You are on page 1of 95

Electrical System Planning

By

Max Billington, P.E.


March 20, 2012

Goals

March 20, 2012

Safety
Sustainability
Project Specific Parameters
Properly Sized for the Load
Minimum Initial Investment
Maximum Service Continuity
Maximum Flexibility and
Expandability
Maximum Power Quality
Maximum Electrical Efficiency
Minimum Operating Costs
Minimum Maintenance Cost

Safety
Fundamental Canon of
Professional Engineering:

Hold paramount the safety, health


and welfare of the public in the
performance of their duties.

March 20, 2012

Safety
State of Colorado Title 12
Professions and Occupations
Article 25 - Engineers and Surveyors
12-25-101. General Provisions

In order to safeguard life, health and


property and to promote the public
welfare

March 20, 2012

Configuration of the
Distribution System

Functions of structure, present and future


Life and flexibility of structure
NEC Prescriptions
Reliability requirements
Locations of service entrance and distribution
equipment
Sources of power; including normal, standby and
emergency
Continuity and quality of power available and
required
Distribution and utilization voltages
Locations and characteristics of loads

March 20, 2012

System Reliability

Multiple power sources


or services.
Multiple connection paths
to the loads served.
Redundancy of Critical
Components
Maintenance

March 20, 2012

System Reliability
According to recent presentation by
Steve Fairfax of MTechnology:

70% of all data center system failures are


human caused
Most human caused failures occur during
scheduled maintenance

March 20, 2012

UPS maintenance - 250% higher probability of


failure
Generator maintenance - 10% higher probability of
failure

Design Progression

Project Specific Parameters


Determining the Load
Voltage selection
Selecting the Type of Distribution System
Layout the system configuration
Power quality

March 20, 2012

Project Specific
Parameters

Short Circuit Calculations


Coordination
Motor Protection
Specific Equipment
Protection
Voltage Drop
Ground Fault Protection

March 20, 2012

Project Specific Parameters

Short Circuit Calculations


Cost of bracing
Conductor protection

Motor Protection

Elevation
Temperature
Power quality
Motor starting

Specific Equipment
Protection

March 20, 2012

Voltage Selection
600Y/346

Standard Nominal System


Voltages and Voltage Ranges
(From IEEE Standard 141-1993)
March 20, 2012

Voltage Selection

Selection of Motor Horsepower


Ratings as a Function of System Voltage
(From IEEE Standard 141-1993)

March 20, 2012

Voltage Selection
Voltage drop
Load
Distance
Size and location of utilization equipment
Cost
Less than 1000 amps 120/208 or 120/240
More than 1000 amps 277/480
More than 4000 amps 277/480 or 346/600

March 20, 2012

Selecting the Type of


Distribution System
Number of Services
Six Handle Rule
Only one, except

March 20, 2012

NEC ARTICLE 230 Services


I. General
230.2 Number of Services.
A building or other structure served shall be supplied by only one service unless
permitted in 230.2(A) through (D). For the purpose of 230.40, Exception No. 2
only, underground sets of conductors, 1/0 AWG and larger, running to the same
location and connected together at their supply end but not connected together
at their load end shall be considered to be supplying one service.
(A) Special Conditions. Additional services shall be permitted to supply the
following:
(1) Fire pumps
(2) Emergency systems
(3) Legally required standby systems
(4) Optional standby systems
(5) Parallel power production systems
(6) Systems designed for connection to multiple sources of supply for the
purpose of enhanced reliability
March 20, 2012

ARTICLE 230 Services


230.2 Number of Services (contd)
(B) Special Occupancies. By special permission, additional services
shall be permitted for either of the following:
(1) Multiple-occupancy buildings where there is no available
space for service equipment accessible to all occupants
(2) A single building or other structure sufficiently large to make
two or more services necessary
(C) Capacity Requirements. Additional services shall be permitted
under any of the following:
(1) Where the capacity requirements are in excess of 2000
amperes at a supply voltage of 600 volts or less
(2) Where the load requirements of a single-phase installation
are greater than the serving agency normally supplies through
one service
(3) By special permission
March 20, 2012

ARTICLE 230 Services


230.2 Number of Services (contd)
(D) Different Characteristics. Additional services shall be
permitted for different voltages, frequencies, or phases, or for
different uses, such as for different rate schedules.

230.71 Maximum Number of Disconnects.


(A) General. The service disconnecting means for each service permitted by
230.2, or for each set of service-entrance conductors permitted by 230.40,
Exception Nos. 1, 3, 4, or 5, shall consist of not more than six switches or
sets of circuit breakers, or a combination of not more than six switches and
sets of circuit breakers, mounted in a single enclosure, in a group of
separate enclosures, or in or on a switchboard. There shall be not more than
six sets of disconnects per service grouped in any one location.

March 20, 2012

Services

Only one service, unless

Fire pumps
Emergency systems
Legally required standby systems
Optional standby systems
Parallel power production systems
Systems designed for connection to
multiple sources of supply for the purpose of enhanced
reliability
Multiple-occupancy buildings
structure sufficiently large
in excess of 2000 amperes
Different Characteristics

not more than six disconnecting means

March 20, 2012

Services

Utility
Source

FIRE
PUMP

NEC 230.71(A) Maximum


Number of Disconnects
not more than six
switches
March 20, 2012

SIX HANDLE RULE

Power System
Configurations

Utility
Source

277/480V,
3PH, 4W

277/480V,
3PH, 4W

LARGE
MOTOR
LOADS

277/480V,
3PH, 4W

CLEAN
POWER
LOADS

Simple Radial
Distribution System
March 20, 2012

Power System
Configurations

Utility
Source A

NO

NC

Utility
Source B

277/480V,
3PH, 4W

Loop Utility Feed to a


Simple Radial
Distribution System
March 20, 2012

Power System
Configurations

Utility
Source A

NO

NC

Utility
Source B

277/480V,
3PH, 4W

Simple Radial
Distribution System
with Draw-Out
Switchgear
March 20, 2012

Power System
Configurations

Utility
Source

277/480V,
3PH, 4W

March 20, 2012

Distribution System
with Auxiliary
Generator

March 20, 2012

Power System
Configurations

Stand-By
Loads

March 20, 2012

Auxiliary
Generator

Critical
Loads

Utility
Source

Life Safety
Loads

Distribution System
with Separated Load
Types

Normal
Loads

Power System
Configurations

MAINT.
BY-PASS

Facilities Managers
need to be able to
completely isolate the
component to repair,
maintain or replace
while maintaining
power to the load.
March 20, 2012

Utility
Source

277/480V,
3PH, 4W

UPS
SYSTEM

UPS
SYSTEM

MAINTENANCE
BY-PASS FOR
CIRTICAL LOADS

MAINT.
BY-PASS

Power System
Configurations

Stand-By
Loads

Auxiliary
Generator

Critical
Loads

Utility
Source

Life Safety
Loads

Distribution System
with By-Pass
March 20, 2012

Normal
Loads

Power System Configurations


Utility
Source A

NC

NO
277/480V,
3PH, 4W

March 20, 2012

NC

NO

Utility
Source B

277/480V,
3PH, 4W

Loop Utility Feed to


Simple Radial
Distribution Systems

Power System Configurations


Utility
Source A

NC

NO

NO

277/480V,
3PH, 4W

277/480V,
3PH, 4W

NO
TIE
BREAKER

Distribution System
with Tie Breaker
March 20, 2012

NC

Utility
Source B

Power System Configurations


Utility
Source A

NC

NO

NO

277/480V,
3PH, 4W

277/480V,
3PH, 4W

NO

Double-Ended
Distribution System
March 20, 2012

NC

Utility
Source B

Power System Configurations


Utility
Source A

NC

NO

NO

NC

Utility
Source B

NO

Double-Ended Distribution
System with Parallel Generation

March 20, 2012

March 20, 2012

High School

March 20, 2012

High Rise Office Building

March 20, 2012

TV Broadcast NOC

March 20, 2012

HPC Data Center Primary Distribution

March 20, 2012

HPC Data Center UPS Distribution

Power System
Configurations

If there is only one


alternate path of power to
a critical load, be sure to
provide a manual
alternate path for
maintenance.

Utility
Source

277/480V,
3PH, 4W

100% UPS
SYSTEM

MAINT.
BY-PASS

UPS FOR CRITICAL


LOADS
March 20, 2012

Power System
Configurations

Utility
Source

277/480V,
3PH, 4W

100% UPS
SYSTEM

The second alternate


path of power to a critical
load provides an
alternate path for
maintenance.
March 20, 2012

100% UPS
SYSTEM

N+1 UPS FOR


CRITICAL LOADS

Utility
Source

Power System
Configurations

277/480V,
3PH, 4W

50% UPS
SYSTEM

50% UPS
SYSTEM

50% UPS
SYSTEM
1 OF 3 IS
STAND-BY

March 20, 2012

N+1 UPS FOR


CRITICAL LOADS

Power Quality Design


Subdistribution Design

CLEAN &
DIRTY
POWER
LOADS

CLEAN &
DIRTY
POWER
LOADS

[A] WORST!

March 20, 2012

CLEAN &
DIRTY
POWER
LOADS

CLEAN &
DIRTY
POWER
LOADS

[B] BAD!

DIRTY
POWER
LOADS

CLEAN
POWER
LOADS

[C] BEST!

Power Quality Design


System Design
Using Separation and Dedication
120/208V,
3PH, 4W

120/208V,
3PH, 4W

120/208V,
3PH, 4W

120/208V,
3PH, 4W

277/480V,
3PH, 4W

277/480V,
3PH, 4W

120/208V,
3PH, 4W

277/480V,
3PH, 4W

277/480V,
3PH, 4W

277/480V,
3PH, 4W

277/480V,
3PH, 4W

277/480V,
3PH, 4W

277/480V,
3PH, 4W

277/480V,
3PH, 4W

120/208V,
3PH, 4W

LARGE CLEAN
MOTOR POWER
LOADS LOADS

[A] WORST!

LARGE
MOTOR
LOADS

CLEAN
POWER
LOADS

[B] FAIR!

LARGE
MOTOR
LOADS

CLEAN
POWER
LOADS

[C] OKAY!

LARGE
MOTOR
LOADS

CLEAN
POWER
LOADS

[D] BETTER!

120/208V,
3PH, 4W

LARGE
MOTOR
LOADS

[E] BEST!

FIPS PUB 94 recommended separation of sensitive


equipment power distribution from support equipment
power distribution

March 20, 2012

CLEAN
POWER
LOADS

Electrical System Topology


Tier I
http://uptimeinstitute.com/

Tier I

No redundancy
Multiple single
points of failure
99.67 % availability
(28.8 hours down
time per year)

March 20, 2012

Electrical System Topology


Tier II
http://uptimeinstitute.com/

Tier II

Electrical
redundancy
required (N+1)
Multiple single
points of failure
99.75 %
availability
(22 hours down
time per year)

March 20, 2012

Electrical System Topology


Tier III
http://uptimeinstitute.com/

Tier III
(N+1)
No single
points of
failure
99.98 %
availability
(1.6 hours
down time
per year)

March 20, 2012

Electrical System Topology


Tier IV
http://uptimeinstitute.com/

Tier IV
2(N+1)
No single
points of
failure
99.99 %
availability
48 minutes
down time
per year

March 20, 2012

Tier I 99.67% Availability


29 hours down time per year
calculated 99.92%; 7 hr. per year*

http://uptimeinstitute.com/

Tier II 99.75% Availability


22 hours down time per year
calculated 99.998%; 11 min. per year*

Tier III 99.98% Availability


(1.6 hours down time per year)
calculated 99.9999%; 32 sec. per year*

Tier IV 99.99% Availability


(48 minutes down time per year)
calculated 99.9999%; 29 sec. per year*

* Stephen Fairfax, MTechnology; Quantitative Reliability Analysis of Tier Like


Data Center Topologies, Nov. 16, 2010; 2010 Fall Conference of the
7x24Exchange International
March 20, 2012

System Coordination

Type of gear
Type of OCPs
Coordination
Fault bracing

March 20, 2012

Coordination

March 20, 2012

Coordination:
Breakers
coordinate
well in short
and long time
scales
Breakers do
not
coordinate
well in
instantaneous
scale

Coordination:
Fuses
coordinate
well in short
and long time
scales
Fuses
coordinate
well in
instantaneous
scale
March 20, 2012

Voltage Drop and


Distance Limitations

NEC 210.19(A)(1) Info Note 4


3% for branch circuits

NEC 215.2(A)(3) Info Note 2


2% for feeders

March 20, 2012

Maximum 5% voltage drop

Voltage Drop

Load
Power Factor
Distance
Voltage
Copper/Aluminum Conductor
Metallic vs. Non-Metallic Raceway
Approximate:

Evd= IR cos + IX sin

Exact Method:

March 20, 2012

Evd= Es + IR cos + IX sin SQRT(Es2+ (IX cos + IR sin)2)

Voltage Drop
Exact Method:
Evd= Es + IR cos + IX sin - SQRT(Es2+ (IX cos + IR sin)2)

March 20, 2012

Voltage Drop

The reality of 80% loaded circuits:


120v 20A2G: 65 ft max (3%vd)
120v 30A2G: 70 ft max (3%vd)
208v 20A2G: 110 ft max (3%vd)
208v 20A4G: 130 ft max (3%vd)
277v 20A2G: 185 ft max (3%vd)
480v 400A4G: 360 ft max (2%vd)
480v 1000A4G: 370 ft max (2%vd)
600v 1000A4G: 460 ft max (2%vd)
4160v 1000A4G: 3300 ft max (2%vd)

March 20, 2012

Voltage Drop
Rules of thumb:
Feeder Circuits
100 ft max for 208 volt 3 ph (2%vd)
300 ft max for 480 volt 3 ph (2%vd)
Branch Circuits:
70 ft max for 120 volt 1 ph (3%vd)
120 ft max for 208 volt (3%vd)
200 ft max for 277 volt (3%vd)
400 ft max for 480 volt (3%vd)

March 20, 2012

Ground Fault Protection

NEC 230.95
>150 volts to ground
1000 amps and higher

March 20, 2012

Determining the Load

Amperage and kVA Limitations


Bus and Feeder Sizes
Common Loads
Load Densities
Load Estimating
Examples

March 20, 2012

Amperage and kVA


Limitation Guidelines

3000 amps and larger


Consider the effects of a large scale outage
Costs of switchgear at this size is greater

>1500 kVA service


Excessive short circuit > 65kAIC
Excessive amperage: >2000 amps

>75 kVA transformer


Excessive short circuit > 9kAIC
Excessive amperage: >225 amps

March 20, 2012

Bus and Feeder Sizes

Plan for the future


Full size bus
Full size feeders
Full size neutral

March 20, 2012

Design Guide Loads

Common Loads
Equipment loads

March 20, 2012

Kitchen Loads
Load Densities

Load Estimating

Load Analysis Worksheet


Building Floor Plan
Building Areas
Load Densities
Point Loads

Floor Totals
Building Totals

March 20, 2012

High Rise Office Building


Example

Load Analysis
Typical floor plate
Preliminary
One-Line
Final One-Line

March 20, 2012

Basic Floor Plan


120 feet

70 feet

250 feet
18,500 square feet

Examine proportions and distances


Determine area of major spaces and rooms
March 20, 2012

Load
Estimating
Detailed Loads Per Area

Area Loads

Point Loads

March 20, 2012

Load
Estimating

March 20, 2012

Summary Loads
Per Area

Basic Floor Plan


120 feet

70 feet

250 feet
18,500 square feet

Avoid mechanical rooms and chases, elevator shafts and egress stairs
Consider panel placement for optimal circuit conductor length and size
March 20, 2012

Load Estimating

March 20, 2012

Detailed Loads
Per Area

HVAC Loads

Load
Estimating
March 20, 2012

Elevator Loads

Load
Estimating
March 20, 2012

Summary Sheet

Load
Estimating
March 20, 2012

March 20, 2012

March 20, 2012

Success
Story:
Valor
Christian
High
School

Load
Estimating
March 20, 2012

One that did


not work so
well:
Cordera K8

Load
Estimating
March 20, 2012

Load Estimating

SDs: Load Analysis


Worksheet
DDs: Load Analysis
Worksheet but include
mechanical point loads
65% CDs: Load Analysis Worksheet
but include all point loads
CDs: Actual panel schedule loads
plus all point loads

March 20, 2012

Residential Load Calculations

March 20, 2012

Residential
Load
Calculations

March 20, 2012

March 20, 2012

System Layout

Service Location
Utility requirements
Access and egress

March 20, 2012

Feeder lengths
Branch circuit lengths
Major load locations
Distribution equipment locations
Panel locations
Future expansion

System
Layout

Utility
Source
DIST

DIST
MAXIMUM
300 FEET
MDP

DIST

MAXIMUM
70 FEET

DIST

DIST

DIST
DIST

In an Ideal World
March 20, 2012

March 20, 2012

The Reality

March 20, 2012

Power Quality Design


Summary of IEEE Recommended Guidelines

Voltage sags or swells


Separation of load types

Separation/Dedication/
Location/Isolation
Harmonic Canceling
Transformers

Connect large loads nearest


utility source

Transient Overvoltages
Lightning protection system

200% neutrals

Ground ring

Proper grounding and


bonding

SPD
Separation/Dedication/
Location/Isolation

Harmonics

Power Outages
UPSs & generators

Ground Faults
Relay coordination
March 20, 2012

12 & 18 pulse drives

EMF/RFI
SPDs
Separation/Location

Power Quality Design


Recommendations by The RMH Group, Inc.

Design electrical distribution system per IEEE recommended guidelines.

Use an outside copper ground ring and multiple ground electrodes to


achieve lowest practical resistance to ground, and to redirect earth
currents. The grounding electrode system must have a resistance no
greater than 10 ohms, 2 ohms in installations that contain many
computers and other sensitive electronic equipment. All systems must be
properly bonded to the common grounding electrode system. Bond
electrode to ground ring in only one location.

Separate the large motor loads from sensitive loads at the main service or
provide separate service altogether.

Use lightning protection per NFPA 780. Place SPDs at main service,
secondary distribution and branch panelboards feeding sensitive loads.
Progressively reduce SPD clamping voltages from the service to the
panelboard.
March 20, 2012

Power Quality Design


Recommendations by The RMH Group, Inc.

Segregate outlets that serve computer equipment from those


used for general service. Segregate sensitive loads on separate
branch circuits, fed from separate panelboards, fed from
separate feeders and separate transformers.

Specify 200% neutrals in three-phase feeders to nonlinear-load


branch panelboards. Use separate full-sized neutrals for each
phase leg in branch circuits feeding sensitive equipment.

Use a separate copper grounding conductor (green wire) for


each circuit. Follow recommendations spelled out in IEEE 1100
and TIA/EIA 607.

March 20, 2012

Power Quality Design


Recommendations by The RMH Group, Inc.

Use RMS sensing feeder breakers, panelboards designed for


non-linear loads (200% neutral, dedicated ground), and highefficiency phase-shifting harmonic-canceling transformers
for panels serving high harmonic loads. Locate transformers
as close to the load as possible. Keep branch circuits short
(70 ft., or less).

Install no more than four to six outlets per branch circuit in


those circuits that serve computers and other sensitive
electronic equipment.

Specify 12 or 18 pulse Adjustable Speed Drives and soft


starts.

March 20, 2012

Power Quality Design


Comparison using Academic Office West
277/480V,
3PH, 4W
Bus Riser

277/480V,
3PH, 4W
Bus Riser

K-Rated 112.5 kVA


Drytype
120/208V, 3PH, 4W
Combined Loads in
2-Section Panel,
separate circuits for
clean loads

[A] Combined Loads with


K-Rated Dry Type

March 20, 2012

Standard 75 kVA
Drytype
120/208V, 3PH, 4W
Dirty
Power
Loads

45 kVA Harmonic
Canceling, with Phase Shift
120/208V, 3PH, 4W
Clean
Power
Loads

[B] Combined Dry Type and


Harmonic Canceling

What
Does
All
This
Cost?

Power Quality Design


Comparison using
Academic Office West
3PH, 4W

Bus Riser

K-Rated
112.5112.5
kVA kVA
K-Rated
Drytype
Drytype
120/208V,
3PH,3PH,
4W 4W
120/208V,

Combined
Loads
in in
Combined
Loads
2-Section
Panel,
2-Section
Panel,
separate
circuits
for for
separate
circuits
cleanclean
loadsloads

March 20, 2012

[A] Combined Loads with


K-Rated Dry Type

277/480V,

Costs

200 A Bus Plug


175 A Primary Feeder
112.5 K-Rated Transformer
350 A Secondary Feeder
2-Section 400 A Panelboard

$17,128 per assembly


including OH&P
$308,340 for nine floors, 2-locations

Power Quality Design


Comparison using
Academic Office West

Dirty
Power
Loads

45 kVA Harmonic
Canceling, with Phase Shift
120/208V, 3PH, 4W
Clean
Power
Loads

[B] Combined Dry Type and


Harmonic Canceling

March 20, 2012

[B] Combined Dry Type and


Harmonic Canceling

277/480V,
3PH, 4W
Bus Riser

Standard 75 kVA
Drytype
120/208V, 3PH, 4W

Costs

200 A & 100A Bus Plugs


125 A & 70 A Primary Feeders
75 kVA Drytype
45 kVA Harmonic Canceling
225 A & 150 A
Secondary Feeders
225 A Panelboard
225 A 200%N, IG Panelboard

$21,922 per assembly


including OH&P
$394,597 for nine floors, 2-locations

Power Quality Design

Costs

Comparison using Academic Office West


[A] Combined Loads with
K-Rated Dry Type

[B] Combined Dry Type and


Harmonic Canceling

$17,130 for one floor, 1-location


$308,340 for nine floors, 2-locations

$21,900 for one floor, 1-location


$394,200 for nine floors, 2-locations

There is about an $86,000 premium for the Power


Quality Upgrade.
Given a total Electrical Project cost of $3,500,000
this results in a 2.5% increase in cost.
Given a total Project cost of $29,000,000 this results
in a 0.3% increase in cost.
March 20, 2012

Power Quality Design

Costs

Comparison using Academic Office West


Combined Dry Type and Harmonic
Canceling
$86,000
Lightning Protection
$27,930
Ground ring
$18,530
Lightning arrestor at service entry
$4,320
SPD at service and branch panels
$83,590

March 20, 2012

There is about an
$220,300 premium for all
the Power Quality
Upgrades.
Given a total Electrical
Project cost of
$3,500,000 this results in
a 6.3% increase in cost.
Given a total Project cost
of $29,000,000 this
results in a 0.8% increase
in cost.

Putting it all Together


What does all this Power Quality buy?
Combined Dry Type and Harmonic
Canceling ($86,000)
Longer equipment life
Less lost time and data due to
computer malfunctions
Lower labor costs for
maintenance and repairs
ROI of 2 to 4 years for xfmrs
Lower energy bills
for life of building

Lightning arrestor at service


entry ($4,320)
Less damage to expensive
equipment

SPD at service and branch


panels ($83,600)
Longer equipment life
Less damage to expensive
equipment
Less lost time due to
Lightning Protection & Ground Ring
computer malfunctions
($46,460)
Lower labor costs for
Life Safety
maintenance
Less damage to expensive
equipment

March 20, 2012

Putting it all Together


What is the ROI on all this Power Quality?

Combined Dry Type and Harmonic


Lightning arrestor at service entry
Canceling ($86,000)
($4,320)
At $0.07/kWHr
less damage to expensive
ROI of 2.4 to 3.9 years for xfmrs
equipment (at $5,000 per
Lower energy bills ($16,400/yr.)
computer, saving 1 computer
for life of building ($820,000/50yr.)
pays for investment)
Lightning Protection & Ground Ring
($46,460)
Life Safety (priceless)
less damage to expensive
equipment (at $5,000 per
computer, saving 10 computers
pays for investment)
March 20, 2012

SPD at service and branch panels


($83,600)
longer equipment life
less damage to expensive
equipment (at $5,000 per
computer, saving 17 computers
pays for investment)

Questions and Answers


March 20, 2012

ELECTRICAL LOAD DENSITIES WORKSHEET


Project Name:
For:
12600 West Colfax Ave., Suite A-400

ELECTRICAL LOAD DENSITIES


[ ]

By: Max D. Billington, P.E.

Lakewood, Colorado 80215

Job No.: [ ]

Comments: [ ]

(303) 239-0909/FAX (303) 239-8913

10:32 AM
March 16, 2012

[]

Information on this document is presented for information only and is intended for use by design professionals under the supervision of a registered
professional engineer. The user must make careful investigation as to its application.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60

Building
Type
High Rise
Low Rise

Lighting
W/SF

Devices
W/SF

HVAC
W/SF

2.2
2.0
1.0
1.0
1.0

3.0
3.0
4.5
3.5
15.0

Apartment
Apartment
Art Gallery
Auditorium
Auditorium

General
Stage

0.7
0.7
1.1
1.8
1.6

Bank
Bank

Branch
Main

1.5
1.5

2.1
1.5

5.7
5.7

Cafeteria
Church
Evang.
Church
High
College
Library
College
Phys Ed
College
Science B
Computer
Data Center
Correctional Facility
Corridors
Courthouse

1.4
1.3
1.3
1.3
1.4
1.2
1.2
1.0
0.9
1.2

0.5
1.1
0.8
0.8
1.0
3.0
1.2
3.4
0.3
2.5

6.8
3.7
3.3
5.7
4.5
5.3
10.0
7.8

Dept Store
Dept Store
Dept Store
Dept Store
Donut Shop
Dormitory
Dwelling
Dwelling
Dwelling

Basement
Main Floor
Upper Floor
Drive In
College
0-3000 SF
3K-120K SF
> 120K SF

1.5
1.5
1.5
1.5
1.5
1.0
1.0
0.7
0.7

0.9
1.5
1.0
1.0
4.0
1.2
0.5
0.3
0.2

4.0
3.5
6.0
4.5
6.8
4.0

Garage

Commercial

0.9

0.5

Lobby
Rooms
Elderly

1.2
1.2
1.2
1.0
1.0
1.0
1.0

4.5
4.5
3.8
1.0
0.5
0.5
1.2

Building

1.4

Laboratories
Library

Appliances
W/SF

Heat
W/SF

Computer
W/SF

1.6
1.4

Other
W/SF

Total
W/SF

1.0
1.0
1.0
0.8
0.5

6.9
6.7
7.6
7.1
18.1

1.4
1.4

12.3
11.5

4.0
1.0
0.8
1.4
1.1
1.3
2.2
1.2

0.5

0.6

12.7
7.1
6.2
9.7
8.0
12.4
26.6
14.7
1.2
12.5

1.0
0.5
0.5
0.5

1.0
1.0
1.0
1.0
1.7
1.0
1.0
0.5
0.5

8.4
8.0
10.0
8.5
14.0
7.2
2.5
5.0
4.4

0.5

1.9

5.0
5.0
5.0
5.0
6.0
5.0
4.0

1.0
1.3
1.3
1.3
1.0
0.5
1.0

11.7
12.0
11.3
8.3
8.5
7.0
7.2

2.0

4.5

1.0

8.9

1.2
1.3

5.0
1.0

6.0
5.5

0.5
0.5

14.7
8.3

Mall Shops
Manufacturin Apparel
Manufacturin Food
Manufacturin Tools
Medical
Clinic
Medical
Center
Motel

1.5
1.3
1.3
1.3
1.0
1.0
1.0

0.5
1.0
1.0
1.0
1.5
2.0
0.5

4.5
4.5
4.5
4.5
3.2
4.0
3.2

1.0
1.1
1.1
1.1
1.0
0.5

7.5
7.9
7.9
7.9
7.2
7.5
5.2

Nursing Home

1.0

1.6

4.0

1.0

7.6

Office Bldg
Office Bldg High Rise
Office Bldg High Tech

1.0
1.0
1.0

1.9
2.0
2.3

5.3
4.7
6.5

1.2
1.2
1.0

11.9
10.6
15.8

Hospital
Hospital
Hospital
Hotel
Hotel
Hotel
Housing
Industrial

General
Pediatric

0.5
1.6
12.0
1.2

7.3

0.1
0.4

3.5
3.0

2.0

0.5
0.5

0.7

0.05

1.7
1.7
5.0

LoadDensities-V_0312.xls

ELECTRICAL LOAD DENSITIES WORKSHEET


Project Name:
For:
12600 West Colfax Ave., Suite A-400

ELECTRICAL LOAD DENSITIES


[ ]

By: Max D. Billington, P.E.

Lakewood, Colorado 80215

Job No.: [ ]

Comments: [ ]

(303) 239-0909/FAX (303) 239-8913

10:32 AM
March 16, 2012

[]

Information on this document is presented for information only and is intended for use by design professionals under the supervision of a registered
professional engineer. The user must make careful investigation as to its application.
1
2
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84

Building
Type

Lighting
W/SF

Devices
W/SF

HVAC
W/SF

Radio-TV
Studio
Restaurant Dining
Restaurant Fast Food
Retail Store

1.6
1.3
1.4
1.5

2.2
0.3
2.0
0.9

7.6
6.0
6.8
5.5

School
Elementary
School
Junior High
School
Senior High
Shops, Corner
Storage
Spaces
Store
Jewelry
Supermarket

1.2
1.2
1.2
1.5
0.8
1.5
1.5

1.7
1.6
1.5
1.0
0.5
0.5
1.0

6.1
5.3
4.6
4.0
1.0
8.5
4.0

Telephone
Theater
Town Hall

1.0
1.2
1.1

0.6
1.0
1.9

4.5
3.3
5.3

1.1
0.8
0.8

2.0
0.6
0.3

5.0
0.0
0.0

Exchange

US Post Office
Warehouse Grocery
Warehouse Storage

I:\RMH Electrical Standards\V_1107 Standard Schedules\[LoadDensities-V_0312.xls]calcsht

Appliances
W/SF

1.81
0.7
0.9

Heat
W/SF

1
0.2
0.1

Computer
W/SF

0.6
0.5

2.0

Other
W/SF

Total
W/SF

1.9
0.5
1.7
1.4

13.3
8.1
11.9
9.3

0.9
0.6
1.3
0.5
0.5
1.0
1.0

12.8
10.1
10.2
7.0
2.8
11.5
7.5

1.1
0.8
1.3

9.2
6.3
9.6

1.3
0.5
0.5

9.4
1.9
1.6

Version 1107

LoadDensities-V_0312.xls

You might also like