Professional Documents
Culture Documents
http://www.tunneltalk.com/Santiago-Metro-Apr03-NATM-optimisation.php
Page 1 of 6
Apr 2003
05-11-2015
Page 2 of 6
Part 2: Current NATM construction for the Santiago Metro, Chile, is costing some 40% less than NATM running
tunnels constructed five years ago. Value engineering processes are creating even greater potential economies on
the coming Line 4 contracts. How these economies have been achieved and where Metro goes from here on its
path of design and construction evolution is investigated.
Technical feasibility of NATM construction in Santiago, as demonstrated by projects in 1994-5 and 1997-2000, gave
Santiago Metro's management the confidence to take major leaps forward for the current Line 2 and Line 5 extensions
and for the underground sections of the new Line 4.
First, all the underground stations and connecting running
tunnels are mined. There are no open boxes, to cause the
disruption and closure of public roads endured during earlier
open-cut Metro works. Secondly, a combi-shell lining system
has been adopted for all underground spaces. Previous NATM
running tunnels were finished with 400mm thick heavily
reinforced in-situ concrete linings over 200mm-250mm of
primary shotcrete support. Running tunnels on the current
works are lined with 150mm-200mm of initial reinforced
shotcrete and finished with a 250mm-300mm secondary lining,
for a total 400mm-450mm shotcrete finish.
These two strategic decisions represent a large part of the
reported 40% cost reduction of subsurface metro construction
for the current extensions, compared to the 1997-2000 Line 5
As a result, most current excavations are less than one tunnel diameter deep. With top of rail at 17 -18m below ground
2
surface, the crowns of 17m wide x 14m high (150m ) station caverns lie just 6-7m below surface, with 10m-12m cover
2
impressive. The junction of 150m mezzanine access adits, with 150m station platform caverns and 60m -70m
double-track running tunnels either end make for spectacular NATM excavations and all beneath limited cover.
http://www.tunneltalk.com/Santiago-Metro-Apr03-NATM-optimisation.php
05-11-2015
Page 3 of 6
These issues were considered during basic design of the new works by Cade-Idepe/Geoconsult, and detailed designs
have since introduced refinements and different philosophies for NATM structures in these conditions. Such differences
have considerable influence on constructability and tunnelling crews admit to having favourites among the different
design specifications.
Fig 1 - (clockwise from top) Details of the junctions zones at La Clstema Station, illustrating the
increased size of the adits for breakout of lateral platform tunnels; a plan of La Cisterna Station shows
its location under Gran Avenida main street; detail of the combi-shell primary and final shotcrete lining
system that represents part of the reduction in subsurface metro extension costs
La Cistema Station at the end of the Line 2 south extension, connecting with Line 4, is the 1argest station on the
current works from a passenger access point of view. From a large access box, three 150m2 passenger access adits
extend laterally some 7m under the adjacent Gran Avenida main street to intersect the 150m2 x 140m long station
platform cavern. Designed in detail by DSC, the large station caverns are being excavated by contractor DPS using
the two sidewall drift and central core excavation sequence. Work on this large station contract started in
September 2001. When TunnelTalk was on site, excavatin of the two outer access adits was complete, work had
started on the middle access adit, and the tunnelling crews had broken into excavation of the perpendicular station
platform tunnels. La Cisterna Station with its 500mm of final combi-shell finish (300mm primary + 200mm
secondary) is scheduled to be handed over to M&E contractors in September 2003. The two new stations and
2.2km of track on the Line 2 south extension is due to open in December 2004. Subsequent surface alignment
construction-of Line in this area will run over the top of the mined Line 2 station structures.
Design differences
2
A major difference in design is the division of multiple headings for excavation of large faces. For 150m access adits
Cade-ldepel/Geoconsult favours full span top headings, followed by a bench and invert sequence, with a wedge of
unexcavated ground in the top heading providing face support and worker access. Under shallow cover, full span top
headings require pre-support using spiling or mini-pile forepollng to stabilise conditions and control potential surface
settlement. Larger boulders in the ripio had caused drilling accuracy and rod jamming problems for long, small
diameter pre-support systems. These were overcome using shorter, larger diameter pipe roof methods, with 140mm
diameter pipes installed and filled with concrete prior to excavation advance.
2
advance.
http://www.tunneltalk.com/Santiago-Metro-Apr03-NATM-optimisation.php
05-11-2015
Page 4 of 6
With regard to the long-term stability, DSC believes that lattice girders contribute minimal load bearing support and
could be omitted from the primary lining, with steel fibre providing extra strength or load bearing support where
necessary. Engineers in other design groups agree in certain instances. As Martin Bfer. Senior Design Engineer with
Geoconsult explained: "The arguably limited contribution of lattice girders to short term load bearing capacity of the
primary lining is an advantage which is highly appreciated. We must also design for the possibility of earthquake
activity during construction, which requires a margin of stability to allow primary lining to stand for 1-2 years before
the final lining goes in. If you remove the lattice girders, their contribution to the load bearing safety factor would have
to be substituted with extra layers of wire mesh or steel bar reinforcement. Steel fibre has been considered for Line 4
contracts and in principle, whenever structural efforts do not require wire mesh or steel bar reinforcement, steel fibre
is preferred, but we would use it only in the running tunnels. In our opinion bending moments would be too great for
its application in station cavern excavations."
Engineers within Metro are yet to be convinced and girders
remain in all NATM designs. In addition to their arguably
limited contribution to load bearing requirements, girders also
help maintain a correct tunnel profile. Although this could be
achieved by other means, the purpose is important in Santiago.
"If the distance between the girders is increased from just 1m
to 1.2m centres in this ground," said Otto Gerstgrasser, NATM
site supervision engineer for DSC on the Line 2 south
extension, "the shape of the profile suffers; and shotcrete
applied to fill excavation outside the design fine is a cost to the
contractor."
To date, the largest percentage of shotcrete by far in Santiago
is dry mix with nearly all contractors on current contracts
using Aliva dry mix rotor units and hand-held nozzles.
http://www.tunneltalk.com/Santiago-Metro-Apr03-NATM-optimisation.php
05-11-2015
Page 5 of 6
Fig 4. Binocular configuration design for the Plaza Egaa and Los Orientales stations located in a clay
zone near the Mapocho River
For the two underground stations located in the clay dominated deposits on Line 4 (Plaza Ega and Los Orientales,
Cade-idepe and Geoconsult have designed a binocular configuration for the two 140m long stations located in the
clay zone. Volume losses and surface settlements are expected to be higher then in the ripio, at up to 30mm on
the runing tunnels. To control deformation in the stations, sequenced excavation will start with a 10m high x 6m
wide pilot heading, into which a series of 1.1m diameter permanent central support columns on 4.7m centres will
be cast, working back to the access point.
This will be followed by excavation of the binocular tubes either side, progressing together on a staggered advance
and on a top heading, with temporary invert and bench/invert excavation sequence. Beneath an average cover of
8m-9m, the station cavern will be supported initially with 300mm of reinforced shotcrete and finished with a
200mm thick in-situ concrete lining.
Production cycles would also improve by using higher output wet-mix shotcrete nozzle booms and mobile units. In
conjunction with purpose designed excavator machines, more headings could be developed. At present, advance in
many cases is limited by logistics of one or two headings.
While there are these areas presenting room for production improvement, it must be said that the quality of the
workmanship on display in Santiago is impressive, with contractors undertaking NATM work with very little or in some
cases no previous tunnelling experience.
Commenting on the differences between detail designers, Aculla said that it is from these differences that Metro will
establish its own set of design standards and norms for future works, "We believe we have made a good compromise
between speed of advance, application of modern technology, cost and quality," he said, "and that we have achieved
good optimisation between construction needs and permanent works requirements. Our efforts to research cost
savings and improve quality and construction rates, however, will continue as we progress network expansion
projects."
References
Santiago Metro withstands massive earthquake - TunnelTalk, Mar 2010
Santiago Metro goes underground with NATM - TunnelTalk, Apr 2003
http://www.tunneltalk.com/Santiago-Metro-Apr03-NATM-optimisation.php
05-11-2015
Page 6 of 6
Search
Current
Stay Connected
Forward
Marketplace
Back to top
Home Office
Archive
Feedback
Alert
http://www.tunneltalk.com/Santiago-Metro-Apr03-NATM-optimisation.php
05-11-2015