You are on page 1of 21

8/23/2015

Project Cost Management

7.4 COST CONTROL

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

7.4 Control Costs


Control Costs is the process of monitoring the status of
the project to update the project costs and managing
changes to the cost baseline. *
The key benefit of this process is that it provides the
means to recognize variance from the plan in order to
take corrective action and minimize risk. *

* These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK Guide) - Fifth Edition, Project Management Institute, Inc., 2013.

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

8/23/2015

7.4 Control Costs

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK Guide) - Fifth Edition, Project Management Institute, Inc., 2013, Figure 7-10, Page 215

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

Control Costs: Inputs


1.
2.
3.
4.

Project Management Plan


Project Funding Requirements
Work Performance Data
Organizational Process Assets

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

8/23/2015

Control Costs : T&T


1.
2.
3.
4.
5.
6.

Earned Value Management


Forecasting
To-complete Performance Index (TCPI)
Performance Reviews
Project Management Software
Reserve Analysis

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

Control Costs : T&T


1. Earned Value Management
EVM develops and monitors three key dimensions for each
work package and control account:
Planned value
Actual cost
Earned Value

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

8/23/2015

Planned Value
Planned value (PV) is the authorized budget assigned to scheduled
work.
It is the authorized budget planned for the work to be accomplished
for an activity or work breakdown structure component, not
including management reserve.
This budget is allocated by phase over the life of the project, but at a
given moment, planned value defines the physical work that should
have been accomplished.
The total of the PV is sometimes referred to as the performance
measurement baseline (PMB). The total planned value for the
project is also known as budget at completion (BAC).
* These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK Guide) - Fifth Edition, Project Management Institute, Inc., 2013.

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

8/23/2015

Actual Cost
Actual cost (AC) is the realized cost incurred for the work
performed on an activity during a specific time period.
It is the total cost incurred in accomplishing the work that the
EV measured.
The AC needs to correspond in definition to what was
budgeted in the PV and measured in the EV (e.g., direct hours
only, direct costs only, or all costs including indirect costs).
The AC will have no upper limit; whatever is spent to achieve
the EV will be measured.
* These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK Guide) - Fifth Edition, Project Management Institute, Inc., 2013.

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

Earned Value
Earned value (EV) is a measure of work performed expressed in
terms of the budget authorized for that work. It is the budget
associated with the authorized work that has been completed.
The EV being measured needs to be related to the PMB, and the EV
measured cannot be greater than the authorized PV budget for a
component.
The EV is often used to calculate the percent complete of a project.
Progress measurement criteria should be established for each WBS
component to measure work in progress.
Project managers monitor EV, both incrementally to determine
current status and cumulatively to determine the long-term
performance trends.
* These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK Guide) - Fifth Edition, Project Management Institute, Inc., 2013.

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

8/23/2015

Earned Value

Earned Value = % completed x Budget


Progress measurement technique measures the percent
complete which will assist in calculating the earned value. The
budget is the budgeted cost of the measured component
which could be a work package, control account, or the
project.
* These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK Guide) - Fifth Edition, Project Management Institute, Inc., 2013.

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

Progress Measurement
Units completion, Start/Finish, Incremental
Milestone, Supervisor Opinion, Cost Ratio and
Equivalent Units/Weighted Average

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

8/23/2015

Units Completion
Formula

x 100

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

Start/Finish (Fixed Formula)

30%
Start

70%
Finish

This method is applicable to tasks that lack readily definable


intermediate milestones or those for which the effort/time
required is very difficult to estimate.

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

8/23/2015

Incremental Milestone

This method is applicable


to any control account that includes subtasks
that must be handled in sequence.

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

Supervisor Opinion

In this method, the supervisor


simply makes a judgment of percent
complete.

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

8/23/2015

Cost Ratio
This method is applicable to tasks that involve a long
period of time or that are continuous during the life of a
project, and which are estimated and budgeted on bulk
allocations of dollars and work hours rather than on the
basis of production.

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

Weighted or Equivalent Units


This method is applicable when the task being controlled
involves a long period of time and is composed of two or
more overlapping subtasks, each with a different unit of
work measurement.

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

8/23/2015

Equivalent Units - Example

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

Performance Measurement
Cost Variance, Cost Performance Index,
Schedule Variance, Schedule Performance
Index
2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

10

8/23/2015

Earned Value Calculation

Calculate BAC, PV, AC and EV

Schedule Plan
Schedule: To complete the work in 4 weeks
work is equally distributed

Wall 2

Wall 4

Budgeted Cost
USD 10000 / wall

Wall 1

Status at the end of week 3


Wall 1 100% - $ 12000
Wall 2 100% - $ 13000
Wall 3 50% - $ 7000
Wall 4 0% - $ 0

Wall 3

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

Solution
Work Package Planned Value

Actual Cost

Progress

Earned Value

Wall 1

10000

12000

100 %

10000

Wall 2

10000

13000

100 %

10000

Wall 3

10000

7000

50 %

5000

Wall 4

10000

0%

Total

40000

32000

25000

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

11

8/23/2015

Definitions
Cost Variance (CV). The amount of budget deficit or
surplus at a given point in time, expressed as the
difference between the earned value and the actual
cost.*
Schedule Variance (SV). A measure of schedule
performance expressed as the difference between the
earned value and the planned value.*
* These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK Guide) - Fifth Edition, Project Management Institute, Inc., 2013.

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

Definitions
Cost Performance Index (CPI). A measure of the cost
efficiency of budgeted resources expressed as the ratio of
earned value to actual cost.*
Schedule Performance Index (SPI). A measure of
schedule efficiency expressed as the ratio of earned value
to planned value.*

* These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK Guide) - Fifth Edition, Project Management Institute, Inc., 2013.

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

12

8/23/2015

Performance Measurement

Cost Performance
Cost Variance

Cost Performance Index

Earned Value Actual Cost

Positive = Under planned cost


Neutral = On planned cost
Negative = Over planned cost

Greater than 1.0 = Under planned cost


Exactly 1.0 = On planned cost
Less than 1.0 = Over planned cost

Schedule Performance
Schedule Variance

Schedule Performance Index

Earned Value Planned Value

Positive = Ahead of Schedule


Neutral = On schedule
Negative = Behind Schedule

Greater than 1.0 = Ahead of schedule


Exactly 1.0 = On schedule
Less than 1.0 = Behind schedule

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

Cost Performance
Cost Variance

Cost Performance Index

25000 32000 = (7000)

25000 / 32000 = 0.781

Schedule Performance
Schedule Variance

Schedule Performance Index

25000 30000 = (5000)

25000 / 30000 = 0.833

* These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK Guide) - Fifth Edition, Project Management Institute, Inc., 2013.

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

13

8/23/2015

Control Costs : T&T


2. Forecasting
An estimate or prediction of conditions and events in the
projects future based on information and knowledge available
at the time of the forecast.
The information is based on the projects past performance
and expected future performance, and includes information
that could impact the project in the future, such as estimate at
completion and estimate to complete.
* These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK Guide) - Fifth Edition, Project Management Institute, Inc., 2013.

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

Definitions
Estimate at Completion (EAC). The expected total cost of
completing all work expressed as the sum of the actual
cost to date and the estimate to complete.*
Estimate to Complete (ETC). The expected cost to finish
all the remaining project work.*

* These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK Guide) - Fifth Edition, Project Management Institute, Inc., 2013.

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

14

8/23/2015

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

Estimate At Completion
EAC

EAC

AC + (BAC EV)

CPI is expected to be the same for the


remainder of the project

Future work will be accomplished at the


planned rate

EAC

EAC
AC +

( )
( )

CPI and SPI influence the remaining work

AC + Bottom up ETC
Initial plan is no longer valid

* These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK Guide) - Fifth Edition, Project Management Institute, Inc., 2013.

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

15

8/23/2015

Estimate At Completion
EAC

EAC

= 51216
.

32000 + (40000 25000) = 47000

CPI is expected to be the same for the remainder of the


project

Future work will be accomplished at the planned rate

EAC

EAC

32000 +

( )
(. .)

32000 + Bottom up ETC

= 55055

CPI and SPI influence the remaining work

Initial plan is no longer valid

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

Estimate To Complete
ETC

ETC
EAC AC

Assumes work is proceeding on plan.

Re-Estimate
Re-estimate the remaining work from the
bottom up.

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

16

8/23/2015

Estimate To Complete
ETC

ETC

51216 32000 = 19216


CPI is expected to be the same for the remainder of the project.

Assumes work is proceeding on plan.

Re-Estimate
Re-estimate the remaining work from the
bottom up.

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

Control Costs : T&T


3. To-complete Performance Index (TCPI)
A measure of the cost performance that is required to be
achieved with the remaining resources in order to meet a
specified management goal, expressed as the ratio of the
cost to finish the outstanding work to the remaining
budget.*

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

17

8/23/2015

To Complete Performance Index

To Complete Performance Index


TCPI

TCPI
(BAC EV)/(BAC AC)

The efficiency that must be maintained in


order to complete on plan.

(BAC EV)/(EAC AC)


The efficiency that must be maintained in
order to complete the current EAC.

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

To Complete Performance Index


TCPI

TCPI
(BAC EV)/(BAC AC)

(BAC EV)/(EAC AC)

(40000-25000) / (40000-32000)

(40000-25000) / (51216-32000)

1.875

0.781

The efficiency that must be maintained in


order to complete on plan.

The efficiency that must be maintained in


order to complete the current EAC.

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

18

8/23/2015

Control Costs : T&T


4. Performance Reviews
Performance reviews compare cost performance over time,
schedule activities or work packages overrunning and
underrunning the budget, and estimated funds needed to
complete work in progress.*

* These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK Guide) - Fifth Edition, Project Management Institute, Inc., 2013.

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

Variance At Completion
VAC

BAC EAC
40000 51216 = (11216)
The estimated difference in cost at the completion of the project.

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

19

8/23/2015

Definition
Variance at Completion (VAC). A projection of the
amount of budget deficit or surplus, expressed as the
difference between the budget at completion and the
estimate at completion.*

* These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK Guide) - Fifth Edition, Project Management Institute, Inc., 2013.

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

Control Costs : Outputs


1. Work Performance Information
The calculated CV, SV, CPI, SPI, TCPI, and VAC values for WBS components, in particular
the work packages and control accounts, are documented and communicated to
stakeholders.*

2. Cost Forecasts

3.
4.
5.
6.

Either a calculated EAC value or a bottom-up EAC value is documented and


communicated to stakeholders.*

Change Requests
Project Management Plan Updates
Project Documents Updates
Organizational Process Assets Updates

* These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK Guide) - Fifth Edition, Project Management Institute, Inc., 2013.

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

20

8/23/2015

END OF CHAPTER 7

PROJECT COST MANAGEMENT

2014 3FOLD Education Centre . All rights reserved . contact@pmexamstudy.com . www.pmexamstudy.com . www.3foldtraining.com . PMP Exam Review

21

You might also like