SavingEnergyThroughLoadBalancingandScheduling
Themoredatayouhavetoanalyze,themore
likelyyouaretocomeupwithenergysavingideas
RandyBarnett,AmericanTrainco,Inc.,fortheFlukeCorp.|ElectricalConstructionand
Maintenance
SHARE

Tweet

Recommend

Jan1,2009

COMMENTS 0

You can find significant energy-saving opportunities through load balancing and load scheduling when
using power logging test tools. Whether conducting an energy audit or troubleshooting to find energy
losses, a typical power logging session should record several factors, including voltage, current, power
trends, transients, and event logs. Although analysis of each parameter is important in the overall

Youcanfindsignificantenergysavingopportunities
throughloadbalancingandloadschedulingwhenusing
powerloggingtesttools.Whetherconductinganenergy
auditortroubleshootingtofindenergylosses,atypical
powerloggingsessionshouldrecordseveralfactors,
includingvoltage,current,powertrends,transients,and
eventlogs.

OverdueInvoices
TipoftheWeek:DetermininganAppropriate
LevelofPPE
UsingTachometerstoTestYourMotors
TipoftheWeek:TheBasicsofChapter4in
NFPA70(NEC)
HowUsefulisYourTestEquipment?

Photo Galleries
HauntedPlaces:
ElectricalEdition

We'veunearthednine
spookytalesbasedon
(supposedly)trueevents
andinvolvingwhatelse?electricity.

Join the Discussion on EC&M Talk


HotTopics

Althoughanalysisofeachparameterisimportantintheoverallschemeofreducing
energycosts,thefocusofthisarticlewillbeonreducingyourenergybillbybalancing
loadsacrossa3phasedistributionsystemandschedulingtheoperationofcertainloads
toreduceenergydemand.Therefore,we'llconcentrateontakingvoltageandcurrent
unbalancereadingstodetermineloadbalancingissuesandonrecordingpowerand
relatedeventstoidentifyloadschedulingissues.
Loadbalancing

Comments

LightingContactors

NewTopics

10

lastreplybyEddyCurrentinLighting&Lighting
Controls

DemandFactorforElectricTanklessHotWater
Heaters

lastreplybyglene77isinGeneralElectricalTalk
Discussion

Systemdesignersandelectriciansusuallytrytobalanceloadsacrossa3phase
distributionsystemduringinstallation.LoadsarecalculatedinaccordancewithNECArt.

HighCurrentDSUBConnectorsNeeded

220basedontheirvoltamperes(VA)orkilovoltamperes(kVA),ratherthanwatts(W)
orkilowatts(kW).Thisprovidesanaccurateanalysisoftheamperevaluesthatwillflow
inthecircuit.Eventhoughnoninductiveloadratingsareexpressedinwattsorin
kilowatts,thesewattageratingscanbeconsideredtheequivalentofthesameratingin
voltamperesorkilovoltamperes.Understandinghowloadsarecalculatedandthe
associatedunitsofmeasurementallowsforproperpowerqualityinstrumentsetup,results
interpretation,andcorrectiveactiondecisions.
Electriciansinstallequipmentandusuallydividekilovoltamperesbetweenphasessuch
thateachphasewillcarryanequalamountofload.Thisconcept,however,holdstruein
theoryonly.Inthepracticalworld,the3phasesystemisrarelyperfectlybalanced.Load
unbalance(imbalance)manifestsasavoltageandcurrentunbalance.Therefore,you
mustmonitorandrecordbothvoltageandcurrenttodeterminetheextentoftheload
imbalanceinasystem.
Youcanuseoneoftwomethodstodetermineanunbalancesituation.Thefirst,which
manyrefertoastheIEEEorNEMAmethod,usesadigitalmultimeter(DMM)totake
spotvoltagereadings.Tousethismethod,youmeasurethethreephasetophasevoltage
readings(AB,AC,BC),sumtheirvalues,andthendividebythreetoobtaintheaverage
voltage.Anyphasevoltagereadingthatdeviatesbymorethan1%fromtheaveragevalue
warrantscorrectiveaction.

lastreplybyUSSHornetinElectricalTalkPics&
Videos

AdditionalServicetoSchool
lastreplybyHowardPinNationalElectricalCode
(NEC)

DeadEnd4wayw/ExtendedSwitchLeg

lastreplybyUSSHornetinGeneralElectrical
TalkDiscussion

EC&M White Papers


AddingReliabilityand
AvailabilitytoYour
Manufacturing
Process
Reliabilityandavailability
ofmediumvoltage
equipmentiscriticalinvirtuallyallapplicationsanyfailure
willgenerallydisablearelativelylargeportionoftheplant.
Withareducednumberofcomponentsandenhanced
More

VIEWMOREWHITEPAPERS

Whilethisprocessshouldbeoneofyourfirststepswhentroubleshootinganidentified
unbalanceproblem,itwillnotprovideforanaccurateanalysisovertimeasloadscycleon
andoff.Thisrequirestrendingorpowerlogging.

EC&MWebinars
SEP10,2015
SPONSORED

ONDEMAND:An
EffectiveElectrical
SafetyProgramthat
Delivers
JUL21,2015
SPONSORED
Inthisexampleofunbalance,theV<sub>neg</sub>
of9.2%indicatesexpectedoverheatingof3phase
motorsandtransformersandreductionsofmotor
torqueandspeed.TheV<sub>zero</sub>of8.2%
indicatesexcessivecurrentflowintheneutraldue
totheunbalance,withexpectedoverheatingof
conductorsandtransformers.

Somemakesofpowerqualityanalyzersandpowerloggersuseamathematicaltoolcalled
themethodofsymmetricalcomponentstoanalyzeunbalance.Thismethodnotonly
simplifiesthevoltageimbalanceconceptbyprovidingagraphicalrepresentationof
unbalanceinvectorformat,butitalsoprovidesaccurateanddetailedinformationtobe
usedforanalysis.Basically,theseinstrumentsspliteachphasevoltageandcurrentinto
threeseparatecomponents:thepositive,negative,andzerosequences.
Thepositivesequencecomponentrepresentsthenormalvoltageorcurrentinabalanced
3phasesystem.Thenegativesequencevoltageorcurrentiscreatedbyanunbalancein
thesystemandresultsinoverheatingininductiveloadssuchasmotorsandtransformers.
Thiscomponentisalsoresponsibleforreducingmotortorqueandcanaffectspeed.The
zerosequencecomponentrepresentstheunbalancedcurrentthatflowsintheneutralof
the3phase,4wiresystem.Thisresultsinenergylossesintheformofheatinconductors
andtransformers.
TheEN50160powerqualitystandard,VoltageDisturbances:VoltageCharacteristicsin
PublicDistributionSystems,(fromtheLeonardoPowerQualityInitiative)setsthe
maximumunbalanceat2%atthepointofcommoncoupling(PCC),whichistheratioof
thenegativesequencecomponent(Vneg)tothepositivesequencecomponent,orthezero
sequencecomponent(Vzero)tothepositivesequencecomponent.Neithervalueshould
exceed2%(Figureonpage18).Iftheselimitsareexceeded,youshouldisolateand
correctthesourceoftheproblem,orenergylossescouldbecomesubstantial.Aftera
powerloggingsession,downloadthedatatoaPCandanalyze.
Youmustalsoconsidertheoptionsavailablewhensettingarecorderinstrumenttolog
voltageunbalanceparameters,includingthefollowingvalues:

ONDEMAND:
MitigationMethodsfor
ArcFlashHazards
EnhancingPersonal
Safety
VIEWMOREWEBINARS

EC&M TV
NewCertification
Announcementfrom
NFPA
...

More

BROWSEALLVIDEOS

Frequency

EC&MLearningCenter

UnbalanceVneg%
Understandingthe2014NEC,
Volume1(Articles90to480)

UnbalanceAneg%

Thisresourcehasprovenitselfinthe

Voltage(positive,negative,andzerosequence)

fieldandintheexamroom.Thislatest
editionwillprovideyouwitharocksolid

Amperes(positive,negative,andzerosequence)

foundation...

Themoredataavailabletoanalyze,themorelikelyyouaretocomeupwithenergysaving
ideas.However,donotbeoverwhelmedwithdata.Youshouldselectonlythespecificset
ofdatayouwishtoanalyzeatonetime.Armedwithknowledgeofwhatsinglephase
equipmentwasoperatingatwhattimeandwithanuptodateonelinediagramofthe
distributionsystemyoucannowisolateloadsandequalizethemacrossallthreephases
tocorrecttheunbalanceproblem.

UnderstandingNECRequirements
forGroundingvsBonding

Loadscheduling

Don'tletthescaleofthecodechanges

Oneofthemostconfusingareasofthe
tradecontinuestobegroundingand
bonding,whichiswhythisbookneedsto
beinthehands...

ChangestoTheNEC2014
intimidateyou,thisbookwillgetyouup

Inadditiontoreducingenergycoststhroughloadbalancing,youcanalsocreate
immediateenergysavingsthroughloadscheduling,whichisthepartofenergyload
managementthatminimizesdemand.
Electricutilitieschargelargecommercialandindustrialcustomersapeakdemand
penaltyinadditiontothetotalusageofelectricityoverthebillingperiod.Maximum
demandisthemaximumamountofelectricityusedbyacustomeratanypointintime.
Theelectricutilitymustbecapableofsupplyingthisload,mustsizeitsdistribution
equipmentaccordingly,andwillthereforechargethecustomertobeabletomeetthis
need.
Thismaximumelectricalenergyusage,ordemand,isaveragedovera15min.period
(typical),anddeterminestheratescheduleatwhichacustomerwillbecharged.Peak
demandisusuallycausedbyaspikeinpowerconsumption,mostoftenwhenmultiple
loadscomeonsimultaneously.Theseadditionalpenaltiescanbehighandadd
significantlytothecostofelectricalenergy.Itonlymakessensetominimizetheamount
ofpeakpowerbeingused,ifatallpossible.Powerloggingprovidesthisopportunity.
Ifyouareattemptingtomoreeffectivelyscheduleloadoperation,conductpowerlogging
recordingsessionstomeasureenergyusageovertimeandidentifylargeloadsthat
operateconcurrently.Useonelinediagramstodeterminetheenergydemandofvarious
loadsandcomparethemtooperatingneeds.Donotlookforjustoneparticularloadas
theculprit.Quiteoften,youmustworkwithoperationspersonnelandadjustaprocessby
staggeringcyclingtimes,orcompletecertainprocessesduringoffpeakhourstoreduce
demand.Youmustalsoworktogetherwithoperationsmanagementtoreviewthe
electricalenergybillandcompareittocollectedpowerloggingdatatoaidinmakingthe
bestplantoperationsandenergycostsavingsdecisions.
Youshouldalwaysbeginmonitoringattheserviceentrancetodeterminetotalenergy
usage.Settheaveragingtimeinthepowerloggerto15min.ifthat'sthetimeusedbyyour
utility.(Consultwithyourutilitytodeterminetheactualaveragingtime,as30min.may
alsobeused.)Inaddition,monitorpowerforanentirebillingcycleof30days.Thiswill
providethemostcomprehensiveinformation.Considerrepeatingthisonaseasonalbasis,
aspowerconsumptionrequirementschange.
ImportthedatatoyourPCuponcompletionoftheloggingsessionandsearchforperiods
whereenergyusageexceedsdesiredlimits.Identifytheequipmentcreatingthepeak
demandchargesbyobservingexcessiveusesofactivepower(kW).Finally,adjustplant
operationsandprocessesasnecessary,tominimizedemandcharges.
Youcanplayalargeroleinreducingplantenergycostsbysettingupapowerquality
instrumenttorecordneededvoltageandpowervalues.Byusingsoftwaretoanalyzethe
recordeddata,youcanreapthebenefitsofsignificantenergysavingsthroughproper
loadbalancingandloadscheduling.
BarnettistrainingdirectorforAmericanTrainco,Engelwood,Colo.,andtechnical
authorforFlukeCorp.,Everett,Wash.Hecanbereachedat
RandyB@americantrainco.com.

SHARE

Tweet

Recommend

tospeedonthemostessential...

BROWSEALLTITLES

Signuptoreceiveourfreenewsletters
eTrain(BiWeekly)ViewSample
ProductNewsWire(Monthly)View
Sample
ElectricalZone(Weekly)ViewSample
MROInsider(BiWeekly)ViewSample
PQNewsBeat(BiWeekly)View
Sample
IlluminationInsider(BiWeekly)View
Sample
CodeWatch(BiWeekly)ViewSample
GBiz(Varies)ViewSample
ElectricalTesting(Monthly)View
Sample
EMAIL*
COUNTRY*

UnitedStates

Enteryouremailabovetoreceivemessagesabout
offeringsbyPenton,itsbrands,affiliatesand/orthird
partypartners,consistentwithPentonsPrivacyPolicy.

ConnectWithUs

TwitterFacebook
LinkedRSS

You might also like