Professional Documents
Culture Documents
Fluid Grouts
Rotary
Shaft Mix
e.g.,
DSM, Trevimix
Schnabel
Dry Materials
Rotary
End Mix
End Mix
End Mix
e.g.,
SSM, SCC,
Mectool
Hayward Baker
e.g.,
GeoJet
e.g.,
Lime-Cement
Columns
Nature of Material
Placed
Mixing/Blending
Principle
Mixing/Blending
Location
U.S. Examples
Conventional DMM
Potential Drawbacks
Rotary
Vertical
Axis
Jet
Assisted Vertical
Axis (Turbojet)
Conventional
Trench Cutting
and Mixing
(TRD)
Horizontal
Axis Cutting
and Mixing
Low
High
Pressure Pressure
(CSM) (CT Jet)
wide.
Continuous wall created by lateral
motion of vertical chain saw,
installed in a predrilled hole.
Blue print
A)Standard blade
B)Rounding blade for hard clay
C)Long-nosed blade for boulder
TRD
Particular Advantages
(20 ft).
Very quite, modest size support
equipment, clean operation.
TRD
Potential Drawbacks
boulders/rock.
Only one (excellent) contractor!
in 2003
Combines expertise in hydromill and deep mixing.
Rapidly increasing in popularity worldwide (over 30
units in service).
Similar system developed by Trevi (CT Jet).
Maximum depth 180 feet, 20-47 inches wide.
CSM
Particular Advantages
CSM
Potential Drawbacks
(continued)
Extraction of Column
Protected
Side
Flood Side
Orleans Avenue
Design
In order to prevent settlement of the additional overburden and
resist potential lateral forces originated by storm surges, the
ground improvement was designed to cover 30% of the new
levee footprint to create rows of parallel buttresses, approximately
15 feet apart, perpendicular to the levee axis. In between
adjacent buttresses, an individual element was installed to avoid
differential settlement.
Large diameter single and double deep mixed columns were
incorporated in the design.
The larger columns allowed the reduction of the total number of
elements to be installed with obvious advantages for the highly
demanding schedule.
Design
Technology
Over 60% of the ground improvement was
accomplished with the Trevi Turbo Mix
technology, single and double axis.
The TTM method is a recent development of
the deep mixing technology. It combines the
injection of cement slurry at high velocity
into the ground with mechanical mixing of
the rotating blades.
The additional energy provided by the grout
jets greatly improves the quality of the
mixing of the soil with the grout and
reduces the time required for the
installation of the soil-mix columns.
Pre-Construction
The contract required that pre-construction activities be
performed during the design phase to determine the most
appropriate construction parameters and technical solutions:
Due to schedule constraints, only the first stages of the preconstruction activities were accomplished before the beginning
of the actual production. The remaining stages were performed
as work areas became available .
Production
Some numbers.
PRODUCTION START DATE
PRODUCTION COMPLETION DATE
TOTAL CALENDAR DAYS
TOTAL MONTHS
TOTAL SHIFTS WORKED (as of 3/18/2011)
TOTAL MANHOURS (as of 3/18/2011)
TOTAL DMM ELEMENT INSTALLED
TOTAL VOLUME TREATED
TOTAL CEMENT USED
TOTAL TRUCK-LOADS (approx.)
TOTAL WATER USED
TOTAL CORING
TOTAL UCS TESTS
OVERALL AVERAGE UCS (required = 100 psi)
TOTAL FAILING UCS TESTS (<100 psi)
TOTAL FAILING UCS TESTS (10% allowed)
N
N
N
N
N
CY
SHTON
N
GAL
N
N
PSI
N
%
1/14/2010
3/18/2011
439.00
14.43
3,309
502,817
18,028
1,681,579
457,693
17,500
136,832,094
506
5,082
292
66
1.30%
Construction
LPV111 CHALLENGES:
schedule logistics design soil characteristics size of the job