Professional Documents
Culture Documents
Construction
Technology CE3221
Road Construction
This assignment is work related to construction which includes equipment
costing, equipment selection and use, earthwork planning, earthwork
compaction and road construction
Contents
Page
Introduction
03
Equipment Costing
05
Earthwork Planning
10
Earthwork Compaction
13
Road Construction
15
References
17
Page 1
List of figures
Figure 1 - Equipment with scale
Figure 2 - Net volume (Bank cubic yards, Loose cubic yards and Compacted cubic yards)
Figure 3 Mass diagram
Figure 4 - D7H dozer
Figure 5 - Moisture content vs Dry density
Figure 6 - While road constructing
List of tables
Table 1 Cut and fill chart
Page 2
1.0 Introduction
Roads are an integral part of the transport system. A countrys road network should be
efficient in order to maximize economic and social benefits. They play a significant role in
achieving national development and contributing to overall performance and social function of
the community. It is acknowledge that roads enhance mobility and taking people out of isolation.
Prior to commencement of any road construction project involving site formation work, site
investigation is carried out to establish the geological profile along the road alignment. Very
often, samples are taken by borehole drilling for tests including, particle size distribution,
moisture content and triaxial tests etc. The results are useful for engineering design.
The engineering properties of most soils can be improved by compaction. Compaction is the
art of mechanically densifying materials. The base layer of a road lays the foundation for the
upper pavement structure. It must offer excellent bearing capacity, be capable of withstanding a
broad range of different climatic conditions, and remain functional over several decades. If the
moisture content of a soil is below its optimum moisture range, add water to the soil before
compaction. The project officer must consider following,
Compaction equipment ranges from handheld vibratory tampers (suitable for small or
confined areas) to large, self-propelled rollers and high speed compactors (ideally suited for
large, horizontal construction projects). When selecting compaction equipment type and
properties of the soil, density desired, placement lift thickness, size of the job and availability of
compactions equipments are should be considered. Since the use of several types of compaction
equipment overlaps, it is good to use a test strip to make the final determination of the most
efficient compactor and compaction procedures. Locate a test strip adjacent to the project site.
The test strip provides an evaluation/validation of the proposed construction procedures.
Information obtained from a test strip includes,
Page 3
The term sub grade describes the in-place soil on which a road, an airfield, or a heliport is
built. Sub grade includes the soil to the depth that may affect the structural design of the project
or the depth at which the climate affects the soil. Depths up to 10 feet may be considered sub
grade for pavements carrying heavy loads. The quality and natural density of this material dictate
what action(s) to take to prepare the sub grade. For example, a highly organic sub grade material
may have to be totally removed and replaced with a higher quality, select material. In most
situations this is not the case. Often the in-place material is suitable, but requires some degree of
compactive effort to achieve the required density.
After preparing the sub grade, bring in fill material to form the sub base and base courses for
the project. When placing fill, it is important to spread the material in uniform layers and to
maintain a reasonably even surface. The thickness of the layers is dependent on the desired
compacted lift thickness. The thickness of the uncompacted lift is normally 1 1/2 to 2 times the
final compacted lift. For example, place fill in 9- to 12-inch lifts to achieve a compacted lift
thickness of 6 inches. Place the fill material with a scraper or a dump truck and spread it with a
dozer or grader. When spreading material on a prepared sub grade, spreading the material from
the source to the nearest or vice versa. The advantages of spreading fill from the farthest point to
the nearest are as follows:
The first person in the paving team, however, is the truck driver who fills the asphalt into the
paver's hopper. Two mutually independent conveyors transport the material through the machine
to the rear, where it is uniformly distributed between paver and screed by two individually
controlled rotating screw conveyors. When paving a standard mix, the temperature should
always remain above 110 C in order to ensure sufficient time for compaction.
Page 4
Page 5
Page 6
Lubricant cost
Total oil consumed = (260 fwhp x 0.6244 x 0.006 lb/hp.hr) / 1.85 lb/litre + 0.45litre/hr
= 0.5265 + 0.45 = 0.9765 litre/hr
Oil cost = 0.9765 litre/hr x Rs.800/litre = Rs.781.21/hr
Total oil cost = Rs.781.21/hr + Rs.45/hr = Rs.826.21/hr
Repair cost
Initial cost
= Rs.33,009,550
Page 7
Total operating cost = Fuel cost + Lubricant (oil) cost + Repair cost + High wear item cost
= Rs.2,779.33/hr + Rs.826.21/hr + Rs.3,040.78/hr + Rs.176/hr
= Rs.6,822.32/hr
Example 02
A CAT d7H (power -shift) dozer is used in a pushing operation. The dozer is equipped with a
straight blade. The material (dry and noncohesive) weighs 106pcf in the bank state. It is
estimated that the material will swell 7% , from bank to loose state. Estimate centre-of-mascenter-of-mass pushing distance for 2-1 above and assume 3% grade. The operators have
average skill and job will be performed in dusty conditions. Job efficiency can be assumed to be
equivalent to a 45 min hour. Calculate the direct cost of the proposed earthmoving operation in
Rs. per bcy. The company normal O&O cost for these machine is Rs7,000 per hour and the
operators wage is Rs.200 per hour plus 41% for fringes, insurance, workers compensation, and
so on.
Answer
Given data
Page 8
Page 9
Figure 2 Net volume (Bank cubic yards, Loose cubic yards and Compacted cubic yards)
Example
Complete the earthwork calculation sheet here and plot the resulting mass diagram. Divide ccc
by 0.88 to convert to bcy. Calculate the area under the mass diagram curve. What quantity of
material must be hauled along the length of the project? What is the average haul distance, in
situation, for this material?
Srilanka Institute of Information Technology
Page 10
Station
0 + 00
1 + 00
2 + 00
3 + 00
4 + 00
5 + 00
6 + 00
7 + 00
8 + 00
9 + 00
10 + 00
11 + 00
12 + 00
EN 13529550
9550
Endarea
cut
(m2)
0.00
End
area
fill
(m2)
0.00
Vol of
cut
(bcy)
Vol of
fill
(ccy)
0.00
0.00
Stripping
cut
(bcy)
0.00
0.00
95.96
0.00
1912.69
0.00
285.96
0.00
3.96
270.96
6.96
Algebraic
sum
(bcy)
0.00
Stripping fill
(ccy)
Total
cut
(bcy)
Total
fill
(ccy)
Adj. Fill
(bcy)
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1912.69
2173.51
2173.51
2173.51
7612.68
0.00
0.00
0.00
7612.68
8650.77
8650.77
10824.2
8
78.84
11100.98
0.00
0.00
78.84
11100.9
8
12614.7
5
12535.9
1
23360.1
9
220.96
217.47
9805.32
0.00
0.00
217.47
9805.32
11142.41
10924.9
4
34285.1
3
12.96
180.96
396.87
8011.34
30.96
0.00
427.82
8011.34
9103.79
8675.97
42961.1
0
50.96
42.96
1273.93
4463.24
86.96
211.91
1360.88
4675.15
5312.67
3951.78
46912.8
9
120.96
0.00
3426.71
856.23
150.96
438.91
3577.67
1295.14
1471.75
2105.92
44806.9
7
250.96
0.00
7413.34
0.00
250.96
801.91
7664.30
801.91
911.26
6753.04
38053.9
3
290.96
0.00
10801.98
0.00
380.96
1168.91
11182.94
1168.91
1328.31
9854.63
28199.3
0
310.96
0.00
11997.97
0.00
340.96
1334.91
12338.93
1334.91
1516.94
10821.9
8
17377.3
2
200.96
0.00
10203.99
0.00
33.96
692.91
10237.94
692.91
787.40
9450.55
7926.77
0.00
0.00
4005.67
0.00
0.00
11.91
4005.67
11.91
13.53
3992.14
3934.64
Maximum
Massordinat
e
0.00
46912.
89
Page 11
Mass Diagram
50000.00
40000.00
30000.00
Mass Diagram
20000.00
10000.00
0.00
0
10
11
12
13
Quantity of material is wanted to hauled along the length of the project = 3934.64bcy
Average haul distance = (298848.7 100) / 46912.89 = 6.37 1 00 = 6+37 Sta
Page 12
Normally, it is good practice to adjust water content to OMC = 2%. But this depends on
wind, temperature, and soil type. Lift is a layer of soil placed on top of soil previously placed in
an embankment. The term can be used in reference to material as spread or as compacted.
Temping foot compactor, sheeps foot roller, impactor, pneumatic roller etc are using for the
compaction purposes. The formula to determine compactor production in CCY per hour is,
Production (CCY per hour) = (16.3 W S L E ) / N
16.3 = constant for converting the factors in feet, mph, and inches to CCY
W = compacted width per pass, in feet
S = compactor speed, in mph
L = compacted lift thickness, in inches
E = efficiency
N = number of passes required
Page 13
Answer
Production = (W x S x L x E) / N
= (2.5 x 12 x 150 x 50/60) / 7
= 535.71 m3/hr
Page 14
Example
An asphalt plant will produce 180 tph for the above highway project. The mat will be 12ft wide
and 1.5inch thick, and will have a density of 115lb/sy-in. A vibratory roller with a 66-in wide
drum will be used for compaction. Assume a 50-min hour efficiency factor for the roller. The
overlap between adjacent laps and over edges will be 6-in. minimum. It is estimated that nonproductive travel will add about 15% to total travel. From a test mat, it was found that three
passes with the roller are required to achieve the density. To account for acceleration and
deceleration when changing directions, add 10% to the average roller speed to calculate a
running speed. If it is desired to keep the following speed under 3 mph, how many rollers are
required for the project.
Srilanka Institute of Information Technology
Page 15
Given data
Page 16
6.0 References
https://books.google.lk/books?id=ICwaJKGeFWcC&pg=PA216&lpg=PA216&dq=calcul
ated+the+direct+cost+of+the+proposed+earthmoving&source=bl&ots=JweqmsjShZ&sig
=vGdpFYWzxLqeTUpAoYHxh5G3ZD0&hl=si&sa=X&ved=0CCsQ6AEwAmoVChMI
pKjp-uDsyAIVwiWmCh2TfA0m#v=onepage&q=vibratory%20roller&f=false (accessed
01.11.2015)
Page 17