Professional Documents
Culture Documents
PROJECT TEAM
: Technical Officer
ACKNOWLEDGEMENT
The report is a part of the Council of Scientific & Industrial Research (CSIR)
Network
Project
COR-0013.
During
implementation
of
the
project
M/s Hindustan Colas Pvt. Ltd. agreed to sponsor the field evaluation part of the
project for which we wish to extend our sincere thanks. We also extend our
sincere thanks to Hindustan Colas for providing bitumen emulsion for laying test
sections in Rajasthan, Mizoram and Jammu & Kashmir. We deeply acknowledge
with sincere thanks for the co-operation extended during the identification of test
sites in snow bound area (J&K) and desert area (Rajasthan) by Directorate
General Border Roads, Chief Engineers- Chetak and Beacon Projects,
Commanders of different BRTFs, Officer Commanding and other officials
especially from Beacon Project - 77 BRTF / 99 RCC and Chetak Project - 49
BRTF / 101 RCC. The assistance rendered by Border Roads Organisation is
gratefully acknowledged for providing manpower, materials & machineries during
the construction of test sections and their periodical performance evaluation. We
also extend our deep sense of gratitude to PWD Mizoram with special mention of
Sh. Vanlal Duhsaka, Chief Engineer, Sh. Dela, S.E and other officials for
providing test sites, man power and materials for laying test sections in Aizawl,
Mizoram. Thanks are also due to M/s OM Infrastructure for providing emulsion
for laying one test section in Mizoram. The assistance and cooperation rendered
by M/s Goyal Construction of Rajasthan and NBCC of Aizawl, Mizoram is
acknowledged for providing Bituminous Mix Plant and Paver for laying test
sections.
Thanks are also due to the staff of BRO, PWD Mizoram and Flexible Pavement
Division of Central Road Research Institute directly or indirectly connected.
DISCLAIMER
Central Road Research Institute (CRRI), New Delhi can accept no responsibility
for the inappropriate use of this report. Engineering judgment and experiences
must be used to properly utilize the principles and guidelines contained in the
report, taking into account available equipment, local materials and conditions.
All reasonable care has been taken in the preparation of this report; however, the
CRRI can accept no responsibility for the consequences of any inaccuracies,
which it may contain.
FOREWORD
The construction of bituminous roads by conventional methods is energy consuming
and pollutes the environment as a result of heating of bitumen and aggregates at
elevated temperatures. The findings of R & D programme for development of cold
mix technology for structural layers will address development of suitable emulsions
for open graded cold mixes including design methods and their validation by full
scale field trials, will enable highway profession for adoption of this technology.
There are no construction specifications for bituminous binder courses such as
bituminous macadam (BM) and wearing courses such as semi dense bituminous
concrete SDBC and mix seal surfacing (MSS) using cold mix technology. Therefore,
it is felt essential to develop the cold mix technology and to frame their specifications
and guidelines. To encourage environmentally friendly and energy efficient cold mix
technologies, Central Road Research Institute, with the help of Border Roads
Organisation and PWD Mizoram, conducted field trials for construction and
performance of BM as base course and wearing courses such as SDBC, MSS and
PMC using bitumen emulsion in desert climate (Rajasthan), heavy rainfall (Mizoram)
and in snow bound areas (J & K).
This report gives the details of selection of test sections, laboratory studies, and
construction of test sections with mechanized methods using mix plant, paver
and road roller;
and their
(Dr. S. Gangopadhyay)
DIRECTOR
October, 2010
CONTENTS
S. No.
1.0
2.0
3.0
3.1
3.2
4.0
5.0
6.0
Content Description
Acknowledgements
Disclaimer
Foreword
List of Tables
List of Photographs
List of Figures
Executive Summary
INTRODUCTION
OBJECTIVES AND SCOPE
SPECIFICATIONS ADOPTED FOR TEST TRACK
Existing Construction Specifications with Emulsion
Specification Adopted For Test Sections
6.1
6.1.1
6.1.2
6.1.3
6.1.4
6.1.5
6.1.6
Page
No.
(i)
(ii)
(iii)
(iv)
(v)
(vi)
(vii)
1
4
5
5
5
7
7
8
9
10
10
11
13
14
14
15
16
18
18
18
18
19
19
19
19
S. No.
Page
No.
Content Description
6.2 Construction of Semi dense Bituminous Concrete
(SDBC) with Bitumen Emulsion
6.2.1 Preparation of Road Surface Over
Macadam
6.2.2 Preparation of Cold mix
Application of Tack Coat
6.2.3 Transportation of Cold Mixes
6.2.4 Laying and Compaction of Cold Mixes
6.2.5 Traffic Control
Bituminous
CONSTRUCTION
AND
PERFORMANCE
OF
BITUMINOUS MACADAM AND SEMI DENSE
BITUMINOUS CONCRETE/ MIX SEAL SURFACING
WITH BITUMEN EMULSION IN HIGH RAINFALL
AREAS IN MIZORAM
7.1 Laying of Bituminous Macadam with emulsion
7.1.1
7.1.2
7.1.3
7.1.4
7.1.5
7.1.6
25
25
25
25
26
26
26
27
27
27
27
32
32
32
39
39
39
39
39
40
40
40
S. No.
7.2
7.2.1
7.2.2
7.2.3
7.2.4
7.2.5
7.2.6
7.2.7
Content Description
Construction of Semi dense Bituminous Concrete
(SDBC) and Mix Seal Surfacing with Bitumen
Emulsion
Preparation of Road Surface Over Bituminous
Macadam
Preparation of Cold mix
Application of Tack Coat
Transportation of Cold Mixes
Laying and Compaction of Cold Mixes
Traffic Control
Results and Discussion
Page
No.
44
44
44
44
45
45
45
46
52
52
52
52
52
CONSTRUCTION
AND
PERFORMANCE
OF
BITUMINOUS MACADAM AND SEMI DENSE
BITUMINOUS CONCRETE/ MIX SEAL SURFACING
USING BITUMEN EMULSION IN COLD AND SNOW
BOUND AREA IN Jammu &Kashmir
Laying of Bituminous Macadam (BM) with Bitumen
emulsion
Preparation of Road Surface
Preparation of Cold Mix
Application of Tack Coat
Transportation of Mix
Spreading and Compaction of Cold Bituminous Mix
Traffic Control
56
57
57
57
57
58
58
58
58
8.1
8.1.1
8.1.2
8.1.3
8.1.4
8.1.5
8.1.6
56
56
56
56
56
56
57
Sr. No.
9.0
Content Description
COST ANALYSIS OF CONSTRUCTION
EMULSION AND BITUMEN
Page
No
WITH
64
Economic Analysis
64
10.0
CONCLUSIONS
65
11.0
RECOMMENDATIONS
ANNEXURE-1
66-67
68
ANNEXURE-2
80
ANNEXURE-3
92
LIST OF TABLES
Table
No.
1.
2.
3.
Description
Consumption of Bitumen Emulsion V/S Bitumen
Test Results Of Developed Cationic Bitumen Emulsion
Test Results of Cationic Bitumen Emulsion for Trials From
Hindustan Colas
Page
No.
2
11
12
13
15
33
34
35
47
10
LIST OF PHOTOGRAPHS
Photo
No.
Description
Page
No.
20
20
21
21
22
22
23
23
24
10
24
11
28
12
11
28
Photo
No.
Page
No.
Description
13
29
14
29
15
30
16
30
17
31
18
31
19
36
20
36
21
37
22
37
23
38
24
38
25
41
26
41
27
42
28
42
29
43
12
Photo
No.
Description
Page
No.
30
43
31
48
32
48
33
49
34
49
35
50
36
50
37
51
38
52
39
53
40
53
41
54
42
54
43
44
55
55
45
59
46
59
13
Photo
No.
Description
Page
No.
47
60
48
60
49
61
50
61
51
62
52
62
53
63
54
64
14
LIST OF FIGURES
Photo
No.
Description
Page
No.
TEST TRACK WITH BITUMEN EMULSION DANTAURKHAJUWALA ROAD LAID IN APRIL 2007
TEST TRACK WITH BITUMEN EMULSION ON AIZAWL BYPASS AIZAWL ROAD LAID IN JUNE, 2007
TEST TRACK WITH BITUMEN EMULSION ON JAMMU SRINAGAR ROAD (NH - 1A) LAID IN SEPTEMBER, 2007
GRAPHICAL
GRADATION
13
PRESENTATION
15
OF
AGGREGATE
15-16
evaluation of test sections was carried out periodically. The marginal aggregates
were used for construction of test sections in Mizoram.
The report is a part of the Council of Scientific & Industrial Research (CSIR)
Network Project COR-0013 and provides with the details of selection of test
sites, laboratory studies, laying of test sections with emulsion based cold mixes
with mechanized methods using hot mix plant (without heating facility), paver and
road roller; and their periodical performance evaluation. It sets forth the
recommendations for cold mix technology using cationic bitumen emulsion in
16
The slow set (SS-2) bitumen emulsion shall be used for preparation of
cold mix for PMC when using marginal aggregates instead of medium set
(MS) grade as provided in IRC-14.
17
1.
INTRODUCTION
Hot mix technologies involving use of bitumen serve the intended purpose but create
environment problems during production of mixes and laying. The other vital issues
associated with construction, maintenance and operation of road network are
materials and energy conservation, which is to be addressed by taking up research
and development activities. The road sector alone account for 71 % of total High
Speed Diesel (HSD) consumed which amount to about 32 million tones in a year,
the retail price of which is of the order of Rs. 60,000 crore. A mere 10 % saving
through better use of cost effective technologies mean a great deal to our economy.
Hot mixed bituminous macadam and bituminous concrete form various structural
layers of flexible pavements. The construction of these by conventional methods is
energy consuming and pollutes the environment. Cold mixes consume less energy
and does not create environmental pollution. The proposed R & D programme for
development of cold mix technology for structural layers address development of
suitable emulsions for open graded cold mixes, performance based mix design
methods and their validation by full scale field trials is of vital importance for our
country.
Bituminous road construction with conventional paving grades bitumen is
sometimes not feasible or even not desirable in high rainfall areas as intermittent
rain throughout the year affect production and laying of mixes. In cold climate of
snow-bound areas, the hot bitumen looses its temperature rapidly and its binding
property on contact with existing cold pavement surface. Cutback bitumen is,
therefore, specified to overcome such problems but requires a little heating and
is accompanied by emission of solvents used as cutter stock, which create
marginal environmental problems.
Slow but steady rise in consumption of bitumen emulsion has been registered
from 1930-1950s. With the enforcement of stringent environmental law in USA
and European countries the growth of emulsion consumption in road construction
noticed a rapid growth. Now bitumen emulsions are used world-wide for different
18
Annual Tonnage
Bitumen
Percentage
Bitumen
Emulsion
USA
3,166,000
28,000,000
11.31
FRANCE
1,200,000
2,800,000
43.0
SPAIN
440,000
1,600,000
27.5
GERMANY
168,000
2,780,000
6.0
JAPAN
334,996
4,418,000
7.6
SWEDEN
69,000
492,000
14.0
AUSTRALIA
80,000
807,000
9.91
AUSTRIA
21,000
386,000
5.4
BRAZIL
420,000
1,336,000
31.42
SOUTH AFRICA
120,000
300,000
40.0
MEXICO
45,000
266,360
16.9
SAUDI ARABIA
12,000
89,000
13.5
TURKEY
20,000
600,000
3.3
RUMANIA
30,000
200,000
15.0
INDIA
70,000
30,50,000
4.3
UK
140,000
3.0
19
The cold mix technology is not a new one in the field of highway engineering.
This technology is becoming more attractive due to awakening about
environmental protection. Significant research and development work in
developed countries and in our own country has brought out improved quality of
bitumen emulsion. Some considerations such as concern about environmental
pollution, increased cost of energy, limited time period available for road
construction and maintenance work with hot mixes, will make the cold mix
technology a viable option.
There are few technical reasons against cold mix technology namely quality of
bitumen emulsions, long setting time before allowing traffic on roads, nonavailability of appropriate specifications and construction machinery. In order to
find answer to these queries and thereby create confidence among the user
agencies to adopt this technology the present study has been undertaken.
In order to develop cold mix technology for structural layers of flexible pavement,
CRRI has undertaken the task activity as part of CSIR Core Network Project
0013. The test sections of structural layers with bitumen emulsion of Hindustan
Colas were laid in Rajasthan, Mizoram and J&K from 2007-2008. Hindustan
Colas requested CRRI for post construction performance evaluation of test
sections vide their letter No. HIN/NK/0016 dated 23.10.2009. The report has
been prepared based on laboratory and field studies for cold mix design ,
characterization of materials, construction of test sections with mechanized
methods using hot mix plant ( without heating facility), paver and road roller; and
their periodical performance evaluation.
.
20
2.
macadam
(BM)
as
base
course
and
semi-dense
bituminous concrete (SDBC) and mix seal surfacing (MSS) with cold
mixes
21
IRC: 110-2005
MOST-2001
Border Roads Organisation and other road building agencies provide surface
courses such as Dense Bituminous Concrete (DBC), Semi Dense Bituminous
Concrete (SDBC), Mix seal surfacing (MSS) and open graded Premix Carpet
22
23
The Dantaur- Khajuwala Road in Rajasthan passes through the plain terrain. The
existing road surface had developed distress in the form of cracking and
potholes. The detailed field investigation of the road indicated that overall crust
thickness consisted of 20mm premix carpet, 75mm water bound macadam,
120mm brick soling and 100mm kankar. Hence total crust thickness worked out
to 320mm. An equivalency factor of unity was assigned for existing black top
surfacing as it was in cracked and in fatique state. Field investigation and
laboratory indicated unsoaked CBR value of subgrade as 8%, and 3% when
soaked for four days. The traffic was reported 400 CVPD. Mostly buses and
Military armoured vehicles are plying on the road. As per IRC: 37-1984 CBR
value of subgrade in area where climate is arid throughout the year i.e. annual
rainfall is of the order of 50mm or less, may be determined in field condition. The
location of test track was selected from Km. 57.200 to km. 57.450 on DantaurKhajuwala Road.
The plan of the test tracks on Dantaur- Khajuwala Road (Rajasthan) is given in
Fig 1
24
DANTAUR
50mm BM
50mm BM
50mm BM
50mm BM
25mm SDBC
25mm MSS
25mm SDBC
25mm MSS
Bitumen
Bitumen
Emulsion
Emulsion
KM 57.200
4.2
0. 275
0.350
0.400
0.450
Aizawl By-pass Aizawl Road was taken up for field trials. The road stretch from
km 2.100 to 2.300 on Aizawl By-pass was selected for laying test sections with
bitumen emulsion. The plan of laying of test tracks on Aizawl By-pass Aizawl
Road is given in Fig 2
FIG 2:- TEST TRACK WITH BITUMEN EMULSION ON AIZAWL BY-PASS
AIZAWL ROAD LAID IN JUNE, 2007
HILL
TOP
KM 2.100
50mm BM
50mm BM
25mm SDBC
25mm MSS
Emulsion
Emulsion
KM 2.200
25
KM 2.300
4.3
BENIHAL
TUNNEL
KM 213.200
50mm BM
50mm BM
25mm SDBC
25mm SDBC
Emulsion
Emulsion
KM 213.300
26
KM 213.400
27
1)
2)
3)
Results
Obtained
0.01
30 - 150
108
28
Nil
0.4
+ve
NA
NA
1.6
Nil
65
89
90
99.5
Shelf Life Test : The shelf life test was conducted on emulsion by testing
emulsions after 6, 9 and 12 months and coagulation was not found which implies
that developed emulsions have shelf life of more than a year as required by BIS
standard. The particles of sizes in the range of 4-10 m were found after 6 month
which indicates stable emulsion (IS:8887-2004). The samples of bitumen
emulsion used in construction of test sections were evaluated for their properties
in accordance with IS: 8887- 2004. The coating test of aggregates suitability was
also carried out as per ASTM: D-2397. The test results of bitumen emulsion of
medium setting (MS) and slow setting (SS) grades are given in Table 3.
Table 3:Test Results of Bitumen Emulsion of Hindustan Colas for Trials
S.No
Properties of Bitumen Emulsion
Results
Requirement of
.
obtained
IS:8887-1995
MS
SS-2
MS
SS-2
i)
Residue on 600 micron IS sieve
0.01
0.01
0.05
0.05
(% mass)
max.
max.
ii)
Viscosity by Saybolt Furol Viscometer,
seconds
At 250C
33.0
20-100
At 500C
98
50-400
iii)
Coagulation of emulsion at low
Nil
Nil
Nil
Nil
temperature
iv)
Storage stability after 24 hrs. , %, max.
0.6
0.2
1.0
1.0
v)
Particle charge
+ve
+ve
+ve
+ve
vi)
Stability to mixing with coarse
<40
<5
aggregate, % coagulation
vii)
Coating ability and water resistance
(a) Coating, dry aggregates
Good
Good
Coating after spraying water
Fair
Fair
(b) Coating, wet aggregates
Fair
Fair
Coating after spraying water
Fair
Fair
viii)
Stability
to
mixing
cement,
X
1.1
<2
%coagulation
ix)
Miscibility with water (coagulation)
Nil
Nil
Nil
Nil
x)
Test on residue :
(a) Residue by evaporation, %
66.1
61.7
65 min.
50 min.
0
(b) Penetration, 25 C/100 gm/5 sec.
96
205
60-210
60-210
(c) Ductility, 270C/cm.,
100+
87
75 min.
75 min.
(d) Solubility In Trichloroethylene, %
99.0
99.5
97.5
97.5
min.
min.
29
Characterization of Aggregate
The aggregates were tested for gradation and their properties as per IS :
2386 and the gradation and properties are given below in Table 4. The
gradation was found in specified gradation( Fig. 4)
Table 4. Aggregate Gradation of Cold SDBC for Dantaur- Khajuwala
Road ( Rajasthan)
Sieve
size(mm)
19
13.2
9.5
4.75
2.36
1.18
0.6
0.3
0.15
0.075
20mm
size
0
0
0
0
0
0
0
0
0
0
0
10mm
size
0.7
70
70
68
19
3
0
0
0
0
0
Stone
Dust
0.3
30
30
30
30
29
20
19
11
5
5
Combined Specified
Grading
Grading
1
100
100
100
100
98
90-100
49
35-51
32
24-39
20
15-30
19
0
11
9--19
5
0
5
3--8
120
100
% Passing by Weight
Coarse
Gradation
Fine Gradation
80
Blend
Gradation
60
40
20
22
.4
13
.2
11
.2
5.
6
2.
8
0.
71
0.
18
0.
35
5
0
0.
09
5.3
30
5.4
For the determination of optimum water content for premixing, the quantity of
bitumen emulsion is first estimated using the following equation.
P = 0.05A+0.1B+0.5C
where ,
P = Quantity of bitumen emulsion, %
A = Percent aggregate retained on 2.8 mm sieve
B = Percent aggregate retained on 90 micron sieve
C = Percent aggregate passing on 90 micron sieve
Different batches of aggregates - emulsion mixes were prepared keeping
the above-predetermined quantity of bitumen emulsion constant and varying
the water content. The coated aggregates were visually observed for coated
area of aggregate with binder. The optimum water for SDBC was found 4.0 %
and BM 2.5% by weight of aggregates. However this quantity of optimum
water content may vary depending on site condition and quality of
aggregates. Similarly the premix water for MSS was found 3.0% by weight of
aggregate.
5.5 Marshall Specimens for SDBC with Emulsion
The Marshall test specimens were prepared with different bitumen emulsion.
1100gm graded aggregates were first moist with optimum water uniformly.
The 7 percent bitumen emulsion was then added to the wet aggregates and
mixed for 2 minutes for uniform binder coating. The cold mix was kept at 60oC
for three hours. The cured cold mix was then transferred into the Marshall
mould with a filter paper on base plate and compacted with 75 blows of
Marshall hammer on both faces. Similarly, the Marshall specimens were
prepared with optimum water content and other bitumen emulsion content of
8 and 9%. The Marshall specimens were extracted from the mould after 24
31
hours. Specimens were then cured in air oven at 400C for 72 hours. The
cured Marshall specimens were subjected to different tests such as bulk
density, stability and flow value in dry state at 250C. Different design
parameters like voids content, voids filled by binder will be calculated. The
properties of the cold mixes are given in Table 5.
Table 5 : Properties of Cold SDBC with Developed Emulsion
S. No.
5.6
Properties
8.0%
9.0%
Bitumen residue, %
4.2
4. 8
5.4
2.33
2.37
2.34
Voids, %
11
470
600
535
Flow, mm
8.2
7.2
determined with the bulk density , air voids and stability of Marshall specimens.
1 2 .5
12
1 1 .5
11
1 0 .5
10
9 .5
9
2 .2 0 0
2 .1 8 0
2 .1 6 0
2 .1 4 0
4 .0 3
4 .5 8
5 .1 2
a ir vo id s
2 .2 2 0
gm/cc
Bulk Density,
b u lk d e n s it y
5 .6 6
B in d e r C o n te n t, M ix
Fig . 2 -a : P r o p e r ty o f C o ld S D B C M ix
32
stab
VFB
55
800
50
600
400
45
200
0
VFB, Percent
Stability, kg
1000
40
4.03
4.58
5.12
5.66
The optimum emulsion content (SS-2) for Cold SDBC was 8% by weight
of aggregates for Rajasthan and J&K test section
The optimum emulsion content for Cold SDBC (SS-2) was 8% by weight
of aggregates for Marginal aggregate Mizoram test section
5.7
The cold mix design for BM was carried out with emulsion (SS-2) in similar
manner as given in above paras.
The aggregates were tested for gradation and their properties as per IS :
2386 and the gradation and properties are given below in Table5.
33
Rajasthan
BM
50mm
Sieve
size
20
mm
0.4
10
mm
0.45
Stone
dust
0.15
Combined
1
mid
ll
ul
40
40
21
1
0
0
0
0
0
45
45
45
35
5
0
0
0
0
15
15
15
15
15
15
7
3
1
100
100
81
51
20
15
7
4
1
100
95
72
0
26
12
0
6
4
100
90
56
0
16
4
0
2
0
100
100
88
0
36
19
0
10
8
26.5
19
13.2
9.5
4.75
2.36
1.18
0.3
0.075
(MoSRTH)
34
35
36
Photo 1: Distress condition of road before laying test section on DantaurKhajuwala Road (Rajasthan)
Photo 2: Unevenness condition of road before laying test section on DantaurKhajuwala Road (Rajasthan)
37
Photo 4: Distress condition in the form of ravelling on road before laying test
section on Dantaur- Khajuwala Road ( Rajasthan)
38
Photo 6: Site for Laying Test Sections on Dantaur- Khajuwala Road ( Rajasthan)
with Border Roads Organisation and Hindustan Colas
39
40
41
6.2
42
bitumen. The tack coat turned from brown colour to black in 15-20 minutes
depending upon weather condition.
6.2.4 Transportation of Cold Mixes
The cold mix was transported by dumper to site for construction for laying
cold mixed SDBC of test section. Due care was exercised to avoid early breaking
of emulsion in summer by putting wet gunny bags on cold mix.
6.2.5 Spreading and Compaction of Cold Mixes
The cold mix was transferred from dumper into paver bin for laying cold
mixed SDBC on Bituminous Macadam. For half road width, the cold mix was
spread over on tack coated area for thickness about 1/3 more than required
thickness by paver. The cold mix turns black from original brown colour after half
a hour when water of emulsion exudes after breaking of emulsion. The cold mix
was aerated for about one hour and then compacted with 8-10 ton road roller
(Photo 13). The rolling was done with the outside drive wheel covering equal
parts of the pavement and shoulder. The wheels of roller were kept wet with
water during compaction. The 8-9 passes shall be provided to achieve the
required compaction. The finished SDBC with emulsion was achieved
(Photo 14).
6.2.6 Traffic Control
The traffic was regulated at slow speed and test section was left open for
traffic after 3-4 hours. The traffic at some location could not be controlled at the
time of laying and traffic was allowed at slow speed as per IRC guidelines.
43
6.3
6.3.1 General
Preparation of road surface was executed as mentioned in section 6.2.
6.3.2 Preparation of Cold Mix
The blended aggregates of 10mm and 10mm aggregates in 60: 40 ratio
were charged into HMP mixer. The water content @ 3 per cent by weight of
aggregate was added into aggregates over conveyor belt to wet the aggregate
surface. The required quantity of bitumen emulsion of slow set SS-2 grade @ 7
% by weight of aggregates was then mixed with aggregates for two minutes.
Prolong mixing was avoided as it tends to decoat the binder from aggregate. The
cold mix was discharged into trolley for transportation to the to construction site
( Photo 15).
6.3.3 Laying Test Section
Tack coating, spreading of cold mix and compaction of cold mixed MSS
with 8-10 Ton road roller( Photo 16 & 17) were carried as per para 6.2. The
photo 18 indicates the finished Mix seal surfacing (MSS) with emulsion..
6.3.4 Traffic Control
The traffic was regulated and test section was left open for traffic after 4-5
hours. The traffic at some location could not be controlled after completion of
laying and traffic was allowed at slow speed as per IRC guidelines
44
Photo 11: Adding Water in Aggregates before Mixing with Bitumen Emulsion
for Cold Mix
Photo 12: Modification of Hot Mix Plant for supply of bitumen emulsion for
laying test section on Dantaur- Khajuwala Road ( Rajasthan)
45
46
47
48
6.4
It is a pointer to
performance grading such as good (G) when marks were above 80%,
satisfactory (S) (60% - 80%), poor (P) (40% - 60%) and bad (B) (below
40%). These ratings have been denoted as G, S, P and B respectively.
The typical results for grade of marks allotted against the test sections
of BM+ semi-dense bituminous concrete or mix seal surfacing is given
in Tables 6, 7 and 8.
The construction of test sections BM + SDBC and BM + MSS using
emulsion based cold mixes and reference sections BM + SDBC using
hot bitumen mixes on Dantaur- Khajuwala Road in desert area was
found good as indicated by the marks obtained in the range above 91
to 93 percent for SDBC in first inspection carried out just after
construction. The marks obtained were above 80 percent so this was
placed in Good (G) rating. The 2nd Inspection indicated the good
performance of sections of SDBC / MSS with emulsion ( Photos 19 &
22) and with bitumen respectively. The evaluation of test sections in 3rd
inspection after two years showed negligible distress (Photo 23 & 24).
49
Table 6 :
S.
No.
Factor
Bitumen
Performance
Marks
1
MSS
R
Aggregate
Surface
texture
Cracking
Pot. Holes
Surface
Evenness
Ravelling
Stripping
i) Normal
ii) Slightly dry/rich
iii) Dry/rich
iv) Very dry/rich
I) Normal
II) Less
III) Excessive
i) Good
ii) Satisfactory
iii) Smooth
iv) Coarse
i) No crack
ii) Fine hair cracks
iii) Localised cracks
iv) Scattered cracks
v) Extensive cracks
i) None
ii) Very few
iii) Scattered
iv) Extensive
i) Good
ii) Satisfactory
iii) Poor
iv) Very poor
i) None
ii) Very few
iii) Some
iv) Extensive
i) None
ii) Very few
iii) Medium
iv) High
Total Marks
10
7
5
3
10
5
3
10
7
5
3
10
7
5
3
1
10
7
5
3
10
7
5
3
10
7
5
3
10
7
5
3
Max. marks %
% Marks
Test sections
2
3
SDBC
MSS
R
T
9.2
9.2
10
10
10
10
9.5
9.0
10
10
73.5
73
74.4
74
80
80
80
80
92
91
93
93
Grading
Good
more than 80%
Satisfactory
60-80%
Poor
40-60%
Bad
less than 40%
T - Test Section with Emulsion.
R - Control (Reference) Section Dr. N.K.S. Pundhir, CRRI Naresh Prasad (AEE Civil) BRO
50
4
SDBC
T
Table 7:
S.
No.
Factor
Bitumen
Performance
Marks
1
MSS
R
Aggregate
Surface
texture
Cracking
Pot. Holes
Surface
Evenness
Ravelling
Stripping
v) Normal
vi) Slightly dry/rich
vii) Dry/rich
viii) Very dry/rich
IV) Normal
V) Less
VI) Excessive
v) Good
vi) Satisfactory
vii) Smooth
viii) Coarse
vi) No crack
vii) Fine hair cracks
viii) Localised cracks
ix) Scattered cracks
x) Extensive cracks
v) None
vi) Very few
vii) Scattered
viii) Extensive
v) Good
vi) Satisfactory
vii) Poor
viii) Very poor
v) None
vi) Very few
vii) Some
viii) Extensive
v) None
vi) Very few
vii) Medium
viii) High
Total Marks
10
7
5
3
10
5
3
10
7
5
3
10
7
5
3
1
10
7
5
3
10
7
5
3
10
7
5
3
10
7
5
3
Test sections
2
3
SDBC
MSS
R
T
4
SDBC
T
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
71
73
71
72
Max. marks %
80
80
80
80
% Marks
89
91.3
89
90
Grading
Good
more than 80%
Satisfactory
60-80%
Poor
40-60%
Bad
less than 40%
T - Test Section with Emulsion.
R - Control (Reference) Section Naresh Prasad (AEE Civil) BRO
51
Table 8 :
S.
No.
Factor
Performance
Marks
1
MSS
R
Bitumen
Aggregate
Surface
texture
Cracking
Pot. Holes
Surface
Evenness
Ravelling
Stripping
i) Normal
ii) Slightly dry/rich
iii) Dry/rich
iv) Very dry/rich
i) Normal
ii) Less
iii) Excessive
i) Good
ii) Satisfactory
iii) Smooth
iv) Coarse
i) No crack
ii) Fine hair cracks
iii) Localised cracks
iv) Scattered cracks
v) Extensive cracks
i) None
ii) Very few
iii) Scattered
iv) Extensive
i) Good
ii) Satisfactory
iii) Poor
iv) Very poor
i) None
ii) Very few
iii) Some
iv) Extensive
i) None
ii) Very few
iii) Medium
iv) High
Total Marks
10
7
5
3
10
5
3
10
7
5
3
10
7
5
3
1
10
7
5
3
10
7
5
3
10
7
5
3
10
7
5
3
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
68
68
68
66
Max. marks %
80
80
80
80
% Marks
85
85
85
83
Grading
Good
more than 80%
Satisfactory
60-80%
Poor
40-60%
Bad
less than 40%
T - Test Section with Emulsion.
R - Control (Reference) Section
Neeraj Chaube
(Supdt B/R II-BRO)
52
Photo 19: SDBC with Emulsion After One Year Service Life
Photo 20: MSS with Emulsion After One Year Service Life
53
Photo 21: SDBC with Emulsion After One Year Service Life
Photo 22: MSS with Emulsion After One Year Service Life
54
Photo 23: SDBC with Emulsion After Two Year Service Life
Photo 24: MSS with Emulsion After Two Year Service Life
55
7.0
7.1
56
off leaving behind the residual bitumen on the road surface. The road surface
was made wet or damp if found dry, before applying the tack coat with emulsion.
7.1.4 Transportation of Mix
The cold mix was then discharged in wheel barrow and transported to
construction site for spreading cold mix on tacky road surface. Due care was
exercised to avoid taking wheel barrows on newly laid surface.
7.1.5 Spreading and Compaction of Cold Bituminous Mix
The cold mix was put into paver for spreading on half of road width (Photo 28).
The cold mix was laid over the tacky surface and spread uniformly by paver
(Photo 29) in required thickness of about 75 mm loose mix to get 50mm
compacted BM layer. The cold mix turns black from brown colour after some time
when water of emulsion exudes after breaking of emulsion. The cold mix was
aerated for about two hours and then rolled with 8-10 tones three-wheel roller to
compact the cold mix to achieve BM layer ( Photo 30). The rolling was done with
the outside drive wheel covering equal parts of the pavement and shoulder. The
wheels were kept wet with water during compaction. The rolling was also
repeated after 2 hours.
7.1.6
Traffic Control
The traffic was regulated and test section was left to open for traffic after 4 -5
hours. The traffic at some test sections could not be controlled after completion
of laying and hence, it was allowed at slow speed as per IRC guideline.
57
Photo 25: Examination of Bitumen Emulsion for Coagulation before its Use
58
Photo 28: Transfer of Cold Mix in Paver for laying Bituminous Macadam
59
60
61
62
7.2.7
63
Table 9 :
S.
No.
Factor
Bitumen
Aggregate
Surface
texture
Cracking
Pot. Holes
Surface
Evenness
Ravelling
Stripping
Performance
Marks
4
SDBC
T
9
10
10
10
10
74
Max. marks %
73
80
80
% Marks
91
93
i) Normal
ii) Slightly dry/rich
iii) Dry/rich
iv) Very dry/rich
i) Normal
ii) Less
iii) Excessive
i) Good
ii) Satisfactory
iii) Smooth
iv) Coarse
i) No crack
ii) Fine hair cracks
iii) Localised cracks
iv) Scattered cracks
v) Extensive cracks
i) None
ii) Very few
iii) Scattered
iv) Extensive
i) Good
ii) Satisfactory
iii) Poor
iv) Very poor
i) None
ii) Very few
iii) Some
iv) Extensive
i) None
ii) Very few
iii) Medium
iv) High
Total Marks
Grading
Good
Satisfactory
Poor
Bad
T - Test Section with Emulsion.
10
7
5
3
10
5
3
10
7
5
3
10
7
5
3
1
10
7
5
3
10
7
5
3
10
7
5
3
10
7
5
3
64
65
66
67
68
using
performance
evaluation
proforma
by
individual
officers
69
70
71
72
73
outside drive wheel covering equal parts of the pavement and shoulder. The
wheels were kept wet during compaction. The rolling was also repeated after 2
hours. The finished BM layer was achieved (Photo 50)
8.1.6 Traffic Control
The traffic was regulated and test section was left to open for traffic after 4 -5
hours. The traffic at some test sections could not be controlled after completion
of laying and hence, it was allowed at slow speed as per IRC guideline.
8.2
74
Traffic Control
The traffic was regulated and test section was left to open for traffic after 2-3
hours. The traffic at some test sections could not be controlled after completion
of laying and hence, it was allowed at slow speed as per IRC guideline.
8.2.7 Performance of Semi Dense Bituminous Concrete / MSS with
Bitumen Emulsion:
The first inspection of test section just after construction showed good
construction taking into account of performance factors. The test section was
completely covered with snow in the month of February and section was wet for
more than two months. The 2nd inspection after 6 month showed that
performance of test section SDBC / MSS with emulsion was satisfactory
(Photos 53 & 54).
75
Photo 45: View of Display Board for Field Trial on NH1A near
Srinagar
76
77
78
79
80
9.0
2)
20mm:10mm:SD: water: emulsion :: 0.50 : 0.35: 0.15
by weight of mix
Also, hot mixes require LDO for the heating up of aggregates and bitumen.
The amount of LDO required is taken as 5% of the total mix produced, i.e. 5%
of 350m.
The total amount of these materials required and cost of layer for the 50mm thick
compacted BM mix is given in following Table 11.
Table 11: Cost Analysis of Cold Mix and Hot Mix Bituminous Macadam
Material for 50mm
Amount
Thick BM
required
Rate
mix layer
mix layer
(Rs.)
(Rs.)
20mm aggregate
207.5m
28/cft
205151
205151
10mm aggregate
180m
28/cft
177912
177912
Stone Dust
77.5m
30/cft
82096
82096
Water
18200 lit.
0.20/lit
3640
Bitumen emulsion
40974 kg.
24/kg
983376
Bitumen
25025 kg
28/kg
700700
250 kg
150 / kg
154000 lit.
30/lit
462600
514 MT
36/MT
18504
18504
1251
28/kg
Anti-stripping Agent
37500
( 1 % of bitumen)
Heating (LDO), 3%
Transportation,
Laying& compaction
Waste Bitumen (5%)
35035
Total
1470679
1719498
210
246
Hence, the cold mix BM layer works out to be approximately 17% more cost
effective as compared to the hot mix layer.
82
Amount
Thick SDBC
required
Rate
mix layer
mix layer
(Rs.)
(Rs.)
10mm aggregate
178.5 m
28/cft
176479
173019
Stone Dust
76.5.m
30/cft
75634
75634
Water
10000 lit.
0.20/lit
2000
Bitumen emulsion
30590 kg.
24/kg
734160
Bitumen
20125
28/kg
563500
Anti-stripping Agent
200 kg
150/kg
30000
12500lit.
30/lit
375000
255 MT
36/MT
9180
9180
1006
28/kg
( 1 % of bitumen)
Heating (LDO), 3% of
mix
Transportation,
Laying& compaction
Waste Bitumen (5%)
28175
Total
993993
1254508
142
179
Hence, the cold mix SDBC layer works out to be approximately 26% more cost
effective as compared to the hot mix layer.
83
Based on the study, the cost of construction of different specifications with cold
mix technology and hot mix technology was calculated and given below:
S. No.
Specification
Thickness,
Binder
mm
Cost / m2,
Rs.
SDBC
25
Bitumen
142
SDBC
25
Emulsion
179
BM
50
Bitumen
246
BM
50
Emulsion
210
84
10.
CONCLUSIONS
The slow set (SS-2) bitumen emulsion shall be used for preparation of
cold mix for PMC when using marginal aggregates instead of bitumen
emulsion of medium set (MS) grade as provided in IRC-14..
85
11.
RECOMMENDATIONS
(i)
(ii)
(iii)
(iv)
(v)
(vi)
The cold mix shall be covered with wet empty gunny bags to
prevent from early setting and hardening
(vii)
(i)
(ii)
(iii)
(iv)
(v)
(vi)
(vii)
86
(i)
(ii)
(iii)
(iv)
(v)
(vi)
87
Annexure - 1
Proposed Tentative Specification for Bituminous Macadam (Base and
Binder Course) with Cationic Bitumen Emulsion
1.0 INTRODUCTION
Bituminous road construction with conventional paving grade bitumen is
sometimes not feasible or desirable in high rainfall areas as intermittent rains
throughout the year affect the production and laying of hot mixes. In snow-bound
areas and at high altitude, hot mixes get solidified quickly and loose binding
properties due to the existing pavement surface getting cold within short time.
Presently, there is no construction specification available in the country for
bituminous macadam (BM) with cationic bitumen emulsion as the binder, which is
expected to have great application in future. It is, therefore, imperative to develop
specification for BM with bitumen emulsion. the R & D studies had been
undertaken in the country to develop specification by conducting laboratory
studies and field trials in different climatic conditions of India.
Bituminous macadam shall consist of the construction of one or more courses of
compacted crushed aggregates, premixed with a bituminous binder, laid
immediately after mixing. It is an open graded mix suitable for base and binder
courses and should not be used as a wearing course as such. It may be used as
a temporary riding surface when covered with an appropriate seal coat.
The tentative specification has been prepared with inputs from
Dr. N.K.S.
Pundhir, Scientist, CRRI based on the results obtained from the laboratory study
and a number of field trials carried out by CRRI, BRO, PWD Mizoram and oil
companies (IOCL and Hindustan Colas Ltd.)
This tentative specification is intended to indicate what is considered to be a
good practice for construction of bituminous macadam (base and binder course)
under average operating conditions.
88
2.0
SCOPE
2.1
This draft specification deals with the basic outline for the design and
construction needed to lay Bituminous Macadam (BM) mix as base
course for highways using cationic bitumen emulsion. It only highlights
the essentials so as to be of use while preparing the contractual
documents for specific job and is not intended to be a detailed code of
practice.
2.2
3.0 MATERIALS
3.1
Aggregates
The aggregates shall consist of crushed stone, crushed slag, crushed gravel
(shingle) or other stones, as specified. The aggregates shall have clean, strong,
durable and fairly cubical fragments free from disintegrated pieces, organic and
other deleterious matter. The aggregates shall preferably be hydrophobic and of
low porosity.
3.1.1
89
Binder course
35
50
30
40
12
30
25
12
30
25
Where all or some of these requirements can not be satisfied, it is left to the
Engineer-in-charge to allow reasonable tolerances.
The use of low grade aggregates by improving their qualities shall also be
considered.
3.1.2 Grading of Aggregates: The aggregates for the bituminous macadam
for different thicknesses shall conform to the grading, as given in Table 1.
Table 1 : Compacted Thickness of 50 mm
Sieve Size, mm
26.5
22.4
13.2
11.2
5.6
2.8
0.090
Bitumen Emulsion (SS-2) by
wt. of mix
75 (min.)
IS : 8887:2004 (Annexure F)
2 (max.)
sulphate),%
Soundness (Loss with Magnesium
sulphate)
90
3.1.4 Fine Aggregates: The fine aggregates shall be the fraction passing 2..36
mm sieve and retained on 75 micron sieve. These shall consist of crushed
screenings, natural sand or a mixture of both and shall be clean, hard, durable,
uncoated and free from injurious, soft or flaky pieces and organic or deleterious
matter.
3.1.5
75 micron sieve) shall be stone dust, cement, hydrated lime or other approved
non-plastic mineral matter.
3.2
Cationic Bitumen Emulsion
The bitumen emulsion for preparation of cold mix BM shall be Slow setting grade
(SS-2), conforming to IS: 8887 2004. For tack coating, Rapid setting (RS-1) or
Slow setting (SS-2) grade of bitumen emulsion, conforming to IS: 8887- 2004,
shall be used. The bitumen emulsion should not be stored below 0oc and it shall
be thoroughly mixed by rolling the drum to and fro upto a distance of 10 metre for
five minutes before manufacturing cold mixes for road construction. The shelf life
of bitumen emulsion should be such that it meets the physical requirements, as
given in Table 2, at the time of its use. During prolonged storage of emulsion
(say about a year), the drum shall be kept in shade and rolled two or three times
to and fro upto 8-10m distance once in a month. The bitumen emulsion should
satisfy the various properties, as given in Table 3.
Table 3 : Properties of Cationic Bitumen Emulsion
S No.
i
ii
iii
iv
v
vi
vii
Specified Values
RS-1
SS-2
0.05
0.05
20-100
Nil
2.0(max.)
+ve
No
91
30-150
Nil
2.0(max.)
+ve
2(max.)
No
viii
(d)
(e)
Tests on residue :
Residue by evaporation, (%)
Penetration, d mm at 250C/100 gm/5 sec.
Ductility, 270C/(cm)
Solubility in Trichloroethylene (%)
60(min.)
80-150
50 (min.)
98(min.)
4.0
4.1
Aggregates
60(min.)
60-120
50(min.)
98(min.)
Binder
4.2.1
Premixing
The bitumen emulsion (SS-2) required for premixing of the bituminous macadam
shall be at the rate specified depending on the gradation of aggregates. The upper
limit may be raised when absorptive types of aggregates are used, and the exact
rate shall be specified by the Engineer-in-charge.
4.2.2
Tack coat
If and when required, the quantity of bitumen emulsion (RS-1 / SS-2), needed for
the tack coat, shall be between 3.0 to 3.5 kg. per 10 m2 on primed Water Bound
Macadam surface.
5.0
5.1 While the laboratory cold mix design gives different proportions of the mineral
aggregates combination in terms of individual sieve sizes, blending of two or
more sizes of aggregates (each size having within it a range of individual sieve
sizes) would be necessary for actual operational purpose in the field. This
blending ratio is obtained on a weight basis, giving the percent weight of coarse
aggregate, fine aggregate and filler needed to give the ultimate basis based on
the unit weight or bulk density of the aggregate supplied. The mineral aggregate
92
combination together with the optimum premixing water content and bitumen
emulsion content, as determined in the laboratory, constitutes the job mix formula
for implementation during construction.
5.2
practice, the mix design shall be worked out based on a correct and truly
representative sample of the materials that will actually be used in the specific
construction project.
The detailed procedure for job mix formula for BM, using cationic bitumen
emulsion, is given in Annexure-I
6.0
CONSTRUCTION
93
6.5
Preparation of Base
The base over which the cold mix bituminous macadam is to be laid shall be
completely free from dust, caved mud etc, before its laying. Where the existing
base is having potholes or rutting, the irregularities shall be properly corrected. If
the existing base is extremely irregular and wavy, it may be considered worthwhile to lay a cold mix bituminous leveling course (Profile corrective course) of
adequate thickness.
6.6
Tack coat
For tack-coat, bitumen emulsion of Rapid setting (RS-1) grade may be used.
The bitumen emulsion is applied on an existing pavement, preferably on damp
surface, at the rate of 3.0 to 3.5 kg per 10 sq.m area if the surface is hungry and
dry and 3.5 to 4 kg. per 10 sq.m. area on a normal bituminous base. The tack
coat with emulsion shall be applied not earlier than 10 minutes before laying the
cold mix.
6.7
6.7.1 It is imperative to prepare the cold mix of proper and uniform quality for
bituminous macadam by using cold mix plant or hot mix plant without heating
arrangement. The plant may be either a batch mix type or a continuous type /
drum mix type having two-stage mixer.
6.7.2 The coarse aggregates shall be charged first into the operating mixer / pug
mill followed by the addition of optimum water content on conveyor belt leading to
mixer and then adding the required quantity of bitumen emulsion (SS-2). The
above ingredients shall be mixed for about one minute to achieve the uniform
coating. Thereafter, fine aggregates including filler shall be charged into the
coated coarse aggregates and allowed to mix for about one minute. The cold mix
shall be discharged for further loading on to the tipper / trolleys.
94
6.8
Spreading of Mix
6.8.1 The cold mix shall be transported from plant site by tipper trucks to the
laying site and the spreading will be done preferably by means of a self
propelled mechanical paver with suitable speed capable of spreading, tamping
and finishing the mix, true to the proper grade, line and cross-section. The mix
should be spread in such a manner that, after compaction, the required thickness
of surfacing layer is laid uniformly.
6.8.2 Longitudinal joints and edges shall be constructed true to the line,
marking parallel to the centre line of road. Longitudinal joints should be offset
atleast by 150 mm from those in binder course, if any, and transverse joints or
construction joints shall be placed in the original thickness of previously laid mix.
The vertical cut face shall be painted with bitumen emulsion prior to the laying of
fresh mix against it.
6.9
Compaction
The paver/manual laid cold mix, after becoming black from brown colour of
original mix due to breaking of emulsion on surface of coated aggregate, shall
be thoroughly and uniformly compacted through a set of rollers at a speed of
not more than 5 km per hour. The initial or break down rolling shall be done
with 8-12 tonne three wheel steel roller and the surface finished by final
rolling with 8-10 tonne tandem roller. Before finishing with tandem roller,
break down rolling shall preferably be followed by an intermediate smooth
wheel pneumatic roller of 15 to 30 tonne capacity having a tyre pressure of 7
kg. / sq.cm. The joints and edges shall be rolled with 8-12 tonne three wheel
roller. All the compaction operations i.e. breakdown rolling, intermediate
rolling and finish/final rolling can be accomplished by using a vibratory roller
of 8-10 tonne static weight. During finish rolling, the vibratory system shall be
switched off. The wheels of the roller shall be kept moist to prevent the mix
from sticking to them. Rolling shall commence longitudinally from edges and
progress towards the centre except on super elevated portions where it shall
progress from lower to the upper edge. Rolling shall be continued till the
95
desired density (of not less than 98 per cent of the laboratory design density)
is achieved and all roller marks are eliminated.
6.10
Opening to Traffic
Traffic may be allowed after 3-4 hours after the mix has set in the finished
surface and is not be picked up by the vehicles.
7.0
7.1
OUALITY CONTROL
Adequate quality control at every stage of the work is essential and as such
a field laboratory must be set up to ensure the following controls:
7.1.1 Periodic sieve analysis of each type of aggregate at feeder end should
be made to see that the gradation of aggregate follows reasonably the
original gradation of job mix designed. The number of samples per day would
depend upon the bulk supply of aggregates made in a day at the plant site.
The physical proportions of different constituent materials should be decided
to achieve the gradation, as given in Table 2. The characteristics of these
materials shall be determined at the rate of one test for every 50-100 m3 of
aggregates or as directed by the Engineer-In-Charge.
7.1.2
96
(iii) Sieve analysis of aggregates after the bitumen is extracted shall be done to
determine the gradation.
7.1.5 The permissible variation of the individual percentages of various
ingredients in the actual mix from the job mix formula shall be within the
limits indicated below in Table 4.
Table 4: Permissible Variations from Job Mix Formula
Permissible Variations by
S. No.
Description
1.
# 8
2.
# 7
5.
# 4
6.
# 3
7.
Bitumen residue
3.
4.
# 6
# 5
# 0.3
7.1.6 For every 700 m2 or less of compacted surface, one field density test
should be conducted to determine the density of mix as laid, compacted and
finished. The density shall not be less than 98 percent of the maximum laboratory
density.
7.1.7 The longitudinal profile of the finished surface shall be tested with a 3m
straight
edge,
The mix shall not be laid when the atmospheric temperature is less than 8c
and when it is raining heavily. The BM can, however, be laid on a damp
surface.
97
Enclosure- I
COLD MIX DESIGN OF BITUMINOUS MACADAM (BM)
I.
Evaluation of Materials
98
II.
S.No
.
1.
2.
3.
4.
Properties
99
Annexure - 2
PROPOSED TENTATIVE SPECIFICATION FOR SEMI-DENSE BITUMINOUS
CONCRETE (SDBC) USING CATIONIC BITUMEN EMULSION
1.0
INTRODUCTION
Use of cold mixes in road construction eliminate emissions and reduce fuel
requirement leading to conservation of energy at the mixing plant. Construction
of .bituminous road with conventional paving grade bitumen is sometimes not
feasible or desirable in difficult areas such as high rainfall areas as intermittent
rains throughout the year affect the production and laying of hot mixes. In snowbound areas and at high attitude, hot mixes get solidified quickly and loose
binding property due to the existing pavement surface getting cold within short
time. presently, there are no construction specifications available in the country
for semi-dense bituminous concrete (SDBC), mix seal surfacing (mss) and
bituminous macadam (BM) with bitumen emulsion, which are expected to have
great applications in the near
prepared with
inputs from
Dr. N.K.S. Pundhir, Scientist, CRRI, based on the results obtained from the
laboratory study and a number of field trials carried out by CRRI, BRO and Oil
Companies such as Indian Oil Corporation and Hindustan Colas Ltd.
100
2.0
2.1
SCOPE
This draft specification deals with the basic outline for the design and
construction needed to lay Semi-dense bituminous concrete (SDBC)
mixes as wearing course on highways using bitumen emulsion. It only
highlights the essentials so as to be of use while preparing the
contractual documents for specific job and is not intended to be a
detailed code of practice.
2.2
3.1
DESIGN CRITERIA
(i)
(ii)
(iii)
(iv)
(v)
Notes:
75
400
8 (max.)
5 10
6.0 8.0
101
4.0
4.1
MATERIALS
22.4 mm
--
100
13.2 mm
100
79-100
11.2 mm
88-100
68-90
5.6 mm
42-64
33-55
2.8 mm
22-38
22-38
0. 710 mm
11-24
6-22
0. 355 mm
7-18
4-14
0. 180mm
5.13
2-9
0.090 mm
3-9
0-5
102
4.2
emulsion conforming to IS: 8887- 2004 shall be used for tack coat. Bitumen
emulsion should not be stored below 0oc and it shall be thoroughly mixed by
rolling the drum to and fro upto a distance of 10 meter for five minutes before
manufacturing cold mixes for road construction. The shelf life of bitumen
emulsion should be such that it meets the physical requirements, as given in
Table 3, at the time of its use. During prolonged storage of emulsion (about a
year), the drum shall be kept in shade and rolled two or three times to and fro
upto 8-10m distance once in a month. The bitumen emulsion should satisfy
various properties, as given in Table 3.
iii
iv
v
vi
vii
viii
103
Specified Values
RS-1
SS-2
0.05
0.05
20-100
Nil
2.0
+ve
30-150
Nil
2.0
+ve
NA
2 (max.)
No
No
60(min.)
80-150
50 (min.)
98(min.)
60(min.)
60-120
50(min.)
98(min.)
(Percent
Test Method
Maximum)
Aggregate Impact value
30
40
30
Coating value
75
Water Absorption,
12
IS : 2386 (Part V)
18
IS : 2386 (Part V)
sulphate)
Soundness, (Loss with Magnesium
sulphate)
4.2.3 Fine aggregate: The fine aggregate shall be the fraction passing 2..8 mm
sieve and retained on 90 micron sieve, and shall consist of crushed screenings,
natural sand or a mixture of both. It shall be clean, hard, durable, uncoated and
free from injurious, soft or flaky pieces and organic or deleterious matter.
4.2.4 Filler :
104
5.0
5.1
While the laboratory mix design gives different proportion of the mineral
practice, the cold mix design shall be worked out based on a correct and truly
representative sample of the materials that will actually be used in the specific
construction project.
The detailed procedure evolved for job mix formula for Semi Dense Bituminous
Concrete using cationic bitumen emulsion, is given in Annexure-I
6.0
6.1
CONSTRUCTION
The base over which the cold mix semi-dense bituminous concrete is to be laid
shall be completely free from dust, caved mud etc, before laying the surface
course. Where the existing base is having potholes or ruttings, the irregularly
shall be corrected. If the existing base is extremely irregular and wavy, it may be
considered worthwhile to lay a cold mix bituminous levelling course (Profile
corrective course) of adequate thickness to avoid an excessive use of costly
surface course.
105
6.2
Tack coat : For tack-coat, bitumen emulsion of rapid setting (RS-1) grade
concrete by using cold mix plant or any other suitable mixer of adequate capacity
to yield a cold mix of proper and uniform quality. The plant may be either a batch
type or a continuous one having a two-stage mixer.
The coarse aggregate shall be charged first into the operating mixer / pug mill
followed by addition of optimum water content on conveyor belt leading to mixer
and then required quantity of bitumen emulsion (SS-2). The above ingredients
shall be mixed for about one minute for uniform coating. Then fine aggregate
including fillers shall be charged into the coated coarse aggregate and allowed to
mix for about one minute. The cold mix shall be discharged for further loading on
tipper / trolleys.
6.4
laying site and the spreading will be done preferably by means of a self propelled
mechanical paver with suitable speed capable of spreading tamping and finishing
the mix true to proper grade, line and cross-sect ion. The mix should be spread in
such a manner that after compaction, the required thickness of surfacing layer is
uniformly laid.
106
Compaction
The paver/manual laid cold mix, after becoming black from brown
roller
and
the
surface finished by final rolling with 8-10 tonne tandem roller. Before
finishing with tandem roller, break down rolling shall preferably be followed by
an intermediate smooth wheel pneumatic roller of 15 to 30 tonne having a
tyre pressure of 7 kg. /sq.cm. The joints and edges shall be rolled with 8-12
tonne three wheel roller. All the compaction operations i.e. breakdown rolling,
intermediate rolling and finish rolling can be accomplished by using a
vibratory roller of 8-10 tonne static weight. During finish rolling, the vibratory
system shall be switched off. The wheels of the roller shall be kept well moist
to prevent the mix from sticking to them. Rolling shall commence
longitudinally from edges and progress towards the centre except on super
elevated portions where it shall progress from lower to the upper edge, to the
centre line of pavement. Rolling shall be continued till the desired density of
not less than 98 per cent of the laboratory design density is achieved and all
roller marks are eliminated.
6.6
Opening to Traffic
Traffic may be allowed after 3-4 hrs after ensuring the setting of mix in the
finished surface and the mix should not be picked up by vehicles.
107
7.1
7.1.1 Periodic sieve analysis of each type of aggregate at feeder end should
be made to see that the gradation of aggregate reasonably follows the
original gradation of job mix designed. The number of samples per day would
depend upon the number of bulk supply of aggregates made in
a day at
the plant site. The physical proportion of different constituent materials should
be decided to achieve the gradation, as given in Table 2. the characteristics
of these materials shall be determined at the rate of one test for every 50-100
m3 of aggregates or as directed by the Engineer-In-Charge.
7.1.2
graded aggregate.
7.1.4 At least one sample for every 100 tonnes of cold mix discharged at the
pugmil chute or a minimum of one sample per plant per day shall be collected
and the following tests shall be carried out.
(i) Three Marshall specimens shall be compacted, extracted from the mould after
overnight and then cured at 40c for 3 days. These specimens shall be tested for
average stability, flow, voids content and density. The values should be close to
the laboratory design values.
(ii) Bitumen shall be extracted from about 1000 gm of the mix and bitumen
content determined.
(iii) Sieve analysis of aggregates after the bitumen is extracted shall be done and
gradation determined.
7.1.6 The permissible variation of the individual percentages of various
108
ingredients in the actual mix from the job mix formula shall be within the
limits indicated below in Table 5
Table 5: Permissible Variations from Job Mix Formula
Permissible Variations by
S. No.
Description of Ingredient
1.
# 8
2.
# 7
5.
# 4
6.
# 3
7.
Bitumen residue
3.
4.
# 6
# 5
# 0.3
7.1.6 For every 700 m2 or less of compacted surface, one field density test
should be conducted to determine the density of mix as laid, compacted and
finished. The density shall not be less than 98 percent of the maximum laboratory
density.
7.1.7 The longitudinal profile of the finished surface shall be tested with a 3-m
straight edge, parallel to the centre line and the transverse profile with a camber
template. Any irregularity greater than 6 mm shall be corrected. The longitudinal
profile of the finished surface shall also be tested with a roughometer /
profilometer and it should be ensured that the roughness shall not exceed 2500
mm per kilometer.
8.0
109
Enclosure-2
COLD MIX DESIGN OF SEMI DENSE BITUMINOUS CONCRETE (SDBC)
I.
Evaluation of Materials
Specific gravity
Aggregate Impact Value
Water Absorption
(ii) Testing of Bitumen Emulsion : The samples of slow setting bitumen emulsion
(SS-2) to be used for construction of SDBC shall be evaluated as per IS : 88872004. The coating test of aggregates suitability should also be carried out as per
ASTM: D-2397 or AASHTO: M208.
(iii) Optimization of Premixing Water Content : For determination of optimum
water content for premixing, the quantity of bitumen emulsion is first determined
using the following expression.
P = 0.05A+0.1B+0.5C
where ,
P = Quantity of bitumen emulsion, %
A = Percent aggregate retained on 2.8 mm sieve
B = Percent aggregate retained on 90 micron sieve
C = Percent aggregate passing on 90 micron sieve
Different batches of aggregates - emulsion mixes are then prepared keeping the
quantity of bitumen emulsion constant (as determined from the above equation)
and varying the water content. The coated aggregates are visually observed for
coated area of aggregate with binder. The optimum water content is the water
content at which maximum coating of aggregate with water is observed. This
water content is taken as premix water content in designing the cold mix semi
110
dense bituminous concrete. The optimum water content for SDBC is found to be
3- 4% by wt. of aggregate. However, this quantity of optimum water content may
vary depending on site conditions and quality of aggregates.
III.
S.No
.
5.
6.
7.
8.
9.
10.
11.
12.
13.
Properties
Bitumen residue, %
Bulk density, gm/cc
Volume of Agg., %
Volume of binder, %
Voids, %
Voids in Mineral Aggregate (VMA), %
Voids Filled with Binder (VFB), %
Stability, kg. at 250C
Flow, mm
111
Annexure- 3
PROPOSED TENTATIVE SPECIFICATION FOR MIX SEAL SURFACING
(DENSE-GRADED PREMIX CARPET) WITH CATIONIC BITUMEN
EMULSION
1.0
INTRODUCTION
indicate that Mix seal surfacing (MSS) with cationic bitumen emulsion can be
laid successfully using the same machineries and plants as used for hot mix
type construction
tentative
specification
has
been
prepared
with
inputs
from
Dr. N.K.S. Pundhir, Scientist, CRRI based on the results obtained through the
laboratory studies and field trials.
112
2.0
2.1
SCOPE
This draft specification deals with the basic outline for the design and
construction needed to lay 25mm thick Mix seal surfacing (MSS) using
bitumen emulsion as wearing course for highways. It only highlights the
essentials so as to be of use while preparing the contractual documents
for specific job and is not intended to be a detailed code of practice.
2.2
Mix seal surfacing (MSS) shall be used as wearing course and shall not
be laid directly over WBM or any granular base course. The item shall
consist of mineral aggregates and cationic bitumen emulsion of Slow
setting grade (SS-2) mixed in a cold mix plant/any other suitable mixer
and laid with paver / manually on a previously prepared base, in
accordance with the specifications and conforming to the lines, grades
and cross-sections.
3.0
3.1
MATERIALS
Slow setting (SS-2) grade complying with IS 8887-2004. For tack coat , Rapid
setting (RS-1) grade of cationic bitumen emulsion, complying with IS 8887-2004,
shall be used or as directed by the Engineer.
The bitumen emulsion shall satisfy the various properties, as given in Table 1.
113
S
Properties of Bitumen Emulsion
RS-1
SS-2
0.05
0.05
ii
iii
20-100
Nil
30-150
Nil
iv
2.0
2.0
(max.)
(max.)
+ve
+ve
No.
Particle charge
vi
vii
viii
3.2
2 (max.)
No
No
60(min.)
80-150
50 (min.)
98(min.)
60(min.)
60-120
50(min.)
98(min.)
114
2 (max.)
sulphate)
Soundness, (Loss with Magnesium
sulphate)
3.3
Fine Aggregate: The fine aggregate shall be the fraction passing 2..8 mm
sieve and retained on 90 micron sieve, and shall consist of crushed screenings,
natural sand or a mixture of both. It shall be clean, hard, durable, uncoated and
free from injurious, soft or flaky pieces and organic or deleterious matter.
3.4
Grading of Aggregates :
The gradation of aggregates for mix seal surfacing is given in Table 3.
Table 3 : Gradation of Aggregates for Mix seal surfacing
Sieve size
% Passing by weight
Type A
Type B
13.2 mm
100
11.2 mm
100
88-100
5.6 mm
52-88
31-52
2.8 mm
14-38
5-25
0.090 mm
0-5
0-5
115
3.5
CONSTRUCTION
4.1
Preparation of Base
The base over which the cold mix seal surfacing is to be laid shall be completely
free from dust, caved mud etc, before its laying. Where the existing base is
having potholes or ruttings, the irregularly shall be corrected. If the existing base
is extremely irregular and wavy, it may be considered worthwhile to lay a cold
mix bituminous levelling course (Profile corrective course) of adequate thickness.
4.2
Tack coat : For tack-coat, bitumen emulsion of Rapid setting (RS-1) grade
may be used. The tack coat can also be carried out with bitumen emulsion of
Slow setting grade,(SS-2). The bitumen emulsion is applied on an existing
pavement, preferably on damp surface, at the rate of 3 to 3.5 kg for 10 sq.m area
if the surface is hungry and dry and 3.5 to 4 kg. per 10 sq.m. on a normal
bituminous base. The tack coat with emulsion shall be applied not earlier than 10
minutes before laying the cold mix.
4.3
6.3.1 It is imperative to prepare the cold mix for MSS by using conventional hot
mix plant without switching heating arrangement or cold mix plant or any other
suitable mixer of adequate capacity to yield a cold mix of proper and uniform
quality. The plant may be either a batch type or a continuous type having twostage mixer. The bitumen emulsion can be added into the mixer by having a
separate outlet of emulsion tank.
116
The aggregate shall be charged first into the operating mixer / pug mill followed
by the addition of optimum water content on conveyor belt leading to mixer and
then adding the required quantity of bitumen emulsion (SS-2). The above
ingredients shall be mixed for about one minute to achieve the uniform coating.
The cold mix shall be discharged for further loading on to the tipper for its
transportation to laying site.
4.4
Spreading of Mix
4.4.1 The cold mix shall be transported from plant site by tipper trucks to the
laying site and the spreading will be done preferably by means of a self propelled
mechanical paver with suitable speed capable of spreading, tamping and
finishing the mix, true to the proper grade, line and cross-section. The mix should
be spread in such a manner that, after compaction, the required thickness of
surfacing layer is laid uniformly.
4.4.2 Longitudinal joints and edges shall be constructed true to the
line,
marking parallel to the centre line of road. Longitudinal joints should be offset
atleast by 150 mm from those in binder course, if any, and transverse joints or
construction joints shall be placed in the original thickness of the previously laid
mix. The vertical cut face shall be painted with bitumen emulsion prior to the
laying of fresh mix against it.
4.5
Compaction
4.5.1 The cold mix laid with the paver, after being changed to black from
brown colour of due to breaking of emulsion on surface of coated aggregate,
shall be thoroughly and uniformly compacted through a set of rollers at a
speed of not more than 5 km per hour. The initial or break down rolling shall
be with 8-12 tonne three wheel steel roller and the surface finished by final
rolling with the 8-10 tonne tandem roller. Before finishing with tandem roller,
break down rolling shall preferably be followed by an intermediate smooth
wheel pneumatic roller of 15 to 30 tonne having a tyre pressure of 7 kg.
/sq.cm. The joints and edges shall be rolled with 8-12 tonne three wheel
roller. All the compaction operations i.e. breakdown rolling, intermediate
117
Opening to Traffic
Traffic may be allowed after 3-4 hours after the mix has set in the finished
surface and the mix should not be picked up by the vehicles.
5.0
5.1
OUALITY CONTROL
Adequate quality control at every stage of the work is essential and as such
a field laboratory must be set up to ensure the following controls.
5.1.1 Periodic sieve analysis of each type of aggregate at feeder end should
be made to see that the gradation of aggregate reasonably follows the
specified designed gradation. The number of samples per day would depend
upon the bulk supply of aggregates made in a day
materials shall be determined at the rate of one test for every 50-100 m3 of
aggregates or as directed by the Engineer-In-Charge.
5.1.2
118
pugmil chute or a minimum of one sample per plant per day shall be collected
and the following tests shall be carried out.
(i) Bitumen shall be extracted from about 1000 gm of the mix and bitumen
content determined.
(ii) Sieve analysis of aggregates after the bitumen is extracted shall be done to
determine gradation.
5.1.5 The permissible variation of the individual percentages of various
ingredients in the actual mix from the job mix formula shall be within the limits
indicated below in Table 4.
Table 4: Permissible variations from Designed Mix
S. No.
Description
Permissible Variations by
Weight of total mix (percent)
1.
# 8
2.
# 7
5.
# 4
6.
# 3
7.
Bitumen residue
3.
4.
# 6
# 5
# 0.3
5.1.6 For every 700 m2 or less of compacted surface, one field density test
should be conducted to determine the density of mix as laid, compacted and
finished.
5.1.7 The longitudinal profile of the finished surface shall be tested with a 3m
straight edge, parallel to the centre line, and the transverse profile with a camber
template. Any irregularity greater than 6 mm shall be corrected. The longitudinal
profile of the finished surface shall also be tested with a roughometer /
profilometer and it should be ensured that the roughness shall not exceed 2500
119
mm per kilometre.
6.0
The surfacing shall not be laid when the atmospheric temperature is below 8c
and or when it is raining. The Mix seal surfacing with cold mix can, however, be
laid on a damp surface.
120