Comprehensive Disaster Management Programme (CDMP II)


Ministry of Disaster Management & Relief

Meeting of the LDRRF Approval Committee

Review and endorse decisions of the last AC meeting

Rural Projects

Summary of Proposed Rural Interventions


Total Districts: 3
Total Upazilas: 3
Total Unions: 3
Total Schemes: 04
Total Budget (BDT): 21,372,239
Total Budget (USD): 277,561

Siddipasha Union Abhaynagar Upazila in Jessore District


Re-construction of road cum embankment DigholiaNolamara Puza mondir to Nolamara sluice gate
Major Hazards
Inundation due to
overflowing of River Majul
Khali .
Water logging
Arsenic contamination
Vulnerabilities
Inundation of HHs, road.
Disruption of educational
activities due to inundation
academic institution.
Crop damage, loss of
livelihood.
Arsenic0sis.

Re-construction of road cum embankment Digholia-Nolamara Puza Mondir


to Nolamara sluice gate at Siddipasha Union Abhaynagar Upazila under
Jessore District

Siddipasha Union Abhaynagar Upazila in Jessore District

Target Hazard
Waterlogging

Proposed DRR Interventions

Re-construction of road
cum embankment
Digholia-Nolamara
Puza Mondir to
Nolamara sluice gate.

Impacts & Expected Results

1. Reduce water logging.


2. Land & HHs will be
protected from inundation

Siddipasha Union Abhaynagar Upazila in Jessore District


Scheme Name of the
Estimated
Beneficiaries Design Data
Scheme
Budget-BDT
JSR 0414016 Re1
Length: 1740 m
construction of
Top Width: 3.6 m
road cum
Bottom Width: 8.4 m
embankment
Height : 1.6 m.
Digholia-Nolamara
510 Slope : 1: 1.5
1,566,512
Puza mondir to
HFL: .85m
Nolamara sluice
gate.

Adampur Union of Austogram Upazila in Kishorgonj District


Target Hazard
Wave Action

Major Hazard
Wave Action
Flash Flood
Water & Sanitation
Vulnerabilities
Homesteads with
inadequate protection
against waves action.
Cultivable land under
inundation, livestock.
Connecting Roads.
Personal health & hygiene

Upazila map

Adampur Union of Austogram Upazila in Kishorgonj District

Proposed DRR Interventions


@KRG 0514053: 485 meter Village
Protection Wall Construction at
Vatura Village
(1st Portion: Romeshshors Jam tree
to east side existing protection wall
395m; 2nd Portion: Near Ram
Chandra House to East side road
90m)
@ KRG 0514054 : 229 meter Village
Protection Wall Construction at
Chowdanto Village (Near H/O Mr.
Proshanto
to
Chowdanto
Government Primary School.

Impacts & Expected Results


1. Protection of social infrastructure
from Haor waves.
2. Facilitating crop drying and
shelters for livestock during flood.
3. Sustainable water and sanitation.

485 meter Village Protection Wall Construction at Vatura Village


(1st Portion: Romeshshors Jam tree to east side existing protection wall 395m;
2nd Portion: Near Ram Chandra House to East side road 90m)

485 meter Village Protection Wall Construction at Vatura Village


(1st Portion: Romeshshors Jam tree to east side existing protection wall
395m; 2nd Portion: Near Ram Chandra House to East side road 90m)

1st Portion: Romeshshors Jam tree to


east side existing protection wall
395m

2nd Portion: Near Ram Chandra


House to East side road 90m

Existing Wall

45m
Proposed wall
60 m

320 m

Proposed wall

30 m

Part-1

Existing Wall

30 m
Part-2

229 meter Village Protection Wall Construction at Chowdanto Village (Near H/O Mr.
Proshanto to Chowdanto Government Primary School

229 meter Village Protection Wall Construction at Chowdanto Village


(Near H/O Mr. Proshanto to Chowdanto Government Primary School)

Existing Wall
Proposed Wall
12 m

26 m

3.5 m

4.5 m

36 m

14 m

NOT TO SCALE
TOATAL GAP =09 NOS & TOTAL LENGTH=229 M

24 m

93 m

16 m

Adampur Union under Austogram Upazila in Kishorgonj District


S/No

Name of the Scheme

KRG 0514053: 485 meter Village


Protection Wall Construction at
Vatura Village (1st Portion:
Romeshshors Jam tree to east
side existing protection wall
11,727,735
395m; 2nd Portion: Near Ram
Chandra House to East side road
90m)

2.

Estimated
BudgetBDT

KRG 0514054: 229 meter Village


Protection Wall Construction at
Chowdanto Village (Near H/O
6,525,376
Mr. Proshanto to Chowdanto
Government Primary School

Beneficiaries Design Data

As per Retaining
Wall design

7000

----do------

7000

Kaikhali Union of Shamnagar Upazila under Satkhira District


Re-Excavation of Poranpur Govt. pond
Major Hazard
Cyclone
Tidal Surge
Water logging
Saline Water intrusion
Vulnerabilities
Access to Saline free water.
Inundation of homestead .
Crop damage

Kaikhali Union of Shamnagar Upazila under Satkhira District

Kaikhali Union of Shamnagar Upazila under


Satkhira District
Target Hazard
Saline water
Proposed DRR
Interventions
Re-Excavation of Poranpur
Government pond.

Impacts & Expected


Results
Ensure water for

drinking and domestic


use round the year.
Reduce the intensity of
water born disease.
Save time and labor for
collecting sweet water of
women.

Koikhali Union of Shamnagar Upazila under Satkhira District


Sche
me

Name of the
Scheme

SAT0514033 ReExcavation of
Poranpur Govt.
pond.

Estimated Beneficia Design Data


Budgetries
BDT
Length: 72m
Width: 50m
Depth: 4.5m
1,552616.0 2,200

For more information contact:


Comprehensive Disaster Management Programme (CDMP II)
United Nations Development Programme (UNDP)
Department of Disaster Management Bhaban (6th Floor)
92-93 Mohakhali C/A, Dhaka-1212, Bangladesh, Tel: (+88 02) 989 0937, 882 1255
Comprehensive Disaster Management Programme (CDMP II)
Ministry of Disaster Management & Relief

Website: www.cdmp.org.bd

Photo: Otin Dewan/CDMP

Thank you

You might also like