You are on page 1of 44

TRANSMISSION CONSTRUCTION STANDARD

TCS-Q-113.03, Rev. 0

TABLE OF CONTENTS
1.0

SCOPE

2.0

GENERAL REQUIREMENTS

3.0

CONFLICTS AND DEVIATIONS

4.0

CODES AND STANDARDS


4.1
4.2
4.3
4.4
4.5
4.6
4.7

5.0

MATERIALS
5.1
5.2
5.3
5.4
5.5
5.6

6.0

Concrete
Steel Reinforcement And Positioning Devices
Form Materials
Joint Materials
Curing Materials
Miscellaneous Materials

DESIGN AND FUNCTIONAL REQUIREMENTS


6.1
6.2

7.0

COMPANY Standards
SASO Standards
AASHTO Standards
ACI Standards
ASTM Standards
U.S. Corps Of Engineers Standards
CRSI Standards

Reinforcement
Formworks

CONCRETE WORKS
7.1
7.2
7.3
7.4
7.5
7.6
7.7
7.8

Preparation
Acceptance Of Concrete on Arrival
Concrete Placement
Concreting Under Water
Concreting In Hot Weather
Concreting For Slab-On-Grade
Construction Joints
Concrete Placement Acceptance

TCSQ11303R0/SZA

Date of Approval: April 10, 2006

PAGE NO. 2 of 44

TRANSMISSION CONSTRUCTION STANDARD

8.0

POST CONCRETE WORKS


8.1
8.2
8.3
8.4

9.0

Finishing
Removal Of Forms And Shoring
Curing
Corrosion Protection and Durability

REPAIR OF DEFECTIVE CONCRETE


9.1
9.2
9.3
9.4
9.5
9.6
9.7

10.0

TCS-Q-113.03, Rev. 0

Surface Air Voids/Sand Streaking/ Peeling /Blistering


Honeycombs
Tie Holes
Pop-Outs/ Scaling
Discoloration and Stains
Cracks
Defect With Exposed Reinforcing Steel

QUALITY CONTROL
10.1
10.2
10.3

Pre-Concreting Quality Control


Post-Concreting Quality Control
Non-Compliance of Quality Control

11.0

SUBMITTALS

12.0

APPENDICES
Appendix I
Appendix II

TCSQ11303R0/SZA

Date of Approval: April 10, 2006

PAGE NO. 3 of 44

TRANSMISSION CONSTRUCTION STANDARD

1.0

TCS-Q-113.03, Rev. 0

SCOPE
This Transmission Construction Standard (TCS) intended to be used in the system of the
Saudi Electricity COMPANY (SEC), Saudi Arabia, covers the minimum mandatory
requirements for receiving, forming, placing, consolidating, finishing, jointing, curing and
all other related WORKS as required for Cast-In-Place Concrete.

2.0

3.0

GENERAL REQUIREMENTS
2.1

Concrete shall be constructed true to lines, dimensions and details shown on the
drawings.

2.2

The mix design, mixing, delivery and testing of normal weight, ready-mixed
concrete shall be governed by the requirements of COMPANY Material Standard
70-TMSS-03.

2.3

No material, regardless of its source, shall be incorporated in the WORK until


representative samples are taken and tested by a COMPANY approved independent
laboratory and found acceptable.

CONFLICTS AND DEVIATIONS


3.1

Any conflicts between this standard and other applicable Saudi Electricity Company
(SEC) Standards, industry standards, codes, and forms shall be resolved in writing
by the COMPANY Representative.

3.2

Any request to deviate from this standard shall be directed to the Manager of
Transmission Standards and Specifications.

TCSQ11303R0/SZA

Date of Approval: April 10, 2006

PAGE NO. 4 of 44

TRANSMISSION CONSTRUCTION STANDARD

4.0

TCS-Q-113.03, Rev. 0

CODES AND STANDARDS


The latest revisions/amendments of the following Codes, Standards and Specifications are
intended as guidance in providing an acceptable level of quality of materials and practice. In
case of conflict between these Standards and the text of this Standard, the latter shall govern.
4.1

4.2

COMPANY Transmission Standards


4.1.1 TCS-Q-113.02

Earthworks

4.1.2

Normal Weight
Concrete

4.4

Ready-Mixed

Portland

Cement

SASO Standards - Saudi Arabian Standards Organization Standards


4.2.1

4.3

70-TMSS-03

SASO/SSA 2

Steel Bars for the Reinforcement of Concrete

4.2.2 SASO/SSA 143

Portland Cement, Ordinary and Rapid Hardening

4.2.3

SASO/SSA 224

Steel Fabric for Reinforcement of Concrete

4.2.4

General Specifications for Building Construction in Kingdom of Saudi


Arabia-Latest Edition

AASHTO Standards -

American Association
Transportation Officials

of

State

4.3.1 AASHTO M182

Burlap Cloth made from Jute or Kenaf

Highway

And

ACI Standards - American Concrete Institute


4.4.1

ACI 117

Specifications
for
Tolerances
Construction and Materials

4.4.2

ACI 201.2R

Guide to Durable Concrete

4.4.3

ACI 212.3R

Chemical Admixtures for Concrete

4.4.4

ACI 214.3R

Simplified Version of the Recommended Practice for


Evaluation of Strength Test Results

4.4.5

ACI 224R

Control of Cracking in Concrete Structures

4.4.6

ACI 301M

Specifications for Structural Concrete for Buildings

TCSQ11303R0/SZA

Date of Approval: April 10, 2006

for

Concrete

PAGE NO. 5 of 44

TRANSMISSION CONSTRUCTION STANDARD

4.4.7

4.5

ACI 302.1R

TCS-Q-113.03, Rev. 0

Guide for Concrete Floor and Slab Construction

4.4.8 ACI 304R

Guide for Measuring, Mixing, Transporting and


Placing Concrete

4.4.9

Placing Concrete by Pumping Methods

ACI 304.2R

4.4.10 ACI 305R

Hot Weather Concreting

4.4.11 ACI 308R

Standard Practice for Curing Concrete

4.4.11 ACI 309R

Guide for Consolidation of concrete

4.4.12 ACI 318RM

Building Code Requirements for Structural Concrete


and Commentary

4.4.13 ACI 347R

Guide to Formwork for Concrete

4.4.14 ACI 350R

Code Requirements for Environmental Engineering


Concrete Structures

4.4.15 ACI 503R

Use of Epoxy Compounds with Concrete

4.4.16 ACI 504R

Guide to Joint Sealant for Concrete Structures

4.4.17 ACI SP-2

Manual of Concrete Inspection

ASTM Standards - American Society For Testing And Materials


4.5.1

ASTM A 82

Standard Specification for Steel Wire, Plain, for


Concrete Reinforcement

4.5.2

ASTM A 184

Standard Specification for Welded Deformed Steel Bar


Mats for Concrete Reinforcement

4.5.3 ASTM A 185

Specification for Steel Welded Wire Reinforcement,


Plain, for Concrete

4.5.4 ASTM A 496

Standard Specification for Steel wire, Deformed, for


Concrete Reinforcement

4.5.5 ASTM A 497

Specification for Steel Welded Wire Reinforcement,


Deformed, for Concrete

4.5.6 ASTM A 615

Standard Specification for Deformed and Plain Carbon


-Steel Bars for Concrete Reinforcement

TCSQ11303R0/SZA

Date of Approval: April 10, 2006

PAGE NO. 6 of 44

TRANSMISSION CONSTRUCTION STANDARD

TCS-Q-113.03, Rev. 0

4.5.7 ASTM A 767

Standard Specification for Zinc-Coated (Galvanized)


Steel Bars for Concrete Reinforcement

4.5.8

ASTM A 775M

Specification for Epoxy-Coated Reinforcing Steel Bars

4.5.9

ASTM A 884

Standard Specification for Epoxy-Coated Wire and


Welded Wire Reinforcement

4.5.10 ASTM C 31M

Standard Practice for Making and Curing Concrete


Test Specimens in the Field

4.5.11 ASTM C 39

Test Method for Compressive Strength of Cylindrical


Concrete Specimens

4.5.12 ASTM C 42M

Test Method for Obtaining and Testing Drilled Cores


and Sawed Beams of Concrete

4.5.13 ASTM C 94

Specification for Ready-Mixed Concrete

4.5.14 ASTM C 125

Standard Terminology Relating to Concrete And


Concrete Aggregates

4.5.15 ASTM C 143

Standard Method of Test for Slump of Hydraulic


Cement Concrete

4.5.16 ASTM C 171

Specification for Sheet Materials for Curing Concrete

4.5.17 ASTM C 309

Specification
for
Liquid
Membrane-Forming
Compounds for Curing Concrete

4.5.18 ASTM C 494

Specification for Chemical Admixtures for Concrete

4.5.19 ASTM C 803M

Test Method for Penetration Resistance of Hardened


Concrete

4.5.20 ASTM C 805

Test Method for Rebound Number of Hardened


Concrete

4.5.21 ASTM C 1077

Standard Practice for Laboratories Testing Concrete


and Concrete Aggregates for Use in Construction and
Criteria for Laboratory Evaluation

4.5.22 ASTM C 1107

Specification for Packaged Dry, Hydraulic-Cement


Grout (Non-Shrink)

TCSQ11303R0/SZA

Date of Approval: April 10, 2006

PAGE NO. 7 of 44

TRANSMISSION CONSTRUCTION STANDARD

4.6

4.7

TCS-Q-113.03, Rev. 0

4.5.23 ASTM D 1751

Preformed Expansion Joint Filler for Concrete Paving


and Structural Construction

4.5.24 ASTM C 1602

Standard Test Method for Mixing Water used in the


Production of Hydraulic Cement Concrete

4.5.25 ASTM C 1603

Standard Test Method for Measurement of Solids in


Water

4.5.26 ASTM D 1752

Preformed Sponge Rubber and Cork Expansion Joint


Filler for Concrete Paving and Structural Construction

4.5.27 ASTM D 3963

Standard Specification for Fabrication and jobsite


Handling of Epoxy-Coated Steel Reinforcing Bars

4.5.28 ASTM E 96M

Test Methods for Water Vapor Transmission of


Materials

U.S. Corps Of Engineers Standards


4.6.1

CRD C513

Rubber Waterstops

4.6.2

CRD C572

Polyvinyl Chloride (PVC) Waterstops

4.6.3

CRD C583

Expansive Grout

4.6.4

CRD C621

Non-Shrink Grout

CRSI Standards - Concrete Reinforcing Steel Institute


4.7.1

Manual of Standard Practice for Reinforced Concrete Construction

4.7.2

Manual of Concrete Reinforcing Steel Institute

TCSQ11303R0/SZA

Date of Approval: April 10, 2006

PAGE NO. 8 of 44

TRANSMISSION CONSTRUCTION STANDARD

5.0

TCS-Q-113.03, Rev. 0

MATERIALS
5.1

Concrete
5.1.1

Concrete shall be ready-mixed, truck delivered, supplied from a batching


plant by a supplier acceptable to The COMPANY. Concrete shall fully
comply with all the requirements of COMPANY Standard 70-TMSS-03.

5.1.2

Field-mixed concrete may be used where it is impractical to procure readymixed concrete due to remoteness of the concrete pour location, or, for any
other reason, making it difficult to sustain the pre-pour concrete temperature
and plasticity within the required limits. Approval of a trial mix design is
required from the COMPANY for this purpose, if mix design differs from the
one originally approved.
After all materials are charged in the drum, the batch mixer shall be rotated at
the manufacturer's recommended speed, for at least 1-1/2 minutes for
quantities less than or equal to 1 cubic meter and increased by 20 seconds for
every additional cubic meter or fraction thereof. Batching and mixing shall
be done as per Section 7.2 of ACI 301M.

5.1.3

5.2

Grouts mentioned below shall be chloride free, high performance, free


flowing, non-catalyzed, shrinkage compensated and hydrogen free in
addition to the following requirements:
a.

Pre-Mixed, Non-Shrink, Non-Metallic Cementitious


conforming to CRD C621 or ASTM C 1107

b.

Expansive Grouts, conforming to CRD C583

Grouts,

Steel Reinforcement and Positioning Devices


5.2.1

Reinforcing bars shall be deformed or plain billet steel bars in conformance


with SASO/SSA 2 and ASTM 615.

5.2.2 Welded wire fabrics shall be electrically welded cold-drawn wire with
minimum yield strength of 240 MPa in conformance with the following:
SASO/SSA 224
ASTM A 185 Plain Wire
ASTM A 497 Deformed wire

TCSQ11303R0/SZA

Date of Approval: April 10, 2006

PAGE NO. 9 of 44

TRANSMISSION CONSTRUCTION STANDARD

TCS-Q-113.03, Rev. 0

5.2.3 Devices such as spacers, chairs, bolsters, ties, etc., used for spacing,
supporting and fastening the steel reinforcement shall conform to the
requirements of Concrete Reinforcing Steel Institute (CRSI) Manual.
5.2.4 Epoxy-Coated reinforcing steel bars shall satisfy the requirements of ASTM
A 775M.
5.3

Form Materials
5.3.1

Form materials shall conform to ACI 347R and shall be of wood, steel,
driven steel sheet piling or other approved material. The type, size, shape,
quality and strength of all materials of which the forms are to be made shall
be consistent with the specified finishes and safety. Plywood for formwork
material shall meet the requirements of APA grade-trademarked, USPS PS 1,
B-B plywood, exterior type, Class 1, sealed edges, mill oiled and not less
than 20 mm thick.

5.3.2

Embedded form ties shall be of a non-metallic material or galvanized steel.

5.3.3

Form Release Agent


Form Release Agent shall be non-staining, non-reactive, rust preventive,
guaranteed to be compatible with subsequent surface applications to
concrete.

5.4

For Wood Forms:

Straight, refined, pale, paraffin mineral oil, or


approved equivalent

For Steel Forms:

Refined mineral oil suitably compounded, or approved


equivalent

Joint Materials
5.4.1

Joint Fillers and Joint Sealant


Joint filler material shall be extruded closed cell polyethylene foam rod or
polyurethane foam rod conforming to the requirements of ASTM D 1751 or
ASTM D 1752.
Joint sealant shall conform to the requirements of ASTM D 2628.

TCSQ11303R0/SZA

Date of Approval: April 10, 2006

PAGE NO. 10 of 44

TRANSMISSION CONSTRUCTION STANDARD

5.4.2

TCS-Q-113.03, Rev. 0

Waterstops
Size and type shall be as shown on the design drawings and shall satisfy the
following material requirements:
Rubber made, Conforming to CRD C513
PVC made, Conforming to CRD C572

5.5

Curing Materials
5.5.1

Different curing materials and their requirements are as given in the Tables I
and II below:
Table I

Item

Standard

Impervious Sheeting

ASTM C 171

Burlap

AASHTO M 182

Liquid MembraneForming Compound

ASTM C 309,
Type 2

5.5.2

TCSQ11303R0/SZA

Requirements

Remarks

Minimum weight
0.29 kg/m2.

Fabric woven of
jute or kenaf

Potable water for curing shall be clean and free from injurious amounts of
oil, acids, alkalies, salts, organic materials or other substances that may be
deleterious to concrete or steel reinforcement and shall meet the requirements
listed in the Table below:

Date of Approval: April 10, 2006

PAGE NO. 11 of 44

TRANSMISSION CONSTRUCTION STANDARD

TCS-Q-113.03, Rev. 0

Table II

Form of Contamination

Maximum
Concentration
(ppm)
(%)

Total Dissolved Solids

2000

0.2

Sulfates (SO4)

500

0.05

Alkali carbonates and Bicarbonates

500

0.05

Chlorides

300

0.03

Suspended Solids

500

0.05

pH Value

6.5 - 8.5

Note: Submit analysis results if approved source is changed.

5.6

Miscellaneous Materials
5.6.1

Vapor Barriers
Polyethylene sheeting shall conform with ASTM E 154 and shall be a
minimum of two (2) layers of 150 microns thick each.

5.6.2

Chamfer Strips
Chamfer Strips shall be of Wood, PVC or neoprene and shall be approved by
the COMPANY Representative.

5.6.3

Dovetail Anchor Slots, Anchoring Inserts, Fabricated Embedments


These items to be used at site subject to approval by the COMPANY
Representative.

TCSQ11303R0/SZA

Date of Approval: April 10, 2006

PAGE NO. 12 of 44

TRANSMISSION CONSTRUCTION STANDARD

6.0

TCS-Q-113.03, Rev. 0

DESIGN AND FUNCTIONAL REQUIREMENTS


6.1

Reinforcement
6.1.1

All reinforcement at the time of placing shall be free of loose mill scale or
rust, dirt, mud, oil or any coating that would adversely affect bonding of the
reinforcement to concrete.

6.1.2

All reinforcing bars shall be cut and fabricated in accordance with the
dimensions shown on the approved construction drawings. Hooks and bends
shall be in accordance with ACI 318RM.

6.1.3 All reinforcing bars shall be bent cold. Tolerance for longitudinal location of
bends and ends of reinforcement shall be 50 mm, except at discontinuous
ends of members where tolerance shall be l2 mm. Fabrication tolerances
shall conform to ACI 117. Once steel has been bent, it shall not be re-bent.
6.1.4

Reinforcing bars shall be placed to the following tolerances:


Clear Distance to Formed Surfaces: 6 mm
Minimum Spacing Between Bars: -6 mm
Top Bars in Slab and Beams:
Members 200 mm deep or Less 6 mm
Members more than 200 mm, but not over 600 mm deep: l2 mm
Members more than 600 mm deep : 25 mm
Bars may be moved as necessary to avoid interference with adjoining bars,
conduits or embedded items. The COMPANY Representative's approval is
required for movements by more than 1 bar diameter or which exceed the
tolerance.

6.1.5

Steel reinforcement shall be checked against drawings for bending details. It


shall be ensured that all steel reinforcement are accurately in place and firmly
secured against possible displacements.

6.1.6

Reinforcing steel splices shall be made only as required and permitted on


locations shown on the approved construction drawings.

TCSQ11303R0/SZA

Date of Approval: April 10, 2006

PAGE NO. 13 of 44

TRANSMISSION CONSTRUCTION STANDARD

6.1.7

TCS-Q-113.03, Rev. 0

Where steel reinforcement is supported by means of concrete bricks or


blocks, these shall be made of the same grade of concrete to be used for the
structure. PVC or HDPE spacers and chairs can be used after approval by the
COMPANY Representative.

6.1.8 Unless otherwise specified, reinforcement shall be held in position by means


of approved spacers so that a minimum clear covers of concrete, as given
below in Table III are maintained:
Table III

Concrete members in
contact with soil and
water incl. slabs-ongrade
Columns and walls
exposed to atmosphere
up to 3 m height from
grade level
Columns and walls
above 3 m height from
grade level and beams
Slabs and joists exposed
to atmosphere

Minimum Cover in mm

Exposure Condition

Very
Severe and
Severe

Moderate

Mild

75

75

75

75

50

50

50

50

40

40

40 for >35 mm bars 40 for >35 mm bars


30 for <35 mm bars 20 for <35 mm bars

Ensurance of the required minimum clear cover shall not result in the
reduction at site, of the design effective depth of the member.
6.1.9

TCSQ11303R0/SZA

All bolts, sleeves, anchors, dowels, fastenings or other items to be embedded


in the concrete shall be accurately positioned and firmly secured against
possible displacement. When concrete is placed at locations where anchor
bolts, stub angles or other items requiring high accuracy are present, wooden
or steel templates shall be carefully and accurately fabricated and set. Anchor
bolts shall be plumb and within 2 mm of the position shown on the approved
construction drawings.

Date of Approval: April 10, 2006

PAGE NO. 14 of 44

TRANSMISSION CONSTRUCTION STANDARD

TCS-Q-113.03, Rev. 0

6.1.10 Metallic sleeves shall not be allowed and anchor bolts shall not be in contact
with reinforcing steel.
6.1.11 Welding for reinforcing bars shall not be permitted unless the mill test
reports were furnished indicating that the steel has been modified for
weldability. Welding shall be done as per requirements of AWS D1.4 (TESW-1).
6.2

Formworks
Forms shall be used, wherever necessary, to confine concrete and shape it to the
dimensions required in the design drawings. The forms shall be sufficiently tight to
prevent leakage of cement paste/mortar from the concrete. Formwork shall be
constructed so that the concrete surfaces conform to the tolerance limit listed in ACI
117.
6.2.1

Formwork shall be designed, erected, supported, braced and maintained so


that it will safely support all anticipated loads (vertical & lateral) that might
be applied to the formwork until such loads can be supported by the concrete
structure.

6.2.2

Forms shall be properly braced or tied together with standard accessories to


maintain the position and shape during placing and curing of concrete.

6.2.3

Maximum deflection of facing form materials, which reflect in concrete


surfaces exposed to view shall not exceed 1/240 of the span between
structural supports.

6.2.4

Eccentric loads on any part of the formwork shall be avoided unless these
members have been designed for such loadings.

6.2.5

Where necessary, to maintain the tolerances indicated, the formwork shall be


cambered to compensate for anticipated deflections due to the weight and
pressure of the fresh concrete, and also due to any construction loads which
may exceed the design live load.

6.2.6

The surface of the forms shall provide the correct finish, as specified in
Section 8.1, Finishing.

6.2.7

Forms for wall openings shall be constructed so as to facilitate loosening and


removal. Form material shall be good so as not to be disfigured by moisture
or heat.

TCSQ11303R0/SZA

Date of Approval: April 10, 2006

PAGE NO. 15 of 44

TRANSMISSION CONSTRUCTION STANDARD

6.2.8

TCS-Q-113.03, Rev. 0

Form Ties
Embedded ties for holding forms shall remain and shall be terminated within
the concrete at a distance of not less than the specified concrete cover. Snap
ties or through-bolts shall not be used. COMPANY approval is required for
form ties of other types.

6.2.9

Forms for Sloped Surfaces


Forms for sloped surfaces shall be built so that the sheathing can be placed
board-by-board immediately ahead of concrete placement, so as to enable
ready access for placement, vibration, inspection and repair of the concrete.
The sheathing shall also be built so that the boards can be removed one by
one from the bottom up, as soon as the concrete has attained sufficient
stiffness to prevent sagging. Surfaces of construction joints and finished
surfaces with slopes steeper than 4 (horizontal) to 1 (vertical) shall be formed
as required herein.

6.2.10 Forms For Curved Surfaces


The forms shall be constructed so that the curvature is continuous between
sections. Where necessary to meet requirements for curvature, the form
lumber shall be built up of laminated splines cut to make tight, smooth form
surfaces.
After the forms have been constructed, all surface imperfections shall be
corrected, and all surface irregularities at matching faces of form material
shall be dressed to the specified curvature.
6.2.11 In areas where removal of the formworks is not possible, or the working
space is very small, permanent formworks of concrete blocks filled with
grout/mortar mix with strength not less than that of the concrete blocks can
be used.

TCSQ11303R0/SZA

Date of Approval: April 10, 2006

PAGE NO. 16 of 44

TRANSMISSION CONSTRUCTION STANDARD

7.0

TCS-Q-113.03, Rev. 0

CONCRETE WORKS
7.1

Preparation
Following are the preparatory works to be done prior to Concrete placement:
7.1.1

Concrete shall not be placed until all formwork, embedded parts, steel
reinforcement, foundation surfaces and joints involved in the placing have
been inspected and approved by the COMPANY Representative.

7.1.2

Surfaces of forms and embedded items shall be cleaned of all encrustations


of mortar, grout or other foreign materials. Forms shall be coated with an
approved form release agent, which is compatible with a subsequent coating
system (if any) on the concrete surface. Lubricating (machine) oil shall not be
used.

7.1.3

All necessary checks, as required in the concrete pour and placement card,
(Appendix I), shall be made and approved by the COMPANY Representative
before concrete placement commences.

7.1.4 Provision at site of the required number and rating of vibrators needed for a
specific concrete pour including a standby power source shall be ensured.

7.2

7.1.5

All precautions related to concrete placement in hot weather (refer to Section


7.5) shall also be ensured.

7.1.6

All concrete laitance (on reinforcing bars) and other unsound material shall
be removed before placing of new concrete against hardened concrete.

Acceptance of Concrete on Arrival


7.2.1

Upon arrival of concrete at the place of deposition, the delivery ticket shall
be checked to ensure that all information required as per 70-TMSS-03 is
available and duly complied with.

7.2.2

The concrete shall reach the jobsite such that it can be compacted in its final
position within the time duration mentioned in 70-TMSS-03 from the time of
introduction of cement into the aggregates. In case of dry mix, the time is
considered from the instant of adding the water from the approved source.

7.2.3

Re-tempering or addition of water in excess of the design water/cementitious


material ratio, to compensate for slump loss resulting from delays in delivery
or placement, is strictly prohibited.

TCSQ11303R0/SZA

Date of Approval: April 10, 2006

PAGE NO. 17 of 44

TRANSMISSION CONSTRUCTION STANDARD

7.3

TCS-Q-113.03, Rev. 0

7.2.4

Addition of super plasticizers is permitted only at site. Where the slump is


deemed inappropriate for acceptable workability, a high range water reducing
admixture (super plasticizer), conforming to ASTM C494, may be added
immediately prior to the placement of concrete and in accordance with the
manufacturer's recommendations (especially with respect to dosage and
mixing time). This addition shall be recorded in the concrete placement card
(Appendix I).

7.2.5

The temperature of concrete while leaving the mixing plant should be such
that at the time of final placement, the maximum temperature of concrete
does not exceed the limits mentioned in 70-TMSS-03.

7.2.6

The testing requirements of 70-TMSS-03 shall be fully met for the evaluation
and acceptance of concrete.

Concrete Placement
7.3.1

Concrete shall be placed in accordance with ACI 301M and ACI 304, unless
otherwise stated.

7.3.2

Placing equipment shall be capable of providing a continuous supply of


concrete at site of final deposit without separation of ingredients and without
interruptions, sufficient to permit loss of plasticity between successive
increments.

7.3.3

Concrete shall not be dropped through congested reinforcing steel which may
cause segregation of the coarse aggregates. Restrict the free fall of fresh
concrete within 1.0 meters. Employ spouts or flexible drop chutes to avoid
nesting of coarse aggregates.

7.3.4

Concrete shall be placed and consolidated in continuous layers of uniform


depth not exceeding 450 mm in thickness, except in large mass pours where
it may be necessary to increase the layer thickness to 600 mm. Concrete shall
not be allowed to flow laterally a distance greater than 1.0 m from the point
of deposit.

7.3.5

Following details shall also be observed at the time of placing concrete:

TCSQ11303R0/SZA

a.

Concrete shall not be placed where standing water is present. The


water shall be removed by pressurised air or sponging.

b.

Movement of concrete shall only be by shovel and not by raking.

c.

Re-tempering of concrete shall not be done after placement.


Date of Approval: April 10, 2006

PAGE NO. 18 of 44

TRANSMISSION CONSTRUCTION STANDARD

7.3.6

TCS-Q-113.03, Rev. 0

Where concrete is placed by pumping, the following requirements shall


apply:
a.

Pumping equipment shall be with adequate pumping capacity and


boom-length.

b.

The placement shall be controlled to avoid segregation of the


discharged concrete.

c.

Slump obtained at the point of final placement shall be as specified in


70-TMSS-03.

d.

Concrete shall not be conveyed through pipe made of aluminum or


aluminum alloy.

e.

Minimum Inside Diameter (I.D.) of hose shall be:


Table IV

Maximum Size of Aggregate

Minimum ID of Hose

40 mm

150 mm

20 mm

100 mm

7.3.7

Lean concrete mat 75 mm thick with minimum fc 17 MPa shall be laid under
structural foundations, unless stated otherwise in design drawings. A vapor
barrier, two (2) layers of polyethylene sheet with 150 microns thick each,
shall be laid on top of the lean concrete mat.

7.3.8

After concreting is started, it shall be carried on as a continuous operation


until the placing of a panel or section, as defined by its boundaries or a
predetermined joint is completed. Construction joints shall be placed
horizontally or vertically with keys and dowels. For construction joints, refer
Section 7.7.2.

TCSQ11303R0/SZA

Date of Approval: April 10, 2006

PAGE NO. 19 of 44

TRANSMISSION CONSTRUCTION STANDARD

TCS-Q-113.03, Rev. 0

7.3.9 Consolidation
a.

Concrete shall be thoroughly consolidated (compacted) and worked


around the reinforcement steel, around embedded items and into
corners of forms, eliminating all air or stone pockets which may cause
honeycombs, pitting or planes of weakness.

b.

Vibrators in adequate number and rating shall be employed as to


properly consolidate and ease the placement of concrete. Equipment
for consolidation shall be as per ACI 309R.
In normal circumstances, refer to Table V below for guidance.
Table V

TCSQ11303R0/SZA

Maximum Size of
Aggregate

Minimum Outer Diameter of


Vibrator Head

40 mm

75 mm

20 mm

50 mm

c.

Vibrators shall be employed with care so that the designed positions


of the reinforcing bars will not be altered.

d.

Internal vibrators shall have a minimum frequency of 8,000 vibrations


per minute and sufficient amplitude to consolidate the concrete
effectively.

e.

Vibrators shall not be used to move or spread concrete horizontally.

f.

Vibrators shall be inserted and withdrawn at points approximately


450 mm apart. At each insertion (minimum 100 mm deep), the
duration shall be sufficient to consolidate the concrete without
segregation, generally from 5 to 15 seconds.

g.

Vibrators shall be operated in a near vertical position, allowing the


vibrating head to penetrate the upper layer under its own weight, and
to enter and vibrate the concrete in the upper portion of the
underlying layer.

Date of Approval: April 10, 2006

PAGE NO. 20 of 44

TRANSMISSION CONSTRUCTION STANDARD

7.4

7.5

TCS-Q-113.03, Rev. 0

h.

Concrete shall be vibrated in two stages as per ACI 309. Care shall be
taken to avoid loss of bonding between steel and concrete during revibration. The initial stage of vibration shall be at the time of concrete
placement. The second stage of vibration shall be as late as the
formed concrete will respond to the vibrator, where the running
internal vibrator will sink due to its own weight into the concrete.
Timing of re-vibration is of particular importance in hot weather
concreting and especially in application on thin slabs.

i.

Standby vibrators shall be available during concrete placement.

Concreting Under Water


7.4.1

Concreting under water shall be done by the "Tremie" method. This method
consists of placing concrete through a vertical pipe, allowing the concrete to
flow from the bottom. This method shall be applicable for deeper work and
confined areas.

7.4.2

The dry pipe method requires a Tremie pipe that is watertight, including
gasketed and bolted flanges at the couplings. The pressure seal plate, which
is at the bottom of the Tremie pipe keeps the Tremie pipe watertight, while
concrete is extruded from it under pressure and such that the discharge end of
the Tremie bottom moves gradually (upwards or away) and is always under
900 mm (approximately) head of fresh concrete. The equipment and
placement procedure shall conform to ACI 304R.

Concreting in Hot Weather


Hot weather concrete practice shall be adopted when the ambient temperature
(maximum air temperature during daytime) is 32C or above with low relative
humidity and wind velocity that will seriously impair the quality and strength of
concrete. For hot weather definition see ACI 305.
7.5.1 In dry areas, concreting may be done, if permitted by COMPANY
Representative when temperature and humidity are confirmed to be
comfortable for work.
7.5.2

Placement of concrete in hot weather shall be in accordance with


recommended practice of ACI 305R, unless otherwise specified.

7.5.3 Concrete shall be scheduled for placement during the early (cooler) morning
hours or at night in hot weather and high relative humid conditions.

TCSQ11303R0/SZA

Date of Approval: April 10, 2006

PAGE NO. 21 of 44

TRANSMISSION CONSTRUCTION STANDARD

TCS-Q-113.03, Rev. 0

7.5.4

The temperature of concrete at the point of final placement shall at all times
be less than the limits specified in 70-TMSS-03.

7.5.5

A water-reducing and set-retarding admixture conforming to ASTM C494,


Type D, and possessing a reliable performance history shall be used.

7.5.6

Part of the mixing water shall be substituted by an equivalent amount of ice,


when necessary, to obtain the allowable placement temperature. The ice shall
be finely crushed to avoid slump loss and cold joints.

7.5.7

Temperature of concrete shall be measured 50 mm below the surface


immediately prior to placement in the forms.

7.5.8 Reinforcing steel and forms shall be protected from direct sun rays.
Whenever ice is used in concrete, reinforcing steel and forms shall be cooled
off with potable water, immediately before concrete placement, unless
arrangements are made for night time concreting.
7.5.9

Concrete shall not be placed under wind blown sand conditions. Concrete
placement shall be planned taking into consideration the humid conditions
and requirement mentioned in Section 7.5.8.

7.5.10 Provisions shall be made for erecting windbreaks and sunshades, fog
spraying of reinforcement, dampening subrgrade and forms, placing concrete
at the lowest practicable temperature, reducing time between placement of
concrete and start of curing, and minimizing evaporation particularly during
the first few hours subsequent to placing concrete shall be made in advance
of placement.
7.6

Concreting for Slabs-on-Grade


7.6.1

Slabs-on-grade shall be placed upon two (2) layers of 150 microns thick
each, polyethylene sheets as vapor barrier over a lean concrete mat of
thickness as specified in the approved construction drawings.

7.6.2

Placing shall follow the guidelines in ACI 302.1R and shall be in compliance
with the following requirements:

TCSQ11303R0/SZA

a.

Concrete shall be placed continuously so that each unit of operation


will be monolithic in construction.

b.

Concrete shall be placed in alternate checker board pattern,


terminating at contraction or expansion joints.

Date of Approval: April 10, 2006

PAGE NO. 22 of 44

TRANSMISSION CONSTRUCTION STANDARD

7.7

TCS-Q-113.03, Rev. 0

c.

Construction joints shall be located and as shown in the approved


construction drawings.

d.

Expansion and Contraction Joints shall be provided as shown on the


approved construction drawings.

e.

Concrete joints shall be filled with a joint sealant and filler as detailed
in the approved construction drawings.

Construction Joints
Construction joints are hardened concrete surfaces to which fresh concrete is poured
so as to make it monolithic, with the existing concrete being so rigid that the fresh
concrete cannot be made monolithic by vibration.
7.7.1

Cleaning at Joints
Construction joints shall be clean with exposed sound aggregates, rough in
profile and damp, before pouring adjoining fresh concrete. Cleaning shall
consist of removal of all laitance, loose or defective concrete, coatings, sand,
sealing compound and/or other foreign materials. If required by the
COMPANY Representative, the concrete surface at all the construction joints
shall be uniformly chipped approximately 6.0 mm in a manner that will
remove laitance, loosened aggregates or damaged concrete at the surface.
Joints shall be cleaned/washed thoroughly with air-water jets and the
hardened concrete surface shall be pre-soaked for the last eight (8) hours
immediately before fresh concrete is placed.
Surfaces of contraction joints and control joints shall be coated with an
approved bond breaker prior to the placement of adjoining fresh concrete.

7.7.2

Location of Joints
Construction joints, expansion joints and control joints shall be provided at
the locations and in accordance with details shown on approved construction
drawings. In absence of such details, the practices of ACI 224.3 shall be
adopted.
Where construction joints have to be provided for any unanticipated reason,
and hence have not been indicated on the design drawings, the joints shall be
in accordance with ACI 301M.

TCSQ11303R0/SZA

Date of Approval: April 10, 2006

PAGE NO. 23 of 44

TRANSMISSION CONSTRUCTION STANDARD

TCS-Q-113.03, Rev. 0

Beams, girders, haunches, drop panels and capitals shall be placed


monolithically as part of a slab system, unless otherwise shown in the design
drawings or specifications.
Construction Joints shall be so made and located as not to impair the strength
of the structure. Suitable provision shall be made for transfer of shear and
other forces through construction joints.
7.7.3

Providing Watertight joints


Watertight joints shall be provided at locations shown on the approved
construction drawings. Unless indicated otherwise, PVC type waterstop of a
practical width for the intended application shall be used. Installation shall be
as per manufacturer's recommendations.

7.8

Concrete Placement Acceptance


Concrete shall be protected from damage due to impact, overloading, marring and
cracking of surfaces due to rapid drying.
Inspection of post concrete-placement activities, listed below (but not limited to)
shall be part of the acceptance process, taking special precautions demanded by hot
weather conditions (Section 7.5).
-Finishing and Jointing
-Curing
-Formwork and Shore Removal
-Re-shoring and Re-shore Removal
-Concrete Testing, Evaluation and Acceptance, as outlined in 70-TMSS-03
All necessary checks and monitoring, as required in the "Post Concrete Placement
Acceptance Card," Appendix II, shall be made and then approved by the
COMPANY Representative before final acceptance.

TCSQ11303R0/SZA

Date of Approval: April 10, 2006

PAGE NO. 24 of 44

TRANSMISSION CONSTRUCTION STANDARD

8.0

TCS-Q-113.03, Rev. 0

POST CONCRETE WORKS


8.1

Finishing
8.1.1

All concrete floors and slabs shall be classified by their intended use, as per
ACI 302.1R. Tools and finishing procedures for each class shall also be in
accordance with ACI 302.1R.

8.1.2 Sidewalks and other outdoor areas subject to foot traffic shall receive a nonskid finish by drawing a fine, soft bristled broom over the trowelled surface.
Edges and joints shall be tooled.
8.1.3

Concrete surfaces shall be screeded and finished to the required tolerance


class as specified in ACI 117.
Surface with irregularities shall be tested by the use of a template consisting
of a straightedge or equivalent thereof for curved surfaces. The length of the
template shall be 1.5 meters for testing of formed surfaces and 3 meters for
testing of unformed surfaces.

8.1.4

Finishes to Unformed Concrete Surfaces


a.

TYPE U I:
This is a screeded finish for surfaces of roads, foundations, beds,
slabs and structural members to be covered by backfill, subsequent
stages of construction, bonded concrete, topping or cement mortar
beds to receive pavings and exposed surfaces or paving where
superior finish is not required. It is also the first stage of Type U2 and
U3 finishes. The finishing operation consists of levelling and
screeding the concrete to produce a unifom plane or ridged surface,
with the surplus concrete being struck off by a straight edge
immediately after compaction.

b.

TYPE U2:
This finish is a wood floated finish for surfaces of beds and slabs to
receive mastic pavings or block or tile pavings where a hard, smooth,
steel-trowelled surface is not required. Floating shall be done only
after the concrete has hardened sufficiently and may be done by hand
or machine. Care shall be taken to ensure that the concrete is worked
no more than is necessary to produce a uniform surface free of screed
marks.

TCSQ11303R0/SZA

Date of Approval: April 10, 2006

PAGE NO. 25 of 44

TRANSMISSION CONSTRUCTION STANDARD

c.

TCS-Q-113.03, Rev. 0

TYPE U3:
This finish is a hard, dense, smooth steel-trowelled finish for surfaces
of concrete pavings, tops of walls, copings or other members exposed
to weathering, surface beds and slabs to receive thin flexible sheet
and/or tile.

d.

TYPE U4:
This finish is a broom finish for surfaces, which are for foot traffic,
e.g., walks and steps where a special finish is not designated. A
broom finish is obtained by motion of a broom in a pattern acceptable
to the COMPANY. Workmanship is to be similar to that of adjacent
areas.

e.

TYPE U5:
This finish is a non-slip (dry shake) finish for surfaces where slipping
could be hazardous. Application shall be as per manufacturer's
recommendations.

f.

Type U6:
This is a hard, dense, smooth power floated finish for surfaces of
exposed rafts in basements and reinforced concrete floor slabs both
exposed and to receive epoxy or ordinary paints.

g.

Type U7
This is a hard, dense, smooth surfaces to receive epoxy screed floor
toppings like switchgear rooms.

TCSQ11303R0/SZA

Date of Approval: April 10, 2006

PAGE NO. 26 of 44

TRANSMISSION CONSTRUCTION STANDARD

8.1.5

TCS-Q-113.03, Rev. 0

Formed Finishes for Concrete


a.

TYPE FI:
This finish is for surfaces against which backfill or further concrete
will be placed. Formwork shall consist of sawn boards, sheet metal,
plywood or any other suitable material, which will prevent the loss of
cement paste/mortar when concrete is vibrated.

b.

TYPE F2:
This finish is for surfaces, which are permanently exposed to view,
but where the highest standard of finish is not required. Forms for
providing a Type F2 finish shall be faced with wrought or finished
boards with square edges arranged in a uniform pattern. Alternatively,
plywood or metal panels may be used if they are free from defects
likely to detract from the general appearance of the finished surface.
Joints between the boards and panels shall be horizontal or vertical
unless otherwise directed. This finish shall be such as to require no
general filling of surface pitting; however, fins, surface discolorations
or other minor defects shall be repaired by approved methods.

c.

TYPE F3:
This is for surfaces prominently exposed to view where good
appearance and alignment are of special architectural importance. To
achieve this finish, which shall be free of board marks, the formwork
shall be faced with plywood or an equivalent material in large sheets.
The sheets shall be arranged in an approved uniform pattern.
Wherever possible, joints between sheets shall be arranged to
coincide with architectural features, sills, window heads or changes in
direction of the surface. All joints between panels shall be vertical or
horizontal, unless otherwise directed. Suitable joints shall be provided
between sheets. The joints shall be arranged and fitted so that no
blemish or mark is imparted to the finished surfaces. Unfaced
wrought boarding or standard steel panels will not be permitted for
Type F3 finish. The use of internal metal ties shall not be allowed.

8.1.6

Quality of Finish
The quality of finish shall not be inferior to that specified in the drawings.
Plastering of defective concrete as a means of achieving the required finish
shall not be permitted.

TCSQ11303R0/SZA

Date of Approval: April 10, 2006

PAGE NO. 27 of 44

TRANSMISSION CONSTRUCTION STANDARD

8.1.7

8.2

TCS-Q-113.03, Rev. 0

Miscellaneous Requirements
a.

Surfaces on which mortar/grout is to be placed shall be chipped a


minimum of 3 mm deep and thoroughly cleaned.

b.

Spreading dry cement on a wet surface to absorb excess water shall


not be permitted.

c.

Slabs which will be covered with tiles shall be screeded.

Removal of Forms and Shoring


8.2.1

Precautions
The removal of formwork shall be in accordance to a planned procedure,
considering the temporary support of the whole structure, as well as that of
each individual member. This shall be worked out prior to construction and
shall be based on a structural analysis. Forms (except those used for slabs on
grade) shall be removed upon COMPANY Representative's approval after
the concrete has gained sufficient strength to support its weight and
superimposed loads. In addition, following items shall be taken into account
as a minimum;

8.2.2

a.

The structural system that exists at the various stages of construction


and the construction loadings corresponding to these stages

b.

The strength of the concrete at the various ages during construction

c.

The influence of deformations of the structure and shoring system on


the distribution of dead loads and construction loadings during the
various stages of construction

d.

The strength and spacing of shores used, as well as the method of


shoring, bracing, shore removal and re-shoring, including the
minimum time intervals between the various operations

De-Shuttering Period
Where the structure is adequately supported on shores, the side forms of
beams, girders, columns, walls and similar vertical forms may generally be
removed after the stated durations (refer Tables VI & VII) of "cumulative
curing time," provided the side forms support no loads other than the lateral
pressure of the plastic concrete. "Cumulative Curing Time" represents the
sum of time intervals, not necessarily consecutive, during which the
temperature of the air surrounding the concrete is above 10C.

TCSQ11303R0/SZA

Date of Approval: April 10, 2006

PAGE NO. 28 of 44

TRANSMISSION CONSTRUCTION STANDARD

TCS-Q-113.03, Rev. 0

Table VI

Period (Days)

Location / Item
Walls (Note a)

Columns (Note a)

Sides of Beams and Girders (Note a)


Pan Joist Forms: (Note b)
0.75 meter wide or less
Over 0.75 meter wide

1
3
4

Table VII
Period (Days)
Structural live load is
Less Than Structural
More Than Structural
Dead Load
Dead Load
14
7

Location / Item

Arch Centers
Joist, Beam or Girder Soffits (Note c)
Under 3 m clear span between supports
3 m to 6 m clear span between supports
Over 6 m clear span between supports

7 (Note d)
14 (Note d)
21 (Note d)

4
7
14

One-Way Floor Slabs (Note c)


Under 3 m clear span between supports
3 m to 6 m clear span between supports
Over 6 m clear span between supports

4 (Note d)
7 (Note d)
10 (Note d)

3
4
7

Two-Way Slab Systems

TCSQ11303R0/SZA

The removal shall be per ACI 347-14. Removal


times are contingent on reshores where required,
being placed as soon as practicable after
stripping operations are complete, but not later
than the end of the working day in which
stripping occurs.

Date of Approval: April 10, 2006

PAGE NO. 29 of 44

TRANSMISSION CONSTRUCTION STANDARD

TCS-Q-113.03, Rev. 0

Notes Related to Tables VI and VII:


a)

If the forms also support formwork for slab or beam soffits, the
removal times of the latter shall govern.

b)

Shall be of those which can be removed without disturbing forming


or shoring

c)

Distances between supports refer to structural supports and not to


temporary formwork or shores.

d)

Where forms may be removed without disturbing shores, use half of


the values shown, but not less than 3 days.

e)

The durations mentioned in Tables VI and VII do not apply to


concrete utilizing set retarding admixtures and blended cements. In
such cases, these durations shall be extended, and approved by the
COMPANY.

8.2.3

Forms shall be removed in such a manner so as not to impair safety and/or


serviceability of the structure and prevent damage to the concrete thereby.
Wooden wedges only shall be used between the concrete surface and the
form where force is necessary to separate the form from the concrete. Metal
wedges, bars or tools shall not be used for this purpose.

8.2.4

Forms not supporting dead mass may be loosened and removed as soon as
the concrete has hardened sufficiently to prevent damage from form removal.
All forms and falsework supporting concrete beams and slabs, or other
members subject to bending stress, shall not be removed or released until
job-cured test cylinders are tested to show a strength of not less than 80% of
the current mean 28-day strength. Methods of removal tending to induce
shocks, jolts or fractures in concrete will not be permitted.

8.2.5 Construction loads exceeding the combination of superimposed dead load


plus specific live load shall not be supported on any unshored portion of the
structure under construction, unless analysis indicates adequate strength to
support such additional loads.
8.2.6

TCSQ11303R0/SZA

Any required repairs or damaged finish treatment shall be performed as soon


as the forms have been removed, and shall then be followed immediately by
the specified curing.

Date of Approval: April 10, 2006

PAGE NO. 30 of 44

TRANSMISSION CONSTRUCTION STANDARD

8.3

TCS-Q-113.03, Rev. 0

Curing
All concrete shall be cured with specified potable water, Section 5.5.2, and in
accordance with recommendations of ACI 308 and ACI 305R, and as specified
herein, immediately after finishing flatwork or removal of forms. Concrete shall be
protected from premature drying, temperature extremes and mechanical injury for
the entire specified curing period. Moisture loss from surfaces placed against
wooden forms shall be minimized by keeping the forms continuously wet until they
can be safely removed. After removal of forms curing shall continue.
Note: No concrete shall be allowed for casting, unless the curing proposal is
approved.
8.3.1

Methods of curing:
One of the following methods shall be used to cure concrete:
a.

Pond Curing:
Pond curing shall comprise of at least 40 mm deep potable water
covering the entire surface of the concrete. The water shall be
replenished when less than 50 mm deep to assure that a 40 mm
minimum depth is maintained.
Additional protection/precautions (from direct sun rays) for the
ponded water shall be done to avoid temperature rise during hot
summer conditions.

b.

Wet Burlap Curing:


Wet burlap curing shall comprise of at least two (2) layers of
constantly damped burlap laid tight against the pre-soaked concrete
surface. The burlap shall be kept uniformly damp, so that lighter
patches or drier burlap are not evident, by a clock valve regulated soil
soaker hose supplied with water at adequate pressure.

TCSQ11303R0/SZA

Date of Approval: April 10, 2006

PAGE NO. 31 of 44

TRANSMISSION CONSTRUCTION STANDARD

c.

TCS-Q-113.03, Rev. 0

Membrane Curing:
Application of this type of curing shall be restricted to non-critical
situation/structures and in keeping with compatibility of the
membrane forming compound with a subsequent protective coating
on the cured concrete. Whenever used, membrane curing shall be
preceded by saturation of concrete with sprayed water. This water
shall be sealed against evaporation from the concrete surface, by
application of a white (reflective) curing membrane in strict
accordance with the manufacturer's recommendations.

8.3.3

Only water curing shall be used in the following cases:


a.

Silica fume/fly ash modified concrete

b.

Mass concrete

c.

Critical situations/structures

d.

Hot weather conditions, as defined in Section 7.5.

8.3.4

Any alternative methods of curing requires approval of the COMPANY


before use. The choice of methods employed shall be combined as required
to provide adequate thermal protection. The curing methods for hot weather
shall be part of the hot weather concreting submittal, where due emphasis
shall be laid upon an extended curing period and an increase of thermal
protection. Protection shall be provided to concrete from heavy rains, flowing
water and mechanical injury.

8.3.5

All concrete shall be continuously cured for at least seven (7) days, except as
specified below:
Un-reinforced Mass Concrete

14 days

Concrete Blended with Pozzolanic material:

TCSQ11303R0/SZA

November to April (Cold weather condition)

14 days

Remaining period (Hot weather condition)

21 days

Date of Approval: April 10, 2006

PAGE NO. 32 of 44

TRANSMISSION CONSTRUCTION STANDARD

8.3.6

TCS-Q-113.03, Rev. 0

A formalized curing record shall be maintained at the Site for inspection and
verification by the COMPANY Representative.
Minimum mandatory information to be provided in the curing record:

8.4

a.

Time duration between concrete placement and actual start of curing


process

b.

Type of curing

c.

Conformance of curing materials to specification

d.

Physical arrangements including frequency of replenishment, etc.

e.

Duration of curing process

f.

Satisfactory compliance statement

Corrosion Protection and Durability


To produce durable concrete of high quality in resisting corrosion and adverse
environmental conditions, the guidelines presented in ACI 201.2R shall be followed
in construction practices. Some of the practices are, but not limited to, the following:
8.4.1

All concrete foundations and slabs-on-grade shall be laid on two (2) layers of
150 microns thick each, polyethylene sheeting as vapor barrier over 75 mm
thick lean concrete as mentioned in Section 7.3.6.

8.4.2 All concrete surfaces below grade and in contact with soil shall be protected
by waterproofing coating/membrane material, unless specified otherwise in
the approved design drawings. The coating membrane shall extend 150 mm
above ground level, unless aesthetically unacceptable. COMPANY approval
is required for the waterproofing material.
Tanking system, with approved water proofing materials, shall be done for
shallow concrete foundations in Sabkhah soils. For deep foundations in
Sabkhah soils, steel casing should be used as an extra protection or any other
approved protection methods.

TCSQ11303R0/SZA

Date of Approval: April 10, 2006

PAGE NO. 33 of 44

TRANSMISSION CONSTRUCTION STANDARD

9.0

TCS-Q-113.03, Rev. 0

REPAIR OF DEFECTIVE CONCRETE


Special care shall be taken by adopting new/latest methods during the construction in order
to minimize future concrete repairs.
Concrete shall be repaired if defective or if in the opinion of the COMPANY Representative
does not meet the specified requirements. Repair of defects and imperfections, described
below, shall be started within 24 hours of form removal and shall be completed without
delay. For color matching, the use of a mixture of white and gray cements is permitted.
Listed below are various types of defects, mostly encountered in newly-constructed
concrete, and methods for their repair. All repair procedures shall be submitted to the
COMPANY for approval. All repaired areas shall be properly moist cured for a minimum of
seven (7) days and as recommended by the repair materials' manufacturer.
9.1

Surface Air Voids/Sand Streaking/Peeling/Blistering


Pre-packaged cementitious repair products shall be mixed and used as per
manufacturer's recommendations. Fins shall be neatly removed from exposed
surfaces.

9.2

Honeycombs
Concrete in honeycomb areas shall be chipped to a depth of 25 mm or more, as
needed to reach sound concrete, with edges perpendicular to the surface. Any loose
concrete shall be removed and the surface kept clean and free from contaminants. An
area, determined from a perimeter extending at least 150 mm beyond the chipped
region shall be pre-soaked for at least the last 8 hours immediately prior to repair.
A mortar mix with strength not less than that of the original concrete at 28 days age
shall be brushed into the cavity. Immediately after, a dry pack patching mortar shall
be applied, the mix composition being similar to that of the parent concrete. The
water content shall be the minimum amount required for handling and placing. The
mortar shall be compacted in layers into the cavity and screeded off to protrude
slightly from the surrounding surface and then left undisturbed for one or two hours
before finishing. During application, each layer shall be solidly compacted over its
entire surface by the use of a hard wood board and a hammer.
Alternatively, a pre-packaged, non-shrink grout with strength equal to or exceeding
the parent concrete strength shall be used.

TCSQ11303R0/SZA

Date of Approval: April 10, 2006

PAGE NO. 34 of 44

TRANSMISSION CONSTRUCTION STANDARD

9.3

TCS-Q-113.03, Rev. 0

Tie Holes
Holes from removed ties shall be repaired using the same grout/mortar mix as for
honeycombs. If the holes are limited in depth, then a dry pack consistency grout
shall be used. Concrete surfaces shall be pre-soaked for at least the last 8 hours, prior
to repair.

9.4

Pop-outs /Scaling
All the affected materials, which may have an area larger than that from first visual
appearance, shall be removed. The same repair procedure as for the honeycombs,
shall be used.

9.5

Discoloration and Stains


Concrete surfaces shall be clean of all dirt and stains caused during construction. The
discoloration and Stains shall be minimized by utilizing proper construction
practices. If discoloration or stains do occur, procedures and materials for repair and
modification shall be submitted to The COMPANY for approval.
The discoloration may be caused by the following conditions:
a.

Change in Mix

b.

Aggregate Transparency

c.

Hydration Discoloration

d.

Segregation Discoloration

e.

Drying Discoloration

f.

Cold Joints Discoloration

g.

Improper Concreting and Finishing Practices

TCSQ11303R0/SZA

Date of Approval: April 10, 2006

PAGE NO. 35 of 44

TRANSMISSION CONSTRUCTION STANDARD

9.6

TCS-Q-113.03, Rev. 0

Cracks
Any cracks detected shall be reported to the COMPANY Representative
immediately. Depending on the cause and type of cracking and the need for repairs,
the cracks shall be repaired using either rigid patching or elastomeric caulking based
upon approval by the COMPANY.
The method of repairs are any one of the following or a suitable combination of
more than one of:

9.7

a.

Sealing

b.

VGrooving

c.

Resin injection

Defects with Exposed Reinforcing Steel


Concrete replacement shall be used for large defects and when reinforcing steel bars
are exposed. Other materials may be proposed for approval by the COMPANY.
Surface preparation for the repair is as given below:
Concrete shall be removed to a depth of 25 mm to 50 mm (depending upon the
member thickness and maximum aggregate size) behind the exposed reinforcing bar.
Area to be repaired shall be cleaned, pre-soaked for the last eight (8) hours before
placement of concrete or repair mortar, and repair as for honeycombs shall be made.
When the repaired region is thicker than 75 mm, 10 mm maximum aggregate size
shall be mixed with the repair mortar. Strength of the repair material shall not be less
than the original concrete strength at 28 days.
Immediately before placement, the concrete repair mix shall be re-mixed if desired,
to reduce the subsequent shrinkage.

TCSQ11303R0/SZA

Date of Approval: April 10, 2006

PAGE NO. 36 of 44

TRANSMISSION CONSTRUCTION STANDARD

10.0

TCS-Q-113.03, Rev. 0

QUALITY CONTROL
Quality Control Program shall be implemented in all respects after approval by the
COMPANY in practice at every stage of work. Quality Control and Quality Assurance shall
be done, as required in 70-TMSS-03, including the following functions:
10.1

Pre-Concreting Quality Control


10.1.1 Inspection and approval of the batching and mixing, facilities, and metering
(dispensing) calibration records
10.1.2 Inspection, testing and approval of concrete materials
10.1.3 Inspection and approval of excavation, formwork, reinforcing steel, shoring,
falsework, bracing, supports, embedded items, joints, waterstops, etc.
10.1.4 Inspection and approval of placement, consolidation and finishing operations
10.1.5 Checking the items listed in the concrete placement card (Appendix I)

10.2

Post-Concreting Quality Control


10.2.1 Inspection and approval of form removal, including reshoring operations
10.2.2 Inspection and approval of curing facilities
10.2.3. Inspection and approval of testing facilities

10.3

Non-Compliance of Quality Control


Following actions shall be taken in case of work not being conducted per the
requirements of COMPANY Standards:
10.3.1 Postponing concreting operations until outstanding requirements are fulfilled
10.3.2 Rejection of materials or workmanship, which do not conform to the
specifications
10.3.3 Stop any WORK, which is not being done in accordance with this Standard
and report immediately to the COMPANY, providing records, upon
discovery of any non-compliance

TCSQ11303R0/SZA

Date of Approval: April 10, 2006

PAGE NO. 37 of 44

TRANSMISSION CONSTRUCTION STANDARD

11.0

SUBMITTALS
11.1

12.0

TCS-Q-113.03, Rev. 0

Working drawings for the following shall be prepared:


a.

Details of Formwork System

b.

Methods of Form Construction and Erection

c.

Falsework and Computations

d.

Location of Form Joints, Form Ties and Construction Joints

e.

Sequence of Form Removal and Computations

11.2

A working schedule for the dates and rate of concrete placement for each item of
WORK shall be prepared. This shall be done periodically, as acceptable to The
COMPANY.

11.3

Document describing quality control and Quality program shall be submited to The
COMPANY for approval prior to start of any work at site.

11.4

Special methods for compliance with hot weather concreting, including delivery,
placement, curing and protection requirements shall be included in quality control
and Quality program. This shall be in addition to a curing proposal to be submitted
for approval.

APPENDICES
APPENDIX I: Please see next page.

TCSQ11303R0/SZA

Date of Approval: April 10, 2006

PAGE NO. 38 of 44

TRANSMISSION CONSTRUCTION STANDARD

TCS-Q-113.03, Rev. 0

CONCRETE POUR CARD AND PLACEMENT RECORD


SAUDI ELECTRICITY COMPANY (SEC)
CONTRACTOR:
CONTRACT
J.O. NO.
POUR CARD NO.
NO.
LOCATION OF POUR:
DESCRIPTION OF POUR:
TYPE AND SOURCE OF CONCRETE
QUANTITY/ VOLUME OF CONCRETE
CHECK LIST
INSPECTED & APPROVED
DATE
BY
Line and Grade
Formwork and Waterstop
Reinforcement
Embedded Metals
Embedded Pipes
Embedded Conduits & Ground Wires
Preparation of Embedded Joints
Waterproofing
Cleanliness and Access
Verification of Rate of Placement Cu. m/ hr.
Provision of Hot Weather Concreting
PLACEMENT RECORD AND DATE:
Weather
Rate of Placement
Type of Equipment Used
Type of Finish
Slump Specified/Actual
Is Water Added at Site? Yes/No If Yes,
(Only Dry Mix)
Amount of Water Added

Temperature
Curing Method
Qty Of Concrete Placed
Start Time
Finish Time
Trip Tickets Conform To
Approved Design Mix
Yes/No
Numbers Of Trip Tickets
Attached
Amount of Super Plasticizer
Were Cylinders Taken? If yes,
28 day test results
Yes/No
Amount of Super Plasticizer (SP) Added, [If Placement breakdown & other
Applicable, Only Permitted at Site]
remarks
Slump At Addition of SP
CONTRACTORS QC ENGINEERCOMPANY REPRESENTATIVE
Sign/Date/Time
Sign/Date/Time

TCSQ11303R0/SZA

Date of Approval: April 10, 2006

PAGE NO. 39 of 44

TRANSMISSION CONSTRUCTION STANDARD

TCS-Q-113.03, Rev. 0

APPENDIX II
POST CONCRETE PLACEMENT ACCEPTANCE CARD (Sample Checklist)

MEMBER /ITEM
LOCATION
DATE CAST
DATE STRIPPED
DATE INSPECTED
CURING TYPE
CURING START
CURING FINISHED
NO. OF DAYS CURED
FINAL ACCEPTANCE

TCSQ11303R0/SZA

DATE:

Date of Approval: April 10, 2006

PAGE NO. 40 of 44

TCSQ11303R0/SZA

2.

1.

Sl.
No

Date of Approval: April 10, 2006

Cast in areas (Repair required)

Exposed
aggregate
uncompacted concrete

Tie holes
and

Blow holes
Uneven surfaces not meeting the
specs. requirements

Damaged surface by concrete nails,


etc
Stained & colored surfaces

Formwork Pieces Cast Into Surfaces


(Wood, Plywood, Polystyrene)
Cleaning and removal of concrete,
grout and spillage.
Honeycombing/washouts

CONCRETE FINISH

Removal time

FORM REMOVAL

DESCRIPTION

LOCATION
(Attach sketch
if required

ACTION
REQUIRED
Contractors
QA/QC Rep.

SEC

ACCEPTANCE
REMARKS

TRANSMISSION CONSTRUCTION STANDARD


TCS-Q-113.03, Rev. 0

PAGE NO. 41 of 44

TCSQ11303R0/SZA

4.

CONCRETE FINISH (Contd)

2.

Date of Approval: April 10, 2006

Repairs required on construction


joints

Cleaning of joints and some repairs


required

Incomplete joints

JOINTS

Cleaning of door frames and some


repairs required

Cleaning and removal of formwork


and polystyrene props on blockouts

Cast-in frames & sleeves cleaning


& some repair required

Exposing & cleaning of cast-inplates & some repair required

CAST INSERTS

Finish as specified

Cleaning & removal of sprayed


curing compound

Fins & other projections

DESCRIPTION

Sl.
No

LOCATION
(Attach
sketch if
required

ACTION
REQUIRED
Contractors
QA/QC Rep.
SEC

ACCEPTANCE
REMARKS

TRANSMISSION CONSTRUCTION STANDARD


TCS-Q-113.03, Rev. 0

PAGE NO. 42 of 44

TCSQ11303R0/SZA

Date of Approval: April 10, 2006

AS-BUILT
SURVEY
FOR
LOCATIONS AND POSITIONING
TOLERANCES PER ACI 117

8.

* Where Applicable

CONCRETE
TESTING
AND
EVALUATION (per 70-TMSS-03)

Repair required for crack width >


0.02 mm

Crack monitoring report

Visible Cracks

CRACK INVESTIGATION*

Within tolerances

7.

6.

COVER SURVEY* (If Suspected)

5.

Insufficient Reinforcement Cover

DESCRIPTION

Sl.
No

LOCATION
(Attach sketch
if required

ACTION
REQUIRED
Contractors
QA/QC Rep.
SEC

ACCEPTANCE
REMARKS

TRANSMISSION CONSTRUCTION STANDARD


TCS-Q-113.03, Rev. 0

PAGE NO. 43 of 44

TRANSMISSION CONSTRUCTION STANDARD

TCS-Q-113.03, Rev. 0

ACCEPTED AS PRESENTED

REPAIRS REQUIRED AS INDICATED ABOVE

REPAIRS INSPECTED AND FOUND


SATISFACTORY, JOB ACCEPTED

RE-SCHEDULE INSPECTION

Name & Signature

Contractor's Q.C. Representative

TCSQ11303R0/SZA

COMPANY Representative

Date of Approval: April 10, 2006

PAGE NO. 44 of 44

You might also like