You are on page 1of 15

Annex 4: Technical and Financial Proposal Template

Technical proposal Template

Introduction
Executive Summary
This includes the bidders understanding of the terms of reference, scope of work and necessary skills, and company profile. This involves including an
overview of the main points contained in the proposal with references to sections where more detailed discussion of each point can be found (maximum 4
pages).

Approach
A detailed description of how the bidder will undertake each major area in the SCOPE OF THE PROJECT and DELIVERABLES section, required resources
(bidder, ministry and third party) and any special skills required, the deliverables (format and structure), use of any metho dology and how it will cover the
scope, use of any standard tools, and duration of any work streams.

[Activity 1]

Implementation Approach
Actions

Approach
Describes the bidders approach for implementing the action; including

Provides a listing of the actions needed


for the Activity

Process (i.e. steps)


Standard methodologies adopted
Scope of involvement for each stakeholders

Deliverables
Deliverables
Provides a listing of the deliverables of
the Activity

Format and Structure


Describes the format (e.g. MS Word document) and Structure (e.g. Outline,
indicating the scope and content) of each deliverable.

[Activity 2]

Implementation Approach
Actions

Approach
Describes the bidders approach for implementing the action; including

Provides a listing of the actions needed


for the Activity

Process (i.e. steps)


Standard methodologies adopted
Scope of involvement for each stakeholders

Deliverables
Deliverables

Format and Structure

Provides a listing of the deliverables of


the Activity

Describes the format (e.g. MS Word document) and Structure (e.g. Outline,
indicating the scope and content) of each deliverable.

[Activity]

Implementation Approach
Actions

Approach
Describes the bidders approach for implementing the action; including

Provides a listing of the actions needed


for the Activity

Process (i.e. steps)


Standard methodologies adopted
Scope of involvement for each stakeholders

Deliverables
Deliverables

Format and Structure

Provides a listing of the deliverables of


the Activity

Describes the format (e.g. MS Word document) and


Structure (e.g. Outline, indicating the scope and
content) of each deliverable.

Work Plan and Duration


The work plan and duration for the overall consulting work, including any dependencies between the separate items in the scope. The bidder should provide
milestones for each deliverable. The work plan should break down the phases and tasks within each phase and indicate which re sources will be working on
these tasks

Track Record
The bidders track record on projects similar in both size and nature undertaken in the last (7) years, and references of suitable client references with contact
details

CVs of Project Staff


A summary of proposed team and a description of each project staff role and their relevant experience. Brief resumes of the team who will work on the project
(all detailed resumes should be included in an Appendix). The bidder should also indicate the availability of the proposed staff and indicate which phases of
the project each team member is participating in, what role they will be playing, and what their utilization rate will be (percentage of their time), below is the
required template to be filled for each team member

Curriculum Vitae
Proposed Position on the Project:
Name of Firm:
Name of Personnel:
Profession/Position:
Date of Birth
Years with the Company:
Proposed Duration on Site:

Key Qualifications and Relevant Experience

Expected Role in MOICT Project

Education

Nationality:

Employment Record:

(a) Employment Record

From date present

Employer
Position held

(b) Employment record

Employer
Position held

(c)

Employment record

Employer
Position held

Languages:
Reading

Speaking

Language 1
Language n

------------------------------------------------------

-----------------------------

Writing

Signature

Date

Other Information
Appendices

Financial Proposal Template


Please indicate the overall estimated cost of your proposed solution.
Cost should be broken down as per the schedules below as well as the detailed scope of work presented in section 2 and 3 of the RFP.
The price quotation should be all-inclusive fixed lump sum price and provided in Jordanian Dinars (JD).
All prices are inclusive of all fees, finance rate and taxes.
All prices are for site delivery.
Scope of Work Components
1.0 Gathering and Analysis of Business Requirements
2.0 System Design and Implementation
3.0 System Security
4.0 Quality Management
5.0 Training and Knowledge Transfer
6.0 Operations, Support and Maintenance
7.0 Project Management
Total
Total Amount in Words: (Only ------------------------------------------------------------------------------Jordanian Dinars)

Amount

Project Detailed Cost:


1. Gathering and Analysis of Business Requirements:
Gathering and Analysis of Business
Requirements
[List all activities associated with
Gathering and Analysis of Business
Requirements]

Resource

Unit cost
(man day
cost)

Number of
Units (man
days)

Total Cost

Comments

Skill 1

Skill 2
Skill N
TOTAL
Total Amount in Words: (Only ------------------------------------------------------------------------------Jordanian Dinars)
2. System Design and Implementation:
2.1 System design and implementation professional services

System Design and Implementation

Resource

[ List all activities associated with


Skill 1
System Design and Implementation]
Skill 2
Skill N

Unit Cost
(man day
cost)

Number of
Units (man
days)

Total Cost*

Comments

* This cost shall include all professional services required for the proper implementation of the *System design and implementation* excluding
the cost required to integrate the solution with PKI system
Total Amount in Words: (Only ------------------------------------------------------------------------------Jordanian Dinars)
2.2 Proposed Solution Required Hardware

Architecture Components

Unit Price

Quantity

Total Units Price

24 months Maintenance
and Warranty Cost

Total

Description

List all required items for


production, staging and
development environments such
as servers, routers, databases,
SAN, Firewall , Load Balances,
IDS,

TOTAL
Total Amount in Words: (Only ------------------------------------------------------------------------------Jordanian Dinars)

2.3 Integration Government services with the Citizen Profile


Entity Name*

Service
Name*

Resource

Skill 1
Skill 2

Unit cost
(man day
cost)

Number of Units (man days)

Total Cost

Comments

TOTAL
*Refer to Annex 3 to fill in the service and entity name

Total Amount in Words: (Only ------------------------------------------------------------------------------Jordanian Dinars)


2.5 Integration of the proposed solution with Jordan PKI system
Service Name
Resource

Unit cost
(man day
cost)

Number of Units (man days)

Total Cost

Comments

Skill 1
Skill 2
Total
Total Amount in Words: (Only ------------------------------------------------------------------------------Jordanian Dinars)

3. System Security
3.1 Security Requirements implementation excluding the vulnerability testing by third party
Security Requirements
[ List all activities associated with
System Security]

Resource
Skill 1

Skill 2
Skill N

Unit cost (man


day cost)

Number of Units
(man days)

Total Cost

Comments

TOTAL
Total Amount in Words: (Only ------------------------------------------------------------------------------Jordanian Dinars)
3.2 Vulnerability testing by a third party
Security Requirements
[ List all activities associated with
System Security]

Resource

Unit cost (man


day cost)

Number of Units
(man days)

Total Cost

Comments

Unit Cost (man


day cost)

Number of Units
(man days)

Total Cost

Comments

Skill 1

Skill 2
Skill N
TOTAL

4.

Quality Management:
Testing and Validation

[ List all activities associated with


Testing and Validation]

Resource
Skill 1

Skill 2
Skill n
TOTAL
Total Amount in Words: (Only ------------------------------------------------------------------------------Jordanian Dinars)
5. Training and Knowledge Transfer:

Training and Knowledge Transfer


[ List all activities associated with
Training and Knowledge Transfer]

Resource

Unit cost (man


day cost)

Number of Units
(man days)

Total Cost

Comments

Skill 1

Skill 2
Skill n
TOTAL
Total Amount in Words: (Only ------------------------------------------------------------------------------Jordanian Dinars)
6. Operations, Support and Maintenance:
6.1 Support and Maintenance Professional Services (24 months)

Service Name

Resource

Unit cost (man


day cost)

Number of Units (man days)

Total Cost

Comments

Skill 1
Skill N
TOTAL
Total Amount in Words: (Only ------------------------------------------------------------------------------Jordanian Dinars)
6.2 Existing Government Portal Software Licenses**
Software
Supplier

Name of
software

License metric(i.e. by
number of clients,
processor power or other)

Total No.
Licenses

Unit price per


year

Duration*

Total

Skill 1
Skill N
TOTAL
*Duration shall include:
1. Duration of maintenance and support for two years starting from the date of initial acceptance
** This is applicable for proposed solution that is based on IBM

Total Amount in Words: (Only ------------------------------------------------------------------------------Jordanian Dinars)


6.3 New Government Portal Software Licenses
Software
Supplier

Name of
software

License metric(i.e. by
number of clients,
processor power or other)

Total No.
Licenses

Unit price per


year

Duration*

Skill 1
Skill N
TOTAL

*Duration shall include:


1. Duration of maintenance and support for two years starting the date of initial acceptance.

Total Amount in Words: (Only ------------------------------------------------------------------------------Jordanian Dinars)

7. Project Management

Total

Project Planning and Management


[ List all activities associated with
Project Management]

Resource

Unit cost (man


day cost)

Number of Units
(man days)

Total Cost

Comments

Skill 1

Skill 2
Skill n
TOTAL
Total Amount in Words: (Only ------------------------------------------------------------------------------Jordanian Dinars)

8. Other Costs (if any)


Note (1): The Itemized Financial Proposal will be examined prior Contract Award in order to ascertain that the items are correctly calculated. The
itemized prices are for reference only and the lump sum price shall constitute all costs etc incurred by the bidder for the execution of the
project. Should any arithmetical error be found, it will be corrected and the Proposal Value will be amended accordingly. MoICT encourages all
bidders to study carefully their prices and to submit their final and lowest prices.
Note (2): The bidder shall also take into account that all the rates quoted in his Price Proposal shall be fixed throughout the Contract duration and
that no adjustment to such rates shall be accepted by MoICT, except when otherwise provided for in the Contract.