You are on page 1of 88

EXTENSIVE SURVEY REPORT-2012

BATCH-2
INTRODUCTION
Mangalore is located at 1252N 7453Eto 12.87N 74.88E in the Dakshina Kannada
district of Karnataka. It has an average elevation of 22 meters (72 ft) above mean sea level.
Mangalore is situated on the west coast of India, and is bounded by the Arabian Sea to its
west and the Western Ghats to its east. Mangalore city, as a municipal entity, spans an area of
132.45 km2 (51.14 sq miles). The topography of the city is plain up to 30 km (18.64 miles)
inside the coast and changes to undulating hilly terrain sharply towards the east in Western
Ghats. The geology of the city is characterized by hard laterite in hilly tracts and sandy soil
along the seashore. The Geological Survey of India has identified Mangalore as a moderately
earthquake-prone urban center and categorized the city in the Seismic.

1. NEW TANK PROJECT


A New Tank (Earthen Dam) is proposed to construct across the valley in order to store the
water for irrigation and domestic water supply. The site for the proposed tank project should
be so selected that it should satisfy all the requirements of best possible site and to irrigate the
area of downstream side of the dam. Before taking up this work the following data must be
collected.

Nature of the Catchment Area.


Area to be irrigated.
Rainfall records of the area.
Nature of soil and crops to be grown.
Population of the area.
Communication.
Transportation.

Nature and availability of materials required for the construction of the dam.

To fix the height and storage capacity of tank the following survey works are necessary for
the NTP

Preliminary survey
Detailed survey

SSE, MUKKA, MANGALORE

Page 1

EXTENSIVE SURVEY REPORT-2012


BATCH-2
1.1 The Preliminary Survey Work consists of the following

Longitudinal and cross sections along and across the centerline of the Bund
Block Levels for the waste weir or Surplus weir
Capacity contours, for different reduced levels
Canal alignment

Longitudinal and Cross Sections of center line of the canal

Instruments use
Auto level/Dumpy level, Leveling staff, Chain, Arrows, Ranging rods, Prismatic compass ,
Tape, Cross staff, etc

1.2Survey Details
In order to obtain the bund level we need to locate the two points of equal elevation at each
side of the valley. The survey work is done along the bund line for the section of levels of
sluices maximum water level full tank level waste weir free board height of the bund. The
following survey works are conducted namely

Longitudinal and Cross section of bund

Capacity contour

1.2.1 Longitudinal section and cross section of the bund


In longitudinal leveling the back sight, intermediate sight and fore sight readings are taken at
regular intervals at every setup of instruments. The bearings of the line and the benchmark
are taken. The change points are noted in the level book. This station is taken up to determine
the undulation of the ground surface along the profile line. The reduced levels are calculated.
In the present survey work levels are taken at 5m intervals on steep terrain and at 20m
intervals on the flat terrain.
In cross section leveling, the levels are taken in the transverse direction to the longitudinal
leveling. The cross sections are taken at 5m intervals up to 20 m on either side of center
line. It is carried out to know the nature of the ground across the centre line alignment.

SSE, MUKKA, MANGALORE

Page 2

EXTENSIVE SURVEY REPORT-2012


BATCH-2
Table No.1:- LEVELING READINGS
LONGITUDINAL AND CROSS SECTION OF NTP
SI.NO
C0.00

B.S

I.S

0.335

F.S

H.I

R.L

48.410

48.075

R5

0.415

47.995

R10

0.450

47.960

L5

0.260

48.150

L10

0.185

48.225

C10.00

0.400

48.010

R5

0.420

47.990

R10

0.495

47.910

L5

0.400

48.010

L10

0.315

48.090

C16.85

0.460

47.950

R5

0.825

47.585

R10

1.315

47.090

R15

2.130

46.280

L5

0.585

47.825

L10

0.445

47.965

L15

0.125

48.285

C20.00

1.085

47.325

R5

1.090

47.320

R10

1.820

46.590

R15

2.500

45.910

L5

1.120

47.290

L10

1.045

47.365

L15

1.260

47.150

C30.00

3.055

45.355

R5

3.300

45.110

R10

3.630

44.780

R15

4.340

44.070

R20

2.815

43.310

L5

2.900

45.510

SSE, MUKKA, MANGALORE

Page 3

REMARK

EXTENSIVE SURVEY REPORT-2012


BATCH-2
L10

2.955

45.455

L15

3.240

45.170

L20

1.315

3.600

46.125

44.810

C40.00

2.775

43.350

R5

3.140

42.980

R10

3.250

42.870

R15

3.810

42.310

R20

3.490

42.630

L5

2.690

43.435

L10

2.950

43.175

L15

3.220

42.900

L20

3.920

42.205

C50.00

4.700

41.425

R5

1.765

4.855

433.035

41.270

R10

2.070

40.965

R15

2.420

40.610

R20

2.920

40.110

L5

1.645

41.390

L10

1.650

41.385

C60.00

3.395

39.640

R5

3.460

39.575

R10

3.700

39.330

R15

3.850

39.185

L5

3.065

39.970

L10

1.765

4.125

40.675

38.910

C65.00

1.870

38.800

R5

1.810

38.860

L5

2.110

38.560

L10

2.610

38.060

L15

2.790

37.880

C75.00

4.145

36.530

R5

4.245

36.430

R10

4.220

36.450

L5

4.060

36.615

L10

3.800

36.875

L15

4.150

36.525

SSE, MUKKA, MANGALORE

Page 4

EXTENSIVE SURVEY REPORT-2012


BATCH-2
L20

4.100

36.570

C85.00

4.180

36.495

R5

4.255

36.420

R10

4.215

36.460

R15

4.235

36.440

R20
R25
R30
L5

4.125
2.390
1.330

36.550
35.810
35.530
36.590

L10

1.345

36.570

L15

1.350

36.570

L20

1.280

36.640

L25

1.005

36.915

L30

0.560

37.360

C89.37

1.345

36.575

L5

1.350

36.570

L10

1.335

36.580

L15

1.330

36.590

L20

1.320

36.600

L25

1.290

36.620

L30

0.550

36.930

R5

1.990

35.930

R10

2.190

35.730

R15

2.400

35.520

R20

2.415

35.500

R25

2.415

35.500

R30

2.430

35.490

C92.22

2.290

35.630

L5

2.100

35.810

L10

1.580

36.340

L15

1.480

36.430

L20

1.310

36.610

L25

1.310

36.610

L30

0.520

37.390

R5

2.250

35.670

R10

2.200

35.720

2.110

SSE, MUKKA, MANGALORE

4.865

Page 5

37.920

EXTENSIVE SURVEY REPORT-2012


BATCH-2
R15

2.430

35.490

R20

2.440

35.480

R25

2.420

35.490

R30

2.430

35.480

C97.22

2.360

35.560

L5

2.320

35.600

L10

2.040

35.870

L15

2.060

35.850

L20

2.050

35.870

L25

2.060

35.850

L30

1.690

36.230

R5

2.340

35.570

R10

2.410

35.510

R15

2.420

35.490

R20

2.440

35.470

R25

2.430

35.480

R30

2.420

35.490

C102.22
R5

2.390

35.520

2.400

35.520

R10

2.260

35.650

R15

2.420

35.500

R20

2.420

35.490

R25

2.440

35.470

R30

2.430

35.490

L5

2.050

35.870

L10

2.020

35.900

L15

2.020

35.890

L20

2.030

35.890

L25

1.700

36.220

L30

1.520

36.400

C107.22
R5

2.400

35.520

2.390

35.520

R10

2.430

35.490

R15

2.370

35.540

R20

2.390

35.520

R25

2.440

35.480

SSE, MUKKA, MANGALORE

Page 6

EXTENSIVE SURVEY REPORT-2012


BATCH-2
R30

2.440

35.480

L5

1.900

36.020

L10

2.010

35.900

L15

2.000

35.920

L20

1.980

36.430

L25

1.520

36.390

L30

1.490

36.420

C112.22
R5

2.180

35.740

1.940

35.970

R10

2.530

35.390

R15

2.500

36.420

R20

2.300

35.620

R25

2.395

35.520

R30

2.420

35.500

L5

1.850

36.070

L10

1.990

35.930

L15

2.000

35.910

L20

1.990

35.930

L25

1.500

36.420

L30

1.530

36.390

C117.220
R5

1.270

36.650

1.490

36.420

R10

1.440

36.470

R15

1.900

36.010

R20

2.460

35.460

R25

1.800

36.110

R30

1.880

36.040

L5

1.620

36.300

L10

1.900

36.010

L15

1.910

36.010

L20

1.850

36.060

L25

1.520

36.400

L30

1.500

36.420

C122.22
R5

1.425

36.490

1.255

36.660

R10

0.495

37.425

SSE, MUKKA, MANGALORE

Page 7

EXTENSIVE SURVEY REPORT-2012


BATCH-2
L5

3.920

0.945

40.400

36.480

L10

2.440

0.450

42.390

39.950

C137.22
R5

1.235

41.155

1.290

41.090

R10

2.920

39.470

R15

3.895

38.490

L5

1.415

40.970

L10

1.000

41.390

L15

4.900

0.715

46.575

41.675

C147.22
L5

1.980

44.595

2.380

44.190

L10

2.590

43.980

R5

1.010

45.560

R10

3.210

43.360

R15

4.720

2.425

48.870

44.150

C161.52
L5

0.795

48.070

1.370

47.500

R5

0.585

48.280

R10

0.890

47.980
0.340

SSE, MUKKA, MANGALORE

Page 8

48.530

END
POINT

EXTENSIVE SURVEY REPORT-2012


BATCH-2
Table No.2:- LONGITUDINAL AND CROSS SECTION OF SMALL BUND
CHAINAGE

BS

C0
L5
L10
R5
R10
0
C14.1
L5
L10
R5
R10
C29.10
L5
L10
R5
R10

1.460

IS

HI

RL

REMARK

99.560

98.100
97.140
96.125
98.685
99.060
95.270
94.405
93.705
92.870
94.905
94.990
90.980
90.540
90.035
91.125
91.205
89.900
89.900
89.950
89.960
90.100
90.170
92.050
91.985
91.935
92.185
92.080
95.350
95.955
95.910
95.045
94.975
97.325
97.495
97.275
96.895
96.810

END POINT

2.420
3.435
0.875
0.500
0.255

4.290

95.525

4.545

91.650

1.750

93.835

1.755

96.310

1.335

98.230

1.120
1.820
2.655
0.620
0.535
0.670
1.110
1.615
0.525
0.445
3.935

C51.1
L5
L10
R5
R10
C71.1
L5
L10
R5
R10
C91.1
L5
L10
R5
R10
C97.1
L5
L10
R5
R0

FS

3.935
3.885
3.875
3.735
3.665
1.785
1.850
1.900
1.650
1.230
0.960
0.355
0.400
0.265
0.605
0.735
0.955
1.335
1.420

SSE, MUKKA, MANGALORE

Page 9

EXTENSIVE SURVEY REPORT-2012


BATCH-2
Fig No.1:- COMPONENTS OF EARTHEN DAM

Summary of the New Tank Project

NTP bund length


161.52m
Top of the bund
1.50m
Free board
1.20m
Upstream slope
2:1
Downstream slope
2:1
Maximum water level
46.125Mm
Length of the waste weir
3.02m
Storage capacity:
1. Maximum capacity of water
63004.25m3
2. @ FTL
53321.55m3
3. @ Dead storage
10264.17m3

SSE, MUKKA, MANGALORE

Page 10

EXTENSIVE SURVEY REPORT-2012


BATCH-2
Table No.3:- Capacity of reservoir

Sl. No

1
2
3
4
5
6

RL in
m
37.325
39.325
41.325
43.325
45.325
47.325

Water
spread
area sqm
4465.42
5798.75
5369.18
3408.82
10019.93
9345.47

SSE, MUKKA, MANGALORE

From

To

R.L

R.L

0
37.325
39.325
41.325
43.325
45.325

Page 11

0
39.325
41.325
43.325
45.325
47.325

Contour
interval
in m
0
2
2
2
2
2

Volume by
Trapezoidal Cumulative
formula

Vol. cum

cum
0
10264.17
11167.93
8778
13428.75
19365.4

0
10264.17
21432.1
30210.1
43638.85
63004.25

EXTENSIVE SURVEY REPORT-2012


BATCH-2

1.3 Design Procedure


1.3.1 YIELD CALCULATION:
1. Catchment area = 3.00 km2
2. Rainfall data considered is for a period of 10 years (2001 to 2010) from rainfall table.
3. Yield /sq.km as per strangers table considering catchment yield average
For 1524.00mm

= 0.68582.cum/sq.km

For 3555.6mm

= 1.60 cum/sq.km

Total yield= catchment area x yield/km2


=3.00 x 1.60
Area
=designated
4.80 cum @
Chainage
20
30
40
50
60
70
80
90

Depth of
embankment
0.53
2.834
4.735
6.645
8.045
9.92
10.855
11.035

SSE, MUKKA, MANGALORE

Mid
rectangular
area
0.795
4.251
7.1025
9.9675
12.0675
14.88
16.2825
16.5525
Page 12

U/s triangular
area
0.2809
8.031556
22.420225
44.156025
64.722025
98.4064
117.831025
121.771225

D/s
triangular
area
0.2809
8.031556
22.420225
44.156025
64.722025
98.4064
117.831025
121.771225

Total area in
sq. Mt
1.3568
20.314112
51.94295
98.27955
141.51155
211.6928
251.94455
260.09495

EXTENSIVE SURVEY REPORT-2012


BATCH-2
100
110
120
130
140
150
161.42

11.54
11.475
10.9
8.687
5.755
2.245
0

17.31
17.2125
16.35
13.0305
8.6325
3.3675
0

133.1716
131.675625
118.81
75.463969
33.120025
5.040025
0

133.1716
131.675625
118.81
75.463969
33.120025
5.040025
0
Total=

283.6532
280.56375
253.97
163.958438
74.87255
13.44755
0
2107.60275

Volume of core
V=h[(A40+A140)/2+A50+A60+A70+A80+A90+A100+A110+A120+A130)]
V=1108.84 m3
Volume of bund by trapezoidal Rule
V=h[(A20 + A150)/2 + A30 + A40 + .A140] + 76.74
Where h=10mtr
Total volume of bund =21078.74 cu mtr
Volume of earthwork = Volume of bund - Volume of core
Volume of earthwork = 21078.74 - 1108.84
Volume of earthwork =19969.90 m3

Fig No.2:- VARIOUS LEVELS OF A STORAGE RESERVOIR

SSE, MUKKA, MANGALORE

Page 13

EXTENSIVE SURVEY REPORT-2012


BATCH-2

The maximum water level (MWL), to which the water will rise in the reservoir during
ordinary operation condition is called Normal pool level. The normal level is corresponding
to the level of the spillway crest, or to the spillway gates. The level to which water rises
during the flood is known as Maximum water level. The lowest operation to which the water
in the reservoir is to be drawn under ordinary operating conditions is called minimum pool
level.
The volume of water stored between the normal pool level and the minimum pool level is
known as the useful storage (live storage). The volume of water below the minimum pool
level is known as the dead storage and is not useful under ordinary operating conditions. The
volume of water stored between the normal pool level and maximum level corresponding to a
flood is surcharge storage, and is usually uncontrolled. The term bank storage and valley
storage are referred to the volume of water stored in the pervious formations of the river bank
and the soil above it. Such storage depends upon the geological conditions of the river banks.
The bank storage increase the capacity of the reservoir above that indicates by the elevationstorage curve.

Gross capacity of the Tank or Reservoir


The gross capacity of a tank is the cubic content of water impounded up to the Full Tank
Level (F.T.L). The total capacity of the tank is the sum of the capacities between the
successive contours.

1.4 Canal
SSE, MUKKA, MANGALORE

Page 14

EXTENSIVE SURVEY REPORT-2012


BATCH-2
Canal project is a part of irrigation science which deals with the artificial carriage of water
from the reservoir to the required field. Canal is an artificial channel constructed to carry
water from river or reservoir for various purposes such as irrigation, power generation,
navigation etc. in general, canals are trapezoidal in cross section. The canals are usually
designated according to the purposes for which they are used.

Summary of the Canal Project

Length of the canalBase width of the canalTotal height of bankingFree board

Fig No.3:- CROSS SECTION OF CANAL

Table No.5:- LOGITUDINAL AND CROSS SECTION OF CANNAL


SSE, MUKKA, MANGALORE

Page 15

EXTENSIVE SURVEY REPORT-2012


BATCH-2
Chainage
C0
L5
L10
L15
R5
R10
R15

BS
4.625

IS

0.650

40.825

3.175

39.150

3.290

36.580

1.930

35.830

2.585
1.310
0.635
0.225
4.850
5.390
5.260
1.500
0.915
0.495
2.265
3.545
1.500
1.535
1.370
2.065
3.250
3.260
3.290
3.380
3.210
3.470
0.720

C85.5
L5
L10
R5
R10
C125.5
L5
L10
R5
R10

HI
41.120

2.695
1.360
0.125
4.470
5.380
5.595
0.355

C15
L5
L10
L15
R5
R10
R15
C45
L5
L10
R5
R10
C45
L5
L10
R5
R10
C70.5
L5
L10
R5
R10

FS

1.840
1.860
1.850
1.860
1.560
1.930
1.870
1.860
1.920
1.180

SSE, MUKKA, MANGALORE

Page 16

RL
36.495
38.425
39.760
40.995
36.650
35.740
35.525
40.470
38.240
39.515
40.190
40.600
35.975
35.435
35.565
37.650
38.235
38.655
36.885
35.605
37.650
37.615
37.780
37.085
35.900
35.890
35.860
35.770
35.940
35.680
35.860
34.740
34.720
34.730
34.720
35.020
34.650
34.710
34.720
34.660
34.650

Remarks

change point

change point

change point

change point

EXTENSIVE SURVEY REPORT-2012


BATCH-2
C137.4
L5
L10
R5
R10
C170.5
L5
L10
R5
R10
C170.5
L5
L10
R5
R10

2.190
2.195
1.191
2.235
2.231
2.080
2.115
2.110
2.145
2.140
2.080
2.110
2.115
2.145
2.145
0.825

C185.5
L5
L10
R5
R10
C245.5
L5
L10
R5
R10

34.575

1.440

34.355

1.370
1.370
1.370
1.370
1.371
1.440
1.445
1.442
1.440
1.435
1.220

C268.9
L5
L10
R5
R10
C268.9
L5
L10
R5
R10
C298
L5
L10
R5
R10

2.080

2.070
2.075
2.070
2.080
2.075
2.750
2.080
2.070
2.085
2.080
2.085
2.015
2.010
2.060
0.065

SSE, MUKKA, MANGALORE

Page 17

33.640
33.635
34.635
33.595
33.595
33.750
33.715
33.720
33.685
33.690
33.750
33.720
33.715
33.685
33.685
33.750
33.205
33.205
33.205
33.205
33.204
33.135
33.130
33.133
33.135
33.140
33.135
32.285
32.284
32.285
32.275
32.280
32.285
32.275
32.285
32.270
32.275
32.270
32.340
32.345
32.295
32.290

change point

change point

EXTENSIVE SURVEY REPORT-2012


BATCH-2
C329.9
L5
L10
R5
R10
C335.9
L5
L10
R5
R10
C355
L5
L10
R5
R10
C390.1
L5
L10
R5
R10
C420.1
L5
L10
R5
R10
C450.1
L5
L10
R5
R10
C480.1
L5
L10
R5
R10
C500
L5
L10
R5
R10

1.289

2.365

33.270

1.785

32.770

1.255
1.250
1.305
1.295
1.545
1.540
1.545
1.555
1.550
1.740
1.785
1.780
1.780
1.280
1.515
1.520
1.520
1.540
1.540
1.910
1.805
1.805
1.865
1.860
2.150
2.155
2.150
2.225
2.220
2.650
2.645
2.640
2.660
2.655
2.750
2.960
2.965
2.970
2.975

1.4.1 TIME FACTOR

SSE, MUKKA, MANGALORE

Page 18

31.990
32.015
31.020
31.965
31.975
31.825
31.730
31.725
31.715
31.720
31.530
31.485
31.490
31.490
31.490
31.255
31.250
31.250
31.230
31.230
30.860
30.965
30.965
30.905
30.910
30.620
30.615
30.620
30.545
30.550
30.120
30.125
30.130
30.110
30.115
29.820
29.810
29.805
29.800
29.795

change point

change point

END POINT

EXTENSIVE SURVEY REPORT-2012


BATCH-2
It is the ratio of number of days the canal has actually to run, to the base period in days.
Water requirements of the channel (i.e., its capacity) should be divided by time factor, so as to
obtain the design capacity. Since the factor is less than 1.

1.4.2CAPACITY FACTOR
It is the ratio of the mean supply discharge to the full discharge capacity.

1.4.3 FULL SUPPLY COEFFICIENT

Area estimated to be irrigated during base period


Design full supply discharge at its head during peak demand.
It is also called Duty on capacity.

1.4.5 DETERMINATION OF REQUIRED CHANNEL CAPACITY


Whenever one plans for supplying irrigation water. One has to think of likely crops that are to
be sown in any one season. The peak rate of water requirement of all crops in each season is
also to be worked out. The capacity of the channel should be such so as to fulfill the
maximum of peak demand of the all crops that one required at any one time amongst all the
seasons it is explained in details.
The most important Rabi crop is wheat, which requires water from December to March,
during the Rabi season. Similarly paddy (rice) is the most important Kharif crop requiring
water from June to November so it can presume that when Rabi crops require water Kharif
crops do not and vice-versa. Sugarcane is a perennial crop which requires water through the
year. Hence the channel may be designed for a capacity equal to the greater of the water
requirement of rabi and sugar or kharif and sugar. This is very simple method for fixing the
capacity of channel. The entire Rabi area is supposed to be sown with wheat and entire kharif
area with paddy (sugarcane area excluded from both) and their water requirements in cumec
are worked out. The water requirement of sugarcane is separately worked out. The channel
capacity may be fixed for the maximum of the two values.

SSE, MUKKA, MANGALORE

Page 19

EXTENSIVE SURVEY REPORT-2012


BATCH-2
The most important point which must be kept in mind while fixing the channel capacity is
that we must take into account the keenest demand of the crop and not the average demand.
For example, Rice requires 120cm of water during 120days, thus giving an average outlet
factor of 864 hectares/cumecs
I.e. D = 864B/
= (864*12)/120
= 864
But the channel designed on this average outlet factor will prove to be very inadequate, as it
will fail to supply the required water to the crop at its peak demand i.e., at the time
Kor- watering, as explained below,
The kor depth of the rice is about 19cm and the kor period is about 2 weeks (i.e 14days). It
means that 19cm of water depth must be supplied in about 14 days.
The outlet factor for this works out to be 637 hectare / cumecs as
D = 864B /
= (864 * 14)/19
= 637.
Now, discharge requires maturing a hectare of land for an outlet factor of 864 is A/864
cumecs, while that for an outlet factor of 637 is A/637 cumecs. Out of these two values the
second value (i.e. A/637) is more and hence the discharge required for fulfilling the kor
demand of the crop is more than for the average demand.
Similarly wheat requires 40 cm of water in a total base period of about 160days. Thus giving
an average outlet factor of 3464 hectares/cumecs. But the kor water depth required by wheat
is about 14cm in about 4 weeks giving an outlet factor of 1728 hectares/cumecs.
Applying the previous reasoning, we can say that the discharge required to fulfill kor-demand
is much more than that for the average demand (almost double of average). Hence, it follows
that the peak demand, i.e kor-demand of the crop should be taken into account while fixing
the capacity of the channel. Moreover, the provision for channel losses should also be made,
while deciding the final channel capacity.
The method described above, for determining the channel capacity is a simplified
approximate process to be more precise, we can find out the monthly or 15 days water
requirement of various crops. The water depth required in this interval is multiplied by the
crop area. So as to give the volume of water required in this interval. Dividing the volume by
interval, we can find out the discharge required in each interval, by various crops. The
SSE, MUKKA, MANGALORE

Page 20

EXTENSIVE SURVEY REPORT-2012


BATCH-2
summation of which for all crops will give us the discharge required by all crops in each
interval. The channel may then be designed for maximum of these values.
It is evident that in order to be more precise, the interval should be as small as possible.
Generally, monthly water requirement studies are conducted and the channel capacity is
increased by 20% to 25% to cater for the peak demand in the months.

1.4.6 CONTOUR CAPACITY


This is a typical case of volume in which the finished surface (i.e surface of water) is level
surface. The volume is calculated by assuming it has been divided into a number of
horizontal slice by contour line is measured by planimeter and volume can be calculated.
Let A1, A2, A3..An the area of successive contour
H = contour interval
V = capacity of reservoir
By trapezoidal formula,
V = h [(A1+An)/2 +A2+A3+A4+An-1]
By Prismoidal rule,
V = h/3 [A1+ 4(A2+A4+.) + 2(A3+A5) =An]

Table No.6:- Rain fall data of the last 10 years:year

Rain fall data in mm

Rain fall in descending

2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
2011

4343.5
3227.4
3532
3271
3114.2
3555.6
3838
2916.2
3119.6
5160.4
3775.4

5160.4
4343.5
3838
3775.3
3555.6
3533
3271
3227.4
3190.6
3114.2
2916.2

SSE, MUKKA, MANGALORE

Page 21

EXTENSIVE SURVEY REPORT-2012


BATCH-2

1.4.6 Design of Left Bank Canal:


GCA = CCA = 933.00hactors
Duty = 3168ha/cumec
Discharge = Area/duty
Q = 933.00/3168
Q = 0.29M3sec
Channels are to be designed for 20% excess requirement towards rush irrigation
(Engineers hand book)
= 0.29 x 0.2 = 0.058
= 0.058 + 0.29
Total discharge =0.348cumec
Now, using Continuity equation Q=AV
Area=Q/V
A=0.348/0.45
A=0.87M2
V=0.45 m/s for minor distributaries (allowable velocity)
(Engineers hand book)
Area =0.87/0.45=0.87m2

SSE, MUKKA, MANGALORE

Page 22

EXTENSIVE SURVEY REPORT-2012


BATCH-2

For most Economical Trapezoidal section,


We have condition
A={(B+2nd+B)/2}* d
A= (B+D)*D
0.87 = (B+D)*D-------- (1)
We have condition,
(B+2nD)/2=D {sqrt (n2+1)}
(B+2*1*D)/2=D {sqrt (12+1)}
B+D=1.41D
b=0.41D
From (1) we have,
0.87 = (0.41D+D)*D
0.87=1.41D2
D=0.78m
Say, D =0.80m
Therefore,
b =0.41*0.80
b=0.32m
So, D=0.80m & b=0.32m

Perimeter:P =b+2*2D
P=0.32+2*2*.80
SSE, MUKKA, MANGALORE

Page 23

EXTENSIVE SURVEY REPORT-2012


BATCH-2
P=2.58m

Mean depth:R=A/P
=0.87/2.58
R=0.34m
Mannings Constant N=0.0225
Velocity =1/n R2/3 S1/2
0.45 =1/0.0225(0.34)2/3 (S) 1/2

(since velocity is limited to 0.45m/s)

S =1 in 4211

Discharge (Q):Q=A x V
=0.87x0.45
Q= 0.39m3

Fig No.4:- Design of Sluice gates:-

Limiting Velocity through sluice gate is a maximum of 4.5 m/sec [S.K.Garg book,
page- 936].
By using Engineers Handbook
SSE, MUKKA, MANGALORE

Page 24

EXTENSIVE SURVEY REPORT-2012


BATCH-2

1.4.7

Design of sluice gate procedure

V= Cd x (2gh) 1/2
Cd= 0.62 for free flow
h= height of the F T L above sill level of Sluice.
V= Cd x (2gh) 1/2
V= 0.62x (2x9.81x10.605)1/2
= 8.94 m/sec > 4.5 m/sec
Limit value of velocity = 4.5 m/sec
A = Q/V
= 0.39/4.5
= 0.087 m2
A=
0.087=

/4
2

/4

d= 0.33m
d=0.33m can be provided.

Fig No.5:- DESIGN OF VERTICAL DROP WEIR

SSE, MUKKA, MANGALORE

Page 25

EXTENSIVE SURVEY REPORT-2012


BATCH-2
1. Hydraulic calculations for fixing various elevations.
2. Design of weir wall.
3. Design of impervious floor (or apron).
4. Design of protection works on upstream and downstream sides.
The following data must be known for the design of a vertical drop weir.

Maximum flood discharge(Q)

High flood level (H.F.L)before construction of weir

Downstream bed level

Fully supply level (F.S.L)of canal taking off from the river

Allowable afflux

Laceys silt factor

1.5 Design of vertical drop weir


i.

The length of waterway (L) is calculated from Laceys regime formula


L = 4.83Q^ (1/2)

Where L=Length of waterway in meters


Q= discharge in cumec
= 4.83*0.39^ (1/2)
L = 3.02m
ii.

The discharge q per unit length of waterway is calculated from the relation
Q = Q/L

Where q is in cumec per meter


= 0.39/3.02
Q = 0.13cumec per meter
iii.

The regime scour depth in calculated from Laceys formula


R=1.35[q^2/f]^(1/3)

Where

R=scour depth in meters


f=Laceys silt factor (assume f=1)
=1.35[0.13^2/1]^(1/2)

SSE, MUKKA, MANGALORE

Page 26

EXTENSIVE SURVEY REPORT-2012


BATCH-2
R=0.176m
iv.

The regime velocity and velocity head are calculated from the expressions
V= Q / R
=0.13 / 0.176
V =0.738m/sec

Velocity head= V^2/2g


= 0.738^2/2*9.81
= 0.0277m/sec
v.

Water levels and total energy line (T.E.L) on the downstream side (d/s) and
upstream side (u/s) are calculated as follows:

Level of d/s T.E.L= (H.F.L before construction) +V^2/2g


=46.125+0.0277
=46.402m
Level of u/s T.E.L=Level of d/s T.E.L+Afflux
Allowable Afflux=1
=46.129+1
=47.129m
Level of u/s H.F.L=Level of u/s T.E.L-V^2/2g
=47.129-0.0277
=47.1013m
vi.

Discharge over the crest of the weir is given by


q=1.70K^ (3/2)

Or

K= (q/1.70) ^ (2/3)
= (0.13/1.70) ^ (2/3)
K=0.18

Therefore crest level=u/s T.E.L-K


=47.129-0.18
Crest level=46.949m
SSE, MUKKA, MANGALORE

Page 27

EXTENSIVE SURVEY REPORT-2012


BATCH-2

Table No.7:- VOLUME OF EARTHWORK FOR PROPOSED CANAL ALIGNMENT


Chainage
0
15
45
70
85.5
125.5
137.4
170.5
185.5
245.5
268.9
298
329.9
335.9
390
420
450
480
500

Area in
cutting(m3)
0.1097
6.6266
3.1811

Area in
filling(m3)
8.08
5.9591
2.6595
21.2618
38.8107
40.6488
59.362
60.3995
72.1408
73.7335
12.21
11.093
15.6
19.81
45.56
51.77
59.25
69.63
77.3744
Total Volume

Volume of
cutting(m3)

Volume of
filling(m3)

50.52
147.11
39.76

105.29
129.27
299.01
465.55
1589.19
595.06
1982.05
994.05
4376.229
1005.53
339.05
425.7
106.23
1768.2
1459.95
1665.3
1933.2
1470.044
20708.903

237.39

Total Volume of earthwork in cutting= 237.39 m3


Total Volume of earthwork in filling =20708.93 m3
Fig No.6:- SLUICE GATE OPENING:

SSE, MUKKA, MANGALORE

Page 28

EXTENSIVE SURVEY REPORT-2012


BATCH-2

1.6 CONCLUSION: The nearby wells can be recharged by construction of this bund. Thus the water
stored in the tank can be used for various purposes such as irrigation, power
generation, domestic water supply etc.
This project can also help to increase the ground water table in the region. Thus the
overall prosperity of the people will increase because of this project.

Fig No.7:- Catchment Area from AutoCAD:-

SSE, MUKKA, MANGALORE

Page 29

EXTENSIVE SURVEY REPORT-2012


BATCH-2

2. WATER SUPPLY
2.1 INTRODUCTION
Safe drinking water is the primary need for every human being. Water is absolutely essential
not only for survival of human being but also animals, plants and all living beings. The
purpose of Municipal water supply system is to provide portable water, which is chemically,
and bacteriological safe for human consumption. For domestic use, water should be free from
unpleasant taste, Odour and should be improved for human health.
While designing a water supply scheme it first of all, essential to search a source for village,
for which the scheme is to be designed. Basically there are two main water sources, i.e.
1. Surface water sources: River, Lakes, Ponds, Impounding reservoir, Canals, Stored
rain water, etc.
2. Ground water sources: Springs, Wells, Infiltration Galleries and Infiltration Wells.
Surface water sources are generally contaminated and cannot be used without proper
treatment and purification system, compared to Ground water source.

2.2 Main Objective


The main objective of this project is to provide pure and safe drinking water supply with
proper sewerage system to the proposed village.
SSE, MUKKA, MANGALORE

Page 30

EXTENSIVE SURVEY REPORT-2012


BATCH-2
2.3 Specific Objectives
To carry out this project under rural water supply scheme and to achieve the main objective
we have drawn some of the specific objectives.
Selection of project site for the proposed Village.
Identification of water sources, required for the proposed Village.
Survey work is to be carried out to obtain the key plan of the entire water supply
project and sewage system.
Location of Intake Works, Water Treatment Plant, Overhead Tank, Distribution
System and Sewage Treatment System.
Design of Water Treatment Plant, Rising Main and Water Distribution System.
Preparation of Village plan, Population projection and Quantity and Quality of water,
etc for the entire project.

2.4 Selection of Project site


We have selected a site for NTP project which is located on downstream side of the NTP
reservoir. Before commencement of the survey work we have made reconnaissance survey to
locate the site for intake works, water treatment plant, overhead tank, rising main, gravity
main and distribution system for the proposed village.
Detailed survey work is to be made for the entire project work and is given below:
Block levels for the proposed intake works (Reservoir Intake works).
Compass survey work is made from intake works to the Proposed Water

Treatment plant (L/S).


Block levels for the proposed Water Treatment plant.
Rising main (L/S) to Overhead Tank using compass.
Block leveling for proposed Overhead Tank on the hill station.
Gravity main (L/S) using compass up to the proposed village.
Block leveling for Water Distribution system to the proposed village.

Using the data available from survey work we have designed Water Supply and sewerage
system.

2.5 The Design work for the entire project is made in two Stages.
1. Water Supply Project - Intake works, Water Treatment Plant, Rising Main
Tank, and Distribution system.

SSE, MUKKA, MANGALORE

Page 31

Overhead

EXTENSIVE SURVEY REPORT-2012


BATCH-2
2. Sanitary project (sewerage system) - collection, transport, treatment and safe disposal of
sewage.
All the drawings connected to the above two stages are given in detail in a separate bounded
report.

2.5.1 Water Supply Project


After the selection of site for the proposed village, detailed survey work has been carried out.
Using survey data, we have made the following design. Based on the prepared Layout for the
proposed village and the no. of occupants in each residential unit, and total population of the
village is estimated as follows:

Total residential building in the proposed layout = 2000 nos.

No. of inhabitant in each house = 5 nos.

Total expected population for the proposed village = 2000 x 5 = 10000 for the
year 2010.

Design period consider for the water supply project = 20 years (2 Decades)

Population projection after 20 years (2030) by considering the factors like


Birth rate, Death rate and Migration etc. The future Population is about =25%,
increasing per decade.

So, expected population at the end of 2030 = 16000 (say).

Average Domestic Water Consumption


Whenever an engineer is given a duty to design the water supply scheme for a particular area
of the community, it becomes imperative upon him, to first of all, evaluate the amount of
water available and the amount of water demanded by the public. In fact very first duty is to
consider the actual Water Demand and then find out the source to fulfill that demand.
It is necessary to find out, not only daily demand but also total annual requirement is to be
determined.

2.6 Per Capita Demand

SSE, MUKKA, MANGALORE

Page 32

EXTENSIVE SURVEY REPORT-2012


BATCH-2
Per Capita Demand is the average amount of daily water required by one person, and includes
the domestic use, industrial and commercial use, public use, waste, thefts, etc. In India, the
requirement of water in various uses is as follows:

Table No.8:- Per Capita Demand for various village/town/city populations


Population of town

Per Capita Demand (in Lpcd)

Up to 10000

70-100

10,000- 50,000

100-135

Above 50,000

135-250

2.7 Common Demands of a Community


1. Domestic water demand.
2. Commercial water demand.
3. Demand for public amenities.
4. Fire demand.
5. Water required for compensating losses in wastes, thefts etc

Table No.9:- Domestic Water Demand (Per Capita Demand) - (100-135 Lpcd)
S. No.

Use

Consumption in Lpcd

Drinking

Cooking

Bathing

30

Cloth washing

30

Utensils washing

20

Cleaning of houses

15

SSE, MUKKA, MANGALORE

Page 33

EXTENSIVE SURVEY REPORT-2012


BATCH-2

Flushing of latrines

30

Total

135 Lpcd

2. Commercial Water Demand


This includes the quantity of water required to be supplied to offices, factories, hostels,
hospitals etc. This depends on the type of city or town & nature of establishments. On an
average a provision of 20-25% of the total water consumption of the community will be
considered.
3. Demand for Public amenities.
This includes the quantity of water required for public utility purpose such as watering for
public parks, gardening & sprinkling on roads, use in public sanitary units etc. Normally an
average of 5% of the total water consumption of the community will be considered.
4. Fire Demand
In thickly populated areas, fires generally break out & may lead to serious damages if not
controlled effectively. Generally water required for fire demand hardly amounts to about
1lt/person/day, which is also considered in our design.

5. Water required for compensating- losses in wastage, thefts etc


This includes the water lost in leakage due to poor plumbing fittings, unauthorized water
connection, other losses & wastes etc. These losses can be reduced by careful maintenance.
This amount is usually taken as 15% of the total consumption.

6. Quantity of Water
Based on the available population, it is assumed that the rate of water supply=
100LPCD, and the Maximum daily demand is also estimated= 1.8 MLD.
Qavg = (Population x WS)
= (1000 x 135)
SSE, MUKKA, MANGALORE

Page 34

EXTENSIVE SURVEY REPORT-2012


BATCH-2
= 135000Lpcd
= 0.135 MLD

Qmax = (1.8 x Qavg)


= (1.8 x 0.135)
Qmax = 0.243 MLD
Water samples were collected from the reservoir and analyzed for Drinking water
Quantity parameters as per BIS: 10500-2003 to know the quality of water, which is to be
supplied to the village. Based on the result is obtained for the available water source we have
designed the treatment plant.

Table No.10:- WATER QUALITY STANDARDS (BIS: 10500 - 2003)


Range
Serial No.

Permissible limit

Parameters

Excisable limit

Physical

Color ( Hz )

Odour and Taste

Turbidity ( NTU )

10

TDS ( mg/l )

500

2000

II

25
Not objectionable

Chemical

pH

6.5-8.5

6
7
9

Total alkalinity(as CaCo3in mg/l)


Total hardness (as CaCo3 in mg/l)
Chlorides (as Cl- in mg/l)

200
300
250

600
600
1000

9
10
11

Sulphate (as S04 in mg/l)


Fluoride (as F in mg/l)
Nitrates (as NO3 in mg/l)

150
1.0
50

400
1.5
50

12

Nitrites (as NO2 in mg/l)

13

Calcium (as Ca in mg/l)

75

200

14

Magnesium ( as Mg in mg/l)

30

100

15

Total iron (as Fe in mg/l)

0.3

1.0

SSE, MUKKA, MANGALORE

Page 35

EXTENSIVE SURVEY REPORT-2012


BATCH-2
III
16

Biological
MPN/100ml

Less than 1/100ml

2.8 Intake for Collecting Surface Water


The basic function of the intake structure is to help in survey with- drawing water from the
source over a predetermined range of pool levels & then to discharge this water in to the
withdrawal conduits through which it flown up to the water treatment plant.

Reservoir Intake
The Reservoir Intake shows a clear idea about the intake structures which is used to draw the
water from earthen dam reservoir. It is essentially consists of an intake tower constructed on
the slope of the dam on U/S at such a place from where, intake can draw sufficient quantity of
water even in the driest period. Intake pipes are fixed at different levels as so as to draw water
near the surface in all variations of water level. All the inlet pipes are connected to the one
surface in all variations of water level. All the inlet pipes are connected to the one vertical
pipe inside intake well. Screens are provided at the mouth of all intake pipes to prevent the
entrance of floating and suspended objects in them. The water which enters the vertical pipe
intakes to the other side of the dam by means of an outlet pipe. At the top of the intake tower,
sleeve valves are provided to control the flow of water. The valve tower is connected to the
top of the dam by means of the foot bridge for reaching it.

2.9 Aeration unit


Aeration is necessary to promote the exchange of gases between water and atmosphere. In
water treatment aeration is preceded for the following purpose.
1. To add oxygen to water for freshness.
2. Removal of CO2, H2S and other substances and to bring taste and odour.
3. To precipitate impurities like iron and manganese etc.
The raw water from reservoir is conveyed from reservoir intake works collected in a storage
tank (sump) and lead to aerobic unit. Water fall or cascade type of aerator is normally
recommended and is generally provided.
SSE, MUKKA, MANGALORE

Page 36

EXTENSIVE SURVEY REPORT-2012


BATCH-2
2.10 Reaction with Alum
When Aluminum Sulphate (Al2 (SO4)3.18H2O) (Alum) is added to water it reacts with the
natural alkalinity which is present in the raw water and produces, a gelatinous precipitate
(flock) of aluminum hydroxide. The flock attracts the fine suspended colloidal particles and
grows in size and finally settles down to bottom of the tank.
The chemical reaction is as follows:
Al2 (SO4)3.18H2O + 3Ca(HCO3)2 2Al(OH)3 + 3CaSO4 + 18H2O + 6CO2
Amount of alum required for coagulation is depending on the turbidity and color of raw
water. It is an effective coagulant extensively used throughout. It does not require any skill
supervision for handling. The water obtained from this treatment is quite clear and taste and
color of raw water is considerably reduced.

2.11 Filtration Unit


Filtration is defined as, passing passage of fluid through a porous media to remove the
floating matter held in suspension in water purification.
The matter to be removed includes suspended and colloidal particles, clay and microorganisms including algae and bacteria.
There are three types of Gravity Filters,
1. Rapid sand filter
2. Slow sand filter
3. Pressure filter
Among them, Rapid Sand Filter is most commonly used and same is designed
Design of Rapid Sand Filter is governed by many factors such as;

The quality of raw water

The nature and efficiency of pre-treatment

The characteristics of filter media

The hydraulic loading of filters

The method of disinfection

The method of internal cleaning

SSE, MUKKA, MANGALORE

Page 37

EXTENSIVE SURVEY REPORT-2012


BATCH-2
2.12 Disinfection
The filtered water still contain some kinds of impurities present in it, mainly in the form of
harmful disease causing pathogenic bacteria and they must be killed in order to make the
water safe for drinking. This can be used by the chemicals called disinfectants and this
process is called disinfection.
The main purpose of disinfection is to prevent contamination of water during its transit from
treatment plant to the place of its consumption. Chlorine is an ideal material for treating water
in a large scale.

2.13 Distribution System


There are 3 different types of distribution systems;
1. Gravity system
2. Pumping system
3. Combined system
In our project, combined system is used, in which the water is pumped from source which is
at lower level, to overhead tank at the higher level and then, from the overhead tank, the
water is supplied to the public, by gravity.
As the layout of village in haphazard manner, the dead end system is adopted.

2.14 System of Supply


1. Continuous supply
2. Intermittent supply
For this project intermittent supply is adopted.

2.15 Pressure in Distribution System


The pressure which is required to be maintained in the distribution system depends upon the
following factors:
1. The height of highest building up to which water should reach without boosting.
2. The distance to the locality from the distribution reservoir.
3. The supply is to be metered or not. Higher pressure will be required to compensate
for the high loss of head in meters.
4. The funds available for the project work.
SSE, MUKKA, MANGALORE

Page 38

EXTENSIVE SURVEY REPORT-2012


BATCH-2
In multistory structures the following pressure are considered satisfactory
Up to 3 storey

2.1 kg/sq.cm

From 3 to 6 storey

2.1 to 4.2 kg/sq.cm

From 6 to12storey

4.2 to 5.27 kg/sq.cm

2.16 Pipe Appurtenances


The distribution pipes are provided with various pipe appurtenances or accessories so as to
make the distribution of water easy and effective. The pipe appurtenances are air valves, bib
cocks, fire hydrants, reflux valves, sluice valves, stop cocks, water meters etc...

2.17 Economical Diameter of Main pipe


For pumping a particular fixed discharge of water, it can be pumped through bigger diameter
pipe at low velocity or through lesser diameter pipe at high velocity. But if the diameter of the
pipe is increased, it will lead to the cost of the pipe line on the other hand if diameter of the
pipe is reduced, and the increased velocity will lead to the higher frictional head loss and will
require most of the required pumping, hereby increasing the cost of the construction.
For obtaining the efficiency it is almost necessary to design the pumping main, which will
be overall most economical in initial cost as well as maintenances cost of the pumping the
required quantity of the water.
Following formula given by Lea is commonly used in determining the diameter of the
pumping main:
D = 0.97 to 1.22 Q 0.5
Where,
D = Economical diameter of the pipe in m
Q = Required discharge of water to be pumped in cumec/second
The above formula given optimum velocity of water flow between 0.8 to1.35 m/s.
SSE, MUKKA, MANGALORE

Page 39

EXTENSIVE SURVEY REPORT-2012


BATCH-2

2.18 Design Details for Water Supply System


Table No.11:- Water Demand for Domestic Purposes:
Sl. NO.

USE

CONSUMPTION IN LPCD

Drinking

Cooking

Bathing

30

Cloth washing

30

Utensils washing

20

Cleaning of houses

15

Flushing of latrines

30

Total

135 Lpcd

Assume total population of the area = 1000


Table No.12:-population with respect to year
YEAR

POPULATION

1992
2002
2012
2032

620
780
1000

SSE, MUKKA, MANGALORE

Page 40

DECREASE IN
DECADE
160
220
Avg = 190

% INCREASE IN
DECADE
25.80
28.20
Avg = 27.00

EXTENSIVE SURVEY REPORT-2012


BATCH-2
Arithmetic increase:x =190
Population at 2032 = P0 + xn
= 1000 + (2 x 190)
= 1380
Geometric method:r = (25.80 x 28.20)
2
= 27.00
Population at 2032 = P0 (1 + (r / 100)) n
= 1000(1 + (27.00 / 100)) 2
1612.90 say 1612.
Design period = 20 years.
Average water consumption = 135 Lpcd.
Average daily demand = 135 x 1612
= 0.218 MLD
Required capacity of major component of proposed water work:
1) Average daily draft = 0.218MLD.
2) Maximum daily draft = may be assumed as 180%
Average daily draft = 0.218 x 180
100
= 0.392 MLD
Capacities of various components:
1) Intake structure may be designed for maximum daily draft of 0.392MLD.
2) Pipe mains carrying the water from intake to the reservoir may be designed for.

DESIGN OF RISING MAINS:


Design of pump:
SSE, MUKKA, MANGALORE

Page 41

EXTENSIVE SURVEY REPORT-2012


BATCH-2
Assume the pumping is done for 5 hours.
Average quantity of water = 0.392 MLD
Q=

0.392 x 106 x 24
24 x 1000 x 3600 x 5

Q = 0.022 cumec
D = 0.972Q to 1.22Q
= 0.9720.022 to 1.220.022
D= 14.5 cm to 18 cm say 18cm pipe dia.

Using Hazen Williams formula


HL=

HL=

HL= 6.17mt
Minor loss, hf = 4 f L v2
2gd
f= friction factor of PVC pipe
L= Length of the pipe
v = Velocity of water
g = Gravitational constant
d = Diameter of the pipe
= 4x 0.00625 x 800 x 0.452

= 1.14 m due to friction.

2 x 9.81 x 0.18
SSE, MUKKA, MANGALORE

Page 42

EXTENSIVE SURVEY REPORT-2012


BATCH-2
Assume 10% losses in fitting = 6.17 = 0.617mt
10
Total head losses = 6.17 + 1.14 + 0.617 = 7.93mts
Power of pump:
Total Height from the dead storage to the over head tank = (Height from the dead storage to
top bund level + Height from top bund level to tank ground level + Height of the over head
tank + total head loss)
H = 10.8+ 10+12+ 7.93 =40.73m
Say H = 40m

Water Horse Power (WHP) =

Where,

= Density of water
Q = Discharge
H = Head loss due to friction
= Efficiency of water 70%

= 13.20 HP

Breaking horse power

SSE, MUKKA, MANGALORE

Page 43

EXTENSIVE SURVEY REPORT-2012


BATCH-2

(BHP) = 16.77 HP

3.

HIGHWAY PROJECT

3.1 Introduction
Transportation is a vital infrastructure for the speedy economic growth of a developing
country. Road transportation is one of the important modes of transport having many
desirable characteristics. Such as flexibility, door to door service and accessibility to remote
areas.
Highways in road transport system have been rightly compared to the arteries of a human
being and their importance in the social and economic up lift of a nation cannot be over
emphasized.
SSE, MUKKA, MANGALORE

Page 44

EXTENSIVE SURVEY REPORT-2012


BATCH-2
In the present era planning is considered as a pre-requisite and basic need for any new
project or an expansion program. Thus highway planning is also a basic need for highway
development. Since, we have undertaken HIGHWAY PROJECT as our project work; we
have considered the following objectives:

Efficient and safe traffic operation but a minimum cost.

Attainment of maximum utility.

Construction with locally available resources to minimize the cost of project.

Future requirements and improvements in view of anticipated developments.

Availability of funds and economic considerations.

Incorporation of technical recommendations framed by Indian Roads Congress


(IRC) for various aspect of Highway construction.

Proposal
This project deals with the design of road and can be executed in following manner.

A road was selected and detailed surveys including cross section and longitudinal
sections were carried out.

Plan of road alignment longitudinal section were drawn to scale and final alignment
was fixed, as per IRC specifications, confirming to village roads.

Block leveling for the culvert.


SSE, MUKKA, MANGALORE

Page 45

EXTENSIVE SURVEY REPORT-2012


BATCH-2
3.2 Geometric Design of Highway Pavement
The geometric design of a highway deals with the dimensions & layout of visible features of
highway such as alignment, sight distance, curves, super elevation & intersections etc. The
geometrics of highway should be designed to provide optimum efficiency in traffic operation
with maximum safety at reasonable cost. The designer may be exposed to planning of new
highway network to meet the requirements of the anticipated traffic. The design is also
includes the sizes of drainage, aggregates, cross slopes, super elevation etc.
3.2.1 Requirements
The basic important requirements of an ideal alignment should be as follows:

The proposed alignment should be short as possible.

The road should be easy for construction & maintenance.

The road should be safe to operation and economical.

3.3 Factors Controlling Alignment


3.3.1 Obligatory points
These are control points governing the alignment of the highways. These control points are
divided into two categories, namely

Obligatory points through which the road alignment should pass.

Points through which the alignment should not pass. These will cause the alignment
often deviated from the shortest or easiest path.

3.4 Traffic
The proposed alignment should suit the traffic requirement. Origin and destination study
should be carried out in the area and desire lines be drawn showing the trend of traffic flow.
The new road to be aligned should keep in view the traffic flow patterns and future trends.
3.5 Geometric design

SSE, MUKKA, MANGALORE

Page 46

EXTENSIVE SURVEY REPORT-2012


BATCH-2
Geometric design factors such as gradients, radius of curve and sight distance also would
govern final alignment of highway. If straight alignment is aimed at, often it may be
necessary to provide very steep gradients. As far as possible while aligning a new road, the
gradient should be flat and less than the ruling or design gradient. Thus it may be necessary to
change the alignment in view of design speed, maximum allowable super elevation and
coefficient of lateral friction. It may be necessary to make the adjustment in the horizontal
alignment of roads keeping view the minimum radius of the curve and the transition curves.
Economy
The alignment should be economical. The initial cost, maintenance cost & vehicle operation
cost should be minimum, high embankment or deep cuttings are avoided & choose the
balance cutting & filling sight. These factors also control the alignments of road.

3.6 Engineering Surveys for Highway Location


The engineering surveys have to be carried out before finalizing the highway project. The
stages of engineering surveys are:
Map Study
Map study gives a rough guidance of routes to be surveyed in the field. The main features
like river, hills and valleys, etc. are known by map study. B y careful study of maps, the idea
of aligning a new highway can be obtained.

Reconnaissance Survey
In this survey, the land along the various proposed highway routes are inspected. All the
relevant details not available in the map study are collected and noted down.
Preliminary Survey

SSE, MUKKA, MANGALORE

Page 47

EXTENSIVE SURVEY REPORT-2012


BATCH-2
This is carried out to collect all the physical informations, which is necessary in connection
with the proposed highway alignment. The quantity of earth work and cost of construction
are worked out. The best proposal is selected after preliminary survey.
Detailed Survey
After preliminary survey, a detailed survey is carried out. Here Temporary Bench Marks are
fixed and leveling works are performed. Here an elaborate and complete data are collected
for preparing detailed plan and estimates of the project.

3.7 Curves
Curves are usually employed in the lines of communication in order that the change in
direction at the intersection of the straight lines shall be gradual. The curves are generally
circular arcs.
Circular Curves
The circular curves are divided into three types, namely;

Simple curve: It is a single arc connecting two tangents.

Compound curve: It consists of two arcs of different radii bending in the same
direction and lying on the same side of their common tangent.

Reverse curve: A reverse curve is composed of two arcs of equal or different radii
bending in opposite direction.

Transition Curves
A transition curve has a radius, which decreases from infinity at the tangent point to a
designed radius of circular curve. The rate of change of radius of transition curve will depend
on the equation of the curve or its shape.
Vertical Curve
There are two types of vertical curves, namely

Summit curve: These are the curves with convexity upwards.

Valley curve: These are also called as sag curves, where the convexity is downwards.

SSE, MUKKA, MANGALORE

Page 48

EXTENSIVE SURVEY REPORT-2012


BATCH-2
3.8 Super Elevation
In order to counteract the effect of centrifugal force and to reduce the tendency of vehicles to
overturn or skid, the outer edge of the pavement is raised with respect to its inner edge, thus
providing transverse slope throughout the length of a horizontal curve. This transverse
inclination of the pavement surface is known as Super elevation

3.9 Surveying Details


Introduction
In road survey, the first step is leveling. This is carried out using, instruments such as dumpy
level, cross staff and leveling staff. Other instruments used are prismatic compass to note the
bearings, arrows and ranging rods which are used to mark the points on the field. The
leveling operation starts from the benchmark. A benchmark is a point of known elevation.
The road is aligned by two operations, namely,

Longitudinal Sectioning.

Cross Sectioning

Where ever there is a necessity of providing a culvert, block leveling is carried out.
Longitudinal Sectioning or Profile Leveling
Profile leveling is a process of determining the elevation of points at fixed intervals along the
chain line. Here the line along which the section to be taken is marked by ranging rods, and
the fore bearing of the line is taken with the help of a prismatic compass. The level is then
setup at a point. The telescope is then directed to a staff, held on the temporary benchmark of
R. L. 100.00 m and the reading is taken. This reading is called as the back sight. Height of
collimation is determined. All these readings are noted down in a level book. Then the
intermediate sight is taken on the starting point of the line by holding the staff. For each
setup, intermediate sights should be taken after the fore sight on the next turning station has
been taken. To find the R.L. the intermediate sights are subtracted from the height of
collimation. When the instrument is removed, a change point is selected and a staff is held on
the same point and read it, which is fore sight.
It is then subtracted from the height of instrument to find the R.L. of the change point. The
instrument is then transferred to the second position. Having adjusted the instrument, a back
SSE, MUKKA, MANGALORE

Page 49

EXTENSIVE SURVEY REPORT-2012


BATCH-2
sight is taken on the change point just established. This reading when added to the change
point gives the R.L. of the new line of collimation. Then successive intermediate sights are
taken.
The horizontal distances are plotted along the horizontal axis to some convenient scale and
the distances are also marked. The elevations are plotted along the vertical axis. The various
points obtained are joined by straight lines.
Checking the levels
For checking the levels, we use the technique called Fly Levelling. In this, we start from the
last point and go to the first point, taking back sights and fore sights only, At the end, the last
point should be in the vicinity of the bench mark.
Cross Sectioning
Cross sections arc run at right angles to the horizontal profile and at either side of it for the
purpose of lateral outline of the, round surface. It provides data for estimating quantities of
earth work and other purposes. The cross sections are plotted in the same manner as the
longitudinal sections.
Contouring
On a plan, the relative altitudes of the points can be represented by contour lines as they
indicate the elevators directly. The area to be surveyed is divided into a number of squares.
The levels on the comer of these squares are determined by direct levelling. The contour
interpolation is done by graphical methods
Design Speed
It is the speed to which a road is designed.

Design speed on rural highways.

Design speed in kmph for various terrains.

Table No.13:-Design speeds for various terrains

Design speed in Kmph for various terrains


SSE, MUKKA, MANGALORE

Page 50

EXTENSIVE SURVEY REPORT-2012


BATCH-2
Road
Classification

Plain

Rolling

Mountainous

Steep

Rolling

Min

Rolling

Min

Rolling

Min

Rolling

Min

100

80

80

65

50

40

40

30

National and
State
Highway
Gradients
Gradient is the rate of rise or fall along the length of the road with respect to the horizontal. In
road design as much as possible les gradient are provided to increase the design speed.
Gradient are divided into following types.
a) Ruling gradient: It is the maximum gradient within which the designer attempts to
design the vertical profile of the road.
b) Limiting gradients: It is the gradient steeper than the ruling gradient.
c) Exceptional gradients: It is the unavoidable steeper gradient provided for a smaller
road stretch of the road.
d) Minimum gradient: It is the minimum gradient provided in the roads for the drainage
of rain water as quick as possible. It will depends on the soil property, rainfall, runoff,
etc.
Table No.14:-Gradient according to IRC

Terrain

Ruling Gradient

Limiting Gradient

Exceptional

Plain and rolling


Mountainous

3.3% (1 in 30)

5% (1 in 20)

6.7%(1 in 15)

having elevation

5%( 1in 20)

6%(1 in 16.7)

7%(1 in 14.3)

6%(1 in 16.7)

7%(1 in 14.3)

8%( 1 in 12.5)

gradient

>3000m above
MSL
Steep terrain up to
3000m above MSL
Width of Roadway or Formation
It is the sum of widths of pavements or carriageway including separators if any and
shoulders. Formation width is the top width of the highway embankment or the bottom width
of the highway cutting excluding the side drains.
SSE, MUKKA, MANGALORE

Page 51

EXTENSIVE SURVEY REPORT-2012


BATCH-2

Table No.15:-Width of roadway recommended by IRC

SL. No.

Road Classification

Roadway width for plain &


rolling terrain, m

1.

2.

NH & SH
a) Single lane

12

b) Double lane

12

MDR
a) Single lane

b) Double lane

Camber
Cross slope or camber is the slope provided on the road pavement to drain off the rainwater
from the road pavement surface. It usually maximum at center of the road & at edge camber
value is zero in a stretch.

Table No.16:-IRC recommended values of camber

SL. No.

1.

Types of road

Range of cambers in areas of rainfall

Surfaces

range
Heavy to light

Cement concrete and


high type bituminous

1 in 50 (2%)

1 in 60 (1.7%)

surface
2.

Thin bituminous
1 in 40 (2.5%)

1 in 50 (2%)

3.

surfaces
WBM and gravel
pavement

1 in 33(3%)

1 in 40 (2.5%)

Earth

1 in 25(4%)

1 in 33(3%)

4.

SSE, MUKKA, MANGALORE

Page 52

EXTENSIVE SURVEY REPORT-2012


BATCH-2
Kerb
Kerbs are provided at the edge of road b/w the road & shoulders. It prevents the direct entry
of road vehicles in to the shoulders.
Shoulders
It is the thin strip of land provided along the road edge for the emergency lane for parking or
to repair the damaged vehicles.
The minimum shoulder width recommended by IRC is 2.5m

3.10 Design of horizontal alignment


Horizontal curves
When the centerline of the road changes the direction along the horizontal plane, horizontal
curves are provided & the same are designed as follows.

Super Elevation
To counteract the effect of centrifugal force and to reduce the tendency of vehicle to overturn
or skid the, outer edge of pavement is raised with respect to inner edge. Such provision of
transverse slope is provided on horizontal curves. The design of super elevation is illustrated
as below
Extra Widening
Extra widening is provided to provide extra space required for mechanical and psychological
reasons along the horizontal curve, which is provided as per the table below

Table No.17:-Extra widening valve IRC recommended

SL. No.

Radius of curve (m)

Up to 20m

1.5

20-40m

1.5

41-60m

1.2

61-100m

0.9

5
101-300m
SSE,
MUKKA,
MANGALORE
6

Above 300m

Extra width for two lane road (m)

Page 53

0.6
nil

EXTENSIVE SURVEY REPORT-2012


BATCH-2

3.11 Vertical Alignment


When two different or contrary gradients meet, they are connected by a curve in the vertical
plane known as vertical curve. These are needed to secure a gradual change in grade so that
abrupt change in grade at the apex is not allowed. The vertical curves used in highway may
be classified in to two categories.

Summit curve

Valley curve

a) Summit curve:
A curve with convexity up wards is called a summit curve. This occurs when an ascending
intersect a descending gradient or when an ascending meets on other ascending gradient or an
ascending gradient meeting a horizontal a summit curve is provided here as there is change in
gradient matching the requirements of a summit curve. The summit curve is designed end as
below.
b) Valley Curve:
A vertical curve, concave upwards is called as valley curve. This is formed when a
descending gradient intersect an ascending gradient or when a descending gradient meets
another descending gradient or when a descending gradient gains a horizontal path, they
should be designed for:

Comfort

Head light sight distance condition.

3.12 Pavement Design


For the safety and comfort ability of fast vehicles road surface should be even along the
longitudinal profile. The surface should also so be stable and unyielding in different
conditions and it should allow the heavy load of traffic to move with least possible resistance.
SSE, MUKKA, MANGALORE

Page 54

EXTENSIVE SURVEY REPORT-2012


BATCH-2
In order to provide a stable and even surface for traffic the road way is provided with a
suitably designed and constructed pavement structure. Pavement is designed and to distribute
wheel load in larger area and elastic deformation caused by the load to fall within the
permissible limit.
Table No.18:-LONGITUDINAL AND CROSS SECTION OF HIGHWAY ALIGNMENT
SI.NO

B.S
0.650

C0.00

0.750

R.L
90.000
89.900

L5

0.645

90.000

L10

0.525

90.120

L15

0.395

90.255

R5

1.160

89.490

R10

1.425

89.225

R15

1.800

88.850

C20.00

1.265

89.385

L5

1.135

89.515

L10

1.215

89.435

L15

1.610

89.040

R5

1.495

89.155

R10

1.795

88.855

R15

2.155

88.495

C40.00

1.790

88.860

L5

1.640

89.010

L10

1.810

88.840

L15

2.040

88.600

R5

1.955

88.690

R10

2.150

88.500

R15

0.120

88.380

C60.00

2.200

88.450

L5

2.290

88.360

L10

2.435

88.215

L15

2.630

88.020

R5

2.220

88.405

R10

2.360

88.285

R15

2.260

88.385

SSE, MUKKA, MANGALORE

I.S

Page 55

F.S

H.I
90.650

REMARKS
Bench Mark

EXTENSIVE SURVEY REPORT-2012


BATCH-2
C83.94

2.220

88.430

L5

2.375

88.275

L10

2.755

87.895

L15

3.195

87.405

R5

2.155

88.495

R10

2.205

88.445

R15

2.545

88.100

C98.94

1.100

86.615

L5

0.595

87.120

L10

0.635

87.080

L15

0.685

87.030

R5

1.165

86.550

R10

1.335

86.380

R15

1.365

86.350

C113.34

2.445

85.270

L5

2.000

85.710

L10

4.580

83.135

L15

4.930

82.780

R5

1.890

85.820

R10

1.900

85.810

R15

1.910

85.800

C128.34

1.895

3.555

86.055

84.160

L5

1.855

84.200

L10

1.505

84.550

L15

1.320

84.735

R5

2.050

84.005

R10

2.055

84.000

R15

2.045

84.010

C143.34

1.835

85.880

L5

1.830

85.885

L10

1.830

85.885

L15

1.840

85.875

R5

1.830

85.885

R10

1.830

85.885

R15

1.830

85.885

C173.34

0.335

87.380

SSE, MUKKA, MANGALORE

Page 56

EXTENSIVE SURVEY REPORT-2012


BATCH-2
L5

0.355

87.360

L10

0.380

87.335

L15

0.495

87.220

R5

0.165

87.550

R10

0.160

87.555

R15

4.230

1.290

90.655

86.425

C203.34

1.890

88.765

L5

2.860

88.795

L10

2.920

87.735

L15

2.950

87.705

R5

1.525

89.130

R10

1.500

89.155

R15

1.520

89.135

C213.34

1.160

89.490

L5

2.170

88.480

L10

2.320

88.330

L15

2.440

88.210

R5

1.145

89.510

R10

1.165

89.490

R15

1.205

89.450

L5

2.230

88.420

L10

2.800

87.850

L15

3.010

87.645

R5

1.105

89.550

R10

0.880

89.775

R15

0.505

90.150

C213.34

C226.34

0.100

3.055

87.700

87.600

L5

0.810

86.890

L10

1.675

86.025

L15

1.905

85.795

R5

0.785

86.915

R10

0.755

86.945

R15

0.735

86.965

C236.44

2.570

85.130

L5

2.965

84.795

SSE, MUKKA, MANGALORE

Page 57

EXTENSIVE SURVEY REPORT-2012


BATCH-2
L10

3.350

84.350

L15

3.720

83.975

R5

1.820

85.880

R10

0.970

86.730

R15

0.805

86.895

C246.44

5.160

82.540

L5

1.310

L10

5.210

83.800

4.645

82.490
79.150

L15

81.000

R5

4.600

87.700

83.100

R10

3.600

87.700

84.100

R15

84.000

C256.55

4.680

L5

4.670

79.120

L10

4.680

79.120

L15

4.680

79.120

R5

1.840

81.960

R10

0.595

83.200

R15

0.250

83.550

C286.55

5.725

78.070

L5

5.720

78.080

L10

5.715

78.080

L15

5.710

78.090

R5

5.715

78.080

R10

0.150

83.650

R15

0.050

83.750

C316.55

5.720

78.075

L5

5.730

78.070

L10

5.850

77.950

L15

5.900

77.900

R5

5.720

78.090

R10

5.710

78.080

R15
Change point
C329.55

0.590

83.210
78.200
80.645

6.275
6.095

L5
SSE, MUKKA, MANGALORE

83.800

5.600
3.830
3.220
Page 58

84.475
86.740

79.120

83.520

EXTENSIVE SURVEY REPORT-2012


BATCH-2
L10

3.520

83.210

L15

3.840

82.900

R5

3.350

83.390

R10

3.410

83.330

R15

3.420

83.320

C339.55

1.940

84.790

L5

2.050

84.690

L10

2.150

84.590

L15

2.235

84.505

R5

0.795

85.945

R10

0.445

86.295

R15

0.175

86.565

C349.55

1.035

85.705

L5

1.630

85.110

L10

2.245

84.495

L15

2.930

83.310

R5

0.605

86.135

R10

0.435

86.305

R15

0.405

86.335

C363.25

2.930

84.350

L5

2.500

84.240

L10

3.155

83.585

L15

3.935

82.805

R5

1.600

85.140

R10

1.610

85.130

R15

1.780

84.960

C378.25

0.390

5.700

81.430

81.040

L5

5.605

81.135

L10

5.600

81.140

L15

6.220

80.520

R5

0.515

80.920

R10

0.465

80.965

R15

0.690

80.740

C383.25

1.710

79.720

L5

2.000

79.430

L10

2.210

79.220

SSE, MUKKA, MANGALORE

Page 59

EXTENSIVE SURVEY REPORT-2012


BATCH-2
L15

2.330

79.100

R5

2.025

79.450

R10

2.105

79.325

R15

2.175

79.255

C388.25

4.630

76.800

L5

4.520

76.910

L10

4.500

76.930

L15

4.490

76.940

R5

4.520

76.910

R10

4.500

76.925

R15

4.510

76.920

C393.25

2.150

7.500

76.080

73.930

L5

2.795

73.285

L10

2.400

73.680

L15

2.350

73.730

R5

1.700

74.680

R10

1.785

74.295

R15

1.520

74.560

C398.25

3.420

72.660

L5

3.645

72.435

L10

3.740

72.340

L15

3.800

72.280

R5

3.325

72.755

R10

3.310

72.770

R15

3.025

73.055

C408.25

2.850

3.645

75.285

72.435

R5

2.950

72.335

R10

2.850

72.435

R15

2.370

72.915

L5

2.750

73.135

L10

4.160

71.125

L15

4.245

71.040

C413.48

3.020

72.620

L5

4.180

71.105

L10

4.540

70.740

L15

4.720

70.565

SSE, MUKKA, MANGALORE

Page 60

EXTENSIVE SURVEY REPORT-2012


BATCH-2
R5

3.010

72.275

R10

2.780

72.505

R15

2.715

72.570

C426.98

0.915

74.370

L5

1.230

74.055

L10

1.680

73.605

L15

1.975

73.310

R5

0.760

74.525

R10

0.550

74.735

R15

5.750

0.320

80.715

74.965

C441.98

1.945

78.770

L5

2.030

78.685

L10

1.970

78.745

L15

2.045

78.670

R5

1.820

78.895

R10

2.000

78.715

R15

2.305

78.410

C461.98

1.020

79.695

L5

1.180

79.535

L10

1.240

79.475

L15

1.270

79.445

R5

1.080

79.635

R10

1.110

79.605

R15

1.130

78.585

C461.98

1.020

79.695

L5

1.090

79.625

L10

1.160

79.555

L15

1.190

79.525

R5

1.160

79.555

R10

1.215

79.500

R15

1.300

79.415

C483.98

0.915

79.800

L5

0.850

79.865

L10

1.315

79.400

L15

1.520

79.195

R5

1.085

79.630

SSE, MUKKA, MANGALORE

Page 61

EXTENSIVE SURVEY REPORT-2012


BATCH-2
R10

1.110

79.605

R15

1.050

79.665

C513.98

2.790

1.405

82.210

79.310

L5

4.320

77.780

L10

4.900

77.310

L15

5.640

76.570

R5

1.340

80.870

R10

0.255

81.955

R15

0.090

82.120

C543.98

3.240

78.970

L5

4.150

78.060

L10

5.325

76.885

L15

5.855

76.355

R5

1.780

80.430

R10

0.660

81.550

R15
CH POINT
C573.98

0.430
2.425

81.780
79.970
79.195

L5

3.580

78.040

L10

4.485

77.135

L15

5.605

76.015

R5

1.510

80.110

R10

0.580

81.040

R15

0.235

81.380

C871.51

1.300

L5

1.100

83.735

L10

1.115

83.720

L15

1.110

83.725

R5

1.190

83.645

R10

1.185

83.650

R15

1.180

83.655

C894.170

1.600

83.235

L5

1.940

82.895

L10

2.050

82.785

L15

2.125

82.710

R5

1.460

83.375

1.635

SSE, MUKKA, MANGALORE

Page 62

84.835

83.535

EXTENSIVE SURVEY REPORT-2012


BATCH-2
R10

1.210

83.625

R15
Change point
C917.87

1.220
1.605

83.615
83.385
82.490

L5

1.575

82.520

L10

1.590

82.505

L15

1.610

82.485

R5

1.605

82.490

R10

1.615

82.480

R15

1.620

82.475

C917.87

1.605

82.490

L5

1.595

82.500

L10

1.590

82.505

L15

1.595

82.500

R5

1.605

82.490

R10

1.610

82.485

R15
Change point
C947.87

1.620
1.610

82.475
77.835
77.385

L5

1.590

77.405

L10

1.585

77.410

L15

1.590

77.405

R5

1.605

77.390

R10

1.610

77.385

R15

1.610

77.385

C977.87

1.610

77.385

L5

1.600

77.395

L10

1.590

77.405

L15

1.595

77.400

R5

1.600

77.390

R10

1.615

77.380

R15

1.615

77.380

c1007.87

1.615

77.380

L5

1.605

77.390

L10

1.610

77.305

L15

1.600

77.395

0.170

1.450

1.160

SSE, MUKKA, MANGALORE

6.260

Page 63

84.095

78.985

EXTENSIVE SURVEY REPORT-2012


BATCH-2
R5

1.620

77.375

R10

1.625

77.370

R15

1.635

77.360

C1037.87

1.610

77.385

L5

1.605

77.390

L10

1.595

77.400

L15

1.600

77.395

R5

1.615

77.380

R10

1.620

77.370

R15
Change point
C1052.47

1.630
3.860

77.365
77.575
77.525

L5

3.850

77.535

L10

3.840

77.545

L15

3.800

77.585

R5

3.885

77.500

R10

3.840

77.545

R15

3.400

77.985

C1052.47

3.860

77.525

L5

3.855

77.530

L10

3.855

77.530

L15

3.850

77.535

R5

3.870

77.515

R10

3.875

77.510

R15

3.875

77.510

C1091.47

1.305

80.080

L5

1.100

80.285

L10

0.950

80.435

L15

0.750

80.635

R5

1.425

79.960

R10

1.560

79.825

R15

1.875

79.510

C1091.47

1.305

80.080

L5

1.300

80.085

L10

1.290

80.095

L15

1.295

80.090

3.810

SSE, MUKKA, MANGALORE

1.420

Page 64

81.385

EXTENSIVE SURVEY REPORT-2012


BATCH-2
R5

1.310

80.075

R10

1.320

80.065

R15
Change point
C1111.57

1.345
0.665

80.060
80.720
81.300

L5

0.910

81.555

L10

0.455

81.510

L15

0.500

81.465

R5

1.595

81.370

R10

1.980

79.985

R15

1.210

79.900

C1111.57

0.665

81.300

L5

1.015

80.950

L10

0.465

81.500

L15

0.490

81.475

R5

1.515

80.450

R10

1.725

80.240

R15

1.750

80.215

C1146.97

1.790

80.175

L5

0.250

81.715

L10

0.400

81.565

L15

0.550

81.000

R5

1.840

80.125

R10

1.940

80.025

R15

1.980

80.000

C1167.67

2.520

79.445

L5

1.250

80.715

L10

1.535

80.430

L15

1.620

80.345

R5
change point
R15

2.440
0.800

79.525
79.570
79.720

C1167.67

2520.000

78.000

L5

1.245

79.275

L10

1.625

79.895

L15

1.805

78.715

1.245

0.665

0.950

2.395

SSE, MUKKA, MANGALORE

Page 65

81.965

80.520

EXTENSIVE SURVEY REPORT-2012


BATCH-2
R5

3.015

77.505

R10

2.390

78.130

R15

1.805

78.715

C1186.67

2.745

77.775

L5

2.750

77.770

L10

2.755

77.765

L15

2.760

77.760

R5

2895.000

77.625

R10

2.890

77.630

R15
change point
C1201.77

2.900
4.600

77.620
77.920
72.075

L5

4.595

72.080

L10

4.590

72.085

L15

4.595

72.080

R5

4.605

72.070

R10

4.610

72.065

R15

4.610

72.065

C1201.77

4.600

72.075

L5

4.590

72.085

L10

4.595

72.080

L15

4.585

72.090

R5

4.605

72.070

R10

4.615

72.060

R15

4.620

72.055

C1213.77

2.210

74.465

L5

2.205

74.470

L10

2.200

74.475

L15

2.195

74.480

R5

2.215

74.460

R10

2.225

74.450

R15

2.230

74.445

C1213.77

2.210

74.465

L5

2.205

74.470

L10

2.200

74.475

L15

2.195

74.480

0.755

SSE, MUKKA, MANGALORE

4.600

Page 66

76.675

EXTENSIVE SURVEY REPORT-2012


BATCH-2
R5

2.215

74.460

R10

2.225

74.450

R15

2.230

74.445

C1243.77

3.555

73.140

L5

3.550

73.120

L10

3.540

73.135

L15

3.545

73.130

R5

3.560

73.115

R10

3.565

73.110

R15

3.575

73.100

C1273.77

2.010

74.665

L5

2.005

74.670

L10

2.000

74.675

L15

1.995

74.680

R5

2.015

74.660

R10

2.020

74.655

R15
change point
C1303.77

2.025
1.000

74.650
74.665
74.425

C1333.77

1.555

74.870

C1363.77
Change point
C1383.77

2.075
1.960

73.350
73.350
71.845

C1403.77

2.085

71.720

C1423.77
Change point
C1443.77

1.835

71.970
71.970
72.335

0.760

2.010

0.455

2.075

2.150

C1451.27
END POINT

75.425

1.835

74.120

1.785
1.380
1.190

3.13 DIFFERENT TYPE OF DESIGN ASSPECTS


Fig No.9:- CHAINAGE AT 213.34 (SIMPLE CURVE)

SSE, MUKKA, MANGALORE

Page 67

72.740
72.930

EXTENSIVE SURVEY REPORT-2012


BATCH-2

ANGLE = = 70 (deflection angle)


D= 70 (degree of curve)
D = 40 * ( / 180)
= 1.22 (rad)
1) Radius (R) = 1719/D
= 1719/1.22
= 1409.00m
2) Tangent length = R tan (/2)
= 1409.00 * (tan (70/2)
= 986.60 m
3) Length of curve =( * R* ) / 180
= ( *1409 * 70)/180
= 1721.41 m

Fig No.10:- CAHINAGE AT 1111.57 TO 1052.47 (COMPOUND CURVE)

SSE, MUKKA, MANGALORE

Page 68

EXTENSIVE SURVEY REPORT-2012


BATCH-2

1= 47 2=55
D1= 134 D2 = 125
D1 = 134 * /180 = 2.338 (rad)
D2 = 125 * / 180 = 2.182(rad)
1) Radius (R1) = 1719 / D1
= 1719 /2.338
= 735.0 m
(R2) = 1719 / D2
= 1719 /2.182
= 789.93 m 790.0 m
2) Tangent length ( T1 E) = R1 * (tan1 /2)
= 735 * tan (47/2)
= 319.58 m

3) F T2 = R2 * (tan2 /2)
SSE, MUKKA, MANGALORE

Page 69

EXTENSIVE SURVEY REPORT-2012


BATCH-2
= 790 * tan (55/2)
= 411.24 m
The total tangent length (T1 to T2) = 319.58 + 411.24
= 730 .82 m
4) Length of the curve (T1 D) = ( * R1* 1) / 180
= ( * 735 * 47)/180
= 603.0 m
Length of the curve (T2 D) = ( * R2* 2) / 180
= ( * 790 * 55)/180
= 758.44 m

Fig No.11:- CHAINAGE AT 1273.77 (SIMPLE CURVE)

ANGLE = = 70 (deflection angle)


D= 70 (degree of curve)

SSE, MUKKA, MANGALORE

Page 70

EXTENSIVE SURVEY REPORT-2012


BATCH-2

D = 40 * ( / 180)
= 1.22 (rad)
1) Radius (R) = 1719/D
= 1719/1.22
= 1409.00m
2) Tangent length = R tan (/2)
= 1409.00 * (tan (70/2)
= 986.60 m
3) Length of curve =( * R* ) / 180
= ( *1409 * 70)/180
= 1721.41 m

DESIGN OF SUMMIT CURVE


Upward gradient

= 1 in 450

Downward gradient = 1 in 30
n = +1/450
n = -1/30
N=1/450 - (-1/30)
N= (3+45)/1350=48/1350
I If L>OSD
L= NS2/9.6= 48*455.142/1350*9.6
L= 767.23M
As this value is greater than OSD, assumption is correct
The length of the summit curve is greater than stopping sight distance
L>SSD
Length, L=NS2/4.4 = 48*1472/1350*4.4 = 174.61
Hence, the assumption is correct.
SSE, MUKKA, MANGALORE

Page 71

EXTENSIVE SURVEY REPORT-2012


BATCH-2
The length of summit curve required is 174M which is greater than 147M.

SSE, MUKKA, MANGALORE

Page 72

EXTENSIVE SURVEY REPORT-2012


BATCH-2
Fig No.12:- DESIGN OF VALLEY CURVE

Upward gradient

= 1in 182

Downward gradient = 1in 30


n1 = 1/30
n2 = 1/182
N = -1/30-1/182 =-91-25/2730 = -106/2730
Assume V= 65KMPH = 65/3.6 = 18.05m/sec
Centrifugal acceleration, C=0.6m/sec3 (assume)
i) Comfort Condition
L= 2*[NV3/C]1/2
= 2*[106*18.053/2730*0.6]1/2
= 39.01M
ii) Head light sight distance condition
If L>SSD
L= NS2/(1.5+0.035S)
= 106*1472/2730(1.5+0.035*147)
= 2290554/18140.85
= 126.26M <SSD

SSE, MUKKA, MANGALORE

Page 73

EXTENSIVE SURVEY REPORT-2012


BATCH-2

L<SSD
L= 2S-1.5+0.035S/N
= 2*147-(1.5+0.035*147)/(106/2730)
= 294-171
= 122.8M
The assumption is correct according to the head light sight distance condition. The design
length of valley curve is 122.8M say 125M.

GEOMETRIC DESIGN OF HIGHWAY


1) Stopping sight distance (SSD)
i) Head light stopping sight distance =( 0.278vt+v2) / 254f
Where,
v= design speed, assume = 65kmph
t= reaction time of driver, assume= 2 sec
f= coefficient of lateral friction, assume= 0.15 sec
SSD= 0.278*65*2+652/ (254*0.15)
SSD= 147.00m

ii) Intermediate stopping sight distance = 2* SSD


= 2* 147.00
= 294.00 m
2)

Over taking sight distance (OSD)

V= design speed, assume = 65kmph


SSE, MUKKA, MANGALORE

Page 74

EXTENSIVE SURVEY REPORT-2012


BATCH-2
A= acceleration, assume = 2.5kmph/sec

i) One-way traffic
OSD=d+d
a) d= 0.28v*t
d=0.28*65*2

d = 36.4m
b) d= 0.28v*T+2s
s= 0.2v+6

s= 0.2*65+6
s= 19m
T = 14.4s/2.5
=14.4*19/2.5
= 10.46 sec
d= 0.28*65*10.46 + (2*19)
d= 228.37m
OSD= d+d
OSD =36.4+228.37
OSD=264.77m

ii) Two-way traffic


OSD= d+d+d
Where,
d= 36.40m
d= 228.37m
d= 0.28v*T
d= 0.28*65*10.46
d = 190.37m
OSD= 36.40+228.37+190.37
OSD= 455.14m

SSE, MUKKA, MANGALORE

Page 75

EXTENSIVE SURVEY REPORT-2012


BATCH-2

iii) Super elevation (e)

v= design speed, assume= 65kmph


R=radius of curve, assume = 1410m
e=V2/225R
e=652 / (225*1410)
e= 0.0133m
If the calculated value of e is less than 7% or 0.07 the value so obtained is provided. If the
value of e as per equation e exceeds 0.07 than provide the maximum super elevation equal
to 0.07.

iv) Coefficient of lateral friction (f)


f= v2/127R e
f= 652/ (127*1410) 0.07
f= 0.046
If the value of f thus calculated is less than 0.15, than super elevation of 0.07 is safe for
design speed. If not, calculate the restriction speed or allowable speed.

SSE, MUKKA, MANGALORE

Page 76

EXTENSIVE SURVEY REPORT-2012


BATCH-2

v) Extra widening of pavement (we)

n= no. of lane, assume=2


L= wheel base, assume=6m
We =n*L2 /2R + V/9.5R
= (2*62) / (2*760) + 65/9.51410
We= 0.047 + 0.182
We= 0.229m
Say We= 0. 30m
DESIGN OF PAVEMENT (FLEXIBLE PAVEMENT)
a) Specific gravity of soil

= 2.05

b) Water content (W)

= 8%

c) Maximum dry density d= Gw

= 2.05*9.81

(1+W)

(1+0.08)
= 18.8 KN/M3

Maximum dry density


d) CBR value

= 10%

e) Camber

= 2%

f) Average daily traffic of commercial vehicle = P= 1000


g) Growth rate of traffic

= r = 10%

h) Provide a camber of 2% (Combination of straight)


i) Carriage way
SSE, MUKKA, MANGALORE

= 2 lane of 7.5M
Page 77

EXTENSIVE SURVEY REPORT-2012


BATCH-2
j) Shoulder width

= 1.50M each side

k) Design speed

= 65KMPH

l) Period of construction

= x = 1 year

m) Design life

= n = 25 years

i)

A= P(1+r)x

Where, A= Initial traffic in terms of number of commercial vehicles per day


P= Number of vehicles per last count
r = Annual growth rate of commercial vehicle
x = Number of years for competition of construction
A = P (1+r) x
= 1000(1+0.1)1
A = 1100
ii)

N = 365*[(1+r)n-1/r]*A*D*F

Where, A= Initial traffic in terms of number of commercial vehicles per day


D= Lane distribution factor= 0.75 for 2 lane single carriage way
F= Vehicle damage factor = 3.5 for traffic volume of 150 to 1500 CVD
N = 365*[(1+0.1)25-1/0.1]*1100*0.75*3.5
N = 103.81 say 104 Msa
From IRC chart for 104Msa i.e., (Between 10 to 150 Msa, CBR = 10%)
iii)

Thickness of pavement,
t = 630 + (650-630)/(150-100)*(104-100)
t = 631.6mm say 632mm
So provide, Sub base
Dense bituminous macadam (DBM) = 260mm
Bituminous concrete

= 150mm

Total pavement thickness

= 632mm

SSE, MUKKA, MANGALORE

Page 78

EXTENSIVE SURVEY REPORT-2012


BATCH-2

The summary of our project is as follows


1. Road length

: 1423m

2. Design speed

: 65kmph

3. Camber

: 1 in 30

4. Width of pavement

: 3.75m

5. Width of roadway

: 7.50m

6. Width of the shoulder

: 1.50m

7. Soil type throughout route

: Gravelly soil

8. Pavement

: Flexible

3.14 Conclusion:From the above proposal-I and proposal-II, the difference I quality of cutting and filling is very
minimum in case of proposal-II, the alignment passes through one of the town. Therefore, the
final alignment is preferred.
The highway is designed to serve the people around the region selected, so that it connects the
nearby existing roads. The village people therefore can easily access the city. Hence
transportation will be much easier than before. The people traveling through this road will have
a healthy atmosphere and it gives good aesthetic appearance. Hence further, the village will be
improved in future.

SSE, MUKKA, MANGALORE

Page 79

EXTENSIVE SURVEY REPORT-2012


BATCH-2

4.

TRIANGULATION

4.1 Introduction
The horizontal control in geodetic survey is established either by triangulation or by precise
traverse. In triangulation a number of inter connected triangles are involved in which the length
of only one line called base line is measured and all angles are measured. The other two sides
can be calculated by geometry. The apex of triangles is known as triangulations stations and the
whole figure is called triangulation figure. One of the main drawback of triangulation is errors
gets accumulated. At stations astronomical observations are made for azimuth and longitude to
control these accumulations. Such stations are called Laplace stations.

4.2 Objects of Geodetic Triangulation


1) To provide the most accurate system of horizontal control points on which less
precise triangles may be based which in turn from the frame work on which
topographical, geological, hydrological, surveys may be based.

2) To arrest in determination of size and shape of earth while making observations


for latitude, longitude and gravity.

4.3 Routine of triangulation survey


Triangulation survey usually consists of following operations.
1. Reconnaissance.
2. Erection of signals and towers.
3. Measurement of base lines.

SSE, MUKKA, MANGALORE

Page 80

EXTENSIVE SURVEY REPORT-2012


BATCH-2
4. Measurement of horizontal angles.
5. Astronomical observations at Laplace stations.
6. Computations.

4.4 Reconnaissance
Call for a great amount of skill, experience and judgment involves.

Examination of country to be surveyed.


Selection of suitable positions for triangulation stations.
Selection site for base line.
Determination of inter visibility and height of stations.
Collection of miscellaneous information regarding water, food, labor etc.

4.5 Selection of triangulation stations

Station must be interred visible.


They should form well-conditioned triangles. No angle should be smaller than

30degrres and greater than 120degeers.


Stations should be easily accessible.
They should be in commanding positions to serve as control in subsidiary

triangulations.
They should be so suited that lines of site should not pass over towers of
factories.

4.6 Signals and towers

A tower is a structure erected over a station for the support of instrument


provided when station or signals or both are elevated.
A signal is a device erected to define the exact position of observed station.
A signal has to fulfill following requirements.
1. It should be concisions.
2. It should be capable of lying accurately centered over station mark.
3. It should be suitable for accurate bisections.
4. It should be free from phase.

SSE, MUKKA, MANGALORE

Page 81

EXTENSIVE SURVEY REPORT-2012


BATCH-2
4.7 Base line
Measurement of base line forms the most important part of the triangulation survey as it
serves as the basis for the all other computation. Following points are to be considered while
selecting the site for the base line.

Site should be free from obstructions throughout out the length.


Site should be fairly level.
The extremes of the base line should be inter visible.
Ground should smooth and fair.
Site should suit extension of primary triangulations.
A) Equipment:
30m steel band.
30m steel tape.
Theodolite and its accessories.
Wooden pegs.
Thermometer.
Level and accessories.
Spring balance.
Substance bar and its accessories.
B) Procedure:
Base line is determined by two flag post with drums at A and B. following
operations has to be carried in order.

4.8 Transferring of signal points to the ground


Double plan method is adopted for the purpose. The Theodolite is set at point P and flag
of the signal is bisected. Telescope is swung towards the ground and two points in the
vertical plan are marked on the point Q. the intersection of two lines gives the position
of the signal on the ground. The two signals A and B are transferred on the ground in the
above said manner.

4.9 Measurement of angles


In order to make angular measurements Theodolite is setup over the station point A.
angle between different stations are measured by following method.
SSE, MUKKA, MANGALORE

Page 82

EXTENSIVE SURVEY REPORT-2012


BATCH-2

Repetition method.
Reiteration method.

4.9.1 Measurement of angle PQR by repetition method:

Theodolite is set on point Q, vernier A is made to read 0. The lower screw is

clamped after station P is bisected.


The upper screw is unclamped and station r is bisected. Reading of vernier A &

B are recorded. The upper screw is clamped and the lower screw is unclamped.
The station Q is bisected and the process is repeated again. These operations are
carried out as many times as required usually three).

For the accurate results the operation is carried out four times.

Face right clockwise swing.


Face left clockwise swing.
Face right anticlockwise swing.
Face left anticlockwise swing.
Angles are determined by dividing the final angles by number of repetitions.
Average of face right and face left readings is taken as the horizontal angles.

4.9.2 Measurement of angles by reiteration method


In this method several angles are measured simultaneously and horizon is closed.

The instrument is set at O and vernier is made to read 0. Lower screw is clamped

after bisecting point A.


Upper screw is unclamped and the station B is bisected. The vernier readings are

noted down.
Simultaneously stations C & D are bisected and the readings are noted down.
Finally station A is bisected and errors if any are distributed to all angles.
Process is repeated as in case of repetition method.

4.10 Measurement of base line

Theodolite is set on station A and station B is sighted. The telescope is depressed

and along the line AB, several pegs are driven at suitable intervals.
The distance between each peg is measured accurately. Hence steel band is
stretched between the pegs at a pull of around 5-6 kgs.

SSE, MUKKA, MANGALORE

Page 83

EXTENSIVE SURVEY REPORT-2012


BATCH-2

Temperature of the band is noted at the two ends and the middle.
Fly leveling is carried out from an established bench mark and levels on top of

pegs are noted down.


Exact length of base line is obtained by applying required correction to all spans

and adding them.


Length should cross checked by using the substance bar method.

4.11 Correction for length


1. Correction for absolute length.
2. Correction for temperature.
3. Correction for pull or tension.
4. Correction for sag.
5. Correction for slope.
6. Correction for alignment.
7. Reduction to sea level.

Correction for absolute length


If the absolute length of the tape is not equal to designated length, corrections will be
applied. Correction is positive if the absolute length is more than designated length and
vice versa.
Thus

Where,
Ca=correction.
L =measured length.
C =correction for absolute length.
l =designated length of tape.

Correction for temperature


Metals undergo contraction or elongation due to variation in temperature. Hence
correction for temperature will have to be applied. Correction is positive if temperature

SSE, MUKKA, MANGALORE

Page 84

EXTENSIVE SURVEY REPORT-2012


BATCH-2
is more than the temperature at which tape is standardized and vice versa.
Ct= X (Tm-To) L
Where,
= co-efficient of thermal expansion.
Tm = mean temperature of the tape.
To = standardized temperature.
L = measured length.

Correction for pull


Correction is positive if pull applied during measurement is more than pull at which tape
has been standardized. Correction is negative if pull is less than the pull at which tape
has been standardized.

Where,
P=pull during measurement.
Po=standard pull.
A=cross-sectional area of tape.
E=Youngs modulus.
L=mw=measured length.
Pill applied in the field be less than 20 times the weight of the tape.

Correction for slope


Difference in elevation between the points is known. Correction for slope is always negative.
Ch =

Where,
h=difference in elevation.
L=measured length.

Correction for sag


When a tape is stretched between two points, the self weight causes it take the form of
horizontal catenaries. A correction is to be applied for this and it is always negative.

SSE, MUKKA, MANGALORE

Page 85

EXTENSIVE SURVEY REPORT-2012


BATCH-2
Cs= Where,
L=measured length.
W=weight of tape in kg.
P=applied pull in kg.
Reduction to mean sea level:
The sphere city of earth causes measured length to be different at different elevations. Hence, all
measurements are reduced to length at mean sea level.
CMSL= -

Where, L=measured length of base.


h=Average elevation above MSL.
R=radius of the earth=6367Kms.
[

Procedure of base line measurement


Base line measured falls under tertiary triangulation system.

Fig No.16:- Measurement of base line

The location of wooden pegs on the base line starting from trigonometric stations A to B

Procedure followed in the base line measurement


Base line is defined by two flag with drawn at A&B following procedure is adopted in
measurement of distance AB.

SSE, MUKKA, MANGALORE

Page 86

EXTENSIVE SURVEY REPORT-2012


BATCH-2
Fig No.17:- Transferring signal point on to ground

4.12 Transferring signal point on to ground


The Theodolite is setup at point P1, focus the telescope to tip of the pointer on the drum, and
move vertically down mark on to the ground and locate the line of sight by an arrow on the
ground. Run the tape from p to C draw an arc on the ground at C.
Shift the Theodolite to point Q (arbitrarily selected). Follow the above procedure and locate
point D. Draw an arc at D with zero end of the tape at Q. Bisect the previously drawn arc at C.
The bisected points of the two arcs at C&D give the triangulation station A.

Follow the same procedure at station B and locate the station point B on ground.

1. To fix up wooden pegs and measurement


Set the Theodolite on point A, sight B, clamp and plunge the telescope to locate new instrument
point A on the ground. Shift the instrument to A. Bisect point A & clamp both the screws. For
every 20m interval, the ranging rod is moved in view of telescope and fixes the wooden pegs on
ground. So that station AB & peg points are all in a same line. The wooden pegs are driven on to
the ground.
The steel band or tape is taken and the tape is held fix on the center of one wooden peg and the
spring balance is attached on the other end of the band. The pull is applied on the second point.
The length is measured and noted.

2.To find levels of pegs top


Fly leveling is carried from known bench mark is located near to stations. Back sight is taken on
the temporary bench mark and intermediate sights on the wooden pegs are taken and noted.

3.To Measurement of angles


Theodolite is set on the station point A&B and all other trigonometric stations are bisected and

SSE, MUKKA, MANGALORE

Page 87

EXTENSIVE SURVEY REPORT-2012


BATCH-2
corresponding horizontal and vertical angles are taken and noted.

SSE, MUKKA, MANGALORE

Page 88

You might also like