You are on page 1of 62

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Volume II: Technical

Section 7 Method Statement

SINOHYDRO CORPORATION LIMITED

EPC Tender Documents: Volume II: Technical

180 MW Kali Gandaki Koban Hydroelectric Project

Method Statement
of Kali Gandaki Koban Hydroelectric Project

Content
1.

Project Description .......................................................................................................................1

2.

Project Execution Organization and Main Construction Equipment ............................................. 2


2.1 Project Execution Organization ..............................................................................................2
2.1 Main Construction Equipment ................................................................................................3

3.

General Construction Layout ........................................................................................................7


3.1 Principles for General Construction Layout ............................................................................7
3.2 General...................................................................................................................................7
3.3 Camp & Office Building ..........................................................................................................8
3.4 Access Road .......................................................................................................................... 9
3.5 Air Compressing System for Site Works.................................................................................9
3.6 Power Supply ....................................................................................................................... 10
3.7 Water Supply ........................................................................................................................11
3.8 Communication System........................................................................................................12
3.9 Construction Auxiliary Facilities ............................................................................................12

4. Main construction methodology .................................................................................................... 15


4.1 Open Excavation Works .......................................................................................................15
4.2 Dam Embankments ..............................................................................................................16
4.3 Underground Works .............................................................................................................19
4.4 Grouting Work ...................................................................................................................... 23
4.5 River diversion ...................................................................................................................... 23
4.6 Concrete works ....................................................................................................................24
4.7 Turbine equipment installation ..............................................................................................28
4.8 Generator Installation ........................................................................................................... 39
4.9 Penstock manufacturing and installation ..............................................................................46
4.10 Steel gate and trash rack installation ..................................................................................53
5. Project Preliminary Schedule.......................................................................................................59
5.1 Milestone and Critical path ...................................................................................................59
5.2 Construction Rate at Peak ....................................................................................................60

180 MW Kali Gandaki Koban Hydroelectric Project

1.

EPC Tender Documents: Tender Schedules

Project Description

Kali Gandaki Koban Hydroelectric Project (KGK HEP) with proposed installed capacity of 180MW, is a
high head hydropower plant. Its Headworks is located at Dhampu and the underground PowerStation at
Ghasa in Lete VDC of Mustang District. The project is a run of river type development having storage
capacity for peaking operation.
The general scope of works envisaged includes but is not restricted to the following:
(a) Design and Construction of all civil works, civil structures including:
Concrete Face Rockfill Dam (CFRD), Spillways & Undersluices, Intake Structures, Control Building
at Headworks,
Sediment Bypass Tunnel and its Guiding Structures including Overflow Weir and Side Channel
Spillway,
Headrace Tunnel, Surge Tunnel, Valve Chamber, Drop Shaft with trifurcation, Access Tunnel to
PowerStation, Tailrace Tunnel (a portion of which is expected to be in soft soil),
(b) Design, procurement, fabrication, testing and installation of all electrical, mechanical, hydromechanical, electromechanical, hydraulic steel structures including but not limited to operate and
maintain the plant in a manner that conform to the Contract Documents.
Hydraulic and Hydro-Mechanical steel structures (gates & stoplogs, cranes, valves, trash racks &
cleaning system, liners, manifold, trifurcation pipes).
Electromechanical, electrical, instrumentation & control equipments required at the powerhouse and
other structures. These include turbine, generators & transformers with its auxiliaries, cable and
cable ducts, Control System, GIS Switchyard and Outgoing Gantry, monitoring equipment, cooling
system, compressed air, hydraulic systems, fire fighting, ventilation, illumination in the Power House
and elsewhere, for construction/ operation/ maintenance of the plant.
(c) Design, procurement, testing and installation of a GIS (including cable head). Ducts and all civil
works for such switchyard to complete the Outgoing Gantry are also included.
(d) Design, rehabilitation/realignment, construction and maintenance of Beni Jomsom Road from Ghasa
to Larjung and all internal access roads required for construction works.
(e) Design and construction of all required Adits as indicated or approved by the Employer.
(f) Care of water
Dewatering in open excavation as well as in underground works,
River Diversion and flood control
(g) Design and Installation of temporary and permanent protection/support measures for all excavation
and civil works.
(h) Design and installation of fencing, gates, guard house, sentry post, landscaping, illumination as
indicated or as approved by the Employer.
(i) Bidders obligations towards health and safety as well as environmental mitigation plans are also
included.
(j) Commissioning, testing and rectification of defects to the extent and duration as provided in the
contract.
(k) Training of manpower for operation and maintenance.
SINOHYDRO CORPORATION LIMITED

Page 1 of 60

EPC Tender Documents: Tender Schedules

180 MW Kali Gandaki Koban Hydroelectric Project

The main quantities to be used in this project are shown in the following table.

No.

Items

Earth
Exca.

Rock
Open
Exca.

Rock
Tunnel
Excavation

Concrete

Filling

Grouting

Rock
Bolt

Unit

Kg

Roadworks

Cofferdam

Bypass Tunnel

Guiding Structure

CFRD Dam &


Headworks

Head Race Tunnel

Pressure shaft

324,219

38,872
98,072

116,600

56,496

120,398

25,237

70,201

26,122

21,213

212,042

134,286

370,938

58,381

224,324

579,018

81,201

2,873,255

13,349

275,455

46,366

2,407,589

111,000

8,708

3,951

186,483

21,300

Power station access


tunnel

66,697

7,904

189,131

13,500

Tairace tunnel

68,900

12,704

10

Power station

33,766

8,050

11

Transformer cavern

10,800

520

584,724

184,326

Total

2.

23,730

645,306

516,158

24,021
300,000

8,540
501

534,438

6,535,476

273,412

Project Execution Organization and Main Construction Equipment

2.1 Project Execution Organization


Sinohydro is the leading company in the world in the field of engineering, procurement and construction
of the hydropower project, and has also practices and experiences working in Nepal, would like to have
further cooperation with AEHPL and make more contributions and benefits to Nepal.
Once Sinohydro has the opportunity to get the Project, we shall set up an efficient organization, and
select experienced staff in management, engineering, construction and installation, dispatch specialized
construction teams, and complete this project per the schedule.
Our head office will also establish a team to provide full supports and helps in technical and
management.
The staff and labor number at the peak will be about 1200, preliminary Organization Chart is shown
below:

SINOHYDRO CORPORATION LIMITED

Page 2 of 60

EPC Tender Documents: Tender Schedules

180 MW Kali Gandaki Koban Hydroelectric Project

Head Office
Expert Team

Project Manager

Commercial
Manager

Chief Engineer

Construction
Manager

M&E Manager

Construction Department

M&E Department

Purchase Department

Quality Safety
Department

Design Department

Laboratory

Survey Department

Technical Department

Contract Department

Accounting Department

General Affairs

Department

General Office

Machinery Repair Plant

Aggregate Processing Plant


Concrete Batch Plant

Comprehensive Processing
plant

M&E Installation Section

Guiding Structure & Dam Section

Bypass Tunnel Section

Intake Structure Section

HRT Adit-1 Section

HRT Adit-2 Section

HRT Adit-3/4 Section

Underground PowerStation
Section

Tailrace Tunnel Section

Road Works Section

2.1 Main Construction Equipment

Hydraulic Drilling DX700

DX700

Down-in-Hole Drill 89mm

YQ100B

10

Rotary disk drill

JP100

Pneumatic Drill

YT27

120

ZFY2.0/LM400

XY-2

Exploration Drill

SGZ-III(A)

Air Compressor

Atlas

27m3/h

Air Compressor

Atlas

20m3/h

Air Compressor

Atlas

12/m3

Air Compressor

VFY-3/7

3m3/h

Air Compressor

2V-0.6/7

0.6m3/h

Raise Boring Machine


Geological Drilling

SINOHYDRO CORPORATION LIMITED

Page 3 of 60

EPC Tender Documents: Tender Schedules

180 MW Kali Gandaki Koban Hydroelectric Project

Mortar Mixing Machine

NJ2000

Wet Jet Machine

TK500

5m3/h

10

Wet Jet Machine

Spritz CSS-3

30m3/h

BW-250/50

GJY-III

10

Backhoe

CAT330

1.6m3

Backhoe

PC220

1.0m3

Backhoe

CAT312D2

0.53m3

Hydraulic Hammer

KCB250

2.8t

Loader

WA380

3.5m3

Wheel Loader

ZL50

3m3

Loader

ZL30

1m3

JCB
Bulldozer

JCB3CX

D85

175KW

Dozer

HP220

220KW

Grader

GR100

75Kw

XZJ5110GLQ

100Kw

Asphalt Distributor
Dump Truck

20t

Dump Truck

15t

10

Dump Truck

5t

10

Dump Truck

8~10t

20

Heavy Duty Lorry

EQ1141G

8t

Heavy Duty Lorry

EQ1108G

5t

Platform Trailer

EQ4260G

40t

Flat Truck

EQ1208G

10t

EQ3208GZY

10t

Axial flow Fan

2*75Kw

150KW

Axial flow Fan

2*55KW

110KW

Axial flow Fan

2*37KW

74KW

Axial flow Fan

2*30KW

60KW

200t/h

90m3/h

Explosive Vehicle

KXP-1

Grouting Recorder

Inclinometer

Grouting Pump

Aggregate Production System


Concrete Batching Plant

SINOHYDRO CORPORATION LIMITED

HZS90

Page 4 of 60

EPC Tender Documents: Tender Schedules

180 MW Kali Gandaki Koban Hydroelectric Project

Concrete Batching Plant

JS1000

60m3/h

Concrete Batching Plant

JS500

25m3/h

Ready-mix Concrete Truck

EQ5242GJB

6m3

Concrete Extruding Machine

BJY40

45Kw

Concrete belt feeder

800mm

70m

Concrete Bucket

LG1

1m3

Concrete Bucket

LG1.5

1.5m3

Concrete Pump

30m3/h

Concrete Pump

60m3/h

Steel mould trolley

10m

Truck Crane

QY50K

50t

Truck Crane

QY25VF

25t

Truck Crane

QY16E

16t

5t

Truck crane

Electric Winch

JM5

5t

Tower Crane

SHENYANG7050

25t

gantry crane

20t

20t

gantry crane

10t

10t

Vibratory Roller

SR18M

18t

Vibratory Roller

XS262J

26t

Vibratory Roller

LTC6

6t

Vibratory Roller

BW75S

1.5t

Hand Vibratory Roller

DX-70

0.7t

Electric Rammer

GVR200Y

Diesel Generator

500kw

Diesel Generator

300kw

Diesel Generator

250kw

Diesel Generator

200kw

Diesel Generator

100kw

Inverse DC arc welder

ZX7-500

Welding rod oven

ZYH-60

2 set

SINOHYDRO CORPORATION LIMITED

Page 5 of 60

EPC Tender Documents: Tender Schedules

180 MW Kali Gandaki Koban Hydroelectric Project

Ultrasonic detector

CTS-22

X-ray detector

XX2505

Magnetic powder detector

XDYY-III

Ring welding trolley

HGK-20

Three-roller plate roll

W11S-503000

Submerged arc automatic welder

MZ-1-1250

Contravariant AC welding machine

ZX7-500

15

Facing machine

SKF-20

CG1-30B

Auto-flux dry oven

NZHG

Welding rod thermostat

101-

semi-auto cutting machine

Caterpillar infrared heater

LCD64-220

Ultrasonic Detector

MFDS-350

Air compressor

6m3/min

Air compressor

0.6m3/min

Windlass

JJMW3-10t

Windlass

JJMW3-5t

10

HY4030

Y32-2000KN

Hawking welding stress eliminator


Presses

Fueling Vehicle

EQ5141GJY

132kw

SGZ5141GSS

8t

Submerged Pump

65QW30-40

7.5kw,30m3/h

Submerged Pump

QW40-15-30

7.5kw,15m3/h

Submerged Pump

50WQ20-40-7.5

7.5kw,20m3/h

Submerged Pump

65QW35-60

15kw,35m3/h

Submerged Pump

QW200-400-30

55kw,400m3/h

Submerged Pump

QW150-200-30

37kw,200m3/h

Centrifugal Pump

IS125-100-200

45kw,200m3/h

Centrifugal Pump

QS40-30/2-55

5.5kw,40m3/h

Centrifugal Pump

IS100-80-125

15kw,100m3/h

2PW

7.5kw,43m3/h

16

Sprinkler

Sewage Pump
Equipment Maintenance Machine

1 Set

Laboratory Equipment

1 Set

Survey Instruments

5 Set

SINOHYDRO CORPORATION LIMITED

Page 6 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

3.

EPC Tender Documents: Tender Schedules

General Construction Layout

3.1 Principles for General Construction Layout


Combining the scale, features, construction environment and conditions of the project, the principles for
the general layout of the construction shall be scheduled to be as follows:
(1) The temporary facilities of construction campsite and site and the access road shall be planned and
laid out in the confirmation area according to the site survey and the conditions.
(2) The scale and volume of all the temporary life and production facilities and auxiliary plants for the
construction shall be planned and designed according to the total construction schedule and
intensity in an effort to reach compact, reasonable and convenient layout.
(3) In the underground construction, whether the layout of temporary projects including air, water and
electricity supply and ventilation and drainage in the tunnel is reasonable or not has a great effect on
the construction safety, schedule and investment, so such factors as the construction procedures,
traffic, safety, excavation explosion effect and balancing construction intensity shall be
comprehensively taken into account in the layout.
(4) All the construction campsites and sites shall be equipped with enough reliable environment
protection facilities and firefighting equipment according to related requirements to avoid the
impairment on the public interests.

3.2 General
In view of the topography and landform nearby the Site acknowledged by the site investigation, the
temporary facilities and auxiliary construction plant in each construction area, along with the access road
will be arranged in accordance with the Tender Documents and conditions provided by the Employer
within the expropriation range. Overall planning will be carried out with reference to the detailed location,
landform feature and current status described in the Tender Documents.
The temporary facilities include camps, offices, workshops, stores and yards and so on. The exact
location of all temporary facilities to be constructed will be agreed by the Engineer after commencement.
Generally, the following items are considered:
Contractors Main office and Camps
Clinic and First-aid station
Sub Offices
Construction Access Roads
Water-supply and Sewage system
Air supply system for construction
Power Supply and Lighting system
Communication system
Machinery Repair Plant
Comprehensive Processing Plant
Metalwork Structure Fabricating Plant
Disposal area
Explosive magazine
SINOHYDRO CORPORATION LIMITED

Page 7 of 60

EPC Tender Documents: Tender Schedules

180 MW Kali Gandaki Koban Hydroelectric Project

Fuel station and Storage


Laboratory
Aggregate processing Plant
Concrete Batch Plant

3.3 Camp & Office Building


a) Contractors Offices and Residences.
Several camps shall be set up to meet the requirements of construction and living, the camp scales are
shown in the following table:
No.

AREA
m2

Came Name

Building
Area m2

Dam Section Labor Camp

8000

855

Dam Section Office and Camp

11000

1900

Adit-2 Site Camp

2000

470

Adit-3/4 Section Camp

6000

1070

PowerStation Section Labor Camp

6000

1900

PowerStation Section Main Camp

18000

1865

Tailrace Section Camp

8000

830

According to the construction progress and intensity, it is preliminarily estimated that about 1200 labors
and staffs will be required in the peak construction period of this project
b) Clinic and First-Aid Station
The Contractor will make arrangements which are satisfactory to the Government Medical Authority for
provision of free accident and emergency services for all labors and staffs on the Works.
The Contractor will provide at the site of the Permanent Works an ambulance and two staffed, furnished
and equipped first-aid hut, one to be located at the main camp and one to be moved from one location to
another with the Contractor field office.
Planning of Clinic & First Aid Facilities:
No.

Description

Building Area

Land Area

Remarks

Clinic and First Aid Station

25m2

200m2

Fixed

First-Aid Hut

10m2

25 m2

Movable

roads and parking

500m2

green areas and planting

500m2

Total

35m2

1225m2

c) Living camps and office facilities for Contractors


Living camps and office facilities for Contractors are mainly located in DAM and Power Station area.
SINOHYDRO CORPORATION LIMITED

Page 8 of 60

EPC Tender Documents: Tender Schedules

180 MW Kali Gandaki Koban Hydroelectric Project

3.4 Access Road


3.4.1 External Access Road

The project site can be reached by a blacktopped road from Pokhara to Beni and by an earthen and
gravel road from Beni to Jomsom about 320 km by road north-west of the capital city Kathmandu of
Nepal.
3.4.2 Construction Access Roads

Total nine site access roads shall be constructed to access to different working sites, the parameters for
the access roads are listed below:

Construction Access Road Parameters

Name

Start - End

length
km

Road surface

Remark

Ghasa - Kalopani

10.0

6m wide, asphalt

maintenance

1# road

Existing road Employers camp

1.20

6m wide, gravel

new

2# road

Existing road tailrace outlet

0.35

6m wide, gravel

new

3# road

Existing road adit-3

4.5

6m wide, gravel

new

4# road

Existing road adit-4

0.2

6m wide, gravel

new

5# road

Existing road 2# disposal area

0.95

6m wide, gravel

new

6# road

Existing road quarry site

0.85

6m wide, gravel

new

7# road

Existing road adit-2

1.8

6m wide, gravel

new

8# road

Left abutment - CFRD

1.7

6m wide, gravel

new

9# road

Kalopani

7.0

6m wide, gravel

new

External road

Larjung

Total

28.55

3.5 Air Compressing System for Site Works


Compressing Air will be produced by movable compressors and conveyed to the various working faces
through pipelines.
Features for Compressor air supply system
Model

Capacity
m3/min

Quantity

Main Pipe

Sub-pipe

Bypass Tunnel

Atlas

27

DN108/2000m

DN50/800m

Headrace
Inlet

Atlas

20

DN108/300m

DN50/100m

Adit-1

Atlas

27

DN108/2500m

DN50/1000m

Adit-2

Atlas

27

DN108/5400m

DN50/2000m

Adit-3

Atlas

27

DN108/2700m

DN50/1000m

Location

Tunnel

SINOHYDRO CORPORATION LIMITED

Page 9 of 60

EPC Tender Documents: Tender Schedules

180 MW Kali Gandaki Koban Hydroelectric Project

Adit-4

Atlas

20

DN108/900m

DN50/500m

Power House

Atlas

27

DN108/1500m

DN50/600m

Tailrace Tunnel

Atlas

20

DN108/1700m

DN50/100m

Concrete
system

Atlas

11

DN108/200m

Mixing

Total

10

3.6 Power Supply


According to the bidding documents and field investigation the 11 Kv power lines pass through the
construction area, it shall be used in the camp area. To ensure the continuity of site construction, some
Diesel generators should be provided at each working site.
Diesel Generator List
Power Equipment

Location

Capacity

Generator

Dam Site

Generator

Dam Section Auxiliary Factories

Generator

Camp of Dam Section

Generator

Dam Section Labour Camp

Generator

Dam Concrete System

Generator

Aggregate Proceeding System

Generator

Adit-1

500

Generator

Adit-2

500

Generator

Adit-3

500

Generator

Adit-4

250

Generator

Powerhouse Site

1000

Generator

Powerhouse Concrete System

300

Generator

Powerhouse Section Chinese Camp

Generator

Powerhouse Section Labour Camp

Generator

Powerhouse Section Auxiliary Factories

Generator

Tailrace Section Camp

Generator

Tailrace Adit

KW)

500

300

500

500

250
Total

SINOHYDRO CORPORATION LIMITED

5100

Page 10 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

3.7 Water Supply


Water supply will be carried out by water pipe from stream, whose water will be conveyed to the
headwork site through the main pipelines ( 108-159 steel pipes) and then to the storage basins of all
construction sites and living camps via pipes of different diameters. An automatic control system will be
provided across the water supply system for its automatic operation.
The water transferred to the living camps will only be used after being purified in the purification basin.
Water tanks will be arranged above the tunnels and camps along the rivers to satisfy water demands for
camps and construction. Water will be diverted to these tanks from the stream of seti khola, lete khola
etc. at right mountain near the access road. Using high-lift pump to lift water from the khola, pool floor
elevation should be higher than the highest elevation above the vault inside the cave, 30m, to meet the
drill pipe inside the water pressure is greater than 0.3Mp, the pool water through the pipe to the
construction of D108 points and camps. Water pipe inside the tunnel to the cave operations using
surface water, set along the water, fork and valves, water pipes along the tunnel wall hanging, from the
ground 50cm, laid in the lower part of the tunnel side wall. There will be an elevation difference of 30m
between tunnel crown and water tank bottom, which could maintain water pressure as 0.3Mp for drill
machine and water supply pipes. Water will be distributed to every construction area and camps through
D108 steel pipes. In the tunnels, water distribution pipes will be suspended 50cm high along the walls
together with valves and distributors.
Water Pump
Capacity
Location

Rate

Lift

Power

m3/h

KW

Model
m3/d
Dam

100

65QW30-40

30

40

7.5

Bypass Tunnel

50

QW40-15-30

15

40

7.5

Adit-1

100

65QW30-40

30

40

7.5

Adit-2

100

65QW30-40

30

40

7.5

Adit-3

100

65QW30-40

30

40

7.5

Adit-4

50

QW40-15-30

15

40

7.5

Powerhouse

150

65QW35-60

35

60

15

Tailrace Tunnel

50

50WQ20-40-7.5

20

40

7.5

Camp of Dam Section

60
65QW35-60

35

60

15

Dam Section Auxiliary Factories

100

Dam Section Labour Camp

30

50WQ20-40-7.5

20

40

7.5

Site Camp in Concrete System

50

50WQ20-40-7.5

20

40

7.5

Dam Concrete System

1,000
QW200-400-30

400

30

55

Aggregate Proceeding System

1,000

Site Camp in Adit-2

30

QW40-15-30

15

40

7.5

Powerhouse Concrete System

800

QW150-200-30

200

30

37

SINOHYDRO CORPORATION LIMITED

Page 11 of 60

EPC Tender Documents: Tender Schedules

180 MW Kali Gandaki Koban Hydroelectric Project

Powerhouse Section Labour Camp

50
65QW35-60

35

60

15

60

65QW35-60

35

60

15

Tailrace Section Camp

30

QW40-15-30

15

40

7.5

Top of Surge Tunnel

400

65QW35-60

35

60

15

Powerhouse
Camp
Powerhouse
Factories

Section

Chinese

Section

Auxiliary

200

3.8 Communication System


3.8.1 Exterior Communication

The Contractor shall request the local communication company to establish a communication station
inside the Project area. Before the station is put into operation, communication with outside shall by
satellite communication system.
3.8.2 Communication on Site

The Contractor will maintain 60 hand-held two-way radios with a range of up to 5~30km, and all
necessary equipment to ensure that the radios operate safely.

3.9 Construction Auxiliary Facilities


Auxiliary Facilities will be established dispersedly near Dam camp and Powerhouse camp, which are
marked in layout drawing.
3.9.1 Storehouse

The total land area of storehouse is about 4000m2. It includes 10 rooms for store metal materials,
equipment parts, pipe parts, tools, protection goods, reinforcement steel bar and other purchase
materials.
Planning Table of Storage
S.No

Name of Storehouse

Building
Area (m2)

Storehouse for small equipment, tools and


devices

100

Storehouse for hardware parts

80

Storehouse for labor protection gears

60

Material storehouse

100

Management room

40

Guard room

20

Open goods yard

Total

SINOHYDRO CORPORATION LIMITED

Occupation
of land (m2)

Remark

4000
400

4000

Page 12 of 60

EPC Tender Documents: Tender Schedules

180 MW Kali Gandaki Koban Hydroelectric Project

3.9.2 Machinery Repair Plant and Parking Areas

The Contractor plans to establish a machinery and equipment repairing plant in the Contractors works
area.
Planning of Machinery & Equipment Repairing Workshop
S.No
.

Content

Unit

area

Building Area

m2

200

Shed building

m2

200

Occupation area

m2

10000

Remark

3.9.3 Comprehensive Processing Plant

According to construction schedule of this project, during the peak period of construction, the mean
monthly intensity of reinforcement steel process will be about 350t per month, and mean daily intensity of
rebar processing will be about 12t.
Two rebar cutting machine, three rebar bending machine and 1 mobile crane with capacity of 16t will be
equipped in processing plant. Non-standard steel and wooden formworks will also be made here.
Planning of Steel & Formworks Processing Plant
Technical index
S.No.

Name of the program

Unit
Rebar processing shop

Formwork
processing shop

Capacity of production

shift

12t

20m2

Working system

Shift/day

Building area

m2

40

40

Shed

m2

200

60

Occupation of land

m2

2000

500

Equipment & Tools in Steel & Formworks Processing Plant


S.No

Description

Model

Number

Power (KW)

Rebar cutting machine

GQ40

Rebar bending machine

GW40

Mobile crane

YQ 16

Carpenters circular saw

MJ109

7.5

Carpenters circular saw

MJR154

4.0

Carpenters planning machine

MB104

5.0

Carpenter's flat plane

MBG502

4.5

Tenoner

MX2115

3.0

Carpenters drilling machine

MK515

2.5

SINOHYDRO CORPORATION LIMITED

Remark

Page 13 of 60

EPC Tender Documents: Tender Schedules

180 MW Kali Gandaki Koban Hydroelectric Project

3.9.4 Metalwork Plant

A metalwork plant will be set up to process some minor metalwork structure, the occupation of land will
be of about 8,000m2.
Planning of Metalwork Plant
S.No

Content

Unit

Building
area

Tool room

m2

20

Examining & repairing shop

m2

50

Storeroom

m2

40

Processing plant

m2

300

Storage yard

m2

Total

m2

Occupation
of land

Remark

shelf
8000

350

8000

3.9.5 Explosive Magazine

Temporary explosive magazine will be established on site to meet the requirement of blasting materials
during construction. The design storage capacity of temporary explosive magazine will be about 30t,
which can meet the requirement of site rock excavation works for
days during the peak construction
period. The temporary explosive magazine will be located on the right bank of river, with building area of
200m2 and occupation of land of 500 m 2. The designing, constructing and management of the temporary
explosive magazine will be carried out according to related laws of Nepal.
3.9.6 Fuel Station

In order to ensure the continuity of construction, the storage capacity of the fuel depot will be designed
as 100t. One fuel depot will be located at the right bank of dam and another one will be located near
powerhouse camp. The fuel depot will be designed, constructed and built by Contractor with two oil tanks.
Two tank trucks with capacity of 50 tons each will be provided on site to provide fuel for all machines and
vehicles.
Planning of Fuel Depot for the Project
No

Content

Unit

Fuel Depot

Storage capacity

100

Oil tank with capacity of 50t

Nos.

Occupation of land

m2

2000

Control room

m2

20

Construction of fuel depot (reinforced concrete


structure)

m3

210

Surrounding fencing (including gate)

260

3.9.7 Aggregate Processing Plant

The aggregate processing plant will be established adjacent to quarry site for production of concrete
aggregates, bedding materials and transition materials.

SINOHYDRO CORPORATION LIMITED

Page 14 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

In accordance with the analysis of demand quantity of graded aggregate used in the construction of dam,
access road and concrete placement in the peak period of construction, it is estimated that the
production capacity of sand/aggregates processing plant will be about160t/h, and the designed
processing capability of this system will be 200t/h.
Main Technical Parameter of Sand/aggregate Processing Plant
3.9.8 Concrete Batch Plant

According to the preliminary calculation and technical statistics, there are about 180,000m3 concrete to
be placed in this project, the average intensity of concrete placement during the peak time of
construction will be 11000m3/month, the concrete batching & mixing system will be designed and
planned accordingly.
One batch plant (u/s batch plant) with a design capacity of 90m3/h will be set up near the dam, another
batch pant (d/s batch plant) with a design capacity of 60m3/h will be set up near switchyard. Several
minor batch plants shall be established near the adits portal to provide some shotcrete.
Main Equipment Proposed for Concrete Mixing System
Serial No.

Items

Model

Quantity

Remark

Concrete mixing plant

HZ90-2F1500

90m3/h

Concrete mixing plant

HZ50-2F1000

60m3/h

Bulk cement silo

100t

Single-compartment silo pump

CP2.0

Air tank

3m3

Air compressor

DY-6/7

Bag-type dust collector

QMC24

Screw conveyor

GX300

3.9.9 Precast Production Yard

The precast concrete yard is set up near u/s concrete batch plant, the area is about 2000m2.
3.9.10 Laboratory

In order to meet the needs of inspecting and testing of raw material, semi-finished products and final
products used in the construction of this work, the central laboratory will be built up near the concrete
batch plant .Building area of the central laboratory is 120m2 with occupation of land of 1000m2.

4. Main construction methodology


4.1 Open Excavation Works
Open excavation shall follow the following procedures:
(1) Construction surveying

SINOHYDRO CORPORATION LIMITED

Page 15 of 60

EPC Tender Documents: Tender Schedules

180 MW Kali Gandaki Koban Hydroelectric Project

According to the requirements for different terrains, landforms and accuracy, the proper equipment and
different sampling methods shall be selected for construction surveying, with all the sampling work
conducted under the supervision of the engineer.
(2) Overburden excavation
The excavation of the overburden shall be executed by excavator. The layering excavation from top to
bottom shall be conducted according to the survey, with the bench height of 4 to 5m. The excavation
construction at the same level shall be subject to the order of first earth excavation, rock excavation and
slope support. The excavated materials are loaded onto 15~20t dump truck with the excavator to the
designated area.
(3) Rock excavation
The rock excavation is conducted after the overburden layer and the weathered rock are removed
completely. The rock excavation shall be subject to the bench blasting, the permanent inclined slope is
formed by presplitting blasting, the horizontal foundation formation is formed by the horizontal presplitting
blasting, for the narrow areas the protection layer will be preserved and excavated with control blasting.
Bench blasting hole making is mainly subject to the ROCD7 hydraulic drill and YQ-100B down-in-hole
drill; the YT27 hand drill is used for hole making in the narrow parts.
The construction procedures of presplitting blasting: operation instruction issuing---surveying and hole
distributing---drilling machine in place (with angle corrected) ---drilling hole---hole inspection---charging
and blastingentering the next cycle.
Excavated material transportation shall be loaded with excavator, unused materials are transported with
the 20t dump truck to the designated disposal areas, and utilizable materials for the dam to the
designated filling place.

4.2 Dam Embankments


Backfill and filling construction of soil and rock works in this Contract consist of: backfill and filling at
Guiding Structure, backfill and filling of Concrete Faced Rockfill Dam (CFRD).
Main quantities of backfill and filling project are showed as below:
Main quantities of backfill of soil and rock
No.
1

Description
Rockfill

Unit

Quantity

Remark

212320

Guiding Structure

17920

Guiding Structure

Boulder Rip Rap

Coarse Filter (Rockfill)

m3

150000

CFRD Zone 0-600mm

Medium Filter(Rockfill)

90000

CFRD Zone 0-400mm

6000

CFRD Zone 0-60 mm

2600

CFRD Zone 50- 400 mm

4
5

Filter in Transition

Downstream Slop Drainage

m3

4.2.1 Dam Filling Material Classification

CFRD dam filling materials consists of rockfill materials, transition materials, and downstream slope dry
boulder pitching. Guiding Dam filling materials consists of sand and gravel material, upstream face
bedding material and downstream face dry boulder pitching.

SINOHYDRO CORPORATION LIMITED

Page 16 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

Rockfill materials shall be obtained from the excavated materials of the spillway/under sluice and tunnel
excavation material, sand and gravel from river beach, and other bedding materials and transition
materials shall be gained from aggregate processing system.
4.2.2 On-site Filling and Compaction Test

Dam material compaction test is made up of the tests of bedding materials, transition materials, main
rockfill materials, and secondary rockfill materials.
4.2.3 Unit Division and Construction Procedures for Dam Filling

(1) Division and Cycling of Filling Unit of Working Face


It is proper that the area of each unit is within 3000 to 5000 m2.
The principle for unit cycling is that: the material spreading and leveling in the first unit, sprinkling water
and rolling in the second unit, and the quality inspection and acceptance in the third unit, which goes in
circles.
(2) Construction procedures for dam filling
Plane surveying of filling unit

Material side line surveying of


the areas, scattering lime

Foundation face acceptance

To next filling unit

Feeding and unloading

Excavation and loading of


filling material

Extra-diameter rock treatment

Control of leveling materials and


layer thickness

Sprinkling water

Rolling

Inspection of compaction quality

NO

Unit acceptance

(3) Order of zonal embankment of dam materials


The order of the filling operation of the dam plane is subject to the filling of one-layer 80cm-thick main
rockfill materials followed by filling of two layers of 40cm-thick transition materials, ensure that different
filling materials are always kept at the same level. The excavator is used to clear away the oversize
stone; the junction rolling shall be conducted at the joint of main rock material and transition material to
guarantee the compaction degree.
SINOHYDRO CORPORATION LIMITED

Page 17 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

4.2.4 Dam Filling Construction Technology and Method

1.

Dam materials transportation and downloading

(1) Dam materials transportation


The 15~20t dump truck is used to transport the dam materials with the sign boards on such vehicles to
distinguish the different materials areas. The cleaning should be kept for the carriage and tyres of the
transportation vehicles.
(2) Dam materials downloading
The frontward downloading method is applied to the main rockfill materials, and the backward
downloading method of downloading to the transition materials.
3.

Spreading materials

The thickness of spreading materials in each layer is 2 to 10 cm filling more than the compacted
thickness to reach the layer thickness of the technical requirements after being rolled. The layer
thickness of spreading materials in the areas of the dam shall be finally determined through the site test.
The bulldozer is used to level the fill materials. The elevation is controlled with the leveling instrument in
the material spreading to avoid big error.
4.

Oversize rock treatment

When oversize rocks arise in the main rockfill materials, the hydraulic breaker shall be used to crash
them, or the excavator is used to clear away them.
5. Dam material watering
To improve the compaction effect, water will be added to the filling materials outside the dam and on the
dam is applied.
(1) Water adding outside the dam: before the dam materials to the dam, water is added through the
watering station, and then delivered to the filling working face. The watering station is managed by
specially-assigned person and automatically controlled.
(2) Water adding on the dam surface: the method of combining watering cart sprinkling and the water
hose on the dam surface sprinkling is applied. Main water pipe is arranged at the upstream, connect
hose to add water on the dam surface.
6.

Material filling construction in the different area of the dam

(1) Filling of dam transition materials area


Transition materials are subjected to the 3 m3 loader for loading and the 15t dump truck for transportation
with the downloading subject to the backward method, T220 for spreading, 18t roller for compaction
In order to ensure the compaction degree and protect the u/s dam face, concrete extruding side wall may
be placed prior to the transition materials spreading, the side wall will be cast with extruding machine and
have a height of about 40cm for each lift.
(2) Filling of dam rockfill materials
The dam rockfill materials are from the excavated materials of the spillway and the tunnels, the 2 m3
excavator is used for loading and the 20t dump truck for transportation, downloading is subject to the
frontward method, and the T320 bulldozer is used to level materials. When spreading materials, the
levelling instrument is employed to control the thickness by the specially-assigned person to command
the leveling of the bulldozer.
Rockfill material watering control is determined through test, with the watering by combining the watering
outside the dam and on the dam.
SINOHYDRO CORPORATION LIMITED

Page 18 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

4.2.5 Construction of stone pitching behind the dam

The downstream stone pitching shall be placed layer by layer with the rise of the dam by excavator and.

4.3 Underground Works


4.3.1 Scope of Work

The underground works includes the excavation and support of the Bypass Tunnel, Headrace Tunnel,
Adit-1\2\3\4, Surge Tunnel, Drop Shaft, Underground Powerhouse, and Cavern for Transformers,
Tailrace Tunnel, PS Access Tunnel etc. The total excavation volume will be 490,000m3, with the rock
bolt of 253,000m, the shotcrete of 28,800m3.
4.3.2 Construction plan

1. Headrace tunnel
Four adits (adit-1 at chainage of 0+415, adit-2 at chainage of 4+177, adit-3 at chainage of 6+970, adit-4
at middle of connection tunnel of 2 shafts) shall be arranged to use as the access to carry out the
headrace tunnel excavation, each adit will provides two heading faces, and total eight heading faces will
be available.
New Austrian Tunneling Method will be adopted, micro-second delay-detonators and perimeter smooth
blasting will also be employed. Pneumatic drills (on a quick-fabricated platform) will be used for the hole
drilling, 0.5m3 excavator for muck loading and 10t dumper for transportation.
2. Sediment tunnel
Sediment tunnel shall be excavated from the intake and outlet simultaneously. New Austrian Tunneling
Method will be adopted, micro-second delay-detonators and perimeter smooth blasting will also be
employed. Pneumatic drills (on a self-making trolley) will be used for the hole drilling, 3m3 side-dump
loader for muck loading and 10t dumper for haulage.
3. Surge tunnel
After the headrace tunnel stretch 6+970~4+177 is completed, surge tunnel excavation will commence,
adit-3 will be the access. New Austrian Tunneling Method will be adopted, micro-second delaydetonators and perimeter smooth blasting will also be employed. Pneumatic drills (on a quick-fabricated
platform) will be used for the hole drilling, since the tunnel slope is little steep, 3m3 loader will be used to
load and transport the muck to the junction with the headrace, and load 10t dumper for transportation.
4. Drop shaft excavation
There are 2 shafts with the upper one having a height of 240m and the lower one having a height of
290m. Adit-3, adit-4 and access tunnel will be used as the access to transport the machine and the muck.
Raise boring machine shall be employed for the shaft excavation, firstly a pilot shaft with a diameter of
1.4m shall be drilled with raise boring machine, then enlarge the pilot shaft to the design line from top to
bottom by drilling & blasting method.
5. Access tunnel excavation
Excavation method is same as Sediment tunnel.
6. Power station excavation
SINOHYDRO CORPORATION LIMITED

Page 19 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

Power station has a dimension of 85m*15m*30m (L*W*H), the access tunnel will be access for the
excavation construction. Excavation shall be carried out from top to bottom in layer wise, New Austrian
Tunneling Method will be adopted, micro-second delay-detonators and perimeter smooth blasting and
pre-splitting blasting will be employed
1st layer: EL1932~EL1921
Normally full-section smooth blasting method will be adopted. If the rock condition is not satisfied, central
part shall be excavated firstly, after the primary arch support, both side parts shall be excavated
accordingly. Pneumatic drills (on a self-making trolley) will be used for the hole drilling, excavator and
loader for muck loading, 20t dumper for muck haulage.
2nd layer: EL1921~EL1914
Pre-splitting balsting shall be conducted firstly, then execute bench blasting section by section from
inside to outside, hole drilling by D7 hydraulic drill, muck loading by excavator and muck haulage by 20t
dumper.
3rd layer: EL1914~EL1910
Pre-splitting balsting shall be conducted firstly, then execute bench blasting section by section from
inside to outside, hole drilling by D7 hydraulic drill, muck loading by excavator and much haulage by 20t
dumper. Some muck will be hauled by 10t dumper through 1# manifold tunnel (the section has to be
extended to meet the dumper dimension) and access tunnel.
4th layer: EL1910~EL1905
Pre-splitting balsting shall be conducted firstly, then execute bench blasting section by section from
inside to outside, hole drilling by D7 hydraulic drill, muck loading by excavator and muck haulage by 10t
dumper, the access is 1# manifold tunnel and access tunnel.
5th layer: EL1905~EL1902
Pre-splitting balsting shall be conducted firstly,, hole drilling by pneumatic drill, muck loading by
excavator and loader, muck haulage by 10t dumper, the access is 1# manifold tunnel and access tunnel.
6. Transformer Cavern excavation
Access tunnel will be used as the access, exaction method is same as 1st layer of power station.
7. Tailrace tunnel excavation
Tailrace tunnel excavation shall be carried out from outlet to upstream, execution method is same as the
headrace tunnel.
For the first 150m stretch which is located in the river borne material, special attention shall be paid
during excavation. Leading consolidation grouting and leading anchor shall be proposed to stabilize the
unstable rock, the principle of short footage and weak blasting shall be followed. Shotcrete and steel rib
support shall be applied immediately as soon as current footage excavation is completed.
Deformation of surrounding rock shall be monitored at all the time.
4.3.2 Tunnel excavation measure

General tunnel excavation procedures are shown in the following chart:

SINOHYDRO CORPORATION LIMITED

Page 20 of 60

EPC Tender Documents: Tender Schedules

180 MW Kali Gandaki Koban Hydroelectric Project

When necessary
Excavation preparation
Setting out

Locally pilot rock bolt

Drilling holes
Explosive charging and blast
Ventilation and water spraying
Safety monitoring

Safe treatment
Primary support

Mucking

Extending air, water and power


lines and shifting to next cycle
1) Setting out: Measurement and setting out will be performed before construction according to the blast
design. The total station and laser directional instrument will be used for the setting out.
2) Drilling operation: Pneumatic drill YT-27 will be used for the hole drilling. When the tunnel section is
more than dia.6m, a drilling trolley will be equipped, several drills can work on the trolley at the
same time. When the tunnel section is smaller, a quick-fabricated platform will be equipped, the
platform will be dismantled while the mucking commences. Perimeter smooth blasting holes shall be
controlled strictly to ensure the excavation line meets the design.
3) Explosive charging and blast: No.2 rock blasting explosive or emulsion explosive will be used.
Different explosive cartridges will be adopted for different holes. The method of explosive charging
and blasting process refer to the following table.
Charging method and ignition order
Location of Hole

Explosive Cartridge

Remarks

Cut hole

32

35mm

Successive charging

Breaking hole

32

35mm

Successive charging

Perimeter hole

22 mm

Interval charging

The sequence of millisecond delay blasting is:


cut hole

breaking hole

perimeter hole.

4) Ventilation and smoke extraction: heavy duty propeller fan will be adopted to supply the forced
ventilation after blasting. Fresh air will be blown to the working face through the air duct.

SINOHYDRO CORPORATION LIMITED

Page 21 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

5) Safe-handling: After blasting, the safety staff and worker will firstly investigate and handle the
potential safety hazard of heading face and arch. After the mucking, the heading face shall also be
inspected and treated by safety personnel.
6) Mucking: WA380 side-dump loader and excavator will be adopted to load the muck, and 10~20t
dumper for haulage. Excavated material for reuse shall be placed directly in its final position, if
possible. Otherwise it may be stockpiled or deposited on site. Unused materials shall be deposit to
spoil area. For the truck crossing, passing bays will be established with a space of about 400m, to
allow turning of transport vehicles.
4.3.5 Support construction

constructions of bolt (anchor)

Anchor bolt construction shall be generally carried out after initial shotcreting is finished on excavation
face. For the excavation face with relatively poor stability, temporary support anchor bolt can be first
installed and then shotcreting can be conducted.
The installation position of anchor bolt shall be determined according to the design drawing or site
designation by the engineer or safety requirement. Measuring personnel shall mark the drilling position.
Hand pneumatic drill and anchor jumbo drill shall be used to drill according to the design hole position,
angle and hole depth. After drilling, the hole shall be cleaned. Injection pipe shall be used to inject grout
outward from the hole bottom, and then anchor bolt shall be inserted into the hole. After anchor bolt is
fixed with steel wedge, mortar mixed with accelerator shall be used to fill the orifice solidly.
Construction procedure: initial shotcreting
setting out
inserting anchor bolt fixing orifice treating orifice.

drilling

cleaning the hole

grouting

As to the anchor bolt for emergency support, ordinary grout might not be injected into bolt hole, and
special injection gun can be used to inject the composite containing accelerator into bolt hole, so as to
make anchor bolt and composite grout quickly solidified with certain strength. Therefore, the surrounding
rock can be reinforced fast.
2

Constructions of shotcrete

Shotcreting shall be organized and carried out after excavation face is made. When the geological
section is poor, shotcreting shall be conducted immediately after excavation. The construction shall be
carried out according to instructions of the engineer. The distance between shotcreting face and
excavation working face shall ensure no influence of blasting vibration on concrete solidification.
According to site conditions, wet shotcreting or dry shotcreting can be adopted. For wet shotcreting,
concrete shall be first mixed in batching station and then be transported to the working point; concrete
shall be put into concrete sprayer manually, and liquid accelerator shall be added at the sprayer head.
Before shotcreting, rock surface shall be treated to make it clean and wet. Shotcreting shall be
conducted symmetrically from bottom to top in layers. The shotcreting thickness of each layer is about 50
mm. For relatively large shotcreting face, operating platform shall be erected. After shotcreting, wet
curing shall be carried out until the design strength is reached.
Construction procedure: construction preparation
quality inspection curing.
3

rock surface treatment

setting out

shotcreting

I-Steel Support

For the surrounding rock sections with relatively poor geological conditions, in order to ensure stability of
surrounding rock during tunnel excavation and surrounding rock of excavated section, and according to
analysis of observation data of surrounding rock displacement, for the tunnel section which still shows
the sign of instability after shotcreting anchorage, steel support will be adopted to strengthen support, so
as to ensure stability of tunnel excavation.
I-shaped steel is generally adopted to process steel support, which is designed according to the tunnel
section and processed in segments in comprehensive processing plant. After steel supports are
transported to the construction site, they shall be assembled, and bolts or welding will be adopted to
connect segments.
Construction process of steel support: cleaning excavation face
anchor bolt installation of steel support shotcreting

SINOHYDRO CORPORATION LIMITED

initial shotcreting

installation of

Page 22 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

4.4 Grouting Work


4.4.1 Tunnel surrounding rock consolidation grouting

According to design drawing, use pneumatic drill to drill grouting holes. In order to avoid drilling holes
encountering rebar in lining concrete, it is proposed to embed steel pipe or PVC casing based on design
during concrete lining construction, and then carry out drilling from embedded pipe.
After drilling, use pressure water to wash the hole repeatedly and carry out water pressure test.
According to parameter gained from water pressure test, adjust grouting pressure and grout mix
proportion. During process of grouting in sequence, adjust grout mix proportion level by level according
to grout-take volume, until it reaches designed standard to stop grouting. If it does not reach the standard
for a long time, report to engineer to analyze the reason and figure out dealing measures together. When
grouting is finished, seal the hole and cut off the embedded pipe exposed on the concrete surface.
4.4.2 Curtain grouting

The dam curtain grouting construction will be done on plinth.


Grouting shall be carried out in stages, 'B' line holes shall be drilled and grouted prior to drilling of 'A' line
holes. No holes of subsequent series shall be drilled until grouting has been completed to full depth in
adjacent holes of the previous series.
Before construction, conduct grouting test to investigate grout-take capacity of underground rock. At the
time of grouting through a single hole, based on fracture degree of surface rock, determine to conduct
sectional grouting from top to bottom or from bottom to top. If foundation rock is fractured, it is suggested
to conduct downstage grouting.
Based on designed hole-depth, XY-2 rotary geological drill with carbide bit or artificial diamond bit shall
be selected for drilling of curtain grouting. After drilling, rinse the hole and conduct water pressure test
selectively to get reference information for adjustment of grout mix proportion. As construction area of
curtain grouting is kind of centralized, grout preparation station may be set in neighbor area to supply
grout. Use grouting pipe to deliver grout to pumps. During the whole course, use automatic recorder to
record and print the grouting data which will be used as the original date for calculation of grouting work
volume and the reference of following grouting.

4.5 River diversion


4.5.1 Plan

As per the project scale and the local hydrology, 20-year return period flood standard shall be
adopted to make the design, the respective flow is 500m3/s, stage diversions shall be arranged, please
refer to the river diversion plan drawing.
Stage 1 cofferdam for Guiding structure: build u/s transversal cofferdam, d/s transversal cofferdam
and longitudinal cofferdam to enclose the structures at the right abutment, and construct the headrace
intake and the spillway and the side channel, river flow will run in the original river bed.
Stage 2 cofferdam for Guiding structure: After the sediment bypass tunnel is ready, build the u/s
cofferdam, and construct the guiding structure, the river flow will run in the bypass tunnel. River diversion
shall be carried at the beginning of the dry season.
Cofferdam for CFRD: After stage 2 cofferdam for guiding structure is completed, the river flow will
run in the bypass tunnel, at this time to build cofferdam at CFRD d/s, then construct the CFRD and the
structures at the right abutment.
Power station and switch yard are at higher level, no cofferdam is required.
4.5.2 Structures for river diversion

Cofferdam shall use earth and rock embankment, Geo-membrance and high-pressure-jet cutoff for
anti-seepage.
When building Stage 1 cofferdam for Guiding structure, the river water level will be about EL2508m,
the cofferdam crest will be set at EL2509m. The cofferdam will have a height of 4m with the crest width
of 4m, the cofferdam side slope is 1:2~1:2.5.
SINOHYDRO CORPORATION LIMITED

Page 23 of 60

EPC Tender Documents: Tender Schedules

180 MW Kali Gandaki Koban Hydroelectric Project

When building Stage 2 cofferdam for Guiding structure, the river water level will be about EL2511m,
the cofferdam crest will be set at EL2513m. The cofferdam will have a height of 5m with the crest width
of 4m, the cofferdam side slope is 1:2~1:2.5.
When building CFRD d/s cofferdam, the river water level will be about EL2506m, the cofferdam crest will
be set at EL2507m. The cofferdam will have a height of 5m with the crest width of 4m, the cofferdam
side slope is 1:2~1:2.5.
4.5.3 Cofferdam construction

Since the river diversion will be carried out at the dry season, the river flow is limited, so the river
diversion will be easier. The closure dike shall progress from one side to the other side, excavator for the
earth and rock loading, dump truck for hauling, and dozer for pushing and leveling.
After the closure dike is completed, use rotary drill to drill hole and high-pressure jet trolley to make
the cutoff, then increase and widen the dike to the design section
.4.5.4 Foundation pit drainage

After the cofferdam is ready, several sump pits shall be made, and pump out the water (seepage
water, rain water and construction waste water) and keep the construction in dry condition.

4.6 Concrete works


4.6.1 Dam concrete construction

4.6.1.1 Concrete construction of plinth


1.

Plinth concreting procedure

As shown in the following flow chart:

Cleaning

Install
water stop

Concreting

2.

Erect steel
bar

Drill anchor
bar

Embed
anchor bar

Measure
template

Embedded
parts

washing

acceptance
inspection

Concrete curing

Concrete placing

The concrete is mixed by the concrete mixing station, transported by 6 m3 mixer truck, and delivered to
the place by chute or concrete pump. The general plinth concrete is vibrated by Foshan 100 vibrator,
and it adopts 50 vibrator for the concretes in parts with intensive waterstop, embedded parts and
reinforcing steel bars.
3. Waterstop protection
After removing the formwork of plinth, waterstop shall be protected in time by wooden boxes. The placing
close to waterstop will be undertaken by specially assigned personnel by small vibrator to prevent from
the deformation of the waterstop. The placing layer shall be controlled at about 30cm. When placing the
plinth in abutment slope, it shall start from the lower area, and keep the placing surface horizontal.
4.2.3.2 Concrete face slab construction

1. Face slab concreting procedure

SINOHYDRO CORPORATION LIMITED

Page 24 of 60

EPC Tender Documents: Tender Schedules

180 MW Kali Gandaki Koban Hydroelectric Project

Trackless sliding formwork shall be employed to construct the face slab. The procedure of concrete face
slab construction is shown in the following chart.
Set out

Apply mortar at joints

Set copper waterstop

Install winch

Set joint bar

Install. transport trolley

Install. reinforcing

Remove the trolley

Install chute

Install side form

place slip form

Manual
operation

Crane hosting

Face slab concreting process

Install side form

Concreting

Surface finishing

Dismantle side form


Concrete curing
Remove slide form

2. Lifting of the sliding formwork and arrangement of the chute


After installing the side formwork and reinforcing mattress, it can install the sliding formwork. After
fabricating at the dam heel, lift the sliding formwork onto the side formwork by crane. Trail sliding has to
be executed prior to the formal placing.
Installation of the chute: after the sliding formwork is in position, it can install chutes on the reinforcing
mattress. The chutes are tied to the reinforcing mattress to guarantee the safety. It can arrange two to
three pieces of chutes for one slab.
3. Concrete pouring and Formwork lifting
The concrete is mixed by the concrete mixing station, transported by 6 m3 transit mixer truck.
Upon the completion of the inspection and acceptance, concrete can be poured. Concrete shall be
placed horizontally in lift wise with the lift thickness of 25 30cm. Conduct vibration after the whole layer
SINOHYDRO CORPORATION LIMITED

Page 25 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

concrete surface is even and flat. It will be vibrated by immersion vibrator with diameter less than 50mm.
During the construction, it shall pay attention to the vibration at the waterstop, for which it shall use
smaller vibrator.
When sliding up, it shall stably and synchronically lift both ends with uniform speed. It will slide up one
time for 25-30cm after one lifts concrete pouring finished. The average pouring speed with the sliding
formwork shall be controlled at about 1m/h, and the maximum speed shall be no larger than 2.5m/h. it
shall timely conduct manual finishing to the concrete surface with steel trowel after the formwork is slid
up.
Concrete curing shall be applied in time curing to the concrete face, special-assigned personnel shall
record the whole process of curing.
4.6.2 Spillway and Undersluice construction

1.

Concreting procedure

Concrete shall be placed in lift wise with each lift height of about 3m. In general, the concrete placement
procures:
Foundation clearing (construction joint clearing)
Inspection of prepared foundation surface
setting out
Erecting formwork & reinforcement & embedded parts
Clearing off the debris
Inspecting & acceptance
for Placing Concrete
Concrete mixing and transport
Concrete placing and vibrating
Removing of
formwork and concrete curing

2.

Concreting measures

(1) Checking before concreting


After completion of treatment of foundation surface and trimming of construction joint surface, the treated
surface upon which concrete will be placed shall be cleared by manpower and flushed with high-pressure
water, followed by draining off all of collecting water. The construction joint surface shall be green-cut in due
course except for some narrow locations where the construction joint surface shall be roughened by the
manpower. Thereafter, all of debris, foreign matters and other materials shall be washed off.
The points, lines, grades and elevations shall be precisely surveyed and set out by using a total station. The
markings of points, lines and levels shall be clear and visible for easy measuring.

(2) Steel bar processing and fixing


Technicians shall fill in the rebar request sheet in accordance with the shop-drawings and technical
specification, and submit the request sheet to rebar processing workshop where the re-bars will be cut and
bended as per the aforesaid sheet. The identification label shall be attached to each bundle of rebar to avoid
any confusion. The fabricated rebar shall be hauled to the site with flat-bed trucks and installed by the
manpower. The installation of reinforcement shall conform to the requirements of construction drawing and
specification.

(3) Installing Formwork


Steel and wooden formwork shall be used. The formworks shall be transported and installed in a safe and
protective manner to prevent them from deformation and damage. The formwork should be elected by tower
crane or mobile crane in coordination with the manpower. Every time, removal of dust from the formworks
should be carried out before they are erected, and the surface of formworks shall be applied with a layer of
formwork stripping agent. The formwork should be erected at the exact location and level, and shall be
securely tied and supported, to ensure the levels and the dimensions of concrete in conformity with the
requirements of design and specification. The embedded parts and waterstop will also be firmly fixed.
After completion of installation of formwork, surveying and correction of formwork shall be carried out carefully,
then water stop shall be installed. Finally, the pouring block shall be cleared and washed by high-pressure
SINOHYDRO CORPORATION LIMITED

Page 26 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

water gun to remove all the debris, chippings, garbage and other foreign matter out of the block.

(4) Concreting
Prior to the starting of each concrete placement in a pouring block, the technicians along with the Quality
Controller and the Engineer shall carry out a careful inspection to the pouring blocks and issue the Release
Order for Concrete Placement.
Concrete will be mixed in u/s concrete batch plant, transported with 6m3 concrete mixer truck or dump truck,
lifted and deposited by tower/mobile crane and bucket, conveyance belt and chute and concrete distributing
belt could be used where the site condition is permitted.
The concrete shall be deposited as nearly as possible in its final position without re-handling or segregation
and in such a manner as to avoid displacement of the reinforcement, other embedded items or the formwork.

(5) Curing
After completion of each concrete placement, it should be covered with straw mat for curing till the initial
setting of concrete is achieved. Then, the concrete can be cured by spraying some water up to the expiry of
aging.

(6) Removing Formwork


When the concrete reaches the condition to possibly remove the formwork, formworks shall be stripped off by
using crane in combination with manpower. After removal of formworks, the concrete surface shall be carefully
inspected. If any defect is found, and suitable measures to repair the defect shall be taken.
For the tunnel intake and outlet, similar method and procedure shall be taken for the concrete placing.
4.6.3 Tunnel concrete lining

In the headrace tunnel, when the class-5 surrounding rock is encountered, whole section concrete lining
will be applied.
Firstly the invert concrete slab shall be placed, then install side-wall and arch steel mould trolley, to cast
the side-wall and arch. Concrete is mixed in u/s concrete batch plant, transported by 6m3 mixer truck,
and deposited to the place with concrete pump.
Concrete lining shall be carried out in section wise with each section length of about 10m, the mould
trolley will move on the steel rail driven by loader or excavator. Before the mould trolley is to be in
position, the steel bar fixing and embeddd parts and water stop installation should be ready.
Floor concrete shall be placed ahead of the side-wall and arch by several blocks, floor surface shape
shall be controlled by template frame.
4.6.3 Drop shaft lining

Shaft will be lined with penstock and concrete. Upon the completion the excavation and support, Lining
can be carried out. Lining shall be executed from bottom to top in section wise with each section height
of about 10m.
First the penstock pipe will be lowered from top with wench and steel cable, then positioned and welded.
After the pipe the welding seam are inspected and detected, concrete can commence.
Concrete shall be mixed in d/s batch plant, transported to shaft top by 6m3 mixer truck. Concrete
conveyance from top to the place by Dia.200 steel pipe equipped with buffer box at every 10m height, to
guarantee no segregation will happen.
At the Dia.250 pipe bottom, a rotatable distributing pipe is connected to distribute the concrete to the
place evenly, concrete leveled by manpower and vibrated by flexible-shaft vibrator.
SINOHYDRO CORPORATION LIMITED

Page 27 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

4.6.3 Power station concrete

Power station has a dimension of 85*15*30m (L*W*H), the concrete volume is about 8000m3. Access
tunnel will be the access for concrete placing.
Concrete shall be placed in lift wise with each lift height of 1.5m to 3m, combined steel formwork and
scaffold pipe and tie bar shall be used.
Concrete shall be mixed in d/s batch plant, transported by 6m3 mixer truck, conveyance belt, concrete
distributing belt, chute shall be used to deposit concrete to the place. At some higher locations, concrete
pump shall be used to pump concrete to the casting place.
Flexible-shaft vibrator shall be used to compact the concrete, flat-vibrator shall be used for the floor
concrete compaction. During the concreting, attention shall be paid to the embedded parts and water
stop, special staff shall be designated to supervise this work, no deformation or movement shall happen
to these items.

4.7 Turbine equipment installation


4.7.1 General Installation Procedure

Preparatory works
Embedded of base plate and pipes installed

Installation of turbine housing and maintenance platform

Installation of distributor parts

Installation of pit liner

Second stage concrete

Installation of turbine shaft

Installation of turbine guide

Installation of water passage shield

Installation of generator foundation

Installation of installation of generator

Installation of nozzle assemblies

SINOHYDRO CORPORATION LIMITED

Page 28 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

Installation of runner

Installation of nozzle assemblies

Coupling of turbine & generator shafts

Adjustment of axis
Adjusting centerline of rotating parts

Installation of main shaft seal

Dry test

Commissioning

4.7.2 Embedding of base plate and pipes

1) First stage concrete finished


2) Base plates for distributor and turbine housing installed
3) First stage embedded pipes installed

SINOHYDRO CORPORATION LIMITED

Page 29 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

4.7.3 Install turbine housing and maintenance platform

1) Installation of turbine housing


2) Installation of maintenance platform
3) Adjustment of the parts
4.7.4 Install distributor parts

1) Installation of distributor parts


2) Alignment of distributor parts
3) Welding of distributor parts
SINOHYDRO CORPORATION LIMITED

Page 30 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

4) Welding of connections to turbine housing


5) Installation of piping
6) Application of pressure test devices
7) Pressure test
(Touch-up painting if applicable)

4.7.5 Install pit liner

1) Alignment of pit line on turbine housing


2) Weld on pit liner on turbine housing
3) Touch-up painting if applicable
4) Apply stiffeners if applicable

SINOHYDRO CORPORATION LIMITED

Page 31 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

4.7.6 Secondary stage concrete

1) Concreting of up to generator floor


2) Distributor pipe shall be concreted under pressure
3) Remove stiffeners if applicable
4) Closing of openings for concreting
5) Touch up painting if applicable

SINOHYDRO CORPORATION LIMITED

Page 32 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

4.7.7 Install turbine shaft

1) Installation of bearing support on turbine housing


2) Lifting in of turbine shaft
3) Installation of temporary support for turbine shaft (bearing cover)
4) Shaft alignment
5) Shaft free

SINOHYDRO CORPORATION LIMITED

Page 33 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

4.7.8 Install turbine guide bearing

Installation of remaining bearing parts (pads, cooler, covers, etc.)


4.7.9 Install water passage shield

Lifting up and install the water passage shield.

SINOHYDRO CORPORATION LIMITED

Page 34 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

4.7.10 Install generator foundation

May be done after 2nd stage concreting

SINOHYDRO CORPORATION LIMITED

Page 35 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

4.7.11 INSTALLATION OF GENERATOR

Generator installation may be started immediately after shaft free (in coordination with turbine supplier)

SINOHYDRO CORPORATION LIMITED

Page 36 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

4.7.12 INSTALLATION OF NOZZLE ASSEMBLIES

1) Modification of passflange for nozzles - justify with dummy nozzle and dummy
2) runner
3) Bring in nozzle with transportation cart to maintenance platform
4) Install lifting devices (chain hoists) on turbine housing
5) Lift up and install nozzles to distributor pipe (include passflange)
6) Install oil piping
7) Install water piping

SINOHYDRO CORPORATION LIMITED

Page 37 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

4.7.13 INSTALLATION OR RUNNER

1) Using Lifting cylinder in turbine shaft:


2) Bring in runner by transport cart to maintenance platform
3) Lower hydraulic lifting cylinder and connect to runner
4) Lift up runner
5) Couple runner to shaft
6) Install cover for coupling bolts

4.7.14 INSTALLATION OF REMAINING PARTS

Installation of remaining parts such as piping, instruments, smaller parts as well as auxiliary systems
such as governor, inlet valve, cooling water system (as far as applicable) can be done in parallel with
other works.

SINOHYDRO CORPORATION LIMITED

Page 38 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

4.7.15 COMMISSIONING AND FIELD TESTS

Commissioning of the unit including dry & wet tests, in coordination with the generator supplier.

Field tests according to the contract.

4.8 Generator Installation


The Section shall describe the installation of stator, rotor, thrust bearing and guide bearing, upper and
lower brackets, slip ring and brush, cooling water system, lubrication system, brake system, fire fighting
system, relay and instrument etc.
4.8.1 General Installation flowchart for generator
Preparation works

Embeding soleplate

Assembly the stator

Preassembly the lower


and upper bracket
Lifting the upper bracket out of pit

Lifting the lower bracket out of pit bracket


Put the elevation
f
Lowering the turbine parts

Installing the lower bracket

Erecting the rotor hub

The rotor assembly

Installing the upper bracket


Installing the trust bearing
Shrinking the thrust cone on
Coupling the main shaft and the turbine shaft
Installing the collecting ring

Installing the upper


Align the axial line of unit

Installing the oil

adjusting the gap of the guide


bearing segments

water pipeline
Installing the other parts of unit

Cleaning and checking the unit

Starting up and trial run

Completion
SINOHYDRO CORPORATION LIMITED

Page 39 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

4.8.2 Embedding soleplate

4.8.3 Lowering the stator

SINOHYDRO CORPORATION LIMITED

Page 40 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

4.8.4 Assembly of stator

4.8.5 Preassembly the lower bracket

SINOHYDRO CORPORATION LIMITED

Page 41 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

4.8.6 Preassembly the upper bracket

4.8.7 Assembly of the lower bracket

SINOHYDRO CORPORATION LIMITED

Page 42 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

4.8.8 Rotor assembly

4.8.9 Rotor pole turning over

SINOHYDRO CORPORATION LIMITED

Page 43 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

4.8.10 Lowering the rotor

4.8.11 Installing the upper bracket

SINOHYDRO CORPORATION LIMITED

Page 44 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

4.8.12 Installing the other parts of unit

4.8.13 Demolition flowchart for generator overhaul


The demolition of oil and water pipe
The demolition of
guiding pads

The demolition of oil pipes and water pipes

The demolition of temperature


lines

The demolition of Carbon brush and cooler

The demolition of cover Collection slip ring

The demolition of upper bracket

The demolition of upper axis

The demolition of rotor

The demolition of axis

The demolition of lower bracket

SINOHYDRO CORPORATION LIMITED

Page 45 of 60

EPC Tender Documents: Tender Schedules

180 MW Kali Gandaki Koban Hydroelectric Project

4.9 Penstock manufacturing and installation


4.9.1 Flow chart of penstock manufacturing and installation
Preparations for penstock manufacturing

Preparing purchasing plan for raw material


Compiling the instruction of
ti
Purchasing raw material
Test of evaluating welding process

Compiling welding process

Compiling welding process of


penstock

Test of evaluating painting process

Compiling painting process

Inspection, acceptance check and test of raw


material

Compiling process workflow at


penstock shop workshop

Assembling and welding of penstock section


Cutting of rolling sheet

Assembling and welding accessories and


penstocks

Assembling and welding of the


i

Derusting and painting of penstock section

Assembling and welding of penstock section


Inspection & acceptance check of single-section
t k
Inspection & acceptance check of penstock section

Transportation of penstock

Preparations for penstock


installation

Assembling and welding of penstock

Concrete backfilling of penstock

Grouting treatment for penstock

Closure welding for grouting holes

Derusting and painting of the welding gaps

Clean, inspection and acceptance check of


penstock

SINOHYDRO CORPORATION LIMITED

Page 46 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

4.9.2 Penstock manufacturing

4.9.2.1 Field arrangement of penstock manufacturing


Workshop for penstock manufacturing shall be set up at site, the main arranged equipments for penstock
manufacturing are: 20t weight, 24m-span gantry crane (1 Pc.), which is used for the hoisting of loading/
unloading , blanking, circular, installing and welding of the finished steel sheet and penstock, W11STNC50

3000 3-roll rolling machine (1 Pc.), 10t weight, 8m-span hoisting gantry crane (1 Pc.) is used for the

rolling of penstock tile, roll-welding trolley (1 Pc.) is used for circular seam welding of penstock sew.
Steel sheet are stacked orderly and leaving from ground in different kinds and thickness, and they are
marked clearly.
Welding material: welding wire and welding rod should be put in storeroom, welding liquid should be put
in dry container, and welding wire and welding rod should be kept clean and dry.
4.9.2.2 Manufacturing Flow Chart of Penstock
Marking and cutting of steel plate

Steel tube attachment marking and

Weldingbutt joint of steel plate

Assembling of steel tube attachments

Steel plate rolling

Welding of steel tube

Assembling sections of steel tube

Butt inspection of steel tube

Welding the longitudinal joints of steel

Back chipping of internal longitudinal

Welding the external longitudinal of

Assembling sections of the steel tube

Penetrating inspection on longitudinal

Welding the interal circular joints

Assembling and welding of steel tube

Back chipping of internal circular joints

Welding inspection

Welding of external circular joints

Derusting and painting of tube

Installation the interanal supports of

Inspection of size shape

Single section of tube leave factory

SINOHYDRO CORPORATION LIMITED

Girth welding flaw detection

Derusting and anti-corrosion of

Inspection of size shape

Large section of steel tube leave

Page 47 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

4.9.2.3 Blanking and machining of steel sheet


1) Steel sheet blanking
(1) Steel sheet blanking base on the real width of steel sheet, the ordered width of steel sheet is 2m,
2 sections make a bigger segment, and the size of the bigger segment is 4m.
(2) After scoring steel sheet, mark the number of machine, segment, block, water flow direction, the
centering line in horizontal and vertical, the location of grouting hole, the angle of groove, the cutting line
and so on.
(3) The steel sheet cutting and the preparing groove is made by semi-auto-cutting machine. The
slag, burr of cutting side and the gap made through cutting should be rubbed out by grinding wheel. After
cutting, the limited deviation of groove size should follow the requirements in related technical
specifications or design.
(4) After machining the groove, then paint the anti-rust paint which is hazard-free and not affect the
welding capability and quality.
2) Rolling sheet
Single-segment penstock could be machined into two (2) penstock tiles, firstly should weld the steel
sheet into entirety as per markings, then roll to tile shape. When rolling steel sheet, make sure the
direction of rolling-sheet should be the same with the press forging direction. Measuring and rectifying
sheet by sample while rolling, in order to ensure the radian following requirements. When rolling the
sheet, dont hammer the sheet, and keep the sheet form appearing any scar.
Before rolling penstock, should clean the attached horn wire, oxidations and so on, and carry out
cleaning during rolling operation accordingly.
3) Fabrication of penstock
(1) Penstock circular is made in circular platform. Should imagine and measure if the up and down
nozzle is even, the even degree of nozzle shouldnt more than 2mm.
(2) The penstocks perimeter, vertical, clearance and assembly tolerance should comply with the
specifications.
(3) After welding the longitudinal seam, should arrange the supporting which have the adjusting
functions inside the penstock, which can reach the requirements of the different requirements on
maximum and minimum diameter of penstock.

Circling support of penstock

SINOHYDRO CORPORATION LIMITED

Stiffening support of penstock

Page 48 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

(4) The installation of the bigger segment shall be completed through the bigger-segment assembly
trolley. Hang the penstock segment and put it on the trolley, move the penstock to a correct installing
direction, using the combination of strainer and chain jack, then conduct seam-pressing and spot-welding
symmetrically by seam-pressing machine after measure the two opening perimeter and the averagelydistributed displacement.
(5) Penstocks longitudinal jointing and circular jointing should adopt automatic submerged arc
welding, and the circular welding should be conducted on the roll-welding trolley.
(6) Never harm the substrate when welding and dismantle accessories as fixture tools and lifting lug
at penstock segment for the requirements of assembly, transportation and installation, and the place of
welding should be ensured of no harm to penstock and produce over-stress while lifting. If there is no
bad influence to the following procedures, the accessories can not be dismantled.
(7) Installation of stiffening ring
After conduct longitudinal welding to the penstock and pass non destructive inspection, can use the
adjusting inner circling support at welding place of stiffening ring, and weld stiffening ring and penstocks
stabilizer. The butt weld of stiffening ring and longitudinal seam should be misplacement more than
100mm as required, and the inner radian should be checked by sample with the string is 1.5m, and
check clearance shouldnt over 2.5mm.
The welding of stiffening ring and penstock should adopt manual electric arc welding.
4) Manufacturing of manifold penstock and bending penstock
When making manifold penstock, should adjust the rolling machines upper roller to a leaning angle,
then roll according to the mean line of big and small border radian. Check two pieces of different radial
sample sheet in plane position while rolling. When a piece of steel sheet is in finished, should continue to
roll the steel sheet to next mean line, after the manifold penstock is in finished form, some part of radian
may bigger or smaller, should correct radian of the manifold penstock using flame. After the radian
correction, should fix two sides of the nozzle by temporary supporting. When the sections of manifold
penstock are machined, should conduct preassembly at machining spot. The manufacturing way of
bending penstock and reducing penstock are the same as manifold penstock.
The forked penstock should be installed and welded entirely on-site, and every size of welding
should comply with the specifications of the design drawings.
4.9.3 Transportation of penstock

(1) The finished penstock should be transported to the spot by a 40t trailer. When transporting,
penstock should be placed in side direction and level. Interior can be fixed by movable supporting, the
space between penstock and trailer can be supported by arc-pallet, and fastened by steel wire.
(2) Should pre-embed two 40t flukes on the top of the construction lateral tunnel which is the cross
between the construction lateral tunnel and every penstock tunnel, and should dispose a 10t hoisting
machine inside the construction lateral tunnel. After transported penstock into the tunnel, should hang
penstock in four sides horizontally by hoisting machine and pulley block, then the trailer retreat from the
tunnel. Hoist the upper flat tunnel and the inclined straight section to the track directly, then back
transport to the installation position. Hoist the down flat section penstock to the penstock trolley, and tow
to the installation position by hoisting machine and install.
SINOHYDRO CORPORATION LIMITED

Page 49 of 60

EPC Tender Documents: Tender Schedules

180 MW Kali Gandaki Koban Hydroelectric Project

(3) The transportation of inclined straight sections and upper flat sections. Dispose a 5t hoisting
machine and a 10t hoisting machine in the upstream of the construction lateral tunnel. After penstock is
transported from construction lateral tunnel to the penstock tunnel, should utilize the pre-embedded fluke,
then unload penstock to the track by hoisting machine and pulley block. Tow the penstock to upper
bending penstock by 5t hoisting machine and pulley block,
then slide penstock to the installation position by 10t hoisting

Preparation

machine and pulley block and install.


4.9.4 Installation of penstock
Hoisting to installation

(1) Penstock transportation access: adit-3 for stretch of


upper shaft, adit-4 for stretch between 2 shafts and lower

Butt joint of penstock

shaft, access tunnel for stretch of d/s of lower shaft.


(2) Penstock will be put in the position by winch and

position, they will be jacked up by jack through arc pallet,


then readjust penstocks orderly. When seam-pressing and
welding the penstock, the inside and outside of penstock can
be fixed in upper opening by removable working platform to

Repeat in this order

trolley and penstock stabilizer. After the penstocks are in

Circular welding

Detection of defects

Stiffening and cleaning

make sure the builders safety.


(3) The installing of penstock and the concrete pouring

Check and acceptance

can be alternately made in segment, the installing and


pouring length of every section is 10~12m, as the right

Concrete pouring

flowchart of penstock installation is showed, installation by


pouring one after one. After finishing a section of pouring,
should make a whole checking and adjusting, and fix the

Grouting

penstock to the steel dowel on the tunnel wall by junction


pieces (strainer and round steel) etc. according to the

Finishing painting

designing requirements. The junction pieces should weld to


the

penstocks

stiffening

ring,

fix

tightly

and

avoid

final acceptance

displacement when pouring. Before pouring, should meet


inspector for pilotscale inspection, the mileage, highness and installation centers deviation of penstock
should comply with the specifications.
(4) Should keep the stiffening support inside the penstock until the pouring is finished, and can be
removed only until certain intensity is reached. Should consider the turnover quantity of the stiffening
support
4.9.5 Welding of penstock

Before welding, should prepare the technical specifications following the approved Welding
Technology Reviewing Report, combined with the reality of this project, and report to the inspector then
weld after approved.
SINOHYDRO CORPORATION LIMITED

Page 50 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

The welding of penstock longitudinal jointing should adopt automatic submerged arc welding; the
longitudinal jointing of penstock after tiles butting and the circular jointing of penstock after installing the
bigger segment should be welded on the roll-welding trolley; the circular jointing, stiffening ring and other
accessories of the bending penstock should be welded by manual electric-arc welding.
4.9.5.1 Cleaning before welding
Before welding, should clean impurities such as oxidized surface, rust, oil dirt and so on which are
in the all welding surfaces and the two sides of groove at the range of 50 ~ 100mm, and clean at once
after one section welding finished, then continue welding after checking qualified.
4.9.5.2 Tack weld
The project need to be welded should be assembled and tack welded by means of the approved
methods. All welding work including tack welding and temporary welding should follow the welding
procedure strictly. The preheating temperature of tack welding seam should higher 20 ~30 than the
preheating temperature of main welding seam, and should maintain the preheating temperature during
the welding, the interlayer temperature shouldnt lower than the preheating temperature and should less
than 230 ,
4.9.5.3 Welding
(1) The welding of longitudinal seam and circular seam in manufacturing factory should be
conducted in an ease work shed via automatic welding. The welding of stiffening ring should be
conducted in the open air.
(2) The welding of penstock in tunnel should be weld via manual electric-arc welding, every weld
seam should be welded by 6 welders symmetrically via DC Inverter Welding Machine.
(3) Before welding, should check the installation of main parts, if there is any deviation, should
correct in time.
(4) Adopt multi-layer and multi-pass welding for the seam. The bedding joint of multilayer welding
should be staggered. Every seam should be welded continuously, if the welding is interrupted by
accident, should take proper measure to prevent cracking, and keep warm in time. Before welding
restarted, should clean the surface and make sure no crack then continue to weld according to the same
technical process. After welding, should burnish the welding scar to be flush with the substrate.
(5) After welding, the welder should check by himself, then put on steel mark nearby the qualified
weld seam which is Type I and Type II, and record properly.
4.9.5.4 Treatment of stress relief and hydrogen relief after welding
During the welding, should conduct the treatment of stress relief and hydrogen relief to the welded
part on each layer by using Haokeneng Welding Stress Relief Machine, so as to relief the stress.
4.9.5.5 Remedy of defects on penstock surface
After finished the welding, should check the situation of penstocks inside/ outside faces and the
welding places totally, burnish the bulging on inside face. If there is pit which is deeper than 10% of the
surface thickness, should make repairing welding and recheck as per the approved measures by
inspector.
4.9.6 Check of weld seam

4.9.6.1 Classification of weld seam


SINOHYDRO CORPORATION LIMITED

Page 51 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

Type I: including weld seam received main stress, for example, longitudinal seam in penstock wall,
circular seam in joining section, butt welding seam of stiffening accessories (including supporting ring)
and combined weld seam between the penstock walls.
Type II: including weld seam received secondary stress, for example circular seam in penstock wall,
butt weld seam of strengthening ring and combined weld seam between penstock walls.
Type III: including weld seam of accessories which are weld seam received minor stress, and will not
cause to stop generating electricity and water supply when make repairing weld.
4.9.6.2 Radiographic Examination
All the weld joints in the pipe shells and bifurcation shall be radiographed at the rate of the followings:
(a) Longitudinal weld joints : 100% of weld line in length including T-joints
(b) Girth weld joints: More than 20% of weld line in length including T joints.
Radiographs shall be in accordance with the requirements in the Specification.
Weld defect detected shall be repaired in accordance with the following procedures:
(1) 30 cm length weld lines of both sides of the defect portion shall be radiographed to examine
whether there is the objectionable defect therein or not.
(2) If there is the defect therein, all weld lines of concerned joint shall be radiographed and defective
welds discovered shall be repaired.
(3) If there is not the defect therein, the defect portion only shall be repaired.
(4) Objectionable defects in welds shall be chipped or flame or arc gauged to show sound metal and
the defects rewelded. Welds that have been repaired shall be 100 per cent radiographed again.
The Contractor shall furnish all equipment, films and labour necessary to perform the radiographic
tests. All original films of the radiographs shall become the property of the Employer.
The Contractor shall provide proper storage for his radiographs and shall store and preserve all
radiographs of welding, whether the welding is accepted or rejected. All radiographs shall be identified
and a identification drawing prepared.
The Contractor shall submit the radiographic inspection procedure for approval to the Engineer and
shall obtain Employer's approval before the inspection is made. The Employer shall have the right to add
further radiographic inspection of the welded lines when needed.
4.9.7 Treatment of welding defect

The inside defects of weld seam should be removed completely by pneumatic digger or burnishing
machine, and burnish it with grinding wheel to a flute which is easy to be welded. Before repairing,
should check strictly and make sure defects are removed. The defects which belong to crack, should
check by magnetic powder firstly, then make repairing weld after the crack is removed.
After welding, should recheck defects by ray detection and ultrasonic wave detection. The repairing weld
in the same location shouldnt be more than 2 times. If the repairing is more than 2 times, make reliable
technical measure, and ask for approval from supervisory Engineer, only then can the repairing been
done, the repairing shall be recorded in writing as well.

SINOHYDRO CORPORATION LIMITED

Page 52 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

4.9.8 Test of water pressure

The water pressure test is not advised for this project because that the diameter of penstock in the
project is relatively big, and the construction is conducted inside the tunnel. Hence, it is very important to
control strictly in every step of the welding procedures including flaw detection so as to meet the
requirements of specification and quality.
4.9.9 Painting

Before painting, should do the technical test according to the requirement of drawing and the rule of
painting factory. Do the test strictly as the ratio of dope, the way of preparing, and the interval of painting
ordered. The result of test should be reported to the Engineer and the painting shall only be carried on
after the test result being approved.
The painting should adopt high-pressure airless spraying technology. It is required even painting, without
bubbler, cavity and impurity, and no phenomenon of separation. After finishing paint, should check if
there are defects like sagging, wrinkling, pinhole, crack and blistering, and make sure the surface is good,
the color is consistent. The testing of inside quality should follow the requirements of drawing and
specifications. The test of coating thickness and the binding ability should follow the requirements of
drawing and specifications. After painting, make joint inspection with the Engineer participated in to
check and make acceptance to the quality of the penstock painting surface, and report the testing result
to the Engineer.

4.10 Steel gate and trash rack installation


4.10.1 Plain Gates and Embedded parts

4.10.1.1 Manufacture of Plain Gate & Embedded Parts


The embedded frames and parts for the gate are composed of sill, main guide, auxiliary guides, reverse
guides, lintel and the like. The manufacture procedure is shown in the following:
Inspection and correction of sectional steel
Measuring & cutting of section steel
Setting out
Welding
Correcting after welding
Machining & planning of metal parts
De-rusting & painting
Inspection for quality. The fabrication method and procedure is described as the following:

4.10.1.2 Fabrication of Gate Leaf


1 Gate leaf is composed of the faceplate, main beam, side beam, small horizontal beam, longitudinal
separating plate, clamping plate, lifting eye, main wheel, reverse wheels, and side wheels. The
fabrication procedure include cutting of steel plate, assembling, non-destructive test for the welding seam,
pre-assembly of gate body, inspection and correction, de-rusting and painting, and so forth.
2

Technical requirement for fabrication and assembly of gate leaf

a. The bearing pad of slide channel of fate shall be adjusted by referring to the surface of rubber seal
seat. All the slide channels shall be on the same plane with allowance not more than 1.0mm. Minimum
one point one either end of slide channel shall be surveyed.
b. the bearing pad face of slide channel shall be parallel with reference surface of rubber seal seat, with
allowable difference not more than 0.5mm. The difference in height between the joints of adjoining slide
channel shall not exceed 0.5mm.
c. The allowable deviation of span between the bearing pads of slide channel shall be 2.0mm and the
central line of same slide channel shall not deviates from the design value by more than 2.0mm.
d. On the same profile, the allowable difference from the bearing pad face to the rubber seal seat shall
be 1.5mm.
SINOHYDRO CORPORATION LIMITED

Page 53 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

4.10.1.3 Quality Control in Fabrication of Gates


The welding seam of gate leaf shall be symmetrical on both sides, that is, welding shall be performed
simultaneously by even welders on both sides of gate leaf. Welding shall be done from center towards
outside, following such a sequence: Butt seam
Vertical welding seam
Flat-filled weld seam
Flange plate overhead welding seam. Welding shall be done in sections and in backing direction by the
welders who shall use the same technical parameter in respect of welding. The beams and faceplate
shall be welded by using CO2 protective welding method.
The welding seam shall be of multi-layer and multi-pass welding joint, with thickness of each layer not
more than the diameter of welding rod. During the welding operation, care shall be taken to prevent any
deformation of welding plates.
No-destructive test for the welding seam shall be carried out to ensure no any defects appearing on the
steel works.

4.10.1.4 Requirement on the welding operation


Prior to the starting of welding works, the specification and method for the welding works shall be
prepared, which shall be abided by during the period of performing the welding works. At the same time,
it is allowed to timely correct some parameters when doing the welding works, to avoid any deformation
arising from the welding.
The welder who is going to participate in the welding of welding seams Class I and Class II shall obtain
the valid qualification certificate issued by the appropriate authority.
4.10.1.5 Hauling
Prior to the starting of transportation of gate leaf, temporary bracing and supporting works shall be
provided to them by using the some I beam and/or channel steel as necessary. The embedded parts,
such as guides, lintels, sills and so on, shall be packed in bundles, with square timber or straw mats put
beneath them, all to avoid colliding with each other and deforming during the hauling period.
4.10.2 Trash-rack
4.10.2.1 Fabrication of Trash-rack
The trash-rack is composed of side beam, horizontal beam, vertical beam and lifting eyes, etc.
1 Fabrication of trash-rack bar: Steel plate Settling out
shape of bars
Matching
Welding
Correcting

Cutting of steel plate

Correcting the

Assembling: Setting out


Positioning of the horizontal beam Positioning of the vertical beam
Positioning of the side beam Installation of bars Installation of lifting eye Examination of the
dimension
3

Welding: Welding of vertical seam

Welding of butt seam of flange plate

4 Inspection and correction: all the dimension and size shall be carefully inspected in strict accordance
with the design drawing and specification. Any dimension found not in compliance with the design shall
be rectified immediately.
5

No-destructive test of welding seam

4.10.2.2 Technical Requirement for Fabrication and Assembling of Trashrack


1 the deviation of height and width from the specified ones shall be not more than 4mm, and that of
thickness from the design one shall be not more than 3mm.
2

the difference between the diagonal line of the trash-rack shall be not more than 4.0mm, and the

distortion allowance shall not exceed 3.0mm.


SINOHYDRO CORPORATION LIMITED

Page 54 of 60

EPC Tender Documents: Tender Schedules

180 MW Kali Gandaki Koban Hydroelectric Project

3 All the bars shall be parallel with each other, and the apart space between the bars shall not
deviate from the design one by 5%.
4.10.3 Radial gate and embedded parts
4.10.3.1 Process measures for radial gate of spillway
The embedded parts of radial gate include bottom sill, side rail and anchor bolt of hinged support and so
forth, which shall be manufactured segmentally as per the design and drawings. The production methods
used are the same to those applied to embedded parts of plain gate.
4.10.3.2 Flow chart of radial gate manufacturing
Technology documents

Staff and equipments

Lofting

Positioner supporting

Blanking

Material rechecking

Castings and forgings

Casting and
machining

Number of goods

Antiseptic treatment

Acceptance checks

Holistic splicing

Package and
transportation

Quality control

Non-destructive examination

Assembling

Bought-in components

Machining of other components

Machining of hinge

Machining of fixed hinge

Machining of acting hinge

Manufacturing of miscellaneous
parts

Manufacturing of gate flap

Manufacturing of supporting arm

Calibration

Purchasing of standard parts

Preparatory work

drawings

4.10.3.3 Manufacturing of gate flap


1) Manufacturing process of gate flap comprises the following steps: machining of faceplate, machining
of main beam, machining of side beam, machining of minor crossbeam, longitudinal baffle, watertight
platen, machining of lifting lug and side wheel, articulatory assembly, articulatory welding, articulatory
calibration, non-destructive testing of welding seam, holistic preassembly, testing and calibrating and so
on. Following is the detailed information of the manufacturing process:
SINOHYDRO CORPORATION LIMITED

Page 55 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

A: Machining of faceplate: plate leveling, scribing, cutting, plate rolling, fitting up, welding, testing,
calibrating.
B: Machining of main beam: plate leveling, scribing, cutting, non-shrinking flange, fitting up, welding,
calibrating.
C: Machining of minor crossbeam: calibrating, scribing, cutting, fitting up, calibrating.
D: Articulatory assembly: faceplate in position, scribing and fitting up, main beam in position, minor
crossbeam in position, baffle in position, side beam in position, fitting up the stiffening plate, testing of
geometrical size.
E: Welding: butt welding of the rear edge plate, vertical seam welding, flat fillet seam.
F: Testing and calibrating: testing as per the design drawings and acceptance specifications, and
calibrating the places where mismatching the specifications.
G: Machining of watertight platen: plate leveling, scribing, cutting, calibrating, scribing on the faceplate,
drilling on the basis of actual measure, testing.
H: Non-destructive testing of welding seam: adopt ray or ultrasonic wave to test as per the percentage of
detection specified in DL/T5018-94 criteria. Infiltration or magnetic powder will be used for testing the
surface.
I: Holistic preassembly: using the crane to carry through preassembly on cambered workbench and
ensure the consistency between geometrical size and criteria; distinguishing marks and serial numbers
should be plotted onto the welding position and locking plates be welded when assembling.
4.10.3.4 Manufacturing of supporting arm
1) Manufacturing process of supporting arm comprises the following steps: machining of main beam,
machining of supporting montant, machining of supporting diagonal brace, holistic assembly, welding,
calibrating, non-destructive testing of welding seam, descaling and spray painting. Following is the
detailed information of the manufacturing process:
A: Machining of main beam and supporting montant and diagonal brace: plate leveling, scribing, cutting,
non-shrinking flange, fitting up, welding, testing, calibrating.
B: Holistic assembly: lofting on the platform at the ratio of 1:1, main beam be filled in position, adjusted
and fastened. Afterwards miscellaneous parts are filled in position and fit up. The opening size of
supporting arm should be controlled strictly.
C: Welding: vertical seam, butt welding of flange plate.
D: Calibrating: check the dimensions of each parts after welding and calibrate the greatly-deformed
places with flame correcting method.
4.10.3.5 Machining of supporting hinge:
The castings and jointed-shaft materials used in supporting hinge should conform to the requirements of
specifications.
4.10.3.6 Installation technical measures of radial gate
Generally, the installation of radial gate can be divided into three sections:
The first section is the installation of embedded parts for trunnion beam, bottom sill, side rail and door
head and so forth.
The second section is the installation of radial gate body, which comprises the installation of hinge
support, support leg, gate leaf and watertight rubber and so forth.

SINOHYDRO CORPORATION LIMITED

Page 56 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

The third section is the installation of hoist, which comprises the installation of hoist body, coupling shaft,
pulley block and distribution equipment and so forth.
Generally the installation of gate wont start unless the civil works are basically finished and will be
carried through on the basis of civil works, therefore, the installation of gate and civil works are closely
related. The former is both restricted and closely coordinated by the latter.
1) Processes and methods of the installation of gate
(1) Setting out
Setting out consists of the following steps: setting out the axis of sluice chamber, trimming the side line,
setting out the bottom sill and the speedometer cable of trunnion beam; setting out the uniform altitude
traverse and radius line of side rail, capturing the central coordinate of supporting hinge axis, etc.
(2) Installation of bottom sill and trunnion beam
Installation of bottom sill and trunnion beam. Recheck and clear the bottom sill and trunnion beam prior
to their installation to find out the manufactured central line and axis. Attach sufficient importance to the
perching of bottom sill, or domino effect and unimaginable destructive consequence will be caused for its
fundamental status among the whole installation work and possible imperceptible changes of axis,
speedometer cable and elevation. Therefore each size should be captured accurately during the
perching course. Use the lifting jack and reversible bolt to adjust horizontal position during work progress,
and the level gauge to control elevation by dint of multipoint and repeated measurement, The concrete
placing in Phase II cannot be carried through unless the specified standard are reached.
Ascertain the central point of hinge axis prior to the hoisting of trunnion beam to facilitate wire drawing
and the adjusting of concentricity. The concrete steps are as following: make two calibrating plates
applicable to hinge axis and fasten the plates respectively onto the dowel bars of preformed holes at
bilateral walls with about two-thirds of the plates above the central altitude traverse of trunnion beam.
Also the central perpendicular of faceplate and the perpendicular at speedometer cable of hinge axis
coincide, whereafter gouge along the coincident line by hacksaw with the depth reaching altitude
traverse to make the bottom sill the central point of hinge axis. Link the central points at two terminals by
fine steel wire as both the axis of pivot shaft and working baseline for adjusting trunnion beam.
Calibrating the trunnion beam and fixing hinge support simultaneously as per specific conditions, which
requires install the fixing hinge support onto beam prior to the hoisting of trunnion beam and position the
nether margin of trunnion beam onto the designed coordinate point during hoisting. Calibrate pivot shaft
to achieve the gradient. Hitherto, the hoisting work is completed. According to worksites actual situations,
hoisting will be fulfilled with hoist or horizontal bar or door-shaped hanger.
Some trunnion beams have integral structures while others are divided into two parts. The latter should
be respectively hoisted with the central lines of hinge axis are collinear. Moreover the strengthening
welding should not be carried out unless concentricity on the left and right sides is captured. Tools such
as lifting jack, chain block or tightening bolt should be used during temporary fastening prior to welding
so that welding deformation can be avoided. Constant measurement and calibrating of concentricity of
two hinges should be carried out during fastening until the welding is finished. In the Phase II concrete
placing, instrument detecting is still needed to avoid displacement and ensure the installation quality.
2) Installation of hoist
In order to accelerate the process of the project, save cost and keep the construction site in good order,
if possible, install the hoist during the process of installing the trunnion beam and bottom sill. Setting out
and elevation-measuring is also needed prior to the installation of hoist. Also, the axes of hoist and sluice
chamber must coincide. Rinse and check each part of the equipment, mend the disfigurement and
prepare all the accessories.

SINOHYDRO CORPORATION LIMITED

Page 57 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

Accurate locating, smooth positioning and stable bedplate are required for installing the radial gate hoist,
therefore the anchor bolt in the bedplate should be manufactured as per the drawings. If the locations of
preformed holes of the anchor bolts are inaccurate, modify them to prevent the expansion of screw holes.
Moreover, after concrete placing in Phase II, the embedded bolts should not be tightened until the
concrete strength reaches specified value.
3) Installation of head sill of gate
Some head sills have integral structures while others are divided into two parts. We will take the latter as
an example to illustrate its installation methods. Merge two main body parts and weld them firmly after
they are checked. Please note dislocation is not allowed. Hoist them onto the designed height by hoist,
and repeatedly measure and calibrate their mileage, elevation and gradient. Weld and fix them with
dowel bars on parapet after all requirements are met. Meanwhile, weld them with the side rail after the
latter is further adjusted. Finally assemble the first watertight rubber and place the cover plate. As there
will be replacement of watertight rubber in subsequent operations, the cover plate should not be welded
with the side rail. In this case, there will be a gap between the cover plate ends and the side rail, which
will lead to water leakage if handle improperly. The best method is to add a 1.5mm rubber pad of the
same shape as the surface of the cover plate.
4) Installation of support leg and gate leaf
Put the support leg and gate leaf in place, erect the gate leaf and cut off the extra part of the support leg
and assemble movable trunnion; measure the compatibility between trunnion axis and the hole and
modify defects if any; then hoist the support leg and assemble the trunnion axis. Lubricate the axle hole
with machine oil prior to hoisting. The assembling of support leg and gate leaf will be carried out after the
assembling of trunnion axis. The following steps should be followed: hoist the support leg to a certain
height and lean the gate leaf against the lower end of the support leg; measure the radius of the gate leaf
and make sure the central line of the gate leaf and the axis of sluice chamber coincide before the
welding of the support leg and the pressure-reducing plate. Please note the position alignment. Ensure
the lower margin is about 23mm shorter than the upper margin when measuring the radius of the gate
leaf for the smooth hoisting of radial gate and reducing the friction of top watertight; finally fasten the
pressure-reducing plate and gate leaf with bolts. After the procedures above are finished, hoist the radial
gate and perform tracking measurement for vibration or abnormal situation of the central line of gate leaf.
Timely proper handle of problems is required until the flexible and agonic hoisting is achieved.
5) Installation and adjustment of side rail
The welding of side rail was mentioned in the illustration of installation of head sill. In actual practice the
side rail parts should be hoisted with hoist after the completion of hoist installation. Then fasten the side
rail onto the prepared steel bars with reversible bolts as per the radius of side rail. As the bottom sill is
already setup, the nether margin of side rail and bottom sill can be first welded as long as the
measurement of the side rails radius is accurate. After the gate leaf is well adjusted, utilize the hoist of
gate leaf to further adjust the side rail. Specifically, measure the distance between the working surface of
the stainless steel side rail and the plate of the gate leaf., and adjust the upper and lower gap according
to design requirements with the pre-fixed reversible bolt and lifting jack. Measure a point every 500mm
and make a record, or carry out adjustment through the hoisting of radial gate. Further strengthening
welding should be carried out for the adjusted section.
6) Installation of watertight rubber
Make suitable space and cut the watertight rubber as per the dimensions stipulated by the drawing.
Afterwards assemble the watertight rubber as the following sequence: first bottom watertight, then side
watertight and finally the top watertight.
Installation of bottom watertight: fasten the bolts one by one from central to two ends, and save 23
bolts on both ends respectively unfastened to facilitate the connection with side watertight rubber.
SINOHYDRO CORPORATION LIMITED

Page 58 of 60

EPC Tender Documents: Tender Schedules

180 MW Kali Gandaki Koban Hydroelectric Project

Installation of side watertight: fasten the bolts from top to bottom and overlap joint the side and bottom
watertight rubber; bind the lap joint with stick in prison(adhesive); cut off extra parts and fasten all the
bolts.
Similar to the bottom watertight, carry out the installation of top watertight from central to two ends and
cut off extra parts; fasten bolts with suitable strength and over-tight fastening may lead to the
deformation of P-type watertight rubber and affects the waterproof effect.
7)Concrete placing in Phase II
The concrete placing, including side rail and head jamb, is the final working procedure of the whole
installation of radial gate. It has a decisive effect to the fixing and protection of embedded parts, therefore
it should be taken seriously. To ensure construction quality, all the performed grooves in concrete
placing in Phase II must be surface roughened and cleaned as per the required specifications. Proper
proportion of concrete mixture is required and no disturbance is allowed in the placing process.
8) Trial running
After all the assembling works are finished, trial running of the gate is required to check the overall effect
of installation. Clean the gate leaf, especially the watertight rubber prior to trial running. Continuously
pour cold water onto the watertight rubber during the hoisting course for cooling and lubrication to avoid
the damage of watertight rubber. Trial running should achieve effects such as flexible hoisting, rigorous
watertight, with no abnormal voice and vibration.

5. Project Preliminary Schedule


According to the requirement of 42 months duration and the data depicted in the bidding documents, the
preliminary schedule is developed with P6 software and attached herein.

5.1 Milestone and Critical path


(1) Milestone:
Work commencement: 1 January 2014
Civil design completion: 28 September 2014
Sediment tunnel cons. Completion: 14 October 2015
Guiding structure cons. Completion: 5 September 2016
CFRD cons. Completion: 5 September 20 June 2017
Headrace tunnel cons. Completion: 8 June 2017
Power station M&E install. Completion: 17 April 2017
Work completion: 30 June 2017

(2) Critical path:


Mobilization

Access tunnel excavation & support

station concreting

Turbine & generator install.

Power station excavation & support

Power

Turbine & generator commissioning

Since the float time for the CFRD and the headrace tunnel adit-2 working face is very few, so great
attention should also be paid to these work.

SINOHYDRO CORPORATION LIMITED

Page 59 of 60

180 MW Kali Gandaki Koban Hydroelectric Project

EPC Tender Documents: Tender Schedules

5.2 Construction Rate at Peak


Earth and rock fill monthly peak: 86222m3/month, in May 2016
Rock open excavation peak: 55634m3/month, in December 2015
Tunnel excavation peak: 28889m3/month, in October 2014
Concrete placing peak: 10960m3/month, in July 2016

SINOHYDRO CORPORATION LIMITED

Page 60 of 60

You might also like