Excess EFB
Value
930 tons / hour
60 tons/ hour
870 tons/ hour
6000 hours / year
5,220,000 tons / year
1,148,400 tons / year
122,500 tons / year
1,025,900 tons/ year
362,727 tons / year
663,173 tons / year
10
Anders Evald et al 2005: Renewable Energy Resources (in Malaysia) Recalculated based in table 2.2 p 10
11
Percentage of excess
182.83 %
Table B.10 conservatively affirms that there is approximately 182.83 % of unconsumed EFB in the
region after deducting all the volume consumed by the (CDM) project activities in the region. This
percentage exceeded the 25% unconsumed EFB benchmark required as the criteria to rule out leakage.
Furthermore, there is still excess EFB to accommodate other minor uses without changing the conclusion.
B.6.2. Data and parameters that are available at validation:
ID No.
Data / Parameter:
Data unit:
Description:
Source of data:
A
GWPCH4
t CO2 e /t CH4
Global Warming Potential (GWP) of methane, valid for the relevant commitment
period
Decisions under UNFCCC and the Kyoto Protocol (a value of 21 is to be applied
for the first commitment period of the Kyoto Protocol)
21
21 for the first commitment period. This value shall be updated according to any
future COP or MOP decision.
Value applied:
Justification of the
choice of data or
description of
measurement methods
and procedures actually
applied :
Any comment:
-
ID No.
Data / Parameter:
Data unit:
Description:
Source of data used:
Value applied:
Justification of the
choice of data or
description of
measurement methods
and procedures actually
applied :
Any comment:
ID No.
Data / Parameter:
Data unit:
Description:
B
EFCH4,BF
Kg/TJ
IPCC 2006
41.1 kg methane/TJ (calculated as the original 30 kg methane/TJ *
conservativeness factor of 1.37)
The methane emission is relatively uncertain, and thus a high conservativeness
factor is used in calculating the annual emissions.
C
EFgrid,y
tCO2/ MWh
The emission factor of the Sabah grid
Emissions reductions of the project activity during the year y in tons of CO2,
Emission reductions due to displacement of electricity during the year y in t CO2
Emission reductions due to aerobic decay of biomass residues in t CO2
Project emissions during the year y in tons of CO2, and
Leakage emissions during the year y in tons of CO2.
EG y
EF electricity, y
Where:
ER electricity, y = Emission reductions due to displacement of electricity in the year y in tons of CO2 / year
EGy
= Net quantity of electricity generation in the project plant during the year y in MWh
EF electricity, y = CO2 emission factor of the grid for the year y in tons CO2/MWh
B.6.3.1 Determination of EF electricity, y
As per the approved methodology, the emission factor for the displacement of electricity of a project
activity with more than 15 MW should correspond to the grid emission factor (EF electricity, y= EF grid, y) and
EFgrid, y should be calculated as a combined margin (CM) as per Tool to calculate the emission factor for
electricity system (version 01.1).
The basis for determination of EF electricity, y is given in Annex 3 Baseline information
Emission reductions ( baseline emissions) due to displacement of electricity during operation of first year
would be calculated as follows,
Baseline emissions during first six months of the project activity
ER electricity,
EG x EF electricity, y
34,718 MWh
69,435 MWh
Baseline emissions during the first year due to displacement of electricity is,
ER, electricity, y
27,774 + 55,548
B.6.3.3 Baseline emissions due to aerobic decay of biomass residues in a year BEbiomass, k, y
BEbiomass, y
= GWPCH4
BEbiomass
21 tCH4 / tCO2
BFpj,k,y
* NCVk
EF burning, CH4, k, y
* 0.001971 tCH4 / ton
= PETy +
PEFF
CO2, y
+ PEEC,y +
GWPCH 4 * PE biomass,
CH 4, y
Where:
PETy
CO2 emissions during the year y due to transport of the biomass residues to the project
activity (ton CO2/year)
PEFF CO2,
CO2 emissions due to consumption of fossil fuel during the year by the project activity in
ton CO2 / year
PEEC,y
CO2 emissions during the year y due to electricity consumption by the project activity
in ton CO2/year
GWPCH4
= Global Warming Potential for methane in ton CO2/ton CH4
PEBiomass,CH4,y= CH4 emissions from the combustion of biomass during the year y in ton CH4 / year.
B.6.3.4.1 CO2 emissions due to transport of biomass residues to the project activity
The formula to calculate the emissions from the transport of biomass to the project activity is
PETy =
BF
T ,k , y
TLy
Where,
PETy
TLy
BFT,k,y
=
=
AVDy
EFkm,CO2,y
CO2 emissions during the year y due to transport of the biomass residues to the
project site (t CO2/year)
Average truck load of the trucks used (tons) during the year y
Quantity of biomass residue type k transported to the project activity during the
year y (tons)
Average round trip distance (from and to) between the biomass residue fuel
supply sites and the project activity during the year y (km)
Average CO2 emission factor of the trucks (t CO2/km)
=
=
=
=
=
=
=
=
=
=
=
=
=
0.6 litre / km
0.845 kg / litre
0.507 kg of diesel/ km
42.4960 GJ/ tonne 12
0.0748 t CO2/ GJ 13
3.1787 t CO2 / tonne
3.1787 kg CO2 / kg of diesel.
3.1787 kgCO2/ kg l X 0.507 kg / km
1.612 kg CO2 / km
0.001612 t CO2 / km
100 kms
x 0.001612 t CO2 / km
B.6.3.4.2- CO2 emissions due to consumption of fossil fuels by the project activity
Small quantities of diesel would be required during start up of the boilers. The quantities of diesel
expected to be consumed per year by the project activity would be as follows :
- 200 litres / hour for 24 hours during start up from cold condition which is expected to
happen 4 times per year.
- 200 litres hour for 4 hours during start up from warm condition which is expected to
happen 6 times per year
- 100 litres/ hour for 14 days during pressure vessel inspection which is once a year.
On the above basis, diesel required by the project activity
Density of diesel
Quantity of diesel required
=
=
=
As discussed in section B.6.1.2.ii, project emissions due to consumption of diesel in the project activity,
PE FF, CO2, y is estimated as follows :
PEFF, CO2,y
=
=
FCi.j.y
x COEFi,y
FCi.j.y (ton) x 3.1787 t CO2/ ton
12
Source : National default value for diesels as per National Energy Balance ,2005, Malaysia
13
Source : Upper value of Table 1.4 of chapter 1 of IPCC 2006 as per methodology
Where
FCi,j,y is the quantity of diesel consumed in tons / year
COEF, j, y is the CO2 emission factor of diesel in t CO2/ ton
=
=
Where:
PEEC,y
ECPJ,y
EFgrid,y
TDLy
=
=
=
Project emissions from electricity consumption by the project activity during the year y
(ton CO2 /year);
Quantity of electricity consumed by the project activity during the year y (MWh / year);
Emission factor for the grid in year y (ton CO2/MWh)
Average technical transmission and distribution losses in the grid in year y for the voltage
level at which electricity is obtained from the grid at the project site
Estimation of EC PJ ,y
Although electricity for the fuel preparatory system would be from the biomass power plant, as per
methodology, electricity required for the fuel preparatory system would have to be considered as
imported from the grid.
The approximate installed capacity of the fuel preparatory system is 100 kW.
Number of operating hours
=
7,446 hours/ year.
Electricity required for operating the system
=
100 x 7446 x 1/1000
=
744.6 MWh/ year
Transmission and distribution losses (TDL)
The transmission and distribution losses are calculated from net electricity generation and net electricity
consumption in Sabah grid during the year 2005 which is the latest year for which the data is publicly
available.
Net electricity generation for the year 2006
Net electricity consumption for the year 2005
Transmission and distribution losses
TDL %
PE EC, y
=
=
=
=
1294 GWh 14
1007 GWh 15
287 GWh
22.18 %
* ( 1+0.2218)
14
Source : National Energy Balance, 2005, Malaysia, Ministry of Energy. Water and Communications, Malaysia
15
Source : National Energy Balance, 2005, Malaysia, Ministry of Energy. Water and Communications, Malaysia
728
Quantity of biomass type k used as fuel in the project plant during the year y in ( tons of
dry matter)
Net calorific value of the biomass type k in TJ / ton of dry matter of biomass,
CH4 emission factor for the combustion of biomass in the project plant tons CH4 per TJ.
NCVk
=
EFCH4,BF =
= BFk,y
= NCVk
41.1 kg CH4 / TJ
=
=
Hence,
PEbiomass,CH 4, y=
126,954
18
x 0.0000411
The project emissions during the first year of operation would be 3020 ton CO2/ year. Details of
calculation are given in attached Appendix 1.
Emissions reductions due to the project activity during I year ,
ER,y,
=
=
Therefore, the emissions reductions due to the project activity in a year from second year,
16
Source : Renewable Energy Resources, by Anders Evald and others Integrated Resource Planning,
DANIDA, February, 2005
ER,y,
=
=
=
Baseline emissions
Project emissions
127,214 ton CO2/ year + 5,255 ton CO2 / year
128,297 ton CO2 / year
B.7.
Year
Total Baseline
Emissions, EBL
(t CO2e)
Total Project
Emissions, EPA
(t CO2e)
Total Leakage
Emissions, ELE
(t CO2e)
Emissions
Reduction, ER (t
CO2e)
Year 1
86,799
3,020
83,780
Year 2
132,469
4,172
128,297
Year 3
132,469
4,172
128,297
Year 4
132,469
4,172
128,297
Year 5
132,469
4,172
128,297
Year 6
132,469
4,172
128,297
Year 7
132,469
4,172
128,297
Year 8
132,469
4,172
128,297
Year 9
132,469
4,172
128,297
Year 10
132,469
4,172
128,297
TOTAL
1,279,022
40,568
1,238,454
ID No.
Data / Parameter:
Data unit:
Description:
Source of data :
Measurement
procedures ( if any) :
01
BFk,y
Tonnes dry matter of EFB
Quantity of EFB combusted in the project activity during the monitoring period.
On site measurements
Quantity of EFB fed to the boiler would be weighed and recorded in the plant
records. The weight of EFB on dry basis would be calculated by multiplying
the quantity of EFB combusted during the monitoring period with the dry matter
content of EFB. The dry matter content of the biomass is 100 % minus Moisture
content % of the biomass.
Monitoring frequency
QA/QC procedures to
be applied:
Any comment:
Data would be archived for the crediting period and 2 years thereafter
ID No.
Data / Parameter:
Data unit:
Description:
Source of data :
Measurement
procedures ( if any)
02
Moisture content of EFB
%
Moisture content of EFB
On-site measurements.
Measurements are undertaken for representative samples of the biomass residues
used in the project activity. The analysis would be done as per accepted
international standards.
The moisture content of EFB would be analysed once in a month
Comparison with other measurements and with default values from literature.
Monitoring frequency:
QA/QC procedures to
be applied:
Any comment:
ID No.
Data / Parameter:
Data unit:
Description:
Source of data :
Measurement
procedures ( if any)
Monitoring frequency:
QA/QC procedures to
be applied:
Any comment:
ID No.
Data / Parameter:
Data unit:
Description:
Source of data:
Measurement
procedures if any:
Monitoring frequency:
QA/QC procedures:
Data would be archived for the crediting period and 2 years thereafter
03
EF CH4,BF
tCH4 /TJ
Methane emission factor for the combustion of biomass residues
Default values from Table 4 of ACM0006 version 06.2
Default values as per approved methodology
Since default value is adopted, frequency is not applicable.
Since the emission factor is uncertain, a high conservativeness factor is used in
calculating the project emissions.
Although methane emissions due to decay of biomass is not considered in the
baseline, methane emissions due to combustion of biomass is considered for
conservatism.
04
AVDY
Km.
Average round trip distance (from and to) between biomass fuel supply sites and
the project sites.
Records by project participants
The average distance can then be calculated as the weighted average of distance
to the mills. The sampling will be continuous.
Continuously
Check consistency of distance records provided by the truckers by comparing
recorded distances with other information from other sources (e.g. maps).
Any comment:
ID No.
Data / Parameter:
Data unit:
Description:
Source of data:
05
TLy
Tons.
Average load of the trucks used for the transportation of biomass.
Data from the weighing of incoming trucks are used to calculate the average
weight of the truck loads arriving at the plant.
Determined by averaging the weights of each truck carrying biomass to the
project plant. Continuously, aggregated annually.
Continuously
Check consistency of the number of truck trips with the quantity of biomass
combusted, e.g. by the relation with previous years.
Data would be archived for the crediting period and 2 years thereafter
Measurement
procedures if any:
Monitoring frequency:
QA/QC procedures:
Any comment:
ID No.
Data / Parameter:
Data unit:
Description:
Source of data:
Measurement
procedures if any:
Monitoring frequency:
QA/QC procedures:
Any comment:
ID No.
Data / Parameter:
Data unit:
Description:
Source of data :
Measurement
procedures:
Monitoring frequency:
QA/QC procedures to
be applied:
Any comment:
06
EFkm,CO2,y
tCO2/km.
Average CO2 emission factor for the trucks during the year y.
Sample measurement of the fuel type, fuel consumption and distance travelled
for all truck types will be conducted. CO2 emissions from fuel consumption shall
be calculated based on methodology. For NCV and EFCO2, reliable national
default values or IPCC default value values can be used.
Once in a year
The results will be cross-checked with emission factors referred to in the
literature.
Data would be archived for the crediting period and 2 years thereafter
07
FF project plant,i ,y (As per ACM 0006 ver 06.2 )
or
FCi,,j,y (As per Tool to calculate project or leakage CO2 emissions from fossil
fuel combustion )
Both data have the same definition.
Litres of diesel/year.
Quantity of diesel used in the project activity
Plant records
The quantity of diesel used in the project activity would be monitored and
recorded.
Continuously
Would be cross checked with fuel purchase receipts and usage details
Data would be archived for the crediting period and 2 years thereafter
ID No.
Data / Parameter:
Data unit:
Description:
Source of data:
Measurement
procedures if any:
Monitoring frequency:
QA/QC procedures:
Any comment:
08
EF,FF, CO2,
tCO2/GJ
CO2 emission factor for diesel used
Default National values would be used, If national values are not available,
latest default IPCC value would be used
Default value
Since default value is adopted, frequency is not applicable
Data would be archived for the crediting period and 2 years thereafter
ID No.
Data / Parameter:
Data unit:
Description:
Source of data:
Measurement
procedures:
Monitoring frequency
QA/QC procedures to
be applied:
Any comment:
09
EG project plant, y
MWh/year.
Net electricity generated by the project activity in a year
On site measurements
The data would be measured from the energy meter and recorded.
ID No.
Data / Parameter:
Data unit:
Description:
Source of data:
Measurement
procedures :
Monitoring frequency
10
NCVk,
GJ/ton of dry matter
Net caloric value of EFB.
Measurements.
Measurements shall be carried out at reputed laboratories and according to
relevant international standards.
The NCV of EFB would be measured once in six months, taking at least three
samples for each measurement.
The consistency of the measurements would be checked by comparing the
measurement results with relevant data sources (e.g. values in the literature) If
the measurement results differ significantly, additional measurements would be
conducted. It would be ensured that, the NCV would be determined on the basis
of dry biomass.
The data would be archived electronically for the crediting period and two years
thereafter
QA/QC procedures:
Any comment:
ID No.
Data / Parameter:
Data unit:
Continuously
Meter would be calibrated as per standard procedures.
The data would be archived electronically for the crediting period and two years
thereafter
11
Tons
Description:
Source of data:
Measurement
procedures:
QA/QC procedures:
Any comment:
ID No.
Data / Parameter:
Data unit:
Description:
Source of data:
Quantity of EFB that are utilized (used for energy generation) in the defined
geographical region.
Survey or statistics.
Annual collection of data from small scale renewable energy projects and CDM
projects using EFB as fuel or feedstock in the districts of Lahad Datu, Kunak,
Tawau and Semporna.
If possible, data on amount of used EFB is collected directly. Where only power
production data are available estimates of the fuel use are calculated by default
values from PDDs or generic information.
Element in evaluation of the leakage based on approach L2.
12
Tons
Quantity of available EFB in the region.
Calculations are based on annual production statistics from MPOB on state level
recalculated to cover the geographic region.
Annual calculations of the quantity of EFB is based on the default relation
between FFB and EFB of 22 %.
Description of
measurement methods
and procedures actually
applied :
QA/QC procedures:
Any comment:
Element in evaluation of the leakage based on approach L2.
ID No.
Data / Parameter:
Data unit:
Description:
Source of data:
Measurement
procedures :
Monitoring frequency
QA/QC procedures to
be applied:
Any comment:
ID No.
Data / Parameter:
Data unit:
Description:
Source of data
13
ECpj,y
MWh.
On-site electricity consumption for the biomass fuel preparatory system.
Calculated
The value would be obtained by multiplying the installed capacity of the fuel
preparatory equipment in kW and the number of operating hours of the project
activity and dividing by 1000
Continuously
.
The data would be archived electronically for the entire crediting period and two
years thereafter
14
EF grid, y
tCO2/ MWh
CO2 emission factor for grid electricity during the year y
Adopted if publicly published by relevant national agencies, especially by Pusat
Tenaga Malaysia (Malaysia Energy Centre). If not available, the emission factor
would be calculated
Measurement
procedures
Monitoring frequency
QA/QC procedures to
be applied:
Any comment:
ID No.
Data / Parameter:
Data unit:
Description:
Source of data:
Measurement
procedures:
QA/QC procedures to
be applied:
Any comment:
15
TDLy
Average technical transmission and distribution losses in the grid in the year y,
for the voltage level at which electricity is obtained from the grid at the project
site.
Calculated if sufficient data are publicly available. If the data re not available,
the default value from the Tool to calculate baseline, project and/ or leakage
emissions from electricity consumption (version 1) would be used
Calculated from data or default value from tool
-
The Chargeman would have a Chargeman Certificate and would be qualified to operate in high voltage
stations. The data recorded by the Operators would be regularly checked by the Chargemen.
A qualified electrical engineer (Steam grade engineer) would be in charge of the day to day running of
the project activity including operation and maintenance of boiler, turbine and other equipment in the
project activity. The electrical engineer would check the plant records regularly.
The weekly and monthly summary of the operating data of the project activity would be prepared by the
Electrical engineer and be reported to the Plant Manager and General Manager.
The electricity exported to the grid would be measured at the export meter. The electricity exported by
the project activity to SESB grid would be recorded by representatives of SESB and project proponents
each month. This reading would be the basis for invoicing by the project proponent and would be the
basis for calculation of emissions reductions of the project activity. These meter readings would be
maintained by the project proponent in power plant and in the head office. Monthly invoices are prepared
based on the joint certification of meter reading.
Internal Audits
The internal audit of the project activity would be conducted by the General Manager. He would review
all the records, safety installations, operating procedures, etc., any corrective action to be taken would be
recorded and steps would be taken to implement the corrective action.
Brief responsibilities of each person of the project activity
1. General Manager
He would be Overall In charge of the administration and operation of the mill and the project activity
and for reporting to the head office. He has more than 25 years experience in operation of palm oil
mills and biomass based power systems. He would be in charge of the Overall management of the
implementation of the monitoring plan and quality control of data and records.
He would periodically audit the records and if any discrepancy is found shall record them and take
corrective action as required.
2. Plant Manager
He is In charge of operation and maintenance of the project activity and would assist the General
Manager in implementation of the monitoring plan and summarizing the results. He would check the
results of all data monitored and would ensure the quality and accuracy of the data monitored.
3. Electrical engineer
He is In charge of the day today running of the project activity, its effective operation, maintenance
and monitoring. He would be directly responsible for maintenance of the plant records and operating
data. He would be in charge of ensuring the calibration of meters, analysis of biomass etc., and all
QA/QC activities associated with the project activity.
4. Protocol engineer
He would be in constant touch with SESB grid officials about day today running of the project
activity, offtake of electricity, etc.,
5. Boiler Chargemen
The Boiler Chargemen would be qualified to operate in high voltage stations and would be in charge
of the maintenance of the boiler. They would ensure that the data are recorded in the plant records
regularly.
6. Turbine Chargemen
The Turbine Chargemen would be qualified to operate in high voltage stations and would be in
charge of the maintenance of the turbine. They would ensure that the data are recorded in the plant
records regularly
7. Operators
They would be In charge of operating the Project activity and recording the data in the plant records.
8. Accounts and Admin Executive
Cross checking the monitoring records with receipt and procurement records.
The general structure of the monitoring team of the project activity is given below in Fig B-3:
General Manager
Plant Manager
Protocol Engineer
Electrical Chargeman
Boiler Chargeman
(3 one in each shift)
Operators
(3 one in each shift)
Turbine Operators
(6 two per shift)
B.8.
Date of completion of the application of the baseline study and monitoring methodology and
the name of the responsible person(s)/entity(ies)
Date of completion of the application of the baseline study and monitoring plan: 28/10/2008
Entity responsible for application of baseline study and monitoring plan :
YTL- SV Carbon Sdn. Bhd.
Level 4, Annex Block, Lot 10 Shopping Centre,
50, Jalan Sultan Ismail, 50250 Kuala Lumpur,
MALAYSIA
Tel : +6 03-2144 7200 Fax : +6 03-2144 7573
The entity determining the baseline and monitoring methodology is not a Project Participant.
24/10/2008
The date of purchase order for the boiler of the project activity is considered as the starting date of the
project activity. This is the first purchase contract for the project activity.
In accordance with para 68 of EB 41 and Annex 46 of EB 41, a letter with reference: SDR/CDM/08/020
dated 15th October 2008 was sent to DNA, Malaysia and a letter with reference :SDR/CDM/08/021 dated
15th October 2008 was sent to UNFCCC informing the intention to implement the project activity as
CDM project activity and seek CDM status for the same.
C.1.2. Expected operational lifetime of the project activity:
25 y-0 m
C.2.
Length:
D.2.
If environmental impacts are considered significant by the project participants or the host
Party, please provide conclusions and all references to support documentation of an environmental
impact assessment undertaken in accordance with the procedures as required by the host Party:
The environmental impacts due to the project activity are not considered to be significant by the Host
Party and the project participants.
Brief description how comments by local stakeholders have been invited and compiled:
A local stakeholder meeting was held for the project activity on 20 th October, 2008 at the project
proponents premises at Lahad Datu to compile the views and comments of the local stakeholders.
Invitation to the local stakeholders
Letters of invitations were sent to various institutions such as Malaysian Palm Oil Board, SESB, the
electric utility, Department of Environment, non governmental organisations, local community, other
palm oil mills in the area, etc.,
Advertisement was published in newspaper, Daily Express on Wednesday, 15 October, 2008 inviting
local public and others to attend a meeting on the project activity. The copy of Newspaper Advertisement
is attached as Annex 5.
Notice was displayed in the Notice Board of the premises inviting the staff of the project proponent to
attend the meeting and give their comments.
The list of attendees of the local stakeholders meeting is given in the Table E-1 below
Table E-1 List of attendees of the local stakeholders meeting
No.
Name
Organization
En Ruby Thaddesu
10
11
12
13
14
Mr. Anjang
15
16
En. Rosli
17
18
Sepangar Shipyard
19
20
Mr. T. Rajendran
21
22
Mr. Gopal
23
24
Sinar Enterprise
25
Mr. Max
Milivest
26
27
28
29
30
31
Mr. T. Rajendran of the project proponent welcomed the gathering and gave a presentation about the
technical details of the project activity, objectives and their intention to develop the project activity as a
CDM project activity. He also explained the need for the meeting and requested the delegates to offer
their views / comments and opinions about the project activity. Subsequently Mr. Ilango Bharathi gave a
presentation about CDM, the initiatives of UNFCCC in mitigating climate change and requested the
delegates for their frank comments on the project activity.
E.2.
The comments and queries of the delegates and responses by the project proponents are given below in
the form of questions and answers:
Question: Mr. Azmer Shamsuddin, Lahad Datu Edible Oil (LDEO) (Sr. General Manager) : What type of
cooling system method does this turbine be using?
Answer: Mr. T Rajendran, S.D. Resources : The turbine will be using a straight forward method of
Condenser which complies to the requirement of environmental authorities.
Q: Mr. Azmer Shamsuddin, LDEO : What type of incentive the government is offering in terms of tax
rebate? To what extent SD Resources would benefit from the governments incentives?
A: Mr. T Rajendran, S.D. Resources : The government is yet to officially announce any financial
incentive for this type of project. As of now, to the best of our understanding, the tax incentives do not
apply to income derived from the trading of CERs (Certified Emission Reductions) generated by the
project activity.
However, we hope that project activity would have official support from the Government of Malaysia as
the project activity would contribute to meet the Government of Malaysia s Ninth Plan target of 350
MW to be produced from renewable energy.
Q: Mr. Azmer Shamsuddin, LDEO : How confident you are that you would be able to achieve reduction
of nearly 1 million tons of CO2 for 10 years when the Kyoto Protocol expires by 2012?
A : Mr. Ilango Bharathi,: Although the uncertainty of Kyoto Protocol exists, it is normal practice to
estimate emission reductions for a period of 7 years or for a period of 10 years. The project activity has
adopted a crediting period of 10 years, it is expected that the project activity would reduce about 1
million tons of CO2 in 10 years. It is hoped that Kyoto Protocol would be extended beyond 2012.
However, the project would continue to produce electricity from renewable biomass and displace grid
electricity reducing greenhouse gas emissions even after 2012.
Q: Norizah Bt. Mohd. Nor, Suruhanjaya Tenaga, Sandakan (Energy Commission, Malaysia) : What
about the raw material availability for the project as another project is already operating in the area?
How much power would be exported to the grid?
A : Mr. T Rajendran, S.D. Resources
We are aware of the similar project and requirement of biomass. As per our study, there is ample
availability of EFB in the area and still a huge quantity of EFB is being dumped in the fields and allowed
to decay. Our study shows that there is more than 100 % excess EFB available within a radius of 50
kilometres of the project activity.
About 10 MW would be exported during the first stage and about 21 MW would be exported after
commissioning the 2nd stage of the project activity.
Q: Norizah Bt. Mohd. Nor, Suruhanjaya Tenaga, Sandakan (Energy Commission, Malaysia) : What is
the experience of the consultant in CDM projects and similar projects, especially in Malaysia?
A: Mr. Ilango Bharathi,: Currently, we are assisting in the development of about 42 projects in Malaysia
which includes biomass based electricity generation projects, composting projects, biogas projects, etc.,
Apart from above, we are also developing waste heat recovery based electricity generation projects,
landfill projects, energy efficiency projects, etc., in other countries. Two of our projects have been
registered and few projects have been submitted for registration and others are under various stages of
CDM process.
Q : Norizah Bt. Mohd. Nor, Suruhanjaya Tenaga, Sandakan (Energy Commission, Malaysia) : What
about the storage capacity of incoming raw material?
A : Mr. T Rajendran, S.D. Resources : We would have 1 to 2 days storage as there would be
continuous supply of EFB.
Q: Mr. Lam Kai Peng - Majlis Daera, (Municipal council), Lahad Datu : What are you going to do with
the ash that would be generated in the project?
A: Mr. T Rajendran, S.D. Resources: Ash has several uses. It could be used as manure in plantations,
could be used in brick manufacturing, cement manufacturing, etc., It would be disposed as per
environmental regulations.
Q: Mr. Ruby Thaddesu Sabah Electricity Supply Berhad: Could you explain in more detail the
electricity export to state grid?
A: Mr. T Rajendran, S.D. Resources: The electricity would be generated at 11 kV and net electricity after
inhouse consumption would be exported to the grid at 11 kV since the nearest injection point is at 11 kV.
The interconnection line would be implemented in accordance to SESBs requirements and practices. The
project activity would have one Protocol Officer who would be in constant touch with SESB for day
today export of the electricity.
After commissioning the first phase of the project activity, about 10 MW would be exported to the state
grid and after completion of the second phase, 21 MW would be exported to the grid.
E.3.
Since there was no comment requiring immediate action from the project proponents, no action was taken
due to the comments.
Annex 1
CONTACT INFORMATION ON PARTICIPANTS IN THE PROJECT ACTIVITY
Project Participant - Host Country
Organization:
Street/P.O.Box:
Building:
City:
State/Region:
Postfix/ZIP:
Country:
Telephone:
FAX:
E-Mail:
URL:
Represented by:
Title:
Salutation:
Last Name:
Middle Name:
First Name:
Department:
Mobile:
Direct FAX:
Direct tel:
Personal E-Mail:
General Manager
Mr.
T.
Rajendran
+6019 833 211
+6089 884588
+6089 887036
rajendran@fordeco.com
Last Name:
Middle Name:
First Name:
Department:
Mobile:
Direct FAX:
Direct tel:
Personal E-Mail:
Hallett
Andrew
+44 7747 481131
+44 (0)208 439 9514
+44 (0)208 439 9512
ahallett@natsource.com
Annex 2
INFORMATION REGARDING PUBLIC FUNDING
Annex 3
BASELINE INFORMATION
The baseline emission factor of the grid for electricity displacement and net quantity of electricity
generation and transmission and distribution losses are calculated in this section.
A.3-1 Determination of emission factor for electricity displacement (EF electricity, y)
As per the approved methodology version 06.2 of ACM0006, if the power generation capacity of the
project activity is more than 15 MW, the grid emission factor (EF electricity, y= EF grid, y) should be calculated
as per Combined Margin method as described in the Tool to calculate the emission factor for electricity
system (version 01.1).
Step 1. Identification of the relevant electric power system
The electricity grid network of Malaysia is as follows:
1. Peninsular grid
2. East Coast Sabah grid
3. West Coast Sabah grid
4. Sarawak grid
The project activity is located in eastern coast of Sabah state and supplies electricity to the East Coast
grid of Sabah. The tow main grids of Sabah state- East coast grid and West Coast grid are not
interconnected 17 . Since, the grids are not interconnected, the electricity supplied by the project activity
would displace electricity only in the East Coast Sabah grid. Hence, East Coast grid of Sabah is
considered as the applicable grid for the project activity and the electricity emission factor of East Coast
Sabah grid is considered to estimate the emission reductions of the project activity.
The CDM Energy Secretariat of Pusat Tenaga Malaysia (Malaysian Energy Centre) publishes Study on
Grid Connected Electricity Baselines in Malaysia wherein the baseline electricity emission factor of
each grid is calculated and published. The latest study was published in January, 2008.
The published Study has calculated the emission factor of East Coast Sabah grid based on combined
margin method 18 .
17
Source : Study on Grid Connected Electricity baselines in Malaysia, 2005 prepared by CDM Energy Secretariat,
Pusat Tenaga Malaysia, (Malaysia Energy Centre).
18
The Baseline Study mentions that the emission factor has been calculated as per ACM0002. It must be noted that
the steps specified in ACM0002 to estimate the emission factor are same as in Tool to calculate the emission factor
for an electricity system Version1.1. The Baseline study had adopted the latest IPCC 2006 Guidelines for National
Greenhouse Gas Inventories to estimate the emission factor. Therefore, it may be considered that the emission
factor has been calculated as per the tool.
The emission factor of East Coast Sabah grid is calculated as 0.8 t CO2 / MWh 19
Since data of generation of electricity, fuel consumption, etc., are not publicly available for estimation of
emission factor of the grid, this official study by CDM Energy Secretariat of Malaysian energy Centre
has been adopted.
A. 3-2 Determination of Transmission and Distribution losses of Sabah grid
The Transmission and Distribution Losses (TDL) of the connected grid have to be determined for
estimating the project emissions due to electricity consumed by the project activity for the fuel
preparatory system.
TDL is determined based on the net electricity generation and net electricity consumption data of Sabah
grid. The latest year for which these data are publicly available is 2006.
TDL is determined below:
Net electricity generation in Sabah grid for the year 2006
1,294 GWh 20
1,007 GWh 21
287 GWh
22.18 %
A.3- 3 Determination of Net quantity of electricity generation by the project activity EGy
As per Scenario 2 of version 06.2 of ACM0006, the net quantity of electricity generated EGy corresponds
to the net quantity of electricity generated by the project plant (EG project plant).
Estimation of net electricity generation during first phase of the project activity ( for first six months)
Capacity of power plant in the first phase
12.5 MW
6 months.
3285 hours
=
=
19
Source : Study on Grid Connected Electricity baselines in Malaysia, 2005 prepared by CDM Energy Secretariat,
Pusat Tenaga Malaysia, (Malaysia Energy Centre).
20
Source : National Energy Balance, 2006, Malaysia, Ministry of Energy, Water and Communications, Malaysia
21
Source : National Energy Balance, 2006, Malaysia, Ministry of Energy, Water and Communications, Malaysia
Estimation of net electricity generation during next six months of the first year
Capacity of power plant in the second phase
25 MW
6 months.
3285 hours
=
=
25 MW x 3285 hours
82,125 MWh
6,570 MWh
6,120 MWh
69,435 MWh
=
=
Estimation of net electricity generation per year after second (final) phase of the project activity
Capacity of power plant
25 MW
22
This figure is estimated based on the generally observed figure of 17 kW/ ton of FFB processed. This figure has
been assumed for estimation purposes. This may slightly vary during actual operations. However, net electricity
exported to the grid would be the basis for estimation of emission reductions.
Annex 4
MONITORING INFORMATION
1.
Introduction
The monitoring plan of the proposed project is a guidance document that provides the set of procedures
for preparing key project indicators, tracking and monitoring the impacts of the proposed project activity.
The monitoring plan will be used throughout the defined crediting period for the project to determine and
provide documentation of GHG emission impacts from the project activity. This monitoring plan fulfils
the requirement set out by the Kyoto Protocol that emission reductions projects under the CDM have real,
measurable and long-term benefits and that the reductions in emissions are additional to any that would
occur in the absence of the certified project activity.
The monitoring plan will use the following definitions of monitoring and verification.
Monitoring: The systematic surveillance of the project activitys performance by measuring and
recording of performance-related indicators relevant in the context of GHG emission reductions.
Verification: The periodic ex-post auditing of monitoring results, the assessment of achieved emission
reductions and of the projects continued conformance with all relevant project criteria by a selected
DOE.
The monitoring plan provides the requirements and instructions for:
1. Establishing and maintaining the appropriate monitoring systems for electricity generated by the
project activity;
2. Quality control of the measurements;
3. Procedures for the periodic calculation of GHG emission reductions;
4. Assigning monitoring responsibilities to personnel;
5. Data storage and filing system;
6. Preparing for the requirements of an independent, third party auditor or verifier.
2.
The emission reductions of the project activity would be calculated as explained in section B.6
3. Monitoring
3.1 Electricity generated
The electricity generated by the project activity would be monitored through metering equipment .The
data would be logged into the computer. The meter reading would be readily accessible. The metering
equipment will be properly calibrated and checked annually for accuracy according to electrical meter
specification guide. Calibration tests records will be maintained for verification.
3.2 Biomass residues consumption
The quantity and type of biomass residues combusted in the project activity would be monitored during
the operation of the project activity, including all the necessary parameters of the biomass residues
according to Section B.7 of this PDD. All relevant records will be maintained for verification.
Annex 5
Newspaper advertisement for the local stakeholders meeting
The copy of the newspaper advertisement on 15 th October 2008 in Daily Express, inviting for local
stakeholders meeting is given below:
Annex 6
Photographs of local stakeholder meeting
Few photographs of the local stakeholder meeting are attached in this annex.