October 2015
Work on site to-date has focused on the construction of a new two storey podium extension to the east and north of the existing structure along with some structural
amendments to the existing structure. These relatively minor structural amendments are designed to make eect to the particular needs of the bank. This includes some
new stairs, bridges and extended oor plates within the atrium space to improve connectivity between the oors and to facilitate its use as a collaborative environment.
May 2015
May, 2015
October 2015
October 2015
October 2015
October 2015
Internal structural alterations are ongoing and include cutting out of new stair openings in the atrium area and creating new door
FACADE
The procurement of the facade commenced in early 2014, one year ahead the start of site
operations. During the design and development phase of the external envelope, the design
team undertook a number of QA/QC visits to the facade contractors supply chain. These
included, glass manufacture, glazed unit manufacture, unitised panel assembly, anodising
plant and stone quarries.
Heat Soaking Kiln All toughened glass being used on the project is being
heat soaked. This reduces the risk of the glass breakage due to Nickel
Sulphite Inclusions.
October 2015