Professional Documents
Culture Documents
Yousry Ragab
QA officer
Global napi pharmaceutical plant
2. Project initiation:
2.2 Developing the business case:
Qualification is an essential part of a pharmaceutical manufacturers quality assurance system;
it should demonstrate that facilities are suitable for their intended use and should also
guarantee that the medicinal products are of an appropriate quality. Qualification is thus a
basic factor for drug product safety.
Our company, a pharmaceutical manufacturing plant is intending to buy a new tablet
compression machine to increase the capacity of the solid dosage forms manufacturing
department as these dosage forms were found to be the most profitable and desirable within
the bigger market slice.
As GMP (good manufacturing practice) requirements are legislative to our company for our
products to be FDA approved and thus be able to be exported to highly pharmaceutical
products consuming markets, qualification of equipment must be done as stated in chapter
3.34 of the GMP guide line states, manufacturing equipments should be designed, located
and maintained to suit its intended purpose. Annex 15 to the EU GMP guideline specifies
how this requirement must be implemented.
Identifying the business opportunity:
Three of our major tablet products have been FDA approved following the European EMEA
approval.
We have a great chance to export a great number of batches yearly to the USA and the
European pharmaceutical market achieving good sales and reasonable profit, together with
the local market.
The capacity of our solid dosage forms manufacturing department will not be able to satisfy the
new requirement of production so top management have decided to buy a new tablet
compression machine.
Before buying the tablet compression machine the quality assurance department manager
informed the production manager that such step needs to pass through all the stages of
qualification as stated in the GMP manual and in the FDA and EMEA requirements manuals.
Qualification procedure consists of 4 steps:
Design qualification DQ
Installation qualification IQ
Operation qualification OQ
Performance qualification PQ
Production manager informed the QA department manager and the chairman that the new
tablet compression machine is needed to start production within 3 months maximally starting
from the 1st of April 2009 to satisfy the market needs, fulfill the assigned contracts and not to
face penalties
Assessing the available options:
The available options for Qualifying the tablet compression machine is to:
1Outsourcing the Qualifying process to an external company.
2Doing the qualification using companys personnel, body of knowledge, experience,
knowhow and time.
Benefit description
New revenue generated
Financial
Benefit Value
About 70000000 LEs
yearly
N/A
N/A
Staff
N/A
Exporting image
N/A
Customer
By using an outsourced company to do the qualification required we will lose the staff gains as
they will not be able to do the upcoming qualifications as they didnt afford the knowledge and
the knowhow.
people
salaries
Physical
Project office
Cultural change, lost
work due to the taken
hours from the project
team
Organizational
CAPEX
N/A
OPEX
OPEX
By using an outsourced company there will be no different types of costs, there will be only one
fixed cost stated in the contract and is due payable only one time after the last stage of the
qualification and after providing all the needed documents and certificates, by using an
outsourced company, sources can be more controllable and within limits (stated in the
contract) and no failures responsibilities or costs will be held by our company.
The top management ordered that the full implementation of qualification by the companies own
personnel is more feasible than the outsourcing as the deliverables can be more controlled.
Assessing feasibility:
A feasibility studies may need to be undertaken to identify the likelihood of each solution
satisfying the business problem or the opportunity.
Table 2.3 Solution feasibility
Solution
Feasibility
method of feasibility
component
rating
By reviewing all models with all the new technologies on
New
the internet, asking companies to provide us with
9
technology
complete description of the features provided in the
compression machines.
No new people were recruited or depended upon as we
new
9
use already recruited staff having the knowledge that we
people
need.
Few new processes will occur due to the little differences
New
8
that will occur between this qualification process and the
process
last qualification done to the old compression machine.
New
Normal and within budget limits as no new assets needed
8
assets
out of the project office needs.
Identifying the risks:
Summarizing the most apparent risks associated with the adoption of each solution.
Table 2.4 Business risks
Risk description
Inability to recruit
skilled resources
Failure to choose
reasonable machine
Failure to provide
complete design
qualifications
Risk
likelihood
Risk
impact
Low
High
low
High
high
low
Solution ranking:
Table 2.4 Solution Ranking
Assessment
Solution1 (full
criteria
manufacturing)
Solution 2
(Toll manufacturing)
Costs
people
Physical
Organizational
6
5
9
7
5
6
9
9
5
6
6
6
5
8
6
8
Benefits
increased
revenue
Reduced
expenditure
Improved efficacy
Enhanced Quality
RISKS
Resources
technology
organizational
Total score
71
69
The table shows that the recommended solution will be the implementation of the qualification
by the companies own efforts.
Documenting the issues:
Table 2.5 Business issues
Issue description
Required capital expenditure
funds have not been budgeted
Qualification procedures in the
GMP manual are not enough
Not enough experience within
our midline personnel
More time is needed to perform
complete-steps qualification
issue
priority
high
low
medium
low
List of assumption:
1. There will be no change in the GMP requirements.
2. There will be no change in the FDA requirements.
3. There will be no change in the EMEA requirements.
4. There will be stability in the purchasing, quality assurance and engineering
department.
5. Additional resources will be available from the business as required.
Risk
likelihood
Risk
impact
Low
low
Medium
high
low
High
high
medium
high
low
Risk
likelihood
Risk
impact
high
high
Medium
high
low
High
medium
low
Low
low
Solution feasibility:
Table 2.10 Solution feasibility
Full
manufacturin
Criteria
g
score 1
Quality of
9
deliverables
Change
control
Work within
budget
Achieving
requirement
s
Achieving
process
understandi
ng
Retrieving
knowledge
expertise
Total Score
Weigh
total
Weight
total X
Score
Toll
manufacturin
g score2
Weigh
total
Weight
total X
Score
30
270
30
240
15
135
15
105
15
90
15
135
30
270
30
240
20
180
20
120
20
180
20
120
20
1265
140
20
1140
180
Scope:
The project is to start at April 2009 and ends at June 2009.
Table 2.11 project deliverables
Deliverables
Components
Purpose of the equipment/facility
Legal requirements:
laws/regulations/standards
Design requirements: technical
data/construction and
workmanship/accessories and spare
parts(balance, code readers,
components)/materials of product contact
part
Requirements of the installation: dimensions,
environmental conditions (rooms, energy,
utilities, HVAC, safety, environment)
Performance data: list of
products(specification, in particular
dimensions, special features)/description of
the sequence of operation (flowchart,
variability of the process conditions)/ pulse
frequencies, quantity produced/setting-up
Design
times
Qualification
Facilities for control, regulation and
measurement
Requirements for maintenance, cleaning,
and care
Evidence for functionality of equipment
Requirements for the accompanying
documentation: technical document, CE
certificates of conformity, calibration and
gauging certificates, operating instructions,
certificates of materials, spare parts list,
quality certificates for software, documents
for training and instruction of staff
Customer service
Necessary supplementations and
modifications following award of contract
Installation schedule at premises of contract
giver
Documents that verify the installation of
equipments, pipes, supply facilities and
instruments following check against current
engineering drawings and specifications
Documents that verify compilation and
Installation
comparison of operating procedures as well
Qualification
as maintenance requirements of the supplier
Documents that record the requirements for
calibration
Documents of verification of construction
materials
Operation
QUALIFICATION PROTOCOL:
Description
Qualification
QUALIFICATION REPORT:
Performance
Qualification
Calibration status
Evaluation of deviations
To demonstrate and
document that facilities and
equipments as connected
together can perform
effectively and reproducibly
based on the approved
process method and product
specification
Customer representative
Project stakeholders:
Listing the persons or entity outside the project that have a key interest or stake in the
project.
Table 2.13 Project Stakeholders
Stakeholders interest
Stakeholders
CEO
Financial controller
EMEA
Government body
FDA
Roles:
Identifying the roles required to undertake the project
Table 2.14 project roles
Resource
Role
Organization
name
Giving technical
Engineering
information about
Engineering
supervisor
engineering issues
Giving technical
information about
Production
pharmaceutical
Production
supervisor
manufacturing
issues
Assessing
information given
and ask for
Quality
Quality
information needed
assurance
assurance
and state the
supervisor
requirements
needed to be fulfilled
Collect needs and
requirements,
perform market
Purchasing
purchase
search, do feasibility section head
studies, contact
manufacturers
Project Charter organization:
Assignment
status
Assignment date
assigned
1-APR-2009
Assigned
1-APR-2009
Assigned
1-APR-2009
Assigned
1-APR-2009
Resources Plan:
Table 2.18 Project resources
Role
Start date
Installation engineer
1-APR-2009
Production pharmacist
1-APR-2009
Purchasing section
1-APR-2009
head
QA supervisor
1-APR-2009
Description
The creation of the purchase order/ordering
the premise from the manufacturer
The assembly of the equipment in the
production room
Testing the variables of the machine and its
ability to achieve required results
Analyzing the produced product against
limits
Is impacted by
Criticality
Date
Completing design
qualifications
High
May 2009
Receiving the
equipments
High
June 2009
Completing the IQ
High
June 2009
End date
Jun-2009
Jun-2009
May-2009
%effort
Part time
Part time
Part time
Jun-2009
Part time
Financial Plan:
Table 2.19 Project finance
Expenses
type
people
salaries
Physical
Project office
Cultural change, lost
work due to the taken
hours from the project
team
Organizational
CAPEX
OPEX
OPEX
Quality plan:
Table 2.20 Project processes
Process
Time management
Description
A check list of the project steps is monthly revised
Cost management
Quality management
Change management
Risk management
Issue management
Procurement
management
Acceptance
management
Communications
management
Risk
likelihood
high
Medium
Risk
impact
high
high
low
High
medium
low
Low
low
Project issue:
Table 2.22 Project issues
Issue description
Required capital expenditure
funds have not been budgeted
Qualification procedures in the
GMP manual are not enough
Not enough experience within
our midline personnel
More time is needed to perform
complete-steps qualification
issue
priority
high
low
medium
low
Description
Milestone date
Compiling up of all the
20 April 2009
pharmaceutical and
technical requirements for
the equipment
After performing a thorough
30 April 2009
market analysis, market
surveys. Offers are received,
reviewed. Then feasibility
study is done to choose from
different suppliers, the
Completion of Site
Acceptance Tests (SAT)
Completion of the
installation Qualification
Completion of operation
qualification
Completion of performance
qualification
15 May 2009
5 Jun 2009
10 Jun 2009
12 Jun 2009
24 Jun 2009
29 Jun 2009
commissioning
Complete DQ
Description
Complete a
document which
defines all the users
pharmaceutical and
technical
requirements for the
equipment.
The job is put out to
tender, quotations
are compared,
decisions are made,
the order is place and
final acceptance is
carried out
Completion and
documentation of all
the design
qualification
requirements
Perform FAT
Tests to confirm
acceptance at the
suppliers premises
Perform SAT
Perform IQ
Perform OQ
Perform PQ
Sequence
After the procurement
decision have been
taken by the top
management
After completion of
the URS and its
approval by all the
users
After commissioning
step has been
completed and
original documents
have been delivered
by the manufacturer
After commissioning
step has been
completed and after
the approval of the
manufacturer
After the delivery of
the whole facility and
its installation
During the installation
of the facility
effectively and
reproducibly based
on the approved
process method and
product specification
Project tasks:
Table 3.4 Project tasks
Phase
Activity
Project planning
Complete DQ
Task
Involving
different areas of the
company to produce
informal requirement
profile of the new
facility
Describe
requirements ,
process, product
capacity
Describe the
agreement with the
contract acceptor
regarding
implementation and
handling
Describe the
requirements of the
contract giver for the
scope of supply and
service
Transfer
requirement profile
into user requirements
Sequence
1st
2nd
3rd
4th
5th
6th
Thorough market
analysis is done to
know what offers are
available
7th
Performing
supplier qualification
8th
User requirements
are dispatched to
suitable supplier
Supplier compile
technical specification
on the basis of the
used requirements
and forward this to the
prospective customer
Then these Technical
9th
10th
specifications are
compared with the user
requirements and the
GMP requirements. If
the technical
specification
corresponds with the
user requirements;
factory acceptance test
11th
is done to make sure
that the user
requirements are
compiled with at the
manufacturers
premises
Perform SAT
Perform IQ
review the
documentation of the
design phase
12th
Purchase contract is
concluded
13th
Completion and
documentation of all
the Tests done to
confirm acceptance
after delivery to the
pharmaceutical
manufacturing plant
Implementation of
the design
qualification
requirements when
assembling the facility
is documented in IQ
Visual examination
is done to the
delivered components
to ensure fault free
workmanship, correct
assembly, correct
1st
1st
2nd
setup, correct
implementation of all
utility connections and
connection with
upstream and
downstream
machines
All deviations during
installation is
documented to be
assessed for the need
of a defect list with
responsibilities and
deadlines, the results
are then listed in a
final report and
comprehensively
checked once again
3rd
Method of testing
and acceptance
criteria must be
defined prior to start
1st
Perform OQ
Perform PQ
Practical tests
are done to
check each
function in detail
Implementation
of disinfectants
and maintenance
work should be
checked at this
stage
2nd
3rd
1st
2nd
3rd
Project efforts:
Table 3.5 Project effort
Task
3 hours
2 hours
3 hours
3 hours
5 days
4 hours
Efforts
5 hours
1 day
3 days
2 days
1 day
7 days
2 days
3 days
3 days
4 hours
3 days
1 day
3 days
1 day
1 day
1 day
1 day
Project resources.
Table 3.6 Project resources
Task
Resources position
QA manager and QA supervisor
QA supervisor
Production supervisor, engineering
supervisor, purchasing section head
QA supervisor, QA manager
QA supervisor
Production supervisor
Engineering supervisor
Engineering supervisor, production
supervisor, QA supervisor
QA supervisor
Project dependencies:
Table 3.7 Project dependencies
Activity
Depend on
Completion of user
Requisition of user
requirements specifications
requirements
(URS)
Choosing the best offer from Completion of user
the best supplier
requirements
Completion of the Factory
Performing feasibility study,
Acceptance Tests (FAT)
supplier qualification,
comparing between technical
specifications and user
requirements
Delivery of the equipments to Completion of FAT and
the manufacturing plant
signing contract
Completion of Site
Delivery of the equipments
Acceptance Tests (SAT)
Completion of the installation Delivery of the equipments
Qualification
Completion of operation
Completion of the installation
qualification
Qualification
Completion of performance
Completion of operation
qualification
qualification
Assumptions:
The project will not change in the scope.
The resources identified will be available upon request
Approved funding will be available upon request
Creation of the resources Plan:
The list of resources:
Human resources
Engineering department:
Engineering supervisor
Purchasing department:
Purchasing section head
Production Department:
Production supervisor
Quality assurance Department:
Quality assurance supervisor
Quality assurance manager
Equipments
printer
laptop
desktop
Internet access point
Microsoft windows
Microsoft office
Materials
paper
ink
electricity
Dependency type
End to start
End to start
End to start
End to start
End to start
End to start
End to start
End to start
Labor Listing:
Table 3.8 labor listing
Role
No
Project
manger
Engineering
supervisor
Purchasing
section head
QA
supervisor
Production
supervisor
Summarized
Responsibilities
Delivering the
approved solutions
to meet the full
requirements of
the customers
Provide technical
support
Purchasing,
supplier
qualification,
commissioning,
feasibility studies
Fulfilling
qualification
requirements
Provide technical
support,
pharmaceutical
production
knowledge
Summarized Skills
Start date
End date
Time management,
Cost management
Quality management
People management
1st of April
2009
30th of Jun
2009
Installation
experience
Technical problem
solving
Commissioning
experience, feasibility
study experience
1st of April
2009
30th of Jun
2009
1st of April
2009
15th of May
2009
Experience in
qualification, solid
dosage form
pharmaceutical
production
Experience in
challenging tests,
broad knowledge of
the compression
machines variables
1st of April
2009
30th of Jun
2009
1st of April
2009
30th of Jun
2009
Equipment Listing:
Table 3.9 equipment listing
Item
No Purpose
Printer and
1 To print and
photocopier
photocopy needed
documents
laptop
desktop
Internet access
point
Intranet access
point
Microsoft
windows suite
Microsoft office
package
2
2
Specification
high speed black
and white laser
printer integrated
with high speed
economical
photocopier
Light weight, high
speed processor
Start date
1st of April
2009
End date
30th of
Jun 2009
1st of April
2009
30th of
Jun 2009
1st of April
2009
30th of
Jun 2009
512 kbps,
secured
1st of April
2009
30th of
Jun 2009
100 Mbps,
secured
1st of April
2009
30th of
Jun 2009
Vista
1st of April
2009
1st of April
2009
30th of
Jun 2009
30th of
Jun 2009
Start date
1st of April
2009
1st of April
2009
1st of April
2009
End date
30th of Jun
2009
30th of Jun
2009
30th of Jun
2009
2007
Material listing:
Table 3.10 Material Listing
Item
Component
Amount
paper
Pack of 500 sheets 2
Laser printer filling
cartridge
Ink cartridge
Cartridge enough
for 1000 papers
Cartridge enough
for 1000 papers
1
1
Unit cost
1500 L.E
4500 L.E
2000 L.E
48 L.E per month
350 L.E
300 L.E
Listing any administration costs that are Associate with the costs of the project:
Table 3.15 Administrative costs
Material Items
Unit cost
Paper package of 500 sheets each
19 L.E each
Laser printer filling cartridge
150 L.E each
Ink cartridge
150 L.E each
The expenses Schedule is prepared the months from Feb. till sep. 2008:
Month
Jun.
Jul.
Aug.
Sep.
Week
Expenses type
Labor
Project manger
Engineering supervisor
Assistant technician
(mechanical)
Assistant technician For
utilities
Researcher for the new
product formulae
Production supervisor
Registration specialist
Equipment
Compression machine with
the associated tools power
consumption
Preparation machine with the
associated tools power
consumption
Single Punch machine for
the researches with the
associated tools power
consumption
Separate PC for the
effervescent production room
Special HAVAC System for
the Production rooms power
consumption
Administration Fees
Total
m
1200
640
1200 1200 1200 1200 1200 1200 1200 1200 1200 1200 1200 1200 1200 1200 1200
640 640 640 640 640 640 640 640 640 640 640 640 640 640 640
3
1
160
160
160
160
160
160
160
160
160
160
160
160
160
160
160
160
160
160
160
160
160
160
160
160
160
160
160
160
264
264
264
264
264
264
264
264
264
264
264
264
264
264
264
264
640
640
640
640
640
640
640
640
640
640
640
640
640
640
640
640
1
6
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
80
80
80
80
120
120
120
120
20000
5
2000
24984 4984 4904 4904 3264 3264 3184 3184 3424 3424 3424 3424 3424 3424 3424 3424
Page
37
Page
38
Likelihood
Impact
Priority
Rating
1.1
20
80
50
medium
1.2
20
100
60
medium
1.3
40
60
50
medium
2.1
60
80
70
high
2.2
40
60
50
medium
2.3
80
80
80
high
3.1
60
40
50
medium
3.2
40
40
40
low
3.3
40
40
40
low
4.1
60
60
60
medium
4.2
60
60
60
medium
4.3
40
100
70
high
5.1
20
80
50
medium
5.2
20
80
50
medium
5.3
60
80
70
high
6.1
20
80
50
medium
6.2
20
60
40
low
6.3
20
80
50
medium
7.1
60
60
60
medium
7.2
60
60
60
medium
7.3
60
60
60
medium
8.1
20
40
30
low
8.2
40
40
40
low
8.3
80
80
80
high
9.1
20
60
40
low
9.2
40
100
70
high
9.3
20
80
50
medium
10.1
60
80
70
high
10.2
20
100
60
high
11.1
60
80
70
high
11.2
60
80
70
high
11.3
40
60
50
medium
Page
39
By sorting the upper tables the High rating of the risk priority are:
Risk ID
Likelihood
Impact
Priority
2.1
60
80
70
2.3
80
80
80
4.3
40
100
70
5.3
60
80
70
8.3
80
80
80
9.2
40
100
70
10.1
60
80
70
10.2
20
100
60
11.1
60
80
70
11.2
60
80
70
Page
40
Rating
high
high
high
high
high
high
high
high
high
high
high
high
high
high
high
high
Action
resource
Action
date
2.1
Clearly
identify the
business
benefits
Project
sponsor
20-Mar2009
2.3
Clearly
identify the
business
benefits
Project
sponsor
20-Mar09
4.3
Specify
certain
accountant
for the
recording of
the project
spent
Project
manger
20-Mar09
5.3
Review after
each step
the output
obtained
and
comparing
with the
customer
requirement
Project
manger
After
each
step
8.3
9.2
Tracing the
delivery of
the
procurement
and there
arrivals
Review after
each step
the output
obtained
and
comparing
with the
customer
requirement
with the
addition of
the obvious
and clear
market
survey of
the product
Project
manger
Project
manger
Action
resources
Action
date
Project
manger
20-Mar2009
Project
manger
20-Mar09
Project
manger
15-Mar09
Quality
assurance
officer
During
each
step
20-May
-09
weekly
inquiry from
the supplier
by the status
of the orders
Project
manger
Starting
from 1apr-2009
After
each
step
In process
control for
the project
steps to
insure that
the project
output will
reach the
customer
requirements
Quality
assurance
officer
During
each
step
Page
41
Contingent
Actions
Measure the
actual
business
benefits
achieved by
the project
Measure the
actual
business
benefits
achieved by
the project
Outsourcing
of a finance
company for
the
monitoring of
the project
budget
In process
control for
the project
steps to
insure that
the project
output will
reach the
customer
requirements
Ratin
g
high
high
Ris
k ID
Preventive
action
10.
1
Through the
weekly
meetings
10.
2
Weekly
report to the
stakeholders
high
11.
1
high
11.
2
Action
resourc
e
Action
date
Contingent
Actions
Action
resources
The
establishment
Starting of the intranet
Project from the for the ease of
Project
manger first of
communicatio
manger
march
n through the
team
members
The
attendance of
Starting
stakeholders
Stakeholders
Project from the
representative representative
manger first of
s in the
s
march
weekly
meetings
Testing the
staff at the
beginning of
Out sourcing
Starting
the project for
or hiring partProject from the
the
timers for the
manger first of
assurance of
project time
march
the
only
Qualification
in the project
Ensuring the
overcoming
presence of
the shortage
Starting
all the
of the
Project from the
equipments
equipments
manger first of
at the
through the
march
beginning of
outsourcing or
the project
hiring
Page
42
Action
date
At the
beginnin
g of April
Starting
from the
first of
march
Project
manger
At the
beginnin
g of April
Project
manger
At the
beginnin
g of April
Page
43
Complete installation
qualification
Complete operational
qualification
Complete performance
Criteria
Purpose of the equipment,
facility
Legal requirements
Design requirements
Requirements for the
installation
Performance data
Facilities of control,
regulation and
measurement
Requirements of
maintenance, cleaning, care
Evidence of functionality of
the equipment
Requirements of the
accompanying
documentation
Customer service
Necessary supplementation
and modifications following
award of contract
Installation schedule at
premises of contract giver
Installation of equipment,
pipes, supply facilities and
instruments following check
against current engineering
drawings and specifications
Compilation and
comparison of operating
procedures as well as
maintenance requirements
of the supplier
Requirements of the
supplier
Verification of construction
materials
Calibration status
Results of the qualification
tests carried out
Comprehensive
interpretation and evaluation
of all tests
Evaluation of deviations
Release of
equipment/facility following
successful completion of
qualification
Results of the first pilot
Page
44
Standards
FDA requirements
EMEA requirements
GPA requirements
FDA requirements
EMEA requirements
GPA requirements
FDA requirements
EMEA requirements
GPA requirements
FDA requirements
qualification
batch of product a
Results of the first pilot
batch of the product b
Results of the first pilot
batch of the product c
EMEA requirements
GPA requirements
After the determination of the milestones and there standards and the criteria of acceptance
the acceptance schedule can be established.
Page
45
Date
30 Apr
2009
Acceptance
review
Review the
orders and the
specification
mentioned in it
Installation of
the
compression
machine
Complete
installation
qualification
12 Jun
2009
Review
installation
against
instructions
Operating the
compression
machine
Complete
operational
qualification
24 Jun
2009
Testing the
operation against
requirements
Production of
the first three
pilot batches
Complete
performance
qualification
29 Jun
2009
Comparing the
manufactured
product against
batch record
Reviewers
Date
Project
manager Q.A
officer
Production
supervisor
Engineering
Supervisor
Project
manager Q.A
officer
engineering
supervisor
Engineering
Supervisor,
Production
supervisor,
QA
supervisor
Engineering
Supervisor,
Production
supervisor,
QA
supervisor
1 May
2009
12 Jun
2009
24 Jun
2009
29 Jun
2009
Page
46
Page
47
Page
48
Method
Verbal
Frequency
Weekly
Date
During the
months from
march 2008
till June 2008
Verbal
Monthly
Beginning of
each month
from the
march till
June
Verbal
Following
the
deliverables
completion
After the
deliverables
completion At
the end of
June 2008
Status
report
send be
electronic
mail
Verbal
Weekly
During the
months from
march till
June.
Monthly
During the
months from
march 2008
till June 2008