1. PROJECT
The Project is based in a production of 5.850 tons of net chicken per year. 20% of that will be sold
butchered and the rest will be sold as a complete chicken.
The production starts with the Budget of fertile eggs and the location of incubators in te property.
We will Guild 27 farms with high technology Systems and 1440 net square meters with a capacity
between 50.000 and 55.000kg of alive chicken. With this we will have a production of 37.500kg of
meat (dead and empty) for farm and 112.500kg each week.
Slaughter house with a capacity of 2000 chickens/hour with the Halal Rite and installations to
butcher the 20% of the production
The refrigeration camera has a capacity for the production of two days.
There are not details of the commercialisation system.
CONCEPT
27 Chicken Farms
1 Cattle Feed Factory
1 Incubator
1 Slaughterhouse
TOTAL
TOTAL COST
5.674.986,09
500.981
364.100
3.442.000
9.982.067,09
www.gei-2a.com
gei-2a@gei-2a.com
2. INCUBATOR MATERIAL
UNIT
4
3
1
1
1
1
1
1
1
CONCEPT
67.000 incubator eggs.
Breeders 33.000 eggs.
Emergency generator.
GSM alarm and climatisation.
Pressure washing machine.
Cleaning machine
Building 48 x 12 and electric installation.
Assembly direction.
Transport
Price
126.800
97.000
30.000
9.000
1.800
1.500
70.000
21.000
7.000
www.gei-2a.com
gei-2a@gei-2a.com
1 Bucket elevator to receive 24Tn/h, 20 mts between drops, 5,5 Moto reducer with brake, 1
transmission with protection stair, visit platform in the high part and two in the middle as regulation,
distributor mount with rest floor, steel cable and tighteners for fixing (Pos.N1)
1 Distributor of 6 drops 160 with manual controller from down part, 5 girdle splices 160 and 42
mts 160 piping.
5 Central silos model 3800/5, capacity 64m3, total height 8.760mts aprox, mounted above 6 legs and
one metallic cone of 60, access stair to the ceiling with protection, ceiling register and respiration
nozzle. Made in galvanized cylindrical wave plates, and flat in cone and ceiling (pos. 2)
5 Augers 130 x 7 y 9 mts length, 3 y 4 Cv Motors with silos exit to the dosser scale with pulleys
protection, fallings (Pos. N 3)
1 Dosser scale of 1000 kgs with double bin mounted on 4 charge cells connected to a box that emits
one signal to the equipment with luminous numbers. This equipment is manual. (Pos. N 4)
1 Auger 160 x 6 metros, motor 4 Cv, exit scale to the bin wait mill.
1 Modular wait mill bin, capacity 1000 kgs, mounted on a decompressor bin. (Pos. N6)
1 Decompressor bin, 2,30 x 3 x 2,50 mts high with 65cone, stairs, protection mailing and inspection
door in cone.(Pos. N7)
1 Turbine installed in the decompressor bin to remove the air to one cyclone 1mts diameter and 2,5
mts high.(Pos. N8)
1 gravity mill 40 Cv, mounted on a decompressor bin with 4 vibrating cues, and one magnet in the
entry that picks the iron.(3)(Pos. N9)
1 Auger 160 x 6 meters, 4 Cv exit motor, decompressor bin to an horizontal mixing bin. (N10)
1 1000kg Horizontal mixer, motorreducer 10Cv, transmission 1, protection chains, and warehouse for
raw materials.
1 1000kg Horizontal mixer bin with two cones, manual zipper. (Pos.N11).
1 160 Auger, 4 mts long, 2 Cv motorreducers attached to the horizontal mixer with recipient bin,
protection grill and cover. (Pos.N12)
1 160 Auger, 11 mts long, motor 55 Cv with the exit in the down part f the horizontal mister to the
filling silos conveyance. (Pos. N 13)
1 Conveyance 220 x 750 meters, motorreducer 2 Cv with 3 drops and 2 gates to the zipper.(Pos. N 14)
1 Auger 200 x 8 meters, motor 75 Cv, with pull with handle and pneumatic wheels, reception bin,
protection grill and door.
(Pos. N 15)
1 Grease equipment 300 Kgs, with electric panel, mixer pump, volume pump, filters and pressure
valve. This machine is installed in an electric and mechanic platform.
3 Silos model 3040/6 central, capacity 44 m3, height between props. 8300 aprox. Mounted on 6 legs
and Metallica cone 60, access stair to the top with protection. Made of wiggly galvanized plates and
cone and top plain. (position 15)
www.gei-2a.com
gei-2a@gei-2a.com
(Pos. N 5)
ELECTRIC PANNEL
TOTAL OFFER ..290.961
GENERATOR...30.000
APROX. BUILDING AND ELECTICITY COST : ...90.000
ASSEMBLY DIRECTION.. 70.000
LOCAL MANPOWER.10.000
TRANSPORT10.000
www.gei-2a.com
gei-2a@gei-2a.com
4. BROILER FARM
BUILDING TYPE
VENTILATION TYPE
HEATING TYPE
ELECTRICITY
REFRIGERATION TYPE
LENGTH (METERS)
WIDTH (METERS)
SQ.M.
CUSTOMER
CONTACT
CONTACT DETAILS
REFERENCE.
DATE
ANNEX N1
Length to axis...120 m.
Width to axis. 12 m.
Useful area..1.440 m.
Roof slope...15%
Distance Interixs..4 m.
Post height......2,5 m. + Baseboard height...0,5 m.
www.gei-2a.com
gei-2a@gei-2a.com
3.- STRUCTURE:
4.- EAVES
Two-pitched roof with lacquered sheet, with lateral eaves at 0,90mts. The sheets
will be fixed on the beams with screws and washers 6,30 x 110 mm.
www.gei-2a.com
gei-2a@gei-2a.com
The width of the panels will be 1,20 mts male/female with PVC H profiles to
assemble them.
The isolation will be placed under the beams.
Thermal transmission is 0,40 kcal per m/2, hour and C.
From the inside the roof will be complete flat for a perfect cleaning and
disinfection.
7.- WINDOWS:
30 PVC Windows model V-60 on the opposite side of the small fans for
minimum ventilation.
96 Windows, model V-60 too, in one side of the building, opposite of the big fans,
for the tunnel entrance, in hot seasons.
All windows have protection to avoid birds entrance.
2 motoreducer to open and close the windows, that allow the tunnel air entrance,
like the windows in one side of the farm. This motorreducers are automatic with
the computer, depending on the ventilation and refrigeration needs.
www.gei-2a.com
gei-2a@gei-2a.com
ANNEX N 2
Total Pans.....351
GEI-2A guarantees the feeding system from the first day. With its design, like a V
AND 4/6 cm height, the pan doesnt move and it is more accessible due to its
height.
2.- DRINKING SYSTEM
2.1 DRINKERS (NIPPLES)
All the nipples are multidirectional (360) . The pressure water must be 2kg/cm
pressure, with regulator.
N. lines....8
Length..117 m.
Nipples/line.468
Total nipples..1.872
www.gei-2a.com
gei-2a@gei-2a.com
10
4.- HEATING:
Two propane gas generators, aprox 70Kw, that will be connected with the
computer receiving instructions.
Well study the possibility of use other fuel, depending on the situation.
The gas tanks or other fuel tanks are not included.
User friendly
Large 20 line x 40 character lighted graphic display
Extensive historial
Communications.
Up to 40 heavy duty relays.
Intelligent on/off switches
Modular construction
Cooling
Alarm relay
Heating.
- Control up to 6 windows.
- Light
- Up to 6 temperature probes
- Humidity probes.
- Water meter.
- Options:
Emergency system (independent battery power)
Light dimmer.
Bird scale.
Feed silo scale.
www.gei-2a.com
gei-2a@gei-2a.com
11
6.- COOLING:
.-. 10 Sets of cellulose with 30 mts long and 2 mts high, installed in the opposite
side of the fans, because in the hot seasons well refrigerate with tunnel system.
ECONOMIC OFFERS.
.- We have calculate 4 containers of 40 per building.
The price is quotated
.- All kind of taxes are not included.
.- The assembly is not included.
Delivery time: The materials of 1 building will be prepared 60 days after the
agreement signed.
Prices valid for 30 days.
Nota: If the owner considers that we should include in the offer other Concepts,
we can study them.
www.gei-2a.com
gei-2a@gei-2a.com
12
DCTO
CANTIDAD
ESTRUCTURA Y CORREAS
APROX. 70 M/3 HORMIGN
MOVIMIENTO DE TIERRAS Y ZANJAS
CERRAMIENTOS LATERALES
CUBIERTA
CUADRO ELCTRICO
ORDENADOR ULISES
ALIMENTACION Y BEBIDA
SILO 17M3
LINEA COMEDEROS 117M.
LINEA BEBEDEROS 117M
TRANSPORTADOR 75, 15METROS
MOTORES ELEVACION LINEAS
TUBERIA PE ALIMENTARIA (FONTANER)
MANIVELAS
BAJANTE COMPLETA POLLOS
SUSPENSION GANCHO ABIERTO
VENTILACION, CALEFACCIN Y REFRIGERACIN
VENTILADOR GC 43,000M3
VENTILADOR 25T-630
PERSIANA 630
COOLING HEK-710/5/200
BOMBA AGUA VIGILA 500
DEPOSITO 200LT.
GENERADOR DE GAS
VENTANAS
VENTANAS V-60
MOTORREDUCTOR 600KG
VARIOS
CLORADOR
KIT DE MEDICACION
GRUPO DE PRESION
TORNILLERIA EXTRA
INSTALACION ELECTRICA
MONTAJE 4 PERSONAS 9 SEM
TRANSPORTE INTERIOR
SUPERVISION OBRA
GENERADOR ELECTRICO EMERGENCIA
TRANSPORTE
P.UNIT
1
75
1
1
1
1
1
NETO
20,00 NETO
NETO
NETO
NETO
NETO
NETO
1
3
4
1
3
260
2
3
280
1.260,00 NETO
2.618,42 10%
1.979,05 10%
973,05 10%
357,97 10%
0,95 10%
32,97 10%
9,19 10%
0,18 10%
7
4
4
30
2
4
2
606,37
359,85
63,26
208,27
174,30
145,82
2.400,00
126
2
65,00
829,90
10%
TOTAL
28.500,00
1.500,00
3.000,00
19.800,00
29.000,00
7.610,00
4.664,00
28.500,00
1.500,00
3.000,00
19.800,00
29.000,00
7.610,00
4.664,00
1.260,00
2.356,58
1.781,15
875,75
322,17
0,86
29,67
8,27
0,16
1.260,00
7.069,73
7.124,58
875,75
966,52
222,30
59,35
24,81
45,36
17.648,40
10%
10%
10%
10%
10%
10%
10%
545,73
323,87
56,93
187,44
156,87
131,24
2.160,00
3.820,13
1.295,46
227,74
5.623,29
313,74
524,95
4.320,00
16.125,31
10%
10%
58,50
746,91
7.371,00
1.493,82
8.864,82
1
819,95 10%
737,96
1 1.811,70 10% 1.630,53
1 1.157,94 10% 1.042,15
1 3.735,00 10% 3.361,50
1 17.000,00 NETO 17.000,00
1 20.000,00 NETO 20.000,00
1 2.000,00 NETO
2.000,00
1 6.000,00 NETO
6.000,00
1 6.000,00 neto
6.000,00
1 13.200,00 NETO 13.200,00
737,96
1.630,53
1.042,15
3.361,50
17.000,00
20.000,00
2.000,00
6.000,00
6.000,00
13.200,00
70.972,13
TOTAL PRESUPUESTO
www.gei-2a.com
gei-2a@gei-2a.com
13
20,00
207.684,66
5. CHICKENS SLAUGHTERHOUSE
1. PROJECT PREVIOUS
This previous project is done at the request of __________in order to define the
technical and economical characateristics of the chicken slaughter project with a
capacity of 2.000 chicken/h modulable.
1
2
3
4
LOCATION
PROPERTY
FLOW CHART OF CHICKEN SLAUGHTER
DESCRIPTION OF MAINLY MACHINERY AND EQUIPMENT FOR SLAUGHTER
www.gei-2a.com
gei-2a@gei-2a.com
14
www.gei-2a.com
gei-2a@gei-2a.com
15
AUTOMATIC SCALDER
9.- Automatic scalder 2 lengths, each containing 3 sections of 2 meters long, with a total of
12 meters per body scalding (scalded total of 24 meters).
With agitation of water by pumps blowers.
Stainless steel radiators for heating hot water or steam (max. 2 ato.)
Rail and tube curves with stainless steel comb.
Two regulators automatic water inlet.
Two keys scalding water drainage
Shock valves for the formation of the bubble.
Four blowers pumps of 5.5 hp. each.
Two by-pass solenoid valve complete with 1 .
Two resistance thermometers PT-100 3-wire sensitivity A.
Two digital electronic temperature controls.
Built and covered with stainless steel side
doors.
Length .- 7000 M.M. Width .- 1800 M.M.
AUTOMATIC PLUCKED
10.- Plucked automatic turntables plates, made of stainless steel, consisting of:
Five banks of plucking two to two front and one at the bottom.
In each of the benches are mounted 20 aluminum bushings , with 2 bearings supported on a
stainless steel shaft dia. 35 mm., Aluminum pulleys for flat belts and carrier plates stainless steel
fingers with 8 fingers of rubber, with a total of 800 fingers plucking.
The plates rotate alternately clockwise and counterclockwise, so that all the plates spinning
in all directions over the body of the bird.
The movement is obtained with 8-phase electric motors 2 hp. 1000 r.p.m. each and flat
belts.
Each row of plates is adjustable in height and width and inclination, as well as horizontally
and vertically.
Length .- 4212 M.M. Width .- 1750 M.M.
www.gei-2a.com
gei-2a@gei-2a.com
16
EVISCERATED CONDUIT
13.- Eviscerated conduit 7 meters with 6 jobs, built in stainless steel.
TRASPORT OF GUTS
14.- Transport of guts by compressed air, including:
Lung receipt of guts, built in stainless steel, with all the elements for both electric and
pneumatic operation.
Stainless steel pipe of 54 x 50 mm. with plates, flanges, bends and stainless steel screws.
3 Pumps vacuum of 5.5 KV. with a flow of 300 m3 / hour each, oil cooled.
Waste dump tank, constructed of galvanized steel.
Filter before reaching the vacuum pump, constructed of galvanized steel.
50 mm pipe. stainless steel. to channel waste to the dump tank.
2 pistols sewer opener with pneumatic actuation and cleaning, Dia. blade 22 mm.
(Suspension balancer included).
2 pistols cleansing of lungs, operated by
vacuum. Electric and pneumatic table of
operation,
www.gei-2a.com
gei-2a@gei-2a.com
17
CHILLER
18.- 1 x Chiller spiral 1600 / 6 The stiring air chiller available for various types of birds is built
modularly according to the
principle of counter-flow for better heat exchange in the chiller.
Made of stainless steel with a width of 1600 mm and includes an inlet section for downloading
and output section. The variable speed motor ensures the optimum time. The air pump for
agitation portions of cold water or ice is included in the chiller. The effective length of the chiller is
6000 mm
-Length: 6830 mm
Width: 1.780 mm
Height: 1,950 mm (Standard)
Electric power: 1,1 Kw.
Pump Power: 3,0 Kw.
The water cooling systemis not included.
TABLE
21.- Stainless steel table. 2,000 x 800 mm. with 4 funnels to pocket the frozen chicken.
www.gei-2a.com
gei-2a@gei-2a.com
18
www.gei-2a.com
gei-2a@gei-2a.com
19
SILOS STRUCTURE
28.- Steel structure for supporting the different silos, built with steel from hot rolled.
CIVIL WORKS
OUTSIDE LANDS AND MOTIONS
Should be given absolute priority at the time of its design, not only the factors of production or
health, but also to interface with the area in which it is situated. Therefore, the complex can be
best integrated into the terrain, if possible following the contours and its peculiar topography,
greatly reducing important
landscape impact.
Base
This will take account of reports of surveyors and field reconnaissance which will be reported
later.
Cleaning
General cleaning of land plants which can affect on the access and buildings by all
appropriate means. A portion of loose earth shall be stacked to level the ground in open
areas after
completing the construction. The surplus will be deposited on the ground. The fill thickness
was considered of 30 cm.
www.gei-2a.com
gei-2a@gei-2a.com
20
Roads
Heavy roads
The centers and roads of trucks type are foreseen for the passage of heavy trucks of 15
tonnes / axis.
The structure of the roadway will be:
distortion in the form at the bottom due to the static pressure in the axis perpendicular to the
trucks.
A loading dock of live animals: scheduled a concrete slab with a width of
3 m to facilitate the evacuation and cleaning of the locks. The shape of this
stone slope given to allow wedging into the wastewater (metal grid).
www.gei-2a.com
gei-2a@gei-2a.com
21
Roads accesories
Reinforced concrete curb types T1, T2, P1, CS1, CS2.
Delineation of the locations of car parks.
Sanitation nerwork
Shall provide the following separate networks:
Rainwater Network: with reinforced concrete pipe or PVC spin, with records of access,
drainage grates registration with casting heavy or light series. The pits will also be
provided to collect rainwater.
-
Network of sewage or industrial with PVC pipe or reinforced concrete according to the
diameters spinning, records of visits and casting series hatches heavy or light.
Service water network: This network includes the waters from personal
Water from the fire network with connection socket near the buildings and a power connection on
the side of the administration and dressing rooms.
www.gei-2a.com
gei-2a@gei-2a.com
22
Closers
A fence height of 2 m in hot-galvanized wire mesh and attached with small metal pillars close the
property. The staff parking will be located outside the enclosure of the unit. Main gate Two sliding
doors will be installed at the main entrance level of the complex. They will
made of aluminum or galvanized steel with automatic control to define.
Foundations.
Foundations and retaining walls
Includes: additional clearings for foundations with corresponding banks.
www.gei-2a.com
gei-2a@gei-2a.com
23
Sanitation.
PVC pipes for sewage networks, storm and
services. The low floor traps in the form of pending:
Type stainless steel with grill or channel to limit the burden of pollution (in the workplace
Stainless steel type on the premises of staff (health, dressing rooms ...).
Records of visits to allow for regular maintenance.
Conduit - Wiring
Planned:
In hot dip galvanized steel for exterior pipes.
Coated steel pipes for low work diameter exceeding 300 mm.
www.gei-2a.com
gei-2a@gei-2a.com
24
The reinforced concrete foundation under the walls insulated with rounded molding at the
bottom and steep upper slope and sealing at high and silicone seal (dimensions 120 x 400
mm).
Bases high leakage protection on the ground and in the periphery and around the columns of
the structure.
Tightness in the soil of the plants (if needed in the redefinition of the final draft,
or in allied industries), self-latching type membrane, allowing entry into the site of
the wall-partitions. Elevations and will take all necessary protective devices.
Masonry.
Concrete block walls in solid of 0.20 m. for certain technical facilities for compliance with
safety standards.
Walls in hollow concrete block 0.15 to 0.20 m. for refrigeration room, walls of the
peripheral area of housing, storage rooms and packaging slaughter.
The corridors for small animals are made of concrete of 0.15 m. thick.
Hand trowelled cement fine, for all areas of masonry with rounded
corners of radius 3 cm. in the incoming angles.
No provision for fine finishing of cement troweled on the walls of brick and will be
www.gei-2a.com
gei-2a@gei-2a.com
25
Flooring.
Terrazzo floors of offices or stoneware. Pavement of local staff and dressing rooms, stoneware
slip. Dressing areas, killing and cutting issue, with epoxy or similar continuous
and non-slip treatment. Maximum strength is required for passage of carts.
The floors of the freezers are made with the help of a surface hardener, with
skidresistant qualities, waterproof and wear. .
The floors of stables receive input from a layer of cement-treated striatum and antiorina.
www.gei-2a.com
gei-2a@gei-2a.com
26
Receiving Pit
For information purposes, the thickness of the walls is about twenty centimeters. The civil
works also include reinforced concrete pipes, vials and local exploitation
Los trabajos de obra civil comprenden: Los movimientos de tierra y las obras en
METALLIC STRUCTURE
Are planned for the metal frame parts:
Armor All the roofs of buildings.
Armor soils support plant (if required).
wiring.
The slab reinforcement made in hot galvanized steel profiles with the help of
commercial use overload 500 Kg./m2 considered for the area of retail space and
movement.
Slabs or trays above hot-dip galvanized steel bearing type, the bottom will be
lacquered in the factory.
Main cover.
Cover sandwich spot on straps, exterior sheet consisting of trapezoidal shaped section,
lacquered than 0.6 mm thick fiberglass blanket placed under the outside deck plate and a
profiled inner plate section trapeze galvanized 0.6 mm thick.
www.gei-2a.com
gei-2a@gei-2a.com
27
Downpipes.
The rainwater downpipes are in PVC; for the areas at risk of
strokes a rounded type protection will be placed. In the workplace,
the downpipes are hold to the insulation panels.
False ceilings.
Shall be a prepainted / galvanized, the same type of enclosure walls and
accessories will all end, angles, coronations, flashings, etc..
Cover accesories.
For ventilation of the ship was placed on the ridge ventilators static, so that lower
temperatures are achieved between indoor and ceiling.
Also place a ventilation chimney, with special badges, which replace the normal plate
for the vent of the brewhouse.
The gutters to collect rainwater, will be double galvanized steel sheet and shall be
insulated with iron legs caught galvanized panels supported on special pieces. The
rainwater downpipes shall be of PVC of 160 mm
approximately, and they will caught in a ring structure.
www.gei-2a.com
gei-2a@gei-2a.com
28
Interior siding.
The closings of cameras and cutting will be performed at 8 and 10 cm. thickness
depending on case. In the upper part, the closures will be carefully attached to the underside
of the deck by the interposition of a single board, enabling differential movements and take a
few flashings of termination.
In areas of slaughter, the walls are masonry, 20 cm. thick, covered with tile joint
health with epoxy paint or plastic food, as appropriate.
Insulated panels of local negative temperature and vertical walls of the fast chillers.
Panels with 2-sided sheet, with the constitution of positive premises. Made thickness
of 20 cm. panels to the periphery. The boards of the walls must be specially designed and cared
for taking into account the effects of expansion and to obtain a seamless continuum of isolation
and anti-vapor barrier and be injected with polyurethane foam.
At the top, these walls will be covered by special devices of the type injected with the deck
panels. At the bottom, the continuity of the insulation and vapor-will also be
performed by isolation of the soil.
www.gei-2a.com
gei-2a@gei-2a.com
29
Floor isolation.
Insulation thickness l6 cm. (frozen), with for-vapor type anti-vapor filter.
Isothermal doors.
The doors will be, as their use of categories or types:
Sliding doors: to ensure closure of the freezers, sliding doors should ensure good thermal
insulation, with FERMOD rails or similar type maneuver, and gaskets carefully installed to
ensure the sealing of the chamber, thickness of the door : 8 to 10 cm.
Type of lining: polyester.
To the gates of the chillers and storage of quick frozen, the insulation will be
strengthened. Thickness of 16 to 20 cm. Boards anti-frost heating and security alarm
for fallen or sick man.
For the doors separating the rooms surrounding temperature, sliding doors are simple rail without
the application of joint during closing, the isolation will be less perfect but
more than enough for the required needs.
For all sliding doors are provided barrier protection (bumpers) in robust manufacturing galvanized
steel.
Doors swing: will be provided with rigid polyethylene sheets in great
strength and easy maintenance, anti-shock protection in stainless steel
bottom, and a peephole in the top, the behavior and appearance of these
doors is much better to use the doors flexible PVC.
METAL WORK
All supplies are hot-dipped galvanized steel. Been established in this chapter:
The set of metallized doors, steel 2 sided, painted in technical facilities.
The racks, metal, painted with its stained glass and accessories.
The ventilation grilles.
Handrails and handrail of the stairs and walkways visit, covered.
The frames and guards of the channels.
www.gei-2a.com
gei-2a@gei-2a.com
30
www.gei-2a.com
gei-2a@gei-2a.com
31
TILES
Working areas: slaught rooms and work)
The tiles are porcelain tile type to 1st. game and made with cement boards (size 11.5 x 14 cm.).
Incoming angles rounded off by a special tile or a similar provision.
www.gei-2a.com
gei-2a@gei-2a.com
32
Tiles .
In the toilets and dressing rooms, the walls will be tiled up to 3
meters. The tile boards will be conducted in white cement.
Flooring tiles
The tiles are of the type-porcelain stoneware 50 x 50 cm. Parts placement skid with cement
mortar or tiles 10 x 20 cm. (according to
local). In offices and health areas inside the plant (at 50 x 50 cm.).
PAINTING.
The new metallic structures will remain as out of hot galvanized.
www.gei-2a.com
gei-2a@gei-2a.com
33
TECHNICAL EQUIPMENTS
Cooling:
In the final project phase will be studied better equipment. All this depending on the
forecast of the allied industries.
The cooling needs to maintain the temperature in storage rooms, workrooms and rapid
cooling were estimated in the calculations of the project after knowing allied industries
and final sizing. Refrigerator production facility is secured with NH3 - 10 C / +35 C
distribution by pumping from a tank located in the engine room. The cooling concept of
production has been made in view of future increases in capacity, having been sized all
fixtures (collectors, evaporative condenser, reservoir, etc.).. In engine room valves are
planned in anticipation of additional joints with compressors that can be made in future to block
extension of the refrigerator.
Was chosen ammonia (NH3), considering the following criteria:
High Energy Efficiency
Need for significant cooling power
Cost of ammonia lower than other coolants.
Easier maintenance of the installation.
It is a gas that does not harm the ozone layer, so there are no problems for future bans.
The production of cold chambers negative temperature of allied industries, with cameras frozen,
freezing tunnels and numerous air-conditioned rooms and chambers are expected
to be independent from the rest and are estimated each of a group of autonomous
production bibloc R22 (to be defined in specific projects). As for the cameras and positive
temperature Boards of allied industries, is considered using the same network of the
slaughterhouse.
NH3/ glycol water and isolated lung deposit ensures the distribution of cold services.
Cameras: glycol water network
Rooms: glycol water network
Frozen storage chambers and tunnels: R-22 autonomous
groups condensed with the network of water-glycol
Production cooling
In the engine room, production of NH3 refrigeration at -10 C, is performed with screw
compressors that develop a total power (to be determined at the planning stage), with
automatic power on the basis of suction pressure. Also in this room are located: a
horizontal repairman equipped with safety accessories and regulation, four circulation
pumps to distribute the NH3 for different chambers and rooms (there is an emergency
pump). There is also an evaporative condenser equipped with centrifugal fans, installed
near the engine room to cool the hot gas returning from the refrigeration compressors.
www.gei-2a.com
gei-2a@gei-2a.com
34
Equipment rooms
All evaporators have double bottom tank anti-condensation, batteries, snorkel and fins in
hot dip galvanized steel in the circuit of NH3.
In the workrooms, the fan speed of the evaporator is 950 rpm to avoid bothering the staff
with too much airflow.
Each room has a station control valves, a thermostat, and a box containing all control
devices (thermostat, switch demand from fans on a forced march or strike, etc.).
All pipes are seamless drawn steel insulated with injected polyurethane coated isoxal, and piping
hot gas and rock wool isoxal finish.
All piping and valve stations, go through the gallery of services, on the ceiling.
The defrosting of rooms with temperature exceeding +2 C, automatic hot gas and
regulated by the automaton. Defrost appliances with above +4 C is by air.
The rapid cooling, is equipped in the 1st and 2nd sections with vertical fins batteries and
galvanized steel tubes and axial fans in the ceiling. Each battery has its own tube station, and
alternating defrost during operation of the airing, returning the cooling capacity of the
battery out of the running.
OPTION:
Energy recovery in refrigeration plant:
An energy recovery can be effected in the condensation and return of the hot gases from the
refrigeration compressors. The components of the energy recovery system shall be established
to ensure a maximum instantaneous peak debit hot water 2 x 15 m3 / h up to full power the
refrigeration plant, allowing warm water of 12 C to 39 C approximately.
www.gei-2a.com
gei-2a@gei-2a.com
35
The final study will define the investment needs of cogeneration and its volume.
Daily consumption of industrial hot water, is estimated at 155 m3 to 65 C and 40 m3 to
90 C per day massacre tip.
Thiswater production is ensured by a vertical tank outside pressure, able to 2 x 30 m at
65 C and 90 C. This production is ensured by installing cogeneration equipment and
emergency generator steam.
The hot water is stored in a reservoir at 92 C.
This material hot water production has been chosen for their high energy efficiency (about
95%)
The deposit ensures the production of hot water to pass the slaughterhouse
or the industry to double its capacity, if in the future was needed.
B. Plumbing
Water treatment at reception
Metering pumps are foreseen, softener, anti-corrosion treatment for the water that feeds the
network of industrial hot water, steam boiler and evaporative condenser refrigeration plant.
www.gei-2a.com
gei-2a@gei-2a.com
36
Plumbing circuits
Plumbing circuits are:
Network of cold water (AF)
Network of industrial hot water at 65 C and recycling (ACI 65 th)
Network of industrial hot water at 90 C and recycling (ACI 90 th)
Compressed air (CA)
Steam Network
Red hot water (DHW)
natural gas network
Elements of the slaughterhouse, cutting and allied industries to connect to networks of
water, washing hands, washing boots, sterilizers, washing stations, tripe taps, fire
hydrants.
The washing stations are supplied with hot and cold water at 65 C, and have a tube of 20 m.
flexible rubber food grade white armed with spear and washed with a box of steel
304 L
The pipes used for the circuits of AF, ACI 65 and AC, are galvanized steel, and the ACI 90th
Circuit in stainless steel. The gas and steam circuits are black steel, and the ACS
circuit using copper pipe tempered.
For the circuit of AC in the vicinity of the important demands (such as pneumatic guns),
buffer tanks are installed.
The pipe insulation is made from rock wool covered with isoxal, and exterior galleries and
services, are protected from ice with heating cords.
Recirculation loops are projected on the main collectors of ACI 65 th and 90 th to get
hot water quickly at the furthermost points of production. The leads are kept warm with
electric resistance self-regulantes. Sterilizers have water at 90 C. Valves are planned
connection if in the future is to expand the slaughterhouse or industry.
Medical Supplies
For each block health, an ACS circuit 35C to the feeding. The locker room sinks and work areas
will be held non-manual and office area will be hand mixer mixer.
Showers and toilets will be installed white, with joint network of copper pipes.
www.gei-2a.com
gei-2a@gei-2a.com
37
D. Ventilation
The slaughter halls, local tripe and washing shall be ventilated to prevent fog,
condensation and odors.
The ventilation fan heaters have new air intakes on the roof with motorized baffles, filters,
centrifugal fans and natural gas burners.
In the textile sleeves for the ventilation of workplaces, the air velocity is 2 to 7 m / s
order not to inconvenience the staff.
Some places are in slight depression to prevent the spread of odors and condensation to
adjacent chambers.
Hall of slaughter:
Installation:
A centrifugal air heater in each hall with natural gas burner and beam blow with aluminum
bars.
Chimneys extraction on areas of condensation and remove smells.
These areas, as mentioned above, will be in slight depression.
The air renewal rate is 12 to 15 volumes / hour.
www.gei-2a.com
gei-2a@gei-2a.com
38
Technical gallery
This is the space above the false ceiling, which are installed the piping network. It will be a
ventilated area to avoid condensation and calories detached by the ventilation fan heaters.
Exhaust chimneys on the ceiling will be provided with thermostatic control and humidity.
Air renewal rate, 4 to 6 volumes per hour.
Technical rooms
The boiler and general low voltage (MLVS), aired by mechanical air extraction (with
chimneys on roof), regulated by thermostat. The rate of renewal of air in the boiler is 20
to 25 volumes / hour, and the MLVS 3 to 4 volumes per hour.
Electricity.
www.gei-2a.com
gei-2a@gei-2a.com
39
E. Electrical Wiring
The cables move through appropriate tubing hot dip galvanized steel, technical and gallery
located in maintenance areas, and PVC in the work rooms and chambers. Have been
extensively dimensioned to allow a further extension of 30%.
The cables used are of the type:
ARO 1000 V 2 V for large sections (aluminum wire).
V 1000 RO 2 V for all distributions (copper wire). All
the remote machine made in 24 V.
Each leg of motive power and lighting will all protected by circuit breakers tripolar or bipolar, as
the case and following the rules in force, and marked with the corresponding engraved plates.
The rate of protection as the rest of electrical equipment is IP 555.
www.gei-2a.com
gei-2a@gei-2a.com
40
G. Electric Heating
In offices in the yards, will be placed thermostat electric convectors. In administration and
dressing rooms, the heating will be mixed (base + support), the heating base is through heating
cables under the pavement, with operation in hours of reduced fee, and is
supported by electric convector with thermostat.
In negative local temperature, freeze-avoiding soil heating cables under the pavement.
PHONE
It provides the facility of an analog autoacumulador Administration,
equipped with 5 outside lines and telephone posts l6.
www.gei-2a.com
gei-2a@gei-2a.com
41
www.gei-2a.com
gei-2a@gei-2a.com
42
Comment: The slaughterhouse is the part of production that has been changing from the
initial offers.
Variations are caused for the posibility to multiply the production by four, the posibility of the
butcher the 20% of the production, because we have to this country with a high technology
product.
According to the machines, we included dry area, clasification, butcher area, packing, etc.
We also thought about the transport of intestinal remainder, transport and treatment of
blood and collection of scraps.
We added to the offer two cameras inside the slaughter house to make easier the transport of
the meat.
The slaughterhouse has been designed to make easy the future extension, using the same
areas to charge and discharge, obviously, this has an economic repercussion from the initial
project.
Anyways, if this project goes on, our collaborators and engineers will study with the property
every detail of the slaughter house, wich will be the final image of the production line of the
chicken meat.
www.gei-2a.com
gei-2a@gei-2a.com
43
QUANTITY
70.000
35.000
70.000
20.000
35.000
40.000
5.000
6.000
30.000
9.000
30.000
TOTAL..
350.000
QUANTITY
Farmers houses
Telephons and communications
Security
Dining, social area and costums
Exterior electricity in farms
Exterior conduction of water
Exterior gas installation
Machines for packing in slaughterhouse.
www.gei-2a.com
gei-2a@gei-2a.com
44
6.-RESUME
TOTAL COST
CONCEPT
5.674.986,09
27 Chicken Farms
500.981
364.100
1 Slaughtery
3.442.000
9.982.067,09
TOTAL
PROYECT
UNIT
1
2
1
1
1
1
SPECIALIST
Incubator assembling supervisor.
Cattle feed factory assembling supervisors
Slaughter assembling supervisor.
Cold stage assembling supervisor.
Poultry farms assembling supervisor.
Electronic supervisor.
www.gei-2a.com
gei-2a@gei-2a.com
45
TIME
7 weeks.
12 weeks
16 weeks
4 weeks
40 weeks
3 weeks
WORKING TIME.
See the chronogram attached. We understand that under the agreement
signed, it takes 8 days to prepare the materials and layouts. The sendings could
start in the week number 9. About the poultry farms, we think that we can start
and finish one every week...
STIMATED PERSONAL.
UNITS
2
2
3
4
2
2
2
4
4
4
4
4
4
4
4
PERSONAL WORKING.
Linquer incubator building.
Incubator electric installation.
Cattle feed factory assembly.
Slaughter assembly.
Slaughter electric installation assembly.
Cold store assembly.
Cold store electric installation.
Farms structure assembly.
Farms ceiling assembly.
Farms wall assembly.
Feeders and drinkers assembly.
Climatization assembly.
Electric installations.
Gas and water installations.
Start-up
TIME
4 weeks
3 weeks
12 weeks
30 weeks
8 weeks
3 weeks
1 weeks
27 weeks
27 weeks
27 weeks
27 weeks
27 weeks
27 weeks
27 weeks
27 weeks
PROYECT - LABOR
WORKING UNIT
Cattle Feed Factory
Chicks Farm.
Breeders.
Chicks and breeders cleaning.
Eggs transport to incubators.
EMPLOYEES
2
N.
1
TOTAL
2
1,2
1
1
9
1
1
11
1
1
1
1
12
3
1
1
1
1
1
1
1
1
12
3
1
2
1
1
1
2
1
www.gei-2a.com
gei-2a@gei-2a.com
46
The numbers are approximate; they can have variations depending on the distance
between the buildings of production and distribution. The feed distribution, chicken distribution
from the incubator, broilers distribution to the slaughter, included distribution of the final product,
change depending of the distances.
The UPP of 3 farms can work with only one person if the chicks are inside. The work is to
take care of the chicks and pick up the dead ones. When the buildings are empty, this person
can be on vacations. But there are moments that this person is going to need help; when cleaning
the farms or prepare the buildings for a new chicks entrance. Thats why we talk about 1,2
persons. This second one could be some person of his/her family, or one for the different UPP.
Working unit.
Cold Store
Poultry farm.
Cattle Feed factory.
Slaughter.
Incubator.
H2O
L/day
No mind.
12.000
No mind.
15.000
2.000
Refrig.
--------22.000
--------3.000
www.gei-2a.com
gei-2a@gei-2a.com
47
Total
H2O
-------34.000
------15.000
5.000
Pot.
Kw
20
14
70
110
100
Real
Kw
25%
25%
75%
80%
20%
ELECTRICITY
TOTAL $0,00331
www.gei-2a.com
gei-2a@gei-2a.com
48
DATA
Price m3 (USD)
1,24
Kg. Chicken/year
5.850.000
WATER
BUILDING
LITR. HOUR
FARM DRINK
HOURS YEAR
FARM REFRIG.
1.720
SLAUGHTERHOUS
INCUBATOR
US $ M/3
COST/YEAR USD
27
20.000
$1,24
$24.800
$0,00424
1.440
2.476,8
27
66.873,6
$1,24
$82.923,26
$0,01417
1.500
2.600
3.900
3.900,0
$1,24
$4.836
$0,00083
500
2.600
1.300
1.300,0
$1,24
$1.612
TOTAL
$0,00028
$0,01952
DATA
Kg. chicken/year
5.850.000
Price egg
Price food (USD /TON)
$0,25
$150
PRINCIPAL EXPENSES
CONCEPT
EGGS/WEEK
YEAR
PRICE $
$ TOTAL
11.700
$150,00
1.755.000
$0,25
1.105.000,0
85.000
4.420.000,0
Technical directions
117.000,0
Medicines
Cleaning and disinfection
117.000
117.000
$0,02000
$0,02000
$0,02000
TOTAL
$0,54889
DATA
Kg. chicken/year
5.850.000
0,14
0,17
OTHER EXPENSES
CONCEPT
QUANT./YEAR
USD /YEAR
67.500
$9.450
$0,00162
6.000
$1.000
$0,00017
$40.000
$0,00684
$11.700
$0,00200
MAINTENANCE
$11.700
$0,00200
$8.000
TOTAL
$0,00137
$0,01399
www.gei-2a.com
gei-2a@gei-2a.com
49
DATA
Kg. Of meat/year
5.850.000
LABOR
PRODUCTON UNIT
SALARY/YEAR (USD)
Chicken farms
Veterynary and director of production
N WORKERS
TOTAL SALARY
$4.200,00
11
$46.200,00
$0,00790
$15.000,00
$15.000,00
$0,00256
Incubator + maintenance
$5.000,00
$5.000,00
$0,00085
Chicken transport
$6.000,00
$6.000,00
$0,00103
Recolection of chicken
$4.000,00
$4.000,00
$0,00068
$5.000,00
12
$60.000,00
$0,01026
$0,00308
Comercial delivery
$6.000,00
$18.000,00
$6.000,00
$6.000,00
$0,00103
Administration personal
$6.000,00
$12.000,00
$0,00205
$30.000,00
$30.000,00
General director
TOTAL
$0,00513
$0,03456
COST/KG (USD)
PRINCIPAL EXPENSES
$0,54889
LABOR
$0,03456
ELECTRICITY
$0,00331
WATER
$0,01952
OTHER EXPENSES
$0,01399
TOTAL
$0,62028
NOT INCLUDED
- Insurance
- Comercialization costs
- Marketing
- Financial costs
- Amortization
www.gei-2a.com
gei-2a@gei-2a.com
50
Price food
170 $ ton.
Price food
190 $ ton.
Price food
200 $ ton.
0,30000
0,34000
0,38000
0,40000
0,18889
0,18889
0,18889
0,18889
0,04000
0,04000
0,04000
0,04000
Direccin tcnica
Electricity in the whole process:
farm, slaughterhouse, camera
0,02000
0,02000
0,02000
0,02000
0,00331
0,00331
0,00331
0,00331
Water
0,01952
0,01952
0,01952
0,01952
CONCEPT
Food at various prices. 2 kg of
food = 1 kg of chicken. Cost per
Kg.
Fertile egg. 85,000 eggs to get
75,000 chickens. Price $ 0.25
egg.
Heating
0,00162
0,00017
0,00684
0,00162
0,00162
0,00162
0,00017
0,00017
0,00017
0,00684
0,00684
0,00684
0,03456
0,03456
0,03456
0,03456
Office expenses
0,00200
0,00200
0,00200
0,00200
Maintenance expenses
0,00200
0,00200
0,00200
0,00200
0,00137
0,00137
0,00137
0,00137
www.gei-2a.com
gei-2a@gei-2a.com
51
TOTAL USA $
ERROR + 5%
0,62028
0,66028
0,6
0,6
0,70028
0,72028
0,7
0,75342
ERROR + 10%
0,6
0,7
0,7
0,78929
ERROR + 15%
0,71017
0,75617
0,80217
0,82517
0,74105
0,78904
0,83705
0,86105
ERROR + 20%