You are on page 1of 10

VOLUME - I

MAIN REPORT
JULY 2014
A Joint Venture of:
Associated Consulting Engineers ACE (Pvt.) Ltd.
1 C/2, M. M. Alam Road, Gulberg- III, Lahore

Engineering General Consultants EGC (Pvt.) Ltd.


49/D-1, Gulberg-III, Lahore

Technical Engineering and Management Consultants

Suit No.9, 4th Floor, Amaan Business Centre, Block H-3, Johar Town, Lahore

GAHRAIT-SWIR LASHT HYDROPOWER PROJECT


INDEX - FEASIBILITY STUDY REPORT

VOLUME I:

MAIN REPORT

VOLUME II:

EIA & SIA

VOLUME III:

ANNEXURES
PART 1 OF 3
PART 2 OF 3
PART 3 OF 3

VOLUME IV:

DRAWINGS

GAHRAIT-SWIR LASHT HYDROPOWER PROJECT


COMPOSITION OF MAIN REPORT (VOLUME I)

CHAPTER 0: EXECUTIVE SUMMARY


CHAPTER 1: INTRODUCTION
CHAPTER 2: SURVEY AND MAPPING
CHAPTER 3: HYDROLOGY AND SEDIMENTATION STUDIES
CHAPTER 4:

GEOLOGY, GEO-TECHNICAL AND CONSTRUCTION MATERIAL


STUDIES

CHAPTER 5: SEISMIC HAZARD ASSESSMENT STUDIES


CHAPTER 6: PROJECT LAYOUT STUDIES
CHAPTER 7: PROJECT SIZING, OPTIMIZATION STUDIES AND POWER
SIMULATION
CHAPTER 8: DAM DESIGN STUDIES
CHAPTER 9: HYDRAULIC DESIGN STUDIES
CHAPTER 10: STRUCTURAL DESIGN STUDIES
CHAPTER 11: HYDRO-MECHANICAL STUDIES
CHAPTER 12: ELECTRICAL ENGINEERING STUDIES
CHAPTER 13: POWER EVACUATION AND TRANSMISSION STUDIES
CHAPTER 14: ENVIRONMENTAL IMPACTS ASSESSMENT (EIA) STUDY
CHAPTER 15: SOCIAL IMPACTS ASSESSMENT (SIA) STUDY
CHAPTER 16: CONSTRUCTION PLANNING AND COST ESTIMATES
CHAPTER 17: ECONOMIC AND FINANCIAL ANALYSIS
CHAPTER 18: NEED FOR DETAILED PROJECT PLANNING AND DESIGN STUDY
CHAPTER 19: CONCLUSIONS AND RECOMMENDATIONS

CHAPTER
0

EXECUTIVE SUMMARY

Feasibility Study
Gahrait-Swir Lasht Hydropower Project

Executive Summary

0.1

Introduction

Volume I, Main Report


July 2014

This Chapter of the Report summarizes the findings of the Feasibility Study carried out for
the Project. According to the study, Gahrait-Swir Lasht Hydropower Project is marked to
have an installed power generation capacity of 377 MW against 340 MW as originally
estimated in the identification studies conducted earlier by GTZ. Accordingly, the Annual
Energy is now estimated as 1579 GWh against 1,553 Gwh indicated in GTZ Report. Salient
Features of the Project and Project Layout Plan are placed at the end of this Chapter.
All relevant desk and field studies including Field Investigations have been conducted as a
part of Feasibility Study. Geological, Environmental and Seismic Studies have not indicated
any major adversity that may challenge/threaten further development and construction of the
Project.
The Feasibility Report has been prepared by a Joint Venture of three local Consultants
including ACE, EGC and TEAM Consultants, ACE being the lead Consultant.
0.2

Project Location

Gahrait-Swir Lasht HPP is located on Chitral River which is the main river that passes
through Chitral Valley. It flows from north to south and enters Afghanistan near Arandu
Town. The dam site is proposed about 35 km downstream of Chitral Town. Powerhouse site
is located about 8 km downstream of Drosh Town near Swir Lasht Village on the right bank
of Chitral River.The national grid at Chakdara is at a distance of about 170 km from the
powerhouse site. Water from the dam will be conveyed through a 10 km long tunnel to an
underground power house, about 8 km downstream of Drosh town near Swir Lasht village.
0.3

Geological and Geotechnical Studies

Significant information about the geology of the project components / parts has become
available, based on which the feasibility of the project has been studied.
Results of Geological and Geotechnical Investigations carried out are presented in this
report and evaluation of the foundation conditions and the parameters established for use in
the design of various surface and underground structures, including the design of rock
excavations, have been defined. Generally the strength of the rocks are not likely to pose
any serious problem for the structures.
Certain Geotechnical Investigations remained outstanding due to various unavoidable
circumstances.Further geological and geotechnical investigations should be carried out at
the detailed design stage of the project.
0.4

Seismic Hazard Analysis

The project is located in a region which is seismically active due to the proximity of the
collisional boundary of the Indian and the Eurasian plates. The seismicity of the area is
depicted by small to major earthquake activity. The main active tectonic features within 100
km of the site, which govern the ground motion at the project site, are the Main Karakoram
Thrust (MKT), Reshun Thrust, Tirich Mir Thrust and the Hindukush Deep Seismic Zone.

| Version: Final |

Feasibility Study Report - Final

0-1

Feasibility Study
Gahrait-Swir Lasht Hydropower Project

Volume I, Main Report


July 2014

The recommended PGA value for Safety Evaluation Earthquake (SEE) associated with
horizontal ground motions is 0.42g which has a return period of 3,000 years. The dam safety
critical features like dam body, bottom outlet and spillway gates are recommended to be
designed to maintain their integrity during shaking from SEE ground motions.
The PGA of 0.18g having a return period of 145 year is recommended for the project
structures to remain operative for horizontal ground motion associated with Operating Basis
Earthquake (OBE). All the appurtenant structures of the dam, tunnel and power house are
recommended to be designed for PGA of 0.26g which is associated with horizontal ground
motion of Design Basis Earthquake (DBE).
0.5

Optimization and Project Sizing

The Project is optimized with a maximum reservoir level of 1337m asl and design discharge
of 430 m3/s, which has availability approximately 26% time of year. Installed capacity of
377MW and Annual Energy equivalent to 1,579Gwh has been attributed to the Project with a
Plant Factor of 49%.
0.6

Environmental and Social Impact Assessment

Surveys and studies are indicative of Low-Adverse Impact resulting from implementation of
Gahrait-Swir Lasht Hydropower Project. All the impacts can be mitigated without difficulty.
0.7

Construction Planning

It is presumed that the construction of this Project shall be carried out as Engineering,
Procurement & Construction (EPC) Package. At this stage, Consultants have carried out an
exercise to establish broad outlines which identify the extent, viability and interdependence
of various activities involved in construction as shown in the Project Construction Schedule
given in Chapter-15 of this Report. The Project can be completed in a Period of 96 months,
out of which 12 months are for pre-construction activities and 84 months for construction.
0.8

Cost Estimate

Cost estimates of the Project are prepared on the basis of Feasibility Level Designs and
Drawings. Unit Rates of various items used for cost estimation are derived from rate
analyses.
Rates have also been obtained from suppliers / manufacturers wherever applicable. All rates
pertain to the year 2013 price level. While working out the cost of each Project component,
appropriate contingencies for Civil Works and E&M items have been included.
Total Project cost has been worked out as US$ 1,838 million or Rs.181,115 million
which also includes US$ 441.46 million as Interest during construction (IDC).
0.9

Economic and Financial Analyses

Economic viability of the Project has been determined using the Alternative Cost approach,
wherein the investment of Gahrait-Swir Lasht Hydropower Project is compared with the
investment of alternative thermal power plants.
EIRR in comparison with thermal plant of equivalent capacity is 23.71% in case of furnace
oil plant and 13.58 % in case of gas operated plant. Benefit-Cost Ratio in each of the two
cases is 2.05 and 1.15 respectively.
| Version: Final |

Feasibility Study Report - Final

0-2

Feasibility Study
Gahrait-Swir Lasht Hydropower Project

Volume I, Main Report


July 2014

To test the robustness of the Economic appraisal of the Project, a sensitivity analysis has
been carried out. This test has been performed only for the combined cycle plant (in case of
furnace oil) as this alternative has been compared with the proposed Project.
The above mentioned analysis has also been tested for its robustness for Cost increase of
10 % and Benefit decrease of 10%. The cumulative effect of the above two conditions gives
an EIRR of 19.75 % and B.C Ratio as 1.68 .Study of Certified Emission Rate (CER)
indicates a saving of emission of 757,920 tons of CO2 per annum compared to furnace oil
plants and 663,180 tons/annum if gas is considered as the alternative source of energy
Financial Analysis has indicated B.C Ratio greater than one (1). It is also seen from the
Financial Analysis that repayment of the loan installments will be easily manageable.

| Version: Final |

Feasibility Study Report - Final

0-3

SALIENT FEATURES

1. Location

377 MW GAHRAIT-SWIR LASHT HYDROPOWER PROJECT


SALIENT FEATURES
10 km upstream of Drosh Town. (District
Chitral), Khyber Pakhtunkhwa, Pakistan.

2. Organization

Pakhtunkhwa Hydel Development


Organization (PHYDO).

3. Hydrology
Catchment area (dam site)
3
Mean Monthly Discharge (m /sec)
Design Flood (Q1000)

13418.5 km
80.8 to 978.50
3
3538 m /sec

4. River Diversion
Design Flood (Q10 year)
No of Diversion Tunnels
Shape
Size (W x H)

1790 m /sec
4 Nos.
D-shaped
7.6 m x 7.6 m

5. Dam & Appurtenant Structures


Dam type
Dam Crest level
Maximum Reservoir Level
Minimum Reservoir Level
Dead Storage Level
Dam Height (from Bed)
Dam bed elevation

Asphaltic face Rockfill Dam (AFRD)


1342.00 masl
1337.00 masl
1331.00 masl
1324.00 masl
34 m.
1309.00 m.asl

6. Spillway & Energy dissipation arrangement


Spillway type
No of Diversion Tunnels
Shape
Size (W x H)
Type of energy dissipation arrangement

Tunnel Spillway
4 Nos.
D-shaped
7.6 m x 7.6 m
Flip Bucket

7. Power Intake/ Connecting Tunnels


No of Intakes
Size of each Twin intake opening
Intakes invert Level
No of Intake Connecting tunnels
Connecting Tunnels (Upstream of Sand trap)

4 Nos.
7.00 m x 3.00 m
1324.00 m.asl.
4 Nos
12 m x 9 m (D-Shaped)

8. Sand Trap / Flushing Tunnels


Type
No of chambers
Length of Chamber
Fall velocity
Size of Chamber (W x H)
Flushing Discharge
No of Main flushing tunnels

Pressurized-D shape
4 Nos
525 m.
0.2 m /sec
14.30 m x 20.30 m
3
86 m /sec
2 Nos

9. Headrace Tunnel
Type
No of Headrace tunnels
Average Length

Horseshoe
2 Nos
10,214 m

Diameter

9.50 m

10. Surge Shaft


Height
No of Surge Tanks
Diameter

71 m.
02 Nos
10 m.

11. Concrete Lined Pressure Shaft


Length
No of Pressure Shafts
Diameter

92.20 m.
02 Nos
6.50.m.

12. Steel Lined Penstock


Length
Diameter

78 m.
6.5 m.

13. Head
Gross head
Head loss (single waterway)
Net Head

109.28 m.
9.12 m
100.16 m

14. Discharge
Design Discharge

430 m /sec

15. Powerhouse
Type
Size (Lx WxH)

Underground
113 m x24 m x35 m

16. Tailrace Tunnel


Type
Total length
Size (W x H)

D-Shaped
3980 m
7 m x 6.5m

17. Hydro-Mechanical Equipment


Type of turbine
No of Units
Discharge/ Unit

Francis
4 Nos
3
107.50 m /sec

18. Electrical Equipment


Generators
Speed

4 Nos
176.5 rpm

19. Installed Capacity


Plant Capacity
Capacity/ unit

377 MW
94.25 MW

20. Energy
Annual Energy
Plant Factor

1579 Gwh
49%

21. Project Cost (with transmission line)


Base Cost
Total Project Cost

110,737 M.Rs
181,116 M.Rs

22. Economic and Financial Analysis


B/C ratio
EIRR
FIRR
Cost/MW
Construction time

2.05
23.71
13.58 %
4.874 M.US$
84 months

You might also like