Professional Documents
Culture Documents
By
Goals
Safety
Sustainability
Project Specific Parameters
Properly Sized for the Load
Minimum Initial Investment
Maximum Service Continuity
Maximum Flexibility and
Expandability
Maximum Power Quality
Maximum Electrical Efficiency
Minimum Operating Costs
Minimum Maintenance Cost
Safety
Fundamental Canon of
Professional Engineering:
Safety
State of Colorado Title 12
Professions and Occupations
Article 25 - Engineers and Surveyors
12-25-101. General Provisions
Configuration of the
Distribution System
System Reliability
System Reliability
According to recent presentation by
Steve Fairfax of MTechnology:
Design Progression
Project Specific
Parameters
Motor Protection
Elevation
Temperature
Power quality
Motor starting
Specific Equipment
Protection
Voltage Selection
600Y/346
Voltage Selection
Voltage Selection
Voltage drop
Load
Distance
Size and location of utilization equipment
Cost
Less than 1000 amps 120/208 or 120/240
More than 1000 amps 277/480
More than 4000 amps 277/480 or 346/600
Services
Fire pumps
Emergency systems
Legally required standby systems
Optional standby systems
Parallel power production systems
Systems designed for connection to
multiple sources of supply for the purpose of enhanced
reliability
Multiple-occupancy buildings
structure sufficiently large
in excess of 2000 amperes
Different Characteristics
Services
Utility
Source
FIRE
PUMP
Power System
Configurations
Utility
Source
277/480V,
3PH, 4W
277/480V,
3PH, 4W
LARGE
MOTOR
LOADS
277/480V,
3PH, 4W
CLEAN
POWER
LOADS
Simple Radial
Distribution System
March 20, 2012
Power System
Configurations
Utility
Source A
NO
NC
Utility
Source B
277/480V,
3PH, 4W
Power System
Configurations
Utility
Source A
NO
NC
Utility
Source B
277/480V,
3PH, 4W
Simple Radial
Distribution System
with Draw-Out
Switchgear
March 20, 2012
Power System
Configurations
Utility
Source
277/480V,
3PH, 4W
Distribution System
with Auxiliary
Generator
Power System
Configurations
Stand-By
Loads
Auxiliary
Generator
Critical
Loads
Utility
Source
Life Safety
Loads
Distribution System
with Separated Load
Types
Normal
Loads
Power System
Configurations
MAINT.
BY-PASS
Facilities Managers
need to be able to
completely isolate the
component to repair,
maintain or replace
while maintaining
power to the load.
March 20, 2012
Utility
Source
277/480V,
3PH, 4W
UPS
SYSTEM
UPS
SYSTEM
MAINTENANCE
BY-PASS FOR
CIRTICAL LOADS
MAINT.
BY-PASS
Power System
Configurations
Stand-By
Loads
Auxiliary
Generator
Critical
Loads
Utility
Source
Life Safety
Loads
Distribution System
with By-Pass
March 20, 2012
Normal
Loads
NC
NO
277/480V,
3PH, 4W
NC
NO
Utility
Source B
277/480V,
3PH, 4W
NC
NO
NO
277/480V,
3PH, 4W
277/480V,
3PH, 4W
NO
TIE
BREAKER
Distribution System
with Tie Breaker
March 20, 2012
NC
Utility
Source B
NC
NO
NO
277/480V,
3PH, 4W
277/480V,
3PH, 4W
NO
Double-Ended
Distribution System
March 20, 2012
NC
Utility
Source B
NC
NO
NO
NC
Utility
Source B
NO
Double-Ended Distribution
System with Parallel Generation
High School
TV Broadcast NOC
Power System
Configurations
Utility
Source
277/480V,
3PH, 4W
100% UPS
SYSTEM
MAINT.
BY-PASS
Power System
Configurations
Utility
Source
277/480V,
3PH, 4W
100% UPS
SYSTEM
100% UPS
SYSTEM
Utility
Source
Power System
Configurations
277/480V,
3PH, 4W
50% UPS
SYSTEM
50% UPS
SYSTEM
50% UPS
SYSTEM
1 OF 3 IS
STAND-BY
CLEAN &
DIRTY
POWER
LOADS
CLEAN &
DIRTY
POWER
LOADS
[A] WORST!
CLEAN &
DIRTY
POWER
LOADS
CLEAN &
DIRTY
POWER
LOADS
[B] BAD!
DIRTY
POWER
LOADS
CLEAN
POWER
LOADS
[C] BEST!
120/208V,
3PH, 4W
120/208V,
3PH, 4W
120/208V,
3PH, 4W
277/480V,
3PH, 4W
277/480V,
3PH, 4W
120/208V,
3PH, 4W
277/480V,
3PH, 4W
277/480V,
3PH, 4W
277/480V,
3PH, 4W
277/480V,
3PH, 4W
277/480V,
3PH, 4W
277/480V,
3PH, 4W
277/480V,
3PH, 4W
120/208V,
3PH, 4W
LARGE CLEAN
MOTOR POWER
LOADS LOADS
[A] WORST!
LARGE
MOTOR
LOADS
CLEAN
POWER
LOADS
[B] FAIR!
LARGE
MOTOR
LOADS
CLEAN
POWER
LOADS
[C] OKAY!
LARGE
MOTOR
LOADS
CLEAN
POWER
LOADS
[D] BETTER!
120/208V,
3PH, 4W
LARGE
MOTOR
LOADS
[E] BEST!
CLEAN
POWER
LOADS
Tier I
No redundancy
Multiple single
points of failure
99.67 % availability
(28.8 hours down
time per year)
Tier II
Electrical
redundancy
required (N+1)
Multiple single
points of failure
99.75 %
availability
(22 hours down
time per year)
Tier III
(N+1)
No single
points of
failure
99.98 %
availability
(1.6 hours
down time
per year)
Tier IV
2(N+1)
No single
points of
failure
99.99 %
availability
48 minutes
down time
per year
http://uptimeinstitute.com/
System Coordination
Type of gear
Type of OCPs
Coordination
Fault bracing
Coordination
Coordination:
Breakers
coordinate
well in short
and long time
scales
Breakers do
not
coordinate
well in
instantaneous
scale
Coordination:
Fuses
coordinate
well in short
and long time
scales
Fuses
coordinate
well in
instantaneous
scale
March 20, 2012
Voltage Drop
Load
Power Factor
Distance
Voltage
Copper/Aluminum Conductor
Metallic vs. Non-Metallic Raceway
Approximate:
Exact Method:
Voltage Drop
Exact Method:
Evd= Es + IR cos + IX sin - SQRT(Es2+ (IX cos + IR sin)2)
Voltage Drop
Voltage Drop
Rules of thumb:
Feeder Circuits
100 ft max for 208 volt 3 ph (2%vd)
300 ft max for 480 volt 3 ph (2%vd)
Branch Circuits:
70 ft max for 120 volt 1 ph (3%vd)
120 ft max for 208 volt (3%vd)
200 ft max for 277 volt (3%vd)
400 ft max for 480 volt (3%vd)
NEC 230.95
>150 volts to ground
1000 amps and higher
Common Loads
Equipment loads
Kitchen Loads
Load Densities
Load Estimating
Floor Totals
Building Totals
Load Analysis
Typical floor plate
Preliminary
One-Line
Final One-Line
70 feet
250 feet
18,500 square feet
Load
Estimating
Detailed Loads Per Area
Area Loads
Point Loads
Load
Estimating
Summary Loads
Per Area
70 feet
250 feet
18,500 square feet
Avoid mechanical rooms and chases, elevator shafts and egress stairs
Consider panel placement for optimal circuit conductor length and size
March 20, 2012
Load Estimating
Detailed Loads
Per Area
HVAC Loads
Load
Estimating
March 20, 2012
Elevator Loads
Load
Estimating
March 20, 2012
Summary Sheet
Load
Estimating
March 20, 2012
Success
Story:
Valor
Christian
High
School
Load
Estimating
March 20, 2012
Load
Estimating
March 20, 2012
Load Estimating
Residential
Load
Calculations
System Layout
Service Location
Utility requirements
Access and egress
Feeder lengths
Branch circuit lengths
Major load locations
Distribution equipment locations
Panel locations
Future expansion
System
Layout
Utility
Source
DIST
DIST
MAXIMUM
300 FEET
MDP
DIST
MAXIMUM
70 FEET
DIST
DIST
DIST
DIST
In an Ideal World
March 20, 2012
The Reality
Separation/Dedication/
Location/Isolation
Harmonic Canceling
Transformers
Transient Overvoltages
Lightning protection system
200% neutrals
Ground ring
SPD
Separation/Dedication/
Location/Isolation
Harmonics
Power Outages
UPSs & generators
Ground Faults
Relay coordination
March 20, 2012
EMF/RFI
SPDs
Separation/Location
Separate the large motor loads from sensitive loads at the main service or
provide separate service altogether.
Use lightning protection per NFPA 780. Place SPDs at main service,
secondary distribution and branch panelboards feeding sensitive loads.
Progressively reduce SPD clamping voltages from the service to the
panelboard.
March 20, 2012
277/480V,
3PH, 4W
Bus Riser
Standard 75 kVA
Drytype
120/208V, 3PH, 4W
Dirty
Power
Loads
45 kVA Harmonic
Canceling, with Phase Shift
120/208V, 3PH, 4W
Clean
Power
Loads
What
Does
All
This
Cost?
Bus Riser
K-Rated
112.5112.5
kVA kVA
K-Rated
Drytype
Drytype
120/208V,
3PH,3PH,
4W 4W
120/208V,
Combined
Loads
in in
Combined
Loads
2-Section
Panel,
2-Section
Panel,
separate
circuits
for for
separate
circuits
cleanclean
loadsloads
277/480V,
Costs
Dirty
Power
Loads
45 kVA Harmonic
Canceling, with Phase Shift
120/208V, 3PH, 4W
Clean
Power
Loads
277/480V,
3PH, 4W
Bus Riser
Standard 75 kVA
Drytype
120/208V, 3PH, 4W
Costs
Costs
Costs
There is about an
$220,300 premium for all
the Power Quality
Upgrades.
Given a total Electrical
Project cost of
$3,500,000 this results in
a 6.3% increase in cost.
Given a total Project cost
of $29,000,000 this
results in a 0.8% increase
in cost.
Job No.: [ ]
Comments: [ ]
10:32 AM
March 16, 2012
[]
Information on this document is presented for information only and is intended for use by design professionals under the supervision of a registered
professional engineer. The user must make careful investigation as to its application.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
Building
Type
High Rise
Low Rise
Lighting
W/SF
Devices
W/SF
HVAC
W/SF
2.2
2.0
1.0
1.0
1.0
3.0
3.0
4.5
3.5
15.0
Apartment
Apartment
Art Gallery
Auditorium
Auditorium
General
Stage
0.7
0.7
1.1
1.8
1.6
Bank
Bank
Branch
Main
1.5
1.5
2.1
1.5
5.7
5.7
Cafeteria
Church
Evang.
Church
High
College
Library
College
Phys Ed
College
Science B
Computer
Data Center
Correctional Facility
Corridors
Courthouse
1.4
1.3
1.3
1.3
1.4
1.2
1.2
1.0
0.9
1.2
0.5
1.1
0.8
0.8
1.0
3.0
1.2
3.4
0.3
2.5
6.8
3.7
3.3
5.7
4.5
5.3
10.0
7.8
Dept Store
Dept Store
Dept Store
Dept Store
Donut Shop
Dormitory
Dwelling
Dwelling
Dwelling
Basement
Main Floor
Upper Floor
Drive In
College
0-3000 SF
3K-120K SF
> 120K SF
1.5
1.5
1.5
1.5
1.5
1.0
1.0
0.7
0.7
0.9
1.5
1.0
1.0
4.0
1.2
0.5
0.3
0.2
4.0
3.5
6.0
4.5
6.8
4.0
Garage
Commercial
0.9
0.5
Lobby
Rooms
Elderly
1.2
1.2
1.2
1.0
1.0
1.0
1.0
4.5
4.5
3.8
1.0
0.5
0.5
1.2
Building
1.4
Laboratories
Library
Appliances
W/SF
Heat
W/SF
Computer
W/SF
1.6
1.4
Other
W/SF
Total
W/SF
1.0
1.0
1.0
0.8
0.5
6.9
6.7
7.6
7.1
18.1
1.4
1.4
12.3
11.5
4.0
1.0
0.8
1.4
1.1
1.3
2.2
1.2
0.5
0.6
12.7
7.1
6.2
9.7
8.0
12.4
26.6
14.7
1.2
12.5
1.0
0.5
0.5
0.5
1.0
1.0
1.0
1.0
1.7
1.0
1.0
0.5
0.5
8.4
8.0
10.0
8.5
14.0
7.2
2.5
5.0
4.4
0.5
1.9
5.0
5.0
5.0
5.0
6.0
5.0
4.0
1.0
1.3
1.3
1.3
1.0
0.5
1.0
11.7
12.0
11.3
8.3
8.5
7.0
7.2
2.0
4.5
1.0
8.9
1.2
1.3
5.0
1.0
6.0
5.5
0.5
0.5
14.7
8.3
Mall Shops
Manufacturin Apparel
Manufacturin Food
Manufacturin Tools
Medical
Clinic
Medical
Center
Motel
1.5
1.3
1.3
1.3
1.0
1.0
1.0
0.5
1.0
1.0
1.0
1.5
2.0
0.5
4.5
4.5
4.5
4.5
3.2
4.0
3.2
1.0
1.1
1.1
1.1
1.0
0.5
7.5
7.9
7.9
7.9
7.2
7.5
5.2
Nursing Home
1.0
1.6
4.0
1.0
7.6
Office Bldg
Office Bldg High Rise
Office Bldg High Tech
1.0
1.0
1.0
1.9
2.0
2.3
5.3
4.7
6.5
1.2
1.2
1.0
11.9
10.6
15.8
Hospital
Hospital
Hospital
Hotel
Hotel
Hotel
Housing
Industrial
General
Pediatric
0.5
1.6
12.0
1.2
7.3
0.1
0.4
3.5
3.0
2.0
0.5
0.5
0.7
0.05
1.7
1.7
5.0
LoadDensities-V_0312.xls
Job No.: [ ]
Comments: [ ]
10:32 AM
March 16, 2012
[]
Information on this document is presented for information only and is intended for use by design professionals under the supervision of a registered
professional engineer. The user must make careful investigation as to its application.
1
2
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
Building
Type
Lighting
W/SF
Devices
W/SF
HVAC
W/SF
Radio-TV
Studio
Restaurant Dining
Restaurant Fast Food
Retail Store
1.6
1.3
1.4
1.5
2.2
0.3
2.0
0.9
7.6
6.0
6.8
5.5
School
Elementary
School
Junior High
School
Senior High
Shops, Corner
Storage
Spaces
Store
Jewelry
Supermarket
1.2
1.2
1.2
1.5
0.8
1.5
1.5
1.7
1.6
1.5
1.0
0.5
0.5
1.0
6.1
5.3
4.6
4.0
1.0
8.5
4.0
Telephone
Theater
Town Hall
1.0
1.2
1.1
0.6
1.0
1.9
4.5
3.3
5.3
1.1
0.8
0.8
2.0
0.6
0.3
5.0
0.0
0.0
Exchange
US Post Office
Warehouse Grocery
Warehouse Storage
Appliances
W/SF
1.81
0.7
0.9
Heat
W/SF
1
0.2
0.1
Computer
W/SF
0.6
0.5
2.0
Other
W/SF
Total
W/SF
1.9
0.5
1.7
1.4
13.3
8.1
11.9
9.3
0.9
0.6
1.3
0.5
0.5
1.0
1.0
12.8
10.1
10.2
7.0
2.8
11.5
7.5
1.1
0.8
1.3
9.2
6.3
9.6
1.3
0.5
0.5
9.4
1.9
1.6
Version 1107
LoadDensities-V_0312.xls