Professional Documents
Culture Documents
ABSTRACT
This paper presents an overview of various ground improvement techniques available and discusses factors
influencing the choice of technique. It then briefly describes relevant quality control procedures for common
techniques. This is followed by some applications of these techniques to different types of structure as well as
different soil conditions. Structures and facilities that have utilized ground improvement include roads and highways,
railways, ports and airports, land reclamations, storage tanks, chemical plants, tunnels and residential buildings.
The basis for choosing the particular technique for the project is explored, be it time, cost, technical performance
or environmental considerations. In addition, the quality control procedures adopted for various techniques are
explored. The paper will show that ground improvement is often the ideal foundation solution for such structures.
1. INTRODUCTION
Infrastructure projects such as highways, railways, airports
and harbours, cover large areas of land, sometimes over tens
of kilometers. This often leads to highly variable soil
conditions for the same project. Almost invariably, projects
such as railways or highways encounter problematic soils. In
addition, a large portion of infrastructure and building work
is in coastal regions, where soils typically have low strengths
and are highly compressible. Construction in increasingly
urban environments means that sites with poor soil conditions
and even landfills are being utilized for various structures and
facilities. This construction activity on poor soils often leads
to the necessity for ground improvement prior to start of
construction. The type of ground improvement required
depends very much on the type of structure to be built (and its
sensitivity to ground movement), the type of soil being treated
(and its short and long term behaviour) and the types of tools
and materials available. However, it is not sufficient to merely
select the appropriate ground improvement method. One must
also ensure that the work is done to an acceptable standard of
quality. This paper presents an overview of the more common
ground improvement methods in use and quality control
procedures that need to be adopted. Specific projects are
described to illustrate the various techniques and quality
control procedures.
2. TYPES OF GROUND IMPROVEMENT
Ground Improvement refers to any technique or process
that improves the engineering properties of the treated soil
122
increase in excess pore pressures. As the excess pore pressures
dissipate, consolidation occurs. The principle is that by preloading the soil, much or all of the settlement that would occur
under the final structural load can be forced to occur prior
to construction. Therefore, little or no settlements will occur
during the service life of the structure. Often, a load higher
than the final structural load is placed as a pre-load, to reduce
the consolidation time. With the PVDs installed, the total
compression of the ground under the pre-load is not altered,
but the consolidation process is accelerated.
In vacuum consolidation, the load is applied by
suction, rather than by a physical pre-load. This has the
advantage of maintaining better internal stability of the
soil mass (no sudden increase in excess pore pressures).
Although pressures measured at the pumps can be -80 to
-90 kPa, losses in the system and differences in the
groundwater level and pump inlet, means that the
practical negative pressure that can be maintained in the
soil is usually between -50 to - 70 kPa. For this reason,
vacuum pressure is often combined with a physical preload.
Stone columns, typically 1.0m in diameter, function
as large drainage elements. However as the columns act
primarily to reinforce (i.e. strengthen and stiffen) the
ground, a pre-load higher than the final load is seldom
necessary.
Chemical Modification
Chemical modification relies on the introduction of a
chemical binder to alter the physical properties of the soil
mass. Typical chemical binders include lime, cement and
fly ash. Often, the objective is to improve the strength and
stiffness of the soil. In some cases, the objective is to reduce
permeability. Ground improvement by chemical
modification is usually classified according to the means
by which the binder is introduced into the soil matrix.
Broadly, these categories are:
Grouting- The voids in the soil matrix are filled with a
chemical such as sodium silicate or Portland cement.
The voids can simply be the pore spaces between sand
grains, or fissures within a limestone formation. Often,
the objective of grouting is to reduce the overall
permeability of the soil/ rock mass.
Fracture Grouting- In this group of techniques, the
binder is injected under pressure resulting in controlled
fracturing of the soil rather than permeation of the soil
matrix. This technique is used mainly to lift structures
(on the surface or even buried) or to compensate for
settlement or volume losses. Hence it is also referred to
as Compensation Grouting. There is some overall
strength gain and reduction in permeability, but this is
not usually the primary purpose.
V. R. Raju
123
happening below ground are very helpful to ensure quality.
In addition, the data loggers can be used to provide a
printout of the construction process, a so called birth
certificate of the improvement point for daily review by
the Engineer. (More details are given in the next section).
Availability of Material
Ground improvement uses a range of materials, some
natural (e.g. stone) and some manufactured (e.g. cement,
geotextiles). The availability of these materials will
influence the choice of technique. Malaysia for example
has several soft soil deposits in the coastal regions with
nearby hilly terrain. The hilly terrain makes stone easily
available and has led to extensive use of stone columns to
treat the soft coastal soils.
Time
Methods which require long consolidation periods will
obviously not be suitable for fast track projects. Installation/
construction time is also important. Nowadays however,
modern high-production machinery allows a significant
reduction in construction time. For example, the use of the
twin configurations in Vibro or DSM equipment or the
use of computerised cranes to drop the pounder in dynamic
compaction have very significantly increased production
rates.
Cost
Assuming that the solution satisfies technical requirements,
cost often becomes the deciding factor. Methods which use
less or cheaper added material are of course cheaper.
However if the cost of time or the risk of non-performance
are added, then other apparently expensive solutions
become economical.
Convenience
Solutions which do not require other additional measures
such as the placement of a large preload, or excavations
(as in excavate and replace methods) are more convenient
and practical.
Protection of the Environment
Methods which produce spoil are of course not desirable.
In-situ treatment methods which do not remove the soil or
discharge excess cement/binder are preferred. For example,
stone columns installed by the dry method only displace
the in-situ soil. In contrast, the wet method of column
installation flushes out some of the soil. For this reason,
the dry method is often preferable. Similarly in-situ soil
mixing would be preferable to jet grouting where possible.
Another criterion would be the influence of the method on
sensitive structures nearby.
4. QUALITY CONTROL PROCEDURES
Quality control procedures are important firstly to assure
124
V. R. Raju
Table 1: Some Features of Various Ground Improvement Techniques
Technique
Soil Type
PVD + Surcharge
Soft clays,
silts
Vacuum Consolidation
Loose
sands,
gravels
Dynamic Compaction
Loose
sands, silts,
clays
Basic
Principle(s)
Comments
Typical grid spacing = 1m to 2m
Drainage/
Consolidation
Excessive
settlement,
Creep,
Liquefaction
Densification
Excessive
settlement, Low
bearing
capacity,
Liquefaction.
Reinforcement,
Drainage/
Consolidation,
Densification
Excessive
settlement, Low
bearing
capacity
Reinforcement
Silts, Clays
Excessive
settlement, Low
bearing
capacity.
Reinforcement,
Densification
Sands,
silts, clays
Excessive
settlement, Low
bearing
capacity
Chemical
modification
Sands,
silts, clays
Excessive
settlement, low
bearing
capacity, high
permeability (in
sands)
Chemical
modification
Injection Grouting
Sands, silts
High
permeability
Chemical
modification
In soils, the binder is often injected via a tubea-manchette giving rise to the name TAM
grouting. Binder choice is determined by soil
type.
Compaction Grouting
Sands, silty
sands
Excessive
settlement,
Liquefaction
potential
Densification,
reinforcement
Mixed- Modulus
Columns
Dynamic Replacement
Jet Grouting
Loose
sands, silts,
clays
Geotechnical
Problems
125
and operator errors tend to give erratic results. Also,
compared to CPTs, drilling boreholes to perform SPTs are
slow and laborious.
Chemical/ Cement-Based Techniques
For cement based techniques (grouting, deep soil mixing
and jet grouting), quality control is focussed on the careful
control of the materials that are used, as well as the mixing
or pumping process. The grout mix is tested for its density
(often using a hydrometer) and viscosity (often using a
Marsh cone). In the case of silica gels for permeation
grouting, setting times are crucial for the success of the
grouting program, and are carefully tested also. The
installation process is also carefully monitored. Key
parameters such as flow-rate, pressure and total volume
injected are carefully monitored, almost always
automatically. In the case of deep soil mixing on jet
grouting, parameters such as rotation speed and withdrawal
rate are also important. Post-construction testing is of some
value, especially in instances where re-injection is possible.
For permeation grouting, post-construction testing can take
the form of pumping tests. In the case of deep soil mixing
or jet grouting, coring and UCS testing is often performed.
However, for deep soil mixing or jet grouting, it is far more
desirable to get it right the first time as re-work is very
difficult and sometimes impossible. For further details on
grouting works, the reader is referred to Raju & Yee (2006)
and Semprich & Stadler (2003). EN 14679: 2005 gives
guidance on the construction and quality control of deep
soil mixing.
Other Techniques
Some common techniques such as prefabricated vertical
drains (PVD) have standards that govern construction and
testing (e.g. IS 15284 (Part 2): 2004; EN 15237: 2007).
Other techniques like Dynamic Compaction or Rigid
Inclusions rely on generally accepted industrial practises,
which are then written into detailed contract specifications.
Because ground improvement techniques work on different
principles and are constructed in a variety of ways, the key
features to be checked vary from technique to technique.
Therefore it is vital that contract specifications for ground
improvement be drafted specifically for the technique. For
example, one cannot simply apply piling specifications to
Vibro stone columns or DSM columns simply because they
are vertical element within the ground.
5. APPLICATIONS
Highways & Roads
Roads on Hydraulic Sand Fill (Jurong Island,
Singapore)
Jurong Island is a petrochemical centre, housing petroleum
storage tanks, petrochemical plants and other related
126
V. R. Raju
Cone Resistance
(MPa)*
0- 2
2- 8
>8
8
12
17
80
70
70
*Whichever is lower
Railways
Railway Embankment Built on Soft Silts and Clays
(Double Tracking Project, Malaysia)
The Malaysian government has been upgrading the railway
network in the country. Certain sections of the existing
network are to be expanded to a double track, for high speed
electric trains. As the new line had more stringent
restrictions on gradients, in general, embankment heights
were raised.
The railway line passes through areas that have
seen extensive tin mining activity in the past. Soils
encountered were highly variable, with a mixture of
loose sands, very soft silts and very soft clays as deep
as 24 m. Cone tip resistance (qc) values in the very
soft silts and clays were often between 150 and 250
kPa. The performance criteria laid down by the railway
authorities are as follows:
127
Stone columns
Soft
Clay
Ports
Access Roads and Hardstanding Pavements on Soft
Clay (Pipavav, India)
Pipavav Shipyard Limited (PSL) is currently developing
an integrated shipbuilding facility in Pipavav. The area
being developed is 85 hectares in total. The construction
of the shipyard includes the construction of a block making
facility for hull blocks, the installation of a ship lift facility
and the conversion of an existing wet basin into a 651 m x
65 m dry dock. Geotechnical and foundation activities
include Vibro stone column works, bored cast in-situ piles
and diaphragm walls. The ground generally consists of
murram fill followed by soft marine clay and then weathered
rock.
128
V. R. Raju
Quality control procedures were adopted from precostruction to post-construction. During construction,
computerised monitoring of installation parameters was
performed. Parameters were displayed to the operator in
his cabin. In addition, printouts were generated in the
operators cabin in real-time, ensuring rapid review of the
construction process for each column. A sample printout
from the project is shown in Fig. 6 below.
Vibro stone column work is also ongoing for the
Offshore Yard area. A load-settlement curve from a singlecolumn load test is shown in Fig. 7 below. At the design
load, the measured settlement was 5.38 mm, below the
allowable settlement of 12 mm.
129
As part of the quality control program, detailed preconstruction soil investigation was performed. Quality
control for the DSM columns, VCC and Vibro stone
columns were by means of materials testing prior to
construction, automatic monitoring and recording of
construction parameters as well as post-construction load
tests.
Under operating load conditions, settlements measured
over a period of 10 months ranged between 5mm and 20
mm for both Cement columns and VCC. A more
comprehensive description of the ground improvement
works carried out on this project and measured settlement
data can be found in the Yee et al (2009).
Olefins Plant on Hydraulic Sandfill (Jurong Island,
Singapore)
Process plants have frequently been founded on
improved ground. The Singapore Olefins Plant in Jurong
Island was constructed in 1998. Vibro Compaction was
carried out for the foundation for the process plant (reactors,
piping, etc.) where the underlying soils were reclaimed
sands. Varying intensities of treatment were adopted to meet
the different requirements in specifications. In general
however, settlements of the steel structures under working
loads had to be restricted to 25-50 mm. Factors of safety
against bearing capacity was to be higher than 2.0. Fig. 10
shows a picture of the Singapore Olefins Plant in operation.
130
V. R. Raju
6. CONCLUSIONS
Ground improvement has developed into a sophisticated
tool to support foundations for a wide variety of structures.
Properly applied, i.e. after giving due to consideration to
the nature of the ground being improved and the type and
sensitivity of the structures being built, ground
improvement often reduces directs costs and saves time. In
Asia, it has been extensively used for the construction of a
wide range of infrastructure and building facilities.
However, careful attention must be paid to quality control
procedures. The focus should not only be on testing after
construction (load testing, etc.), but also on careful
supervision while the work is in progress. Full advantage
should be taken of modern automatic monitoring and
recording of key installation parameters.
ACKNOWLEDGEMENTS
The author would like to thank Jonathan Daramalinggam
and G.T. Senthilnath for their contributions to this paper.
REFERENCES
BS 7777-3: 1993, Flat-bottomed, vertical, cylindrical
storage tanks for low temperature service, Part 3, British
Standards Institution, London, England.
EN 14731: 2005, Execution of Special Geotechnical WorkGround treatment by deep vibration, European
Committee for Standardization, Brussels, Belgium
EN 14679: 2005, Execution of Special Geotechnical WorksDeep mixing, European Committee for Standardization,
Brussels, Belgium
EN 15237: 2007, Execution of Special Geotechnical WorkVertical drainage, European Committee for
Standardization, Brussels, Belgium
Greenwood, D.A., 1991. Load Tests on Stone Columns.
Deep Foundation Improvements: Design Construction
and Testing, ASTM STP 1089, Esrig, M.I. & Bachus,
R.C. (eds.), 148-171.
Holtz, R.D., Shang, J.Q. & Bergado, D.T., 2001. Soil
Improvement, Geotechnical and Geoenvironmental
Engineering Handbook, Rowe, R.K (ed.), 429-462
IS 14268: 1995, Specification for uncoated stress relieved
low relaxation seven ply strand for prestressed concrete,
Bureau of Indian Standards, New Delhi
IS 15284 (Part 1): 2003, Design and Construction of
Ground Improvement- Guidelines, Part 1 Stone
Columns, Bureau of Indian Standards, New Delhi
IS 15284 (Part 2): 2004, Design and Construction of
Ground Improvement- Guidelines, Part 1
Preconsolidation using vertical drains, Bureau of Indian
Standards, New Delhi
131
Kirsch, K. & Sondermann, W., 2003, Ground Improvement,
Geotechnical Engineering Handbook, Volume 2:
Procedures, Smoltczyk, U. (ed.), 1-56.
Moseley, M.P. & Kirsch. K. (eds.), 2004, Ground
Improvement, 2nd Edition.
Raju, V.R. & Sondermann, W., 2005. Ground Improvement
using Deep Vibro Techniques. Ground Improvement
Case Histories, Indraratna, B & Chu., J. (eds.), 601638.
Raju, V.R. & Yee, Y.W., 2006, Grouting in Limestone for
SMART Tunnel Project in Kuala Lumpur, Malaysia,
International Conference and Exhibition on Tunneling
and Trenchless Technology, March 2006, Kuala
Lumpur, Malaysia
Semprich, S., Stadler, G. 2003, Grouting in Geotechnical
Engineering, Geotechnical Engineering Handbook,
Volume 2: Procedures, Smoltczyk, U. (ed.), 57-90.
Sondermann, W & Wehr, W., 2004. Deep Vibro Techniques.
Ground Improvement, 2nd Edition, Moseley, M.P. &
Kirsch, K. (eds.), 57-92.
Yee, Y.W., Chua, C.G., Yandamuri, H.K., 2009, Foundation
works for a Sewerage Treatment Plant using Ground
Improvement Methods in Malaysia, Ground
Improvement Technologies and Case Histories, C.F.,
Chu, J., Shen, R.F. (eds), 677- 683