Professional Documents
Culture Documents
Date: __________________
Project Size:
______ Tons
______ Outdoor Units
______ Indoor Units
Telephone
Phase I - Pre-construction
____________________________________________
Name(s)
Telephone
Telephone
____________________________________________
___________________________________________
Date
Rev. 11-18-2011
Date
Phase II Beginning
Of Construction
Date
Date
Systems: __________________________________________________________________________
Review Install Notes with: ____________________________________________________________
Name
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
Recommendations:
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
Date
Rev. 11-18-2011
Completion of Pre-Commissioning Checklist (PCC) (Please send completed copy to order file in GSO)
Completion of Request for Supervised Commissioning Form (RFC)
Scheduled Supervised Commissioning
Commission Dates: ________ _______ ________ ________
Date
Rev. 11-18-2011
Page 1 of 2
Rev. 11-11-11
Page 2 of 2
Rev. 11-11-11
Cil
-u
-;::
CD
CIJ
~I~
::r::
)f,
""':
: /
i"", , ,/"i
location of
u~it'
.,y
f--
;;: :;::
'- '-
(:ncaseofusi~gAttachedpip;(Note,,)]
(Note,a)
Service
sp~ce
/'/
//
41 5/8
463/4
46-1/8
3!10-3/NI-I/8
3'10-318=31-1/8
GiQ~nding
terminal
(~ote.S,6)
II
5/16-3/8U!C
M4
I 1-1/8
IH/41
3D072212A
1 S~ction gas pipe cUDectiol port (Hote. 5, 6) til-Va ilch br!Z;Dg connection
Kallber
Partnaoe
Cetcriptian
7 Suspensioo bracte!,
6 Co"," bOl (H,le,1I
5 LiqUid pipe cOineelion port
s==~~
,,,,,r\
~,I///(//((//(C(((/((C(//(/v/((////////(///////(///J
.; .~
:;
i' ~
~~
,~
~~
~
~.~,
~
rn
CD
I\)
I/)
::J
0-
:::I
I/)
..:.....
o
3'
Co)
;,
.....
0
0
to
.....
.....
rn
(,)
5-
::::s
_.
::::s
CD
III
;::;:
:::l
c-
-U
Ol
(,)
"< C_.
.,.<
<
lJ
en
OJ
.".
~-'=
1i
~,-
,
'"''
/.
co~necti~g
"H
S~speUjOQ
bractets
(~cte.5,6)
61-1/2
68-1/4
51103/5"51-7/5
56-311
bra.zl~~
~razin~ cO~lecti~~
is/~
p3/8 ilcb
WRectlor
~ICb HU~Dg1:mHt:D~1
5/16-J/9~IIC
'-14
Ifill.
illZ Ileh
12 118
I 6-3/4
3D072213A
I I
.
'""---t--
;110-3/,-51-116
~~
... ~.~1
~
"'1:'\:'~
Service space
t h=ft~1Ir-
--~
017-3/4
'\lAspectiOn hatch
__~
""/
"
, /"" ,
L__
~c
CD
en
<
c..
c:
"0
0)
oCN
<
0)
CN
CD
......
.....
o
o
CN
en
c
c:
f/)
o
::J
f/)
::J
(1)
rJJ
OJ
VJ
o<
-b
'"
.~
"'I~
~ '0
"
a.
<1l
"8
(!l.
gj
l'i.
.~
"'I.E
lQ
co
./
I
I.
"' "' .
(4-5/16)
o
15-1/4
ill
2-518
r:..
W
~
6 )(Note 1.)
o 18 (Note 2.)
-.~
--~
~Inspeclion door
I"\--L---n-
r-
~'-"-"-i'-"-"-',:,J
./
a:>
~I,
!(2
:;;-
, I
1-
16-7/8
103/16
~
c\J
WI
"=
(Servicing space)
V/.
12 or more
t
(Servicing space)
/j
Servicing space
C\J
'""";"
wi
,,=1
indoo~
unit.
3
2
1
3D058236
Grounding terminal
Suspension brackets
7
6
10
9
NI~
oE .'"
0"'
i" ~
__ . =L 10or~~e
10ormore
@'~~~~
~~
<
c...
C
"C
Ol
.0
C/.)
OJ
tn
:J
tn
-.
o
CD
:J
c-.
tn
:I
tn
;j
(1)
o
3'
C>
g
;,
cO
It)
C/.)
C
rJJ
1 (4-5/16) 1
15-1/4
lL..-------
".
1 (4-5/16) 1
.~
.1
13-3/4 or more ,
(Servicing space)
I ~l ~
8
7
6
5
4
3
2
1
Number
10
30058237
Description
~
~
~-----
60 or less_
4. Small sound of refrigerant will be made, which
may be disturbing_
Do not install it al the place such as bedroom
under root
13-3/4 or more
(Servicing space)
~~~~
Servicing space
1" 100rm;~ _/
='(serVicingspaCe)
iw
~\\9ooo~'~
6-518
10-3/16
1-718
~
N
~Il.
<
c...
<h
(0
CW
cCJ)
::s
en
0"
."
2-5/~ I
,.:.
a5
(61(Note 1.)
0 18 (Note 2.)
~Inspection door
---.-~
".
i':
~Ig>
.,
alCl.
.,
\!)
-'5'
~-~~
~~~
::s
en
ex>
0'
"'0
0)
3"
CD
-u
~I!I ~I
(;-5/8)
___ _
If --
S!"j](6
;g
16-7/8
(Suspension bolt pitch)
CJ)
o<
OJ
<
rn
OJ
.j>.
Dimensions
EDUS39-900-FB
BSVQ96PVJU
o
l
-
~g'
0._
'J,
Ul
<D
'"
;~
::;go
s>~
~~
~
~
~s:s;~;;
"~'$."G.v.-
Goo"""
_
.-
~
~
1
-
;~
+-'
'-' ....
.....
..... -
=.
----:::
--
--
~e:~:;:';;~:;;
.;:: ...... ""' ....... ",;:"6 -=- ;;;0>-"
~~HHH~HH
~~
.'"
..........
~::.'=g:~-:~
UDIJO
;;
s;
d..
---!'",'4r- - - - -
+--
I,
,
.-
e:
-:;
.-
91/Ci-11
I/"-Z
91/.-
8!\-~
BSVQ-P
NOTE:
CONTRACTOR TO PROVIDE 5/16" THREADED
ROD HANGERS WITH DOUBLE SIDED RUBBER (1/2" THICK)
ISOLATORS AT EACH SUSPENSION BRACKET (4- EACH)
ON BRANCH SELECTOR FOR SUSPENSION OF UNIT
,/
DETAIL
_~N
Rev. 11-11-11
BRANCH SIDE
NOTE:
DETAIL -
MAXIMUM ROTATION OF
Rev. 11-11-11
PRESSURE-REDUCING VALVE ~
NITROGEN
~
\
REfRIGERANT PIPING
PACKLESS VALVE
NITROGEN
NOTES:
USE DEDICATED MANIFORD. GAUGES AND
HOSES TO GUARD AGAINST CROSS CONTAMINATION
SERVICE PORT CHANGE DIAMETER 1/4" ENLARGED TO 5/16"
DETAIL -
Rev. 11-11-11
RECOMMENDED EQUIPMENT
CLEARANCES:
3" ABOVE
12" ENTERING (3 PIPE)
IN SPACE CONDITIONS THAT
DO NOT ALLOW 3" ABOVE THE
DEVICE, MAINTAIN A 1" AIR
SPACE BELOW UPPER DECK
AND INSTALL 1/2" FOAM
HANGERS
INSULATION ON THE TOP OF
(TYP)
THE DEVICE.
HANGERS
(TYP)
II
I I
I
III
I I I
I I
BRANCH
SELECTOR
UNIT
MIN. 20"
BEFORE ELBOW
DETAIL -
..
MIN. 20"
BEFORE ELBOW
--
_-1
lB"
--<.,.-""'"
-
."...,.."---
~-- -
-<:=-..............
....... -.......
->
- ___ - -
REFRIGIERANT PIPING
AND POWER CONDUIT(S)
LOCAnONS
..............-
--
,.,.,. . .- -- -.......
......
< ............. -
-- -........ ----
-.. . _--->
................................................ .,.--
"::>
.,.--
2.
Rev. 11-11-11
HANGERS
(TYP)
\.
'1'-''1'-'
I I
I I
I I
AI
v
.....
-:'
MIN. 20"
BEFORE ELBOW
O(fP
D
~
~C ORK
DETAIL -
PADS
(TYP)
LENGTH "L"
/ / - - -~
( ( ( SLEEVE
IJ
L"
I
I
I
----,
==
0
~ \1
GUIDE BRACKET
NOTE:
CALCULATION FOR EXPANSION AND CONTRACTION SHOULD
BE BASED ON THE AVERAGE COEFFICIENT OF EXPANSION OF COPPER
WHICH IS 0.0000094 INCH PER INCH PER DEGREE F, BETWEEN
70 degrees F AND 212 degrees F.
(EXAMPLE: EXPANSION OF A 100 DEGREE F RISE FOR EACH 100 FT.
OF ANY SIZE IS 1.128 INCHES)
EXPANSION DIMENSION "L" FOR OFFSET & RETURN TO BE BASED ON
THE EXPECTED EXPANSION INCHES PER DIMENSION OF PIPE
DETAIL -
EXPANSION LOOPS
PLAN VIEW
Rev. 11-11-11
UNISTRUT SUPPORT
ALUMINUM JACKET
OVER INSULATION
REF. PIPE
UNISTRUT
PIPE CLAMP
DETAIL -
Rev. 11-11-11
REFRIGERANT PIPING
FROM OUTSIDE UNIT
OR INTERIOR BRANCH
SELECTORS
MIN. 20"
AFTER ELBOW
LONG SWEEP
ELBOW OR LONG
BEND OF SOFT
COPPER (TYP)
I-------I~~-
MIN. 20
BEFORE ELBOW
TO TYPICAL INTERIOR
TERMINAL UNIT
CAL VRV 4 OR 8
CONNECTOR "HEADER" DEVICE
TO TYPICAL INTERIOR
TERMINAL UNIT
DIAGRAM -
Rev. 11-11-11
REFRIGERANT PIPING
FROM OUTSIDE UNIT
OR INTERIOR "BS"
BRANCH SELECTORS
MIN. 20"
AFTER ELBOW
TERMINAL UNIT
MIN. 20"
TYPICAL VRV
"REFNET" DEVICE
BEFORE ELBOW
LONG SWEEP
ELBOW OR LONG
BEND OF SDFT
COPPER (TYP)
TO TYPICAL INTERIOR
TERMINAL UNIT
DIAGRAM
TO TYPICAL INTERIOR
TERMINAL UNIT
Rev. 11-11-11
,,------71
I"
1
"
/1
/
"
/
//
1
"
1
""
IL _ _ _ _ _ _
1/"
1
,<' / /
,,/
1
~
--.;t-
45 deg. MAX
-:q.
----------~
NOTE:
IN CASES WHERE PIPING/TUBING NEEDS TO DROP BELOW OBJECTS,
(BEAMS, DUCTS, CONDUITS, PIPES ETC.) PIPING SHALL HAVE LARGE RADIUS
TURNS AS INDICATED ABOVE (NO MORE THAN 45 DEGREES PER FITTING)
TO PREVENT TRAPPING OF REFRIGERANT.
DETAIL -
The following outlines the procedure for smooth processing of the installing contractors
commissioning request:
1. Contractor completes the Request for Supervised Commissioning form
2. Contractor submits the Request to Hoffman & Hoffman, Inc.
3. Supervising personnel will contact the installing contractor to schedule the
commissioning.
4. Contractor completes the Pre-Commissioning checklist and submits to the Hoffman &
Hoffman Coordinator a minimum of 48 hours prior to the scheduled commissioning.
5. The contractor, salesperson and supervising personnel meet at the jobsite on the
scheduled date to perform the Supervised Commissioning session.
6. By completing and signing the Pre-Commissioning checklist, the contractor confirms and
represents that the job is ready for commissioning. If upon arrival on the scheduled day
for the commissioning it is found that any portion of the job is not ready for
commissioning, the contractor shall be subject to additional fees.
7. The installing contractor is responsible for arranging access to the equipment on the day
of the commissioning. This includes notifying the necessary parties at the site to insure
access to all components of the system. The contractor must provide any ladders, lifts,
keys, or other devices necessary to access the equipment.
This supervision of commissioning is to offer supervision of the contractor performing
the commissioning onsite. The installing contractor must have adequate personnel
onsite at the time of the assisted commissioning. The installing contractor is responsible
for providing all service tools, test equipment, refrigerant, and other supplies necessary
to conduct the commissioning.
TEL: 866-4DAIKIN
FAX: 972-245-1038
www.daikinac.com
SRO#:___________
Contractor Information
Company Name:
City, State & Zip:
Phone/Fax #:
Contact:
Email Address:
Rep or Distributor Information (Must supply Purchase Order)
Company Name:
City, State & Zip:
Contact:
Phone:
Email Address:
Site Information:
Job Name:
Address:
City, State & Zip:
Contact:
Phone:
Equipment Information
Number of Systems to be Commissioned _______________
Note: each system will require a separate form
Request - 1-
Ver. ELEC
TEL: 866-4DAIKIN
FAX: 972-245-1038
www.daikinac.com
OUTDOOR UNIT(s)
Outdoor Serial
Numbers
Outdoor Model #
Quantity
of Indoor
Units
Quantity
of BS
Boxes
System 1
System 2
System 3
System 4
System 5
System 6
System 7
System 8
System 9
System 10
System 11
System 12
NOTE: if more than 12 Systems complete additional form
Indoor Unit
Model Number(s) and serial numbers:
QTY
Model #
Serial No.
QTY
Request - 2-
Model #
Serial No.
Ver. ELEC
TEL: 866-4DAIKIN
FAX: 972-245-1038
www.daikinac.com
Controller(s):
Quantity
Model Number
Additional Accessories
Manufacturer
Description
Model Number
Description
Status of Installation
Refrigerant Piping Completed
Electrical Wiring Completed
Drain Piping Completed
Yes
Yes
Yes
No
No
No
Please refer to the Daikin AC commissioning policy for full details regarding any fees associated with this Commission. A
commissioning date will not be scheduled until all required information is completed and submitted to Daikin AC. Within 3 business
days a Daikin representative will contact you with a date. Please note:
1.
2.
3.
4.
All equipment must be running and wiring issues identified prior to Daikin arriving onsite.
You agree that you will be responsible for any tools and Freon needed on-site.
Daikin request the system to be pressure tested to 550 PSIG for 24hrs.
Daikin request a triple evacuated to below 500 microns and must hold 500 or below for 1 hr.
5. Daikin requires a 2 wire, stranded, non-shielded, 18 gauge. This will ensure that there are no
communication issues when the system is started up.
The above must be achieved before DAIKIN arrives on-site to complete this commission. If this
is not completed when Daikin arrives you will be charged an extra fee.
Contractor Signature:
Date Submitted:
..
SRO Number:________
Request - 3-
Ver. ELEC
TEL: 866-4DAIKIN
FAX: 972-245-1038
www.daikinac.com
Commissioning
SRO#:___________
Telephone:
E-Mail:
Fax:
Job/Location Name:
Site Address:
City:
State:
Zip:
SITE CHECKLIST
1.
REFRIGERANT PIPING
Yes
(a)
(b)
Has the system piping been pressure tested and leak checked?
If the system has been pressure tested, what pressure was applied?
(c)
PSIG
(d)
HOURS
HOURS
(e)
(f)
List the total line lengths for each pipe size used?
1/4 O.D.
3/8 O.D.
1/2 O.D.
Has the additional refrigerant charge been calculated?
If charge has been calculated what is the amount?
(g)
No
LBS
OZ
Has all system piping been insulated, including RefNET and flare connections?
Checklist-1-
Ver. ELEC
TEL: 866-4DAIKIN
FAX: 972-245-1038
www.daikinac.com
ELECTRICAL CONNECTIONS
(a)
(b)
(c)
(d)
Yes
No
Yes
No
What type and gauge wire was used for control wiring?
(i.e. 18AWG stranded non-shielded)?
TYPE:
(f)
(g)
3.
GAUGE:
L2
L3
(a)
If using ducted fan coil units, has all duct work been connected?
(b)
Have the condensate drain lines been installed and was the
supplied vibration brake hose used?
(c)
(d)
(e)
4.
If using ducted fan coil units and factory installed return air filter
has been removed or if return air flow has been converted to
return air to rear of unit, is any additional air filtration being
provided?
Have Branch Selector boxes been wired for Line voltage and has
control wiring been connected?
OUTDOOR UNITS
Yes
(a)
(b)
(c)
(d)
No
I hereby certify that all items on this list have been checked, and that all information is correct.
I further verify that the job is ready for commissioning. I realize that if upon arrival to the commissioning the job is not
ready for start up, that I will be subject to additional fees as described in the Daikin Policies and Procedures Guide.
Checklist-2-
Ver. ELEC
TEL: 866-4DAIKIN
FAX: 972-245-1038
www.daikinac.com
Quali f i e d A g e n t n a m e :
i - T o u c h
C o n t r o l l e r
Basic Software ID
MAC Address:
Building Location
City, State
Building Type:
(OFC,RES, Medical, BANK, etc)
Number of
Floors
Floor Size
24VAC Power to
Controller:
Yes
No
Number of D3 Ports:
Number of Systems:
Yes
WEB OPTION
Yes
No
No
Web
Software ID:
case sensitive
NOTE: MUST provide MAC address and Basic Software ID for WEB and PPD option
Yes
No
NOTE: MUST provide MAC address and Basic Software ID for the WEB and PPD option
Brand of KW Meter:
case sensitive
Number of KW Meters:
Model of KW Meter:
B A C N E T : Yes
24VAC Power to
Controller:
IP Address:
Yes
No
No
Device Instance Number:
Allowable range: 0-4194303)
FRONT END SYSTEM
MANUFACTURER:____________
Subnet Mask:
MODEL:_____________________
L O N W O R K S : Yes
No
FRONT END SYSTEM
No
MANUFACTURER:________________
MODEL:________________
By completing these forms, you hereby certify that all items on this list have been checked, and that all information is correct. You further verify that the job is
ready for commissioning. You realize that if upon arrival to the commissioning the job is not ready for start up, that I will be subject to additional fees as described
in the Daikin Policies and Procedures Guide.
Checklist-3-
Ver. ELEC
DAIKINJlC'
absolute comfort
I hereby certify that all items on this list have been checked, and that all information is
correct.
I further verify that the job is ready for commissioning. I realize that if upon arrival to
the commissioning the job is not ready for start up, that I will be subject to additional
fees as described in the Daikin Policies and Procedures Guide.
Contractor Signature:
Date:
14