Professional Documents
Culture Documents
[IDP A ]
OPTION 1 :
Installation of Coal fired Boiler generating saturated steam at
20 bar pressure and supplying to the Plant directly. Feed
water at 90 deg C is supplied to the Boiler. Boiler efficiency
based on GCV is 81%. GCV of coal used is 5000 kcal/kg. Cost
of Coal is Rs 5200/Mt. Capital cost of this boiler is Rs 10
crores.
OPTION 2 :
Installation of a Coal fired Boiler generating High Pressure
superheated steam passing through an Extraction Turbine at
20 bar back pressure . Extracted 20 bar steam after
desuperheating with 110 deg C water to meet plant
requirement of 30 Mt/hr, saturated steam. Extraction Turbine
with an Isentropic efficiency of 55% will generate electric
power to be used by plant. For estimation of power saving, Rs
8/kwh can be assumed with 330 operating days in a year. For
estimation of power generation, it is not necessary to
consider additional losses, inorder to have uniformity in
results. Boiler feed water at 90 deg C is supplied to the
Boiler . Boiler efficiency based on GCV is 81%. GCV of coal
used is 5000 kcal/kg. Cost of Coal is Rs 5200/Mt.
ASSIGNMENT :
To do a comparative study of the two options and finally
conclude which option is more economically viable. To
suggest the optimum pressure/superheat of steam from
boiler in the option you found economic in order to get
maximum return on investment.
FACTS GIVEN:
Incremental Capital Cost for High Pressure Boiler for every 10
bar added pressure will be Rs 100 lacs (can be extrapolated
linearly). It can be assumed that variation in superheat will
not affect capital cost. Maximum allowable boiler pressure
and superheat will be 65 bar and 500 deg C respectively.
Capital cost of turbine handling 65 bar inlet pr / 20 bar outlet
pr / 30 mt / hr can be taken as 3 crore . Capital cost of turbine
handling 35 bar inlet pr / 20 bar outlet pr / 30 mt / hr can be
taken as 1.75 crore . Costs at pressures in between 35 to 65
can be linearly extrapolated . Cost below 35 bar pr will not
change. Pressure figures are in bar absolute. For the purpose
of this assignment, only cost of coal consumption to be
considered as variable cost. Other costs can be ignored.
SOLUTION : (option 1 )
BASIC BLOCK DIAGRAM
30 MT/hr SATURATED
STEAM
FEED
WATER
COAL FIRED
BOILER
T = 90C
P = 20 bar
Hf = 376.993
KJ/kg
TS =212.417C
Hg =2798.75
KJ/kg
Given Data :
Boiler efficiency = 81%
GCV of coal =5000 Kcal/kg =20929 KJ/kg
Cost of coal = Rs 5200/MT
Capital cost of the boiler = Rs 10 crores
eff =
ms (H g H f )
m c GCV
0.81 =
30 1000(2798.75376.993)
mc 20929
SOLUTION :
(OPTION 2 )
Case 1:
Abstract
In this case we have a high pressure boiler which produces
steam at a pressure higher than 20 bar. The saturated steam
is then sent to the superheater where it is superheated to a
temperature where its entropy is the same as the entropy of
the steam at the exit of the turbine which we have fixed as
220C i.e. a bit higher than the saturated temperature of the
steam at 20bar i.e. 212.42C. Then the superheated steam is
passed through the turbine which extracts the work ideally
bringing the temperature of steam to 220C but this does not
happen because the turbine has a low efficiency of 55%.
Then the steam is desuperheated with 110C water and then
we get saturated steam at 20bar to be used in the plant.
Feed water temperature to boiler, T = 90C
Enthalpy of feed water at 90
C = 366.993 KJ/Kg
6.38486
KJ
Kg . K
KJ / Kg
6.38486
KJ
Kg . K
KJ
Kg . K
2840.57h2
2840.572820.89
19.68 KJ /Kg
W actual
KW
Now we calculate the actual outlet enthalpy,
actual work
=2840.57-10.824
=2829.745 KJ/Kg
h2 actual
h1
=2820.89 KJ/Kg
h1
90.2
8.333
KJ/Kg
h1
-2820. 89
=2831.7904 KJ/Kg
Coal requirement :
Boiler efficiency = 81%
GCV of coal =5000 Kcal/kg =20929 KJ/kg
Cost of coal = Rs 5200/MT
eff =
msteam (H g H f )
mcoal GCV
Where ,
Hg
Hf
KJ/Kg
0.81 =
30 1000(2831.714376.993)
mc 20929
0.57150 0.2903
= Rs
0.28117 crores
savings ( Rs crores)
1.95
0.28117
6.936
years
Pres
sure
(bar)
Superheat
ed steam
temperat ure
Enthalpy
of steam
inlet to
turbine
(KJ/ Kg )
Ideal
work
done by
turbine
(KW)
Actual
work
done
by
turbine
(KW)
Electricit
y
savings
(Rs
crores )
Incremen
-tal cost
of boiler
& turbine
(Rs
crores)
Additiona
l Electricity
savings
(Rs
crores
Pay
-back
Period
(in
years )
22
227.793
2831.714
164
90.2
0.571507
18
1.95
0.281174
9.002
28
248.413
2860.16
595
327.25
2.073455
92
2.55
1.5758036
9
1.9007
32
260.406
2876.589
843.911
6
464.154
1
2.940880
68
2.95
1.9913653
5
1.27
35
268.694
2887.891
1015.17
558.341
6
3.5376
3.25
2.8378924
18
1.18
44
290.767
2917.795
1468.25
807.537
5
5.116557
4
4.525
4.1988556
1
1.078
46
295.213
2923.784
1559
857.45
5.432802
98
4.808
4.4714487
52
1.076
48
299.517
2929.57
1646.66
7
905.666
6
5.738303
77
5.09167
4.7347802
36
1.0765
54
303.693
2945.872
1893.66
7
1041.51
7
6.599049
34
5.94167
5.936543
02
1.097
60
322.201
2960.822
2120.16
7
1166.09
2
7.388356
5
6.792
6.1570706
27
1.104
65
331.637
2972.421
2295.91
7
1262.75
4
8.000810
08
7.6
6.6849851
71
1.137