Professional Documents
Culture Documents
Ebin Joseph
Goutham Venkatesh K.
P. Akshay Kumar
Vineesh K
Semester 7
Department of Ship Technology
Page |1
Introduction ..................................................................................................................... 3
Outfitting ......................................................................................................................... 4
Fitting Out Ships.............................................................................................................4
Traditional Practice ........................................................................................................5
Disadvantages with Traditional Practice........................................................................6
Concept of Unitisation: ..................................................................................................6
Block Outfitting Concept:...............................................................................................7
Group Technology / Concept of Workstations / Product-Work-Breakdown-Structure:7
Concept of Zone-Outfitting:...........................................................................................8
Management in Outfit Shops .......................................................................................... 10
Typical Responsibilities for College-Educated Staff People Assigned to an Outfitting
Fabrication Shop (e.g., for manufacturing pipe pieces) ..................................................10
Special Activities ..............................................................................................10
Routine Activities .............................................................................................11
Typical Responsibilities for College-Educated Staff People Assigned to an Outfitting
Assembly Shop (e.g., deck, accommodation, machinery and electrical) ........................11
Special Activities ..........................................................................................................11
Pipe Outfitting................................................................................................................ 13
Pipe Shop: Case Study - Cochin Shipyard Ltd. .....................................................................13
Outfit Warehouse at Cochin Shipyard Ltd. ..............................................................14
Work Flow In A Pipe Shop........................................................................................16
Infrastructure ...........................................................................................................16
Layout Sequence of Machinery ...............................................................................18
Location of piping shop............................................................................................19
Storage of piping......................................................................................................20
Advanced Outfitting Practices in a Shipyard ...........................................................21
Machinery Outfitting ...................................................................................................... 28
Main Engine Installation ......................................................................................................29
Deck and Cargo Space Equipment ................................................................................... 31
Deck Crane Installation ................................................................................................31
Crane Pedestal Installation ..........................................................................................32
Accommodation Outfitting ............................................................................................. 33
Page |2
Electrical Outfitting ........................................................................................................ 36
Electrical Repair Shop ..................................................................................................36
Electrical Shop Plan......................................................................................................37
Vote of Thanks ............................................................................................................... 38
References ..................................................................................................................... 38
Page |3
Introduction
In conventional shipbuilding, the ships hull structure is fabricated and erected on the berth
or dock and the outfitting is started only after launching the hull from the berth. As a result,
it has been found that the process of first fabricating and completing the hull structure
followed by outfitting the hull after launching takes longer time. Hence, to reduce the cycle
time and improve the productivity of the shipyards, the concept of advanced outfitting has
been developed.
All the modern day shipyards across the world have now identified that by adopting the
concept of advance outfitting the vessel building cycle time can be reduced and a substantial
saving of costs, along with other benefits, depending on the availability of infrastructure in
the yards can be achieved. Different concepts have been developed for the completion of
outfitting in block stage to derive the benefits of this methods. Where previously outfitting
was done entirely after the ship was launched from the slipway or the dry-dock, modern
concept facilitates the outfitting work to be started even before the launch; i.e. within the
block erection stage.
Page |4
Outfitting
Outfit includes all non-structural parts of a ship.
Among these items are:
1.
2.
3.
4.
5.
6.
7.
Organization of and responsibility for outfit work may vary from shipyard to shipyard,
subject to local traditions, union jurisdictions, subcontractor arrangements, and other
considerations.
Deck equipment
WINDLASS/WINCHES/BOATS/DAVITS
Accommodation Spaces
JOINERY/ELECTRICAL /PLUMBING/VENTILATION
Piping
FUEL/BALLAST/CARGO MAINS
Miscellaneous
Machinery:
Page |5
MAIN ENGINES
AUXILIARY MACHINERY/EQUIPMENT
PIPING
Electrical:
Engine Room
Hull main services.
Traditional Practice
In the past, the tendency has been to separate various trades and to commence outfitting
only after a significant proportion has been erected. The principal features is this mode of
work where the ship spending a relatively short time at the assembly/fabrication stage and
comparatively long periods on the building berth and in the basin.
Page |6
Concept of Unitisation:
Even before the hull block is made, the outfit components (machinery, piping, seating
structures, etc.) which are supposed to be located in a particular small area in the ship are
fully assembled into a small unit and when the hull block is made, this unit is then directly
installed at the required position in the block. Hence you see, in this process, the steel
structure and the machinery outfit units are developed simultaneously instead of a traditional
process wherein the machinery and outfit are installed only after complete erection of the
Page |7
ships hull. This process actually helps in reducing the cycle time required to build the ship.
Remember, in ship-building too, time is money.
Page |8
The question arises as to why do we need such a grouping? The answer lies in the fact that
this method of grouping offers considerable potential for the improvement of the
manufacturing efficiency of the shipyard. Because each workstation is now specialized in
efficiently manufacturing its designated units, since it is equipped with the suitable tools,
machinery and workforce required for the same. This not only allows easier planning of work
but also maintains a steady work load with increased performance of operators.
One very notable aspect that we must take note of is that this method can now be applicable
to develop and manufacture the interim products of units for all types of ships that the yard
will be building in the future. Thus, the advantage of repeated work can be obtained in
utilising the workstation concept in shipbuilding industry.
Concept of Zone-Outfitting:
Before we start understanding this concept of advanced outfitting, it is necessary to
understand what a Zone is when we are speaking in terms of shipbuilding. A zone may
correspond to a compartment or even any integral part of a compartment of a ship, such as
a cargo hold or a machinery space and its sub-divisions. It completely depends on the yard as
to how they define the zones in a ship to be built. Even an entire superstructure or just one
level (deck) of a superstructure could be considered to be a zone. Hence, in a nutshell, a zone
is a sub-division of a ship that is selected for the convenience of outfitting either on units of
hull block or on larger hull blocks or directly on-board the whole ship after all the blocks are
joined.
There are three types of zone outfitting practices, mainly dependent on the scale on which it
is applied.
1. On-Unit
2. On-Block Installation:
3. On board (either on berth or afloat):
Page |9
P a g e | 10
P a g e | 11
Routine Activities
1. Preside over weekly meetings attended by the shop manager, flow lane foremen and
their assistants and other staff assistants to:
a. ascertain the number of components completed per week relative to planned
output per flow lane,
b. establish the amounts of work to be accomplished next week, including
overtime work and work to be subcontracted, and
c. Establish a manning plan per flow lane for next weeks work.
2. Once each month, prepare the shop managers report to the department manager
presenting the actual trend of production (difference between what was planned and
scheduled and final results) and presenting recommendations for improvement.
3. Maintain the accuracy control system.
4. Attend safety control meetings which are held twice per month.
P a g e | 12
5. Prepare 3-months and l-month schedules using the design outputs per pallet and manhour rates associated with fitting specific materials.
6. Continue to contribute to further definition of a build strategy as subsequent design
phases evolve and eventually inputting information needed to facilitate work, e.g.,
check points, reference lines, means for air testing welds , so that the output of detail
design is, literally, work instructions.
7. Document the outfitting strategy and establish targets taking into account new ideas
for reducing costs.
8. Prepare the zone-outfitting schedule insuring that it is compatible with the design
schedule for preparation of work instructions corresponding to pallets (MLF).
9. Prepare a staging plan.
10. Specify access and routes from a safety point of view.
11. For each building contract, budget man-hours and materials allocated to the shop to
the various flow lanes based on records of efficiency achieved and also based on
planned improvements in work methods, e.g., automatic welding, and better jigs and
tools.
12. Plan relocations of on-board cranes to anticipate erection progress.
13. Prepare plans such as for main engine installation, propulsion system alignment,
flushing completed pipe systems, etc.
Routine Activities
1. Attend the brief meeting of electric shop foremen each morning.
2. Preside over the weekly meeting for finalizing next weeks work load specifically by:
a. Checking monthly schedules proposed by foremen and weekly schedules
proposed by assistant foremen,
b. Conveying policy conceived by the shop staff for how work is to proceed.
c. Discussing and adjusting the distribution of workers with the foremen, and
3. Resolve owners and surveyors reports of unsatisfactory items and process feedback
reports.
P a g e | 13
Pipe Outfitting
Pipe Shop: Case Study - Cochin Shipyard Ltd.
At the Cochin Shipyard Ltd., the Outfit department takes over the ship from the Hull Erection
department. The hull erection department assembles the blocks and the basic structure is
laid. Now the ship needs to be stuffed with all the equipment, machinery and comfort. This is
done in the outfit department. There is outfitting of machineries, piping, electrical outfitting
and accommodation outfitting.
P a g e | 14
P a g e | 15
Steam piping
Ballast piping system
Ventilation pipes
Refrigeration pipe
Sounding pipe
Air pipe
P a g e | 16
2. CAD Drafting
3. Cutting Process
4. Edge Preparation
9. Bending
8. Hole Punching
7. Stress Relieving
6. Testing
P a g e | 17
Infrastructure
Machinery Items in Pipe Shop:
MACHINE
SPECIFICATION
Pipe Coaster
350NB
10NB 50NB
15NB 25NB
Threading Machine
Threading Machine
Winch
5T
upto 80NB
upto 175NB
RM62
Centre Lathe
HMT H26
P a g e | 18
Pedestal Grinder
Heavy Duty
Tool Grinder
Light Duty
250Kg/cm2
upto 250NB
EOT Crane
5T & 2T
Post Crane
1T
2. BENDING
3. SPOT WELDING
4. WELDING
5. GRINDING
6. BLASTING
P a g e | 19
P a g e | 20
Storage of piping
In the storage of pipes in shop before fabrication or after fabrication one should
consider the following
Space occupation
Flow of work
Minimum apparatus
In pipe shop pipes are kept in racks with recommended height and proper
accessibility with minimum space available for the handling of pipes
P a g e | 21
Step: 1
P a g e | 22
Shown in previous image is a machinery unit which will contain both a Seawater
Service Pump and an Air-Conditioning Water Pump.
Step: 2
A strainer has been fitted to the Seawater Service Pump, the Air-Conditioning Water Pump
has been fitted and a valve is being lifted into position
P a g e | 23
Step: 3
A pipe piece is being lifted by the shop's bridge crane for bolting to the Seawater Service Pump
Step: 4
A second worker temporarily assists by guiding a strainer to its final position while the
gasket and a few bolts are secured
P a g e | 24
Step: 5
Step: 6
P a g e | 25
On-Block Outfitting
Outfitting on block is the installation of outfit components (machinery with seats, piping,
electrical cables, ventilation trunks, etc.) after an entire hull block is completed. The units are
installed either as separate components or after unitising them (similar to what is described
above)
P a g e | 26
Outfitting components, units, and grand units are sometimes fitted in a block zone
defined for hull construction.
However, when they are to be fitted to ceilings, blocks should be inverted because
fitting down-hand enhances safety and efficiency.
Following block turnover, the outfit zone encompasses the components, units, and/or
grand units fitted to the floor.
P a g e | 27
Outfit items should be fitted in the zone of a double bottom block before its tank top
panel is installed.
The primary goals of this manufacturing level are to outfit ceilings and double
bottoms when blocks can be manipulated to provide ideal access.
P a g e | 28
Machinery Outfitting
On-Board Outfitting
Conventional method of outfitting - It can be defined as all the outfitting work that is done
after the hull blocks are completed and erected in the slipway or docks.
Ideally, assembly and painting work are left for accomplishment on-board.
These works are limited to:
1. Fitting of components that are too large to fit on block like main engine,
diesel generators etc.
2. Connecting distributive systems at block butts and seams
3. Pulling only the ends of electric cables that were fitted on block
4. Pulling electric cables that could not be pulled on block
5. Connecting electric cables
6. Clean up
7. Painting touch up
8. Installation of the main drive line
9. Finish painting
P a g e | 29
STEP 2:
P a g e | 30
STEP 3:
STEP 4:
P a g e | 31
P a g e | 32
P a g e | 33
Accommodation Outfitting
Accommodation spaces are available as pre-outfitted modules. These are installed on the ship
as On-block installations. Depending on the space availability in the unit of installation,
modularised accommodation units are ordered.
P a g e | 34
Modules lifted into ship using Cranes
P a g e | 35
Accommodation Units Before, During and After Installation
P a g e | 36
Electrical Outfitting
Electrical equipment installations in ships:
1. D.C. Generators
2. D.C. Switchgear
3. A.C. Generators
4. Automatic Voltage Regulators
5. A.C. Switchgear
6. Distribution Box Main Switch Board, Sub-Switch Boards.
7. Electric Cables
8. Insulation and Temperature rating of Machinery
9. Motors
10. Motor Control Gear
The potential for electrical shock hazards is greater in shipbuilding and repair than in other
industries, because workers stand on metal decks and often work in a wet environment. Work
on or around energized electrical equipment can expose workers to electrocution, burns, or
electrical shock. Before work is performed, energized equipment must be guarded, deenergized, or appropriate PPE used to prevent worker exposure.
P a g e | 37
P a g e | 38
Vote of Thanks
We would like to take this opportunity to express our sincere thanks to the following persons
who have helped us in completing this assignment.
References
Ship Production Technology Part-I and Part-II, Prof. R.A. Shenoi, University of
Southampton
i.T.. Faculty of Naval Architecture and Ocean Engineering Shipyard Organization
GEM 412-E
Shipyard Management - Design, Planning & Operations: Event Brochure
o BC Asia website@ibcasia.com.sg
Ship Production Storch Lee
Marine Insight Website www.marineinsight.com