Professional Documents
Culture Documents
[CRS]
CONTRACT NUMBER
GC13100800
CONTRACT TITLE
EDD/GC13100800/EXT/TN/348
DOCUMENT NUMBER
VEN-3397-DGEN-2-05-0461
DOCUMENT REVISION
PRE-COMMISSIONING AND COMMISSIONING INSTRUCTIONS / PROCEDURES FOR SOLAR POWER
SYSTEM
DOCUMENT TITLE
No.
1
QP PROJECT NUMBER
QP COMMENTS
Code-1: Approved. Works may proceed.
3397
03-2015
DATE
CONTRACTOR RESPONSE
Noted. Document issued AFC.
Page 1 of 1
C)
Qatar Petroleum
PROJECT/CONTRACT REF 3397 I GC13100800
ENGINEERING PROCUREMENT INSTALLATION AND COMMISSIONING
FOR WELLHEAD SCADA AND CATHODIC PROTECTION IN DUKHAN
DOCUMENT TITLE:
SUNPOWER
M06 NE*GY FCf uff
rfe I .ft
29-03-15
19-03-15
RR/TC
BJ/LM
BD
QP
RR/TC
BJ/LM
BD
QP
25-02-15
RR/TC
BJ/LM
BD
QP
26-01-15
RR/TC
BJ/LM
BD
QP
DATE
REV.
PREPARED
BY
CHECKED
BY
APPRD.
BY
APPRD.
QP
DOCUMENT NUMBER:
VEN-3397-DGEN-2-05-0461
SHT
1 OF
23
REV A
TABLE OF CONTENTS
1.
INTRODUCTION .................................................................................................... 3
2.
OBJECTIVE ........................................................................................................... 3
3.
4.
5.
6.
7.
8.
TROUBLESHOOTING ........................................................................................... 7
RECORDS .............................................................................................................. 8
9.
10.
APENDICES ........................................................................................................... 9
Doc.No.VEN-3397-DGEN-2-05-0461
Rev.A
Page 2 of 23
1. INTRODUCTION
The scope of work is to provide the pre-commissioning and commissioning recommendation &
instructions for the Off-grid solar power system of the project QP DUKHAN FIELD - WELLHEAD
SCADA AND CATHODIC PROTECTION in Qatar.
2. OBJECTIVE
The target of this procedure is to define the commissioning procedure for the Off-grid solar system
& related equipment installations.
The processes and methods detailed in this document adopt best practice associated with the
commissioning of an off-grid solar power system with health and safety requirement
The pre-commissioning phase shall start when construction is successfully completed:
-
This document does include all electrical check to be performed during commissioning but does
not cover visual inspection of the system (i.e. visual check of PV modules, structures and battery
banks). It is assumed that visual inspection is performed during the construction phase of the
project.
QP
Qatar Petroleum
VOC
Voltage Open-Circuit
ISC
RISO
Resistance isolation
PPE
PVS
Photovoltaic Supervisor
Doc.No.VEN-3397-DGEN-2-05-0461
Rev.A
Page 3 of 23
Hard hat
5. APPLICABLE DOCUMENTS
This procedure shall be read along with following documents
-
safety and installation instructions PV module ref. Doc 001-15497 (provided with PV
modules)
Pictures
SolarInstallationTestkit(i.ePV150Seaward)
includingsolarirradiationsensor
DigitalVoltageTesterVAT(i.eDuspolDigital)
Allusualelectriciantools
Doc.No.VEN-3397-DGEN-2-05-0461
Rev.A
Page 4 of 23
7. PRE-COMMISSIONING RECOMMENDATIONS
This section includes all pre-commissioning instructions on components.
PRE-COMMISSIONING RECOMMENDATIONS FOR GROUND CONNECTION
Following minimum verification are required for grounding connections:
-
Verify with the solar installation test kit the continuity of each ground connection point.
Verify with the solar installation test kit the resistance value of the site. It shall be compared
to the CONTRACTOR acceptable value.
Please note that Ground connection shall be in accordance with the approved documents.
PRE-COMMISSIONING RECOMMENDATIONS FOR BATTERIES
Following minimum actions are required for batteries and battery cables:
-
First connect battery cables on regulation controller unit side in order to avoid any risk of
short circuit.
Once done, battery cables can be connected on the battery bank terminals
Record the voltage of each battery cell with following format. A complete table is attached
in appendix (template 1).
Cell 1
Cell 2
Cell 3
Cell 4
Cell 5
Cell 6
Voltage
-
Verify that battery cells are in the acceptable range of voltage according to data coming
from battery manufacturer.
For more information and details on the battery pre-commissioning procedure, please refer
to Saft documentation. Especially In case of a long time storage (more than maximum
required by Saft).
PRE-COMMISSIONING RECOMMENDATION FOR THE LOAD CONNECTION
Verify the polarity connection of each DC output cable from the regulation unit to the CP
Verify the polarity connection of each DC output cable from the regulation unit to the RTU
Visually check the torque mark inside each electrical cabinet. If they are correct, please
continue the test, if not, verification of torque shall be done.
Doc.No.VEN-3397-DGEN-2-05-0461
Rev.A
Page 5 of 23
TEST OVERVIEW
Each PV module except dummy modules will be verified during this phase. All this test must be
done through solar cables of each modules.
In order to verify PV modules work correctly, this test consist in verifying the correct connection
and recording short-circuit current and open voltage circuit of each module.
TEST PROCEDURE
#
Pass
Value
Fail Value
>300
W/m2
<300
W/m2
If step 1 passes then proceed with the next step; if step 1 fails
+V
-V
Positive connector
Negative Connector
5
Doc.No.VEN-3397-DGEN-2-05-0461
Rev.A
Page 6 of 23
Pass
Value
Fail Value
Over 5%
of avg.
If step 5 fails:
5%
of avg.
TROUBLESHOOTING
#
Troubleshooting
(perform steps below as needed to resolve problem)
Check that all connectors are properly seated for the module
Look for a panel with low voltage compared to the other panels
Doc.No.VEN-3397-DGEN-2-05-0461
Rev.A
Page 7 of 23
Troubleshooting
(perform steps below as needed to resolve problem)
Cuts
Scrapes
Pinched wire
Module
Module Junction-Boxes
RECORDS
All measurements shall be recorded and saved in excel. Those measurements shall include all
measured values and tests conditions. Please see an example of a Test Report performed on PV
modules:
9. COMMISSIONING PROCEDURE
This section includes all commissioning instructions on the solar power system provided by
Sunpower.
Each step to perform the commissioning is detailed in appendix (template n2).
Doc.No.VEN-3397-DGEN-2-05-0461
Rev.A
Page 8 of 23
10. APENDICES
TEMPLATE 3:
TEMPLATE 3-1
TEMPLATE 3-2
TEMPLATE 3-3
Doc.No.VEN-3397-DGEN-2-05-0461
Rev.A
Page 9 of 23
Measures
BANK 1
Site n
Site type
Cell 1
Cell 2
Cell 3
Cell 4
Cell 5
Cell 6
Cell 7
Cell 8
Cell 9
Cell 10
Cell 11
Cell 12
Cell 13
Cell 14
Cell 15
Cell 16
Cell 17
Cell 18
Cell 19
Cell 20
Cell 21
Cell 22
Cell 23
Cell 24
Cell 25
Cell 26
Cell 27
Voltage
Voltage
Voltage
Voltage
Voltage
BANK 2
Global Battery Bank Voltage Bank 2
Cell 1
Cell 2
Cell 3
Cell 4
Cell 5
Cell 6
Cell 7
Cell 8
Cell 9
Cell 10
Cell 11
Cell 12
Cell 13
Cell 14
Cell 15
Cell 16
Cell 17
Cell 18
Cell 19
Cell 20
Cell 21
Cell 22
Cell 23
Cell 24
Cell 25
Cell 26
Cell 27
Voltage
Voltage
Voltage
Voltage
Voltage
Doc.No.VEN-3397-DGEN-2-05-0461
Rev.A
Page 10 of 23
Date:
Operator
Switching Order:
Doc rev.
Site n
Site Type
No.
Switching Instruction
Hazard
Responsible Person
Result
Time/
Initials
Doc.No.VEN-3397-DGEN-2-05-0461
Rev.A
Page 11 of 23
Switch On Q1
10
11
Doc.No.VEN-3397-DGEN-2-05-0461
Rev.A
Page 12 of 23
12
13
14
15
16
17
18
Switch On Q4
19
20
21
22
Switch On Q5
23
Doc.No.VEN-3397-DGEN-2-05-0461
Rev.A
Page 13 of 23
Switch On Q8
25
26
Doc.No.VEN-3397-DGEN-2-05-0461
Rev.A
Page 14 of 23
28
29
30
Disconnection/connection
of
the
battery bank without affecting 50% of
the output load.
Doc.No.VEN-3397-DGEN-2-05-0461
Rev.A
Date: __________________
Date: __________________
Page 15 of 23
TEMPLATE 3-1
Date:
Tag number:
Cathodic protection
OK NOK
Tag plate
Polarity check
Communication test
Disable input
Auxiliary input
Interrupt timer
Alarm relay
Remarks:
Doc.No.VEN-3397-DGEN-2-05-0461
Rev.A
Page 16 of 23
TEMPLATE 3-2
Date:
Charge controller
type:
Tag number:
1
OK NOK
Tag plate
Communication test
Remarks:
Doc.No.VEN-3397-DGEN-2-05-0461
Rev.A
Page 17 of 23
TEMPLATE 3-3
Date:
Charge controller
type:
Tag number:
2/3
OK NOK
Tag plate
Communication test
Remarks:
Doc.No.VEN-3397-DGEN-2-05-0461
Rev.A
Page 18 of 23
Date of commissioning
Site type (1, 2 or 3)
Those verifications shall be conducted based on applicable drawings and manuals (see list of
applicable drawings in the project vendor document list)
Visual inspection :
PV array are correctly fixed to the support structure
No particular shadow is present on the PV array which can affect the daily PV production
No particular crack or scratch is present on the glass of the PV module
All part are clean
Describe all present damages or scratch out on the support structures:
TICK
Approved
Approved with comments
Rejected
Comments:
Date
Doc.No.VEN-3397-DGEN-2-05-0461
Rev.A
signature
Page 19 of 23
TEMPLATE 5
Tenesol / Sunpower
Qatar Petroleum
CP Commissioning Procedure
802195-B.doc
1. Revision Status
Issue
Date
Approved
First Issue
Description of Change
5 Jan 2015
MF/LH
23 Jan 2015
MF/LH
2. Introduction
This document describes the commissioning of the CP Controller.
2.1. Typical System Wiring for Cathodic Protection Systems
As a CP system works by passing current through ground, it is essential that the system Common (the Positive
potential) is only grounded at the output of the CP Controller. If a ground connection is made at any other point in
the system, it is possible that the CP Controller will not be able to monitor or control the output current and voltage
correctly, particularly if a reference electrode is used.
COMMON POSITIVE
+
+
+
+
CONTROL
+
CONTROL
+
GROUNDBED
MCB
MCB
SOLAR ARRAY
CHARGE CONTROLLER
BATTERY
CATHODIC PROTECTION
CONTROLLER
PROTECTED STRUCTURE
Grounding of Enclosures
The grounding of enclosures and structures is acceptable, but under no circumstances should a connection be made
from the system common to a metal enclosure or structure otherwise the protective current is liable to have an
adverse effect on these parts, and in some cases may accelerate corrosion.
MF
Page 1 of 4
Doc.No.VEN-3397-DGEN-2-05-0461
Rev.A
Tenesol / Sunpower
Qatar Petroleum
CP Commissioning Procedure
802195-B.doc
3. Commissioning
3.1. Input Power
On the CPC Control PCB Assembly, ensure the Enable/Disable switch is set to the DISABLE position.
Turn on the power to the CP Input terminals.
On the CPC Control PCB Assembly, ensure the green Status LED is illuminated.
Current
H-Cell
00.0V
00.0A
0.0V
Actual
00.0V
5.0A
5.0V
Set-Points
Note: If a Half-Cell (Reference Electrode) is fitted, the indication on the Half-Cell meter should match the structure
to soil potential (as measured by a portable half-cell and meter).
Note: If a Half-Cell is not fitted, then ensure a wire link is fitted across the Half-Cell input terminals.
Current
H-Cell
00.0V
00.0A
0.0V
Actual
00.0V
5.0A
5.0V
Set-Points
Increase the Output Voltage Set-point (Menu 0 Screen 1). The voltage and current actual values should indicate an
increase as the set-point is increased. The CP Controller is operating in Constant Voltage Mode (readings
dependant on ground conditions example shown is 1.0):
Voltage
Current
H-Cell
4.0V
4.0A
0.0V
Actual
4.0V
4.0A
5.0V
Set-Points
MF
Page 2 of 4
Doc.No.VEN-3397-DGEN-2-05-0461
Rev.A
Tenesol / Sunpower
Qatar Petroleum
CP Commissioning Procedure
802195-B.doc
Current
H-Cell
5.0V
5.0A
0.0V
Actual
6.5V
5.0A
5.0V
Set-Points
MF
Page 3 of 4
Doc.No.VEN-3397-DGEN-2-05-0461
Rev.A
Tenesol / Sunpower
Qatar Petroleum
CP Commissioning Procedure
802195-B.doc
4. Commissioning Record
Site:
Date:
Commissioned By:
Signed:
Section
Description
Voltage
Current
Half-Cell
3.1
Input Power
3.2
0.0V
5.0A
5.0V
3.3
LCD Display
0.0V
5.0A
5.0V
3.4
5.0V
3.5
3.6
Half-Cell Voltage
3.7
Disable Input
3.8
Interrupt Timer
3.9
3.10
Communications
3.11
End of Procedure
MF
5.0A
Page 4 of 4
Doc.No.VEN-3397-DGEN-2-05-0461
OK
Rev.A