Professional Documents
Culture Documents
of Bored
Cast-in-Situ Piles Using Rotary Drilling ProcedureA Case Study
IGC 2009, Guntur,
INDIA
954
Construction of Bored Cast-in-Situ Piles Using Rotary Drilling ProcedureA Case Study
GL
to
0.50 m
0.50 m
to
1.50 m
1.50 m
to
3.00 m
3.00 m
to
4.00 m
4.00 m
to
6.00 m
6.00 m
to
7.00 m
7.00 m
to
10.00 m
to
Construction of Bored Cast-in-Situ Piles Using Rotary Drilling ProcedureA Case Study
800
1000
4520
7070
690
860
300
380
Pile diameter, mm
990
1240
1510
2360
570
710
2080
3070
2.65
2.71
Pile
0.00m
0.80m
800
1000
6790
10600
690
860
720
900
320
400
1730
2160
2260
3530
990
1230
3250
4760
Soft clay,
SPT N = 0 to 1
2.61
2.68
4.00m
Loose clayey sand,
SPT N = 0 to9
Pile
0.00m
6.00m
7.00m
Dense sand,
SPT N = 35
0.80m
4.00m
6.00m
7.00m
Soft clay,
SPT N = 0 to 1
10.00m
11.20m
Dense sand,
SPT N = 35
11.20m
Construction of Bored Cast-in-Situ Piles Using Rotary Drilling ProcedureA Case Study
100
Load, tonnes
200
300
400
500
The cut off level for these piles was decided as 2.0 m to 3.0
m below present GL and the steel and concrete was provided
up to a depth equal to 1.0 m above the proposed cut-off level.
The concrete as per the theoretical quantity was poured. It
was reported that most of the piles consumed more than one
cum concrete to make the concrete up to the stipulated level.
The temporary casing was removed after full tremmie
operation and there as an anticipated slump in the concrete to
fill the annular space of the temporary casing. However,
there was a sudden sinking of concrete by more than two
meters 30 to 40 minutes after the withdrawal of the casing in
many of the piles thus completed. This phenomenon was,
however, not reported in the records and no significance was
given to this otherwise unusual experience.
The piling work completed and the site was handed over for
superstructure construction. The excavation was to be made
to a depth of roughly 2.50 m for accommodating the thick
pile caps connecting 4 to 10 piles in a group. Many piles did
not record concrete even after 2.50 m excavation. Deeper
excavations revealed pile concrete of almost required size.
The issue of sinking of concrete at the time of pile
installation was brought to notice and the immediate
conclusion was that the concrete flowed laterally into the soft
sandy clay and loose sand present between 2.0 m and 5.0 m
(Refer Table 1 for soil profile).
5
Settlement, mm
10
15
20
25
957
Construction of Bored Cast-in-Situ Piles Using Rotary Drilling ProcedureA Case Study
Settlement, mm
100
200
300
level. Comparing the static load test result and the pile integrity
test, there is a possibility that the pile have an enlarged
section at about 7.50 m below the working level, similar to
under-reaming. The soil at this depth is dense residual sand
derived from complete weathering of granitic gneiss. More
or less static dial gauge readings over a loading of more than
80 tonnes should suggest failure of the measuring system.
The pile integrity test results further established that the piles
were resting only in the highly weathered and fracture/jointed
rock and not in the weathered jointed rock as stipulated for
the revised safe capacities. This inference is made from the
pile lengths established by the pile integrity tests. As stated
earlier, the construction drawings did not clearly specify the pile
bearing stratum and the criterion for ensuring the bearing
stratum.
7. PROBABLE CAUSE OF THE DEFECTS
400
500
Field curve
Series1
PSeries2
robable curve with
soft muck at tip
10
15
20
25
From the details obtained from the site, the temporary casing
pipe used for stabilising the sides was of about 7.0 m long.
The concreting was completed using tremmie and the concrete
was observed to the stipulated level in all the cases. Most of
the piles required more than theoretical quantity of the concrete
to reach the required concrete top level in the casing pipe. This
suggests that there was an excess consumption of concrete
below the casing tip level. The slump of roughly 2.0 m after
958
Construction of Bored Cast-in-Situ Piles Using Rotary Drilling ProcedureA Case Study
the removal of the casing pipe can only suggest that this part
of excess consumption took place above the temporary
casing tip level.
These piles were executed using rotary drilling which had no
provision for continuous mud circulation. The bentonite mud
was supplied intermittently as the auguring advanced. When
the step by step procedure of the pile construction operation
is reviewed, one would realise that the cutting tool, auger in
this case, was taken out of the borehole several times for
removing the soil cuts. When the auger along with the soil
cuts between the fins of the auger was being lifted, a suction
was created below the auger bottom which produces
tremendous upward pressure within the borehole. Moreover,
a significant amount of water and drilling mud poured from
the top were brought out of the borehole creating excess
hydrostatic head outside the borehole. The dense to very
dense residual sand present at the casing tip level being highly
permeable, sand blow condition took place. At the same time,
the soil just above the temporary casing tip flowed downward
creating a cavity around the temporary casing at least for some
length. This cave like annular was filled with ground water or
drilling mud which had no escape towards sides or upward. The
process continued creating larger cavity around the casing
pipe and loosening the dense sandy soil till the completion of
the boring operation. The loosening during the boring process is
described in Figure 6.
During the tremmie operation keeping the temporary casing
in place, the water/drilling mud within the cave portion
around the temporary casing pipe had no escape leaving the
cavity as it is. When the casing pipe was withdrawn allowing
gradual escape for the trapped water/drilling mud along the
soil-concrete interface allowing the green concrete from the
pile to flow into the cavity. The concrete in the borehole
gradually slumped down. Obviously there is no guarantee
that the concrete flows freely and uniformly as the initial
setting could have been over.
AFTER BORING
OPERATION
The final shape of the pile expected under the above situation
is also presented in Figure 6.
The rectification measures included construction of more
piles, almost 130 percent of the original number. Later when
additional piles were being installed close to the existing
piles, the cutting tool hit the concrete outgrowth of many of
the existing piles confirming the above hypothesis.
8. CONCLUDING REMARKS
There were several other cases of underperformance of bored
cast-in-situ piles reported from the same region where rotary
drilling procedure was adopted. Rotary drilling machines as
such cannot be blamed for this failure, since such system is
working with success in many places. The overall procedure
adopted in these cases shall be defective. The major reason
for the defects can be identified as improper stabilisation of
the borehole sides and bottom during different stages of
boring.
In this case, the piles were also not taken to the stipulated
bearing stratum because of the difficulties in identifying the
bearing stratum during boring process. The temporary casing
provided up to an intermediate depth resulted mining of soil
around the casing tip and below the casing because of the
hydrostatic imbalance created within the borehole during
frequent withdrawal of the cutting tool as a part of the
construction programme.
Very dense residual sand and the highly weathered and
significantly fractured rock below can offer tremendous skin
friction for the piles resting in the jointed rock below. These
formations being highly permeable and the ground water table
being very shallow, the temporary casing shall advance before
boring and should penetrate up to weathered jointed rock
where sand mining is not expected. The cutting tool/auger
shall have suction relief system so that the borehole is filled
with water preventing any sand blow at intermediate level.
AFTER REMOVAL
OF CASING
AFTER TREMMIE
CONCRETING
0.00m
Desiccated clay layer , N = 5
0.80m
Concrete top level
5.00m
7.00m
Temporary casing
pipe
Soil scoured /
collapsed
during boring
Unsupported length
Loosening of soil /
caving in
10.00m
Soft clay, N = 0 to 3
Probable loss of concrete
because of initial setting
and arching of top concrete
which may eventually settle
to some extend- Steel
exposed
Concrete flowed into the
cavity
Dense sand N=30 to >100
Fig. 6: Loosening of Soil around the Casing Tip and Over-Excavation below Casing
959
Construction of Bored Cast-in-Situ Piles Using Rotary Drilling ProcedureA Case Study
960