1)
Project Execution
i) Project Release System Status Release
ii) Project Purchase Order Creation [T-code: ZPS_PO]
a) Creation of Material Purchase Order
b) Creation of Civil Purchase Order
c) Creation of Centages Purchase Order
iii) Material Receipt [T-code: MIGO; Mvt. Type: 103 and 105]
iv) Creation of Service Entry Sheet for Civil [T-code: ZPS_SES]
v) JMC Creation Material & Civil [T-code: ZPS_JMC]
vi) JMC Approval [T-code: ZPS_JMC01]
vii) Creation of RA Bill [T-code: ZPS_RABILL]
PROJECT CREATION
T-code: CJ20N
Click Create ---
Project Definition:
Check
Project Definition
Click Search
System will propose next available No.
Click OK
Project Definition
Description
(Same as Project Description)
At Serial No. 1
WBS Element Column: Enter Project No. (Same as Project Definition)
Description Column: Enter Project Name (Same as Project Description)
& Press Enter
Goto User Tab:
Enter Scheme Name and Cost Data Date
Goto Assignment Tab:
Enter Costing Sheet (Search & select)
Goto Custom Enhancement of Project (Made Mandatory):
Select Project Definition in Project Structure
Go to Cust. Enhancement and add
necessary information of Project manually. Such as Phase of Project, Tender NO, Tender Cost,
Percentage Quoted etc.
Click intermediate Save
Method 2:
Select Project
Right click
Create
WBS Element
WBS Elements
Top WBS(Same as Project Defination)
Second Level WBS(TOP WBS.01)
Second Level WBS(TOP WBS.02)
Description
(Same as Project Description)
Activity Description
Activity Description
At Serial No. 2
WBS Element Column: Enter Project No. with .01, .02, etc for each activity
Description Column: Enter Activity Details for each activity WBS Element
& click intermediate save
Note: We go on adding Second Level WBS in Level 2 only. We can add upto 999 Second Level
WBS elements (Activities)
Method 2:
Select Top Level WBS Element
Right click
Create
WBS Element
Right click
Create
Copy
THIS WILL CREATE INDIVIDUAL WBS ELEMENT WISE NETWORK & ACTIVITY
Plant
Usage
6 (Default Value)
Click OK
Pop-up window will appear (Copy Bill of Material Item) with all materials required for concern
Activity
Select all (or only required material) and click copy
Important Note:
However, the material list added to each activity as above is a standard List of material
required for an activity. But many times considering the on-site situation the actual material
requirement may differ from standard material requirement.
Therefore, any changes in required material quantity shall be carried out in sap also.
Further if any material is not required, same shall be deleted as no zero quantity is accepted by
system. Also, if any additional material is required then same shall also be added in components
of respective activities.
Unit
Right Click
Delete
A message will appear as Price cannot be maintained for given material. It means that we
have to enter price of material added. There are two methods for adding the price.
Method 1: If Price of material as per Cost Data or Tender is not known
Select material
INR
If Price is added then its OK, if price is not added or some error appears that Price of given
Material cannot be determined then change the Cost Data Date of Top WBS Element and then
repeat the procedure. The price will now be added for Given Material
& click intermediate save
Method 2: If Price of material as per Cost Data or Tender is known
Select Material
Price/Currency
Price Unit
No
Fix Price
-7-
Price/Currency
INR
-8-
Right Click
Create
WBS Element
create
Network
Create
Enter
Activity
Enter Quantity
INR
If Price is added then its OK, if price is not added or some error appears that Price of given
Material cannot be determined then change the Cost Data Date of Top WBS Element and then
repeat the procedure. The price will now be added for Given Material
& click intermediate save
Method 2: If Price of material as per Cost Data or Tender is known
Select Material
Price/Currency
Price Unit
No
Fix Price
Repeat the above mentioned procedure for all material required in said activity
THIS WILL ADD NEW (NON-STANDARD) ACTIVITY TO PROJECT
-9-
Note: Some material will appear in Fraction when we enter decimal in required quantity, then
we have change the material quantity as per our requirement of project.
THIS WILL TAKE TOTAL WORK/QUANTITY UNDER PROJECT IN DECIMAL. ALSO, SAME
PROCEDURE SHALL BE FOLLOEW IF NO. OF WORK IN ANY ACTIVITY IS >= 1000
Selection Option
o Project wise
o Activity wise
o Civil Activity wise
o BOQ/Network wise
o Project wise collective
& Execute
Pop-up window will appear (Print)
Enter Output Device as LP01 (Default value) & click Print Preview
Estimate/DPR will appear
Enter T-code: PDF! and save the Estimate/ DPR in PDF format
THIS WILL GIVE TOTAL ESTIMATE OF PROJECT WITH AMOUNT
- 10 -
Enter Date upto which the work shall be Executed and completed
Enter Milestone Quantity (Quantity shall be absolute Quantity and nor percentage of work to be
carried out. The % symbol beside the box will be removed by zensar.
& click intermediate save
THIS WILL CREATE MILESTONE UNDER ACTIVITY. THERE CAN ALSO BE MORE THAN ONE
MILESTONE UNDER AN ACTIVITY
Click Open Original below for attachment of DPR (PDF File) saved earlier
attach file
Browse and
To Lock the file; Right Click on Lock Symbol below on attached file and select Check In
- 11 -
The Lock Open Symbol will be changed to Lock closed i.e. the file is attached in Zip
Now click on Object Links & select WBS Element tab
Table will open
Enter WBS Element in column and Press Enter
& Click Save
THIS WILL ATTACH THE PDF FILE OF PROJECT ESTIMATE TO TOP LEVEL WBS ELEMENT.
SIMILARLY, OTHER TENDER DOCUMENTS, SUCH AS CONTRACTORS INVOICE,
DOCUMENTS, ETC CAN ALSO BE SCANNED AND SAVED IN PROJECT
Notification Type
P1
A message will appear The Currency for the cost is adopted from the Company Code
Click OK
Goto Subject Below:
Description
Document Column
Keep it Blank
check wherever applicable
- 13 -
Select Row
click Service of object (above)
Create
Browse and attach scan copy of BR (if available)
Create Attachment
Keep it Blank
check wherever applicable
Keep it Blank
- 15 -
Investment Program
Search & Select Relevant Project Budget
Position ID
Search & Select Relevant
& intermediate save
THIS WILL ASSIGN BUDGET FROM RESPECTIVE PLAN i.e. INFRA, DPDC, etc TO PROJECT
{TOP LEVEL WBS ELEMENT}
Select Project
Click on
Change Status:
It will show Status as 1 Created
Now Click on 2 ADPR - Approved DPR & click back
Now User Status ADPR
Click on
Click on i
Click on
Project
Test Run
& Execute
THE BUDGET IS ALLOCATED TO EACH WBS ELEMENT
& Enter
IT WILL SHOW THAT THE BUDGET HAS BEEN ALLOCATED TO EACH WBS ELEMENT
- 17 -
T-Code: CJ32
100 %
Release
& save
Now System Status will be
REL
- 18 -
T-Code: ZPS_PO
Project No.
Vendor
Note:
For At-Par Quoted rate select any of % above or below Est. Cost & Enter % Quoted rate as
Zero (0).
Select
o Material PO
o Civil Work PO
o Centages PO
- 19 -
Note:
While changing Price or Quantity in any activity a message appears Error in Commitment
Check, it means that Budget has been exceeded. So in this case, supplement the budget and
then repeat step (1) again as system will not allow saving changes made without supplement
budget.
2) After release of supplementary budget and changing the price or quantity or addition of
activity, the purchase orders created earlier needs to be changed by PO Freezing as under:
T-Code: ZPS_POFRZ
Select
o Material PO
o Civil Work PO
o Centages PO
& Execute
A Message will appear in Pop-up window Special PO ___________________ Changed
IN THIS WAY THE PO FOR EACH i.e. MATERIAL, CIVIL AND CENTAGES CAN BE CHANGED
- 20 -
Position ID
Approval Year
Goto Process Transaction (Below)
Select Supplements
Goto WBS Element
From Project only
& Execute
Change Budget Distribution Supplements: Item Overview
(Table will open)
Add required Supplementary budget in supplement column at Sr. No. 2 i.e. for Project No.
100 %
3) Transfer of Supplement Budget from Top Level WBS Element to Activity Level
WBS Element
[Transfer/ Supplement of Budget (distributable) from Top Level WBS to Activity WBS]
T-Code: CJ37
DyM (F&A)
100 %
Select Relevant
Amount
A message will appear in Pup-up window Enter reason for change of version, Enter requester
for Version
Click on Version Tab in Header and enter following value in tables top row:
Reason Column
Search & select
Text
Freezing or any other details
Requested By
Enter User Id
& Save
T-Code: MIGO
I) MIGO (103)
Display Material Document: Select
Goods Receipt
Purchase Order
103
Material Document
105
T-Code: ZPS_SES
Posting Date
& Execute
Civil Entry Sheet Creation (Table will appear along with the List of Civil Activity): -
Here SES Qty is not editable and fixed at 1. So, if in a particular activity such as Land
Development, the total Qty is say 6, then six separate service entry sheet will be created.
Similarly, only one Row-activity at one time can be selected. (No multiple selections is
allowed).
Select relevant Row of activity and click Create
THE SERVICE ENTRY SHEET FOR CIVIL ACTIVITY IS NOW CREATED AND ONLY
THEREAFTER CIVIL JMC CAN BE CREATED.
T-code: ZPS_JMC
o
o
o
Activity Code
Network Number
& Execute
Section
Location
Name of Work
Milestone
- Select relevant milestone from drop down list & Press Enter
Now, Enter JMC Quantity (actual measured) of each material in JMC table displayed below
& click save
- 27 -
Civil JMC: Only after creation of Material JMC, Civil JMC can be created as while creating Civil JMC,
the system asks for Material JMC No.
For creation of Civil JMC, use T-code: ZPS_JMC and repeat all the steps upto execution by
selecting Civil Activity and Execute
Joint Measurement Certificate Creation: Enter Ref Material JMC No.
& Press Enter
Now, Enter JMC Quantity (actual measured) of each material in JMC table displayed below
& click save
T-Code: ZPS_JMC01
& Execute
In case the JMC is rejected, the creator has to change or correct the JMC using T-Code;
ZPS_JMC by
selecting Change option
Entering Project Definition
Entering JMC Number
Thereafter, the corrected JMC is to be saved and same will again be available for approval from
concern SDO by repeating above mentioned steps.
Repeat the same for Civil JMC also.
THE JMC IS NOW APPROVED AND JMC QUANTITY WILL NOW APPEAR IN RA BILL
- 28 -
Note:
1) The JMC creation and approval procedure shall be carried out with due care as once JMC is
approved; the JMC Quantity cannot be changed at any level.
2) If in any activity there are both material & civil activities and if at certain location, only
material activity work has been carried out and civil work is not required, then in such case
both material and civil JMC has to be created and approved for said location by Material
JMC with actual quantity and Civil JMC with zero Quantity otherwise the system will not
allow creation of RA bill without Civil JMC.
T-Code: ZPS_RABILL
Note:
1) Single RA Bill can be created for Multiple JMCs of one Activity
2) While creating RA Bill, only Material JMC No. is entered as Civil JMC is already linked to
Material JMC during creation. On execution of RA Bill using Material JMC No., the Civil Work
is automatically included in RA Bill
Select relevant from
o Create
(Select for creation of New RA Bill)
o Change
(Select for making changes in rejected RA Bill)
o Display
(Select to view created RA Bill)
Activity Code
& Execute
Enter Quantity of material at RA Bill Qty column for within state (WS) or outside state (OS)
RA Bill Quantity = JMC Quantity =< MIGO (105) Quantity
The Cumulative RA Bill Quantity cannot exceed Total MIGO (105) Quantity
- 29 -
Civil activity by default will be shown zero 0 for outside state column as it shall be entered
for within state only.
Click save
T-Code: ZPS_RABILL01
In case the RA Bill is rejected, the creator has to change or correct the RA Bill using T-Code;
ZPS_RABILL by
Thereafter, the corrected RA Bill is to be saved and same will again be available for approval
from concern SDO by repeating above mentioned steps.
THE RUNNING ACCOUNT BILL (RA BILL) IS NOW APPROVED AND INVOICE CAN BE
CREATED
Creation of Invoice
T-Code: ZPS_INV
Billing Invoice Certificate: A single Invoice can be created for multiple RA Bill.
- 30 -
RA Bill Number
& Execute
Billing Invoice Certificate: Check
The value or amount of Centages will already be displayed in the invoice created above. But
the invoice printing option will only be available after creation of Service Entry Sheet for
Centages.
Service Entry Sheet Creation: Select Centages SES
Fill Details:
Project No.
Invoice No.
Network Number
Posting Date
Enter Date
& Execute
THE SERVICE ENTRY SHEET IS NOW CREATED AND SO THE PRINT OUT OF INVOICE CAN
BE TAKEN USING T-CODE: ZPS_INV AND SELECTING DISPLAY OPTION.
Invoice Parking
T-Code: ZPS_PROJECT_INVOICE
(For WS Materials)
(For OS Materials)
o
o
& Execute
1)
Invoice Number
Posting Date
Reference
Text
Terms of Payment
[Not Mandatory]
Invoice Posting
T-Code: MIR6
Pop-up window (Simulate Document in INR) will appear with List of Material
If Error is displayed, then change the amount such that the Balance in Right Corner is 0.00
& click simulate again
Pop-up window (Simulate Document in INR) will appear with List of Material or work
Click back
- 33 -
If no errors
click Post
Press enter for all the messages displayed in left hand corner below.
THE INVOICE IS NOW POSTED AND BLOCKED FOR PAYMENT
Stock Update
T-Code: ZPS_GI
Project No.
Invoice No.
Posting Date
Enter Date
& Execute
THE STOCK IS NOW CONSUMED AND UTILIZED AGAINST ACTIVITY BILLED UNDER
RESPECTIVE INVOICE
T-Code: MBBS
Project No.
& Execute
Now, the Goods issued as above or Used against said invoice no. will not be available at
Vendor Storage Location V001.
THE LIST OF UPDATED STOCK WILL BE DISPLAYED
- 34 -
T-Code: ZPS_WCR01
Select Relevant
Project No.
Activity No.
Search & Select Relevant Material JMC No. & Press enter
& Execute
Various Messages will be displayed
Enter Date
Enter Supply
- 35 -
Enter Date
- 36 -
Activity Confirmation
[Tagging All work under said activity in completed satisfactorily]
T-Code: CJ20N / CN25
Activity
Confirm
Short Description
Processing
100%
Date
Date
Qty Value
Unit
Activity
- 37 -
Project Confirmation
(One Activity WBS Element at One Time)
T-code: CJ88
Actual Settlement: Project / WBS Element/ Network: In our Project, the cost is always assigned to respective WBS Element and so in the page
displayed only WBS Element No. of the activity (to be settled) is to be entered/ filled. Project
No. and Network Details are to be kept blank.
Project
Keep Blank
OR
WBS Element
OR
Network
Keep Blank
Fiscal Year
Processing Type
Then
1 Automatic
1 Automatic
For Partial Settlement by Technical Person
8 Full Settlement
For Full Settlement by (F&A) Person
Test Run
Check for Test Run to see if any errors occurs, if no error occurs, uncheck for final run.
& Execute
- 38 -
Actual Settlement: Project/WBS Element/Network Basic List: Check for Errors in Max Message Type column in Processing Option,
If no errors, then click save.
Project Confirmation
(Multiple Activity WBS Elements at One Time)
T-code: CJ8G
Create Variant
Enter Details
Database Prof
000000000001
& click OK
- 39 -
TO
Enter Description
Settlement Period
Fiscal Year
Processing Type
Then
1 Automatic
1 Automatic
For Partial Settlement by Technical Person
8 Full Settlement
For Full Settlement by (F&A) Person
Test Run
Check for Test Run to see if any errors occurs, if no error occurs, uncheck for final run.
& Execute
- 40 -
Actual Settlement: Project/WBS Element/Network Basic List: Check for Errors in Max Message Type column in Processing Option,
If no errors, then click save.
THE WBS ELEMENTS OF MULTIPLE ACTIVITY ARE NOW FULLY / PARTIALLY SETTLED BY
TECHNICAL / F&A PERSON
Project Closure
T-code: CJ20N
Open Project
Status
Close
Set
& Save
THE PROJECT IS NOW FLAGGED AS CLOSED FINAL CLOSURE OF PROJECT
Budget Transfer from One Activity WBS Element to another Activity WBS Element
Note:
Only Budget amount in excess to amount under Assigned column of respective activity WBS
Element can be transferred at max.
The procedure comprises of three steps as under:
1) Unrelease of Budget in respect of First Activity WBS Element
T-code: CJ32
Change Release: WBS Element: Copy Amount under Assigned column of the activity WBS Element from where amount is to
be transferred and paste the same to its respective release column. This will release only
assigned column value to that activity WBS Element and remaining amount will be kept as
unreleased and this unreleased amount can be transferred to another WBS Element.
& click Save
The balance amount i.e. difference between Current Budget (before unrelease) and amount
- 41 -
2) Transfer of Budget from First Activity WBS Element to Second Activity WBS
Element
T-code: CJ34
Transfer Budget: List Screen [Table will appear]: Sender WBS Element column
Amount Column
Percentage
Budget Return from Activity WBS Element to Top Level WBS Element
Note:
Only Budget amount in excess to amount under Assigned column of respective activity WBS
Element can be returned at max.
The procedure comprises of two steps as under:
1) Unrelease of Budget in respect of First Activity WBS Element
T-code: CJ32
Change Release: WBS Element: Copy Amount under Assigned column of the activity WBS Element from where amount is to
be transferred and paste the same to its respective release column. This will release only
assigned column value to that activity WBS Element and remaining amount will be kept as
unreleased and this unreleased amount can be returned to Top Level WBS Element.
& click Save
The balance amount i.e. difference between Current Budget (before unrelease) and amount
at Assigned column is available for return to Top Level WBS Element activity.
- 43 -
Change Return: WBS Element Overview: Enter amount to be returned to top level WBS in the Return Column of respective Activity
WBS Element from where budget is to be returned.
Click check (for checking of error); if no errors, click save
THE AMOUNT IS RETURNED TO TOP LEVEL WBS ELEMENT UNDER DISTRIBUTABLE
COLUMN
Note:
Only Budget amount in excess to amount under Distributed column of Top Level WBS
Element can be returned at max.
The procedure comprises of two steps as under:
1) Unrelease of Budget in respect of Top Level WBS Element
T-code: CJ32
Change Release: WBS Element: Copy Amount under Distributed column of the Top Level WBS Element from where amount
is to be transferred and paste the same to its respective release column. This will release only
Distributed column value to the Top Level WBS Element and remaining amount will be kept as
unreleased and this unreleased amount can be returned to IM.
& click Save
The balance amount i.e. difference between Current Budget (before unrelease) and amount
at Distributed column is available for return to Top Level WBS Element activity.
Position ID
Approval Year
- 44 -
& Execute
Change Budget Distribution Supplements: Item Overview
(Table will open)
The amount under Distributable Column of WBS Element can be returned back to IM i.e.
Investment Management at max.
Enter amount to be returned back to IM (max upto Distributable amount of WBS Element)
at Return Column of WBS Element.
& Press Enter
You will see that amount is reduced in Distributable column of WBS Element (Project) and
added to Distributable Column of IM (Scheme)
& click Save
Note: The Budget from multiple projects can also be returned back to IM at one time. For this
purpose, perform Step (1) as mentioned above i.e. T-code CJ32 in respect of all the projects
and then use T-code: IM48. The table with multiple projects will appear. Enter respective
amount of project to be returned back to IM at Return Column of respective Project WBS
Element.
- 45 -