You are on page 1of 17

BLOCK CAVE PRODUCTION SCHEDULING USING PCBC

Tony Diering, Gemcom Software International Inc., Vancouver, Canada


Otto Richter, Gemcom Australia, Perth, Australia
Daniel Villa, Gemcom Software International Inc., Vancouver, Canada

over the years. These companies are listed in the


acknowledgements section of this paper.

Abstract
Gemcom PCBCTM is a software package which
has been developed over the last 22 years for the
planning and scheduling of block cave mines. This
paper presents an update of the various research and
development activities done to PCBC recently. It
also provides an overview of the current capabilities
of the software including tools for both feasibility
type studies as well as tools for operating mines.

Typical project workflow


A significant number of block cave projects
have been studied using PCBC over its 20 year
history. During that time, a well used work flow has
evolved which is usually used as a guideline for new
projects.
Conceptually, the steps are as follows:
Figure out what is in the ground (geological
model)
Work out where you want to mine (X,Y,Z limits)
Work out the tons and grade that you will get
from those limits
Work out how long it will take (time)
Optimize and iterate to add further value to the
project.
Repeat the whole process every time a new
geological model is produced as the project
evolves.

PCBC is used extensively by prospective and


operating block cave mines and some of the recent
applications are described.

Introduction
History
PCBC was first developed in 1988 for the
Premier Diamond Mine in South Africa(Diering,
2000). In 1992, the first production scheduler was
added to the system and in 1994 a significant upgrade
was done for Northparkes Mine in preparation for
their Lift 1. PCBC was upgraded to Microsoft
Windows operating system in 1996. In 2002, the
Cave Management System (CMS) was developed for
Freeport DOZ mine and this was upgraded to provide
SQL Server database support in 2003 for Finsch
Diamond mine(Diering, 2004). A new algorithm
called Template Mixing (Diering, 2007) was added to
provide better and alternate flow modeling options to
users.

The overall steps in the process are described


below:
Footprint Finder. This is an application which
works off the geological block model and whose
primary objective is to help assess the best
elevation (or elevations) for the block caving
footprint (Z extent of the mine)
Generate draw points. Setting up draw points
requires assessment of draw point spacing,
tunnel orientation etc. (X,Y extents)
Construct slice file. This is the process of
conversion of a geological model to be aligned
with the draw points such that each draw point
has an in-situ (un-mixed) resource above it.
Compute best Height of Draw (HOD). Each
draw column is evaluated to assess the best or
highest dollar value which can be achieved for a
given set of mining costs and product revenue
and recovery factors.
Production scheduling. This is the heart of the
PCBC system. It is important to distinguish

More recently, various enhancements to the


production scheduler and other areas of the program
have been completed some of which are described
here.
It is worth noting that the block cave market (in
terms of software) is very limited. As such, it is
difficult to fund high quality research and program
development. We at Gemcom Software International
Inc. have been very fortunate to have companies
sponsor custom development activities within PCBC

between production (tons and grade produced)


and development scheduling (tunneling and
development).
PCBC does production
scheduling. This provides the tons and grade
forecasts for the project which has been
described as the mine planners promise to the
shareholders as to what the mine can produce.
Advanced schedules.
No schedule is ever
complete or final. During the project evaluation
stage, new pricing or geometrical options will be
considered and new geological models generated
as the exploration drilling progresses. During
production, new schedules are generated
whenever the actual production varies from the
plan (which is always). So the need for a
scheduler which can run in typically less than 20
to 30 minutes per run is important.
Operating mine set up. Once a mine is going
into production, then it is possible to set up a
database to store production tons and draw point
assay and other observational data.
The
importance of accurately recording and
managing the tonnages extracted from each draw
point has long been recognized.
CMS can be used to help manage the daily (or
shift based) draw order. This is the daily
tonnage target set for each draw point. This is
essential if a managed block cave is to be
maintained.
Geological/geotechnical monitoring. Tools have
been developed within PCBC to help store,
display and analyze observed data
Least Squares (LSQ) and grade reconciliation
can be used to base schedules on observed assay
data instead of block model data for more
accurate schedules
During the above process, it is essential to have
appropriate tools to interrogate and query the
results generated. Over the years, a substantial
toolbox has evolved based on project and user
requirements.

framework has proven invaluable over the years and


has allowed our development efforts to focus on the
block cave part of the problem minimizing the need
to develop and maintain the underlying graphical and
database subsystems.

Figure 1 Typical view of PCBC running inside the GEMS


general mine planning package

Components of PCBC are described below


including initial assessment of footprint location,
model set up and mineable reserve assessment, then
scheduling and production management.
Foundation
This is the framework within which PCBC
operates. The various components are summarized
as follows:

Graphical interface
Blocks
Lines
Points
Triangulations
SQL database / workspaces
Profile editors / parameter management

Footprint Finder
Input for Footprint Finder utility comes from a
geological block model together with mining costs,
revenue factors, etc. The program will look at each
level in the block model and then construct vertical
columns accumulating the dollar value. Vertical
mixing is applied to each column using an algorithm
based on Laubschers mixing method (Laubscher,
1994).

In this paper
This paper describes the various components in
the PCBC product. It is not intended to provide any
explanation as to how these components work or are
used.

Components of PCBC

This is very useful to obtain an initial idea of


where to locate a footprint and what the initial
footprint shape might be.
Figure 2 shows
accumulated columns plotted according to value.

The various components of PCBC have evolved


to support the above project workflow. PCBC runs
inside the Gemcom GEMSTM mine planning package
developed by Gemcom Software International Inc.
(Figure 1) The ability of PCBC to work inside of this
2

with the process of defining a reasonable


economically and geotechnically feasible outline.
PCBC
Overall steps of a typical project (from the
program, not project perspective) are as follows:
Set up the initial working environment inside a
GEMS project.
Slice file construction (Figure 5). This is an
integral part of the process. Utilizing userdefined draw cone shapes, a column of rock
above each draw point is simulated and stored in
what is termed a slice file. The term slice as the
total column is broken into slices which match
the vertical spacing of the geological block
model.
Figure 2 Footprint Finder example on one level

Repetition of this process on each level allows


the tons and value generated to be plotted as shown
in Figure 3.
9,000
8,000
7,000
6,000
5,000
4,000
3,000
2,000
1,000
-

Dollar Value (M$)

Dollar value

Figure 5 Schematic of block model to slice file conversion

2560
2620
2680
2740
2800
2860
2920
2980
3040
3100
3160
3220
3280
3340
3400
3460
3520
3580
3640

Tonnage (Mt)

Tons
1,000
900
800
700
600
500
400
300
200
100
-

Draw point locations are used to construct a


vertical column which is then intersected with the
block model. The various overlaps of the draw cones
are resolved so as to not double count material and
this is accumulated into the slice file for each draw
point. This is referred to as a NoMix slice file,
since no material mixing has yet been applied.

Elevation

Figure 3 Footprint Finder : Tons and dollar value vs


footprint elevation

An example from Freeports DOZ mine is shown in


Figure 4.

Figure 6 shows a section of a block model and


the resulting NoMix slice file with one column per
draw point.

Figure 4 Footprint Finder example (DOZ mine)

The higher grade zones are shown in warmer


colors. This type of value plot assists considerably
3

Figure 7 shows that the results from Footprint


Finder and Best HOD tools are typically quite similar
as one would hope.
Once the basic preparation work has been done,
production schedules can be generated.
A typical schedule requires input of the
following key components (Figure 8):
Sequence to develop the draw points (and
undercut)
Constraints on the maximum draw rate which
can be applied to draw points
Tonnages required in each scheduling period
Information to control the cave shape. It is usual
to look at different strategies and compare
Numerous other inputs, constraints and reporting
control options

Figure 6 Block model to slice file conversion

A variety of material mixing algorithms may


then be applied to the slice file to simulate the
actual material mixing which takes place as
material is extracted from the draw points.
Best HOD. The Best HOD utility will
accumulate tons, grade and dollar value in each
draw column (after application of vertical
mixing) to provide an estimate of mineable
reserves for different footprint shapes. As this
process uses actual draw point locations and
assumed draw column shapes, it is generally
considered more geometrically accurate than the
Footprint Finder.

Figure 8 Production scheduling components in PCBC

A basic schedule will open draw points


according to the sequence and deplete tons from each
according the Production Rate Curve (PRC), apply
material mixing if required and report tons and grade
mined in a variety of formats.
An advanced schedule could look at changing
parameters for individual or groups of draw points,
adjusting the schedule to past tons mined, having the
HOD profile follow a given cave shape and adding
information to report undercut tons separately from
production tons.
Experience has shown that it is very useful to
have a clean and efficient interface between PCBC
and Microsoft Excel. This allows reports to be
generated in a format which can quickly be further
analyzed by engineers.
In addition, when dozens or hundreds of
schedules are being run, it is useful to have what is
called a playback tool. This allows various aspects
of the schedule to be studied visually to look for
trends (or data input errors!)

Figure 7 Best HOD based footprint (bottom) vs Footprint


finder result (top) (Cadia East)

Each draw point can be categorized in a variety


of ways (Figure 10), including over-draw, underdraw, normal, draw-bell development, wet muck
(which is a safely concern) or as requiring special
treatment. The tonnage for each category is set
accordingly.

The production scheduler can just as easily be


used for forward looking schedules or for analysis of
past performance. This is very useful for grade
calibration and reconciliation purposes.
Cave Management System
CMS was originally developed for Freeport
DOZ mine and then further refined for use at Finsch
mine. Currently there are seven mines using or
planning to use CMS. CMS aims to generate a draw
order for each draw point every day or shift. It uses
the recent historical (actual) tonnages to adjust and
manage the draw and provides the supporting
database, reporting and user interface to facilitate this
process. At De Beers Finsch mine, CMS has been
closely integrated with the Sandvik Automine
system.

Figure 11 Excel map format for draw point result display

Figure 11 shows an example of daily production


data displayed using Excel. It is important to have a
clean interface between the CMS database and Excel
for ease of analysis by the draw control personnel.
LSQ
The LSQ tool is intended for operating mines.
Once a mine has been in operation for a few years, it
will likely have a draw point sampling program. The
draw point assay values can be stored and sorted per
draw point and then composited into 10m or 15m
intervals to provide some averaging of the highly
variable assays.

Figure 9 How CMS fits in between historical tons and


future plans

Subject to a variety of constraints, a least


squares trend line is put through the composites and
then this can be extrapolated for a short distance up
the draw column into what is essentially the unmined part of the column (Figure 12).

Figure 9 shows how CMS fits in between the


historical tons mined and the requirement to adjust
the plan of the next few months (using PCBC
schedules) in a process called Catch-up to fit in
with the long term plan. (Diering, 2004)

This becomes particularly useful when the draw


point assays suggest that the draw point should
remain open (usually after 100% draw) when the
slice file values suggest that the draw point should be
closed. For draw points where the sample trend
differs from the slice file, then the slice file values are
replaced with the sampled values for selected draw
points. This is somewhat similar to the open pit
practice of taking blast-hole samples to improve the
local grade of a bench about to be blasted and mined.
Figure 12 shows a single draw column with
sampled values at various heights (HOD) above the
draw point. The graph shows these together with the
trend line and some extrapolated points. Maximum
and minimum grade values are set so that steep up or
downward trends do not generate unrealistic grade
values.

Figure 10 Categorization of draw points for priority


assignment

Figure 12 Sample compositing and trend line analysis in


LSQ

The LSQ tool can either be run as a stand-alone


tool or right within the PCBC production scheduler.

Figure 13 Example of graphical display of geological data

Operations tools and reconciliation


Once a mine is in operation, there is a variety of
useful ways in which draw point sampling data
(grade, geotechnical and geological) can be displayed
and analyzed. A key reason for doing this type of
work is so that we can better understand if or where
there is irregular behavior with the cave itself. Some
of the analysis types are listed below:

Figure 14 Example of residual slice file to block model


conversion

Use of draw point assays for grade reconciliation


and for calibration of the model
Use of draw point assays for improved short
term forecasting using the LSQ tool already
mentioned.
Use of geological samples to supplement the
reconciliation process or to better understand
horizontal and vertical migration of material
within the cave (Figure 13)
Use of geotechnical (fragmentation) data to
better understand the relationship between draw
rate at draw points and rock type or mining area.
Use of convergence data in production tunnels to
help prevent excessive closure (or collapse) of
these tunnels.
Freeport has shown quite
convincingly at their DOZ mine that a diligent
program of monitoring convergence in these
tunnels is beneficial. In areas where high
convergence rates are observed, adjacent draw
points have an increased tonnage target which
tends to relieve the high stresses.
Seismic data and/or extensometers can be used to
help predict the location of the cave back which
can in turn be used to set up surfaces for
simulation of the rilling process which
migrates material non-vertically.
The residual slice file model can be used to reestimate a block model which can be used either
in a multi-lift mining situation or as part of a new
block model for a super-pit which some mines
are considering.

Figure 14 shows an example in which the


residual slice file (after simulation of mining the full
block cave tons) is used to re-estimate a geological
block model. This block model can then be used for
planning of another future mining block.

Recent Developments
PCBC is over 20 years old and hence should be
considered as a mature product. As such the basic
planning and scheduling work flow is well covered.
On the other hand, being mature and with a good
foundation, PCBC has provided a useful foundation
for a number of recent developments which are
summarized in this section.
Upgrades to material flow tools
Playback utility
Display tools
Each of these is considered in more detail
Material flow upgrades
Material flow is an integral part of the block
cave mining (and material depletion) process. The
entry of dilution is a significant factor in the planning
process and modeling of this has proven to be
difficult. As such, a variety of different mixing tools
have been developed within PCBC and users are then
given the choice as to which approach they would
like to adopt. This is summarized in Table 1.

Method

Ease
of use

Linear?

No mixing

Easy

Yes

No mixing base
case (In-situ)

Pre-Vertical

Easy

Yes

PCBC Default
(includes
preerosion)

Easy

Yes

Uses Laubscher
tables

mixing

Comment

Figure 15 Movement mechanisms in a block cave

Laubscher
mixing
Sequential
mixing

Harder

No

Older method,
includes
toppling

Template
Mixing

Harder

No

Most
flexible
option available

REBOP
interface

Harder

No

Not
generally
available

It differs from other material flow algorithms


such as discrete particle and cellular automaton
methods. A major advantage of Template Mixing is
its speed. Figure 16 shows a few steps in a depletion
simulation. Blue represents dilution, yellow is ore
and the intermediate colors represent progressive
mixing as the ore is extracted.

yet

Table 1 Material mixing options in PCBC

The linear methods can be applied with the Best


HOD utility to find mineable reserves before the
schedule is run. For the non-linear methods, the
mineable reserve will be a function of the mining
sequence and draw strategy. Therefore, mixing has
to be built right into the production scheduler. This is
one of the key differentiators between PCBC and
other commercial scheduling tools.

Figure 16 Template Mixing 2D example

Figure 17 shows an example for our sand-box


project using toppling, rilling and normal mixing.

The pre-mix option in PCBC was recently


upgraded to allow for the inclusion of a draw cone
erosion mechanism. This is useful as there is
increasing evidence that draw cone radii may not be
as large as is often hoped and also that the draw cone
radius changes with time. A fraction of each slice is
frozen and then an erosion rate is specified which
allows this material to be mixed with material higher
up each draw column.
Template Mixing was introduced in to PCBC in
2006. (Diering, 2007). It allows a variety of mixing
mechanisms to be simulated including vertical
mixing, rilling, toppling and fines migration. (Figure
15)

Figure 19 Block model used for PCBC/REBOP calibration

Results from the calibration exercise were really


encouraging, suggesting ways to improve both the
PCBC and REBOP modeling processes. A sample
calibration curve of Cu grade is shown in Figure 20.

Figure 17 Sandbox example with toppling, rilling and


vertical mixing

Cu% Rebop vs PCBC (N2E5)


2.00
1.80
1.60
1.40
1.20
1.00
0.80
0.60
0.40
0.20
0.00

Cu%_M3P3
Cu% Tm4

Jan-08
Jul-08
Jan-09
Jul-09
Jan-10
Jul-10
Jan-11
Jul-11
Jan-12
Jul-12
Jan-13
Jul-13
Jan-14
Jul-14

Cu %

In 2008, a joint initiative was done with Rio


Tinto, Itasca and Gemcom to provide the potential to
combine the PCBC and REBOP programs. This was
done using a hand-shake mechanism so as to
minimize the changes required to each program and
to keep them as independent as possible to facilitate
future development.

Figure 20 Example calibration curve for PCBC (orange) vs


REBOP (green)
Figure 18 REBOP results displayed in PCBC (Markers left
and cones to right)

The original version of PCBC used what we


term Laubscher mixing (Laubscher, 1994). This
was replaced by pre-vertical and sequential mixing
options in 1994 in PCBC. However, there are still
projects (or people) who like to be able to compare
back against the Laubscher mixing. So it was reintroduced into PCBC in 2008. It is also useful for
comparison against Footprint Finder results which
use the same mixing.

Figure 18 shows two examples of REBOP


results plotted within the PCBC program. The results
from REBOP are used directly in the production
scheduler and also for modification of the slice file.
As a separate, but related project, Gemcom
worked with Rio Tinto to calibrate PCBC and
REBOP against one another. Figure 19 shows the
geometry of the calibration problem. 50 fictitious
draw points were located in this block model for
testing purposes.

Figure 22 Excel map transfer utility example

Figure 21 Dilution entry.


Laubscher mixing (bottom)

The Excel map format is useful for a single


attribute per draw point such as HOD. However, if
one has multiple attributes (which sum to 100%), a
very useful display option is the pie chart. The
program will plot a pie chart at each draw point
location using data directly from the underlying
database from what is called multi-bucket format.
(Figure 23)

Pre-vertical mixing (top) vs

Figure 21 shows an example comparing dilution


entry from a single draw column. PCBC pre-vertical
mixing has more of an S-curve dilution entry where
Laubscher mixing has a straight line dilution entry
Playback Utility
This tool is used to playback or study results
from a production schedule. Display options include
Triangular Irregular Networks (TINs), contours, pie
charting, and 3D columns. Playback examples are
shown in the later sections on Freeport DOZ and
Palabora.
Display tools
Over the years, a variety of different graphical
display tools have been developed. The more recent
ones are the Excel interface which allows any draw
point related data to be exported directly into Excel in
the correct cell row and column positions for direct
display in Excel as shown in Figure 22

Figure 23 Example of Pie chart display

In addition to the static displays available, a


more dynamic display of selected information for
individual draw points by right click or mouse
movement over draw points can be very useful
(Figure 24)

Figure 26 Height of draw profile at Freeport DOZ mine


from Playback tool

Freeport Grasberg
The Grasberg block cave is scheduled to start
production as the Grasberg open pit slows down at
the end of its life. (Figure 27) (Brannon, Casten, &
Johnson, 2004) This will be a very large block cave
with production up to 160,000t/d.
Numerous
scheduling options have been evaluated using PCBC
and particular emphasis has been placed on effective
modeling of large open pit failures which will
generate additional dilution material.

Figure 24 CMS control panel with right click and


display information

Other options are size based plots (Figure 13),


3D draw columns (Figure 14) and plotting of draw
points in appropriate shapes.

Project examples
Freeport DOZ
PT Freeport Indonesia has been using PCBC
since around 2000. They are currently mining close
to 80,000 t/d, making it a large block cave mine (T.
Casten, 2008). PCBC and CMS are used extensively
for planning and scheduling at the DOZ mine as well
as for daily draw control. Figure 25 shows a plot of
forecast rock types at one step during a production
schedule. Figure 26 shows a plot of HOD for the
same mining step.

Figure 27 Grasberg block cave in close proximity to the


large open pit

Figure 27 shows the proximity of the block cave


draw columns to the large open pit.

Figure 25 Forecast rock types at Freeport DOZ mine


generated in Playback tool

10

Salvador
The Salvador mine in Chile has used PCBC
both for the detailed scheduling of individual mining
panels (Figure 30) as well as for combined
scheduling of multiple mining blocks (Figure 31).

Figure 28 Column values from Footprint Finder used for


footprint assessment

Figure 28 gives an idea of the variability of the


orebody edges and also alludes to the difficulties in
sequencing and scheduling such a large orebody (grid
size above is 200m!).

Figure 30 Slice file display and layout at Salvador Mine

Northparkes
PCBC was first used for Northparkes E26 Lift 1
around 1994 and then for Lift 2 planning and
currently for Lift 2 North (Figure 29) (Ross, 2008)
and E 48. Each lift has provided surprises and
challenges from a modeling perspective.

Figure 31 Scheduling of multiple mining panels at


Salvador Mine

As this is an older mine, current work is looking


to re-estimate the residual grades in older mined out
areas for use with future planning.

Figure 29 Northparkes E26 mining

11

Andina

Figure 34 Monthly tonnage display (poor draw control


(top) and good draw control (bottom)

Figure 32 View of three panels (lifts) at Andina mine

Palabora went through a period during which it


was difficult to achieve good draw control.
However, more recently, the draw control has been
much improved. (Pretorius & Ngidi, 2008) This is
shown clearly in Figure 34.

Figure 33 Plan of Andina third panel showing grizzly and


LHD sectors and existing development
Figure 35 Seismic data display example from Palabora

PCBC has been used extensively at Codelcos


Andina mine for a number of years. Challenges in
modeling this deposit include the multi-lift aspect
together with reliable estimation of residual grades of
mined out blocks (Figure 32), the effective
scheduling of grizzly and LHD sectors (Figure 33),
the sheer size of the project and caving issues related
to primary and secondary rock types.

Figure 35, also from Palabora shows a plot of


seismic events for one month together with draw
points and the cave Height of Draw profile (which is
different from cave back profile).
Ridgeway
The Ridgeway Deeps Mine of Newcrest used
PCBC with the Template Mixing option to study
rilling and how this impacted the mineable reserve
and overall production schedule (Burgio & Diering,
2008) (Figure 36)

Palabora
The Rio Tinto Palabora mine in South Africa
started block cave production in 2000. (Moss,
Russell, & Jones, 2004)
As the scheduler can work with historical
tonnages as easily as forward looking tonnages, the
playback tool can thus also be used for historical
analysis or reconciliation purposes.
12

Figure 38 Schematic of open pit, cave zone and Block 4


draw points at De Beers Finsch mine
Figure 36 Section of Ridgeway deeps block cave model
showing irregular cave propagation on right side

Figure 39 shows a section with some of the


residual draw columns. These are trimmed against
the known topography and the new failure material
(red) then starts to mix with the existing material
(blue).
The mixing zone is shown by the
intermediate colors.

Different scenarios were modeled to see the


effect of limited cave propagation on the East side of
the cave.
Cadia East
The Cadia East project of Newcrest provided
interesting modeling challenges as it is a large multilift project. (Figure 37) Extensive use has been made
of the Footprint Finder tool to assist with
determination of elevations together with more
accurate schedules from PCBC.

Figure 39 Addition of new failure material and mixing of


this material with existing cave rock mass

Figure 40 is similar to Figure 39 except that the


sequential mixing in PCBC is turned off. This
example shows the importance of being able to
model this process in a non-linear manner. The final
mineable reserve is required to be adjusted monthly
or every time the failure surface is modified.
Additional tools in PCBC allow for the addition of
anticipated material for the remainder of the life of
the Block 4 block cave as well.

Figure 37 Multi-lift example from Cadia East, Newcrest

Finsch
The Finsch Block 4 block cave is an example of
mining beneath an old open pit (Richter & Diering,
2004) (Figure 38). As mining progresses, additional
pit wall material is failing into the developing cave.
The remaining ore and ore/waste combination has to
be continually updated as additional material fails
into the cave.

13

Geological observations are made routinely at


draw points of up to 8 different rock types. These
were also fed into the geological block model so that
comparisons could be made of the observed vs model
rock types. Figure 43 shows the modeled rock types
vs time and Figure 44 the observed rock types vs
time. A detailed study of the differences between the
two can be very informative and lead to ways to
improve the model which may not be apparent from
the grade model / assays. The geological modeling
thus provides another dimension into the
calibration process.
Figure 40 Addition of new failure material without
additional mixing

Calibration examples
Freeport DOZ
A detailed description of the calibration curves
in figures Figure 41 and Figure 42 is beyond the
scope of this paper. (Villa, Prasetyo, & Diering,
2008) Figure 41 is for grade and it shows the extent
to which the PCBC model can be changed to improve
the fit actual against actual observations.

Figure 43 Geological composition from block model and


PCBC production schedule

Figure 41 Freeport DOZ. Calibration of grade

Figure 42 is for the Marble rock type. It shows


how the original PCBC marble curve (bottom) can be
changed to more closely approximate the geological
draw point observations (higher curves).

Figure 44 Geological composition based on draw point


observations

Palabora
Work has been done at Palabora to improve the
short term grade estimates using the LSQ tool
described above. Figure 45 shows the improvement
in the short term comparing the PCBC LSQ forecast
vs Samples.

Figure 42 Freeport DOZ. Calibration of Marble rock type

14

Figure 47 Various PCBC runs vs assayed results for IW


sector, Salvador mine for 8 years

Figure 45 Measured vs PCBC standard and LSQ adjusted


grades

Figure 46 shows a similar set of graphs, but


comparing hang up frequency. In this case, there was
no initial model forecast for hang-ups, but based on
the LSQ approach, a reasonable forecast for short
term hang up frequency was achieved.

Figure 48 Various PCBC runs vs assayed results for ICE


sector, Salvador mine for 17 months

Example of block model adjustment


In this example (Figure 49Figure 35), various
attempts were made to calibrate the PCBC results
with the observed mill feed grades. However, the
PCBC grades were too high irrespective of the
mixing parameters used. This is an example in which
the underlying block model is at fault. Reestimation of the block model with different
interpolation parameters has largely resolved this
discrepancy.

Figure 46 Measured vs LSQ modeled Hang-ups

Salvador
Various calibration runs were done at Salvador
mine. Two examples are shown in Figure 47 and
Figure 48. A detailed explanation of the curves is
beyond the scope of this paper, but the graphs show
how mixing parameters were adjusted to improve
both the model results and the confidence in other
forecast results.

Figure 49 Calibration example in which the block model


required re-estimation

Example involving old mining areas


This example considered two separate runs. In
the first (Figure 50), the block model was not
adjusted correctly for historic mining. Once this had
been recognized and appropriate changes made to the
area in which mining had taken place, a much better
fit between PCBC model grades and observed mill
grades was obtained. (Figure 51)

15

The calibration examples also clearly show the


benefits to be gained from doing a calibration
exercise using both grades and rock types. In each
case, a clearer understanding caving mechanisms is
gained from the work. This type of calibration also
strongly justifies the effort of taking draw point
samples for grade and rock types.
The development process for PCBC has been
significantly enhanced by collaborative projects with
key clients and this assistance is gratefully
acknowledged.

Acknowledgements
The authors would like to thank the following
mining companies for permissions to publish
information and figures pertaining to their projects in
this paper: Freeport-McMoRan Copper & Gold Inc.,
Rio Tinto, Newcrest Mining Limited, De Beers
Consolidated Mines Finsch mine, Codelco Divisin
Salvador, Codelco Divisin Andina and Palabora
Mining Company.

Figure 50 Grade curves measured vs PCBC before


adjustment for mined out area

The authors also gratefully acknowledge


assistance with the development of the software from
Freeport-McMoRan Copper & Gold Inc., PT
Freeport Indonesia, Rio Tinto, De Beers
Consolidated Mines Finsch mine, Codelco Divisin
Andina and Palabora Mining Company.

References

Figure 51 Grade curves measured vs PCBC after


adjustment for mined out area

Concluding remarks
PCBC has been applied to a variety of different
block cave projects and mines over the last 20 years.
Every project has its own unique challenges some of
which have been described in this paper. As the
program has evolved to meet these new problems, its
capability has been enhanced.
A key component of the modeling and program
development process has been the ongoing
calibration of PCBC against observations / sampling.
This process has clearly indicated that it is not always
the material mixing which required the most
adjustment. Careful attention is also required in areas
of past mining, or for open pit failure material or
even to the geological block model itself.
16

1.

Brannon, C., Casten, T., & Johnson, M. (2004).


Design of the Grasberg block cave mine.
MassMin, (pp. 623 - 628). Santiago.

2.

Burgio, N., & Diering, T. (2008). Simulating


irregular cave propagation using PCBC.
MassMin, (pp. 1033 - 1042). Lulea.

3.

Diering, T. (2004). Combining long term


scheduling and daily draw control for block cave
mines. MassMin, (pp. 486 - 490). Santiago.

4.

Diering, T. (2000). PC-BC: A block cave design


and draw control system. MassMin, (pp. 469484). Brisbane.

5.

Diering, T. (2007). Template Mixing: A


Depletion Engine for Block Cave Scheduling.
APCOM, (pp. 313 - 320). Santiago.

6.

Laubscher, D. (1994). Cave Mining: State of the


Art. SAIMM , October, 279 - 293.

7.

Moss, A., Russell, F., & Jones, C. (2004).


Caving and Fragmentation at Palabora:

Prediction to Production. MassMin, (pp. 585 590). Santiago.


8.

Pretorius, D., & Ngidi, S. (2008). Cave


management ensuring optimal life of mine at
Palabora. MassMin, (pp. 63 - 72). Lulea.

9.

Richter, O., & Diering, T. (2004). Production


Scheduling at Finsch Diamond Mine. MassMin,
(pp. 453 - 458). Santiago.

10. Ross, I. (2008). Northparkes E26 Lift 2 block


cave A case study. MassMin, (pp. 25 - 34).
Lulea.
11. T. Casten, L. R. (2008). P.T. Freeport Indonesia's
Deep Ore Zone mine - expanding to 80,000
tonnes per day. MassMin. Lulea.
12. Villa, D., Prasetyo, R., & Diering, T. (2008).
Calibration of mixing model to predict grade at
Freeports DOZ Mine. Massmin, (pp. 1053 1062). Lulea.

17

You might also like