Professional Documents
Culture Documents
SLQS Journal
Editorial Committee
Ajantha Premarathna FRICS, FIQS(SL), ACIArb.
Dhammika T. Gamage
Editorial Policy
We, the editorial committee reserve the right to select, reject, edit, and excerpt articles at our sole discretion. We will
publish no article which, in the opinion of the editorial committee, can be reasonably interpreted as insulting or offensive
to any individual or group. We will not return unsolicited manuscripts. The opinions expressed in articles contained in the
SLQS Journal are the opinions of individual authors and not necessarily those of the SLQS Journal editorial committee.
Articles are provided for the general interest of the quantity surveying and contract administration community, but the
information contained therein does not constitute legal advice and should not be relied on as such. Neither the SLQS nor
the individual authors assume any responsibility for the accuracy of information reported.
The editorial committee assumes no responsibility for failure to report any matter inadvertently omitted or withheld from
it. The mode of citation utilised within the articles and for the bibliography would be the Chicago method.
Email your own creations to journal@slqs-uae.org with your passport size photograph and brief profile of yourself which
should not be more than 35 words.
December 2010
SLQS JOURNAL
CONTENTS
Page
Editorial
Letters of Intent Beware of the Risks
Ragupathy Nadarajah MSc MRICS
Management of Change
Dr. D.A.Harendrasinghe Gunaratne Ph.D; D.Sc;
GC&G;MIESL; MIIE(SL)IEng; MRICS; AAIQS; AIQSSL; Fellow APQSESL; MCIArb; Reg.Arb.
NACSL; Mem.ICCSL; Mem.CCISL; Mem.AACE; Mem.SAVE; Mem.SLAQ; Mem.SLGS
15
18
21
Challenges Facing the Establishment of the Quantity Surveying Profession in Sri Lanka
Ranjith Chandrasiri MRICS MCIOB DipQs(UK) AAIQS ACIArb AIQSSL FIPMSL
24
28
30
The Implied Terms and the Damages of Contracts under Common Law.
A. M. Manju Sri Nandana BSc. (Hons), MRICS, MCIArb, MIIE (S.L.) I Eng, GCGI (UK).
35
38
41
46
SLQS JOURNAL
December 2010
Editorial
I am writing this editorial shortly after our annual get-together held on 09 December, 2010. On behalf of
the SLQS Committee, we, SLQS-Journal Sub-Committee congratulates the SLQS-UAE membership and their
families for their participation. The get-together was a most pleasurable event and may be considered a positive
beginning to the New Year 2011.
The need to better serve our growing membership within the UAE and the Middle East has been recognized by
the SLQS UAE and arrangements has been made within the 2011 agenda to accommodate such requirements.
I believe SLQS Committee can also improve service to our local membership, partly through becoming more
receptive to feedback from our innovative young membership, which can later be transformed into constructive
proposals or new resolutions within the group.
The lull in the international economy that we are experiencing can be used to further enhance our role as pivotal
industry professionals, through Continuing Professional Development (CPD), programmes that allow us to
develop the competencies necessary to conduct our duties in exemplary fashion. I am sure that you will agree
with us in saying that it is our duty to the industry we are part of to ensure that we are in prime professional
condition to carry out the tasks we are entrusted with. The Editorial committee believes that our relatively young
SLQS-Journal is able to shed some light on your search for the path to best practice.
In this issue, we are delighted to publish Prof. Samaratungas revolutionary paper of Head office Overheads Revisited,
adding great value to this edition. We are also pleased to note some eminently practical and useful contributions
of Sajeewa Amantha in his article on Project Controls, and Crishantha Fernandos Risk Management. Volume 6 is
further enhanced by the article entitled Letters of Intent by Ragupathy Nadarajha, warning for the misuse of this
concept implemented across the industry. Niluka Dominigos discussion of Construction Waste Management is a
good academic proposal to a leading waste generator; the construction industry.
Ranjith Chandrasiris article on Quantity Surveying in Sri Lanka, mentioning both its history and way forward
touches on the roles and responsibilities of all practicing professional quantity surveyors and also all professional
institutions associated with the quantity surveying practice in Sri Lanka.
While sharing his wide experience in assessment of professional competence, (APC), Ajantha Premarathna added
value to this issue and Dr. H. Gunarantha and Buddhika Jayathilaka joined the journal through the management
avenue.
On a closing note, we ask all our readers to recall that this journal is your property. As such, its performance is
indeed your concern and all feedback and articles are not only appreciated, but an active part of being a member
of the SLQS and the construction community.
Yet again, the thanks of the Editorial Committee due to Vishwa Chaturangi for her assistance in editing and to
those writers who have contributed to SLQS-Journal Volume 6.
We anticipate your academic pleasure and hope that you assist us in ensuring it for future readers as well, by
providing high-quality articles of your own in the near future.
On behalf of the editorial committee,
Dhammika T. Gamage
December 2010
SLQS JOURNAL
Letters of Intent Beware of the Risks
Ragupathy Nadarajah MSc MRICS
Senior Contracts Administrator- Thiess John Holland, TBM Tunnelling Division, Airport Link, Northern
Busway and Airport Roundabout Upgrade Project, Brisbane, Australia. A Quantity Surveyor with over 25
years experience in Sri Lanka, Hong Kong, Macau and Australia. Member of the Royal Institution of Chartered Surveyors
Abstract
Introduction
December 2010
SLQS JOURNAL
In Monk Construction Ltd v Norwich Union Life Assurance
Society (1992) the Court of Appeal found that the
letters of intent can give rise the following three possible
scenarios;
1. There may be no contract at all. i.e. pure letter of
intent.
2. There may be an ordinary contract.
3. There may be an if contract.
Similarly, in the case of Diamond Build Ltd v Chlapham
Homes Ltd (2008), the courts recognised and confirmed
that three types of letters of intent exist:
1. Pure letters of intent which do not give rise to
contracts at all;
2. Simple contracts, which are capable of being
binding, but are entered into with the intention that
they will be superseded by subsequent finalisation
and execution of the formal contract; and
3. Those that are (so far as they go) the whole contract
(which may be supplemented by verbal agreements,
or even need further terms implied into them), with
no intention that they will be superseded by a formal
contract.
In deciding whether a letter of intent falls into one of
the three types mentioned above, the courts have taken
into account both the wording of the letter of intent and
the perceived intention of the parties at the time of its
issuance.
Quantum meruit
SLQS JOURNAL
In relation to whether a contract had been created, the
trial judge re-affirmed that;
there can be no hard and fast answer to the question
whether a letter of intent will give rise to a binding
agreement, everything must depend on the circumstances
of the particular case
In summary, if the letter of intent is non-binding then the
following would be some of the key rights and obligations
of the parties:
1. The contractor is entitled to be paid on a quantum
meruit basis for work performed
2. The employer will not be able to claim damages for
delay
3. The contractor will not be liable for defects
4. Limitation for action would be 6 years
December 2010
December 2010
SLQS JOURNAL
9. Make it clear that once the contract is concluded it
will apply retrospectively
McNair, Milliner and Mazzochi (2003), suggest that a
binding letter of intent (a contract) is preferable for the
owner, because it creates contractual certainty with respect
to those matters stipulated in the letter. Where a binding
letter of intent needs to be issued, they recommend to
include the wording This letter of intent is intended to
create a legally binding contract between the parties
Acknowledgements
References
1
Concluding observations
6
7
8
December 2010
SLQS JOURNAL
Project Control Practical Aspects
Sajeewa Amantha B.Sc.(QS) Hons. MRICS
Sajeewa is a Quantity Surveyor graduated from University of Moratuwa, Sri Lanka and currently working in
Manila, Philippines, for Australian managed project manegment organisation.
Introduction
SLQS JOURNAL
information on the Project such as scope, definitions,
programming, meetings, reporting, procurement, and
auditing.
The Project Control Manager is the key person responsible
for the implementation of the Project Control Plan. The
Project Control Manager shall ensure that component
personnel are engaged to effect proper control and
reporting regimes over the project. The Project Control
Manager shall be authorised to operate within limits
required by the project control scope. On smaller projects,
the Project Control Managers role will be played by the
Project Manager and he or she is then will be responsible
for the implementation of the Project Control Plan.
Programme Management
10
December 2010
December 2010
SLQS JOURNAL
Project Control Manager should not ignore these facts
but should understand the implication of the action that
is about to be taken and not ignore the effect their action
will ultimately have on the final outcome of the project.
Risk Management
Procurement Management
11
December 2010
SLQS JOURNAL
includes elements of the Works to be completed by
Package Contractor(s), latest date for commencement of
subcontract works and from that, a timeline established
for the procurement of subcontractors for each package.
The selection of subcontractor will be based on capacity,
availability, and price. Standard conditions of contract will
be used with any particular terms in preparing necessary
agreements for suppliers and package contractors.
Project Organisation
Contract Management
12
Meetings
SLQS JOURNAL
December 2010
Document Control
Project Reporting
13
December 2010
SLQS JOURNAL
performance. The procurement report shall also include
a copy of the procurement status and expediting status
reports and shall detail key issues and mitigation strategies
and a summary of risks and opportunities exists.
Summary
14
December 2010
SLQS JOURNAL
Management of Change
Dr. D.A.Harendrasinghe Gunaratne Ph.D; D.Sc;
Chartered Quantity Surveyo & Engineer; Mediator, Arbitrator & Contract Administrator
GC&G;MIESL; MIIE(SL)IEng; MRICS; AAIQS; AIQSSL; Fellow APQSESL; MCIArb; Reg.Arb.
NACSL; Mem.ICCSL; Mem.CCISL; Mem.AACE; Mem.SAVE; Mem.SLAQ; Mem.SLGS
15
December 2010
SLQS JOURNAL
Internal forces:
External forces:
Organizational Entropy
Quite often, due to the intertia of its human resources,
organizations tend to set up self-imposed blinds which
limit the area and range of their vision. Executives are
16
Resistance to Change
People resist change because it is easier to do what they
do than to learn something new. People fight change for
highly personal reasons. The process of implementation
of change will enable managers to find out the limitations
of the people, namely, whether it is for personal reasons or
in the best interests of the organization. Usually a person
is normally in between these two extreme conditions.
Those who are closer to the former end will intensely
resist change and will seldom wish to know the reasons
for change, while the others will show an increasing
desire to cooperate. The change is faster with high
levels of education, communication and greater human
aspirations about what people should have as an expected
part of our life.
December 2010
SLQS JOURNAL
Culture and Change
tell the client that the work was not in his field;
ask the client to employ a specialist;
retain responsibility but pay the specialist out of his own pocket then if the advice proves
faulty the person giving him the advice will owe the same duty to him as he owes to the
client.
17
December 2010
SLQS JOURNAL
Life-cycle Approach to Minimise
Construction Waste
D.D.A. Niluka Domingo B.Sc. (Hons.)
Niluka is a Quantity Surveyor graduated from University of Moratuwa, Sri Lanka and currently reading for a
PhD in Construction Management at the University of Loughborough, UK.
Abstract
Introduction
18
December 2010
SLQS JOURNAL
Pre-design Phase
Design phase
Procurement Phase
Construction phase
19
December 2010
SLQS JOURNAL
parts of the world to identify on-site waste origins and
waste minimisation measures. Many research findings
concluded that waste origins in the construction stage were
due to poor material storage and handling, negligence,
material ordering errors, poor record keeping, poor
workmanship and lack of site waste management plans.
To facilitate waste reduction, researchers suggested the
following practices to implement during the construction
phase in a project.
Conclusion
Construction waste generation is a reality in the 21st
century with the rapid developments in all parts of the
world. Even though physical waste generates during the
construction or demolition phase of a project, waste
20
References
1. CIRIA,1995. Waste Minimisation and Recycling in
Construction: A Review, Guthrie, P. and Mallett,
H. (eds), Construction Industry Research and
Information Association, London.
2. Dainty, A.R.J. and Brooke, R.J., 2004. Towards
improved construction waste minimisation: a need
for improved supply chain integration. Structural
Survey, 22, 20-29.
3. Innes, S., 2004. Developing tools for designing
out waste pre-site and onsite. In: Proceedings of
Minimising Construction Waste Conference:
Developing Resource Efficiency and Waste
Minimisation in Design and Construction, October
21, New Civil Engineer, London, United Kingdom
4. Loosemore, M. and Teo, M.M.M., 2001. A theory
of waste behaviour in the construction industry.
Construction Management and Economics, 19,
741 - 751.
5. Macozoma, D.S., 2002.Construction site waste
management and minimisation: international report,
International Council for Research and Innovation
in Buildings, Rotterdam, available at:www.cibworld.
nl/pages/begin/Pub278/06Construction.pdf
6. McDonald, B., and Smithers, M., 1998.
Implementing a waste management plan during
the construction phase of a project. Journal of
Construction Management and. Economics, 16(1),
7178.
December 2010
SLQS JOURNAL
21
December 2010
SLQS JOURNAL
that the price of rebar, concrete and cement increased
rapidly during the years 2008 and 2009. The price
increase was unusual when compared to the last five to
ten years, and even an experienced contractor could not
have foreseen this, thus reducing the contractors profit
or even loss from the project. The shortage of material
availability in the market is a negative consequence of
material price increase, which also interrupts the progress
of work.
Furthermore, poor performance of subcontractors,
inclement weather, disputes and claims, poor site
management are leading factors when delivering a project
on time.
Moreover, the penalty or liquidated damages imposed in
the contract could lead to unexpected hazards; of course,
this clause is required to drive the contractor to complete
the project on time. However, if the actual progress is
behind schedule, he may take precautions to speed up the
work to avoid penalty, which would lead to unexpected
risks, which may have not been identified from the
beginning of the project.
Apart from the above, insufficient labour force and lack
of skilled labourers was the another major problem
contractors faced in Middle East region. This always results
in the delay of the construction progress. Further, using
more unskilled labourers or utilizing the available labour
force without giving them a sufficient rest increasing the
possibility of causing an accident on a work site, leaving
the site safety at high risk.
Also, poor communication, different cultures, personal
attitudes and poor safety are other factors which may
cause harmful hazards. The probability of occurrence of a
hazard may decrease but consequences may be high.
Once a risk is identified, the next step is to analyze it. This
is the process of evaluating identified risks to discover
their extent and the way responses should be prioritized.
Most risk analyses are carried out in two stages:
22
1
2
3
4
2
4
6
8
3
6
9
12
4
8
12
16
5
10
15
20
10
15
20
Level of Risk (R)
25
SLQS JOURNAL
The final stage of the risk management process is the
decision on how to respond to risks and opportunities,
having identified and analyzed them. In essence, the
decision is simple to do something or to do nothing
(Martin Loosemore p.155). The following paragraphs
describe the ways in which one may respond to risks.
Firstly, risk pre-control is the most desirable way to
eliminate risk, thus preventing the risk from occurring.
Carefully studying tender documents such as soil
investigation reports, specifications, drawings and
physically visiting the actual site before tender could
avoid most risks associated in the project.
Secondly, reducing probability of occurrence could reduce
the hazard of the risk, similar to how conducting safety
induction procedures could reduce the risk of accidents
or injuries. Placing construction materials on time and
following up the delivery of materials could reduce the
probability of delay delivery. It is also important that
managers have reactive strategies in place to deal with
crises if and when they arise. This was obvious during the
global financial crisis which affected businesses in recent
years.
Thirdly, some risks in the construction industry can be
transferred or shared between project members. The main
benefit of passing on a risk to another party or sharing
with members is that the chances of the risk increasing
are reduced. Most risks which have been identified so
far on this project are transferred to another party and
few of them are shared between them. Nevertheless, in
transferring risks, there is a cost, which is a premium or
additional cost charged by the party that absorbs the risk.
Insurance is the most common type of risk transfer to a
third party. The risks passed on to insurance companies are
typically of very low likelihood and very high impact.
Finally, where risks cannot be eliminated, transferred or
avoided, they must be absorbed if the project is to proceed.
This requires sufficient margin or risk contingency in the
projects finances to cover the risk should it occur.
Once the decision has been made about the way to
respond to a risk, regular review and, where necessary,
revision of risk assessments must be undertaken. Risk
assessment should also be reviewed following an accident,
incident or dangerous occurrence to ensure that control
measures are revised to prevent reoccurrence. Managers,
December 2010
23
December 2010
SLQS JOURNAL
Standard of Education:
24
Standard of Education
Supervised Training Programme
Fee Competitions among Practitioners
Experience, quality and standard
Employment opportunities
Establishing the Profession
December 2010
SLQS JOURNAL
surveyors in Sri Lanka and foreign countries before the
recession of the global economy.
Supervised Training:
Fee Competition:
25
December 2010
SLQS JOURNAL
experience and qualified professional quantity surveyor it
may be possible to minimize disputes that may arise due
to errors in the bidding and contract documents prepared
by inexperienced quantity surveyors. The following
example illustrates one of the disputes which occurred
due to poor drafting of tender and contract documents:
The clause stated below was abstracted from preamble
notes given in a measure and pay contract, where the
Employer was a Statutary Authority.
If the BOQ does not contain any work item which is to be
executed by the contractor in accordance with the drawings
or specifications, the cost of the missing work item is deemed
to be included within other items.
The reason for the error seems that the quantity surveyor
who was appointed by the architect copied preambles
notes from a lump sum contract rather than preparing
particular preamble notes for the project and failed to
grasp the unfairness of the terms which he included in
the contract and their potential legal implications.
Due to recent changes in technology, intelligent buildings
and laboratory buildings have a higher proportion of
mechanical and electrical installations compared to
traditional buildings. Quantity surveyors would not be
able to perform their duties for such buildings unless
they have reasonable knowledge and experience in new
technology.
Employment Opportunities:
26
December 2010
SLQS JOURNAL
Representation:
27
December 2010
SLQS JOURNAL
Setting Smart Objectives
Buddhika Jayatillake MBA BSc(Hons) FCIOB MRICS AAIQS
Buddhika attained his first degree from the University of Moratuwa, SL in 1993 and subsequently graduated as a Master of Business Administration from the University of Durham, UK. At present, Buddhika is an
Associate Director of Davis Langdon, an AECOM Company. He is a Chartered Quantity Surveyor whose
expertise include strategic procurement/outsourcing and asset management.
Introduction
28
December 2010
SLQS JOURNAL
although it could be a quite relevant personal objective
to the employee (unless of course, the employees work
performance is likely to be affected by the employees
weight). However, there could be some occupations
where losing weight is a quite relevant objective.
All smart objectives should be Time-bound. That is the
objective should be associated with an achievable time
target. Having measurable interim time-bound targets
will also help ensuring progress towards achievement of
the objective.
29
December 2010
SLQS JOURNAL
Partnering in the Construction Industry
B. Darshanie Taraka Perera BSc (Hons) TCInst.CES
Quantity Surveying, University of Reading, UK
Introduction
Partnering is considered a radical departure from
conventional procurement approaches in the construction
industry. According to the Joint Contracts Tribunals
(JCT) practice note on partnering: it is neither a
particular procurement approach, nor is it a particular
type of contract: it is about culture and the way in which
the participants view and manage the project.
The key objective of developers when implementing any
form of construction contract is the appointment of
appropriately skilled and experienced contractors on the
basis of the right price, programme and risk allocation.
In a market where the balance of power between the
contractors and employers is shifting, this objective is
increasingly hard to achieve. Partnering is a process that
is being used with increasing frequency in the UK and is
slowly being recognised in the UAE as a solution for the
afore-mentioned matters.
Partnering has been defined by number of authors
in different words. However the essences of all those
definitions means that it is a management approach
used by two or more organisations to achieve specific
business objectives by maximising the effectiveness of
each participants resources.
Partnering in construction contracting started getting
earnest attention in the UK through the Latham report
Constructing the Team (1994). Sir Michael Latham drew
attention to the benefits of partnering in order to avoid
the problems in conventional adversarial procurement
methods. The concept has been well supported by Sir
John Egans report Rethinking Construction (1998). In
it, he emphasized the need of applying principles of the
automobile industry, such as total quality management,
30
Development of Partnering
December 2010
SLQS JOURNAL
Strategic Partnering Second Generation
Figure 2 Seven Pillars of Partnering (Partnering in the construction industry, John Bennett
& Sarah Peace - 2006)
Figure 3 - Strategic Collaborative working (Partnering in the construction industry, John Bennett
& Sarah Peace - 2006)
31
December 2010
SLQS JOURNAL
party best able to manage the consequences of their
occurrence
The ICE published NEC Partnering Option X12 is
primarily derived from the Guide to Project Team
Partnering published by the Construction Industry
Council. It is not a separate agreement but has been
drafted as a secondary option for incorporation into the
existing NEC family of contracts.
Option X12 is intended for multi-party partnering where
the agreement can consist of single or multi-projects.
All parties who are intended to make up the projects
partnering team will require the inclusion Option X12
in their contracts respectively.Key features of Option X12
include:
The parties must recognize that by entering into
the contract, they are undertaking responsibilities
in addition to those detailed within the basic NEC
contract. Responsibility is still retained for all the
sub-contractors in the chain below.
Where one party misses a particular target, due
to poor performance, thereby letting the other
members down, all parties may lose their bonus for
that target.
Option X12 does not include direct remedies
between non-contracting partners to recover losses
suffered. Remedies (if any) are a matter between the
parties under their individual contracts. This will
apply to all levels of the chain who are part of the
partnering team
PPC 2000 was published by the ACA and is the first
standard form of contract for project partnering. The
authors of PPC2000 claim that it puts partnering
relationships into a contractual context. It was launched
by Sir John Egan and was recommended by several bodies
such as the Housing Forum, Construction Industry
Council in the UK
Some of the key features included in this form are as
follows.
the integration of the project team under a single
multi-party contract, in which all parties - client,
consultants, contractors and specialists - have rights,
obligations and liabilities with respect to each other
governs the pre-construction phase as well as the
construction phaseprovides a procedural framework
that supports the partnering process
Supply chain management on an open book-basis
32
Benefits of Partnering
December 2010
SLQS JOURNAL
Drawbacks of Partnering
Cultural Barriers
Economic Barriers
33
December 2010
SLQS JOURNAL
The Impact of Market Changes
Conclusion
REFERENCES
-
-
-
-
-
-
-
-
-
-
-
-
34
December 2010
SLQS JOURNAL
The Implied Terms and the Damages of
Contracts under Common Law.
A. M. Manju Sri Nandana
BSc. (Hons), MRICS, MCIArb, MIIE (S.L.) I Eng, GCGI (UK).
Senior Quantity Surveyor, Trafalgar Technical Services Limited, UAE
Damages
Quantum meruit
Specific performance/ specific Implementation
Injunction / Interdiction
David Kelly & Ann Holmes, Principles of Business Law, 1998, Page 147
35
December 2010
SLQS JOURNAL
The modern rules relating to remoteness are based on tests
originally formulated in the case of Hadley v Baxendale
(1854), where it was said that damage is not too remote if
either of the following is satisfied:
36
1.0 Bibliography
Legislation
-
-
Case Law
-
-
-
December 2010
SLQS JOURNAL
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Internet Sources
Other sources
http://sixthformlaw.info/02_cases/mod2/cases_stat_
interp.htm >accessed 7/01/10
http://www.scotcourts.gov.uk/sheriff/index.asp
>accessed 25/01/10
37
January 2011
SLQS JOURNAL
An Out Look of the APC Assessment of
Professional Competence
By an APC Assessor
Ajantha Premarathna FRICS, FIQS-SL, ACIArb
has been a member of the RICS since 1993, and a Fellow since 2000, a fellow member of IQS-SL, holds
ACIArb and works as a Director of Commercial and Contracts, for Dubai Properties. He has over 25 years
of experience in Quantity Surveying and Contract Administration in Sri Lanka, Oman and the UAE. He
regularly acts as a Chairman during RICS APC interviews; Ajantha is also a member of the RICS World Regional Board for the MENEA region, and is a representative of Institute of Quantity Surveyors of Sri Lanka
for UAE.
38
December 2010
SLQS JOURNAL
39
December 2010
SLQS JOURNAL
contractual issues for the report for critical analysis. As
examples, it could be a simple issue related to variation,
measurement, tendering, selection of tenderers, mode
of payments, ambiguity in documents, pricing and
correspondences etc. The issues like claims, settlements
of disputes, arbitrations are interesting topics and writerfriendly to analyze critically. Other main objective of the
report is not the number of issues described in the report
by the candidates it is to demonstrate to what extent the
candidate has been involved with the issues and how the
candidates has handled the issues in his capacity. The
logical and factual presentation of the issue(s) is the most
important in the report. Using of many appendixes may
confuse the reader of the report. Using of tables, graphs,
graphics, photos etc. at the appropriate place of the report
is more effective than adding several appendixes at the
end of the report. This will enhance the readability of the
report.
The critical analysis report would be the basis for the start
of the interview. It will basically start to understand;
Has the candidate identified the key issues?
Have the options been considered and have good
sound and logical reasons been given for those
options rejected?
Are the chosen solutions supported by reasoned
judgment and has the candidate demonstrated
sound problem solving skills?
Does the critical analysis contain a conclusions
together with an understanding of the lessons
learned?
Has the candidate demonstrated a high level of
written communication skills in terms of spelling,
grammar and presentation?
40
December 2010
SLQS JOURNAL
Introduction to Innovation
Innovation in General:
41
December 2010
SLQS JOURNAL
In the current scientific world, innovation in most
businesses depends on the knowledge management of
the organisations. This encourages many writers to focus
on verity of theories to identify and manage tacit (gain
through experience) knowledge, explicit (quantified and
systematic) knowledge, etc. From the literature, it seems
that most US and European companies have adopted
knowledge management strategies and are actively
using them to further their businesses. Following are
comparisons of some of the sub-topic areas on which many
industries have been focusing, to improve innovation and
identification of where the construction industry stands.
42
Problem Solving:
December 2010
SLQS JOURNAL
feedback to the management through a bottom-up
information system.
In construction, we mostly see a top-down information
system, which does not encourage innovation and creativity.
The workers involvement or use of their comments based
on practical problems are rarely incorporated into the
design management process. However, with the advent of
globalisation, the current trend seems to encourage this
bottom-up information system. For instance, some hotel
and residential development projects encourage new ideas
based on customer comments mainly due to competition
in the market environment.
Prototyping:
43
December 2010
SLQS JOURNAL
many construction companies share internal cost details
with selected employees in different stages. This inhibits
industry innovation. Activities due to climate change and
global warming have large impacts on the construction
industry. The recent tsunamis and cyclones are prior
warning to the industry.
Continuous innovation:
44
Conclusion
December 2010
SLQS JOURNAL
has now come to rethink and apply effective measures to
promote innovation and creativity in the Construction
industry.
References:
White, Frost and others -v- Chief Constable of South Yorkshire and
others [1999]
The House considered claims by police officers who had suffered psychiatric injury after tending
the victims of the Hillsborough tragedy.
Held: An employer has a duty to protect his employees from physical but not psychiatric harm
unless there was also a physical injury. A rescuer, not himself exposed to physical risk by being
involved in a rescue was a secondary victim, and as such not entitled to claim. Primary victims are
victims who are imperilled or reasonably believe themselves to be imperilled by the defendants
negligence. Lord Steyn: (T)he law on the recovery of compensation for pure psychiatric harm
is a patchwork quilt of distinctions which are difficult to justify In my view the only sensible
general strategy for the courts is to say thus far and no further. The only prudent course is to treat
the pragmatic categories as reflected in [case law] as settled for the time being, but by and large
to leave any expansion or development in this corner of the law to Parliament. In reality there
are no refined analytical tools which will enable the courts to draw lines by way of compromise
solution in a way that is coherent and morally defensible. It must be left to Parliament to
undertake the task of radical law reform.
45
December 2010
SLQS JOURNAL
Head Office Overheads Revisited
Prof. Indrawansa Samaratunga
46
Insurance.
Travel.
Bad debts.
Entertainment.
Pantry expenses.
Contributions.
Sponsorship fees.
Idle resources.
Training.
December 2010
SLQS JOURNAL
should be distributed over the relevant period.
(c) Insurance costs and financing costs of projects should
not be included in the Head Office Overheads
account. (They should be in the project accounts).
(d) Claims consultancy fees should not be included in
the Professional Fees head.
(e) Any bad debts written-off under the Head Office
Overheads should be completely removed from the
calculations.
(f ) Cost of idle resources should be in the project
accounts and not in the Head Office Overheads
account. (It is permissible to allow the cost of some
idle resources such as the asphalt plant of a road
works contractor to be in the Head Office Overheads
account).
(g) Cost of an employee (such as a Commercial Manager)
whose time is totally dedicated to a project/projects,
should not be in the Head Office Overhead account,
despite being stationed at the Head Office.
(h) Sponsorship fee/parent company fee paid as an
annual/monthly sum of money or as a percentage of
the revenue could be a Head Office Overhead, but
not if it is a portion/percentage of the profit.
Once the Head Office Overheads account is rationalized
in the above manner (lets call it the Rationalized
account), it would be suitable for prolongation cost
calculations.
Where a project completion had been delayed, it is not
difficult for a Contractor to demonstrate (using daily
records, photographs, correspondence etc.) that the cost
of his Site Overheads increased due to the necessity of:- supervision staff to stay longer on Site
- site huts to be maintained for a longer period
- tower crane to be retained on Site longer than
previously planned
- performance security, insurance etc. to be extended
- etc.
The prolongation of these Site Overheads are manifest
and therefore this part of the claim generally receives few
challenges, but when it comes to the matter of Head Office
Overheads, the impact thereof on the site/project costs is
not so obvious and therefore Engineers and Employers
often have the following questions, as to:-
-
-
47
December 2010
SLQS JOURNAL
by the Employer or by those for whom the Employer is
responsible or by an event for which the Employer assumed
the monetary risk, and since Head Office Overheads
contribution is part of such cost, the Contractor would
be in a position to successfully argue his Head Office
Overheads claim, provided that it is quantified in an
appropriate manner.
Where both parties are agreeable to use an existing
formula such as Hudson, Emden, Eichleay or Hank Laan
(see the Schedule at the end of this article), quantifying
the Head Office Overheads claim would be quite simple,
but where there is disagreement, such formulae cannot
be used with FIDIC Forms of contract and most bespoke
forms of contract (or with claims for damages for breach
of contract) due to the necessity to deal with the actual
(but fair and reasonable) costs incurred or to be incurred,
in addition to other limitations/weaknesses found in such
formulae.
It is ideal (but may not be convenient) to have a
transparent method to apportion the Rationalized Head
Office Overheads of a Contractor to all his projects and to
recover monthly from each project, its due contribution,
neither based on the revenue (as is being practised by
some contractors) nor based on the overall expenditure
(as practiced by the others), but based on the limited cost
of staff, workers and equipment deployed on the projects
(or in other words, based on the cost of those resources
that a Contractor moves from one project to another
and from which he generates revenue). If this is practised
by Contractors, there would be no need of formulae to
establish the quantum of Head Office Overheads element
of the claim. The Contractor can simply produce proof
of the contribution made by the delayed project towards
the Head Office Overheads, during the delay period. But
the general practice among Contractors (mainly due to
administrative convenience) is to use either the revenue or
the overall expenditure as the basis for the apportionment,
thus necessitating the use of a formula to later assess (for
the purpose of a claim) what a fair and reasonable Head
Office Overheads contribution should have been, because
the actual contribution made was disproportionate (and
therefore not fair and reasonable). Moreover, a Contractor
is at liberty to collect from any of his projects whatever
level of contribution that he prefers, in order to fund
the Head Office Overheads (which is the contribution
that would be recorded in the project accounts), but an
Employer is required to reimburse only what the project
48
CP
SCP
Additional
Payment due
where:
December 2010
SLQS JOURNAL
project (fast track, slow paced etc.) has been factorized
through the CP component, a fast-track project (where
it is very likely that the Contractors highest paid Project
Director and most of the brand new equipment are
deployed) would need to contribute proportionally higher
than a slow-paced project, which is a fair distribution of
Head Office Overheads that cannot be criticized. Also a
weighting has been introduced (to multiply by the full or
part period of EOT through which a concurrent project
was in progress) in order to avoid unfair apportionment
to a project which was not concurrent through the full
period of EOT. (Such factorization and/or weighting to
ensure a fair apportionment cannot be found in Hudson,
Emden, Eichleay or Hank Laan Formulae). Since actual
costs are taken into consideration, this Formula can be
used in claims under FIDIC Forms of contract and since
a transparent method of fair apportionment is used, this
Formula would be acceptable to both Contractors and
Employers. For the same reasons, this formula should
still be acceptable as a means of assessment of Head
Office Overheads element of a prolongation cost claim
at arbitrations and litigations even where the Form of
contract is not FIDIC, and also where a claim is for
damages for breach of contract.
One would wonder why the Authors Formula takes into
consideration the period of Extension of Time (EOT)
rather than the period through which the delaying event
continued. (It is not all the monetary aspects of the delay
claim that should be calculated for the period of actual
delay! Cost of prolongation of the Site Overheads for
instance, should be calculated for the period of actual
delay whereas financing charges in respect of reduced
revenue should be for the period when the Contractor
actually suffers from such reduction (i.e. probably after
2 months of the occurrence of the actual delay, given 28
days for certification and 28 days for payment. Likewise,
financing charges for the late release of first moiety of
Retention Money should be for the period from original
date for completion to the end of the EOT, whereas in
respect of the second moiety it should be a year later.
Thus each kind of prolongation cost is incurred during
a different period of the project time line). Head Office
Overheads element should be calculated for the period
when the Contractor was unable to generate revenue
from other projects using his resources which were
unforeseeably retained in the delayed project, which is
the same period for which EOT was determined.
Schedule
HUDSON FORMULA:-
HO/P
100
Contract Sum
Contract Period
(Weeks)
Period
of Delay
(weeks)
where :
HO/P = the percentage of head office overhead cost and
profit allowed in the Tender
Authors Comments:(a) This formula does not comply with the actual cost
requirement of FIDIC Forms of contract (or of
claims for damages for breach of contract) due to
the following reasons:- The actual Head Office Overheads percentage could
either be more or less (at the time of delay/EOT)
than that included in the Tender.
- The average-per-week interim assessment is a
departure from the actual.
(b) There is no transparency as to:- whether the Contractor is attempting to recover
all or most of the Head Office Overheads from the
Employer of the delayed project.
- whether the other concurrent projects of the
Contractor are also sharing the Head Office
Overheads in a fair and reasonable manner.
- whether the Contractor is over-recovering/
under-recovering on the Head Office Overheads
contribution of the delayed project.
49
December 2010
SLQS JOURNAL
EMDEN FORMULA:H
100
CP
PD
where :
h = head office percentage arrived at by dividing
the total overhead cost and profit of the Contractors
organization as a whole, by the total turnover.
c = contract sum
cp = contract period in weeks
pd = period of delay in weeks
Authors Comments:(a) This formula does not comply with the actual cost
requirement of FIDIC Forms of contract (or of
claims for damages for breach of contract) due to
the average-per-week interim assessment.
(b) There is no transparency as to:- whether the other concurrent projects of the
Contractor are also sharing the Head Office
Overheads in a fair and reasonable manner.
- whether the Contractor is over-recovering/
under-recovering on the Head Office Overheads
contribution of the delayed project.
EICHLEAY FORMULA:Step 1.
Contract Billings
Total Contract
Billings
for Contract Period
Allocable
Overhead
Step 2.
Allocable Overhead
Days Of Performance
Daily Contract
Head Office Overhead
Step 3.
Daily Contract
Head Office
Overhead
50
Days of
Compensable Delay
Additional
Payment due
Authors Comments:(a) This formula does not comply with the actual cost
requirement of FIDIC Forms of contract (or of
claims for damages for breach of contract) due to
the average-per-day interim assessment.
(b) Where the value of billings of other projects of the
Contractor is low, the delayed project would attract
most of the Head Office Overheads, which would
not be acceptable to an Employer.
HANK LAAN FORMULA:Contract Billings
Total Company
Billings
Additional
Payment due