Jeff/Kelvin/Jacky
Access Shaft formwork design (target submission to ICE by 9Mar-15) Submitted to Simon.
BD/GEO comments on Design 5.1c (target RtC from AECOM by
12-Mar-15 and onward submission to MTR at the same day)
Submitted to Walace and responding Walaces comment and
waiting for Padro to correct the drawing before resubmit to
Walace
-1.4mPD submission based on designed strut level (chase ICE to
return comments by 10-Mar-15) Submitted to ePMS on 16/3
BD/GEO comments on Meinhardts design report of
removal/relocation of stitch joints at Area 2 (contact Meinhardt
early next week for the anticipated date for RtC submission)
Mined tunnel steel formwork design formal submission (formal
submission with ICE certificate by 9-Mar-15) Submitted to ePMS
on 6/3
Mined tunnel base formwork design (Initiate dialogues with subcontractor when selected by Cliff/Aldous) 3 options proposed by
Kason on 18/3
7.1a&c design report ePMS submission (formal submission with
ICE certificate by 9-Mar-15) Submitted to ePMS on 6/3
7.1b&d design report, BD/GEO hard copy submission and ePMS
submission (formal submission with ICE certificate by 10-Mar-15)
Submitted to ePMS on 12/3
Meinhardts design report of removal of stitch joints at
Launching and Receiving Shafts (Update with Meinhardts
Sammy early next week for the timeline)