composition and of sufficient strength to resist chafing when subjected to the

pressure and movement likely to occur in transit. Motors and equipment with
ball or roller bearings shall be protected with resilient packing to prevent damage
due to vibration.
The packing cases and packing materials are included in the Contract
and shall be the property of the Owner (SEC).

6.14.1

Receipt and storage at site

All items, packing cases, containers and packages received at Site shall
be recorded against the shipping schedule and immediately inspected for signs of
damage. All signs of damage shall be investigated and the extent and nature of
the damage recorded. The contents of each packing case, container or package
shall be checked against the contents list and any discrepancies noted. Each
item shall be carefully unpacked and checked for mechanical damage and/or
damage to the corrosion protection. All such damage shall be recorded.
No item will be accepted for storage on Site until all mechanical and/or
corrosion protection damage has been notified and rectified to the
Engineer/Owner (SEC)s satisfaction. It is emphasized in this respect that for
damage which may affect the life or function of the component Contractor C
must submit a full report to the Engineer/Owner (SEC) describing the
consequences of the damage and the proposed rectification procedures.
All plant and equipment to be stored out of doors shall be placed on
timber or the equivalent so that it is out of contact with the ground and provided
with adequate protection against weather. The Engineer/Owner (SEC) may, if he
considers it necessary, instruct Contractor C to carry out a repair or special
cleaning process on any item on which the protection has been ineffective and/or
which has been subjected to adverse storage conditions.
All items stored at Site shall be inspected on a regular basis and
adequate records of inspection and corrosion protection rectification carried out
shall be kept. All such records and the items in store will be subject to periodic
audit and inspection by the Engineer/Owner (SEC) who may require additional
work to be carried out to either restore the condition of the item or to ensure
that deterioration does not occur.
The cost of all recording, inspection and rectification shall be borne by
Contractor C who is also responsible for any necessary insurance claims against
shipper and/or other parties in respect of the damage to or loss of any item or
component.
On withdrawal from store, each item or component shall be prepared
for erection by removal of temporary shipping and site storage protection.
Immediately prior to erection, inspection shall be carried out to ensure that all
APPROVED

AlexV

JAMIL M AL-MUTAIRI,
MANAGER, EPED

QURAYYAH COMBINED CYCLE POWER PLANT


PROJECT C - CONVERSION OF OPEN CYCLE
GAS TURBINES TO COMBINED CYCLE PLANT

PTS # 07EG908
Volume 1 OF 3

Page
260 of 481