QA / QC PLAN

Rev.No.
0

CLIENT

Date
October 2015

Reference No.

Approved

PROJECT :
WORK/
SCOPE

Description
Issued for Approved

PROJECT NO.:

Page1 of 21

Page no.

QA/QC PLAN

:0

Rev. date :
Date

Page
2 of 21

TABLE OFCONTENTS
PART

TI TLEPAGE

1
1.1
1.2
1.3

PART-1 GENERAL.
Purpose. ..
Extent . ..
Definition of Term

3
4
4
4-6

2
2.1

PART-2 ORGANIZATION .
Project Organization .

7
8

3
3.1
3.2

PART-3 DESIGN ..
Design and Relevant Quality Control ...
Changes Control

9
10
10

4
4.1
4.2
4.3
4.4
4.5
4.6

PART-4 PROCUREMENT CONTROL .


General .
Vendors Evaluation ..
Purchasing Control ..
Shop Inspection and Control
Non-Conformance Control ..
Sub contracting ..

11
12
12
12-13
13-14
14-15
15-16

5
5.1
5.2
5.3
5.4
5.5
5.6
5.7

PART 5 SITE CONSTRUCTION AND INSTALLATION


Scope .
Document Control .
Material Receipt, Storage and Trace ability ...
Field Quality Control
Construction Equipment and Test/Inspection Equipment Control
Non-Conformance Control
Final Documentation and Records

17
18
18-19
19
20
20
20-21
21

Page no.

QA/QC PLAN

Rev. date :
Date

1.

PART 1 - GENERAL

1.1. PURPOSE
1.2. EXTENT
1.3. DEFINITION OFTERMS

:0

Page
3 of 21

Page no.

QA/QC PLAN

:0

Rev. date :
Date

Page
4 of 21

1.1. PURPOSE
The main purpose on this QA/QC Plan is to ensure in achieving the desired level of
quality of a completed facility.

1.2. EXTENT
1.2.1. The requirements in this QA/QC Plan pertains to the contract activities effecting
quality including Design, Procurement .Fabrication, Transportation, Storage,
Installation and Testing.
1.2.2. Any organization, firm, sub-contractor or party who carries-out any of the above
activity shall conform to the requirement of this QA/QC Plan. In such cases, the
interfacing between different parties shall be defined and controlled.

1.3. DEFINITION OF TERMS


In this QA/QC Plan the following term are mentioned and defined as follows;
Acceptance Criteria

Specified limits mentioned which characterized


an item, process, or service defined codes,
standards or other requirement document.

Approval

An act of endorsing or adding positive


authorization of both.

Certificate of Conformance

A document signed by an authorized individual,


certifying the degree to which items or services
meet specified requirements at the time of
assessment.

Certification

The authoritative act of documenting compliance


with requirements.

Contractor

Client

Document

Any written or pictorial information describing,


defining, specifying, reporting, or certifying
activities, requirements, procedures, or result.

Inspection

Examination of measurement to verify whether


an item or activity conforms to specified
requirement

Inspection Authority

Clients own inspection department and or

Page no.

QA/QC PLAN

:0

Rev. date :
Date

Page
5 of 21

Nationality or internationally recognized In


specification agency.
Inspection Level

Specified amount of inspection coverage deemed


necessary to assure that a product or services
conforms to specifications.

Interface (Interfacing)

Interrelationship
between
the
different
organization participating to the same project and
also relating to define communication and
physical boundary.

Item

Any level of unit assembly, including structure


system, subassembly, component, part or
material.

Non Conformance

A deficiency in characteristics documentation of


procedure that renders the quality of an item or
activity unacceptable or indeterminate.

Objective Evidence

Any documented statement or fact, information


or record, quantitative or qualitative, pertaining to
the quality of an item or activity, based on
observations, measurements, or tests which can
be verified.

Procedure

A document that specifies or describes show an


activity is to be performed.
It may include methods to be employed or
materials to be used and sequence of operations.

Qualification (Personnel)

The characteristics or abilities gained through


education, training, or experience as measured,
such as standards or tests, that quality of an
individual to perform a required function.

Quality Assurance (QA)

All these planned, systematic actions, and


detailed schemes developed and documented
before hand necessary to provide adequate
confidence that a product, processor service will
be satisfied.

Quality Control (QC)

That pasta QA which through checks, review,


measurements, tests, and inspection determines
that specifications are met.

Page no.

QA/QC PLAN

:0

Rev. date :
Date

Page
6 of 21

Repair

The process of correcting and/or rectifying a


Non conforming characteristics to a condition
such that the capability of an item to function
reliably and safety is unimpaired even conform to
the original requirement.

Surveillance

The act if monitoring or observing to verify


whether any
item or activity
conforms to
specified requirements.

Testing

An element of verification for the determination


of the capability of an item to meet specified
requirements by subjecting the item to set of
physical, chemical, environmental or operating
conditions.

Traceability

The ability to trace the history, application, or


location of an item an like items or activities by
means of recorded identification.

Use-as-is

A disposition permitted for a non conforming


item when it can be established that the item is
satisfactory for its intended use.

Verification

The
act of
reviewing, inspecting, testing,
looking, auditing or other wise determining and
documenting whether items, process, services, or
documents conform to specified requirements.

Waiver

Documented authorization to deviate from


specified requirements.

Page no.

QA/QC PLAN

Rev. date :
Date

2.

:0

PART2 - ORGANIZATION

2.1. PROJECT ORGANIZATION

Page
7 of 21

Page no.

QA/QC PLAN

:0

Rev. date :
Date

Page
8 of 21

2.1. PROJECT ORGANIZATION


2.1.1. The Project Organization, de line at as the authority and responsibility of the
appointed persons and parties performing project activities.
The Organization Chart indicates the key positions both at home office and on
site engaged in the project. While other engineering groups from the permanent
organization will be assigned to the project team in relation to the needs defined
and scheduled by the Project Management.
2.1.2. The structure of the Quality Assurance team in the Project Organization and the
relation ship with the Project Management, the QA/QC team and the other
functions.
2.1.3. The overall responsibility for site construction is of the Site Manager who reports
to the Project Manager.
The execution of the works is the responsibility of the Construction Manager
while field it the responsibility of the Construction Manager while field quality
control activities are the responsibility of Field QC Engineer.
2.1.4. The execution of the work on site in accordance with the drawings and
specifications shall be ensured by the Field Erection Superintendents and
Supervisors who report to the Construction Manager.
2.1.5. At Site, the engineering activities shall be carried out be the Engineering Team
headed by the Field Engineering Manager. On Site, the quality control activities
shall be ensured by the QC team under the coordination of the Field QC
Engineer who reports to the Site Manager.
The Site Quality Control is included but not limited to the activities for materials
and equipment at their arrival at Site. Special process used during construction
and completed testing and examination of items and systems during and after
installation.
2.1.6. The Field QC Team will act as a separate entity from construction team and
therefore free of conflicts with progress and construction restraints.
2.1.7. The Clients representative and Inspection Authority, acting on be half of the
Client, witness to ensure that the project is carried out in accordance with the
contract requirements. The Quality Assurance Plan, system or program which
either during site construction clearly shows the relevant witnessing points.

Page no.

QA/QC PLAN

Rev. date :
Date

3.

:0

PART3 - DESIGN

3.1. DESIGN AND RELEVANT QUALITY CONTROL

3.2. CHANGES CONTROL

Page
9 of 21

Page no.

QA/QC PLAN

:0

Rev. date :
Date

Page
10 of 21

3.1. DESIGN AND RELEVANT QUALITY CONTROL


3.1.1. Measures are established to ensure that the Design activities are planned, carried
and reviewed in a controlled manner in accordance with the established project
requirements. The Engineering documents to be produced in the project will be
controlled with document list which indicate the date of issuing for project use
(inquiry, purchase, construction, etc.) and those which are subject to clients, etc.)
And those which are subject to clients approval/comment.
3.1.2. Responsibilities for preparation, checking, reviewing, and approval of technical
documents shall be clearly defined. Design reviews are planned, performed and
recorded under the coordination of the Project Engineering Manager.
3.1.3. The drawings and specifications to be issued must be approved and signed by the
responsible Engineer concerned or other relevant position after verification that
the established checks and design review shave been satisfactorily performed.
When a document needs to be modified following a design/field change, the
revisions shall be signed for approval by the same positions the approved the
original document.
Status and reason for document revisions is to be clearly indicated in the
document front sheet.

3.2. CHANGES CONTROL


3.2.1. The design document may be revised for completion or for change purpose.
The changes may result mainly from Client request, design requirements, shop or
site exigencies. In any case it must be basic solution previously established or the
project quality requirements.
3.2.2. The document from required change shall be sent by the Engineer concerned to
the Project Management for evaluation. If accepted copies of the change order
are sent to all the involved persons and organizations. The technical documents
reflecting the design change shall be approved using the same procedure and by
the same personnel as ones who approved the original design documents.
3.2.3. Changes with multi disciplinary implications shall be examined by all the
positions concerned. If necessary design review meetings shall be repeated as
appropriate.

Page no.

QA/QC PLAN

:0

Rev. date :
Date:

4.

PART4 - PROCUREMENT CONTROL

4.1. GENERAL
4.2. VENDOR EVALUATION
4.3. PURCHASING CONTROL
4.4. SHOP INSPECTION AND TESTING
4.5. NON- CONFORMANCE CONTROL
4.6. SUB CONTRACTING

Page
11 of 21

Page no.

QA/QC PLAN

:0

Rev. date :
Date

Page
12 of 21

4.1. GENERAL
4.1.1. The Procurement Control System is organized to give assurance that purchased
items, whether directly or through vendors, meet the contractual requirements for
quality, delivery schedule and economy.
4.1.2.

This system requires that Vendors meet the standards and specifications of the
contract.

4.1.3. The Procurement Control System includes provisions for source evaluation and
selection, surveillance of the vendors and inspection of items and examination of
documentation upon delivery.

4.2. VENDOR EVALUATION


4.2.1. Inquiries shall only be sent to qualified Vendors included in the Project Vendor
Lists.
4.2.2. For the vendors not included in the Project Vendor List, a prevention evaluation
and qualification shall be carried out before the purchase order issue. The
qualification is carried out by the Procurement Group in cooperation with the
relevant technical and QA group as required.

4.3. PURCHASING CONTROL


4.3.1. The established procedures shall be implemented to make sure that all the
applicable prescription, regulatory requirements, design basis and inspection
requirements necessary to assure adequate quality of the bids are included or
referenced in the documents for requisition of items and service. A said
procedure defines the type documentation to be included in the inquiries and the
responsibilities for their preparation, control and approval.
4.3.2. Bid Evaluation
The evaluation of the received bids shall be performed according to the
established procedure. All the bids are compared in a bid summary.
Technical bid evaluation is carried out buy the Engineering Group concerned to
assess the adherence to the inquiring documents, the soundness of the proposed
solutions and to evaluate the proposed deviations. Bid clarification meeting will
be held with the Bidder son the short List. A survey may be carried out in
connection with bid clarification meeting depending on previous experience with
theBidder.

Page no.

QA/QC PLAN

Rev. date :
Date

Page

:0

13 of 21

4.3.3. Purchase Orders


The preparation and issuance of the purchase orders to the selected vendors/
subcontractors shall follow the established procedures. Before orders for major
items are issued, verifications will be carried out by the Engineering Group on
the purchase order documentation to check that the following conditions are met;
a. The Technical Bid Evaluation has been properly carried out by the

Engineering Group concerned according to the procedures.


b. The selected Vendor is included in the Project Vendor List and/or has been

duly qualified.
c. The documents attached there to are complete, updated, consistent to each

other and include the approved drawing sand specifications.


4.3.4. Vendor Documentation
Vendors drawing sand data will be described in a Vendor Document List
included in the Inquiry. Such list will specify in detail which documents will be
apart of the supply and those to be submitted to Contractor (for
approval/review/information) according to the delivery program.

4.4. SHOP INSPECTION AND TESTING


4.4.1. The vendor shall carry out the checks, inspection and tests required by the
purchase order and inspection requirements.
4.4.2. The minimum requirements for shop inspections and test for main equipment are
detailed in the Inspection Requirements of the Contract.
4.4.3. The Inspection will perform, as specified in the appropriate procedure;
a. Pre inspection meeting with Vendors of major or critical equipment to clarify

contract requirement, coordination procedures and interfaces.


b. Approval of the shop fabrication.
c. Qualification of Welding Procedures.
d. Qualification of Welders.
e. Verification of Material Identification and Traceability.
f. Check of material source certificates.

Page no.

QA/QC PLAN

:0

Rev. date :
Date

Page
14 of 21

g. Witness shop inspection and testing and/or review relevant results in

accordance with contract and/or relevant specification requirements.


h. Check and validation of examination and test reports and certificates.

4.4.4. The Project QA personnel will at tend the pre-inspection meetings with major
supplies to verify their quality organization to clarify, Final Test Report will be
prepared by vendor.
4.4.5. On completion of inspection, Final Test Report will be prepared by vendor.
4.4.6.

Only after checking that all the established inspections, examinations and tests
have been properly carried out, witnessed, evaluated documented, incompliance
with the P.O., the inspector will review and approve with signature on the final
inspection report to release for shipment.

4.4.7. A final check of the documentation of inspections and test shall be carried out by
the Project QA Team to verify completeness and adequacy.

4.5. NON-CONFORMANCECONTROL
4.5.1. Materials, components, equipment or system at deviate from approved
specifications, drawings or other applicable documents or due to document
deficiencies are indeterminate are considered as Non-Conforming Items and
shall be properly marked and/or segregated in order to avoid the in advertent use.
The Non-Conformance shall be documented by the inspector and the due course
of action shall be initiated according to the concerned procedure.
4.5.2. A Non-Conformance will be classified as;
a. Minor Non-ConformanceWhen it can be solved with in the contractors

QA Group, such as accepting;


- Item replacement which affects the Project Schedule.
- Complete repair in compliance with the applicable codes and
specifications.
- Additional documentation (in case of document deficiency).
b. Major Non-ConformanceWhen it is necessary to involve other Group such

as;
- Repair with a procedure to be approved.
- Repair not leading to full conformance.
- Replacement delaying the project schedule.
- Use-as-is of the item.

Page no.

QA/QC PLAN

:0

Rev. date :
Date

Page
15 of 21

4.5.3. There solution of major non-conformance shall involve all concerned Project
function sand the Project QA Manager. The later will verify that all implications
concerning the quality are duly considered and that there solution of the nonconformance is effective and documented.
The above shall be applied also is the case of vendor, should propose a change
not in compliance with the requirements of purchase specifications.
4.5.4. The Non-conformance resolution such as Use-as-is or a Repair not leading to
full conformance to governing
specifications, drawings or Contract
Documents but not effecting the suitability for service of materials, shall be
exhaustively documented in the non-conformance report by the Contractors
Inspector.
In both cases the documents non-conformance resolution shall be submitted to
the Project Manager for evaluation and disposition.
4.5.5.

As soon as a major non-conformance is found, a copy of the relevant Quality


Control Report shall be sent to the Project QA Manager who will verify the
effectiveness of the corrective action.

4.5.6. There solution of a major non-conformance shall be documented by the Project


QA Manager and the relevant report shall be signed by all individual concerned,
A copy of this report will be filed by the Project QA Manager as QA Record.

4.6. SUBCONTRACTING
4.6.1. General
This describes the measures which are established and documented to assure that
services, complete assemblies or constructions are supplied in a controlled way
with the aim to satisfy the Project requirements for quality, delivery schedule and
cost.
4.6.2. Instructions of Tendering Subcontractors
The Contracts Department is responsible for collecting all documents to be
included in the Tender Invitation such as;
- Scope of Work.
- Technical Requirement (including Inspection and Test Requirements).
- Commercial Conditions.

Page no.

QA/QC PLAN

:0

Rev. date :
Date

Page
16 of 21

4.6.3. Tender Evaluation


The Evaluation of the received tenders shall be preformed by the Engineering
group concerned to assess the adherence to the inquiry documents.
The Final Tender Evaluation will end up with a Tender Evaluation Report where
the contractors are ranked and all necessary documents to be included in the
contract are listed.
4.6.4. Contract Award
Contract commitments are made only the Tender Evaluation Report has been
approved according to the Project provisions. The Procurement Group in
cooperation with the Engineering Group shall prepare the Contract clearly
stating all the requirements of quality related, technical and commercial nature,
including what has been agreed upon during the clarification meetings.

Page no.

QA/QC PLAN

Rev. date :
Date

5.

:0

PART5 - SITE CONSTRUCTION AND INSTALLATION

5.1. SCOPE
5.2. DOCUMENT CONTROL
5.3. MATEIALRECEIPT, STORAGE AND TRACEABILITY
5.4. FIELD QUALITY CONTROL
5.5. CONSTRUCTION EQUIPMENT AND TEST INSPECTION
EQUIPMENT CONTROL
5.6. NON - CONFORMANCE CONTROL
5.7. FINAL DOCUMENTATION AND RECORDS

Page
17 of 21

Page no.

QA/QC PLAN

:0

Rev. date :
Date

Page
18 of 21

5.1. SCOPE
5.1.1. The purpose of this section is to provide a formalized and systematic means for
the implementation of the Quality Control for Construction to ensure that the
contracted facilities installed by the Field Project Organization are fully
compliant with are relevant specifications, procedures, drawings, applicable
codes, rules and regulations.
5.1.2. The working procedures state the activities, for the relevant responsibilities, the
quality control activities, the reports to be prepared, the communication lines to
be maintained and the required recording system.
5.1.3. This section includes the requirements pertaining to the administration and control
of the technical documentation on site.
5.1.4. It is also specified how the same requirements are imposed on subcontractors.
5.1.5. Although the construction subcontractor is responsible for the execution, testing
and documentation of the work, the Site Organization has as advisory function
and is given the responsibility to provide a close follow-up subcontractor
activities.

5.2. DOCUMENT CONTROL


5.2.1. Recording, filing and distribution of design documentation received from home
office shall been sure by the Site Drawing Controller.
5.2.2. The document will be distributed to the personnel concerned so as to be available
at the location where the activity is to be performed prior to commencement of
the activity it self.
All obsolete documents must be marked OBSOLETE to prevent their
misapplication.
5.2.3. On working site, the Field Engineer concerned receives the construction
specifications and drawings and review them, also taking into account any field
requirements. Where necessary, he will ensure that modifications/additions to
said documents are performed in compliance with the procedures.
In case of change effecting the basic design, he ensures through the Field
Engineering Manager the approval of home office Engineer concerned and,
when necessary of the Customer Representative. The data necessary for the As
Built Drawings will be collected by the Field Engineers.
5.2.4. The documents which are prepared on site (or modified without needing the home
office approval as per part5.2.3) will be signed by the Field Engineer concerned
and by the Field Engineering Manager for check and approval.

Page no.

QA/QC PLAN

:0

Rev. date :
Date

Page
19 of 21

A copy of said documents will be sent to the relevant home office the Engineer
who provides for the relevant recording, distribution and filing.
5.2.5. Documentation relevant to fabrication and testing of purchased items and
materials (mill certificates, test reports, manufacturers drawings, specifications,
data reports, instruction manuals) will be received and filed by the Site Drawing
controller.
5.2.6. Recurrent in sections will be carried out at the working are as by the Field
Engineers, to as certain that the latest revisions of construction drawings and
specifications are be ingused.

5.3. MATERIAL RECEIPT, STORAGE AND TRACEABILITY


5.3.1. Material receipt, unloading, check registration, storage and traceability will be
ensured by the material controller in accordance with the relevant procedure.
5.3.2. Only after a satisfactory check, the received material may be release for the final
registration and storage.
Irregularity on the concerning document be found such as to identify anonconformity, the Construction Manager shall be informed.
He shall evaluate the non-conformity, informing when necessary, the concerned
Engineer at home office.
When contractual requirements are effected the client representative is to be
informed.
5.3.3. The Construction Managers evaluation of a non-conformity can be Rejection
or Repair or Use-as-is and shall in any case be documented.
In case of Repair, the relevant repair procedure is the responsibility of the
Construction Manager concerned which, after repair will evaluate the results and
issues the acceptance certificate.
Should any deviation from design documents be accepted, the written approval
of the concerned Engineer is necessary, before the acceptance certificate.
Incase of deviations from contractual requirements, the customer written
approval will be required.
These reports are to be filed as Quality Control Records.
5.3.4. All the materials which have not passed the receiving control are to be marked
HOLD and held being separated from the others, until they are accepted or
rejected. In case rejection they must be marked REJECTED and kept
segregated.
5.3.5.

For the released items or materials the Material Controller will provide for the
project registration, storage, preservation and maintenance (to prevent any
damage or deterioration) ensuring the traceability of stored items and materials
by painting or stamping project, identification symbols or marks, all in
accordance
with
the
procedures.

Page no.

QA/QC PLAN

:0

Rev. date :
Date

Page
20 of 21

5.4. FIELD QUALITY CONTROL


5.4.1. The site installation and construction work shall be performed in a planned and
coordinated manner using construction drawings and specifications.
5.4.2. The inspection and test activities shall be planned in order to maintain overall
project scheduling and shall be supported by the applicable procedures.
The status of inspections and tests in every stage of the construction work shall
be maintained by the Quality Control Engineer.
5.4.3. The purpose of the Field Quality Control Plan is to define all the mandatory tests
and examination to be carried out during the installation work to verify the work
is carried out in conformity to specify prescriptions and to provide for the
relevant documentary evidence.
TheplanwillalsoshowthewitnesspointsandthetimingwhenQualityControl
Engineer shall notify the customer and/or the Inspection Authority.
5.4.4. Quality Control Team Construction Team will have meetings when ever QC
Matter requires coordination or instruction prior to installation activity.
5.4.5. The Client Inspection Group may witness the inspections and tests made in
accordance with the Field QA Plan.
This Plan will show the Clients witnessing points while the coordination between
the Contractor and the Client is defined in the established procedure.

5.5. CONSTRUCTION EQUIPMENT AND TEST/ INSPECTION EQUIPMENT


CONTROL
5.5.1. In general, using equipment (i.e. welding equipment, grinder etc.) the supervisor
and warehouse staff confirm the condition of equipment and make a proper
suggestion to prevent damage and maintain its original quality.
5.5.2. The Field QC engineer nominates for a test and inspection equipment controller
and let him control these equipment.
5.6. NON - CONFORMANCECONTROL
5.6.1. Any deficiency or deviation in characteristic, documentation, procedure or work
which renders the quality of an item or work un acceptable or in determinate
shall be considered as anon-conforming.
A defined course of action shall be applied according to the concerned
procedure.
5.6.2. The finding of a Non-conforming may occur at any time during the installation
work or routine inspection and may be made by any one. All field staff are aware
that it must be reported both to the Construction Manager and Field QC
Engineer.

Page no.

QA/QC PLAN

:0

Rev. date :
Date

Page
21 of 21

5.6.3. The Construction Manager and Field QC Engineer convene a discussion with the
relevant personnel, to discuss the counter measures and make the final decision.
5.6.4. When the disposition plan of non-conformities is considered to effect the original
design, the Field Engineer shall re-evaluate and inform the result to the
Construction Manager and Field QC Engineer.
5.6.5. If repaired, Field QC Engineer confirms the passing of the Final Inspections,
removes the non-conformities identification and sends it to next process.
5.6.6. If scrapping the non- conformities product, the Construction Manager, together
with relevant personnel, separate it from others.

5.7. FINAL DOCUMENTATION AND RECORDS


5.7.1. All reports of examination, inspection, tests, non-conformities and changes issued
during installation works will be collected, checked and signed by the concerned
Field QC Engineer and/or Superintendent.
The documents are to be prepared shall be taken to prevent deterioration,
damages and losses.
5.7.2. The above documents will be checked by the Field QC Team for completeness
and adequacy with the QA Plan prescription and Contract requirements.