You are on page 1of 46

OFFICE OF THE BRGY SUB-PROJECT MANAGEMENT COMMITTEE (BSPMC)

Barangay of Batuhon Dacu


Municipality of Dauin
Province of Negros Oriental, Region VII
SUB-PROJECT PROGRAM-OF-WORK
Project Title
Category

: Concreting of Access Road


: Public Goods

Physical Target
Total Sub-Project Cost

: 0.275 KM
PHP 1,654,450.00

Mode of Implementation

: By Contract

Project Description:

Sub-Project Duration

: 90 Calendar Days

Surplus Common Excavation, Aggregate Base Course, PCCP, RCPC Cross


Drainage and Installation of Project Steel Billboard

Equipment/Tools Needed

Road Grader,Back Hoe, Road Roller, Concrete


Mixer and Vibrator

Technical Personnel

: Engineer, Foreman, Carpenter/Mason,


Instrument Man, Survey Aide and Riprapper

No. of Laborers

: 90 person days

Sub-Project Location:
Sub-Project Site Location is 8KM away from Town Proper
Item
Scope of Work
No.

%(Wt)

102

Surplus Common Excavation

201

Aggregate Base Course

311

Portland Cement Conrete Pavement (PCCP)

500

RCPC CROSS DRAINAGE (with Reinforced Concrete Wingwall, PC Outle

Quantity

Unit

Unit Cost (P)

223.33

cu.m.

309.27

69,070.00

15.96%

214.50

cu.m.

944.70

202,638.38

62.13%

1100.00

sq.m.

717.27

788,994.00

15.73%

12.00

l.m.

16,643.25

199,719.00

0.74%

1.00

lot

9,425.00

9,425.00

5.44%

SPL 1 Project Steel Billboard


Total Direct Cost

100.00%

494,623.23

Total (P)

1,269,846.38

SOURCE OF FUND
Breakdown of Estimated Project Cost

KALAHI Grant

Community

Barangay LGU

In-Kind
A.

Cash

Municipal LGU

In-Kind

Cash

Total

In-Kind

Direct Cost
Materials

842,788.83

10,000.00

99,562.55

952,351.38

Equipment

129,619.47

###

16,850.53

146,470.00

Labor
Skilled

65,150.00

Unskilled

77,000.00

28,875.00

1,114,558.30

28,875.00

Sub-Total A
B.

10,000.00

65,150.00

105,875.00

1,269,846.38

21,000.00

3,390.00

116,413.08

Indirect Cost
Overhead Cost

21,000.00

2,947.83

Handtools and Prot. Equip. (PPE)


Pre-engineering

1,000.00

Project Supervision

442.17
8,500.00

1,000.00

2,000.00

4,000.00

12,500.00

3,000.00

600.00

3,600.00

Administrative Cost

34,782.61

5,217.39

40,000.00

Bidding Publication

6,521.74

978.26

7,500.00

Materials Testing

8,695.65

1,304.35

10,000.00

Environmental Metigating Cost

Treasurer's Bond

5,253.75

5,253.75

VAT (7% of Total Direct Cost)

88,889.25

88,889.25

126,984.63

110,421.42

Sub-Total ( B )

187,369.25

TOTAL ( A+ B )

1,301,927.55

Contractor Profit (10%)

ADD: Contingency

127,748.38

5,000.00

321,117.63

5,000.00

1,590,964.01

28,875.00

10,000.00

1,000.00

244,161.46

28,875.00

10,000.00

1,000.00

255,691.18

5,000.00

1,353,883.82

81.83%

265,691.18

16.06%

34,875.00

2.11%

255,691.18

5,000.00

51,956.27

Total Estimated Project Cost

1,353,883.82

11,529.72

MCC Grant
Cost Sharing to TEPC

16,563.21

1,000.00

LCC Cash
LCC Inkind

63,485.99

1,654,450.00

100.00%

Add: O and M (Other Amenities)


GRAND TOTAL

1,353,883.82

28,875.00

Prepared by :

10,000.00

1,000.00

1,654,450.00

Approved by :

ENGR. JERRY C. BALIOLA

MISAEL ALABAN

Service Provider

BSPMC Chairperson

Checked by:

Concurred by :

ENGR. RODSON R. ESCORA

ERNESTO D. ALEJADO

Deputy Area Coordinator

Barangay Captain

Recommending Approval:

ENGR. CARMEN A. GAUDIANO


Municipal Engineer - MCT DAC

HON. NEIL B. CREDO


Noted by:

ENGR. GEORGE S. ISULAT


Regional Community Infrastructure Specialist

Municipal Mayor

NAME OF SUB-PROJE: CONCRETING OF ACCESS ROAD


: Batuhon Dacu, Dauin, Negros Oriental
LOCATION:

BILL OF QUANTITIES

ITEM
NO.

Quantity Derivation
Computation

ITEM DESCRIPTION

102 Surplus Common Excavation

QUANTI
UNIT
TY

Rate per
No. of
Day / Unit
Crew/
Cost

Add
Frieght &
Handling
Cost

Total Unit
Cost

223.33
223.33

cu.m.
cu.m.

223.33

cu.m.

1.00
3.00
1.00

Day/s
Day/s
Day/s

1.00
4.00
2.00

350.00
300.00
275.00

1.00
1.50
1.50

lot
Day/s
Day/s

1.00
3.00

10,000.00
16,880.00
6,500.00

214.50

cu.m.

(0.78*275) =

214.50

cu.m.

(0.78*275*1.15) =

246.68

cu.m.

246.68

cu.m.

3.00
3.00
3.00

Day/s
Day/s
Day/s

1.00
2.00
2.00

350.00
300.00
275.00

1.00
2.00
1.00

lot
Day/s
Day/s

1.00
1.00

6,500.00
13,800.00
14,800.00

see vol. computation


A. Materials
Existing Ground Profile
Sub-Total
B. Labor
Construction Foreman
Driver / Operator
Laborer

* pls see equipment


* pls see equipment
* pls see equipment
Sub-Total

C. Equipment
Preparation of fnish grade of item 200
including trench canal excavation
Mobilization & Demobilization
1-Backhoe (280 cu.m / day)
3-Dump Truck (240 cu.m / day)

286.4/280 =
286.4/240 =

Total for Item102


201

Aggregate Base Course (including 0.20m


width shouldering both sides)

Total Compacted Volume =


Total Loose Volume =

A. Materials
Aggregate Subbase Course (Balastro Class "A" Type)
Sub-Total
B. Labor
Construction Foreman
*pls see equipment
Driver / Operator
*pls see equipment
Laborer
*pls see equipment
Sub-Total
C. Equipment
Mobilization & Demobilization
1-Road Roller (210cu.m/day)
246.68/210 =
1-Road Grader (400 cu.m / day)
246.68/400 =

550.00

55.00

605.00

Total for Item 200


311 Portland Cement Concrete Pavement
Length of PCCP =
Width =
Area =
Portland Cement Concrete Pavement =
Total Volume =
A. Materials
Portland Cement (40kgs), Type 1
Fine Aggregates (Approved Source)
Gravel 2'- 2-1/2" dia. (Approved Source)
16mm dia. X 6m Def. Bars (Const. Joint)
2"x2"x8' Coco Lumber (Formworks)

1,100.00
275.00
4.00
275*4 = 1,100.00
275*4*0.15 = 165.00
165.00

sq.m.
m
m
sq.m.
cu.m.
cu.m.

165.00*9 = 1,485.00

bags
cu.m.
cu.m.
length
bdft

165.00*0.5=
165.00*1=
((300/1)+1)/(6/.6)*1.7=
(((2"*2"*12')/12)*54=

83.00
165.00
47.00
216.00

250.00
600.00
750.00
370.00
20.00

25.00
60.00
75.00
37.00
2.00

275.00
660.00
825.00
407.00
22.00

ITEM
NO.

Quantity Derivation
Computation

ITEM DESCRIPTION

QUANTI
UNIT
TY

Rate per
No. of
Day / Unit
Crew/
Cost

2.00
37.00
6.50
259.00
6.00
30.00

Total Unit
Cost

(((2"*6"*12')/12)*54=
2"x6"x12' Coco Lumber (Formworks)
((10.8/1)+1)/(6-.3)=
16mm dia. X 6.0 m Def. Bars (Formworks)
(((6*3.6)/0.2)/5)*28)/58
Assorted CWN (2" & 3")
Hard Asphalt (Joint Filler)
Hack Saw Blade
Water (for mixing)
Sub-Total
B. Labor
During Installation of Forms: (150 sq.m./day)
Carpenter
During Concrete Pouring: Gang of 15 Workers (1.40 man-hour/sq.m)
Construction Foreman
Mason
((1.4*1200)/8)/15
Laborers
Concrete Mixer Operator
Concrete Mixer Vibrator
Sub-Total
C.Equipment
7.85 cu.m/day
1- Concrete Mixer
180/7.82 =

648.00
3.00
10.00
5.00
6.00
23.00

bdft
length
kgs.
bag
pcs
cu.m.

4.00

Day/s

5.00

300.00

24.00
22.00
22.00
22.00
22.00

Day/s
Day/s
Day/s
Day/s
Day/s

1.00
2.00
10.00
1.00
1.00

350.00
300.00
275.00
300.00
300.00

22.00

day

1.00

1,000.00

1- Concrete Vibrator

22.00

day

1.00

500.00

12.00

ln.m.

12.00

36" dia. RCPC

12.00

pcs

4,800.00

435.00

5,235.00

1/4"thk. Ordinary Plywood

16.00

pcs

320.00

32.00

352.00

Assorted Form Lumber (Coco)

360.00

bd.ft

22.00

2.20

24.20

Assorted CWN

6.00

kgs

65.00

6.50

71.50

#16 G.I. Tie Wire

12.00

kgs

85.00

8.50

93.50

12 mm dia.x 6.0m Deformed Steel Bar (G-40)

52.00

pcs

225.00

22.50

247.50

180/7.82 =

20.00
370.00
65.00
2,500.00
60.00
20.00

Add
Frieght &
Handling
Cost

22.00
407.00
71.50
2,759.00
66.00
50.00

Sub-Total
Total for Item 311
RCPC CROSS DRAINAGE (with Reinforced
500 Concrete Wingwall, PC Outlet/Inlet,
Headwall)
Length =

16mm dia.x 6.0m Deformed Steel Bar (G-40)

4.00

pcs

370.00

37.00

407.00

Portland Cement (Type 1)

74.00

bags

250.00

25.00

275.00

Gravel 2'- 2-1/2" dia. (Approved Source)

4.80

cu.m.

750.00

75.00

825.00

Fine Aggregates (Approved Source)

9.60

cu.m.

600.00

60.00

660.00

Coarse Aggregates (Ordinary Type-for bedding)

8.00

cu.m.

700.00

70.00

770.00

Cobble Class A stone (20cm - 3cm dia.)

12.00

cu.m.

750.00

75.00

825.00

14.00
10.00
13.00

Day/s
Day/s
Day/s

1.00

lot

1.00

lot

1.00
1.00
1.00

Day/s
Day/s
Day/s

Sub-Total

Construction Foreman
Mason
Laborers

(600/1.5)/15=

1.00
4.00
12.00

350.00
300.00
275.00

Sub-Total
Total for Item 500
SPL - 1Billboard
Quantity: 1 unit
A. Materials
Project Billboard

8,500.00

Sub-Total
B. Labor
Contstruction Foreman
Carpenter
Laborer
Sub-Total
Total for Item SPL -1
Total Direct Cost

1.00
1.00
1.00

350.00
300.00
275.00

ITEM
NO.

ITEM DESCRIPTION

Quantity Derivation
Computation

QUANTI
UNIT
TY

Rate per
No. of
Day / Unit
Crew/
Cost

Add
Frieght &
Handling
Cost

Total Unit
Cost

Direct Cost Summary


Materials
Equipment
Labor
1) Skilled
2)Unskilled
TOTAL DIRECT COST

INDIRECT COST:
OVERHEAD COST
Foreman/Leadman

60.00

days

350.00

10.00
10.00
1.00

pcs.
pcs.
set

125.00
25.00
1,890.00

20.00

shts

100.00

5.00
17.00

days
days

Warning Signs

5.00

pcs.

420.00

Barricades

5.00

pcs.

300.00

1.00

posting

Sub-total
HANDTOOLS AND PROTECTIVE EQUIPMENT
Hard Hat
Hand Glooves
Medicine Kit
Sub-total
PRE-ENGINEERING
Preparation of Plans (TAF)
Reproduction of Plans
Sub-total
PROJECT SUPERVISION
Municipal Engineer
BSPMC volunteers
Sub-total
ENVIRONMENTAL IMPACT

Sub-total
ADMINISTRATIVE COST
BIDDING PUBLICATION
MATERIAL TESTING
TREASURER'S BOND
VAT (7% OF Total Direct Cost)
Contractor Profit (10%)
TOTAL INDIRECT COST
TOTAL (A+B)
Add: Contingency
TOTAL ESTIMATED PROJECT COST (TEPC)
Add: O and M (Other Amenities)
TOTAL CONSTRUCTION COST

Prepared by:

ENGR. JERRY C. BALIOLA


Service Provider

800.00
250.00

2.00

7,500.00

7,500.00

81.83%

Checked & Reviewed by:

RODSON R. ESCORA
Deputy Area Coordinator

Recommending Approval:

CARMEN A. GA
Municipal En

QUANTITIES
COST SHARING
LGU

Total

COMMUNITY
CONTRIBUTI
ON

KALAHI
GRANT

350.00
3,600.00
550.00
4,500.00

350.00
3,600.00
400.00
4,350.00

10,000.00
25,320.00
29,250.00
64,570.00

8,849.56
22,407.08
25,884.96
57,141.59

69,070.00

61,491.59

149,238.38
149,238.38

132,069.36
132,069.36

1,050.00
1,800.00
1,650.00
4,500.00

1,050.00
1,800.00
1,200.00
4,050.00

6,500.00
27,600.00
14,800.00
48,900.00

5,752.21
24,424.78
13,097.35
43,274.34

202,638.38

179,393.69

408,375.00
54,780.00
136,125.00
19,129.00
4,752.00

361,393.81
48,477.88
120,464.60
16,928.32
4,205.31

150.00
150.00

150.00

450.00
450.00

450.00

BRGY.
CASH

IN-KIND

TOTAL

MUN.

CASH

IN-KIND

350.00
3,600.00
550.00
4,500.00

1,150.44
2,912.92
3,365.04
7,428.41

10,000.00
25,320.00
29,250.00
64,570.00

7,428.41

69,070.00

17,169.02
17,169.02

149,238.38
149,238.38

1,050.00
1,800.00
1,650.00
4,500.00

6,500.00
27,600.00
14,800.00
48,900.00

202,638.38

747.79
3,175.22
1,702.65
5,625.66

22,794.68

10,000.00

36,981.19
6,302.12
15,660.40
2,200.68
546.69

408,375.00
54,780.00
136,125.00
19,129.00
4,752.00

COST SHARING
Total
14,256.00
1,221.00
715.00
13,795.00
396.00
1,150.00
654,694.00

6,000.00

LGU
KALAHI
GRANT

12,615.93
1,080.53
632.74
12,207.96
350.44
1,017.70
579,375.22

8,400.00
13,200.00
60,500.00
6,600.00
6,600.00
101,300.00

6,000.00
8,400.00
13,200.00
44,000.00
6,600.00
6,600.00
84,800.00

22,000.00

19,469.03

COMMUNITY
CONTRIBUTI
ON

BRGY.

10,000.00

TOTAL

MUN.

1,640.07
140.47
82.26
1,587.04
45.56
132.30
65,318.78

14,256.00
1,221.00
715.00
13,795.00
396.00
1,150.00
654,694.00

6,000.00

16,500.00

16,500.00

2,530.97

8,400.00
13,200.00
60,500.00
6,600.00
6,600.00
101,300.00

22,000.00

11,000.00

9,734.51

33,000.00

29,203.54

1,265.49

788,994.00

693,378.76

62,820.00

55,592.92

7,227.08

62,820.00

5,632.00

4,984.07

647.93

5,632.00

8,712.00

7,709.73

1,002.27

8,712.00

429.00

379.65

49.35

429.00

1,122.00

992.92

129.08

1,122.00

12,870.00

11,389.38

1,480.62

12,870.00

16,500.00

10,000.00

11,000.00

3,796.46

33,000.00

69,115.24

788,994.00

1,628.00

1,440.71

187.29

1,628.00

20,350.00

18,008.85

2,341.15

20,350.00

3,960.00

3,504.42

455.58

3,960.00

6,336.00

5,607.08

728.92

6,336.00

6,160.00

5,451.33

708.67

6,160.00

9,900.00

8,761.06

139,919.00

123,822.12

1,138.94

4,900.00
12,000.00
42,900.00
59,800.00

4,900.00
12,000.00
31,200.00
48,100.00

11,700.00
11,700.00

199,719.00

171,922.12

11,700.00

16,096.88

8,500.00
8,500.00

7,522.12
7,522.12

977.88
977.88

350.00
300.00
275.00
925.00

350.00
300.00
200.00
850.00

75.00
75.00

9,425.00

8,372.12

75.00

977.88

9,425.00

1,269,846.38

1,114,558.30

28,875.00

116,413.08

1,269,846.38

10,000.00

16,096.88

9,900.00
-

139,919.00

4,900.00
12,000.00
42,900.00
59,800.00

199,719.00

8,500.00
8,500.00

350.00
300.00
275.00
925.00

COST SHARING
Total

LGU
COMMUNITY
CONTRIBUTI
ON

KALAHI
GRANT

952,351.38

842,788.83

146,470.00

129,619.47

BRGY.
10,000.00
-

TOTAL

MUN.
-

99,562.55

952,351.38

16,850.53

146,470.00
-

65,150.00

65,150.00

105,875.00

77,000.00

28,875.00

1,269,846.38

1,114,558.30

28,875.00

21,000.00
21,000.00

21,000.00
21,000.00

1,250.00
250.00
1,890.00
3,390.00

1,086.96
217.39
1,643.48
2,947.83

65,150.00

105,875.00

1,269,846.38

21,000.00
21,000.00

10,000.00

4,000.00
8,500.00
12,500.00

1,250.00
250.00
1,890.00
3,390.00

1,000.00
1,000.00

1,000.00
1,000.00
4,000.00

2,100.00

1,750.00

1,500.00

1,250.00

3,600.00
40,000.00
7,500.00
10,000.00
5,253.75
88,889.25
126,984.63
321,117.63
1,590,964.01
63,485.99
1,654,450.00

3,000.00
34,782.61
6,521.74
8,695.65

110,421.42
187,369.25
1,301,927.55
51,956.27
1,353,883.82

1,654,450.00

1,353,883.82

8,500.00
8,500.00

4,000.00

350.00
-

28,875.00

10,000.00

1,000.00
1,000.00

28,875.00

10,000.00

1,000.00

600.00
5,217.39
978.26
1,304.35
5,253.75
88,889.25
16,563.21
127,748.38
244,161.46
11,529.72
255,691.18

28,875.00

10,000.00

1,000.00
18.16%
18.17%

255,691.18
270,776.76
(15,085.59)

MISAEL ALABAN
BSPMC Chairperson

2,000.00
2,000.00
4,000.00
8,500.00
12,500.00
2,100.00

250.00
-

Approved by:

CARMEN A. GAUDIANO
Municipal Engineer

163.04
32.61
246.52
442.17

2,000.00
2,000.00

116,413.08

1,500.00
-

5,000.00
5,000.00
5,000.00
5,000.00

3,600.00
40,000.00
7,500.00
10,000.00
5,253.75
88,889.25
126,984.63
321,117.63
1,590,964.01
63,485.99
1,654,450.00
1,654,450.00

Noted by:

GEORGE S. ISULAT
RCIS

BSPMC Form No. 3


KALAHI-CIDSS: MCC PROJECT
LOCAL COUNTERPART CONTRIBUTION P
Barangay Batuhon Dacu
Municipality of Dauin
Province of Negros Oriental, Region VII, Phili
Sub-Project Title: Concreting of Access Road
Budget Item

Unit
used

No. of
Units

Per Unit
Cost

Total Sub-Project
Pro-posed
Cost
Amount of Grant

I. Administrative Cost
TE for opening of BSPMC DBP Account of CV's
TE for procurement transactions of CV's
Project Meetings
MCT-Initiated Meetings
Treasurer Payroll Processing
Forms/Supplies and Reproduction
Sub Total
II. Other Indirect Costs
Overhead Cost
Handtools
Pre-engineering
Project Supervisions
Bidding Publication
Environmental Mitigating Cost
Material Testing
Treasurer's Bond
VAT ( 7% of Total Direct Cost)
Contractors Profit (10%)
Contingency
Sub Total
III. Direct Cost
Labor
Materials
Equipment Rental
Sub Total
TOTAL PROJECT COST
IV. Operations & Maintenance
Other Amenities
Sub Total
GRAND TOTAL
Prepared by:

ELEUTERIO S. BANTOTO
Barangay Treasurer

2,800.00

2,434.78

7,140.00
5,400.00
9,900.00
6,000.00
8,760.00
40,000.00

6,208.70
4,695.65
8,608.70
5,217.39
7,617.39
34,782.61

21,000.00
3,390.00
2,000.00
12,500.00
7,500.00
3,600.00
10,000.00
5,253.75
88,889.25
126,984.63
63,485.99
344,603.62

21,000.00
2,947.83

110,421.42
51,956.27
204,542.91

171,025.00
952,351.38
146,470.00
1,269,846.38
1,654,450.00

142,150.00
842,788.83
129,619.47
1,114,558.30
1,353,883.82

0.00
0.00
1,654,450.00

0.00
1,353,883.82

6,521.74
3,000.00
8,695.65

.3
ROJECT
RIBUTION PLAN
Dacu
uin
ion VII, Philippines

Local Counterpart Contribution (LCC) Sources


Target Date of Delivery
of LCC
Mun LGU
Brgy LGU Community
DepEd
Total of LCC
365.22

365.22 August-December 2014

931.30
704.35
1,291.30
782.61
1,142.61
5,217.39

0.00

931.30 August-December 2014


704.35 August-December 2014
1,291.30 August-December 2014
782.61 August-December 2014
1,142.61 August-December 2014
5,217.39

0.00

0.00 August-December 2014


442.17 August-December 2014
2,000.00 August-December 2014
12,500.00 August-December 2014
978.26 August-December 2014
600.00 August-December 2014
1,304.35 August-December 2014
5,253.75 August-December 2014
88,889.25 August-December 2014
16,563.21 August-December 2014
11,529.72 August-December 2014
140,060.71

0.00
0.00

28,875.00 August-December 2014


109,562.55 August-December 2014
16,850.53 August-December 2014
155,288.08
300,566.18

0.00
0.00

0.00
0.00
300,566.18

442.17
1,000.00
12,500.00
978.26
600.00
1,304.35
5,253.75
88,889.25
16,563.21
11,529.72
139,060.71

0.00

0.00

1,000.00

1,000.00

0.00
28,875.00

99,562.55
16,850.53
116,413.08
260,691.18

0.00
260,691.18

10,000.00
10,000.00
11,000.00

0.00
11,000.00

28,875.00
28,875.00

0.00
28,875.00
Approved by:

GEORGE ALAS-AS
BSPMC Chairperson

PLANNED COMMUNITY PRO


Date Prepared

: July 8, 2014

Name of Proposed Sub

Barangay
Municipality

: Batuhon Dacu
: Dauin

Total Cash (Php)


Sub-project Duration

Province

: Negros Oriental

DESCRIPTION
Err:509

1st Tranche (Php)

Err:509
Err:509

2nd Tranche (Php)


3rd Tranche (Php)
TOTAL CASH (Php)

PACKAGES

Mode of Implementation : By Contract

PACKAGE ITEMS

QTY

UNIT

UNIT COST

PROC
METHOD

TOTAL

Surplus Common Excavation


Aggregate Base Course
Portland Cement Conrete Pavement (PCCP)
RCPC CROSS DRAINAGE (with Reinforced Concrete Wingwall, PC Outlet
Project Steel Billboard
CONTRACTOR'S PROFIT (10% of DC)
VAT (7% of TDC)
sub-total
Handtools & Personal Protective Equipment (PPE)
Hard Hat
Hand Glooves
Medicine Kit

223.33
214.50
1,100.00
12.00
1.00

cu.m.
cu.m.
sq.m.
l.m.
lot

ok
10.00
10.00
1.00

pcs.
pcs.
set

Package 3

sub-total

package 4

308.60
942.60
702.27
15,668.25
9,350.00

125.00
25.00
1,890.00
ok

Environmental Mitigating Cost:


Warning Sign
Barricade
sub-total
Indirect Cost:
Overhead Cost
Project Supervision
Administrative Cost
Bidding Publication
Materials Testting

5.00
5.00

pcs.
pcs.

68,920.00
202,188.38
772,494.00
LOCAL
188,019.00 BIDDING FOR
WORKS (LBW)
9,350.00
126,984.63
88,889.25
1,456,845.26
1,250.00
250.00
1,890.00

LOCAL
SHOPPING
FOR GOODS
(LSG)

3,390.00
420.00
300.00

2,100.00
1,500.00
3,600.00

LOCAL
SHOPPING FOR
GOODS (LSG)

21,000.00
8,500.00
40,000.00
7,500.00
10,000.00
5,253.75
63,485.99

Treasurer Bond

Contingency Cost
sub-total

CFA

Package 2

Package 1

Direct Cost:

155,739.74
GRAND TOTAL CASH

1,619,575.00

SAY

1,619,575.00
0.00
Checked & Reviewed by:

RODSON R. ESCORA
Procurement Team Head

PPT

Deputy Area Coordinator

MUNITY PROCUREMENT PACKAGING

roposed Sub-Project

(Php)
ct Duration

: Concreting

of Access Road

:
:

1,619,575.00
90 C.D.

SOURCES OF FUNDS

PERCENTAGE WEIGHT

ESCRIPTION

TOTAL
KC Grant:

.
LEGEND:

TO KC
GRANT

LCC:

AMOUNT
(PESO)

FUND SOURCE

TO LCC CASH

KC GRANT

1,353,883

e (Php)

1,083,107.06

212,552.94

1,295,660.00

80.00%

80%

TOTAL LCC

300,566

he (Php)
e (Php)
ASH (Php)

135,388.38
135,388.38
1,353,883.82

26,569.12
26,569.12
265,691.18

161,957.50
161,957.50
1,619,575.00

10.00%
10.00%
100%

10.00%
10.00%
100%

LCC - In-kind
LCC - Cash
TOTAL

34,875
265,691
1,654,450

REMARKS

TRANCHING SCHEDULE
TOTAL
1st Tranche
KC Grant
61,491.59
179,393.70
610,563.74
171,922.12
8,372.12
20,064.26

2nd Tranche

LCC Cash

KC Grant

1,051,807.53

7,428.41
22,794.68
96,530.26
16,096.88
977.88
16,563.22
30,000.48
190,391.81

1,086.96
217.39
1,643.48

163.04
32.61
246.52

2,947.83

442.17

1,750.00
1,250.00
3,000.00

350.00
250.00
600.00

10,134.31
6,521.74
8,695.65

8,500.00
5,082.60
978.26
1,304.35
5,253.75

25,351.70

21,118.96

22,000.48

1,083,107.06

212,552.94

135,388.38

1,083,107.06

212,552.94

135,388.38

80.00%

0.00

10.00%

3rd Tranche

LCC Cash

KC Grant

TOTAL

LCC Cash

113,387.90

26,569.12
26,569.12

42,369.25
17,280.25
59,649.50

10,000.00

11,000.00

12,000.48

12,782.61

LCC Cash
7,428.41
22,794.68
96,530.26
16,096.88
977.88
16,563.22
71,609.00
232,000.33

68,920.00
202,188.38
772,494.00
188,019.00
9,350.00
126,984.63
88,889.25
1,456,845.26

1,086.96
217.39
1,643.48

163.04
32.61
246.52

1,250.00
250.00
1,890.00

2,947.83

442.17

3,390.00

1,750.00
1,250.00
3,000.00

350.00
250.00
600.00

2,100.00
1,500.00
3,600.00

8,500.00
5,082.60
978.26
1,304.35
5,253.75
11,529.72

21,000.00
8,500.00
40,000.00
7,500.00
10,000.00
5,253.75
63,485.99

15,039.40
15,039.40

51,956.27

11,529.72

21,000.00
34,917.40
6,521.74
8,695.65
51,956.27

75,738.88

11,529.72

123,091.06

32,648.68

155,739.74

26,569.12

135,388.38

26,569.12

1,353,883.82

265,691.18

1,619,575.00

26,569.12

135,388.38

26,569.12

1,353,883.82

265,691.18

1,619,575.00

0.00

10.00%

0.00

MONTHS
1

61,491.59
179,393.70
675,963.74
171,922.12
8,372.12
110,421.41
17,280.25
1,224,844.93

65,400.00

47,987.90

KC Grant

PROPOSED
IMPLEMENTATIO
SCHEDULE

Recommending Approval:

ESCORA

CARMEN A. GAUDIANO

oordinator

Municipal Engineer

Submitted by:

Noted by:

GEORGE S. ISULAT
BSMPC

Regional Community Infra. Specialist

AMOUNT
(PESO)
1,353,883.82
300,566.18
34,875.00
265,691.18
1,654,450.00

PROPOSED
LEMENTATION
SCHEDULE

MONTHS

ecialist

ACTUAL COMMUNITY PRO


Date Prepared

Name of Proposed Su

Barangay
Municipality

: Batuhon Dacu
: Dauin

Total Cash (Php)


Sub-project Duration

Province

: Negros Oriental

DESCRIPTIO
Err:509

1st Tranche (Php)

Err:509
Err:509

2nd Tranche (Php)


3rd Tranche (Php)
TOTAL CASH (Php)

PACKAGES

Mode of Implementation : By Contract

PACKAGE ITEMS

QTY

UNIT

UNIT COST

PROC
METHOD

TOTAL

Surplus Common Excavation


Aggregate Base Course
Portland Cement Conrete Pavement (PCCP)
RCPC CROSS DRAINAGE (with Reinforced Concrete Wingwall, PC Outlet
Project Steel Billboard
CONTRACTOR'S PROFIT (10% of DC)
VAT (7% of TDC)

223.33
214.50
1,100.00
12.00
1.00

cu.m.
cu.m.
sq.m.
l.m.
lot

250.00
950.00
800.00
20,000.00
10,000.00

ok

package 4

Package 3

Package 2

Sub-Total (Actual)

55,832.50
203,775.00
880,000.00
LOCAL
240,000.00 BIDDING FOR
WORKS (LBW)
10,000.00

1,389,607.50

Savings amount determined after procurement

67,237.76

Sub Total for Package (Plan)

1,456,845.26

900.00
150.00
1,850.00

LOCAL
SHOPPING
FOR GOODS
(LSG)

Handtools & Personal Protective Equipment (PPE)


Hard Hat
Hand Glooves
Medicine Kit

10.00
10.00
1.00

pcs.
pcs.
set

90.00
15.00
1,850.00
ok

Sub-Total (Actual)

2,900.00

Savings amount determined after procurement

490.00

Sub Total for Package (Plan)

3,390.00

Environmental Mitigating Cost:


Warning Sign
Barricade

5.00
5.00

252.00
252.00

LOCAL
SHOPPING FOR
GOODS (LSG)

Sub-Total (Actual)

1,260.00
1,260.00
2,520.00

Savings amount determined after procurement

1,080.00

Sub Total for Package (Plan)

3,600.00

Indirect Cost:
Overhead Cost
Project Supervision
Administrative Cost
Bidding Publication
Materials Testting

pcs.
pcs.

21,000.00
8,500.00
40,000.00
7,500.00
10,000.00
5,253.75
63,485.99

Treasurer Bond

Contingency Cost
sub-total

CFA

Package 1

Direct Cost:

155,739.74

Savings amount determined after procurement


Sub Total for Package (Plan)
TOTAL SAVINGS DETERMINED AFTER PROCUREMENT

155,739.74

68,807.76

GRAND TOTAL CASH (Actual)

1,550,767.24

GRAND TOTAL CASH (Plan)

1,619,579.82
1,619,579.82
68,812.58
Checked & Reviewed by:

SAY
%

NOEL B. TUBIL

JULIUS M. ALAP-AP

RODSON R. ESCORA

Procurement Team Head

PPT

Deputy Area Coordinator

MUNITY PROCUREMENT PACKAGING

Proposed Sub-Project

: Concreting

of Access Road

h (Php)
ect Duration

:
:

1,619,579.82
90 C.D.

SOURCES OF FUNDS

PERCENTAGE WEIGHT

DESCRIPTION

TOTAL
KC Grant:

he (Php)

che (Php)
che (Php)
ASH (Php)

.
LEGEND:

TO KC
GRANT

LCC:

TO LCC CASH

KC GRANT

1,353,88

1,083,107.05

212,556.80

1,295,663.85

80.00%

80%

TOTAL LCC

300,57

135,388.38
135,388.38
1,353,883.82

26,569.60
26,569.60
265,696.00

161,957.98
161,957.98
1,619,579.82

10.00%
10.00%
100%

10.00%
10.00%
100%

LCC - In-kind
LCC - Cash
TOTAL

34,87
265,69
1,654,45

REMARKS

TRANCHING SCHEDULE
TOTAL
1st Tranche
KC Grant

2nd Tranche

LCC Cash

KC Grant

3rd Tranche

LCC Cash

KC Grant

TOTAL

LCC Cash

KC Grant

48,404.09
180,980.32
718,069.74
223,903.12
9,022.12

7,428.41
22,794.68
96,530.26
16,096.88
977.88

65,400.00

1,180,379.39

143,828.11

65,400.00

(128,571.86)

46,563.70

47,987.90

26,569.12

59,649.50

15,039.40

(4.34)

1,051,807.53

190,391.81

113,387.90

26,569.12

59,649.50

15,039.40

782.61
130.43
1,608.70

117.39
19.57
241.30

2,521.74

378.26

426.09

63.91

2,947.83

442.17

1,008.00
1,008.00
2,016.00

252.00
252.00
504.00

LCC Cash

48,404.09
180,980.32
783,469.74
223,903.12
9,022.12

7,428.41
22,794.68
96,530.26
16,096.88
977.88

55,832.50
203,775.00
880,000.00
240,000.00
10,000.00

1,224,849.27

231,995.99

1,389,607.50

4.34

67,237.76

1,224,844.93

232,000.33

1,456,845.26

782.61
130.43
1,608.70

117.39
19.57
241.30

900.00
150.00
1,850.00

2,521.74

378.26

2,900.00

426.09

63.91

490.00

2,947.83

442.17

3,390.00

1,008.00
1,008.00
2,016.00

252.00
252.00
504.00

1,260.00
1,260.00
2,520.00

984.00

96.00

984.00

96.00

1,080.00

600.00

3,000.00

600.00

3,600.00

10,130.45
6,521.74
8,695.65

8,500.00
5,086.94
978.26
1,304.35
5,253.75

8,500.00
5,086.94
978.26
1,304.35
5,253.75
11,529.72

21,000.00
8,500.00
40,000.00
7,500.00
10,000.00
5,253.75
63,485.99
155,739.74

11,000.00

51,956.27

11,529.72

21,000.00
34,913.06
6,521.74
8,695.65
51,956.27

12,000.00

12,782.61

11,529.72

123,086.72

32,653.02

4.34

(4.34)

22,000.00

75,738.88

(4.34)

0.48

25,351.70

21,118.96

22,000.48

(127,161.77)

46,723.61

47,987.90

3.86

21,123.30

10,000.00

26,569.12

PROPOSED
IMPLEMENTATI
SCHEDULE

MONTHS
1

3,000.00

25,347.84

AMOUNT
(PESO)

FUND SOURCE

75,738.88

11,529.72

123,091.06

32,648.68

155,739.74

59,649.50

15,039.40

1,405.75

164.25

68,807.76

1,210,264.97

165,833.67

87,400.00

75,738.88

11,529.72

1,352,473.73

265,531.27

1,550,767.24

1,083,103.20

212,556.80

135,387.90

26,569.60

135,387.90

26,569.60

1,353,879.00

265,696.00

1,619,575.00

80.00%

(127,161.77)

10.00%

47,987.90

10.00%

59,649.02

(1,405.27)

(164.73)

Recommending Approval:

68,807.76
Noted by:

Submitted by:

ESCORA

CARMEN A. GAUDIANO

MISAEL M. ALABAN

Coordinator

Municipal Engineer

BSMPC

AMOUNT
(PESO)
1,353,883.82
300,571.00
34,875.00
265,696.00
1,654,454.82
PROPOSED
IMPLEMENTATION
SCHEDULE

MONTHS
3

BARANGAY SUB-PROJECT WORK SCHEDULE & PHYSICAL PROGRESS REPORT


Project Title

: CONCRETING OF ACCESS ROAD

Sub-Project duration

: 90

Physical Target

:
:
:
:
:

Region
Province
Municipality
Barangay

Calendar Days

275 L.M.
VII CENTRAL VISAYAS
NEGROS ORIENTAL
DAUIN
BATUHON DACU

Total Sub-Project Cost

: P

Direct Cost
Indirect Cost
Date Started
Target Completion
Mode of Implementation

: P
1,269,846.38
: P
384,603.62
:
:
: By Contract

1,654,450.00

LABOR

NO.

DESCRIPTION

102 Surplus Common Excavation

201 Aggregate Sub-Base Course

311

Portland Cement Conrete


Pavement (PCCP)

500

RCPC CROSS DRAINAGE


(with Reinforced Concrete
Wingwall, PC Outlet/Inlet,
Headwall)

SPL 1 Project Steel Billboard

QTY

UNIT

WEIGHT

PHYSICAL

(%)

TARGET

AMOUNT

223.33 cu.m.

69,070.00

5.44%

214.50 cu.m.

202,638.38

15.96%

1,100.00 sq.m.

788,994.00

62.13%

199,719.00

15.73%

12.00

1.00

l.m.

lot

T O T A L

9,425.00

1,269,846.38

0.74%

100.00%

PLANNED

PHYSICAL
% PROGRESS (Actual)
PROGRESS (Planned)
FINANCIAL
PROGRESS (Actual)
Prepared by:

WEEK 4

WEEK 5

WEEK 6

MONTH 3
WEEK 7

WEEK 8

WEEK 9

WEEK 10

MONTH 4
WEEK 11

WEEK 12

WEEK 13

# # # # # # # # # # # # # # # # # # # # # # # # # # # #

PLANNED

# # # # # # # # # # # # # # # # # # # # #

ACTUAL
PLANNED

###################################################################################################################################################

ACTUAL
PLANNED

###################################################################################################################################################

ACTUAL
PLANNED

# #

ACTUAL
PLANNED

# # # # # # # # # # # # # # # # # # # # # # # #

# # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # #

ACTUAL
1

PERIODIC
COMMULATIVE
PERIODIC
COMMULATIVE
PERIODIC
COMMULATIVE
PERIODIC
COMMULATIVE
Concurred by:

PIT Chairperson

MONTH 2
WEEK 3

275.00

ACTUAL

II. To be filled up by Deputy Area Coordinator


% PROGRESS (Planned)

WEEK 2

90

TOTAL

MONTH 1
WEEK 1

90

UNSKILLED

I. To be filled up by Deputy Area Coordinator

ITEM

Average
Rate/Day
300.00

No. of Days

SKILLED

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

32

33

34

35

36

37

38

39

40

41

42

43

44

45

46

47

48

49

51

52

53

54

55

56

57

58

59

60

61

62

63

64

65

66

67

68

69

70

71

72

73

74

75

76

77

78

79

80

81

82

83

84

85

86

87

88

89

0.96%

0.96%

0.96%

9.29%

9.29%

18.96%

9.65%

9.65%

9.65%

9.65%

9.65%

9.65%

1.68%

2.64%

3.60%

4.56%

13.85%

23.14%

42.10%

51.75%

61.40%

71.05%

80.70%

90.35%

100.00%

90

91

21,333.42

12,190.53

12,190.53

12,190.53

117,968.73

117,968.73

240,762.87

122,540.18

122,540.18

122,540.18

122,540.18

122,540.18

122,540.18

21,333.42

33,523.94

45,714.47

57,904.99

175,873.72

293,842.45

534,605.32

657,145.50

779,685.67

902,225.85

1,024,766.02

1,147,306.20

1,269,846.38

Checked by & Reviewed by:

MIT Team Leader

50

1.68%

RODSON R. ESCORA
Deputy Area Coordinator

Approved by:

CARMEN A. GAUDIANO
Municipal Engineer

Noted by:

BSPMC

GEORGE S. ISULAT
RCIS

Department of Social Walfare and Development


KALAHI-CIDSS : MCC PROJECT

BARANGAY SUB-PROJECT
MANAGEMENT COMMITTEE

Dauin, Negros Oriental


Sub-Project :
CONCRETING OF ACCESS ROAD
Location: BATUHON DACU, DAUIN NEGROS ORIENTAL

Description of Work
Item No.
Location
Note
STATION
0+000
0+020
0+040
0+060
0+080
0+100
0+120
0+140
0+160
0+180
0+200
0+220
0+240
0+260
0+273
Total Area :
Ave. Area :

QUANTITY CALCULATION

Barangay Batuhon Dacu, Dauin


Negros Oriental

: SURPLUS COMMON EXCAVATION AND EMBANKMENT


: 102 & 104
: STA. 0-000.00 - STA. 0+300.00

: Computed Areas are taken from CAD File ( Poly Line Method)
AREA
DISTANCE
VOLUME
ITEM 102
ITEM 104
(m)
ITEM 102
3.400
0.000
20.00
67.800
3.380
0.000
20.00
38.100
0.430
0.013
20.00
4.300
0.000
0.014
20.00
4.200
0.420
0.000
20.00
7.000
0.280
0.014
20.00
5.900
0.310
0.008
20.00
3.200
0.010
0.004
20.00
0.100
0.000
0.008
20.00
3.200
0.320
0.000
20.00
7.200
0.400
0.013
20.00
6.100
0.210
0.002
20.00
20.768
1.867
0.000
20.00
20.168
0.150
0.003
13.00
35.295
5.280
0.000
16.457
1.029

0.079
0.005
Total Volume =

Submitted by:

JERRY C. BALIOLA

Service Provider

REMARKS /
LOCATION

ITEM 104
0.130
0.270
0.140
0.140
0.220
0.120
0.120
0.080
0.130
0.150
0.020
0.030
0.020

223.330

1.570

223.330

0.235
1.805

ADMINISTRATIVE COST DERIVATION


Sub-project Activities

Destination/Description

Fare/
Allowance/
Unit Price

Qty.

Unit

pesos

No of
transactions

1. TE for Opening of BSPMC LBP Bank Account of CVs


1,500.00

250.00

meals

200.00

BSPMC office to Dgte. (vice


versa)

DBP Initial Deposit


BSPMC office to Dgte. (vice
versa)

1 times

persons x

1 times

persons x

2 times

110.00 x

persons x

6 times

Sub-Total
2. TE for procurement
transactions of CVs
Serving of Canvass

meals
Serving of PO & Payments

persons x

6 times

BSPMC office to Dgte. (vice


versa)

80.00

110.00 x

persons x

6 times

meals

200.00

persons x

6 times

50.00
20.00

12
20

meetings
persons x

12 times

BSPMC office to MCT Office


(vice versa)

130.00

persons x

6 times

Meals

200.00

persons x

6 times

BSPMC office to Dauin (vice


versa)

300.00

persons x

12 times

Meals

200.00

persons x

12 times

Bondpaper long
Reproduction

350.00
2.00

x
x

3
3000

reams
sheets

Staple Wire
Calculator
Columnar Book
Liquid Eraser
Paste/Glue
Folder long
Paper clip
Pentil pen
Log book

30.00
675.00
50.00
35.00
20.00
3.00
20.00
30.00
80.00

x
x
x
x
x
x
x
x
x

8
1
4
1
1
40
1
1
4

boxes
pc
pcs
ps
pc
pcs
box
pc
pcs

50.00

box

Sub-Total
3. Project Meetings
Supplies
Snacks
Sub-Total
4. MCT-Initiated Meetings

Sub-Total
5. Treasurer Payroll Processing

Sub-Total
6. Forms/Supplies and
Reproduction

Fastener
Sub-Total
TOTAL FOR ADMIN COST

Prepared by :

Approved by :

ELSA A. TRUNO
MEO Staff
Checked by:

BSPMC Chairperson
Concurred by :

RODSON R. ESCORA
Deputy Area Coordinator

Barangay Captain

ENGR. CARMEN A. GAUDIANO

HON. NEIL B. CREDO

Municipal Engineer - MCT DAC

Municipal Mayor

Recommending Approval:

Noted by:

GEORGE S. ISULAT
Regional Community Infrastructure Specialist

RATIVE COST DERIVATION


No of
transactions

Amount

1,500.00

500.00

800.00
2,800.00

1,980.00

1,440.00

1,320.00

2,400.00
7,140.00

=
=

600.00
4,800.00
5,400.00

3,900.00

6,000.00
9,900.00

3,600.00

2,400.00
6,000.00

=
=

1,050.00
6,000.00

=
=
=
=
=
=
=
=
=

240.00
675.00
200.00
35.00
20.00
120.00
20.00
30.00
320.00

50.00
8,760.00
40,000.00

BSPMC Chairperson

Barangay Captain

HON. NEIL B. CREDO


Municipal Mayor

PROPOSED PROCUREMENT ACTIO


Sub-project Name : CONCRETING OF ACCESS ROAD
Location : Batuhon Dacu, Dauin, Negros Oriental
Timeline to complete
the activity (Inclusive
Dates)

Responsible Volunteer/s and Project Staff


( Complete Name)

1. Preparation of Planned Community


Procurement Packages

June 4, 2014

Leonila B. Pantajo BSPMC Chair, Senoncia


Saringo-BAC,Conchita Tubog-PT,Engr. Rodson
R. Escora - DAC, Ricky T. Panoy -CF and Engr.
Carmen A. GaudianoM.E.

2. Finalization of Packages & PCPP

June 7, 2014

-do-

Procurement Activities

3. Conduct of Pre-procurement Conference

August 20, 2014

Leonila B. Pantajo-BSPMC Chair, Senoncia


Saringo ,Benadeth Tuala-BAC, Ma.Alice M.
Alagao-PIT,Conchita Tubog-PT, Engr. Rodson
R. Escora - DAC, Ricky T. Panoy-CF and
Carmen A. Gaudiano-M.E.

4. Preparation of Minutes of Conference

August 31, 2014

Conchita Tubog - PT Head and PT members,


Ricky T. Panoy- ACT-CF

5. Preparation of Procurement Documents

Leonila B. Pantajo-BSPMC Chair,Conchita


Tubog-PT,Engr. Rodson R. Escora - DAC,Ricky
September 1-7, 2014
T. Panoy-CF and -Engr. Carmen A. GaudianoM.E.

6. Serving of Canvass/Invitation to Qoutation

Package 1: Direct Cost (LBW)

September 1-7, 2014

Conchita Tubog - PT Head and PT members,


Ricky T. Panoy- ACT-CF

Procurement Activities

Timeline to complete
Responsible Volunteer/s and Project Staff
the activity (Inclusive Conchita Tubog - PT Head and PT members,
( Complete
Ricky
T. Panoy-Name)
ACT-CF
Dates)

Package 2: Handtools & Personal Protective


Equipment (PPE)
September 5-7, 2014

Package 3: Environmental Mitigating Cost

Indirect Cost: Posting/Bidding Publication

September 15, 2014

7: Opening of Canvass and or Quotation

Leonila B. Patajo-BSPMC Chair,Conchita


Tubog-PT,Engr. Rodson R. Escora - DAC,Ricky
September 16, 2014
T. Panoy-CF and -Engr. Carmen A. GaudianoM.E.

8. Preparation of Minutes of Opening

September 16, 2014

9. Evaluation of Canvass and or Quotation

September 16, 2014

10. Preparation of Minutes of Evaluation

September 16, 2014

Leonila B. Pantajo-BSPMC Chair,Conchita


Tubog-PT,Engr. Rodson R. Escora - DAC,Ricky
T. Panoy-CF and -Engr. Carmen A. GaudianoM.E.
Leonila B. Pantajo-BSPMC Chair,Conchita
Tubog-PT,Engr. Rodson R. Escora - DAC,Ricky
T. Panoy-CF and -Engr. Carmen A. GaudianoM.E.
Leonila B. Pantajo-BSPMC
Chair,Conchita
Tubog-PT,Engr. Rodson R. Escora - DAC,Ricky
T. Panoy-CF and -Engr. Carmen A. GaudianoM.E.

11. Conduct of Post-Qualification Evaluation


(LSW,LBG)

September 17, 2014

Leonila B. Pantajo-BSPMC Chair,Conchita


Tubog-PT,Engr. Rodson R. Escora - DAC,Ricky
T. Panoy-CF and -Engr. Carmen A. GaudianoM.E.

12. Preparation of Minutes of Evaluation (PostQua)

September 17, 2014

Senoncia Saringo,Teodulo Bulisid, Bernadita


Tuala

13. Issuance of NPMT NOL

September 28, 2014

14. Preparation of Purchase Order (PO) or


Issuance of Notice to Award, Notice to Proceed &
Contract Signing

September 29October 3, 2014

#REF!

Timeline to complete
the activity (Inclusive
Dates)

Responsible Volunteer/s and Project Staff


( Complete Name)

15. Serving of Purchase Order (PO) or Contract


or Award (Package #)

October 4, 2014

Luzviminda T. Delfino- MIT Chair, MIT Members,


Ricky T. Panoy- ACT-CF, Rodson Escora-ACTDAC

16. Delivery of Materials or Start of SPI

October 5, 2014

Luzviminda T. Delfino- MIT Chair, MIT Members,


Ricky T. Panoy- ACT-CF, Rodson Escora-ACTDAC

Procurement Activities

Prepared by:
Reviewed & Checked by:

CONCHITA TUBOG
PT Chairperson

ENGR. CARMEN A. GAUDIANO


MCT-DAC

ENGR. RODSON R. ESCORA


ACT-DAC

EMENT ACTION PLAN (PAP)

Venue of meeting and


place/s to conduct
procurement

Resources
Requirement

Expected outputs/
Remarks

Brgy. Hall/BSPMC Office

POW/Detailed
Estimates

Draft PCPP

Brgy. Hall/BSPMC Office

POW & Draft PCPP

Final PCPP

Brgy. Hall/BSPMC Office

Final PCPP

Conference Conducted

Brgy. Hall/BSPMC Office

Office supplies

Minutes of Conference

ACT Office

POW & Final PCPP

Invitation to
Quote/Canvass
Documents

Canvass
Form/Request for
Qoutation,
Acknowledgement
Receipt

Acknowledgement
Receipt

Constractor's Office,
Establishment

Name of Potential
Suppliers Contractors

Contractors: Uy Matiao
Trading Corporation, HLJ
Construction & Enterprise,
Big Foot Construction &
Supply, VVER Construction,
Leymark Construction,
NAKKA Construction, Wenly
Tan Construction, Tenaja
Construction & Services,
R.E. SINGSON
Construction, PhilSouth
Builders, SM & MST
Construction, Dumaguete
Zenith Commercial, Uy
Condev Construction

Venue of meeting and


place/s to conduct
procurement

Name of Potential
Suppliers Contractors

Resources
Requirement

Expected outputs/
Remarks

Supplier's Office,
Establishment

Suppliers: Gold
Enterprises, Lucky
Enterprises, JM
Commercials, Dumaguete
Zenith Comercial, Octagon
Hardware, Duplamilco, LKC
Hardware

Canvass
Form/Request for
Qoutation,
Acknowledgement
Receipt

Acknowledgement
Receipt

Supplier's Office,
Establishment

Suppliers: Sun Signs, Ezra


Signs, Ziplink Graphics,
Iconcept, Power Prints

Canvass
Form/Request for
Qoutation,
Acknowledgement
Receipt

Acknowledgement
Receipt

Supplier's: The FREEMAN,


Sun Star, Cebu Daily News

Canvass
Form/Request for
Qoutation,
Acknowledgement
Receipt

Supplier's Office,
Establishment

Brgy. Hall/BSPMC Office

Submitted Canvass
Form/Invitation to
Quote

Opening Conducted

Brgy. Hall/BSPMC Office

Office Supplies

Minutes of Opening

Brgy. Hall/BSPMC Office

Opened
Canvass/Quotation

Evaluation Conducted

Brgy. Hall/BSPMC Office

Office supplies

Minutes of Evaluation

Office of the
Contractor/Supplier with
Lowest Calcuted Quotation

Lowest Calcuted
Quotation
Documents

Brgy. Hall/BSPMC Office

Purchased Order

Kalahi Office (ACT/RPMT)

ACT Office

#REF!

Post Qualification
Evaluation Conducted

Post Qualification
Evaluation Report

NOL Issued

Final PO/Contract

Venue of meeting and


place/s to conduct
procurement

Name of Potential
Suppliers Contractors

Office of the
Contractor/Supplier with
Lowest Calcuted
Responsive amount and
recommended for Award

Resources
Requirement

Expected outputs/
Remarks

Delivery
Receipt/Delivered
Goods

PO/ Contract Signed

Delivery
Receipt/Delivered
Goods

Proposed Project Site

Noted by:

Materials
Delivered/Contract
Implementation Started

Approved by:

ENGR. HELEN C. YBANEZ


Area Coordinator

LEONILA B. PATAJO
BSPMC Chairperson

ENVIRONMENTAL MANAGEMENT PLAN


Sub-Project Title
:
Sub-Project Description :
Location
Total Approved Cost
Cost Sharing

Concreting of Access Road


Surplus Common Excavation, Aggregate Base Course, Portland
Cement Concrete Pavement
Barangay Boloc-Boloc, Dauin, Negros Oriental
PHP 1,658,550.00

:
:
:

Local Counterpart :
KALAHI Grant
Community
Barangay LGU
Municipal LGU
TOTAL
SPI Stage / Activities
Conducted
ITEM 102 Surplus Common
Excavation

ITEM 201 Aggregate Base


Course

PHP
PHP
PHP
PHP
PHP

Negative Impact

1,362,169.00
17,925.00
11,000.00
267,456.00
1,658,550.00
Mitigating Measures

a.

Deep Excavation/Ground
Leveling

a-1.

Provide baricades and warning


signs to make aware of the
community of the on-going
activity. And Strickly follow the
desired elevation on plan.
Strategical Planning to include
excavated materials on Base
course and Shouldering

b.

Presence of Heavy
Equipment in the project
Site

b-1.

Ensure the clearance of


Electrical wiring during transport
of Heavy equipment, Inform the
community of the presence of
Heavy Equipment in the area.

c.

Cutting down of affected


trees covered on the
construction site

c-1.

Minimize Cutting of Trees and


Plant new tree seedling on the
vicinity of the area to prevent
erosion of soil that could
damage the structure

a.

Presence of Heavy
Equipment in the project
Site

a-1.

Inform the community of the


presence of Heavy Equipment in
the area.

Increase in noise level

a-1.

Construction waste that


could harm the
environment

b-1.

ITEM 311 Portland Cement


a.
Concrete Pavement

b.

b-2.

c.

SPCL 1 Project Steel


Billboard

Excessive Dust Particles

c-1.

none

Inform the community about the


incoming activities and instruct
the workers to minimize the
noise during construction.
Observe Proper segregation of
Construction waste e.g.
Biodegradable, NonBiodegradable, and Hazardous
waste
Recycle Construction Waste to
minimize its effects
Enforce the use of Personal
Protective Equipments (PPE) to
workers like dust mask and
safety glasses
none

Reviewed by:

Prepared By:

LEONILA B. PATAJO

RICKY T. PANOY

BSPMC Chair

Community Facilitator

CARMEN A. GAUDIANO

RODSON R. ESCORA

Municipal Engineer

Deputy Area Coordinator

Concurred by:

ACTUAL COMMUNITY PROCUREMENT PACKAGIN


Date Prepared

: Ocotber 9, 2013

Name of Proposed Sub-Project

Barangay
Municipality
Province

: Magsaysay
: Dauin
: Negros Oriental

Total Cash (Php)


Sub-project Duration

:
:
SOURCES OF FUNDS

DESCRIPTION

PACKAGES

Mode of Implementation : Community Force Account (CFA)

PACKAGE ITEMS

QTY

UNIT COST

TOTAL

KC Grant:

LCC:

1st Tranche (Php)

#REF!

#REF!

2nd Tranche (Php)


3rd Tranche (Php)
TOTAL CASH (Php)

#REF!
#REF!
#REF!

#REF!
#REF!
#REF!

PROC
METHOD

TRAN
1st Tranche
KC Grant

2nd Tranche

LCC Cash

KC Grant

Package 1 - A

Package 1

Hardware:
Portland Cement (40kgs) Type 1

1470

bags

245.00

16mm dia x 6.0m def. Bars

#REF!

length

340.00

#REF!

kg

46.50

#VALUE!

# 4 CWN
Hard Asphalt (Joint Filler)

#REF!

bags

1,950.00

Sub-Total (Actual)

360,150.00

#REF!
#REF!

Savings amount determined after procurement


Sub Total for Package (Plan)
Hardware:
Portland Cement (40kgs) Type 1
#REF!

306,127.50
LOCAL
SHOPPING
FOR GOODS
(LSG)

#REF!
#REF!
bags

54,022.50

#REF!
#VALUE!
#REF!
#REF!

54,022.50

#REF!

#REF!

#REF!

#REF!
-

LOCAL
SHOPPING
- FOR GOODS
(LSG)
#REF!

Sub-Total (Actual)
Savings amount determined after procurement
Sub Total for Package (Plan)

#REF!

#REF!

#REF!

Package 3

Package 2

Base Aggregates
Embankment (Fill) Materials

363.15

cu.m

Aggregate Subbase Course (Balastro


Class "A" Type)

#REF!

cu.m

#REF!

#REF!

550.00

Sub-Total (Actual)

#REF!

Savings amount determined after procurement


Sub Total for Package (Plan)
Aggregates
Fine Aggregates (Approved Source)
#REF!
Gravel 3/4" dia. (Approve Source)
#REF!

#REF!
LOCAL
SHOPPING
FOR GOODS
(LSG)

#REF!
#REF!
cu.m
cum

640.00
790.00

Sub-Total (Actual)

#REF!
#REF!

Savings amount determined after procurement


Sub Total for Package (Plan)

#REF!
#REF!

LOCAL
SHOPPING
FOR GOODS
(LSG)

#REF!

#VALUE!
#REF!

#REF!

#REF!
#REF!

#REF!
#REF!

#REF!

#REF!
#VALUE!

#REF!

#REF!

#REF!
#REF!

#REF!
#REF!

#REF!

#REF!

Package 3-A

Aggregates
Class A Stone

#REF!
Sub-Total (Actual)

Savings amount determined after procurement


Sub Total for Package (Plan)

cum

690.00

LOCAL
SHOPPING
#REF!
FOR GOODS
(LSG)
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!

#REF!
#REF!
#REF!

Package 4

Form Lumber
2"x2"x8' Coco Lumber (Formworks)

#REF!

bd.ft

21.00

2"x6"x12' Coco Lumber (Formworks)

#REF!

bd.ft

21.00

Sub-Total (Actual)

#REF!

Package 5

Savings amount determined after procurement


Sub Total for Package (Plan)
Water
Water (for mixing)

#REF!

LOCAL
SHOPPING
FOR GOODS
(LSG)

#REF!

#REF!

#REF!

#REF!

#REF!
#REF!

#REF!

cu.m

#REF!
#REF!

#REF!

LOCAL
SHOPPING
#REF!
FOR GOODS
(LSG)
#REF!

Sub-Total (Actual)
Savings amount determined after procurement
Sub Total for Package (Plan)

#REF!
#REF!

#REF!

#REF!

#REF!

#REF!

#REF!
#REF!

#REF!

#REF!
#REF!

Equipment Rental (Heavy)

Package 6

Mobilization & Demobilization


Backhoe
Road Grader
Road Roller

lot

45,000.00

#REF!
#REF!
#REF!

days
days
days

20,000.00
15,000.00
15,000.00

Sub-Total (Actual)

45,000.00

45,000.00

Savings amount determined after procurement


Sub Total for Package (Plan)

38,250.00
LOCAL
SHOPPING
FOR GOODS
(LSG)

6,750.00

#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!

#VALUE!

#VALUE!

#REF!
#REF!

#REF!
#VALUE!

#REF!
#VALUE!

Package 10

Package 9

Package 8

Package 7

Equipment Rental (Light)


Concrete Mixer
Concrete Vibrator

#REF!

days
days

700.00
520.00

Sub-Total (Actual)

#REF!

Savings amount determined after procurement


Sub Total for Package (Plan)
Labor
Skilled
1.00
Unskilled
1.00

#REF!
#REF!
lot
lot

#REF!

Sub-Total (Actual)

#REF!
#REF!
unit

8,450.00

Sub-Total (Actual)
Savings amount determined after procurement
Sub Total for Package (Plan)
Total Direct Cost
Handtools & Personal Protective Equipment (PPE)
Hard Hat
#REF!
Hand Glooves
10.00
Shovel w/ handle
10.00
Face Mask
10.00
Safety boots
10.00

Sub-Total (Actual)
Savings amount determined after procurement

#REF!
#REF!

Savings amount determined after procurement


Sub Total for Package (Plan)
Project Billboard
Project Steel Billboard
1.00

Medicine kit box to include Betadine


100ml, Agua Oxinada 100ml, cotton
5grams, bandage 5pcs, & 1st aide tape
1 roll

#REF!

1.00

LOCAL
SHOPPING
FOR GOODS
(LSG)

LOCAL
SHOPPING
FOR GOODS
(LSG)

#REF!

#REF!

#REF!

#REF!

#REF!
#REF!
13,612.84
11,153.12

4,000.00
2,163.02

40,000.00
39,340.00

24,765.96

6,163.02

79,340.00

#REF!
#REF!

#REF!
#REF!

#REF!
#REF!

8,450.00

LOCAL
SHOPPING
8,450.00 FOR GOODS
(LSG)
#REF!

#REF!
#REF!
pcs.
pairs
pcs.
pcs.
pairs

set

85.00 #REF!
35.00
350.00
225.00
2,250.00
8.50
85.00
280.00
2,800.00

1,750.00

1,750.00

#REF!
#REF!

6,760.00

1,690.00

6,760.00

1,690.00

#REF!
#REF!
#REF!

#REF!
#REF!
#REF!

#REF!

LOCAL
SHOPPING
FOR GOODS
(LSG)

#REF!
#REF!

#REF!
280.00
1,800.00
68.00
2,240.00

70.00
450.00
17.00
560.00

1,400.00

350.00

#REF!
#REF!

#REF!
#REF!

79,340.00

Package 13

Package 12

Package 11

Sub Total for Package (Plan)


BSPMC Filing Cabinet
BSPMC Filing Cabinet

1.00

pcs.

6,400.00

Sub-Total (Actual)
Savings amount determined after procurement
Sub Total for Package (Plan)
Environmental Mitigating Cost:
Warning Sign
5.00
Barricade
5.00

pcs.
pcs.

280.00
280.00

Sub-Total (Actual)
Savings amount determined after procurement
Sub Total for Package (Plan)
Indirect Cost:
Overhead Cost
Project Supervision
Administrative Cost
Bidding Publication

#REF!

#REF!

6,400.00

5,120.00

1,280.00

5,120.00

1,280.00

#REF!

#REF!
#REF!

#REF!
#REF!

1,400.00
1,400.00

1,120.00
1,120.00

280.00
280.00

2,240.00

560.00

#REF!
#REF!

#REF!
#REF!

LOCAL
SHOPPING
6,400.00 FOR GOODS
(LSG)
#REF!

LOCAL
SHOPPING
2,800.00 FOR GOODS
(LSG)

#REF!
#REF!

#REF!

#REF!

5,860.00
7,491.42

Materials Testting

CFA

Treasurer Bond

8,000.00

8,000.00 #VALUE!

Contingency Cost
Sub-Total (Actual)

#REF!

Savings amount determined after procurement


Sub Total for Package (Plan)
Total Indirect Cost

15,491.42

#REF!
#REF!

GRAND TOTAL CASH (Actual)

2,403,025.00

SAY
%

#REF!
#REF!
Checked & Reviewed by:

Workshop Output by:

#REF!
#VALUE!
#VALUE!
#REF!

#REF!
#REF!
5,860.00
#REF!

#REF!

#VALUE!

85,200.00

1,602,080.00

320,340.00

200,260.00

#REF!

#REF!

#REF!

#REF!
#REF!

#REF!

GRAND TOTAL CASH (Plan)

5,860.00

#REF!
#REF!

#REF!
#REF!

TOTAL SAVINGS DETERMINED AFTER PROCUREMENT

#VALUE!

Recommending Approval:

FELIX ABELLANO

TEODOLO T. BULISID

RODSON R. ESCORA

Procurement Team Head

PPT

Deputy Area Coordinator

CARMEN A

Municipa

NITY PROCUREMENT PACKAGING

Concreting of Barangay Road


#REF!
90 C.D

.
PERCENTAGE WEIGHT
LEGEND:

FUND SOURCE

AMOUNT
(PESO)

KC GRANT

#REF!

TOTAL

TO KC
GRANT

TO LCC
CASH

#REF!

#REF!

#REF!

TOTAL LCC

#REF!

#REF!

#REF!
#REF!
#REF!

#REF!
#REF!
#REF!

LCC - In-kind
LCC - Cash
TOTAL

#REF!
#REF!
#REF!

REMARKS

TRANCHING SCHEDULE
TOTAL
2nd Tranche

3rd Tranche

LCC Cash

KC Grant

LCC Cash

TOTAL
KC Grant

LCC Cash
54,022.50

#REF!

#VALUE!

#VALUE!

#VALUE!

#VALUE!

#VALUE!

#REF!

#VALUE!

#VALUE!

#REF!

54,022.50
#REF!

360,150.00

#REF!
#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#VALUE!

#VALUE!

#VALUE!

#REF!

#REF!

#REF!

#REF!
#REF!
#REF!
#VALUE!
#REF!

#REF!
#REF!
#REF!
#VALUE!
#REF!

#REF!
#REF!
#REF!
#VALUE!
#REF!

#REF!
#REF!

#REF!
#REF!

#REF!
#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!
#REF!

#REF!
#REF!

MONTHS
1

306,127.50

#REF!

PROPOSED
IMPLEMENTATION
SCHEDULE

#REF!
#REF!

#REF!

#REF!

#REF!

#VALUE!

#VALUE!

#VALUE!

#REF!

#REF!

#REF!

#REF!
#REF!
-

#REF!
#REF!
#REF!

#REF!

#REF!

#REF!

#REF!

#REF!
#REF!

#REF!
#REF!

#REF!
#REF!

6,750.00
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!

#VALUE!

#VALUE!

#VALUE!

#REF!
#VALUE!

2,500.00
5,825.00

7,835.00

45,621.02

8,325.00

#REF!
#REF!

#REF!
#REF!

#REF!
#REF!

7,835.00

45,621.02

45,000.00

#VALUE!
#VALUE!
#VALUE!
#REF!
#VALUE!

22,087.16
23,533.86

#REF!
#REF!
-

#REF!

38,250.00

4,000.00
3,835.00

#REF!
#VALUE!

#REF!
#VALUE!

#REF!
#VALUE!

#REF!
#VALUE!

#REF!

#REF!

#REF!

#REF!
#REF!
75,700.00
74,026.98

#REF!
#REF!
10,500.00
11,823.02

#REF!
#REF!
86,200.00
85,850.00

22,323.02

172,050.00

#REF!
#REF!

#REF!
#REF!

149,726.98
#REF!
#REF!
6,760.00

1,690.00

8,450.00

6,760.00

1,690.00

8,450.00

#REF!
#REF!
#REF!

8,325.00
#REF!

#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!

280.00
1,800.00
68.00
2,240.00

70.00
450.00
17.00
560.00

350.00
2,250.00
85.00
2,800.00

1,400.00

350.00

1,750.00

#REF!
#REF!

#REF!
#REF!

#REF!
#REF!

#REF!

#REF!

5,120.00

1,280.00

6,400.00

5,120.00

1,280.00

6,400.00

#REF!
#REF!

#REF!
#REF!

13,488.58
7,000.00
30,000.00
6,000.00

8,708.92
1,500.00
5,008.58
1,500.00

4,000.00

#REF!
#REF!

1,120.00
1,120.00

280.00
280.00

1,400.00
1,400.00

2,240.00

560.00

2,800.00

#REF!
#REF!
3,442.50

#REF!

#REF!
#REF!

19,348.58
7,000.00
37,491.42
6,000.00

12,151.42
1,500.00
13,008.58
1,500.00

12,000.00 #VALUE!
- #VALUE!
81,840.00

#VALUE!

#REF!
#REF!
31,500.00
8,500.00
50,500.00
7,500.00
#VALUE!
#VALUE!
-

3,442.50

60,488.58

16,717.50

#REF!
#REF!
3,442.50
#REF!

#REF!
#REF!
60,488.58
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#VALUE!
#VALUE!
16,717.50 #REF!
#VALUE!
#VALUE!
#REF!
#REF!
#REF!
#REF!

11,277.50

106,109.60

25,042.50

#REF!

#VALUE!

#VALUE!

40,042.50

200,260.00

40,042.50

1,837,292.00

371,253.00

2,403,025.00

115,060.00

#REF!

94,150.40

#REF!

#VALUE!

Submitted by:

#VALUE!

Noted by:

CARMEN A. GAUDIANO

GEORGE A. ALAS-AS

GEOGRE S. ISULAT

Municipal Engineer

BSMPC

Regional Community Infra. Specialist

SCHEDULE OF IN - KIND LOCAL COUNTERPART CO


Date Prepared
###
Barangay:
MAGSAYSAY
Municipality: Dauin
Province:

Name of proposed community project:Concreting of Barang


Total Estimated Cost:
Php2,440,600.00

Negros Oriental

Mode of Implementation:

Community Project Duratio90 Calendar Days


Estimated Cost1st Tranche
###
2nd Tranche 3,557.50
3rd Tranche 3,557.50
CFA

By Contract

ESTIMATED COST INVOLVED and SCHEDULE


PROC.
DELIVERY
PACKAGES

PACKAGE ITEMS

METHOD 1st Tranche2nd Tranche3rd Tranche


In - Kind

Direct Cost:
Materials
Package 1
Unskilled labor

Contract

Indirect Cost:
Hand tools/PPE
Pre-engineering
Project Supervision

CFA

In - Kind

In - Kind

25,260.00

3,157.50

3,157.50

2,000.00
3,200.00

400.00

400.00

### 3,557.50

3,557.50

TOTAL
Workshop output of:

Checked by:

Reviewed by:

FELIX AVELLANO
Procurement Team Head

CARMEN A. GAUDIANO

RODSON R. ESCORA

Municipal Engineer

DAC - Area Coordinating Team

TERPART CONTRIBUTION

ncreting of Barangay Road


0.00
LCC ( In - Kind) :Php 37,575.00

ED and SCHEDULE OF
RY

PROPOSED
IMPLEMENTATION

TOTAL

SCHEDULE

31,575.00

January, 2014 -April, 2014

2,000.00
4,000.00

January, 2014 -April, 2014


January, 2014 -April, 2014

ESCORA

ordinating Team

###
Submitted by:

GEORGE ALAS-AS
BSPMC Chairperson

1st Tranche
CHECKLIST OF DOCUMENTARY REQUIREMENTS
Barangay MAGSAYSAY
Municipality of Dauin
Sub-Project Title: Concreting of Barangay Road
Phase/Cycle: 2
RFR REVIEW SHEET
Item #

1st TRANCHE

Requirements

Comments

1. Request for Fund Release (RFR)


2. POW
3. Colored Photographs of Proposed Project
Site/Plan
4. Guide for the Technical Review
5. Certification of Review by RIE, RFA, CPS &
RPM
6. MDC/ MIBF Resolution
7. Detailed Estimates/Work Schedule &
Physical Progress Report
8. Hydraulic Analysis for Water Supply System
9. Project Proposal
10. Planned Comm. Procurement Packaging
(PCPP)
11. Procurement Action Plan (PAP)
12. LCC for SPI Monitoring Report
13. DBP Certification/Bank Snapshot
14. Schedule of In-kind LCC
15. O&M Action Plan signed by Brgy. Chairman
16. Certification from the Regional Director

17.For SPs amounting to P 1.5 million and above, submit


PSA result, approved technical plans ( for roads indicate critical sections subject for concreting) and
approved specifications

18.Barangay Council Resolution


19.Sub Project Agreement
20.Local Counterpart Contribution Plan/Admis cost
21.Certification on Local Contributions
22.Bond Premium of Treasurer
23. Economic Analysis
24.Notarized Deed of Lot Donation for Titled
Lot or Quit Claim for non Titled lots
Reviewed By: ______ Date: _____

For Further Review of :______________ Date:____________


Other Comments/ Findings/ Recommendation

Reviewed By: ________ _____


Reviewed By: ________ _____

Actions Taken
For Asec. CGG/ NPM's Signature
For regional compliance
For Transmittal to Finance Unit
Returned to Region

Date/ Date Returned


___________________
___________________
___________________
___________________

Department of Social Welfare a

KALAHI-CIDSS:MCC

LCC FOR SUB-PROJECT IMPLEMENTA

As of October 31, 2

PA
C
KA
G

ES

Barangay :
MAGSAYSAY
Municipality : Dauin
Sub-Project : Concreting of Barangay Road

Package Items

Total LCC Committed

Cash
In-Kind

SCHEDULE OF LOCAL
2nd Tranche
Cash

1st Tranche
Cash
Planned

In-Kind
Actual

Planned

Actual

Planned

DIRECT COST:
I# 102-Surplus Common

I# 104-Embankment
I# 200-Aggregate Sub-ba

I# 311-PCCP
I# 505-Grouted Riprap
I# 500-Installation of RCPC
Project Steel Billboard
Unskilled Worker
TOTAL DIRECT COST
INDIRECT COST:
Overhead Cost
Bidding Publication
Administrative Cost
Package 5
Materials Testing
Treasurer's Bond
Contingency
Handtools / PPE
Package 2
Pre-Engineering
Project Supervision
Environmental Impact
Package 4
BSPMC Filing Cabinet
Package 3
VAT (7 % of Direct Cost
Package 1
TOTAL INDIRECT COST
GRAND TOTAL
Package 1

Prepared by:

11,766.00
25,013.09
35,732.85
81,221.35
53,353.50

6,000.00

1,500.00
208,586.79

31,575.00
0.00 31,575.00

0.00

6,000.00

0.00
0.00

34,042.50
34,042.50
40,042.50

1,500.00
8,000.00
2,000.00
5,253.75
1,758.00
8,500.00
720.00
1,500.00
82,521.46
111,753.21
320,340.00

2,000.00
4,000.00

0.00 6,000.00
0.00 37,575.00

Verified by:

ARLENE P. GESULGA
Municipal Financial Analyst

partment of Social Welfare and Development

ALAHI-CIDSS:MCC PROJECT

JECT IMPLEMENTATION MONITORING REPORT


As of October 31, 2013
:

438,000.00

:
:

400,425.00

Total LCC Delivered :


Cash
In-Kind

37,575.00

0.00
0.00
0.00

SCHEDULE OF LOCAL COUNTERPART CONTRIBUTION DELIVERED


2nd Tranche
3rd Tranche
Cash
In-Kind
Cash
In-Kind
Actual

Planned

Actual

Planned

Actual

Planned

TOTAL
Cash

Actual

0.00

0.00

6,000.00

0.00

0.00

0.00

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

0.00
0.00

0.00
1,500.00
8,000.00
2,000.00
5,253.75
17,038.50
1,758.00
0.00
8,500.00
720.00
1,500.00
133,567.96
179,838.21
400,425.00

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

17,038.50

0.00
0.00

0.00
0.00

Verified by:

17,004.00
0.00 34,042.50
0.00 40,042.50

0.00
0.00

0.00
0.00

Actual

11,766.00
25,013.09
35,732.85
81,221.35
65,353.50
0.00
1,500.00
0.00
220,586.79

6,000.00

0.00

Planned

Noted by:

JOEL A. EREDIANO
Area Coordinator

ANTONIO R. DOLAOTA, CPA


Regional Finance Focal Person Coordinator (RFFP-Coordinator)

TOTAL
In-Kind
Planned

Actual

0.00
0.00
0.00
0.00
0.00
0.00
0.00
31,575.00
31,575.00

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00
0.00
0.00
2,000.00
4,000.00
0.00
0.00
0.00
6,000.00
37,575.00

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

oordinator (RFFP-Coordinator)

You might also like