ASSIGNMENT II

(Construction Quality Management)


NICMAR / CODE OFFICE
1.

Name

Arvind K

2.

Reg. No.

214-04-11-12192-2163

3.

Course No.

NCP 27

4.

Course Title

Construction Quality Management

5.

Assignment No.

Two

6.

Date of Dispatch

Page 1

ASSIGNMENT
You have been selected as a project manager for a prestigious high
rise building in Mumbai which will be housing very rich personalities from
industry and film world.
Your company management has asked you to formalize Quality
Management System (QMS) for interior finishes, plumbing and prevention
of rain water seepage so that the overall quality standard and image of
company is raised.

Purpose:
The purpose of this document i.e. Quality Assurance Plan is to
establish work methodology for Quality Control and Material engineering for
Construction of High Rise Building in Mumbai for very rich personalities
from industry and film world.
The procedure will outline the methods that will be used in line with
the National Building Codes, Local building codes Specifications for Building
works and the Technical Specifications as per the requirements of the
Engineer or his representatives.
The methodology also defines the standards of workmanship and
requirements for materials necessary for the work.

Scope:
This procedure is applicable to all engineers, workmen, supervisors,
inspectors and quality control personnel engaged in the works for the
Construction of High rise residential apartments in Mumbai. It intends to
correlate and control the tasks pertaining to Quality Control and Materials
testing in compliance with the requirements.
Page 2

Quality management System


Quality management system refers to all plans, processes and
activities that are developed to achieve the intended degree of
conformance in the design and execution of any project. The QMS concept
focuses attention of the following specific aspects of construction
processes.
1. Construction is a one time activity. It affords no second chance of
modification, repair or rejection once the construction work is
completed. There is no scope for catching the defects after the
construction is over. Therefore quality consciousness, skill and
workers are essential in achieving quality. Training, motivation

and

commitment are the primary requirement of quality construction.


2. With the increase in complexity and the size of construction
operations, the responsibility for ensuring quality has gradually
shifted from the worker to supervisor of inspection and later to the
quality control department. This

3.

Trend has to be reversed if quality is the goal. Responsibility to


ensure quality has to be shifted back to the worker at site and his
supervisor.

4. It is a well known fact that the quality cannot be constructed. It has


to be designed into a project system. QMS therefore starts from the
design stage itself. Quality of design is the difference between
Page 3

various design of the project for achieving the same end use and the
most optimal design finally selected. Thus economy, quality and safety
are very closely interlinked in construction process.
5. Quality is expensive. Quality decisions are based on trade-offs
between cost of construction and the benefits derived from the
operations of facility. Once the decision is taken, it has to be backed
by appropriate staff strength, infrastructure and support services.
The management must therefore be committed to quality, participate
in all measures developed to achieve it and lend support to QMS
personnel.
6. QMS is the responsibility of the project authority. The owner or his
representative formulates the policy, determines the scope of quality
planning and management establishes the relationship between the
various participating organizations and delegates responsibility and
authority to them so that the quality objectives set by the owner are
achieved.

Quality Control:
Quality control refers to the technical processes that gather,
examine, analyze and report the projects progress and conformance with
the performance requirements. QC mainly relates to four basic functions:
1. Setting up of standards and specifications.

Page 4

2. Evaluating materials, processes and outputs through appropriate


tests, inspection etc.
3. Appraising failures to these standards and acting when standards are
not being adhered to.
4. Planning improvements in the standards and specifications.

Quality Control norms, techniques and procedures:


Inspection:
Once quality standards and other things are laid out inspection
becomes a routine matter. In any quality control programme actual
inspection and measurement is an un-detachable factor, which is to be
planned at properly to meet with the overall objective of the quality control.
Various stages of inspection should be determined. Some of such stages
could be following.
i.

Material inspection at suppliers end.

ii.

Material inspection at the stage of receipt.

iii.

Material inspection at the stage of issue.

iv.

Inspection of the process at the time of initial setting of


machine/equipment.

v.

Inspection of trial run batch.

vi.

Inspection while the execution is in progress.

vii.

Inspection of the finished process.

viii.

Inspection before erection and commissioning.

ix.

Inspection of commissioning.
Page 5

x.

Inspection of machines and equipment commissioned.

Having decided various stages of inspection and various quality


characteristics to be inspected it is also important to decide who will
inspect, when the inspection will be carried out, how many units will be
inspected, instruments to be used required approval for acceptance.
While planning such inspection activities it is also important to decide what
information is to be given to the inspector at the time of inspection. Some
of the basic information required is design specifications, product
specification, quality characteristics, quality standards and tolerances
available and the detailed inspection procedures.
For total quality control the following six phases are necessary (6Cs)
i.

Comprehension - What is quality? It should be definable and


measurable

ii.

Commitment

- Clarity of concept and policies organizations for

it.
iii.

Competence

- Develop methods test procedures to evaluate

quality
understand the price conformance to quality.
iv.

Communication - Create awareness, resolve conflicts, coordinate


activities,

Page 6

v.

Correction

- Solve problems for non conformance. They may be

due to lack of attention rather than lack of knowledge or lack of


facilities.
vi.

Continuance

Maintain its importance and do not complacent

ensure exposure to sustained programme.

Quality control standards and specifications


The quality of construction depends upon right material used, the
correct methods followed and produce end product of acceptable
performance. Quality control attempts to ensure just that much. The means
of quality control are tests, inspection, supervision and analysis of data etc.
Quality tests are conducted in laboratories and inspection and supervision
are carried out on the site and the data analysis is done by experts in
office.

Specifications:
The project authorities prepare the process of working out
specifications of various facilities where concrete will be used. However,
the standards and specifications for concrete and its various ingredients
are universally standardized and they are required to be in conformity with
same. Indian standards IS for concrete and its basic ingredients viz.,
cement aggregates coarse and fine, water admixtures and various aspects of

Page 7

concreting, its placement and final acceptance should be as per IS


specifications.

Tests:
Tests are used to determine the various properties of the materials,
which help in their selection as well as for ascertaining the quality of final
product. The test results are compared with the prescribed standards and
specifications and judgements are arrived at. Proper methods of sampling,
prescribed procedures of testing, well qualified and trained personnel for
testing work and properly equipped laboratories are necessary.

What to test:
The manufactured goods such as cement and steel carry their
suppliers warrantee but this does not mean that they are not to be tested.
In case of materials like aggregate and water the properties may vary
widely over time and space and proper selection has to done to meet the
engineering requirements.
The raw materials are processed to obtain the final product. The processing
need to be tested and supervised carefully. Some intermediate process may
not be having tests and they cannot be tested and the inadequacies if any
can known only when the final product is tested. In such situation the
testing of final product is important.
Page 8

Statistical Quality Control:


Total quality management addresses organizational quality from
managerial and philosophical viewpoint. TQM focuses on customer driven
quality standards, managerial leadership, continuous improvement, quality
identified problems at the source and quality made everyones responsibility.
However, talking about solving quality problems is not enough. We need
specific tools that helps us make the right quality decision. These tools
comes from the area of statistics and are used to help identify quality
problems in the production process as well as in product itself.
Statistical quality control is the term used to describe the set of
statistical tools used by quality professionals. Statistical quality control can
be divided into three broad categories.
Descriptive Statistics:
Are used to describe quality characteristics and relationships.
Included are statistics such as the mean, standard deviation, the range and
a measure of distribution of data.
Statistical Process Control:

Page 9

Involves inspecting a random sample of the output from a process and


deciding whether the process is producing products with characteristics
that fall within a predetermined range. SPC answer the questions whether
the process is functioning properly or not.
Acceptance Sampling:
Is the process of randomly inspecting a sample of goods and deciding
whether to accept the entire lot based on the results. Acceptance sampling
determines whether a batch of goods should be accepted or rejected.

Quality Assurance:
Quality assurance refers to the managerial processes which
determine the organizations design, objectives and resources, the project
team, funding agencies, performance standards and feedback on the project
performance, appropriate actions to deal with deviations and all steps
necessary for promoting quality awareness at all levels and in all parts of the
project organizations.

A typical quality assurance programme addresses itself to the following.


1.

Organization structure of the project team and quality assurance


department.

2. Responsibilities and powers of the various personnel involved.


3. Identification of the coordinating personnel.
4. Quality and its programmes.
Page 10

5. Quality education and awareness,


6. Quality circles.
7. Training.
8. Setting up of MIS for quality.
9. Resolution of technical differences and disputes.
10. Preparation of quality assurance manuals and their checklist.
11. Vendor survey procedures.
12. Vendor surveillance procedure
Quality assurance provides protection against quality problems
through early warnings of trouble ahead. Such early warnings play an
important role in the prevention of both internal and external problems. The
assurance is provided from objective evidence but the type of evidence
differs widely according to persons requiring the assurance and nature of
product.
It need not be emphasized that quality assurance is an essential
prerequisite of all construction projects. Over years the accent on quality
has graduated progressively from simple Inspection to quality control to
quality assurance and to quality management. Whereas the limitations of
inspections are quite obvious, a quality control system includes testing of
raw materials at selection and processing stage, testing at various stages of
production, acceptance and feedback.

MANAGEMENT RESPONSIBILITIES:
Page 11

Management Commitment:
Top management comprises of CEO, MD, all Directors, all VPs, and
Functional Heads of various departments at Head Office. The leadership
(including In-charges / Managers / Heads) hold key positions at HO,
and Project sites in a matrix organizational structure. Management has
appointed a Management Representative and a Quality Management Cell
for

effective

organization.

implementation

and

monitoring of

QMS throughout

Management Reviews are planned at various levels for

effective monitoring of QMS.


Evidence

of

top

management

commitment

to

development

and

implementation of the quality management system with a view to


continually improve its effectiveness through the following manner: a) Communicating throughout the organization the importance of meeting
customer as well as statutory and regulatory requirements.
b) Quality policy is established and displayed prominently at all site locations
and Work places and is understood by all employees by discussions, training
and providing printed pocket cards, which are carried by employees.
c) Quality objectives for the company are established & displayed at all site
locations and work places. Quality objectives are also defined for each
major & critical process at Head Office level.
d) Management Review process is established and the frequency for this
review is half yearly.
Page 12

e) Availability of resources for implementing Quality Management System


is ensured through proper planning and logistics.

Customer Focus:
Responsibility: Primary Project In-Charge;
Secondary All Section Heads
Processes are established for customer communication on
suggestions for improvements, information on status of project and
direct meetings. Areas of dissatisfaction / improvements, if any,
are discussed at various levels and informed to project site and
corrective actions taken based on above inputs.
Record the Customer complaint and acknowledge the receipt of the
same within 3 working days.
Discuss the Customer complaint

Examine root causes.

Identify & implement corrective action

Assess Results

Inform customer

Review procedure and reformulate prevention of repetitive complaint.

Reply to Customer complaints with action plan and target dates for

achieving the same.

Communicate to customer on action taken on complaint.


Page 13

Receive information about direct customer satisfaction from MIOF.

Prepare action plan on area of dissatisfaction with the consultation of

all sections

Improve performance on area of dissatisfaction.

Quality Policy:
Top management has articulated Quality
Policy

Shows commitment to comply with the requirements and continually


improve the effectiveness of the Quality Management System

Provides a framework for establishing and reviewing quality

objectives

Communicated and understood within the organization

The policy is communicated to all by displaying at strategic

locations and through Quality manual, which is being distributed to all


sections and intend being circulated to all employees of company.

REFERENCES:
Reference No.

Document

1. Specifications for High rise building National building by


National Building codes & Mumbai Mahanagar Regional
Development authority (MMRDA) building by laws

Page 14

2. Technical Specifications for residential building


3. Quality Control Inspection Plan

Appendix II

4. Quality records Checklists

Appendix III

5. Quality records Format for Appendix IV


Internal tests
6. Calibration Schedule

Appendix V

7. Relevant NBC, Neuferts, IS


standards

codes & Time saver

Methodology:
Identification of source for raw materials.
The identification for source for raw materials will be on the basis of
proximity from the location of work, conformance of quality of material in
accordance with requirement for the project and commercial viability.
For manufactured products, vendors are to be got approved from the
engineer.

Development of Mix design / details.


Different mix designs for various grades of concrete works for High
Rise Building (Frame structures) & foundations construction are to be
developed at the Site Laboratory through trials. On identification and
successful trial in conformity to the requirements, the details are to be

Page 15

supplied for adoption in construction works after due approval from the
Engineer or his representative.

Quality control in Construction.


The Supervisors for Construction work will be assisted with testing
equipment for monitoring of gradation, slump, temperature and for
sampling / spot test of materials as and when required.
Control / checks / monitoring of levels, dimensions, profile during and
after construction activities, will be done by construction engineers / survey
engineers.
QC Engineers will be assigned to the Building work and Road work as and
when required by the Materials Engineer of The Contractors. They will
assist the respective building / Road sectional In-charges / Engineers /
Supervisors for collecting test samples, performing field tests as required.
Whenever required, material samples will be drawn for spot testing or tests
at the site laboratory in accordance with Documents.
Conformance of Post Construction checks will be done by the
respective Engineers of building and road engineer.

Marble /Granite tiling work in floors


Page 16

1.

Marble /Granite shall be of approved quality in terms of source,


thickness, colour, texture, etc.

2.

Sizes of marble blocks, slabs & Tiles shall be as per Approved


Drawings & specification.

3.

Only slabs and tiles shall be machine cut & factory made. The following
tolerances shall be applied (As per CPWD Specification) in the
dimensions of blocks, slabs & tiles.
Dimension
Length
Width
Thickness

4.

Blocks
+ 2%
+ 2%
+ 2%

Slabs
+ 2%
+ 2%
+ 3%

Tiles
+ 3%
+ 3%
+ 1%

Before starting of work the samples shall be approved by Client.


Requirement

for

physical

properties

shall

be

as

per

CPWD

Specifications as follows:
Characteristics
1. Moisture absorption after
24 hours immersion in cold
water
2. Hardness
3. Specific Gravity
5.

Requirements
Maxm. 0.4%
weight
Minimum 3
Minimum 2.5

Method of Test
by IS: 1124

Mhors scale
IS: 1124

Each stone shall be cut to required size and chisel dressed on all bed
and joints.

6.

The mortar shall be as specified. All stones shall be wetted before


placing in position. These shall then be floated on mortar and bedded
properly in position with wooden mallets.
Page 17

7.

Stones shall be laid in regular courses of not less than

15 cm in

height and shall be of the same height unless otherwise noted.


8.

The depth of the joints 6 mm from face shall be uniform and as fine
as possible but shall not be more than 1.5 mm thick.

9.

The curing shall be done for a period of at least 7 days. After curing
it shall be rubbed with carborandum stone of different grades
numbers 60,120 & 320 in succession and cleaned & washed with a
solution of oxalic acid.

10.

Sample size & criteria of conformity shall be as follows( As per CPWD


Specifications ):
Nos.
of Nos.
of
blocks/slabs/tiles blocks/slabs/tiles
in lot
to be selected in
sample
Upto 25
3
26 to 100
5
101 to 200
8
201 to 500
13
501 to 1000
20

Permissible Subnumber of sample


defects
size
in
number
0
2
0
2
0
3
0
4
1
5

Ceramic / Glazed tile flooring


Tiles shall be of approved make, size, colour & thickness.
1.
Sample approvals shall be taken before start of work from client.
2.

The length of all four sides shall be measured correct to 0.1 mm and
average length and breadth shall not vary more than +/- 0.8 mm from
specified dimensions. The tolerance for thickness shall be up to +/0.4 mm.
Page 18

3.

Base concrete (RCC slab) shall be cleaned, wetted & mopped. Bedding
of cement mortar (1:3) shall be laid with average thickness 10 mm
while thickness under any portion of the tiles shall not be less than 5
mm.

4.

Over mortar bedding neat grey cement slurry of required consistency


shall be applied @3.3 kg/m2 over an area to cover 20 tiles.

5.

Tiles shall be soaked in water, washed clean and shall be fixed in this
grout with gentle tapping with wooden mallet.

6.

Surface of flooring during laying shall be frequently checked with a


straight edge about 2 mm long so as to obtain true surface with
required slope.

Brick Work
1.

The bricks shall be of class 7.5 & of non-modular type.

Bond: Generally English bond shall be followed wherever applicable, toothing


and closure shall be provided.
2.

Following tests shall be performed.

a)

Efflorescence.

b)

Crushing strength.

c)

Water Absorption.

d)

Dimension Check.

3.

Frequency of tests/sampling shall be 20 bricks chosen randomly for


every 1 lac Bricks for each brand.

Page 19

No.
of For characteristic specified
Bricks in the for individual bricks
lot
No. of bricks Permissible
to
be no
of
selected
defective in
the sample
2001-10000
20
1
10001-35000 32
2
35001-50000 50
3
Lot size

2001-10000
10001-35000
35001-50000

For
dimensional
characteristic of
group of 20 bricks
No. of bricks to
be chosen
40
60
80

Sampling
size
for
compressive strength, water
absorption & efflorescence
5
10
15

Permissible No.
of defective for
efflorescence
0
0
1

5.

The mortar of brickwork shall be 1:6(1cement:6coarse sand).

6.

Bricks shall be soaked in water before use for a period for the water
to just penetrate the whole depth of brick.

7.

Half or cut bricks shall not be used except as closures where


necessary.

8.

Suitable measuring boxes shall be made for measuring sand to prepare


the mortar.

Page 20

9.

While laying the brickwork the frog should be face up. The joints shall
be racked to an average depth of 10 mm. When plaster or pointing to
be done the joints should be streaked flush.

10.

Curing shall be done for atleast seven days or as per specification.

Plumbing and sanitation


1.

All water supply/plumbing installation work to be done by licensed


plumbers.

2.

All fittings/fixtures and accessories shall be of approved brands only.


Prior approval of samples of all fittings & fixtures shall be taken from
client.

3.

All materials of pipes (CI, GI, Glazed stoneware, etc) shall be of


approved brands only. Prior approval of samples of all Piping materials
& accessories shall be taken from Client.

4.

Unless otherwise specified shop drawings shall be prepared for


various activities and approval of same shall be taken from Client.

5.

No cross connections with waterlines of wholesome water and


wastewater pipelines shall be done.

External drainage
1.

All line out of layout designed for pipelines, manhole and inspection
chambers shall be marked on the ground.

2.

The trenches for underground drainage shall be excavated as per


design depth and grade.
Page 21

3.

The required bed of slope shall be provided as per drawing in the


pipeline to create required velocity.

4.

For joints in the pipeline the caulking material shall be of specified


quality and the same shall be executed as per drawing. Socket ends of
all the pipes shall face uphill.

5.

Sufficient spun yarn shall be forced into the socket and required
depth should be available for filling the caulking material. If the
caulking material is lead then it shall be poured in one action and when
the lead is thoroughly fluid.

6.

C.I. vent pipe shall be provided at the head of drain and cowl is
provided at the top.

Stoneware pipes
1.

Pipes shall be inspected and cracked or chipped pipes shall be


rejected in the work. Pipes shall be thoroughly checked and cleaned
before laying.

2.

The minimum diameter of the pipes for outside drainage shall not be
less than that specified in the drawing.

3.

The pipe trench for laying the pipes shall be of sufficient width to
have easy jointing and caulking activity. The required gully traps and
manholes shall be provided at the pipe junction as per drawing.

4.

Testing for water tightness shall be done as required in the


Specification.

5.

Sufficient time shall be allowed for the joints to set and then
trenches filled, watered and compacted.

Page 22

Sanitary and plumbing- CI pipes


1.

The pipes shall be checked for specified quality and its water
tightness.

2.

The pipes shall be laid in position with the socket ends facing uphill
irrespective of the direction of flow.

3.

The caulking material shall be as specified. In case of lead caulking for


spigot and socket joints sufficient yarn shall be forced into the
socket to have the required depth for lead for filling.

4.

After completion of pipes laying in each section, water tightness shall


be tested before covering with soil.

5.

Unless otherwise specified, Non-return valves or check valves shall be


used of brass, duly chromium polished and provided on ascending part
of the main to check the return flow.

G.I. Pipes and fittings


1.

Pipes laid under ground shall be atleast 0.5m below G.L. or as specified
on grads as specified.

2.

Pipes before laying shall be checked for visible damage (broken


edges, cracking or spallation of pipes) if any. If detected the
defective pipes shall be rejected.

3.

After laying pipes same shall be tested under water pressure at least
100 lbs per sq. inch unless otherwise specified or mentioned.

4.

Joints shall be filled with cement or any other specified material with
proper caulking finishing etc.

Page 23

5.

Pipe work shall be laid in such a way that it is accessible for


inspection, replacement & repairs (as far as not to be buried in walls
and solid floors).

6.

Service pipe or supply pipe shall be connected directly to W.C. All such
suppliers should be connected from cisterns which shall be supplied
from storage tank.

Plastering work
1.

Loose mortar if any is stuck with wall shall be brushed out.

2.

Any hole filling or repairs shall be completed prior to the plastering


work.

3.

The wall surface shall be thoroughly washed with water, cleaned and
kept wet before plastering is commenced.

4.

12 mm thick, 150mm x 150 mm square gauges shall be applied


horizontally and vertically, at not more than 2.0 metre interval.

5.

1st or the undercoat coat of 12 mm plaster shall be applied in 1:5,


cement: sand ratio by volume only.

6.

Proper line and level with true surface shall be provided for this coat.

7.

The surface shall be roughened and furrowed 2 mm deep with


scratching tool / broom to form keys for the finishing coat.

8.

The curing shall be continued till Finish Coat is applied.

9.

The Finish coat shall be applied after the under coat is sufficiently
set, but not dried and in any case within 48 hrs.

10.

Sand for the second coat of plaster shall be sieved with 3.0 mm sieve.

11.

The mortar for 2nd coat shall be in 1:2 cement: sand ratio by volume.

Page 24

12.

The 2nd or the finish coat shall be struck uniformly over the first
coat and firmly pressed and levelled by using a 3.0 to 4.0 mts. Long
aluminum batten.

13.

All the edges, angles, arises and junctions shall be vertical and
horizontal.

14.

When the work is suspended at the end of the day, the plaster shall
be left, cut clean to the line both horizontally and vertically. When
plastering is to be resumed, the edge of the old work shall be scraped,
cleaned and wetted with water before plaster is applied to the
adjacent areas.

15.

The surface shall than be firmly trowelled and sponge floated to


remove excess moisture and bring the sand to the surface. The
surface thus prepared shall be uniformly roughened for texture.

16.

The surface of plaster shall be kept wet for at least 7 days and shall
be protected from the sun (covering it by suitable method).

Health, Safety and Environment


The working areas will be suitably barricaded as and when required.
Proper sign boards / signages shall be erected to caution / inform the
surrounding people.
Personal protective equipment relevant to the nature of work will be used
for the Project. Personnel handling admixtures or other chemicals will use
appropriate protective equipment recommended by the manufacturer.
Persons handling nuclear gauges / instruments shall wear special protective
attires as recommended by the manufacturer.

Page 25

Care shall be taken during dismantling the structures against fall of


materials from top. All excavation shall be provided with slope or bench.
All electrical and mechanical equipment and installations shall be periodically
inspected for safety and necessary maintenance work carried out.
Care shall be taken:
(i)

to reduce generation of dust during operation,

(ii)

against pollution of water source due to construction operation

(iii)

against undue cutting of greenery / plants and trees.

Appendix I
Management of QC / Materials System Flowchart.
Project InCharge

Material
Engineer

QC Engineer Central
Laboratory

QC Engineer Field
Laboratory

QC Engineer Field
Laboratory

Page 26
QC
Supervisor

QC
Supervisor

QC
Supervisor

QC
Supervisor

Page 27

Appendix II
Sl.
NO

Test
Required

Test
Ref.

Quality Control Inspection Plan ( QCIP)


Sampling Ref Test
Acceptance Test
& Process
Location
Criteria
per

As Test
Frequency

Concrete Works material and field control


1

Petro
Cl.1007,
graphic
Cl. 1008
examination
of
Coarse
and
fine
aggregate

Sample from External


source
of
coarse
and
fine
aggregate i.e
quarry , river
bed
from
where rock /
boulders, sand
are
to
be
collected.

Page 28

IS 2386 Initially 1
Pt 8
set of 3
specimens
for
each
source of
supply,
subsequent
ly
when
warranted
by change
of source /
quality.

Remar
ks

Appendix II
Sl.
NO

Test
Required

Test
Ref.

Alkali
Aggregate
reactivity

Cl.1007,
Cl. 1008

Quality Control Inspection Plan ( QCIP)


Sampling Ref Test
Acceptance Test
& Process
Location
Criteria
per
Crushed
External
sample from
proposed
source
of
coarse
and
fine
aggregate i.e
quarry , river
bed
from
where rock /
boulders, sand
are
to
be
collected.

Page 29

As Test
Frequency

Material
IS 2386 Initially 1
shall
be Pt 7
set of 3
Innocuous
specimens
for
each
source of
supply,
subsequent
ly
when
warranted
by change
of source /
quality.

Remar
ks

Appendix II
Test
Ref.

Quality Control Inspection Plan ( QCIP)


Sampling Ref Test
Acceptance Test
& Process
Location
Criteria
per

Sl.
NO

Test
Required

Specific
Cl.1007,
Gravity
of Cl.1008
aggregates

-do-

Site lab

IS 2386 Initially 1
Pt 3
set of 3
specimens
for
each
source of
supply,
subsequent
ly
when
warranted
by change
of source /
quality
otherwise
on monthly
basis.

Water
Cl.1007,
absorption
Cl.1008
of
coarse

-do-

Site lab

IS 2386 Initially 1
Pt 3
set of 3
specimens

Page 30

As Test
Frequency

Remar
ks

Appendix II
Sl.
NO

Test
Required

Test
Ref.

Quality Control Inspection Plan ( QCIP)


Sampling Ref Test
Acceptance Test
& Process
Location
Criteria
per

and
fine
aggregates

As Test
Frequency
for
each
source of
supply.
Subsequen
tly,
one
test
for
coarse
aggregate
and
two
tests for
fine
aggregate
per day.

Deleterious
Cl.1007,
material for Cl.1008
aggregate.

-do-

External

Page 31

IS 2386 Initially 1
Pt 2
set of 3
specimens

Remar
ks

Appendix II
Sl.
NO

Test
Required

Test
Ref.

Quality Control Inspection Plan ( QCIP)


Sampling Ref Test
Acceptance Test
& Process
Location
Criteria
per

Coarse
aggregate

Coal = / < 1%
Clay lump = /
< 1%
Finer
than
75= / < 3%
Total = /
5%

Fine
aggregate

<

Coal = / < 1%
Clay lump = /
< 1%
Finer
than
75= / < 3%
Shale: = / <
1%
Total = /
5%
Page 32

<

As Test
Frequency
for
each
source of
supply,
subsequent
ly
when
warranted
by change
of source /
quality

Remar
ks

Appendix II
Sl.
NO

Test
Required

Test
Ref.

Soundness
Cl. 1007
(5 cycles) of
coarse
aggregate

Quality Control Inspection Plan ( QCIP)


Sampling Ref Test
Acceptance Test
& Process
Location
Criteria
per
-do-

External

Soundness
(5 cycles) of
fine
aggregate

Page 33

As Test
Frequency

Sodium
IS 2386 Initially 1
Sulphate = / Pt 5
set of 3
< 12%
specimens
for
each
Magnesium
source of
Sulphate = /
supply,
< 18%
subsequent
Sodium
ly
when
Sulphate = /
warranted
< 10%
by change
of source /
Magnesium
quality.
Sulphate = /
< 15%

Remar
ks
In
case
for
aggreg
ate
water
absorp
tion
exceed
s 2%

Appendix II
Sl.
NO

Test
Required

Test
Ref.

LA abrasion Cl. 1007


value
of
coarse
aggregate

Quality Control Inspection Plan ( QCIP)


Sampling Ref Test
Acceptance Test
& Process
Location
Criteria
per
-do

Site lab

Page 34

As Test
Frequency

a) = / < 50% IS 2386 Initially 1


for concrete Pt 4
set of 3
specimens
b)
for
for
each
concrete
source of
wearing coat
supply,
= / < 30%
subsequent
ly
when
warranted
by change
of source /
quality
otherwise
on monthly
basis.

Remar
ks

Appendix II
Test
Ref.

Quality Control Inspection Plan ( QCIP)


Sampling Ref Test
Acceptance Test
& Process
Location
Criteria
per

Sl.
NO

Test
Required

Aggregate
Cl. 1007
impact value
of
coarse
aggregate

-do

Flakiness
Cl. 1007
Index
for
coarse
aggregate

Crushed
aggregate
from crusher
or any other
proposed
source.

10

Aggregate
crushing
value

Crushed
aggregate
from crusher
or any other

Cl.1007

Site lab

As Test
Frequency

a) = / < 45% IS 2386 -dofor


Pt 4
concrete
b) for
concrete
wearing
coat = / <
30%
Site lab
= / < 35%
IS 2386, Initially 1
Pt 1
set of 3
specimens
for
each
source of
supply,
subsequent
External / a)= / < 45% IS 2386, Initially at
Site lab.
for
Pt 4
time
of
concrete
approval of
b) = / < 30%
source.

Page 35

Remar
ks

Appendix II
Sl.
NO

Test
Required

Test
Ref.

Quality Control Inspection Plan ( QCIP)


Sampling Ref Test
Acceptance Test
& Process
Location
Criteria
per
proposed
source

11

Gradation
coarse
aggregate

Table
900-6

Crushed
aggregate
from
proposed
source.

As Test
Frequency

for
concrete
wearing
coat.
Site lab.

Subsequently
from
stock
pile at site.

Page 36

IS 2386, Initially
Pt.1
before mix
design for
approval of
source.
Subsequen
tly,
one
test
for
every days
work
of
each
fraction of
coarse
aggregate.

Remar
ks

Appendix II
Sl.
NO

Test
Required

Test
Ref.

12

Gradation
fine
aggregate

Table
900-6

Quality Control Inspection Plan ( QCIP)


Sampling Ref Test
Acceptance Test
& Process
Location
Criteria
per
Fine
aggregate
from
proposed
source.

Site lab.

Subsequently
from
stock
pile at site.

Page 37

As Test
Frequency

Remar
ks

F.M. of sand IS 2386, Initially


shall not be Pt.1
before mix Fine
>2 and < 3.5design for aggreg
approval of ate
source.
confor
Subsequen ming
tly,
one to
test
for zone
every days 1V as
work
of per
each
tablefraction of 4
of
coarse
IS383
aggregate. shall
not be
used
for
reinfor

Appendix II
Sl.
NO

Test
Required

Test
Ref.

Quality Control Inspection Plan ( QCIP)


Sampling Ref Test
Acceptance Test
& Process
Location
Criteria
per

As Test
Frequency

Remar
ks
ced
concre
te.

13

Gradation of
all
in

aggregate

Blended
aggregate

Site lab.

As per IS IS 2386, Initially


383 table -5 Pt.1
during mix
design.
Subsequen
tly
one
test
for
every days
work.

14

Workability Table
of
fresh 900-6
concrete
( slump test)

At concrete At
plant As per table IS 516
batching plant site
and 1700 -4
and site of field
construction.

Page 38

One
test
per
each
vehicle,
both
at
concrete
batching

Values
stated
in
table
1700
4 are

Appendix II
Sl.
NO

Test
Required

Test
Ref.

Quality Control Inspection Plan ( QCIP)


Sampling Ref Test
Acceptance Test
& Process
Location
Criteria
per

As Test
Frequency
plant and
site
of
pouring at
start
of
work.
Subsequen
tly
as
required.

Page 39

Remar
ks
not for
pumpa
ble
concre
te. For
pumpa
ble
concre
te min.
slump
requir
ement
is
around
120
mm.Fo
r
Transi
t

Appendix II
Sl.
NO

Test
Required

Test
Ref.

Quality Control Inspection Plan ( QCIP)


Sampling Ref Test
Acceptance Test
& Process
Location
Criteria
per

As Test
Frequency

Remar
ks
Mixer
minimu
m
slump
is 50
mm

15

Strength of Cl.1716.
concrete
2.3

Cube test

16

Cement
( OPC
grade )

At
manufacturer
s plant.

1.Fineness

Cl.1006
53

Site lab.

As
per
frequency
of
collection
samples.
As per IS As per IS of
MTC
for Except
12269
12269
every
ing
At
batch
of bridge,
manufactur
cement
Cemen
ers lab.
>225 m2/kg
t
of
-doother

Page 40

As
per IS 516
Cl.1716.2.5

Appendix II
Sl.
NO

Test
Required

Test
Ref.

Quality Control Inspection Plan ( QCIP)


Sampling Ref Test
Acceptance Test
& Process
Location
Criteria
per

2.Soundness

<10

(i)Lechatlier
method

-do<0.8

(ii)Autoclave
method
3. Standard
Consistency
4.Temp.durin
g testing
5.Initial
&
Final Setting
time
6.Compressiv
e Strength

At site
At site
At site

27
degree
Celcius
>30
min,<
600 min.

At site
At site

Page 41

>27MPa at 3
days

As Test
Frequency

Remar
ks
grades
also
can be
used
as
approv
ed by
the
Engine
er or
his
repres
entativ
e.

Appendix II
Sl.
NO

Test
Required
Chemical
Requirement
s

Test
Ref.

Quality Control Inspection Plan ( QCIP)


Sampling Ref Test
Acceptance Test
& Process
Location
Criteria
per
External

1.Lime
Saturation
Factor

As per
12269
>0.8<1.02
>0.66
<3.0

2.Alumina
iron Ratio

<6.0

3.Insoluble
residue

<3.0

4.Magnesia

<4.0

5.Sulphuric
Anhydride

Not
specified

6.Total loss
on Ignition

Page 42

As Test
Frequency

IS As per IS Frequency
12269
for
External
test:
1 test in 6
Months
MTC
for
every
batch
of
cement

Remar
ks

Appendix II
Sl.
NO

Test
Required
7.Total
alkalis
Na2o

Test
Ref.

Quality Control Inspection Plan ( QCIP)


Sampling Ref Test
Acceptance Test
& Process
Location
Criteria
per

as

Not
specified

9.Tricalcium
Aluminate
Concrete
admixture

Remar
ks

<0.1

8.Total
chlorides

17

As Test
Frequency

Cl.1012
&
IS:9103

At
manufacturer
s Plant

At
<0.2%*
manufactur
ers Lab.
> 3%*

1.Chloride
content

1*

2.Dry
Material
content

within 2%*

IS 6925

>1%*

Page 43

As per IS
9103

MTC
for
Each
lot/samplin
g
from
every
consignmen
t

Unifor
mity
test
from
extern
al test
house
@
1
test /

Appendix II
Sl.
NO

Test
Required

Test
Ref.

Quality Control Inspection Plan ( QCIP)


Sampling Ref Test
Acceptance Test
& Process
Location
Criteria
per

3.pH value

*All
based
on the value
declared by
the
manufacture

4.Ash
content
5.Relative
Otherdensity
major manufactured products
1.

Reinforceme
nt steel bar
A) Chemical
test

Cl.1009.
3

At
manufacturers
plant

As Test
Frequency

At
manufact
urers lab

Carbon
Sulphur
Phosphorus

Page 44

Fe
Grade

415 IS 228, MTC


for
IS 1608, every
of
A) Chemical IS 1559, batch
reinforcem
IS 1786
test
ent steel.
=
/
<
0.30+.02 %
Frequency:
= / < 0.06 +
1 test in
0.005 %
500 MT
= / < 0.06 +
0.005 %

Remar
ks
7000
Lts.
Accept
able
limits

Appendix II
Sl.
NO

Test
Required

Test
Ref.

B) Physical
test

Quality Control Inspection Plan ( QCIP)


Sampling Ref Test
Acceptance Test
& Process
Location
Criteria
per
At Site.

External

B) Physical
test

0.2% proof
stress

415
N
sqmm.

Elongation

14.5 %

Bend test

Satisfactory

RCC
pipe

Hume

Structural
Cl.1009.
steel
6
sections and
plates

Hot
dip
Galvanised

As Test
Frequency

At
manufacturers
plant

At
manufact
urers lab

As per IS IS 458
458 for
NP4
class
pipe.

At
manufacturers
plant

At
As per 2062 IS 228, -domanufact , GR A, B or IS 1608
urers lab. C
as
applicable
Steel
soil
reinforceme

Page 45

MTC
for
each Lot.

Remar
ks

Appendix II
Sl.
NO

Test
Required

Test
Ref.

a) shape & Cl.4.1.1


form
of
appendi
b) Physical x -1
and
mechanical
properties

Quality Control Inspection Plan ( QCIP)


Sampling Ref Test
Acceptance Test
& Process
Location
Criteria
per
At
manufacturers
plant

At
manufact
urers
lab / lab.
of
specialise
d agency.

c)
Galvanisation
thickness

As Test
Frequency

a)
strips, As
per To
be
grids, sheets designed checked at
dimension random
b)
BS EN IS 228, b)
test
10025
or IS 1608, result for
equivalent of is1559
each lot of
IS 2062
material
c) as per IS 4826
specification
of
specialised
agency.

Page 46

c) do -

Remar
ks

MATERIAL

NAME OF THE TEST

Brick /
Tile bricks/
Concrete
block

a) Efflorescence

FIELD/
LABORATORY
TEST
Field

b) Water absorption

Laboratory

MIN.
QUANTITY
OF
MATERIAL
REQUIRED
As desired by the
Engineer
-

c) Compressive
Strength

Laboratory

d)

Timber

Tolerance (Size & Field


shape)

50,000
required
Engineer.
1 Cum

a) Moisture content
Laboratory
(Oven drying
method)
b) Species

Field

As reqd.
Engineer.

Page 47

nos.
by

FREQUENCY
SAMPLING

OF

TEST/

20 bricks chosen at random


for every 100,000 bricks
for each brick field.

as
the
From each fresh lot or each
10 cum material one sample.

by

the

MATERIAL

NAME OF THE TEST

Flush
shutters/

a) Test
for
immersion

Plywood

Flooring

Precast
Terrazzo
Tiles

Glazed tiles

b) Test
for
adhesion

FIELD/
LABORATORY
TEST
end Laboratory

glue Laboratory

c) Test for adhesion Laboratory


of
Test for abrasion
- do Hardening compound
- do a) Shape & Dimension
b)
Transverse
strength
c) Resistance to wear
d) Water absorption
a) Water absorption
b) Impact test

MIN.
QUANTITY FREQUENCY OF
OF
MATERIAL SAMPLING
REQUIRED
11 Shutters
6 nos. 0 to 65
13 nos. 66 to 110
20 nos. 111 to 180
As reqd. by the 32 nos. 181 to 300
Engineer

- do - do -

- do - do - do - do -

- do - do - do - do -

- do - do -

3000 nos.
*
As decided by the *
Engineer.

Page 48

12 nos./2000 nos.
6 nos./2000 nos.
6 nos./2000 nos.
8 nos./2000 nos.

TEST/

MATERIAL

NAME OF THE TEST

Hardness test

FIELD/
LABORATORY
TEST
- do -

MIN.
QUANTITY FREQUENCY
OF
MATERIAL SAMPLING
REQUIRED
- do *

Granite
marble
Fire Doors

Fire test

- do -

Specified fire rated.

1 Door

Steel doors

a) Thickness of steel
b) Sheets
a) Composition of
Alumn. Alloy
b) Powder coating

Field/Lab.
- do Laboratory
Field

As specified.
- do As per BIS.
65 microns.

1 Door

Aluminium

1 Sample

* To be decided by the Engineer or his representative in accordance with site conditions.

Page 49

OF

TEST/

WATER PROOFING

Waterproofing of Raft and Retaining Walls


Waterproofing of Raft and Retaining walls by external tanking
(including grouting of Concrete)
External tanking (including grouting of concrete) of basement,
trenches, etc. shall be carried out using an approved acrylic chemical
waterproofing compound, in stages given below:
Stage 1:
After the lean concrete has been laid to receive the RCC raft, a
345 mm thick brick toe wall in Cement Mortar 1:6 shall be constructed,
on the perimeter of the area to be water proofed. The height of this
wall shall be equal to the thickness of the RCC Raft. The brick toe wall
shall be paid separately under the item of Brick work.
Stage 2:
Base
The external tanking treatment shall be carried out for the
base raft over the lean concrete in the following sequence.
a)

A layer of cement slurry mixed with the acrylic waterproofing


compound shall be spread over the lean concrete.

b)

In each layer where acrylic waterproofing compound is to be


Page 50

used it shall be mixed in the ratio of 400 gms per 50 kg. Of


cement unless specified otherwise.
c)

Thereafter a 25mm thick (minimum) bedding layer of cement


mortar 1:3 (one part cement: three parts course sand) mixed
with acrylic waterproofing compound shall be laid.

d)

Curing shall be done by spraying water for 7 days.

e)

A layer of Kota stone slabs of approximately 600 x 600mm and


having minimum thickness of 20mm shall be laid. The joints
between the stones shall be 6mm. After laying the joints shall be
raked and sealed with cement mixed with acrylic waterproofing
compound (in the ratio 1:1).

f)

A layer of cement mortar 1:4 (one part cement: four parts


coarse sand) mixed with acrylic waterproofing compound shall be
laid and finished smooth.

g)

Curing shall be done by spraying water for 7 days.

h)

The waterproofing shall be turned up along the brick wall on the


perimeter of the basement raft. The work shall be carried out
as described under walls.

NB: The above specification shall also be followed for the roof of
basement.

Page 51

Stage 3: Grouting of Concrete


Raft
Placing and prefixing of 15mm M.S. nozzles of length 0.5D where
D is the depth of the raft shall be done on the construction joints and
pour strips. The spacing of the nozzles shall be 1 m apart in both
directions in the raft to enable grouting to be done. The pipes shall
project 50mm above the top of the raft and shall be plugged using
M.S. caps.
The RCC shall be cast after placement of the nozzles as required.
After the concrete of raft has attained proper maturity the
injection of cement mixed with non-shrink polymeric grouting
compound through the nozzles under maximum pressure of 2.5
kg/sqcm. By hand/air/electric/pump shall be carried out.
The nozzles shall be sealed after injection operation is over
with a cementations rendering with quick setting admixture of CICO
make or approved equivalent.
The above specification shall also be followed for the roof of
basement if required.
Waterproofing of other areas (roofs, terraces, water tanks,
toilets, floor slabs, etc.)

Page 52

Scope of Work
The work shall include waterproofing for the building roofs,
terraces, water tanks, toilets, floor slabs, walls, planters, chajjas, sills
and any other areas and at any other locations and situations as
directed by the Engineer, in accordance with the design, shapes,
thickness, details, all as shown on the Good for Construction
drawings or as specified or as directed by the Engineer complete in all
respects to give the quality of finished work as desired by and to the
entire satisfaction of the Engineer.
The work shall be carried out by an experienced specialist subcontractor who shall be appointed only after prior approval of the
Engineer.

MATERIALS:

Tapecrete
An acrylic based polymer modified cementations composite
coating system manufactured by FRC Composites India Ltd. Or
approved equivalent.

Waterproofing General
The waterproofing treatment shall be done on smooth plastered
surfaces. Portland ordinary cement shall be used for the plastering on
the concrete screed on roofs. The plastered areas shall be cured for a
minimum of 7 (seven) days. Curing shall be done by keeping wet gunny
or burlap or ponding water.

Page 53

The surface shall be allowed to dry for about 4 to 6 weeks,


after the curing period is over.
The surface on which waterproofing is to be done shall be bone
dry, free of all dust, loose material, laitance etc. A surface dry area
shall not be construed as being totally (bone) dry.
The Contractor shall ensure that everything where the
waterproofing is worked around or into are fixed (e.g. rainwater
downtakes, etc.) in position and all pre-waterproofing application work
by the other Contractors is complete.

Waterproofing to Toilets, Kitchens etc.


Waterproofing treatment to floor slabs and walls, chhajjas,
roof projections, toilets, kitchens etc. in the building shall be done as
described below.
A priming coat shall be applied over the complete area to be
waterproofed. The primer shall be made of net grey cement mixed
with an integral waterproofing compound in the proportion as
recommended by the manufacturer.
Thereafter two coats of Tapercrete mixed with cement in
the proportion 1:2 (1 kg Tapercrete : 2 kg of cement) shall be applied.
All the joints of pipes, edges, corners, openings shall be sealed
with epoxy putty. As refer above.

Page 54

Waterproofing and Testing


The treated area (flat and horizontal only) shall be tested by
allowing water to stand on the treated areas to a depth of 150mm for
a minimum period of 72 hours.
The treated area (flat and horizontal) shall have a continuous
slope towards the rainwater outlets and no water shall pond anywhere
on the surface.
The roofs shall be water-tight and shall be tested on completion
by flooding the roof with water to a minimum depth of 25mm fir 24
hrs. Where it is impracticable, because of roof falls or otherwise, to
contain a 25mm depth of water, the roof shall have water applied by a
continuous hose of sprinkler system to provide a sheet flow of water
over the entire area of the roof for not less than 6 hrs. In either
case the roof shall be considered satisfactory if no leaks or damp
patches show on the soffit. Should the structure not satisfy either of
these tests, then after completion of the remedial work, it should be
retested in accordance with this clause.

The roof insulation and

covering should be completed as soon as possible after satisfactory


testing.

Inspection, testing and controlling of Non conforming


product:
Inspection & Testing:
Plan the characteristics of the raw material, process
and product to be checked, frequency of check,
Page 55

method of check, sampling size


Plan stages of customer verification as per contract
agreement.
Conduct inspection & tests as per plan and keep
relevant records to demonstrate the conformance.
Check the results against planned requirements. Improve
methodology or process and take necessary corrective
action where planned results are not achieved
Get approval of the competent authority and or the
customer for acceptable minor deviations from the
planned arrangements.
Use calibrated equipments for measuring processes.

Control of Non-Conforming Product


Identify Non-conforming product / service found through
Customer complaints, Audits and Inspections
Prepare action plan to remove the non-conformity.
By

rectification

/reworks/corrective

action,

By

alternative use,
By degrading or by scraping.
Implement corrective action to eliminate the root cause
of the non - conformity.

Page 56

Officers & their qualifications:


1.

Project manager
Qualification: Should be Graduate with additional qualification of
masters in Project management from a reputed institute.
Experience: Should have minimum 20 years exp. Out of which
Last five should have worked in similar capacity with lots of
impetus on quality control and assurance.

2.

Senior Engineer (QA/QC) Civil


Qualification: Should be Graduate with additional qualification of
masters in Project management from a reputed institute. Should
be well versed with quality control measures especially for civil
as well interiors and water proofing
Experience: Should have minimum 15 years exp. Out of which
Last ten should have worked in similar capacity monitoring and
controlling quality.

3.

Engineer Civil Execution


Qualification: Should be Graduate from a reputed institute
Experience: Should have minimum 10-12 years exp. Out of which
five years should have worked in similar capacity in execution of
such prestigious high-rise building.

4.

Engineer (QA/QC) Plumbing and sanitary


Qualification: Should be Graduate with from a reputed institute.
Should be well versed with quality control measures especially
plumbing and sanitary

Page 57

Experience: Should have minimum 15 years exp. Out of which last


ten should have worked in similar capacity monitoring and
controlling quality.
5.

Junior Engineer (QA/QC) Civil


Qualification: Should be Graduate/Diploma from a reputed
institute. Should be well versed with quality control measures
especially for civil as well interiors and water proofing
Experience: Should have minimum 8-10 years exp. Out of which
last five should have worked in similar capacity monitoring and
controlling quality.

6.

Junior Engineer Execution Civil


Qualification: Should be Graduate/Diploma from a reputed
institute.
Experience: Should have minimum 8-10 years exp. Out of which
last five should have worked in similar capacity monitoring and
controlling quality.

7.

Store keeper
Qualification: Should be Graduate from a reputed institute.
Should be versed with latest material management procedures.
Experience: Should have minimum 5-7 years exp. Out of which
last three should have worked in similar capacity monitoring and
controlling quality.

8.

Junior Store keeper


Qualification: Should be Graduate/under graduate from a
reputed institute. Should be versed with latest material
management procedures.
Page 58

Experience: Should have minimum 5 years exp. Out of which last


three should have worked in similar capacity monitoring and
controlling quality.

Functions and Responsibilities:


(1)

Project manager
Functions & responsibilities: Should be responsible for overall
quality control and assurance as well as for execution. Should
have overall control and command over all implementation of
quality control measures and will have checks for its outcome.

(2)

Senior Engineer (QA/QC) Civil


Functions & responsibilities: Should be responsible for overall
quality control and assurance. Should have overall control and
command over all implementation of quality control measures and
will have checks for its outcome.

(3)

Engineer Civil Execution


Functions & responsibilities: Should be responsible for overall
quality while execution. Should help and co operate with QA/QC
team to improve overall quality.

(4)

Engineer (QA/QC) Plumbing and sanitary


Functions & responsibilities: Should be responsible for overall
quality control and assurance for all plumbing and sanitary works.
Should have control over all implementation of quality control
measures for sanitary & plumbing and will have checks for its
outcome.
Page 59

(5)

Junior Engineer (QA/QC) Civil


Functions & responsibilities: Should assist in implementing
quality control and assurance procedure. Should supervise
implementation of quality control measures and will monitor for
its outcome.

Monitoring and controlling quality.


(6)

Junior Engineer Execution Civil


Functions & responsibilities: Should assist and supervise work
with an eye for quality control and assurance procedure.

(7)

Store keeper
Functions & responsibilities: Should be responsible in
implementing quality control and assurance procedure for all
materials brought at site using latest material management
procedures.
Should supervise implementation of quality control measures and
will monitor for its outcome.

(8)

Junior Store keeper


Functions & responsibilities: Should assist in implementing quality
control and assurance procedure for all materials brought at site
using latest material management procedures.
Should assist &supervise implementation of quality control
measures and will monitor for its outcome.

Page 60

Reporting to Whom
Project Manager___________ Managing Director
Senior Engineer (QA/QC) Civil________ Project Manager
Engineer (QA/QC) Plumbing and sanitary _______ Senior
Engineer (QA/QC) Civil
Engineer Civil Execution ____________ Project Manager
Junior Engineer (QA/QC) _________ Senior Engineer
(QA/QC) Civil
Junior Engineer Execution Civil ________ Engineer Civil
Execution
Store keeper _____________ Senior Engineer (QA/QC)
Civil
Junior Store keeper ___________ Store keeper

Compliance work with regulations and bylaws


The Contractor shall conform in all aspects with:
(a) the provision of any enactment in India as applicable from
time to time
(b)the regulations or bye-laws of any local body and utilities.
(c) The Contractor shall be bound to give all notices required by
statute, regulations or by-laws, as aforesaid and to pay all
fees and bills payable in respect thereof. The Contractor will
arrange necessary clearances and Approvals before the Work
is taken up.

Page 61

Ignorance of Rules, Regulations and Bylaws shall not constitute a


basis for any claim at any stage of work

Compliance with Contractors Request for Details


i.

The Contractor shall give written notice to the Engineer


whenever progress of the Works is likely to be delayed or
disrupted unless any further Drawing, where the Special
Conditions of Contract provide for such Drawings to be
prepared by the Engineer, or order, including a direction,
instruction or Approval is issued by the Engineer within a
reasonable time. The notice shall include details of the Drawing
or order required and of why and by when it is

ii.

Required and of any delay or disruption likely to be suffered if


this issue is delayed.

iii.

The Engineer shall furnish with reasonable promptness, on


receipt of request from the Contractor, additional instructions
by means of Drawings or otherwise necessary for the proper
execution of the Works or any part thereof. All such Drawings
and instructions

shall

be consistent

with the

Contract

documents and reasonably inferable therefrom. The Engineer


may

ask

the

Contractor

for

alternative

proposals

or

clarifications or additional data or any other detail in respect


Contractors request, if any.
If, due to any failure or inability of the Engineer to issue within
a reasonable time any Drawing or order requested by the
Contractor as stated above, the Contractor suffers delay and /
Page 62

or incurs additional costs, the Engineer shall take such delay into
account while determining any extension of time to which the
Contractor would be entitled under.

Suitable incentives are given to the contractor on successfully,


timely & within the quoted rates (i.e with variations) completion of
work for critical activities.

Delays
Failure or delay by the Employer or the Engineer, to hand over
to the Contractor the Site necessary for execution of Works, or any
part of the Works, or to give necessary notice to commence the
Works,

or

to

provide

necessary

Drawings or

instructions

or

clarifications or to supply any material, plant or machinery, which


under the Contract, is the responsibility of the Employer, shall in no
way affect or vitiate the Contract or alter the character thereof; or
entitle the Contractor to damages or compensation thereof but in any
such case, the Engineer shall extend the time period for the
completion of the Contract, as in his opinion is / are reasonable.
In case of delay on the part of the Contractor, the Contractor
shall be liable to pay liquidated damages in addition to any other
compensation for the damages suffered by the Employer.

This is

without prejudice to the right of the Employer to rescind the


Contract.

Page 63

Bibliography/ Readings:
Material from NICMAR
Internet
Quality control manuals of DLF Metro & Delhi Metro.
CPWD Specifications, National Building Codes.

Page 64