Site Visit Report No.

2
Site visit was carried out on 15.11.2014 to see the construction activities for the
major

Pawana

River

Bridge structure at Chainage 860.350 and vehicular

underpass (VUP) at road chainage 861.040 on six laning of Pune Satara road
project (Section of NH-4) to be executed as Built Operate and Transfer (BOT)
(Toll) on Design, Built, Finance, Operate & Transfer (DBFOT) pattern under NHDP
Phase V.
About the Project :The VUP structure is a part of highway project which is executed on Built, Operate &
Transfer (BOT) (Toll) on Design, Built, Finance, Operate & Transfer (DBFOT) pattern under
National Highways Development Programme (NHDP) Phase-V. NHDP Phase-V project is a
prestigious project & is a part of golden quadrilateral connecting Mumbai to Bangalore. The
project is awarded to Concessionaire (Contractor) M/s. PSTRPL (Subsidiary company of M/s.
Reliance Infrastructure Ltd) for a period of 24 years i.e. up to 30 th Sept 2034. The
Concession Agreement for the said project was signed between National Highways Authority
of India (NHAI) & M/s PSTRPL on 10th March 2010. The appointed date is 1st October, 2010
and construction period is 30 months. M/s. Aarvee Associates, Architects Engineers &
Consultants Pvt. Ltd. has appointed as Independent Engineer (IE) (Consultant) and M/s.
HAKS, Chennai has appointed as safety consultant for the project. The six laning widening
project starts from Satara (Ch. 725.000) and ends at Dehuroad (Ch. 865.350), total length
of the project is 140.350 Kms. Estimated Project Cost is Rs. 1724.55 Crores.
This project is a Access Controlled Highway Project and in the entire construction period, the
highway is to be maintained by the Concessionaire at his cost from the appointed date.
Traffic Management and Safety of workers and the road users shall be ensured at all times
in accordance with the relevant Indian Road Congress (IRC)/IS Codes as stipulated in the
Concession Agreement. Concessionaire has to provide Road side furniture, Street Lighting,
Pedestrian Facilities, Landscaping & Tree Plantation, Highway Patrol Ambulance & Tow
Crane etc.
1. Pawana River Bridge ( Major strcture) at Ch. 860.350 :The silent features along with progress of work observed during the site visit are
i.

as below:
River Pawana: River Pawana is a perennial river. Continuous flow of water is
coming from the upstream end i.e. through Pawana dam. There are number of
K.T. Weirs constructed on the down stream side, due to which it was observed 67 m water depth maintained continuously. So construction of bridge in water is a
challenging task. For accessing the site & for equipment movement the
Concessionaire had constructed earthen embankment platforms, for which huge

quantity of earth filling was required. Concessionaire M/s PSTRPL has adopted
ii.

well foundation for the piers. There are two piers on both the bridges (LHS/RHS).
Existing Bridges: It was observed during site visit that two bridges, one on LHS
2 laned (PSC T girder work completed in 1970) & RHS- 3 laned (PSC Box

iii.

girder- work completed in 2000) were already exiting.


New Bridges: The new bridges (two nos.) are proposed on the service road on
LHS & RHS side. Both are 3 laned each & for that PSC-T girder will be used (four
girders with 3.125 m c/c spacing). Span arrangement for the bridge is 3 spans

iv.

of 30.52 m each.
Pile foundation: pile foundation was observed to be used for abutment
foundation work. Total 15 nos. piles (5x3 rows) were used. Av. depth for pile is
13.5 m upto cut off level. Permanent liner of 6 mm thk. was used for each pile.
Size of each circular pile is 1.0 m dia. and main reinforcement used is 25 mm dia.
and circular helical r/f of size 8 mm dia. was used as a distribution steel. Over the
group of piles, pile cap of 1.50m thickness & size 5.3 m x 6.3m is used. On the

v.

pile cap, there is a pier of size 1.7 m dia., which is yet to be constructed.
Well& Pier : A circular type well of dia. 7.00m & thickness 0.80 m was used. It
is observed that,
A. For RHS Bidge, the work of two wells, 5m above river bed level is completed.
Pier cap & pier is yet to be casted.
B. For LHS bridge, two wells above high flood level is completed. Pier cap is
already completed. Piers upto 5m ht. is also completed.
C. Main r/f used is 32 mm of dia. & for dist. is 10 mm dia. Concrete for well &

vi.

pier as per design is M-35. Pier size is 1.7 m dia.


Girders for New Bridges: Size of the girder is 1.8 m x 0.75m each. Total clear
Length of each girder is 30.52 m. Size of one girder is 1.8m x 0.75m. There are 4
girders to be used for each span with 3.125 m c/c spacing. PSC-T type girders are
proposed by the Concessionaire for the work. Girders were observed to be

vii.

casted, tensioned & ready for launching.


Deck Slab: Thickness of slab is 200 mm & concrete type is M-40. The slab was

not yet casted on the site.


2. Vehicular Underpass (VUP) at Ch. 861.040 :The silent feature of the vehicular underpass is as below.
i.

The Vehicular underpass site is located on the Westerly Diversion to Pune city
road. The structure is located at Ch.861.040 to facilitate the local road users /
public for crossing cross road of Kiwale- Ravet. There is high rapid development
on both sides of the National Highway was observed. This vehicular underpass is
located at Ch. 861.040 (Near Ravet) to facilitate crossing of the local road users /

public travelling towards Ravet to Kiwale. To facilitate easy crossing movement,


ii.

NHAI has proposed an underpass of size 30m span at the junction.


The span arrangement of the structure is 1 x 30 m. Clear height of the structure

iii.

is 5.00 m.
There are Left Hand Side (LHS) and Right Hand Side (RHS) main carriageway of

iv.

width 11.05 m with a central median of 1.2 m.


There are six RCC pre-stressed girders of I section type with a depth of 1.45 m,

v.

length of 31.5 m and center to center spacing between two is 2.20 m.


There are four pier type abutments of size 1.0 m dia on both sides with cross RE

vi.

wall on both sides.


Grade of steel Fe 500, Concrete grade for foundation M 35, Abutment pier
M 35, Pier cap M 35, Deck slab M 40, Longitudinal girder M 45. The

elastomeric bearing is used in the structure.


vii.
Cost of the structure Rs. 8 Cr. appro.
Stage of construction and observations during the site visit :During the site visit, it was observed that,
i.
Work of LHS/RHS pier abutments upto pier cap is completed. Six girders of size
ii.

1.45 m x 31.5 m were observed to be placed on the abutment cap.


Deck slab - Deck slab of thickness 200 mm was already casted and completed in

iii.

M 40 grade concrete as per drawing & design.


Pier Abutment - The open foundation is used for the pier abutment to an
average depth of 2 m below ground level. The main reinforcement steel is 25 mm
dia bar (Total 16 Nos. in each abutment). Circular distribution steel of 10 mm dia,
150 mm C/C is provided with M 45 concrete.

Joint abutment cap of 11.9 m

length x 1.1 m depth (Tapering towards end). Six girder caps were casted in M 45
and girders were placed on the elastomeric bearings above the pedestal caps
iv.

with 2.2 m C/C spacing.


RE Wall - The work of cross RE wall using RE block was already completed. The
RE blocks of size 300 x 200 x 450 mm (Weight 42 Kg) was used with Geo-grid

v.

mess of type 60/80/100 as per the requirement and height of embankment.


Open for Traffic The structure was already completed. It was told from the
staff of M/s PSTRPL that it was opened to traffic fifteen days before. The traffic
was observed to be going on smoothly over the structure.
The site staff along with structural engineer of M/s PS Toll Road Pvt. Ltd. working
on the site had given all the technical details/ information and explained the
execution method used in the construction of said structures. The site visit ended
with thanks to the staff of M/s. PS Toll Road Pvt. Ltd. for their extended cooperation during the site visit.

Photograph no.1- Pier Abutment on Mumbai side+ Pier Cap+ elastomeric


bearings placed.

Photograph no.2- Girders with Pier abutments+RE wall completed.

Photograph no.3- Well foundation for A2 RHS side (Mumbai side)


Pawana Bridge Abutment

Photograph no.4- Well Foundation for A2 (LHS) completed 5m above river bed