Professional Documents
Culture Documents
DIVISION OF RESPONSIBILITY
SR
NO
ELECTRICAL EQUIPMENT
Supervisory engineers
1. Commissioning team.
2. Commissioning tools.
3. Testing and commissioning
equipment.
1.Operation Manpower.
2. Start up power.
3. Statutary clearances if
required.
4. Consumables
WHEN REQUIRED
Supervisory engineers
1. Operation Manpower
2. Chemicals for operation of the
DM plant.
3. Raw water
15 days prior to hydro test of
4. Lab establishment and
boiler
testing.
5. Consumables as per list(Will
be furnished during
commisioning).
Supervisory engineers
1. Commissioning team.
2. Commissioning tools.
1. Operation Manpower.
2. Consumables.
Supervisory engineers
1. Commissioning team
2. Commissioning tools.
1. Operation Manpower.
2. Consumables.
Supervisory engineers
1. Commissioning team
2. Commissioning tools.
Supervisory engineers
1. Commissioning team
2. Commissioning tools.
1. Operation Manpower.
2. Consumables.
1. Operation Manpower
2. Statutary clearances if
required
3. Oil to be provided for trial if
applicable
4. Consumables.(Like Bed
material, Wood Logs, LDO etc)
DCS/PLC
Supervisory engineers
Supervisory engineers
1. Commissioning team
2. Commissioning tools.
1. Operation Manpower.
1. Erection team.
2. Installation of temporary fill
line and drain lines.
1. Arrangining statutory
clearances .
1. Commissioning team
2. Testing and commissioning
equipment as per list
1.Boiler hydrotest
REMARKS
Client scope
Page: Annex-I 1 of 4
Date: 20-03-2015
SR
NO
WHEN REQUIRED
Supervisory engineers
1. Commissioning team.
2. Commissioning tools &
consumables.
3. Commissiioning instruments.
1. Operation Manpower.
3 ESP commissioning
Supervisory engineers
1. Commissioning team.
2. Electrical and mechanical
commissioning crew for
transformer commissioning.
Transformer oil testing and
filtering unit and commissioning
and testing equipment
1. Operation Manpower.
2. Statutary clearances if
required.
3. Oil to be provided for trial.
4. Consumables.
Supervisory engineers
1. Commissioning team.
2. Commissioning tools.
3. Commissiioning instruments.
2. Equipment trials
REMARKS
1. Operation Manpower.
2.. Chemical lab for testing
and chemist round the clock.
10
Supervisory engineers
8. Steam Blowing
Supervisory engineers
1. Operation Manpower.
2. Fuel oil
Supervisory engineers
1. Operation manpower.
2. Fuel oil
Supervisory engineers
1. Operation manpower.
Page: Annex-I 2 of 4
Date: 20-03-2015
SR
NO
Supervisory engineers
1. Operation manpower.
2. Consumables oils and
chemicals.
WHEN REQUIRED
REMARKS
Supervisory engineers
Supervisory engineers
Supervisory engineers
Supervisory engineers
Commissioning team.
2 Equipment for switchgear
testing.
3. Oil filteration equipment&
equipment for transformer testing
Supervisory engineers
1. Commissioning team.
2. Commissioning tools.
Supervisory engineers
1. Hydrotest pump.
2. Commissioning manpower.
3. Flushing loops and temporary
drain piping
Supervisory engineers
Supervisory engineers
1 Commissioning team
2. Hydro
test pump.
Supervisory engineers
1. Commissioning team
Operation manpower
11
Supervisory engineers
1. Commissioning team.
2. Commissioning tools.
3. Commissiioning instruments.
1. Operation Manpower.
2. Fuel / &consumables.
12
VOID
NA
NA
Page: Annex-I 3 of 4
Date: 20-03-2015
SR
NO
13
14
WHEN REQUIRED
REMARKS
Supervisory engineers
2. Vacuum pulling
Supervisory engineers
Supervisory engineers
4.Generator tests
Supervisory engineers
5. Synchronising
Supervisory engineers
PG test procedure to be
submitted
1. Operation manpower.
2. Oil/Charcoal / Wood Logs for
boiler start up and Fuel for
boiler operation.
1. Operation Manpower.
1. Operation Manpower.
1. Operation Manpower.
1. Operation Manpower.
1. Operation Manpower.
2. Maintenance Manpower tools
and consumables.
3. Lubricants and chemical for
regular operation.
1) Operation Manpower
2)load availablity
3) Fuel as per contract
4) confirmation for PG test
NA
After synchronisation.
Note:
1. Service provider will send Engineers For Supervision of Erection & Commissioning when required.
2. Installation & Erection & commissioning team will comprise of commissioning Supervisor skilled and unskilled workmen as required .
3.Owner shall provide workshop facility for minor machining jobs in case required.
Page: Annex-I 4 of 4
Date: 20-03-2015