Task summary during John Wongs Leave between 9-Mar-15

and 24- Mar-15


Anthony/Simon/Joyce

07/08 flood protection board (target formal submission with ICE


certificate by 11-Mar-15)
07/08 interface mega-shor at Zone A design amendment (target
formal submission with ICE certificate by 12-Mar-15)
BD/GEO comments on Meinhardts design report of removal of
stitch joint at 07/08 interface (contact Meinhardt early next
week for the status)
KAT Safety wire for working at height (target formal submission
with ICE certificate by 11-Mar-15)
KAT Entrance A temporary works design (target draft submission
received from AECOM by 9-Mar-15 and onward submission to
ICE/MTR at the same day)
DSD comments on hydraulic assessment of temporary nullah
(target RtC from AECOM by 12-Mar-15 and onward submission to
MTR/DSD at the same day)
Option 3 nullah temporary works design (target draft submission
received from AECOM by 25-Mar-15)
BD/GEO comments on Design 4.4 and 4.5 (target RtC from
AECOM by 9-Mar-15 and onward submission to MTR at the same
day)
4.5 pumping test assessment report (chase ICE to return
comments by 11-Mar-15)
ABWF design submissions for Louvre, external cladding, glass
balustrade, internal cladding (chase the sub-contractors to
revise drawings according to ICE comments by 12-Mar-15) ,
concrete block wall P-08 (target formal submission with ICE
certificate by 12-Mar-15)
Updated Risk Register for the risk workshop held on 26-Feb-15
(Simon: draft risk register has been sent to BMT. Sent to MTR
once received the consolidated risk register and meeting
minutes from BMT)

Jeff/Kelvin/Jacky

Access Shaft formwork design (target submission to ICE by 9Mar-15) Submitted to Simon.
BD/GEO comments on Design 5.1c (target RtC from AECOM by
12-Mar-15 and onward submission to MTR at the same day)
Submitted to Walace and responding Walaces comment and
waiting for Padro to correct the drawing before resubmit to
Walace
-1.4mPD submission based on designed strut level (chase ICE to
return comments by 10-Mar-15) Submitted to ePMS on 16/3
BD/GEO comments on Meinhardts design report of
removal/relocation of stitch joints at Area 2 (contact Meinhardt
early next week for the anticipated date for RtC submission)
Mined tunnel steel formwork design formal submission (formal
submission with ICE certificate by 9-Mar-15) Submitted to ePMS
on 6/3
Mined tunnel base formwork design (Initiate dialogues with subcontractor when selected by Cliff/Aldous) 3 options proposed by
Kason on 18/3
7.1a&c design report ePMS submission (formal submission with
ICE certificate by 9-Mar-15) Submitted to ePMS on 6/3
7.1b&d design report, BD/GEO hard copy submission and ePMS
submission (formal submission with ICE certificate by 10-Mar-15)
Submitted to ePMS on 12/3
Meinhardts design report of removal of stitch joints at
Launching and Receiving Shafts (Update with Meinhardts
Sammy early next week for the timeline)