2G/3G SWAP Training Guideline

Context
1. Abbreviations
2. Requirements
2.1 Hardware Requirements
2.2 Software Requirements
2.3 Documentation Requirements
2.4 Other Requirements
2.5 GSM/UMTS Network Overview

3. Huawei System Overview


3.1 BBU & Common Boards
3.2 GSM/2G Boards
3.3 UMTS/3G Boards
3.4 Extension Boards
3.5 RRU
3.6 BTS3900 (Indoor/Outdoor)
3.7 RFU
3.8 Delta Power System
3.9 Indoor Bracket
3.10 SLPU (UELP/USLP)
3.11 Outdoor Mini Box (OMB)
3.12 Transmission Equipment
3.13 Optical Modules (SFP)

4. General SWAP Process


4.1 SWAP Process
4.2 Downtimes

5. Onsite Preparations
5.1 Enter the site via Naview
5.2 Verify DIP Switches of GTMU & WMPT
5.3 Verify Loop Connection of WMPT
5.4 Load BTS Software via USB Stick
5.5 Load NodeB Software & Configuration via USB Stick
5.6 Delta Power System Check

6. Onsite SWAP Activities


6.1 Check Transmission Status of BTS/GSM
6.2 Check Software Status of BTS/GSM
6.3 Check Transmission Status of NodeB/UMTS
Author
Markus Heiserholt

Date
09/10/2014

Page
-1-

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
2 / 73

2G/3G SWAP Training Guideline

6.4 Check Software Status of NodeB/UMTS


6.5 External Alarm Testing
6.6 Testcall Procedure
6.7 Onsite/Remote Test of Huawei System
6.8 Facc Documentation
6.9 Deinstallation
6.10 Leaving the Site via Naview

7. Other
7.1 Support Contacts
7.2 Emergency Contacts
7.3 BBU Scenarios
7.4 Troubleshooting/FAQ
7.5 EHS
7.6 AOB

Author
Markus Heiserholt

Date
09/10/2014

Page
-2-

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
3 / 73

2G/3G SWAP Training Guideline

1.Abbreviations
BBU Baseband Unit
BTS Basestation
DCDU DC Distribution Unit
FMU Fan Monitoring Unit
GSM Global System for Mobile Communications
GTMU GSM Transmission and Management Unit
HSPA High Speed Packet Access
LBBP LTE Baseband Processing Unit
LMPT LTE Main Processing and Transmission Unit
LMT Local Maintenance Terminal (for NodeB/UMTS)
LTE Long Term Evolution
MMS Multimedia Message Service
NeMo Network Modernization
NMC Network Maintenance Center
OMC Operational Maintenance Center
RFC RF Cabinet (part of Outdoor BTS)
RFU Radio Frequency Unit
RIC Remote Integration Center
RRU Remote Radio Unit
SLPU Signal Lightning Protection Unit
SMS Short Message Service
SMT Site Maintenance Terminal (for BTS/GSM)
SRAN _ Single Radio Access Network
TMC Transmission Cabinet (part of Outdoor BTS)
UBRI Universal Baseband Radio Interface Board
UEIU Universal Environment Interface Unit
UELP Universal E1/T1 Lightning Protection Unit
UMTS Universal Mobile Telecommunication System
UPEU Universal Power and Environment Interface Unit
USLP2 Universal Signal Lightning Protection Unit Type 2
UTRP Universal Transmission Processing Unit
WBBP WCDMA Baseband Processing Unit
WCDMA Wideband Code Division Multiple Access
Web-LMT Web Local Maintenance Terminal (for eNodeB/LTE)
WMPT WCDMA Main Processing and Transmission Unit

Author
Markus Heiserholt

Date
09/10/2014

Page
-3-

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
4 / 73

2G/3G SWAP Training Guideline

2.Requirements
2.1 Hardware Requirements
- 2 *USB Sticks with LEDs ( 1 USB Stick for GSM and 1 USB Stick for UMTS)
- Laptop including Windows XP/Windows 7
-different Browers like Firefox,Internet Explorer and Chrome
- Test Mobile Phone including Monitoring Software,for example Huawei U8800 (Ideos X5)
with Android 2.3

-The Testmobile phone needs to be able to lock the BCCH (GSM) and the primary scrambling
code (UMTS)
-VDF D2 2G/3G Sim Card for Voice & Data
2.2 Software Requirements
a) Correct NE Software is needed
BTS Software & SMT (actual Version BTS3000V100R015C00SPC276)
NodeB Software & LMT (actual Version NodeB V100R008C00SPC276)
NodeB Software (actual Version V100R008C00SPC276)
b) Correct Manager Software for Laptop is needed
SMT (Site Maintenance Terminal) for BTS
LMT ( Local Maintenance Terminal) for NodeB
c) Correct configuration file is needed
For GSM: The BTS configuration will be automatically loaded from the BSC once the
transmission connection is ok
For UMTS: xml based configuration file is needed for each NodeB
Author
Markus Heiserholt

Date
09/10/2014

Page
-4-

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
5 / 73

2G/3G SWAP Training Guideline

d) IP Settings for the Laptop


192.168.0.220 /255.255.255.0 for GSM
192.168.0.220 / 255.255.255.0 for UMTS
e) Software Manager Logins
SMT=> admin/hwbs@com or admin/admin
LMT=> admin/hwbs@com or admin/NodeB
f) SFTP Server Software needed (delivered from Huawei)

Make sure that the SFTP Server Symbol shows green


Username: admin
Password: admin
In case a 6 digit password is needed use admin1 as password
2.3 Documentation Requirements
Site/SWAP Solution for the site which will be swapped
SRAN Facc Guideline (VDF Checklist)
Transmissionplan for the site which will be swapped
2G/3G SWAP Training Guideline
2.4 Other Requirements
- Every SWAP Team needs to be registered to VDF NMC in order to use the Naview System.
- The Naview System is used to enter and leave a VDF Site via a registered Mobile Phone
- Call VDF NMC under +49-211-5337401 and tell them your mobile phone number and that
you are working on the VDF SRAN Project (Installation/Commissioning/Site SWAPs)
-> this needs to be done only 1 Time for every team!
Author
Markus Heiserholt

Date
09/10/2014

Page
-5-

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
6 / 73

2G/3G SWAP Training Guideline

2.5 GSM/UMST Network Overview


The BTS is the Base Transceiver Station within a GSM Network & supports the GSM Cells,
normally between 3 & 6 Cells.
The BTS & the BSC are forming the Base Station Subsystem (BSS) / GERAN which is
connected to the Network Subsystem (Core Network). The core network provides the
connection to switching centre and the Public Switched Telephone Network (PSTN)

The NodeB is the Basestation within an UMTS Network & supports the UMTS Cells,
normally between 3 & 6 Cells.
The NodeB & the RNC are forming the UMTS Terrestrial Radio Access Network (UTRAN)
which is connected to the Core Network (CN). The core network provides the connection to
switching centre and the Internet. UTRAN + CN is the Public Land Mobile Network (PLMN)

Author
Markus Heiserholt

Date
09/10/2014

Page
-6-

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
7 / 73

2G/3G SWAP Training Guideline

3. Huawei System Overview


3.1 BBU & Common Boards
BBU Case with Backplane (Height 2U),Weight <12kg

BBU Slot Assigments

BBU ESN (Electronic Serial Number)

Author
Markus Heiserholt

Date
09/10/2014

Page
-7-

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
8 / 73

2G/3G SWAP Training Guideline

FANc /Fan Unit always in Slot 16

FANc Board is always installed in Slot 16


FANc consists of 3 AVC Fans , each Fan uses 12V DC & 0,84A (~10,08W per Fan)
Controls the Fan Speed & monitors the temperature at the air inlet
Reports the status & temperature to the main controlling processing unit
UPEUc in Slot 18/19 (Unit has 2 external Alarmports to handle 8 ext. Alarms)

UPEUc Board is always installed in Slot 19


2nd UPEUc will be installed in Slot 18 if more DC Power is needed for BBU (see BBU
Layouts)
1 UPEUc provides 360W & the Power Conversion Efficiency is 96%, 2xUPEUc provide
650W
Converts -48V DC into +12V DC for all BBU Boards
Provides 2 External Alarm Ports (EXT-ALM0 & EXT-ALM1)& 2 Monitoring Ports
(MON0&MON1)
Each Alarm Port can handle 4 external alarms ( 1 UPEUc can handle 8 external Alarms)
Monitoring Ports are only used when BBU3900 has been installed into BTS Indoor/Outdoor
Cab.

Author
Markus Heiserholt

Date
09/10/2014

Page
-8-

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
9 / 73

2G/3G SWAP Training Guideline

UEIU always in Slot 18 (Unit has 2 external Alarmports to handle 8 ext. Alarms)

UEIU Board is always in Slot 18 if installed


Provides 2 External Alarm Ports (EXT-ALM0 & EXT-ALM1)& 2 Monitoring Ports
(MON0&MON1)
Each Alarm Port can handle 4 external alarms ( 1 UEIU can handle 8 external Alarms)
Monitoring Ports are only used when BBU3900 has been installed into BTS Indoor/Outdoor
Cab.
3.2 GSM/2G Boards
GTMUb Maintenance and Transmission Unit for GSM always in Slot 5&6

Function:
Controls and manages the BTS
Monitors fans and power modules
Provides transmission over 4xE1 ports and
2xFE ports FE0 (electrical) & FE1(optical)
Provides 6 CPRI ports for communication between GTMU and GSM RRUs/RFUs
Support fault management system, configuration management system,
performance management system and security management service.
Provides Ethernet Port ETH for local Commissioning

Author
Markus Heiserholt

Date
09/10/2014

Page
-9-

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
10 / 73

2G/3G SWAP Training Guideline

Dip Switches from GTMU:

Make sure that the DIP Switches S1,S2,S4,S5 are set correctly for the GTMU!
(DIP Switches are on the circuit board, 1 means ON)

3.3 UMTS/3G Boards


WMPT Maintenance and Transmission Unit for UMTS always in Slot 7

Function:
Controls and manages the NodeB
Monitors fans and power modules
Provides transmission over 4xE1 ports and 2xFE ports FE0 (electrical) & FE1(optical)
WMPT has a build-in GPS controller - GPS Antenna could be connected to Port GPS
Support fault management system, configuration management system,
performance management system and security management service.
Provides Ethernet Port ETH for local Commissioning

Author
Markus Heiserholt

Date
09/10/2014

Page
- 10 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
11 / 73

2G/3G SWAP Training Guideline

Dip Switches from WMPT:

Make sure that the DIP Switches SW1&SW2 are set correctly for the WMPT!
(DIP Switches are on the circuit board, 1 means ON)

WBBPd2 Baseband Board with 6 CPRI Ports for UMTS

Main WBBP Board is always in BBU slot 3, other slots will be used for capacity extension
Function:
Provides 6 CPRI Ports for communication between WMPT & UMTS RRUs/RFUs
Provides Baseband Capacity (Channel Elements) for Uplink/Downlink
1 WBBP Board has 383 Channel Elements

3.4 Extension Boards


UBRI Fiber Port Extension Unit in case more than 6 RRUs need to be connected to 1 BBU.
1 UBRI Board can only support 1 Technology, if more than 6 RRUs are needed for GSM and
more than 6 RRUs for UMTS, 2 UBRI Boards are needed.
UBRI will be installed in slot 2

Author
Markus Heiserholt

Date
09/10/2014

Page
- 11 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
12 / 73

2G/3G SWAP Training Guideline

UTRP Extension Transmission Unit with additional 8 E1s Unit needed if site has more
than 4 E1s

E1 Cable Rules:

Site has 1-4 E1s => E1 No. 1 - E1 No. 4 connectet to WMPT


Site has 5-8 E1s => E1 No.1 - E1 No. 8 connected to UTRP
Site has 9 E1s => E1 No.1 - E1 No. 6 connected to UTRP
E1 No.7 E1 No.9 connected to WMPT
Site has 10 E1s => E1 No.1 - E1 No.7 connected to UTRP
E1 No.8 E1 No. 10 connected to WMPT
Site has 11 E1s => E1 No.1 - E1 No.7 connected to UTRP
E1 No.8 E1 No.11 connected to WMPT
Site has 12 E1s => E1 No.1 - E1 No. 8 connected toUTRP
E1 No.9 E1 No.12 connected to WMPT

3.5 RRU
There are different types of RRUs:

GSM900 > RRU3928 //please check the label if you see 900
GSM1800 -> RRU3928 //please check the label if you see 1800
UMTS2100 > RRU3828 //please check the label if you see 2100

Author
Markus Heiserholt

Date
09/10/2014

Page
- 12 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
13 / 73

2G/3G SWAP Training Guideline

3.6 BTS3900 (Indoor/Outdoor)


a)BTS3900 Ver.c (Indoor Macro BTS)
Supports up to 6 MRFUds
Total Power Consumption 5700W
BBU Power Consumption 650W
3 MRFUd *(2*80W)
3 WRFUd *(2*60W)
Consists of BBU,Fan Tray,DCDU..etc
Dimensions

Author
Markus Heiserholt

Date
09/10/2014

Page
- 13 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
14 / 73

2G/3G SWAP Training Guideline

Cabinet Overview ( EMUA is optional and not used in VDF Project)

Author
Markus Heiserholt

Date
09/10/2014

Page
- 14 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
15 / 73

2G/3G SWAP Training Guideline

RFU Slot Positions

Monitoring System Indoor BTS

Author
Markus Heiserholt

Date
09/10/2014

Page
- 15 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
16 / 73

2G/3G SWAP Training Guideline

Power Cable Connection Indoor BTS

Example:

Author
Markus Heiserholt

Date
09/10/2014

Page
- 16 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
17 / 73

2G/3G SWAP Training Guideline

DCDU11A Overview

Supply DC power to all modules in the cabinet (UPEU, MRFU, FAN)


Support 10 x -48 V DC outputs of 25 A
Can be used also as power supply for external equipment
FAN03B /FMU

Author
Markus Heiserholt

Date
09/10/2014

Page
- 17 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
18 / 73

2G/3G SWAP Training Guideline

Position: Under RFU Slot


Function:
Provide forced ventilation
Provide heat dissipation
Monitor the temperature
Support fan speed adjustment or controlled by the BBU

b)BTS3900A Ver. C (Outdoor Macro BTS) RFC + TMC

MBTS Outdoor Cabinet needs DC power


Outdoor Cabinet consists of TMC11H & RF Cabinet
BBU3900 is installed in TMC11H, RFUs are installed in RF Cabinet
Supports up to 6 RFUs
Total Power Consumption is xxxW
BBU3900 Power Consumption is 650W
3x MRUFd x (2x80W) => 3x 160W = 480W

Author
Markus Heiserholt

Date
09/10/2014

Page
- 18 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
19 / 73

2G/3G SWAP Training Guideline

RFU Slot Position:

Author
Markus Heiserholt

Date
09/10/2014

Page
- 19 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
20 / 73

2G/3G SWAP Training Guideline

Outdoor RF Cabinet Function & Specification (RFC)

Outdoor Transmission Cabinet Function & Specification (TMC)

Author
Markus Heiserholt

Date
09/10/2014

Page
- 20 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
21 / 73

2G/3G SWAP Training Guideline

Monitoring System Outdoor BTS

Outdoor BTS View

Author
Markus Heiserholt

Date
09/10/2014

Page
- 21 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
22 / 73

2G/3G SWAP Training Guideline

Power Cable Connection Outdoor BTS

FAN02B / TCU (Temperature Control Unit)

Author
Markus Heiserholt

Date
09/10/2014

Page
- 22 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
23 / 73

2G/3G SWAP Training Guideline

Heater

FAN01B / FMU (Fan Monitoring Unit)

Author
Markus Heiserholt

Date
09/10/2014

Page
- 23 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
24 / 73

2G/3G SWAP Training Guideline

3.7 RFU
a) MRFUd for GSM900 & GSM1800
Each MRFUd supports up to 8 TRX
Freq Band 900MHz -> RX Freq Band 880 -915 TX Freq Band 925-960
Freq Band 900MHz -> RX Freq Band 890 -915 TX Freq Band 935-960
Freq Band 1800MHz -> RX Freq Band 1710 -1785 TX Freq Band 1805-1880

b) WRFUd for UMTS2100


Each MRFUd supports up to 6 TRX (Non-MIMO) or 4 TRX (MIMO)
Freq Band 2100MHz -> RX Freq Band 1920 -1980 TX Freq Band 2110-2170
c) MRFU Slot Position

Author
Markus Heiserholt

Date
09/10/2014

Page
- 24 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
25 / 73

2G/3G SWAP Training Guideline

d) Example: 900/1800 MRFU connection to GTMU

3.8 Delta Power System


Delta Cabinet Outdoor Type NMC M2,M3, M4 SRAN

Author
Markus Heiserholt

Date
09/10/2014

Page
- 25 -

Huawei TECHNOLOGIES
NIS Department
Title:

Author
Markus Heiserholt

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
26 / 73

2G/3G SWAP Training Guideline

Date
09/10/2014

Page
- 26 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
27 / 73

2G/3G SWAP Training Guideline

Delta Cabinet Indoor

Author
Markus Heiserholt

Date
09/10/2014

Page
- 27 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
28 / 73

2G/3G SWAP Training Guideline

Rack Layout (should be done before/after swap and it is part of the Acceptance
Documentation) - Example

Author
Markus Heiserholt

Date
09/10/2014

Page
- 28 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
29 / 73

2G/3G SWAP Training Guideline

3.9 Indoor Bracket

Installation Scenarios

3.10 SLPU (UELP/USLP)


Author
Markus Heiserholt

Date
09/10/2014

Page
- 29 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
30 / 73

2G/3G SWAP Training Guideline

SLPU (1U Height)

SLPU Slot Assignments

UELP Protection Unit for E1 Cable (only for outdoor) will be installed in the SLPU

Dip Switch of UELP

USLP2 Protection Unit for external alarm cables (only for Outdoor) slot 2&3
Author
Markus Heiserholt

Date
09/10/2014

Page
- 30 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
31 / 73

2G/3G SWAP Training Guideline

Input/Output Ports of USLP2

Common SLPU Configurations


Author
Markus Heiserholt

Date
09/10/2014

Page
- 31 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
32 / 73

2G/3G SWAP Training Guideline

3.11 Outdoor Mini Box (OMB)


The Outdoor Mini Box is a 4U outdoor BBU Subrack with the BBU and an AC/DC Power
equipment (AC Power Input needed). 1 OMB can only provide power for 1 RRU.

3.12 Transmission Equipment


Author
Markus Heiserholt

Date
09/10/2014

Page
- 32 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
33 / 73

2G/3G SWAP Training Guideline

The following Transmission Equipment can be found in the NeMo Project:


a)DF001 DC101 PIX-Distributor/Shelf with 56 Cards

PIX-Plus Distributors will be wrapped in the lower area. The Upper part are reserved for
patching.

Author
Markus Heiserholt

Date
09/10/2014

Page
- 33 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
34 / 73

2G/3G SWAP Training Guideline

The layout will come from VDF and should be available before the SWAP will start.
Make sure that the connection between BBU3900 and the Pix Verteiler/Distributor has been
made accordingly.
b) Huawei Microwave Equipment - RTN

The following RTN Modules are being used in the VDF Project:
RTN910 + RTN950 + RTN980
The E1 connections will be realized via the boards SP3S(16xE1) or the SP3D (32xE1).
For the Ethernet connections in case of IP RAN, the LAN connection will be realized via the
EM4F/EM6F board.
In case of an STM1 connection, the board SL1D will be used.

Pin Assignments of E1s for 120ohm:


Author
Markus Heiserholt

Date
09/10/2014

Page
- 34 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
35 / 73

2G/3G SWAP Training Guideline

c)Ericsson Minilinks Pinlayouts and different Types will be distributed later on

In case of existing Ericsson transmission equipment ( Huawei Microwave not available yet),
we could use a special solution of a Krone Block:
Author
Markus Heiserholt

Date
09/10/2014

Page
- 35 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
36 / 73

2G/3G SWAP Training Guideline

Please use the external document E1 Transmisssion via Krone Blocks as reference.
3.13 Optical Modules (SFP)
Optical Modules will be either used to connect the fiber cable between BBU and RRU or for
connecting the transmission fiber cable between BBU and RTN (Microwave).
For the RRU connection we will always use Single Mode (SM/Blue) for the fiber connection
and for the fiber transmission we will use either Single Mode (SM) or Multi Mode
(MM/Black) depending on the Region/VDF.

4. General SWAP Process


Author
Markus Heiserholt

Date
09/10/2014

Page
- 36 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
37 / 73

2G/3G SWAP Training Guideline

4.1 SWAP Process

SWAP_Workflow.xls swap_operation_co swap_operation_ho


x
ld_v1.2.png
t_v1.2.png

4.2 Downtimes

Preinstall as much as possible!!


a) It is important to inform the RIC in realtime when the downtime starts and stops!!!
b) Important Timeframe is when the last sector has been blocked and the first sector is
on air -> please report these times also to the RIC
c) Any other site issues should be reported in a very accurate way to the RIC.

5. Onsite Preparations
5.1 Enter the site via Naview
For example you want to enter site MXB007,so you have to sent an SMS to +49-172-5289612
with the following text:
naview e mxb007
Now you have to wait for the answer. A successful message should be:
Anmeldung an mxb007 OK
If you do not get a successful message please call the VDF NMC: +49-211-5337401
5.2 Verify DIP Switches of GTMU & WMPT

Author
Markus Heiserholt

Date
09/10/2014

Page
- 37 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
38 / 73

2G/3G SWAP Training Guideline

Make sure that the DIP Switches are set correctly for the GTMU (DIP Switches are on
the circuit board, 1 means ON):

Make sure that the DIP Switches are set correctly for the WMPT (DIP Switches are on
the circuit board, 1 means ON):
Author
Markus Heiserholt

Date
09/10/2014

Page
- 38 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
39 / 73

2G/3G SWAP Training Guideline

5.3 Verify Loop Connection for WMPT


Optical Module needs to be inserted in FE1 port and 1 fiber cable will be used for the loop.
1.25G 1310 NM SFP
The O&M Connection will not work without this loop!!!

5.4 Load BTS Software via USB Stick or Laptop


Author
Markus Heiserholt

Date
09/10/2014

Page
- 39 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
40 / 73

2G/3G SWAP Training Guideline

Prepare the GSM USB Stick and copy the software to the right folder:

Plug in USB Stick with the correct BTS Software Version to the USB port of the GTMU but
make sure that the fiber cables from RRUs are connected to the CPRI Ports of the GTMU.

When USB Stick has been inserted, the Software will be automatically loaded to the Boards
and the start configuration File. The RUN LED will blink for 0.125s and go off for 0.125s.
It will take approximately 25-30 Minutes to finish the load.

5.5 Load NodeB Software & Configuration via USB Stick or Laptop
Prepare the UMTS USB Stick and copy the software & the configuration file (configuration
file name has to be NodeBCfg.xml) to the right folder:

Please make a right-click on the NodeBCfg.xml file and select Open. Now search for the
string SITE and check if the STNAME is for the correct site!

Author
Markus Heiserholt

Date
09/10/2014

Page
- 40 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
41 / 73

2G/3G SWAP Training Guideline

Plug in USB Stick with the correct NodeB Software Version & the correct configuration file
to the USB port of the WMPT but make sure that the fiber cables from RRUs are connected to
the CPRI Ports of the WBBP.

When USB Stick has been inserted, the Software will be automatically loaded to the Boards
and the start configuration File. The RUN LED will blink for 0.125s and go off for 0.125s.
It will take approximately 25-30 Minutes to finish the load.
5.6 Delta Power System Check
Please use the onsite Delta Manual in case of:
-Adding additional Rectifiers , please change the number of rectifiers in the Controller of the
Delta Power System
-Check Battery Voltage when adding Battery Strings
- Check that there are no active alarms at the Delta Power Systems

Author
Markus Heiserholt

Date
09/10/2014

Page
- 41 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
42 / 73

2G/3G SWAP Training Guideline

6. Onsite SWAP Activities


6.1 Check Transmission Status of BTS/GSM
Maximum 4 E1 s can be connected to the GTMU Board and therefore the GTMU has 4 LEDs
(LIU0-LIU3) for each E1 on the right upper corner which are either ON or OFF.
ON means -> NO TRANSMISSION
OFF means -> TRANSMISSION OK
In case more than 4 E1s need to be connected an additional board (UTRP) needs to be
inserted to the BBU.

6.2 Check Software Status of BTS/GSM


In case the BTS software needs to be verified , you need to use the Site Maintenance Terminal
(SMT) .
a)Change the IP settings of the Laptop to 192.168.0.220 with Subnet Mask 255.255.255.0

Author
Markus Heiserholt

Date
09/10/2014

Page
- 42 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
43 / 73

2G/3G SWAP Training Guideline

b) Connect Ethernet Cable to ETH Port of GTMU Board

c) Start SMT by double-click on btsm

d)Type in User Name (admin) and Password (admin) The default IP address for the BTS is
192.168.0.72 ...if it does not work use new Name(admin) and new Password(/hwbs@com)

e) Select Board on the left site and click on Board Management

Author
Markus Heiserholt

Date
09/10/2014

Page
- 43 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
44 / 73

2G/3G SWAP Training Guideline

f) You should see the main boards of the BBU (at least the GTMU).Right-click on the GTMU
Symbol and choose Board Information.

g) The correct SW Version can be seen (actual SW Version is V100R015C00SPC276)

h) Click OK. Doubleclick on GTMU and the RRU Window opens. Selet the
MRRU ,right-click on it and choose Board Information.
Author
Markus Heiserholt

Date
09/10/2014

Page
- 44 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
45 / 73

2G/3G SWAP Training Guideline

i) Check if the RRU SW Version is correct (actual Version is V100R015C00SPC276). Please


also check all other RRUs for the correct SW Version. Inform the RIC immediately if the SW
Versions of GTMU & RRUs are different!

6.3 Check Transmission Status of NodeB/UMTS


Unfortunately the WMPT Board does not have any LEDs for indicating if the transmission is
ok or not. For checking the E1 Status you need to use the Local Maintenance Terminal
(LMT).
a) Change IP Settings of Laptop to 192.168.0.220 with Subnet Mask 255.255.255.0

Author
Markus Heiserholt

Date
09/10/2014

Page
- 45 -

Huawei TECHNOLOGIES
NIS Department

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
46 / 73

2G/3G SWAP Training Guideline

Title:

b) Connect to NodeB(If WMPT)


1) Connect Ethernet Cable to ETH Port of WMPT

2) Double-click on Local Maintenance Terminal Icon

3) Type in User (admin) and Password (NodeB) or new Password (hwbs@com).


Make sure that you see 192.168.0.49 in the Office field.(if not then you need to
click on the ... and add the IP 192.168.0.49). Click Login.

c) Connect to NodeB(If UMPT)


1) Connecting PC to UMPT board with ETH_to_USB port

Author
Markus Heiserholt

Date
09/10/2014

Page
- 46 -

Huawei TECHNOLOGIES
NIS Department

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
47 / 73

2G/3G SWAP Training Guideline

Title:

2) Start the IE browser, enter the IP address(192.168.0.49) of the base station in the
address box, and click Enter to log in to the WebLMT
3) Login with user name and password:
User name of LMT
Password
The default local maintenance
IP

admin
hwbs@com
192.168.0.49

d) LST SITE:,
If Not you need to download the config file via LMT software
e) Run the MML Command DSP E1T1:;
Author
Markus Heiserholt

Date
09/10/2014

Page
- 47 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
48 / 73

2G/3G SWAP Training Guideline

All configured E1s should show Available for the Link Running Status
f) Check the IP transmission with MML Command DSP ARP:;.

6.4 Check Software Status of NodeB/UMTS


a) Run MML command LST VER:;

b) Run MML command LST SOFTWARE:; .Inform the RIC immediately if the SW
Version is different.

Author
Markus Heiserholt

Date
09/10/2014

Page
- 48 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
49 / 73

2G/3G SWAP Training Guideline

6.5 External Alarm Testing


a) General Rules:
Site has only GSM : ext. Alarms run over GSM
Site has only UMTS : ext. Alarms run over UMTS
Site has LTE&GSM: ext. Alarms run over GSM
Site has LTE&UMTS: ext. Alarms run over LTE
Site has only GSM&UMTS: ext. Alarms run over GSM
Site has LTE&GSM&UMTS: ext. Alarms run over GSM
b) VDF Alarm Terminal X6

Author
Markus Heiserholt

Date
09/10/2014

Page
- 49 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
50 / 73

2G/3G SWAP Training Guideline

c) Differencies between Outdoor & Indoor:


The following external alarms have been defined for VDF D2 (16 Alarms over the
UPEUc/UEIU and 1 Alarm over the RRU from first sector):

It could also be that a 2nd UPEUc is installed in Slot 18, but the Ports will be the same as for
the UEIU.

Author
Markus Heiserholt

Date
09/10/2014

Page
- 50 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
51 / 73

2G/3G SWAP Training Guideline

d) External alarm connection via RRU (normally the RRU from 1st Sector):

e) external Alarm connection via SLPU (for Delta Outdoor Sites)

Author
Markus Heiserholt

Date
09/10/2014

Page
- 51 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
52 / 73

2G/3G SWAP Training Guideline

f) Huawei Alarmcable Colorcode

Please test/check the external alarms accordingly to the general rules:


g) Check the alarms on the BTS/GSM via SMT (Connection Procedure in Chapter 7.3)
Active Alarms (only Alarm IDs, not the alarm text) can be seen on the bottom of the SMT

h) Check the alarms on the NodeB/UMTS via LMT (Connection Procedure in Chapter 7.3)
Run MML command LST ALMAF:;.

Author
Markus Heiserholt

Date
09/10/2014

Page
- 52 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
53 / 73

2G/3G SWAP Training Guideline

6.6 Testcall Procedure


Testcall Scenarios are based on the FAcc Procedure Checklist Huawei SRAN Document from
VDF D2.
Testcall Scenarien basieren auf dem FAcc Prozedur Checklist Huawei SRAN Dokument von
VDF D2.
Please ask the RIC for the BCCH&Primary Scrambling Code(PSC)/Sector and the
Azimuths for the GSM900/1800 & UMTS2100.
In order to avoid crossed feeders partner needs to check the BCCH&PSC/Azimuth
against the site build and the azimuth values from the sitesheet. If something is different
please inform the RIC immediately.
Please use a compass or GPS device, identify the azimuth of each sector and conduct a
static testcall in each sector roughly 50-100meters away from the site and confirm :
-Sector orientation is correct
-Correct BCCH/PSC is radiating from the correct Cell
-All Feeders are correctly installed and labeled
Always inform the RIC if something is not clear.
Bitte beim RIC die BCCH&Primren Scrambling Code(PSC)/Sektor und Azimuths fr
GSM900/1800&UMTS2100 anfragen.
Um Crossed Feeder zu vermeiden, mu der Partner die BCCH&PSC/Sektor mit dem
Sitebuild und den Siteunterlagen vergleichen. Sollte etwas anders sein, bitte sofort dem
RIC Bescheid geben.
Bitte einen Kompass oder GPS Device benutzen, den Azimuth von jedem Sektor
bestimmen und einen statischen Testcall in jedem Sektor in einer Entfernung von 50-100
Metern von der Site durchfhren und folgendes besttigen:
-Sektor Ausrichtung ist korrekt
-Die Zellen haben jeweils den richtigen BCCH/PSC
-Alle Feeder sind richtig installiert und gekennzeichnet
Bei Unklarheiten immer den RIC informieren.

Author
Markus Heiserholt

Date
09/10/2014

Page
- 53 -

Huawei TECHNOLOGIES
NIS Department

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
54 / 73

2G/3G SWAP Training Guideline

Title:

For Speedtests you can use the following webpage & choose a 10-20MB file for downloading:
Fr Speedtests kann die folgende Webseite benutzt werden & ein 10-20MB groes File kann
dort zum Download ausgewhlt werden:
http://www.thinkbroadband.com/download.html

a) GSM900
For GSM900 the following calls need to be done one time per site only:
Folgende Gesprche mssen einmalig fr GSM 900 durchgefhrt werden:

Author
Markus Heiserholt

Date
09/10/2014

Page
- 54 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
55 / 73

2G/3G SWAP Training Guideline

Following Testcalls need to be done per sector (Emergency Call only 1 Time per Site):
Folgende Testgesprche mssen fr jeden Sektor erfolgen (Notruf nur einmal pro Site):

b) GSM1800
For GSM1800 the following calls need to be done one time per site only:
Folgende Gesprche mssen einmalig fr GSM 1800 durchgefhrt werden:

Following Testcalls need to be done per sector (Emergency Call has been tested with
GSM900):
Folgende Testgesprche mssen fr jeden Sektor erfolgen (Notruf wurde schon mit GSM900
getestet):

Author
Markus Heiserholt

Date
09/10/2014

Page
- 55 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
56 / 73

2G/3G SWAP Training Guideline

c) UMTS2100
For UMTS2100 the following calls need to be done one time per site only:
Folgende Gesprche mssen einmalig fr UMTS2100 durchgefhrt werden:

Following Testcalls need to be done per sector:


Folgende Testgesprche mssen fr jeden Sektor erfolgen:

d) For Emergency Call/Notruf -> Text in Deutsch vorbereiten & dann mu der Text dem
Notruf Operator vorgelesen werden/Text needs to be prepared in german language and then
read to the emergency operator

Beispiel/Example:
Hallo, ich heie ..... und fhre einen Testanruf im Auftrag von Vodafone D2 durch. Mein
Standort ist der Ort 41517 G, Street XXXX . Bin ich mit der richtigen Leitzentrale/Leitstelle
verbunden? Bitte geben Sie mir den Leitstellen Standort durch.
6.7 Onsite/Remote Test of Huawei System
- include parts of FAcc Handbook from VDF- TBD

Author
Markus Heiserholt

Date
09/10/2014

Page
- 56 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
57 / 73

2G/3G SWAP Training Guideline

6.8 Facc Documentation


Please have a look at the example of an FAcc document. You only need to fill out the
technology that you have swapped/installed on the site. For example if you only swap GSM
900 and GSM 1800, then you only need to fill out the parts where GSM 900 &1800 is
mentioned as well as the common parts. For already existing technologies like LTE , you do
not need to fill out anything.

6.9 Deinstallation
Not 100% clarified yet, still under discussion with VDF but probably a higher percent of sites
need to be disassembled and the hardware needs to be returned to VDF.
6.10 Leaving the Site via Naview
For example you want to leave the site MXB007,so you have to sent an SMS to +49-1725289612 with the following text:
naview l mxb007
Now you have to wait for the answer. The successful message should be:
Abmeldung OK
If you write naview l mxb007 d , you will get the info which alarms are active if the
successful message does not come.
If you do not get a successful message please call the VDF NMC: +49-211-5337401
You also need to lock out of the Naview system after leaving the site by sending an SMS to
+49-172-5289612 with the following text:
naview ld
Now you have to wait for the answer. The successful message should be:
Abmeldung vom Dienst erfolgreich
Under certain circumstances if you enter a site somewhere in the afternoon/evening and you
do not lock out of the system, it can happen that you might be blocked to enter another site on
the next day. Therefore it is mandatory to do the lockout every day.

Author
Markus Heiserholt

Date
09/10/2014

Page
- 57 -

Huawei TECHNOLOGIES
NIS Department

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
58 / 73

2G/3G SWAP Training Guideline

Title:
7. Other
7.1 Support Contacts

***Regional Contacts***

***Central Contacts***
2G/3G Swap

Central Contact List

Region
Central

Contact

Responsibility

Telephone

Email

Sadik Ghalib

Swap Project Manager

0172-8808999

Sadik.Ghalib@huawei.com

ChenHaitao

Technical Director

0172-3093828

haitao.chen@huawei.com

XuXiaofeng

OSS/M2000 Support

0160-98980247

xu.xiaofeng@huawei.com

Marcus Lindemans

Site Solutions Lead

0176-10084297

M.Lindemans@huawei.com

Markus Heiserholt

Technical Support Lead

0176-10151566

markus.heiserholt@huawei.com

HuangYujian

2G/3G Technical Expert

0162-2047580

huangyujian@huawei.com

GongYulong

2G/3G Technical Expert

0176-10259492

gongyulong@huawei.com

Mihai Ciprian Anghel

Datafill & Configuration

0162-6652789

Mihai.A@huawei.com

Author
Markus Heiserholt

Date
09/10/2014

Page
- 58 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
59 / 73

2G/3G SWAP Training Guideline

7.2 Emergency Contacts


VDF NMC 24/7: +49-211-5337401
7.3 BBU Scenarios

Author
Markus Heiserholt

Date
09/10/2014

Page
- 59 -

Huawei TECHNOLOGIES
NIS Department
Title:

Author
Markus Heiserholt

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
60 / 73

2G/3G SWAP Training Guideline

Date
09/10/2014

Page
- 60 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
61 / 73

2G/3G SWAP Training Guideline

7.4 Troubleshooting/FAQ
a) How to connect to the eNodeB/LTE via WebLMT?
Change the IP settings of Laptop to 192.168.0.220 with Subnet Mask 255.255.255.0

Connect Ethernet Cable to eNodeB ETH Port of LMPT Board

Author
Markus Heiserholt

Date
09/10/2014

Page
- 61 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
62 / 73

2G/3G SWAP Training Guideline

Start Web LMT by opening Internet Explorer and type in 192.168.0.49 to get the Login
Page. Username: admin // Password: hwbs@com Type also the Verify Code which is
displayed on the start page

WebLMT Overview

Author
Markus Heiserholt

Date
09/10/2014

Page
- 62 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
63 / 73

2G/3G SWAP Training Guideline

b) How to connect to the BTS/GSM via SMT?


Change the IP settings of the Laptop to 192.168.0.220 with Subnet Mask 255.255.255.0

Connect Ethernet Cable to ETH Port of GTMU Board

Start SMT by double-click on btsm

Type in User Name (admin) and Password (hwbs@com) The default IP address for the BTS
is 192.168.0.72

Author
Markus Heiserholt

Date
09/10/2014

Page
- 63 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
64 / 73

2G/3G SWAP Training Guideline

SMT Overview

c) How to connect to the NodeB/UMTS via LMT?


Change IP Settings of Laptop to 192.168.0.220 with Subnet Mask 255.255.255.0
Connect Ethernet Cable to ETH Port of WMPT

Author
Markus Heiserholt

Date
09/10/2014

Page
- 64 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
65 / 73

2G/3G SWAP Training Guideline

Double-click on Local Maintenance Terminal Icon

Type in User (admin) and Password (NodeB) or (hwbs@com). Make sure that you see
192.168.0.49 in the Office field.(if not then you need to click on the ... and add the IP
192.168.0.49). Click Login.

LMT Overview

Author
Markus Heiserholt

Date
09/10/2014

Page
- 65 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
66 / 73

2G/3G SWAP Training Guideline

d) Load BTS/GSM Software via SMT


TBD

e) Load NodeB/UMTS Software via LMT


Connect to NodeB via LMT and download the correct Software Package with the command:

DLD SOFTWARE

FTP Server IP (laptop IP) : 192.168.0.220


User/Password: admin
FTP Server Directory: Dircetory where the following software has been stored:

Download File Flag: All File


Download Config Flag: No

After the download has finished, activate the NodeB Software with the command :
ACT SOFTWARE

Verify the Software Version with the command: LST SOFTWARE:;


Author
Markus Heiserholt

Date
09/10/2014

Page
- 66 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
67 / 73

2G/3G SWAP Training Guideline

f) Load and activate the configuration file for the NodeB/UMTS via LMT
Download the correct Configuration File to the NodeB with the following MML command :
DLD CFGFILE

Make sure to choose the correct config file for the right site
FTP Server IP (laptop IP) : 192.168.0.220
User/Password: admin
Server Path: Dircetory where the config file has been stored
Source File Name: Only needed if more than 1 config file is in the same directory
Activate the Configuration file with the following MML command : SET CFGFILEENB

g) Transmission Issues for GSM


Check LIU LED of GTMU. If it is off, E1 transmission is ok but the pair could be twisted.
Author
Markus Heiserholt

Date
09/10/2014

Page
- 67 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
68 / 73

2G/3G SWAP Training Guideline

Set a physical loop for the E1 which is unavailable before the PIX Verteiler/Distributor as
below:

If the E1 status is available after the loop, please reconnect E1 cables between GTMU and
PIX Verteiler/Distributor.
Set a physical loop for the E1 which is unavailable after the PIX Verteiler/Distributor as
below:

If the E1 status is available after the loop, Vodafone should check the connections of the PIX
Verteiler/Distributor.
Vodafone does a soft loop from RTN to BSC.
h) Transmission Issues for UMTS

Author
Markus Heiserholt

Date
09/10/2014

Page
- 68 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
69 / 73

2G/3G SWAP Training Guideline

Reconnect the not available E1 cables between WMPT and Pix Verteiler/Distributor

Set a physical loop for the E1 which is unavailable before the PIX Verteiler/Distributor as
below:

Set a physical loop for the E1 which is unavailable after the PIX Verteiler/Distributor as
below:

Vodafone does a soft loop from RTN to RNC.

i) RET Connection Problems


Confirm if the RET is connected
Author
Markus Heiserholt

Date
09/10/2014

Page
- 69 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
70 / 73

2G/3G SWAP Training Guideline

Confirm whether there is any other equipment between RET and RRU, such as Bias T or
TMA.

Reconnect the cables and equipments between RET and RRU. Call the RIC to verify if the
RET connection is working correctly.
Author
Markus Heiserholt

Date
09/10/2014

Page
- 70 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
71 / 73

2G/3G SWAP Training Guideline

j) Check that the SFP Modules (Optical Modules) of RRUs/RFUS and WMPT/GTMU are
matching
k) Verify RRU Type for UMTS by using MML commands
DSP BRDMFRINFO: CN=0, SRN=100, SN=0;
DSP BRDMFRINFO: CN=0, SRN=101, SN=0;
DSP BRDMFRINFO: CN=0, SRN=102, SN=0;

The correct Type is RRU3828


l) If needed run the Error Logfile Collection Script for the NodeB and sent the Logfile to
Huawei

7.5 EHS (Environmental Health & Safety)


All valid EHS regulations and rules have to be followed in the Vodafone Germany Project
Author
Markus Heiserholt

Date
09/10/2014

Page
- 71 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
72 / 73

2G/3G SWAP Training Guideline

There are no exceptions even if somebody will verbally approve it


a) Do not bypass any kind of fuses

b) Use the correct tools when working on electrical equipment


If not sure which tools can be used, please ask your supervisor or Huawei EHS Manager
c) Use the 5 Security Rules when working on electrical equipment- work on energized parts is
forbidden
*De-energise*
*Secure against restarting*
*Unstressedness determine*
*Ground and short circuit*
*Neighbouring energized parts cover or provide with gates*
More details can be found under: http://www.economypoint.org/t/the-five-safety-rules.html
In Germany, only qualified electricians are authorized to establish,change or repair electrical
systems (Elektrofachkraft). see DIN VDE 1000-10

7.6 AOB

Author
Markus Heiserholt

Date
09/10/2014

Page
- 72 -

Huawei TECHNOLOGIES
NIS Department
Title:

Technical Procedure

Version: 2.1
Date :
22.09.2014
Page
73 / 73

2G/3G SWAP Training Guideline

Please feel free to sent your comments,suggestions or concerns regarding this document. If
needed we will update this document accordingly to the SRAN/NeMo requirements and
onsite experiencies during the Site SWAPs.

Author
Markus Heiserholt

Date
09/10/2014