DOCUMENT NO.
: KP-00+++-CY712-B7201
TITLE
TOTAL 5 PAGES
(Including Cover)
Purpose
For Information
For Review
For Approval
For Construction
11.08.2015
Rev.
No.
DATE
As-Built
For Review
PREPARED
DESCRIPTION
CHECKED
REVIEWED
APPROVED
Owner
POSCO ENGINEERING
& CONSTRUCTION CO., LTD.
Main Subcontractor
Doc. No
KP-00+++-CY712-B7201
Rev. No.
Page
2 of 5
Contents
1. PURPOSE...
2. SCOPE..
3. RESPONSIBILITIES
4. PROCEDURES.......
5. ACCEPTANCE CRITERIA
6. REFERENCES
Doc. No
KP-00+++-CY712-B7201
Rev. No.
Page
3 of 5
1. PURPOSE
The purpose of this method statement is to outline the sequences&methods of works
intended to be used for the Cable Conduit & Tray Installation.
2. SCOPE
This procedure is applicable to the KHABAT Project.Also including to the cable tray
installation according to the agreement.
3. RESPONSIBILITIES
Participate in and provide input to Safety Task Analysis Risk Reduction Talk
(START)/Job Hazard Analysis. Provide HSE coverage for Commissioning activities and
walk downs.
Cable tray supervisor shall be ensuring that work area facilities are safe prior to cable
tray work activities.
Personel Protection Equipment have to be used by workers
Our staff has the responsibility to check if workers are wearing the proper PPE at site.
If a worker is not working proper to the HSE rules; supervisor will stop him.
Related Personnel
Project Manager; directs and coordinates the work execution and the administration of
the worksso as to ensure to compliance with the established schedule ,budgets and quality
requirements.
Construction Manager, manage the activity of construction personnel ,to ensure that
the construction and installation work is in accordance with the established construction
schedule .
QC Department;responsible controlling and directing the activities complying with the
quality requirements given in the references and reports to the Project Manager.
Administering and approving project inspection and test plan.
Reporting quality problems to the Project Manager.
4. PROCEDURES
NOTE: The vendors instruction manual takes precedence over this procedure in the
event of conflicts. Detailed equipment installation procedures and parameters shall be
according to the vendors manuals.
Doc. No
KP-00+++-CY712-B7201
Rev. No.
Page
4 of 5
Doc. No
KP-00+++-CY712-B7201
Rev. No.
Page
5 of 5
5. ACCEPTANCE CRITERIA
Installation of cable conduit & tray installation shall be within project design and vendor
requirements and tolerances.
6. REFERENCES