Professional Documents
Culture Documents
Zones)
Mid-Term Evaluation
Madagascar Environment Programme (EP 3) Support Project GEF/UNDP
Final Draft, 22 June 2008
___________________________________________________________________________
Table of Content
Acronyms and terms .............................................................................................................................................. 3
Acknowledgements................................................................................................................................................ 4
EXECUTIVE SUMMARY..................................................................................................... 5
1. Introduction..................................................................................................................................... 8
1.1.
Purpose of the evaluation......................................................................................................................................8
1.2.
Key issues addressed............................................................................................................................................8
1.3.
Methodology of the evaluation..............................................................................................................................8
1.4.
Structure of the evaluation.....................................................................................................................................9
2. The project and its development context...........................................................................10
2.1. The joint WB/UNDP GEF project in Madagascars development and environment policy context................10
2.2. The PA-PASZ concept & pilot areas.........................................................................................................................10
2.3. Project key information................................................................................................................................................11
2.4. The UNDP component................................................................................................................................................12
3. Findings and Conclusions............................................................................................. 18
3.1.
Results....................................................................................................................................................................18
3.2.
Project formulation (and implementation)..........................................................................................................28
3.3
Implementation......................................................................................................................................................32
4. Recommendations...................................................................................................... 33
4.1. Top priority recommendations for immediate management action......................................................................33
4.2. Priority strategic performance areas and operational recommendations...........................................................34
5. Lessons learned......................................................................................................... 48
Annexes..................................................................................................................... 49
ANNEX 1: TOR....................................................................................................................................................................50
ANNEX 2: List of key documents reviewed.....................................................................................................................56
ANNEX 3: List of persons interviewed.............................................................................................................................58
ANNEX 4: Consultation methodology, incl. questionnaire/guidance used.................................................................60
ANNEX 5: Recommendations from 1st Year Evaluation................................................................................................65
ANNEX 6: Itinerary..............................................................................................................................................................70
ANNEX 7: Summary of evaluation work sessions (site visits) .....................................................................................71
ANNEX 8: Reference site summaries concept...............................................................................................................78
ANNEX 9: Assessment: Performance on project objective and results......................................................................83
ANNEX 10: Knowledge/Awareness baseline concept.................................................................................................100
ANNEX 11: Capacity needs self-assessment elements concepts.............................................................................101
ANNEX 12: Draft brochure concepts (for decision makers; project promotional)...................................................102
ANNEX 13: Photo library concept...................................................................................................................................107
Acknowledgements
Over 200 interviews and consultations took place during the evaluation process. All participants are thanked for their enthusiastic, engaging
and critical inputs, without which this evaluation would not have been possible. A thank you is extended to all facilitators from SAGE, who
ensured that all local and regional consultations were successful. The entire evaluation team is thanked for organising my visit so well and for
accompanying me to the regions. The team members of the Project Management Unit, Hanta Hanta Rabefarihy, Helivelo Ramamonjison,
Vololona Rakotarinina and Teddy Rakotondrazafy are thanked for their excellent support. Patricia Ramarojaona of the Environment Unit at the
UNDP Country Office provided invaluable facilitation. All other team members, interviewees and otherwise involved partners are
acknowledged.
EXECUTIVE SUMMARY
Background to evaluation and project concept
This evaluation is conducted at mid-term evaluation of the project implementation according to GEF rules and is
an integral part if the project cycle. The evaluation is commissioned by the United Nations Development
Programme (UNDP) Country Office in Madagascar, on behalf of the project Executing Agencies Coordination
Unit/Cell for the 3rd Environment Programme (EP3) (CELCO) (for the Ministry of Environment, Water, Forestry and
Tourism; MEEFT) and UNOPS. The evaluation analyzes the achievements of the project against its original
objectives. The evaluation considers the effectiveness, efficiency, relevant, impact and sustainability of the project.
It further identifies factors that have facilitated or impeded the achievement of the objectives. This evaluation has
been conducted further to a first support mission, which was completed in 2006.The evaluation has a strong focus
on developing recommendations and lessons learned to assist in defining the future direction of the project,
during the remaining project period of approximately 2 years. The evaluation was conducted in a participatory
manner, and over 200 persons were involved in the assessment of achievements, setting priorities and devising
recommendations for future action. Beneficiaries in the local project intervention areas, members of the various
governance structures established through the project (so-called Platforms as well as Steering Committees at
regional and national level), and national level project partners were consulted. Further a great number of project
related documents were reviewed.
The UNDP/GEF support is integral part of Madagascars EP3, a comprehensive country strategy and programme,
which, amongst other, sets the goal of establishing a significant number of new protected areas (component 2 of
EP3). This project, together with the associated World Bank (WB)/GEF support under the same GEF overall
biodiversity support project, assists in the establishment of four new protected areas (PA) (in French: AP),
exploring co-management and Natural Resoruces Management models with communities situated in so-called
Bufferzones/Support Zones around the PAs (in French: ZAAP). Further, the GEF support assists with the
mainstreaming of Sustainable Natural Resource Management (SNRM) models developed under component 2
into policy processes (component 3 of EP3).
Summary evaluation assessment
The evaluation of project achievements to date have been assessed against the initial project design, as laid out
in the Project Document of 2004, and refined during a First Year Evaluation, conducted in 2006. Based on 22
indicators developed in the Monitoring & Evaluation (M&E) Plan of the project progress in implementation was
assessed. Eleven of the 22 indicators measure progress towards achieving the overall project objective, and the
other 11 indicators measure progress towards achieving the results set out in the original project design. The
progress towards results is rated using standard GEF scales, as follows: HS highly satisfactory, S satisfactory,
MS marginally satisfactory, MU Marginally unsatisfactory, U unsatisfactory. HU highly unsatisfactory.
Development Objective 11: The biodiversity and renewable natural resources of representative eco-regions is
conserved and managed on a sustainable footing with active multi-stakeholder participation; and
Development Objective 2: The systemic framework for sustainable environmental management is further
strengthened through the incorporation of said management objectives into public policy making and investments
[In French : Objectif de dveloppement du projet : La gestion des ressources naturelles et la protection de la biodiversit dans les corgions
critiques sont tablies sur des bases relles et durables avec la participation active des populations locales et des autres parties concernes,
en mme temps que les dimensions environnementales sont effectivement intgres dans la prise de dcisions politiques et les dcisions
dinvestissement.]
Project objective2: Sustainable Natural Resource Management Systems established and strengthened in
Protected Area Support Zones (PASZ/ZAAP)
[In French: Objectif immdiat du projet : Des systmes de gestion durable des ressources naturelles sont tablis et renforcs dans les zones
dappui aux aires protges.]
1
2
Set out in original joint WB/GEF UNDP/GEF ProDoc, as well as French UNDP/GEF ProDoc, based on EP3.
See PIRs 2006 and 2007.
valuation
2006
valuation
2008
Motivation/ comments
MS
MU
MU
MS
HU
No progress
HU
HU
No progress
Rsultat 5
Le partage des connaissances relatives la GDRN
auprs des parties prenantes contribue amliorer
lefficacit et la durabilit de la gestion
Overall evaluation assessment/valuation globale MU
U
du projet
HS highly satisfactory, S satisfactory, MS marginally satisfactory, MU Marginally unsatisfactory, U unsatisfactory. HU highly
unsatisfactory
In summary it is noted that the project is performing below standard at this stage, and decisive mitigative
interventions are required to ameliorate project implementation during the remaining project period. It is further
noted that at this stage more than 67% of the original budget are still available, as well as some additional funds
that were allocated to the project. The enabling environment to intensify project activities is provided.
The originally agreed to outcomes as set out in the ProDoc are used; it is noted that several iterations of reformulation took place (see e.g.
PIR 2007), however the evaluation suggests to revert to the original for coherent referencing and M&E. It should be noted that the objectives
and outcomes are part of the contract between the Government of Madagascar and the GEF and can only be modified after approval from the
GEF; a resubmission of documentation is required.
Summary of Recommendations
A set of seven summary recommendations are made for immediate guidance on project management (see Box 1,
below). Additionally, Section 4 contains a suite of operational recommendations, that have been developed based
on the consultative performance assessment and they are aimed at supporting the effective implementation of the
project from mid-term onward. The 23 operational recommendations are aligned according to three overall
strategic performance areas: A. Vision, Structure & Management, B. Communication, Capacity Building,
Knowledge Management & the Role of Science and Research, and C. The Priority: Implementation at Regional
and Local Levels.
Box 1: Top priority recommendations for immediate management action
Despite poor project performance at mid-term, the recently strongly demonstrated want of national ownership and willingness to improve on
project performance by key players such as MEEFT, related regional structures, regional governments and ANGAP are recognised as a
strong foundation for performance improvement. This commitment forms the basis for the following key recommendations from the
evaluation:
1.
It is recommended to continue project implementation, given that strategic and operational recommendations stemming from the
mid-term evaluation are positively acted upon.
2.
It is recommended to request a 3 year no-cost extension for the PA-PASZ pilot project
a.
68% of funds are still available at mid-term (excl. a supplementary amount of US$ 500,000 availed through UNDP
additionally)
b.
The final time horizon will depend on how fast the project can be realigned (incl. by when a TA can be hired)
3.
A Technical Advisor has to be hired as a matter of urgency to help bring the project on track. Such a position should be advertised
nationally, if available, and internationally. The TA would be a SNRM expert with a track record of strong capacity building [skills],
which would be applied to the MEEFT and the PMU staff, in particular and would aide build a longterm sustainability element into
the project implementation phase.
4.
The evaluation found that the initial project design is still responsive to the key PA-PASZ and SNRM problematic and it is thus
recommended to retain the design framework. Implementation elements can be adjusted in the context of adaptive planning,
and re-phased in line with the request for a 3 year no-cost extension. The TA shall take leadership in such a process and guide
the country team. It is recommended that the overall project objective, the five outcomes and the major project in dicators (22 +2) will
be retained when re-phasing the project. Certain indicators might benefits from minor revisions. Potentially the outputs should be reviewed
with the support of the TA. Esp. outputs 2.2 and 2.3 seem major and should be further unpacked.
5.
It is further advised to install a policy expert TA at senior level of MEEFT, to aide the full integration of the PA-PASZ and SNRM
concepts into Government policy making, [and the up-scaling of the piloting results and integration into a systematic policy
process,] amongst other.
6.
It is critical to tighten the coordination of SNRM work in the PACZ and PA work under an integrated vision; it is proposed that this
vision be furthered between MEEFT and ANGAP, and then be shared and furthered with all project partners.
7.
It is recognised that the key implementation activities have to be carried out at the local and regional level. It is therefore
recommended to decentralise project coordination aspects to the regional level, including a certain level financial authority, to
ensure more responsive management of project affairs. The following points should be taken into consideration, amongst other:
a.
A strategy for decentralised implementation of the project is needed; such a strategy has to be developed in a
participatory manner with all key stakeholders and with potential implementation partners
b.
It needs to be recognised that this project is of piloting nature; thus the prerogative is to utilise a lean and effective
implementation arrangement that allows for best performance during a very limited project implementation period;
capacity support for longterm sustainability shall be considered as part of the project strategy, however cannot lead to
sacrificing the piloting success
c.
A tiered implementation approach is recommended, including a strong prioritisation of key activities to be tested and
implemented at local level; the current number of project sites (reference sites and Community Based Organisations
(CBOs/CLBs)) seem to be too large to ensure effective project implementation.
Site selection should be revisited and based on the needs of the PA-PASZ concept, under the leadership of ANGAP.
d.
e.
Considering the relatively short life-time of the project, and recognising its piloting nature, practical implementation
mechanisms are sought for. Regional and PA-PASZ specific differences need to be taken into account when planning
such mechanisms. It is recognised that different approaches may be taken for each PA-PASZ, based on the peculiar
contexts of each of the PA-PASZs. The capacity of Government extension (CTD) is rated to be currently low; it is
recommended to install intermediaries such as SAGE or other institutions (other national or international NGOs, e.g.
Fanamby, church based networks or other) to aide the successful testing of the pilot approaches. Relevant capacity
support to such organisations shall be provided by the project and other players.
1. Introduction
1.1. Purpose of the evaluation
According to UNDP/GEF rules and in line with the M&E plan outlined in the Project Document (ProDoc), a midterm evaluation of the project implementation to date has been scheduled for early 2008, and is an integral part if
the project cycle. The evaluation is commissioned by the UNDP Country Office in Madagascar, on behalf of the
project Executing Agencies Coordination Unit/Cell for the 3 rd Environment Programme (PEIII) (CELCO) (for the
Ministry of Environment, Water, Forestry and Tourism; MEEFT) and UNOPS.
As indicated in the Terms of Reference of this assignment (ANNEX 1) the evaluation analyzes the achievements
of the project against its original objectives. The evaluation considers the effectiveness, efficiency, relevant,
impact and sustainability of the project. It further identifies factors that have facilitated or impeded the
achievement of the objectives. This evaluation has been conducted further to a first support mission, which was
completed in 2006. The current evaluation assesses to what extend the recommendations of this support mission
in 2006 have been followed. While a thorough assessment of the progress of implementation to date is important,
the evaluation has a strong focus on developing recommendations and lessons learned to assist in defining the
future direction of the project, during the remaining project period of approximately 2 years according to initial
project schedule.
1.2. Key issues addressed
Amongst the key issues addressed during the evaluation are:
Participatory assessment of project implementation results and barriers at national, regional and
local level since project inception; (overall there seems to be a lack of communication so that local and
regional level achievements and concerns are not readily recognised on the national level)
representation of Regional Government and Line Ministries esp. DREEFT, ANGAP; overall facilitation and
participation by SAGE.
(d) Consultative meetings and semi-structured working sessions at regional level, with local level
representation (with various project structures such as various Platforms)
Field visits to the northern and southern project area respectively were conducted. The itinerary of the regional
and local level consultations and visits is provided in ANNEX 6. Meetings were organised and facilitated by SAGE,
the local and regional project implementation and facilitation agent 4, and a primary project partner. All meetings
were conducted in Malagasy and translated into French either personally or to the group. The motivation was to
allow representatives of the various project structures to provide inputs into the evaluation, aide in participatory
assessment and problem identification, and prioritisation for future project action. The evaluation concept
including the design of the regional and local consultations is included in ANNEX 4.
(e) Local level facilitated consultations and site visits
Visits to project partner CBOs/CLBs and communities were included in the itinerary to be able to visualise project
impact at that level and to exchange information relevant for the evaluation, including the establishment of a
general awareness baseline. A selected and limited number of CBOs/CLBs near primary reference sites were
visited. All consultations were facilitated by SAGE and conducted in Malagasy and translated into French.
(f) Feedback meetings
Individual feedback meetings after the various national, regional and local level consultations were conducted, i.e.
with the evaluation core team, with the Secretary General (SG) of MEEFT, the Assistant Secretary General (DGA)
and Director of Operations of ANGAP, the Resident Representative (RR) and his Deputy (DRR) of UNDP and the
Director of SAGE. Further a report back meeting was scheduled at the last day of the mission, and the draft
findings from the evaluation were presented to regional representatives and project partners, and discussion
points are reflected in the evaluation report.
(g) 2-day verification and planning workshop
An in-depth feedback meeting and planning session was scheduled by MEEFT for the 16 & 17 June 2008. The
key findings from the evaluation were presented and discussed at the meeting, however the time for the
evaluation verification was limited.
1.4. Structure of the evaluation
The evaluation report sets out first a comprehensive project description, as information available has been
very general and not updated in detail based on the adaptive planning and implementation approach applied in
the project. For the benefit of all stakeholders concerned with the project, reviewing and using the evaluation
report section 2 describes the project and illustrates e.g. implementation arrangements in some detail. It contains
a translation of the higher tier project design objective outcomes outputs indicators in French and English.
Section 3 provides the performance assessment results / key findings of the evaluation. Firstly an overview of
key activities implemented to achieve project results/outcomes is provided, mainly based on the desk top review
and enriched by the information gathered form the consultations of stakeholders and project partners at all levels.
Performance as per indicator (there are about 22 indicators identified for this project) is also assessed, based on
the same set of information sources. Action gaps and priority activities for future implementation are indicated.
Based on the evaluation guidelines, performance is rated and ratings are motivated. If and how recommendations
made in an earlier evaluation (1 st Year Evaluation, 2006) were addressed in project implementation and how these
actions/inactions impacted on project was added to the assessment as per ToR.
Special emphasis is on section 4 which presents the major recommendations for the amelioration of project
implementation and performance. Recommendations are made on a strategic and operational level. It should
be noted that a great deal of effort has been made to provide tangible recommendations and examples for action,
as this seems to be a key need for successful project implementation. Additionally the specific requests made by
the Minister at the onset of the evaluation indicated that these points should be examined carefully to allow for
unbiased and practical recommendations to be made. The recommendations are to a largely based on the self4
It needs to be mentioned that SAGE currently has no long-term contract with the project and the support to the evaluation visit was
scheduled and contracted separately from other project responsibilities.
identification of solutions and amelioration priorities identified by project partners at local, regional and national
level.
Section 5 contains lessons learnt, both best practices and case examples of approaches that were unsuccessful,
to allow future programming of GEF to be improved, not necessarily in a Madagascar specific context. The
Annexes contain a rich set of background information and specific examples of work outputs relevant to the
project.
2. The project and its development context
The project under review constitutes one part of a joint GEF funded initiative with one WB and another UNDP
implemented project component, respectively. Although the evaluation is concerned with the UNDP project
component, it is important to present the GEF project in its entirety.
2.1. The joint WB/UNDP GEF project in Madagascars development and environment policy context
Madagascar, over the past years, has followed a systematic approach to improving environmental management,
through its integrated national Environment Programme (EP), which is currently in its third phase (EP3). The GEF
support for EP3 was formulated based on the lessons learnt from EP2 and emerging priorities for the next
implementation phase. The well formulated EP3 sought funding from a number of donors, and together attracted
significant donor commitment.
EP3 is a very comprehensive country strategy, and, amongst other, sets the goal of establishing a significant
number of new protected areas/ bringing a significant area of threatened ecosystems under formal protection
(through the establishment of the protected areas) (component 2 of EP3). The mainstreaming of SNRM models
into policy processes is a complimentary priority (component 3 of EP3). Both components are being addressed by
the joint WB/UNDP implemented GEF support (see section 2.3. below).
The GEF contribution to EP3 has been prepared under Focal Areas Biodiversity, Operational Programmes (1)
Arid and Semi-Arid Zone Ecosystems, (2) Coastal, Marine, and Freshwater Ecosystems, and (3) Forest
Ecosystems. Strategic Priority One Catalyzing Sustainability of Protected Area Systems at National Levels and
Strategic Priority Two Mainstreaming Biodiversity in Production Landscapes/Seascapes and Sectors are
addressed.
2.2. The PA-PASZ concept & pilot areas
As for the establishment of new Protected Areas, the Government of Madagascar is testing various comanagement arrangements that would support the effective conservation of biodiversity and natural resources.
Protected Areas (PAs; or in French Aires Protges (AP)) are surrounded by a immediate conservation fringe
(Zone tampoon), and a large Bufferzone (in French Zone dAppui de AP (ZAAP) 5). Whereas no people live in the
demarcated AP, local population inhabits the buffer zones. Through a strong association between the AP and
ZAAP, resources in the buffer zone are managed in a sustainable and biodiversity-friendly manner by the
communities, promoted through incentive measures. The WB component of the GEF project focuses on
supporting the establishment of the new AP, whilst the UNDP component invests into capacity building and
support activities in the ZAAP (Figure 1). Of course both components have a high degree of interaction and are
interdependent.
For the purpose of the report the French abbreviation is used primarily.
10
Figure 1: Concept PA-PASZ (AP-ZAAP) and WB and UNDP component support focus in each area respectively, and
collaborative interaction. The inner light blue shaded area is the PA core area, whilst the larger area demarcated by the blue
line depicts the PASZ. The yellow doted line illustrates that the two GEF project components of WB and UNDP respectively
ought to be implemented in a collaborative manner.
Four PA-PASZ (AP-ZAAPs) are included in the project as pilot areas, covering a suite of priority ecosystems to
conserve and with characteristic ecological, socio-economic baselines, covering terrestrial and marine and coastal
habitats.
A. SOUTH
(1) AP Mikea
(2) APMC Toliara/Nosy-Ve
B. NORTH
(3) APMC Sahamalaza/Iles Radama
(4) APMC Lokobe/Nosy Tanikely
A more comprehensive design for the description of the four PA-PASZs and their respective reference sites
(see Section 2.4.2) is included in ANNEX 8, and will be finalised by the PMU.
2.3. Project key information
A few project key information points include:
Financing:
Joint coordination:
Intended implementation
period:
11
2.2.1. Development of models for coastal and marine ecosystems and mangrove systems
2.2.2. Development of models for the management of the Western Dry Forests Dry/Spiny Forest ecotone
EP 3 Component 3: Environmental Mainstreaming
Sub-Component 3.1. Mainstreaming (WB)
3.1.1. Environmental Information, Education and Communication
3.1.2. Environmental Legislation, Policy Making and Regulations
3.1.3. Environmental Compliance
3.1.4. Environmental Management and Coordination
Sub-Component 3.2.: Knowledge Management for SNRM (UNDP)
[In French : Sous-Composante 3.2. Gestion des connaissances focus GDRN]
3.2.1 Knowledge management for field practitioners
3.2.2 Knowledge application in policy making
2.4. The UNDP component
The specific UNDP component is described in some more detail in the following.
2.4.1 Project Design
Development Objective 16: The biodiversity and renewable natural resources of representative eco-regions is
conserved and managed on a sustainable footing with active multi-stakeholder participation; and
Set out in original joint WB/GEF UNDP/GEF ProDoc, as well as French UNDP/GEF ProDoc, based on EP3.
12
Development Objective 2: The systemic framework for sustainable environmental management is further
strengthened through the incorporation of said management objectives into public policy making and investments
[In French : Objectif de dveloppement du projet : La gestion des ressources naturelles et la protection de la biodiversit dans les corgions
critiques sont tablies sur des bases relles et durables avec la participation active des populations locales et des autres parties concernes,
en mme temps que les dimensions environnementales sont effectivement intgres dans la prise de dcisions politiques et les dcisions
dinvestissement.]
Project objective7: Sustainable Natural Resource Management Systems established and strengthened in
Protected Area Support Zones (PASZ/ZAAP)
[In French: Objectif immdiat du projet : Des systmes de gestion durable des ressources naturelles sont tablis et renforcs dans les zones
dappui aux aires protges.]
Table 1 : Project EP3 sub-component, outcomes and outputs to be attained over project period
Outcomes
Outputs8
SUB-COMPONENT 2.2
Outcome 1:
SNRM and biodiversity conservation are
improved by their full integration into
development planning in PA Support
Zones through stakeholder participatory
planning structures (fora) and other
means
1.1 Platforms that bring together stakeholders and serve joint planning and conflict resolution are
established and operational
Rsultat 1
La GDRN et la conservation de la
biodiversit sont amliores dans les
zones dappui aux aires protges par
leur intgration dans la planification du
dveloppement
1.2 Des plans de dveloppement des ZAAP plusieurs niveaux intgrant la gestion des AP, la
conservation de la biodiversit et la GDRN sont utiliss comme cadre de planification pour les
financements du PE III et du dveloppement rural.
Outcome 2:
Measures to ensure biodiversity
conservation and productive SNRM
developed in the field reference sites are
replicated and adapted in the PASZs
2.1 Approaches (guides) for the development of SNRM measures, based on scientific
knowledge, are developed, tested, applied and up-scaled (transposed).
Rsultat 2
Les approches dveloppes dans les
sites de rfrence de terrain pour dfinir
les mesures appropries de conservation
de la biodiversit, de GDRN et pour le
dveloppement de filires de biodiversit
durables et rentables, sont reproduites
dans les zones dappui aux aires
1.1 Des plates-formes runissant les diverses parties prenantes et servant la planification et
la rsolution des litiges sont mises en place ou amliores et sont oprationnelles
1.2 PASZ Development Plans integrate PA management, biodiversity conservation and SNRM,
and are used as framework for financial planning of EP3 and rural development.
2.1 Des approches (guides) pour la conception de mesures de GDRN sur la base de
connaissances scientifiques sont conues, appliques, mises au point et transposes
2.2. Local/community level resource managers understand and adopt the adaptive SNRM
approaches.
2.2 Les gestionnaires de ressources au niveau communautaire comprennent et adoptent
lapproche adaptative de la GDRN
2.3 Biodiversity-product based businesses operate under cost-recovery and generate revenue
creating incentives for SNRM.
2.3 Des entreprises travaillant sur les produits de la biodiversit gnrent des revenus qui
incitent la gestion durable des ressources naturelles et en couvrent les cots.
13
Outcomes
Outputs
2.4 Sustainable management methods for commercially-used Wild Species are developed,
tested and applied in a participatory manner with local/community level resource managers.
protges
2.4 Des approches pour dterminer des mesures de gestion rationnelle pour les espces
sauvages qui font lobjet de commercialisation sont conues, appliques et mises au point avec
les gestionnaires communautaires
Outcome 3:
Participatory management systems for
marine and coastal protected areas are
improved through the integration of SNRM
principles
3.1 Participatory MCPA management plans, based on best scientific and technical knowledge,
are elaborated.
Rsultat 3:
Les systmes de gestion participative des
aires protges marines et ctires sont
amliors grce lintgration des
mesures de GDRN
3.1 Des plans de gestion participative des APMC bass sur les meilleurs apports
scientifiques et techniques sont labors
3.2 Representative partner CBOs/CLBs that work together with ANGAP in the management of
MCPAs are trained to use and apply adaptive management (SNRM) principles.
3.2 Les institutions communautaires qui participent avec lANGAP la gestion des APMC et
qui sont reprsentatives sont formes utiliser des principes de gestion adaptative
SUB-COMPONENT 3.2.
Outcome 4:
SNRM knowledge production contributes
to efficient management of natural
resources in Madagascar
Rsultat 4 :
La production de connaissances amliore
lefficacit de la gestion des ressources
naturelles Madagascar
4.1 Knowledge and awareness needs pertaining to SNRM in Madagascar are assessed,
covering SNRM knowledge of all major natural ecosystems.
4.1 Les besoins essentiels en matire de connaissances pour le dveloppement de la GDRN
sont dfinis travers une tude de qualit portant sur ltat de la GDRN dans les principaux
cosystmes naturels Madagascar
4.2 A system and a network allowing the systematic collection and the analysis of the SNRM
related data in Madagascar are set up and are operational.
4.2 Un systme et un rseau permettant la collecte et lanalyse systmatiques des donnes
relatives la GDRN Madagascar sont mis en place et sont oprationnels
Outcome 5:
Sharing the knowledge relative to SNRM
among the stakeholders contributes to
efficient and sustainable management
5.1 A Knowledge Sharing system on SNRM has been set up and is operational, for use by
practitioners.
Rsultat 5
Le partage des connaissances relatives
la GDRN auprs des parties prenantes
contribue amliorer lefficacit et la
durabilit de la gestion
5.2 A communication system for the preparation and distribution of SNRM information packages
for decision makers at national, regional and local levels is established.
5.1 Un systme de partage des connaissances en matire de GDRN entre les praticiens est
mis en place et est oprationnel
14
Figure 2: Partnerships and project stakeholder interaction on PA-PASZ level; SAGE and ANGAP are the two primary
facilitators of the PA-PASZ (AP-ZAAP) concept, however other service providers are involved in project implementation.
Thirteen reference sites and a greater number of associated CBOs/CLBs have been established/ are engaged in the pilot
project.
Figure 3: Maps depicting the newly established / to be established Pas and selected reference sites in the pasz. It is to be
noted that a suite of new and additional reference sites has been suggested recently by ANGAP, as the final demarcations of
the PAs have been changing, and project implementation has to be needs-based.
15
Figure 4: The national level implementation and coordination arrangements for the UNDP component of EP3.
these structures that ought to be the primary implementation mechanism for SNRM approaches in the AP-ZAAPs
(see Section 2.4.4.), and the governance approach is an integral part of the SNRM models to be tested and
established during the UNDP project phase.
Figure 5: The decentralised local and regional level implementation arrangements, facilitated by SAGE.
17
Figure 6: Visualisation of local level activities that should be integral part of the SNRM models to be developed and tested in
the four PA-PASZ pilot areas of the project.
18
Project Objective : Sustainable Natural Resource Management Systems established and strengthened in
Protected Area Support Zones (PASZ)
[In French : Objectif du projet : Des systmes de gestion durable des ressources naturelles sont tablis et renforcs dans les zones dappui
aux aires protges.]
Indicators9
Baseline
Target
Indicator 1:
BD compatible SNRM mainstreamed in the
development plans in PASZ
At least one
fully
functioning
multistakeholder
platform with
capacities for
integrated
development
planning exist
for each PASZ
Strategies for
improved
enforcement &
oversight of
SNRM related
laws/
regulations are
completed for
each PASZ
Isolation of Pas
surrounded by
forest, bush
field or
severely
degraded
ecosystems
that are not
ebing allocated
to conservation
compatible
land uses
Participatory
planning and
joint
management
of PASZs
2,209 km2
2,209 km2
Indicateur 1:
La gestion durable des ressources naturelles
compatible avec la conservation de la biodiversit
est intgre dans les plans de dveloppement des
zones dappui aux aires protges.
Indicator 2 :
SNRM legal and institutional framework set up
Indicateur 2:
Les cadres lgal et institutionnel de la gestion
durable des ressources naturelles sont tablis
Indicator 3 :
Conservation plans developed and implemented
Indicateur 3:
Les plans de conservation sont dvelopps et mis
en uvre
Indicator 4 :
Mangrove cover in the 2 project priority zones
maintained at 2004 area of 2,209 km2 level
Weak
institutional
capacity and
serious
governance
issues
in 2004
Indicateur 4:
La superficie couverte par les mangroves dans les 2
zones dintervention du projet est maintenue au
niveau de celle de 2004 correspondant 2 209 km2
[ADDED in 2006: 4a.The surface within the PA and
the dry and spiny forests in the PASZ is maintained
at the 2006 level.
4b. The rate of recovery of living coral is maintained
at the 2006 level in the southern and northern area
of the project.]
The PIR 2006 establishes baseline levels and target levels for all indicators; additional indicators and their baseline and targets were
included in the PIR 2007; current indicator 7 was newly introduced in PIR 2007
10
Progrs ralises au Mai 2008 base sur le rapports PIR, APR, consultations au niveau national, rgional et locale, et vrification avec
lquipe dunit de gestion (coordinatrice), SAGE et PNUD. The full assessment table is presented in ANNEX 9.
19
Indicators
Indicator 5 :
Difference in presence and/or abundance of
indicator species from the upper levels of the food
chain such as large predatory species of the
Lutjanidae family
Baseline
Target
Indicateur 6:
La prsence/absence despces indicatrices
(maintenue, accrue ou diminue selon le type
despce indicatrice) dans les sites o la
conservation et la GDRN sont mises en oeuvre
(indicateur dfini sur la base des recommandations
des scientifiques)
Indicator 7 :
Improvement of the global efficiency index of 4
protected areas supported by GEF (Ref. ANGAP)
ANNEX 9
ANNEX 9
Indicateur 5:
Lvolution dans la prsence et/ou labondance
despces indicatrices au sein des niveaux
suprieurs de la chane trophique, telles les
espces prdatrices de grande taille de la famille
des Lutjanidae
Indicator 6 :
Presence/absence of indicator species (maintained,
increased or decreased depending on the type of
indicator species) in the sites where SNRM is
implemented (based on recommendations from
scientists)
ANNEX 9
ANNEX 9
ANNEX 9
ANNEX 9
Indicateur 7:
Amlioration de lindice defficacit globale de
gestion des 4 aires protges appuyes par le FEM
Indicator 8 :
Number of households deriving income from wild
resource harvests participating in sustainable
natural resource management in the two target
zones
3,000
households
21,500
households
Indicateur 8:
Nombre de mnages dont les revenus proviennent
de la collecte de ressources sauvages et qui
participent la gestion durable des ressources
naturelles dans les deux zones cibles du projet
20
Indicators
Baseline
Target
Indicator 9 :
Improved voice of communes in protected areas
management through fully operational collaborative
management structures as represented by the
percentage of COSAP complying with their rights
and obligations as defined in PA management plans
0%
80%
0%
80%
0%
70%
Indicateur 9:
Prise en compte de la position des communes dans
la gestion des aires protges travers des
structures de gestion participative pleinement
oprationnelles, illustr par le pourcentage de
COSAP qui respectent leurs droits et obligations
tels que dfinis dans les plans de gestion des aires
protges
Indicator 10 :
Improved community empowerment in SNRM
through fully performing GELOSE/GCF
arrangements as measured by the % of
communities benefiting from transfers who have
successfully protected their resources at the end of
the 3-year trial period as determined by the
evaluations scheduled before renewing the
contracts
Indicateur 10:
Renforcement des communauts en GDRN
travers la pleine excution des dispositions
GELOSE/GCF, tel que mesur par le % des
communauts ayant bnfici de transferts et qui
ont protg leurs ressources avec succs la fin de
la priode de probation de 3 ans. Le succs de la
protection des ressources est dtermin lors des
valuations programmes avant le renouvellement
des contrats
Indicator 11 :
% of users who judge SNRM knowledge
management services/ products as meeting their
requirements
Indicateur 11:
% des utilisateurs qui considrent que les services
et produits pour la gestion des connaissances en
GDRN rpondent leurs besoins
Progress indicators towards achieving the overall project objective can show that certain activities have taken
place, however overall performance has been very limited. It should be noted that the established project design
and M&E plan are useful, however could be improved. Especially the formulation of certain baseline and target
values is a bit problematic. However, at mid-term of the project the focus cannot be planning any more. Practical
improvements that can be done without major disruption of implementation can be made, however it is
recommended to use the design and M&E framework as a management tool, not a means in itself. As long as the
vision for the project is clear amongst all stakeholders, focused implementation will take place and disagreements
on decision-making will be negligible. Improved leadership on the management level will also aide.
21
Table 3. Progress of project in terms of outcomes (11 indicators); basis for evaluation rating
Indicator11
Baseline
Targets
Achievements by 31 Mai 200812
Outcome 1: SNRM and biodiversity conservation are improved by their full integration into development planning in PA Support Zones through
stakeholder participatory planning structures (fora) and other means
Indicator 12 :
There exist:
At least 1 multi-stakeholder
Rating
11
12
Progrs ralises au Mai 2008 base sur le rapports PIR, APR, consultations au niveau national, rgional et locale, et vrification avec
lquipe dunit de gestion (coordinatrice), SAGE et PNUD. The full assessment table is presented in ANNEX 9.
22
Indicator
Indicator 14 :
Number of community based
management structures (VOI)
implementing sustainable and
profitable SNRM measures that
contribute to biodiversity
conservation in each
ecosystem, in addition to the
communities already active in
the 13 field reference sites.
Indicateur 14:
Nombre de structures de
gestion communautaires qui
mettent en oeuvre des mesures
durables et rentables de
gestion des ressources
naturelles qui contribuent la
conservation de la biodiversit
dans chaque cosystme, en
plus des communauts
concernes par les 13 sites de
rfrence de terrain
Indicator 15 :
Forest cover loss rate in the
protected area support zones is
decreased as compared to
trends observed for the
reference period.
[Expanded to other ecosystems
see ANNEX 9 and indicator 4]
Indicateur 15:
Diminution du taux de perte de
couverture forestire dans les
zones dappui aux aires
protges relativement aux
tendances observes pour la
priode de rfrence.
[
Baseline
- 6 of the coral reef
laboratories have
established basic rules
(dina) to put an end to
destructive practices
- 2 laboratories in
mangroves have simple
community based
management systems
- some of the
laboratories in the forests
have simple zoning plans
Targets
Management plans and
systems for biodiversity
compatible SNRM systems
are in place in replication
(pilot) sites
23
See Indicator 4
Rating
Indicator
Indicator 16 :
The presence or absence of
ecosystem health indicator
species in the SNRM field
reference sites.
Baseline
Absence of reliable
scientific data on
indicator species
Targets
The presence of indicative
species for the target
ecosystems is verified.
Presence maintained for
health ecosystem indicator
species on all field reference
sites.
Rating
Indicateur 16:
Prsence ou absence
despces indicatrices de la
sant cologique dans les sites
de rfrence de GDRN
Overall evaluation of Outcome 2
MU
Outcome 3: Participatory management systems for marine and coastal protected areas are improved through the integration of SNRM principles
Indicator 17 :
There are only plans
Co-management plans for
24
Indicator
Indicator 19 :
A knowledge management
support system that collects
and analyses economic,
ecological, social & technical
information on SNRM for major
biomes is functional & effective.
Indicateur 19:
Un systme de gestion des
connaissances permet de
rassembler et danalyser les
informations conomiques,
cologiques, sociales et
techniques relatives la GDRN
pour les principaux
cosystmes de Madagascar.
Indicator 20 :
Adequate information and
knowledge are gathered that
enable the adaptation of
practical and sustainable SNRM
models in the main natural
ecosystems of Madagascar
Indicateur 20:
Suffisamment dinformations et
de connaissances sont
accumules pour permettre de
transposer les approches
permettant de concevoir des
mesures de gestion durable et
rentable des ressources
naturelles dans les principaux
cosystmes naturels de
Madagascar.
Baseline
A fairly large number of
field practitioners are
working on SNRM
throughout the country,
but without systems
which are organized for
knowledge generation
and sharing
Targets
A national facility for
collecting, analyzing, and
distributing SNRM related
knowledge for practitioners
and decision makers is
established & effective.
Inadequate knowledge
on sustainable natural
resource community
based management
among the stakeholders
at various levels,
regarding the coral reefs,
the lagoons, the spiny
forests, the mangroves,
and the other natural
ecosystems in
Madagascar.
25
Rating
HU
Indicator
Indicator 22:
% of policy and decision
makers who have basic
understanding of SNRM issues
(as determined through
sampling surveys)
Baseline
No survey has been
conducted, but findings
reveal inadequacy of
communication on
SNRM towards decision
and policy makers
Indicateur 22:
% de responsables de
politiques et de dcideurs qui
ont une comprhension de
base des questions de GDRN.
Targets
Mainstreaming of SNRM
objectives in the strategy
documents for the
development of the country
Eight policy briefs prepared
each year on key issues
related to SNRM.
The estimated number of
policy & decision-makers
reached thro a variety of
communications media
increases each year.
Rating
HU
Note: Project progress is assessed according to the following categories: HS highly satisfactory, S satisfactory, MS marginally
satisfactory, MU Marginally unsatisfactory, U unsatisfactory. HU highly unsatisfactory
The progress evaluation as per result is based on various information sources and assessed against the
performance so far towards reaching the goal, keeping the remaining project time frame in mind. Reference is
made to planned outputs (in French: sous-rsultats) (see Table 1), which aide the more specific assessment of
progress made. It is clear that the project has made limited progress under UNDP/GEF sub-component 2.2 and
no progress under sub-component 3.2. In comparison to the findings of the First-Year Evaluation a regression of
progress is observed, although the work of the scientific and economic group is recognised. One key problem is
that the value of that work must be seen in the bigger picture of establishing SNRM models for the four PA-PASZs
as well as the establishment of functioning SNRM knowledge management at national, regional and local level,
and thus only makes a relatively small contribution to overall performance. It also needs to be noted that the
quality and usefulness of the work in context of the overall project is questionable and should undergo a rigorous
peer review and/or technical debate.
Overall the performance assessment (Table 4) highlights that significant actions need do be put into place to
ameliorate project performance.
Table 4. Summary of progress report
Outcomes
Outcome 1
valuation
2006
S
valuation
2008
MS
Motivation/ comments
Outcome 2
MU
MU
Outcome 3
Outcome 4
Outcome 5
Overall project
evaluation
MS
HU
MU
HU
HU
U
In comparison to the project performance, financial data was to be assessed. Over the first 2 years of project
implementation about 32% of the overall budget have been spent. 68% of the initial budget is still available for the
implementation of the outstanding activities. Additionally, US$ 500,000 were made available recently, and can be
26
GEF
4,500,000.00
TRAC
1,800,000.00
TOTAL
6,300,000.00
Expenses
2005
2006
2007
Total
307,434.00
900,280.92
634,237.37
1,842,052.29
49,801.99
57,961.54
39,892.49
147,656.02
357,235.99
958,342.46
674,129.86
1,989,708.31
Funds available
2,657,947.71
1,652,343.98
4,310,291.69
Budget (US$)
Table 6. Funds available (with an additional US$ 500,000) (data presented by Finance Manager May 2008)
GEF
Project Management (i) PMU, (ii) UNPOS/UNDP
Result 1
Result 2
Result 3
Sub-total GEF
US$
552,147.71
534,950.00
1,867,420.00
203,430.00
3,157,947.71
TRAC
Project Management (i) PMU, (ii) UNPOS/UNDP
Result 4 & 5
Sub-total TRAC
914,543.98
737,800.00
1,652,343.98
Total available
4,810,291.69
support mechanisms (i.e. for this project SAGE), are currently not viewed positively by government. It is critical to
find tangible solutions for the implementation arrangements.
The abolition of CELCO as key coordination unit for EP3, and with it the UNDP/GEF sub-components, may have
sustainability implications of various kinds. Firstly the direct integration into Government (MEEFT) can be
beneficial to long-term sustainability of the PA-PASZ and SNRM model approach, as well as for KM thus to the
overall project objective, given that relevant capacities can be strengthened over the remaining project period.
However, at this stage it is not clear whether the current staff of the UNDP/GEF PMU is well equipped to take the
necessary leadership role.
The lack of establishing any progress of work concerning KM is critical, as KM also helps promote ownership and
understanding, without which the project, its concept and the developed models will not be recognised thus will
not attain any level of sustainability.
In terms of long-term financial sustainability it needs to be recognised that the tasks of establishing new
conservation areas whilst implementing incentive measures leading to the upliftment of the livelihoods of a large
number of people living in the ZAAPs, i.e. through promotion of sustainable SNRM based alternative incomes is
very difficult and required longterm commitment. The piloting nature of this project needs to be highlighted and
plans for future action and upscaling have to be developed now to guarantee sustainability.
3.1.5. Contribution to upgrading skills of the national staff
No explicit capacity and skills activities for staff were mentioned during the assessment. Overall it seems that the
PMU was strongly integrated into CECLO and only operated with limited authority for project implementation. At
this stage, with the recently effected restructuring and changes in executing of the project, it seems that the
prioritisation of establishing a capacity development support programme is timely, and relevant recommendations
are made in Section 4.
In the past it seems that there has been a reluctance to involve international expertise in project implementation
and management, although strongly recommended in the project document, various project progress reports and
the first year evaluation. A capacity support and skills development strategy including for national and regional
staff needs to be urgently developed and implemented, both to improve on project performance as well and to
foster sustainability. Technical advisory support, national or international needs to be sought for as a matter of
urgency.
Focusing on the capacity of the PMU and its four staff members, it would seem important to review their individual
TOR and establish new performance contracts, considering the new institutional arrangements, the draft
recommendations in this report and any decisions that may be taken on refocusing project implementation. A
more hands-on and practical role for PMU staff in project implementation at the national level, enhanced support
functions for regional/local staff, coordination of implementation partners and strong backing for the established
governance structures (e.g. various PFs and CPs) is recommended. Capacity reinforcement may be required.
Although mention was made that efforts need to be directed mainly at local level implementation, the evaluation
did identify capacity gaps and shortcomings at national level and within the various government and other partner
institutions. It therefore is recommended to include capacity building activities for national staff within the larger
PA-PASZ project. Again it needs to be highlighted that it is the project management that needs to have a good
understanding of the project vision, to be able to provide leadership and to aid other stakeholders to become more
understanding of the project concept PA-PASZ and SNRM. Recognition of other work going on in Madagascar
and elsewhere in the World i.e. southern Africa is a critical element of this and a strong link to KM has to be made.
Exposure visits, the invitation of guest speakers and facilitation of discussion groups are just some of the activities
that would assist the visioning, management and overall communication, KM and capacity building.
3.2. Project formulation (and implementation)
3.2.1. Implementation approach
In terms of project design, it should be noted that two Project Documents setting out (i) the design of the
implementation approach for the joint WB/GEF and UNDP/GEF project (English), and (ii) the design for the
UNDP/GEF project only (French) exist. Whilst both documents provide ample information on the project concept,
28
the design may not have been very clear to less experienced project managers (esp. less experiences in terms of
GEF projects). The in 2006 conducted First-Year Evaluation and subsequent PIR have improved on the initial
design, and should be self explanatory. Overall the design seems novel, needs driven and practical.
For ease of reference this evaluation report is presenting the logframe on the objective outcome - output and
indicator levels bilingual. This should aide clear communication of the logframe and any changes. Overall it is
recommended to retain the design as is. On the output level, certain adjustments could be made, i.e. to outputs
2.2 and 2.3, which are at the heart of the project and would need to be further unpacked and operationalised.
This can take place on the activity level. Output 2.4 may not become very significant during the project
implementation, however this would depend on the demand as indicated in the reports of the Scientific and
Economic group and by ANGAP. All outputs, should indicate the final product, for example output 3.1 should be
expanded by adding a note on . And implemented, whilst output 4.1 could have an addendum . And
Knowledge and Awareness Strategy developed and implemented. In terms of indicators it is mentioned
elsewhere that certain indicators, and related baselines and targets may benefit form minor revisions.
Project implementation mechanism:
- SAGE: foreseen as key execution/implementation partner (in French: APEX) responsible for putting the local
and regional project structures in place and responsible for community outreach (see Prodoc)
- ANGAP: key beneficiary of project, responsible for AP management; key implementation partner esp. vis-vis SAGE
- Additional specific Service Providers are commissioned to carry out specific project activities
- CELCO established as coordination unit for EP3, housing the UNDP/GEF PMU, amongst other
- MEEFT: NEX agency; largely coordination function, delegated through CELCO
Key issues:
- The establishment of outside government services is always a political issue and remains often donor
driven. In the case of SAGE and ANGAP the newly established Government is seeking to find new
arrangements that would also strengthen Government, which requires a technical feasibility assessment and
debate
- Especially in the context of a pilot project like the presently discussed, it is critical that implementation
arrangements are followed that guarantee the success of the piloting phase, so that overall up-scaling and the
implementation of the exit strategy can take place
- Renewed or revised implementation arrangements need to be strictly performance based to ensure that this
project can deliver
- Elements for the Exit Strategy including the longterm and nation wide up-scaling of successful piloting
approaches and should already be part of the project strategy
- It is clear that the changed political environment has had strong impacts on the implementation approach; it
needs to be critically assessed if a pilot project like the GEF/UNDP PA-PASZ project can fully react on such
changes
3.2.2. Country ownership/Driveness
The Prodoc and overall project are characterized by a very strong adherence to and integration into EP3, which
would suggest very strong country ownership. The newly developed Madagascar Action Plan (MAP) is a higher
tier development plan, which integrated EP3 elements and in its formulation clearly provides excellent
opportunities for this current project to make nationwide contributions. Overall the PA-PASZ concept is or highest
national interest and there is an urgent need to perform on establishing workable models and successful
demonstration interventions. The urgency for a project like the UNDP/GEF project, but more so the integrated
WB/GEF UNDP/GEF joint approach has been voiced over and over again during the evaluation visit.
In the past the MEEFT had installed CELCO as their coordination body for the project; recent political changes
have led to stronger ownership by MEEFT itself, and the PMU has been moved from CELCO into MEEFT. There
seems to be strong ownership and country driveness given by the project. At the regional level, strong ownership
over the project is observed, although the centralized implementation arrangement inhibits more effective
ownership and regional driveness at this stage. Local and regional level engagement, enthusiasm and readiness
is rated as being high and this should be harnessed. The role of SAGE and ANGAP cannot to be underestimated
in this, and any review or local and regional implementation arrangements need to take this into consideration.
3.2.3. Stakeholder participation
29
The initial project design foresees strong stakeholder participation, especially, but not only on the local
implementation levels. A well designed tiered approach to involving stakeholders at all levels can be deducted
from the concepts set out in the ProDoc.
Stakeholder participation needs to be established at various levels, (i) national, (ii) regional, and (iii) local. The
evaluation found, that best performance in terms of participation is at local and regional levels, and a strong
disconnect with national level is observed. Whilst relatively strong local and regional governance structures have
been established esp. under outcome 1 of the project design, these structures have subsequently not been
operationalised, largely due to national level project management decision making. One of the key bottlenecks of
the project is that national level decision making is done without participation of other national level stakeholders
and experts as well as without recognition of local and regional stakeholders priorities and activities. There is a
lack of national regional technical collaboration and support, which may be caused by the set up implementation
arrangements and a misunderstanding or responsibilities. Whilst SAGE could be seen as the key responsible
organization to establish this link, this is not reflected in any of the annual contracts or work plans. It is debatable if
such functions should rest with the PMU or with other project partners. At the national level an overall EP3
coordination mechanism was set up (e.g. in French: Committee Conjoindre), which in principle could fill some of
the participation gaps identified at that level, however the mechanism has not performed. The National Project
Steering Committee was not formally established during the first half of project implementation, and only a small
management group composed of CELCO, UNDP and partially SAGE and ANGAP seem to have operated. This
is insufficient to allow for relevant stakeholder participation.
3.2.4. Replication approach
In the project design a very strong replication approach is conceptualized, which clearly identifies the current
project as a pilot phase that would test and develop SNRM models, including implementation mechanisms
(ANGAP-SAGE), which would later be up-scaled to other PA-PASZs throughout the country.
It is observed that the replication approach for outcome 1 of the project has been well established and relevant
local and regional project structures have been established, even if they are not fully operational at this stage. In
terms of the methods developed in support to the SNRM systems by the Scientific and Economics group it is
obvious that no follow-up work on their deliverables has taken place. Thus at this stage there simply is nothing
that can be replicated. In the project design it is foreseen that the under results 2 and 3 produced work should be
applied and replicated by esp. ANGAP.
3.2.5. Cost-effectiveness
The in the project design foreseen implementation arrangements and the joint WB/GEF and UNDP/GEF
complimentarity element are novel and one would expect that cost-effectiveness criteria be met.
However, at this stage the lack of real project implementation makes it difficult to assess cost-effectiveness to
date. The fact that almost 70% of project funds are still unspent is hardly a reflection of such cost-effectiveness,
but points to the fact that key project activities have not been implemented. At this stage management decisions
at the national level (MEEFT, CELCO, UNDP) have led to the poor performance of the project. The
discontinuation of several project activities for a prolonged time period (e.g. hiring of KM service providers,
extension of contract for APEX SAGE, testing and application of model components of scientific and economic
group (various service providers), no availing of community funds, to name a few examples) seem ineffective.
If the project design and the developed PA-PASZ models incl. the ANGAP/SAGE partnership will be cost effective
once under proper implementation is taking place will have to bee examined at a later stage. Also if the joint
WB/GEF UNDP/GEF arrangement contributes to cost-effectiveness is not clear at this moment, although the
concepts seem credible (e.g. sharing of administrative and running costs; strong coordination of activities).
3.2.6. UNDP comparative advantage
The technical support services that can be rendered to project implementation are alluded to in the project plan,
mainly through the various support functions (support missions, evaluations), although they are relatively loosely
formulated in the ProDoc.
The UNDP Madagascar Country Office is generally well situated to serve as GEF Implementation Agency,
especially as programming can be aligned with other larger scale country support e.g. to the MAP and
Decentralisation efforts. It is, however stressed, that as CO, an effective and efficient administration and decision30
support system is required to ensure that projects are well guided and implemented. This is particularly true in the
context of a project that seems to have severe performance problems. It is observes that the UNDP Regional
Office in Pretoria has provided invaluable technical and administrative support to the project, i.e. through various
support missions. The voluntarily decision to install a First-Year evaluation, for example, demonstrates good
project support.
Linkages to the WB/GEF component of the joint project seem relatively limited.
3.2.7. Linkages between project and other interventions within the sector
As already pointed out in section 3.2.2. Country ownership/Driveness and elsewhere extremely strong linkages to
all EP3 project interventions were set out in the project concept.
In reality, the initial project idea is well planned, but poorly executed. This is particularly true at the policy and
national level. At the regional and PA-PASZ level, on the other hand, the establishment of the various project
structures such as the various platforms (PFs) allows for good coordination, exchange and establishing linkages;
very pertinent discussions and interactions have arisen amongst PF members, which need to be recognized. A
major difficulty of the project is that the KM component and with it its two foreseen outcomes (outcomes 4 & 5)
have not been implemented are foreseen in the ProDoc. Potential linkages that could be forested through
information sharing and exchange are therefore not tapped on currently.
3.2.8. Indicators
The in the ProDoc set out indicators are directly integrating the in the EP3 formulated indicators, to ensure that a
lean and effective M&E of EP3 progress can take place.
The ProDoc, the First Year Evaluation report and subsequent PIRs build on the initial indicator framework and
refined the outline of the M&E plan. The First Year Evaluation specifically addresses GEF requirements under the
Biodiversity Focal Area, by developing SP 1 impact indicators. It is recognized that the M&E Plan for which
elements were proposed in the First Year Evaluation was never fully completed, although a great deal of excellent
technical work was undertaken by the Scientific and Economic Group in terms of assessing baselines and refining
targets. Current 22 primary indicators are in place, of which 11 assess performance towards the project objective
and another 11 performance under the five project outcomes. Certain indicators are repeated.
Overall the indicator framework is quite strong, but certain indicators seem impractical (see comments in ANNEX
9), e.g. Indicator 5 aims at an increase of specific indicator families but can we really expect such an impact
over the relatively short project time period? Similarly for Indicator 6, which measures increase in endemic
species? Indicator 9: Is the measure in % practical? To name just a few examples.
Whereas the overall M&E plan should be improved, the primary difficulty seems to be the monitoring process in
itself. The mechanisms foreseen for the monitoring, and monitoring responsibilities are vested in a number of
project partners (e.g. scientists, communities, ANGAP), but no effective monitoring system is in place. One
additional difficulty is that the project M&E plan foresees a strong M&E role of ANGAP (mainly related to SNRM),
however consultations do not confirm that such a mandate for ANGAP exists outside of the AP. Role clarification
between MEEFT/DREEFT and ANAGP, and in marine areas MAEP/DDR is required and a check against existing
capacities may need to be undertaken.
It needs to be noted that the M&E data provided for the mid-term evaluation was sub-optimal especially in terms
of impact indicators, as no functional M&E system is in place.
3.2.9. Management arrangements
The established project management arrangements were introduced in Section 2, and are largely based on the
concepts presented in the ProDoc. The role of CELCO as a by the Ministry/Government designated EP3
coordination unit was foreseen to be significant and to facilitate integrated and effective project implementation. A
PMU was established in a subordinate arrangement.
CELCO was recently (May 2008) dissolved on action of the Minister of MEEFT. Although CELCO seems to
remain as WB/GEF mechanism, the UNDP/GEF component has moved under direct coordination from MEEFT
(Directorate of Planning). The new management arrangements mainly affect the PMU, which has now moved into
MEEFT offices. It is clear that the fact that CELCO was dissolved indicates that the arrangement did not suit the
31
current government; it would seem that a decision as significant as this should be based on the best performance
options for a pilot project such as the current. UNDP supports the demonstrated ownership drive by MEEFT. How
this new management arrangement will affect other project partners previously a major part of the ProDoc (esp.
SAGE and ANGAP) needs to be clarified.
It is clear that the management level of the project has suffered from major weaknesses, which have led to the
underperformance of the project. A number of project partners have to take responsibility, including MEEFT, the
PMU, UNDP, ANGAP and SAGE. The currently observed mismatch between national level decision making and
needs and realities on regional and local implementation levels could potentially be ameliorated by stronger
decentralisation of the management arrangements (see Section 4).
3.3 Implementation
The following sections have been partially addressed in Section 3.2 and only relevant additional points and crossreferences are indicated here in point form.
-
32
4. Recommendations
Based on the evaluation visit and the numerous consultations with project stakeholders, a wide ranging set of
recommendations are made, focusing on three reporting elements:
Corrective actions for the design, implementation, monitoring and evaluation of the project
Actions to follow up or reinforce initial benefits from the project
Proposals for future directions underlining main objectives
The recommendations section is divided into two sections, 4.1 and 4.2, with the first stating the top priority
recommendations for immediate management action, whilst the second section elaborates detailed operational
recommendations that could guide the formulation of the management responses to the evaluation.
4.1. Top priority recommendations for immediate management action
Despite poor project performance at mid-term, the recently strongly demonstrated want of national ownership and
willingness to improve on project performance by key players such as MEEFT, related regional structures,
regional governments and ANGAP are recognised as a strong foundation for performance improvement. This
commitment forms the basis for the following key recommendations from the evaluation:
1.
2.
It is recommended to request a 3 year no-cost extension for the PA-PASZ pilot project
a.
68% of funds are still available at mid-term (excl. a supplementary amount of US$ 500,000
availed through UNDP additionally)
b.
The final time horizon will depend on how fast the project can be realigned (incl. by when a TA
can be hired)
3.
A Technical Advisor has to be hired as a matter of urgency to help bring the project on track. Such a
position should be advertised nationally, if available, and internationally. The TA would be a SNRM expert
with a track record of strong capacity building [skills], which would be applied to the MEEFT and the PMU
staff, in particular and would aide build a longterm sustainability element into the project implementation
phase.
4.
The evaluation found that the initial project design is still responsive to the key PA-PASZ and SNRM
problematic and it is thus recommended to retain the design framework. Implementation elements can be
adjusted in the context of adaptive planning, and re-phased in line with the request for a 3 year no-cost
extension. The TA shall take leadership in such a process and guide the country team. It is recommended
that the overall project objective, the five outcomes and the major project indicators (22 +2) will be
retained when re-phasing the project. Certain indicators might benefits from minor revisions. Potentially
the outputs should be reviewed with the support of the TA. Esp. outputs 2.2 and 2.3 seem major and
should be further unpacked.
5.
It is further advised to install a policy expert TA at senior level of MEEFT, to aide the full integration of the
PA-PASZ and SNRM concepts into Government policy making, [and the up-scaling of the piloting results
and integration into a systematic policy process,] amongst other.
6.
It is critical to tighten the coordination of SNRM work in the PACZ and PA work under an integrated vision;
it is proposed that this vision be furthered between MEEFT and ANGAP, and then be shared and
furthered with all project partners.
7.
It is recognised that the key implementation activities have to be carried out at the local and regional level.
It is therefore recommended to decentralise project coordination aspects to the regional level, including a
certain level financial authority, to ensure more responsive management of project affairs. The following
points should be taken into consideration, amongst other:
33
a.
b.
c.
d.
e.
A strategy for decentralised implementation of the project is needed; such a strategy has to be
developed in a participatory manner with all key stakeholders and with potential implementation
partners
It needs to be recognised that this project is of piloting nature; thus the prerogative is to utilise a
lean and effective implementation arrangement that allows for best performance during a very
limited project implementation period; capacity support for longterm sustainability shall be
considered as part of the project strategy, however cannot lead to sacrificing the piloting success
A tiered implementation approach is recommended, including a strong prioritisation of key
activities to be tested and implemented at local level; the current number of project sites
(reference sites and Community Based Organisations (CBOs/CLBs)) seem to be too large to
ensure effective project implementation.
Site selection should be revisited and based on the needs of the PA-PASZ concept, under the
leadership of ANGAP.
Considering the relatively short life-time of the project, and recognising its piloting nature,
practical implementation mechanisms are sought for. Regional and PA-PASZ specific differences
need to be taken into account when planning such mechanisms. It is recognised that different
approaches may be taken for each PA-PASZ, based on the peculiar contexts of each of the PAPASZs. The capacity of Government extension (CTD) is rated to be currently low; it is
recommended to install intermediaries such as SAGE or other institutions (other national or
international NGOs, e.g. Fanamby, church based networks or other) to aide the successful testing
of the pilot approaches. Relevant capacity support to such organisations shall be provided by the
project and other players.
implementation steps, and the initial project idea has been dwarfted to a very limited intervention. A
particularly severe disconnect exists between national level decision making and regional and local
project realities and priorities.
Recommendation 1: It is recommended that a visioning exercise for the project be undertaken, so that all senior
decision makers and major stakeholders share the same project understanding. Without a firm and consolidated
vision that guides project implementation and development it is impossible to exert leadership. This is particularly
important in the context of increased decentralisation, proposed below, for which excellent leadership from
national level is required. Technical Advise, national or international, may need to be solicited in support of such a
visioning exercise. The exercise should be organised by the PMU, under guidance of MEEFT senior
management. It could become an element of the for the 16 & 17 June 2008 scheduled 2-day planning workshop.
A.2 Progressive integration into national development context (e.g. MAP goals 7 & 4)
Since project design, major policy changes have taken place in Madagascar, and these need to be fully
integrated and embraced by the adaptive management of the project. Partially linked to point A.1, it
seems to be a lack of vision and leadership in the project that lead to a limited understanding of this
important conservation and development investment by GEF with its implementing agencies UNDP and
WB. It is noted that the during 2007 performed EP3 mid-term evaluation had identified a fifth key
challenge to conservation, namely rural development, however, no reference to the contributions of the
UNDP/GEF project was made. Considering that the Madagascar Action Plan (MAP) is now the national
development strategy and is progressively being implemented, it is opportune for the project to identify its
contributions to MAP and to communicate on them. Based on an initial review it can be easily
demonstrated how the project interventions contribute to achieving MAP goals 7 (environment) and 4
(rural development). Such visible alignment within the national development context would also help
address matters such as the recent call by the Minister of MEEFT to focus project implementation on
enhancing rural livelihoods.
Although it was previously argued that this GEF investment is made under Biodiversity Strategic Priority 1
(SP1; Catalyzing Sustainability of Protected Areas Systems at National Levels) (First year evaluation,
various reports such as PIR/APR), it is noted that both versions of the ProDoc (English and French)
clearly state that the UNDP project would make contributions to SP 2 (Mainstreaming Biodiversity in
Production Landscapes/Seascapes and Sectors). It may be a strategic decision to include selected SP2
performance indicators at this stage, to ensure that the rural development contributions can be sufficiently
demonstrated.
Recommendation 2: It is recommended to continuously update and align the project context to the evolving
national development framework; this will aide the development and communication of project vision, objectives
and design. It is the role of the Coordinator, under guidance of the Steering Committee, to engage in a national
policy dialogue and ensure that the project interventions evolve together with the overall environment,
conservation and development priorities in Madagascar. This may also include the integration of performance
indicators under GEF Biodiversity SP 2, on Mainstreaming Biodiversity in Production Landscapes/Seascapes and
Sectors.
A.3 Management arrangements and performance
This overall operational area touches on various sub-areas, including
- Overall project management arrangements, dissolvement of CELCO
- PMU
- Steering Committee
The recent decision by the Minister of MEEFT to dissolve CECLO and to integrate project executing more
firmly within the Ministry provides a unique opportunity for the rearrangement and improvement of project
management, however it also comes at an expense of expending more time and resources to a
restructuring process mid-term into the project implementation. For sustainability and also performance
reasons the recent decision can be interpreted as a very useful leadership step to improving
implementation, however it should be cautioned that the project should not have to undergo further such
major disruptions, and UNDP and MEEFT should seek agreement on stability for the future. It is
recommended that the PMU structure be retained as had, although responsibilities may shift (see below).
At this stage the vision of the Minister for the restructuring is not quite clear, however it is anticipated that
35
it will fit well with the recommendations of this mid-term evaluation; in saying this it is noted that the reorientation should also be mindful of and take into consideration the recommendations made during the
First year evaluation of the project13, which, to this date, have received relatively limited attention by
project staff.
With the recent restructuring integration of the UNDP/GEF project under CELCO has ceased, and with it
the prominent role of the Head of CELCO as project responsible. This may indicate a change of roles
and responsibilities of PMU staff. The position of Project Coordinator (PC) in particular, would become
more prominent and the PC would take up more responsibilities. In addition, based on the extensive
observations during the evaluation consultations, a need for top management staff to take up more
hands-on roles was already identified. It is noted that the position of PC is the most prominent and critical
to project performance. A review of the current TORs of the PC indicates that the roles and
responsibilities of the PC may not be spelled out clearly enough, and revision made be required. A clear
performance contract underpinning the TOR should be established for all staff (PMU and other potentially
designated by MEEFT). The coordinator needs to (a) understand all components of the project even is
implementation is outsourced, and (b) is responsible for the synthesis of all programme elements; more
hand-on work on the national level is required and it is recommended that e.g. the TOR of the Coordinator
be amended to include elements of KM and communication. Staff and project management are critical
responsibilities of the Coordinator, and will become even more important if the project implementation
arrangements will become more decentralised in nature (see below).
The project would potentially benefit from the services of a Technical Advisor and other additional support,
esp. to the PC. Because the remaining project implementation phase is relatively short, it may be
advisable to look into pragmatic solutions instead of trying to fill a full time TA position, and part time
solutions could be explored. It is strongly recommend to agree to international support, which should,
however have capacity building and coaching of national staff as primary objective. International support
is recommended as the evaluation clearly identifies a very limited inward vision, with limited technical
understanding; for example, at this stage project staff is too inward looking (at all levels), not really being
used to synthesising lessons learnt from elsewhere in Madagascar or world wide; it would be beneficial to
strengthen the culture of seeking outward support, knowledge and cooperation. A specific capacity
development element for management should be included (see Strategic Performance Areas B).
It is the responsibility of the National Steering Committee to oversee and guide project performance, and
esp. the PMU. It is noted that the NSC has been implemented only haphazardly and has been operating
on an ad hoc basis only. Membership of the NSC has been limited to the key players, mainly CELCO,
SAGE and UNDP, which would come together to take day-to-day management decision in a more or less
formalised manner. This has lead to (i) limited strategic guidance for the project and (ii) limited
stakeholder involvement, project understanding and ownership. Although the concern is understood that
the overall EP3 structures (e.g. Committee Conjoint) would take on such technical and strategic guidance,
this has not happened to date and the UNDP/GEF project suffers from a lack of such leadership. A
number of models can be proposed to ameliorate this issue, and final rearrangements can/ should be in
line with the overall restructuring of the EP3.
Recommendation 3: It is recommended that under the new management arrangements of the project, after
integration into MEEFT, the roles and responsibilities of the PMU staff, esp. the Project Coordinator (PC) are
reviewed and amended to reflect the expanded performance areas (by MEEFT and UNDP). This is also
recommended in view of the proposed stronger project implementation decentralisation efforts, which will
require intensified staff management and strong devolution of responsibilities on one hand, and increasing
communication, capacity building and management responsibilities at the national level, on the other.
Recommendation 4: It is advised to seek additional Technical Advisory services with a strong strategic and
capacity building mandate, which would coach and support national staff for the remaining project
implementation period. Creative models could be explored, to ensure that lengthy recruitment procedures do
not delay project implementation.
Recommendation 5: The National Steering Committee needs to be strengthened to be able to take up
critical leadership and support responsibilities. For example membership should be expanded to include a
wider ranging set of project stakeholders and technical expertise.
13
A great number of the recommendations made during the 2006 evaluation still apply and are not necessarily repeated in this report.
36
37
The project can provide for regional staff to be deployed, however will depend on other service
providers for intensive local level delivery
Need for decentralised planning & budgets; needs specific capacity support
Any proposals made need to be carefully costed and checked against the overall available
budget; a re-structuring of the budget that would reflect the decentralisation move is
recommended
The role of the project is to broker increased investments into the PA-PASZs to promote SNRM
based livelihoods improvements
Role of Regional CPs versus National CP needs ot be clearly established avoid overlaps and
contradictions
B. Communication, Capacity Building, Knowledge Management & the Role of Science and
Research
38
39
Recommendation 12: It is recommended to support the development and implementation of Capacity Building
Plans for project stakeholders at all levels incl. project management; it is important to design the plans in a way
that impacts of the investments made can be demonstrated, as such soft investments often go underrecognised. The PC should oversee the development and implementation of such a project activity, which could
be part of the KM component.
B.3 Review of Knowledge Management component and implementation of segments; allocation of key
responsibilities to MEEFT and Project Management Unit
EP3 sub-component 3.2 on KM is critical to the performance and implementation of the UNDP/GEF
project. It is important to revisit the full concept of the KM project elements and to recap their full
intension. For example, the KM component ought to establish a practical resource centre for lessons
learnt from this project and the four test PA-PASZs, other examples from within Madagascar, as well as
international experiences, resource materials and lessons learnt. Additionally the KM component is tasked
to facilitate the communication and exchange of information between the various project stakeholders,
including the preparation of well targeted materials e.g. on the community level. The information from the
scientific reports, for example, should be translated into materials that can be easily applied in outreach
activities with local communities.
Recommendation 13: It needs to be recognised that the KM component is quite extensive and requires a diverse
set of skills for successful implementation. It is therefore recommended to break the assignment and outsourcing
of its implementation it into smaller portions, which can then be addressed by various competent service providers
as well as project partners and staff already in place. There is no need to outsource KM as one package. An
additional note brought forward from Strategic Performance Area A is that the reviewed TOR for the assignment
did not sufficiently address the scope and extend to work required. This is to be rectified, if not already done.
B.4 Clarification of role of science research and sourcing to most competent and applicable capacities
(incl. international, as required) and establish peer review mechanism
The ProDoc foresees a strong science element of the project, mainly to ensure that the established
models are rigorous sustainable. At this stage the Scientific and Economics Group has produced some
excellent research baseline, which now awaits application in form of (i) resource monitoring and adaptive
management, and (ii) realisation of NR based businesses. At this stage, the evaluation found that there
are widely differing views on the scope and extend of science and research work needed in the context of
the project, as well as on the appropriateness of the work conducted to date. There seems to be a
mismatch between the high level scientific work and the usually more pragmatic local level application of
monitoring and resource tracking tools and methods, which need to be urgently addressed by the project.
This is an issue that needs to be guided by the vision for the models to be developed, as pointed out in
section A.1.
Key products that should be synthesised and further developed based on the already undertaken studies
(e.g. for the development of filieres) needs to be identified and clearly commissioned through the KM
component. In future the commissioning of any contract, and the development of the respective TOR,
should have a strong communication and KM component (see A.4) beyond the compilation of reports.
This is so that more tangible and recognisable products come out of the commissioned work that do not
just end up in the offices of a few managers.
Considering that it is the PA-PASZ communities that should make use of the tools, at is a worrying
(although quite normal) that there is very limited ownership and understanding of the work undertaken by
the Scientific and Economics Group at this stage. Ownership is also questionable with higher tier
organisation such as ANGAP, who, according to the ProDoc and the M&E plan in the First Year
Evaluation, are the responsible authority for undertaken resource monitoring in the PA-PASZ areas.
During the evaluation mention was made of s suite of already existing resource monitoring tools (e.g.
prepared by ANGAP, WWF, WCS, CI), and, especially as the UNDP/GEF work on this result areas has
come to a stand-still over the past year, these should be applied and perhaps improved as part of this
project, instead of developing parallel systems. Science, technical and technological support to the CTD
and decentralised government monitoring entities (e.g. fisheries, forestry) should be considered.
The ProDoc foresees the input of many more studies and background research to be conducted, amongst
other in areas such as market development of NR-based products, policy research on market constraints
40
and opportunities, economic valorisation, value addition and product development, to name a few. It is
important that the most competent research teams are identified and commissioned to carry out this kind
of work, be it with international input and capacity.
Can identify creative ways of having a national and international panel, with appointed/invited experts;
potentially against payment, e.g. propose an ad hoc technical peer review group (e.g. ANGAP,
representatives of relevant CTD, NGOs/expert organisations working in similar fields SAGE, FANABY,
WWF, WCS, CI -, other project experts (e.g. GTZ, USAID) representatives of the Scientific and Economic
Group, PC, other from expanded SC) to be established. Such review will also help and assist the work of
the coordinator and the NSC and adds credibility to decision taken. The web portal could be a good
medium to facilitate such reviews; face-to-face meetings are costly and not necessarily required.
Recommendation 14: It is recommended to establish a peer review process for any of the products and scientific
work conducted under the project to ensure that outputs are well aligned with the project vision and needs. In the
specific case of the work undertaken by the Scientific and Economic Group, it is important to review the reports
and proposed methodologies and to identify the most appropriate ways ahead for their testing and application. It
is proposed that a an ad hoc technical peer review group (e.g. ANGAP, representatives of relevant CTD,
NGOs/expert organisations working in similar fields SAGE, FANABY, WWF, WCS, CI -, other project experts
(e.g. GTZ, USAID) representatives of the Scientific and Economic Group, PC, other from expanded SC) is
established as a matter of urgency to come up with relevant recommendations for the way ahead, without
delaying the implementation and rolling out of project activities further.
Recommendation 15: Based on the ProDoc and the for the remaining project period identified priorities establish
a tangible science and research plan, that will guide the commissioning of expert studies to be undertaken (PC
under guidance of SC, or peer review mechanism). Include a strategy of how to utilise the information generated
at the planning stage (e.g. in KM context), so that the valuable information will be used and applied. Provide
relevant guidance in TOR.
B.5 Promotion of technical debates and advancement of top priority issues emerging from model
development process; establish peer review and learning mechanism as foreseen in KM component
The need for a technical debate on national level, but also in the regions, is clear; there may be existing
structures can be used and promoted through e.g. organising relevant seminars and preparing discussion
papers on the relevant issues (see ProDoc e.g. on valorisation, market access other research, and key
issues identified during consultations, see below). A key element of the project is to develop SNRM
models; such models can only be really furthered if a technical debate peer review takes place. The
issue papers developed for the EP3 mid-term review are a good venture point and could be used for the
furthering of the concepts.
A number of relevant technical issues were identified at the regional levels and should be brought forward
through national and regional level and interactive debates:
- Innovations of platforms; coordination platforms for service providers and beneficiaries; PFIR:
inter-regional approach; interaction with AP management through Angap
- Dialogues and joint work between MEEFT and MAEP (and Ministry of Justice) trying to clarify
issues such as application of GELOSE and TdG currently under MAEP jurisdiction (e.g.
Mangroves, APMCs)
- Plans de sauveguard with Angap
- PCD verte integration of planning
- Established structures potential use by other RD interventions e.g. through Regional
Government; example: GTZ project in Lokobo ZAPP (Crades or Roseda - check)
- ZAAP Lokobe platform used/invited to provide inputs into policy development for Baei de
Ambara
- Potential for Aquaculture development; discussion paper; probably also on EIAs and SEAs
- Furthering of EP3 mis-Parcours issues papers on GELOSE and TdG applications; analysis of key
bottlenecks e.g. lack of M&E and renewal of contracts by DREEFT; problem of establishing TdG
without clear visions of CLBs of how to use/manage the resources
- Conflicts between DINA and TdG and other; also opportunities
41
Recommendation 16: The project, through the KM component but critical to the advancement of other project
results, should facilitate national and regional level technical debates on key policy issues. A suite of important
topics identified in the ProDoc, other documentation and during recent field consultations can serve as a starting
point. The concept of issue papers could be furthered from the EP3 mid-term review, or other strategies be
developed in line with the KM component and communication strategy, under leadership of the PC and with inputs
from the SCs (national and regional), and the technical peer review mechanism.
formally embedded in the project. It is NOT recommended to implement the proposed elements of a model by the
Scientific and Economics Group without a wider technical debate and review.
Recommendation 20: It is recommended to fast track the establishment of community conservation projects
through the availing of funds. The in the ProDoc foreseen establishment of a Community (Conservation) Fund
should be kick started by investments from project resources and supplemented through assisting partner CLBs in
assessing existing funds such as from the SGP. This is proposed to (i) react to the urgent request of ANGAP to
invest in the ZAAP, and (ii) in parallel to establishing selected filieres, which will potentially be a lengthy process
before generating monetary and in the end conservation benefits.
C.4 Implementation structure elements: SAGE, ANGAP, CTDs, Regional Coordinators, established project
structures and a great diversity of partners!
Overall: The stronger decentralisation focus requires a critical look at the current and future
implementation structures and arrangements. It is clear that a strong community outreach/ facilitation
mechanism is required for the PA-PASZ concept to evolve, not only concerning this project. The initial
idea i.e. spelled out in the ProDoc and stemming from the work of PE2, to establish SAGE as the
Governments key partner to serve as a CBNRM agent, facilitating and coordinating the work of a
multitude of other CBNRM support organisations, should be revisited and debated. It is recommended to
examine the question of what type of institutional arrangements are required to make the PA-PASZ
concept successful esp. taking into consideration nation-wide up-scaling commitments under MAP.
SAGE: Overall the evaluation found that at the local and regional level project partners voiced general
satisfaction with the services rendered by the key agencies SAGE and ANGAP, although the call for
moving beyond mobilization activities was loud and clear. The capacity for delivery of community level
interventions, both from a size and skills perspective were raised, specifically relating to SAGE, and
more so in the South than in the North. The initial mandate of SAGE as the Governments key partner to
serve as a CBNRM agent, should be revisited and debated. At this stage it is clear that (i) SAGE has
developed into an independent NGO which has to find its own financial resources to operate, rather than
into a mechanism for CBNRM coordination; (ii) government support to SAGE as an institution has been
sub-optimal in terms of investments made and has now, for various reasons ceased almost completely. It
is recommended to examine what role SAGE could play in a national approach. This is critical to
determine the level of support that SAGE needs to receive incl. from this project in future, in a fully
committed manner, to allow capacities to develop to be able to deliver on the set out objectives. In order
not to halt project implementation whilst the Malagasy stakeholders have found a more final solution to
the implementation structures, it is important to continue with pragmatic interim solutions.
ANGAP: In terms of the UNDP/GEF project components ANGAP is primarily an implementation partners,
and in certain ways a client, concerned with the furthering of the PA-PASZ concept and finding
conservation solutions that involve the community as caretakers, and provide livelihoods opportunities
that contribute to developing conservation incentives. As such it is important that clear workplans and
agreements between ANGAP and the project be established, e.g. through a Joint Work Plan (JWP). One
key problem, for example, has emerged in that the reference sites identified during the project preparation
do not necessarily conform with the final AP boundaries and priorities any longer. The slow and iterative
AP demarcation process does impact on the ZAAP intervention element of the global GEF support
project. However, it is clear that this needs to be integrated into adaptive planning, as it is a reality that
cannot be changed. The project team is encouraged to continue with adaptive decision making, following
the earlier made suggestion to develop a tiered delivery plan. On the other hand ANGAP has expressed
frustration that the UNDP/GEF component has not delivered any tangible results at the community level
and thus pressures on the newly established PAs is mounting, as well as pressure on the decentralised
ANGAP offices and staff. The fast delivery of the in the ProDoc foreseen Community Funds for
conservation projects are seen as a critical tool for quick responses, which could be implemented in
parallel to the filiere establishment, which will take a much longer time to show tangible results to
communities (See above).
CTDs: At this stage only marginally included in project implementation, mainly through PF membership
and ongoing mandates such as GELOSE implementation (DREEFT); during evaluation consultations
clearly indicated interest and need for stronger involvement in project as implementer and beneficiary.
Depending on overall strategy for delivery on PA-PASZ (see above, SAGE, and partially ANGAP) the role
of DREET, and other entities (e.g. DRDR and DDR at Regional Government) need to be decided on.
44
Amongst other roles in SNRM monitoring have been attributed to various CTDs, however a mandate
conflict concerning PA-PASZs may occur vis--vis ANGAP. One important aspect for planning with
Government is to consider the various Ministries planning cycles if project activities ought to be
mainstreamed into e.g. DREEFT work plans, it needs to be considered that DREEFT planning takes
place towards the end of the year in September/October for the coming year.
Regional Coordinators: Not currently in place, however to aide effective decentralisation it has been
proposed to establish designated regional project coordinators. If these are newly hired project staff,
seconded government staff or persons in the APEX SAGE needs to be established. It is not necessary
that in the various regions PA-PASZs the same solutions are being implemented, and there are degre4es
of freedom to develop implementation mechanism specifically tailored to the special needs and
peculiarities of each region/area. The roles and responsibilities need to be carefully considered on the
regional project implementation plans and priorities; again: form follows function! A key planning
consideration is the cost effectiveness of the proposals; a medium-term project specific solution versus a
longterm approach may need to be sought for.
Established project structures (PFs and CBOs/CLBs): The various governance structures have been
put in place to aid truly decentralised/ devolved project implementation and bottom up processes, and to
promote successful and cost-effective and coordinated service delivery to the community level, a key
challenge to rural development worldwide. This approach needs to be well documented and
communicated to highlight its novel ideas and development potential. At this stage it is also clear that
although the structures have been successfully set up, they do not yet fully perform to their functions. In
the North the PFs have started engaging in some critical policy processes, but overall they require a lot
more operationalisation support. It the contact of the revised implementation arrangements it is important
to recall the roles and functions of the PFs and other established entities (CBOs/CLBs) and to then render
the necessary financial and technical support to make them operational (e.g. start with community funds,
funding for implementation of workplan priorities; assist in brokering information and access to other
funds and cooperation partners through project).
Other project partners and service providers: It is clear that creative strategies for engaging other
service providers in delivering on the PA-PASZ concept is urgently needed. Certain well established
organisation (e.g. NGOs such as SAGE, FANAMBY, WWF, WCS, CI and other donor projects and
partners e.g. GTZ, USAID) need to be sought to collaborate in the project areas. Strong capacities and
collaboration of service providers is key to successful implementation of the AP-ZAPP concept, EP3, and
this specific project, however reviews of PE2 and EP3 mid-term have identified that the overall service
providers landscape is relatively limited in Madagascar at this stage, especially at a regional,
decentralised level. Competent consulting services may be available, however usually services of such
offices are short term in nature and are not usually geared towards longterm local level engagement.
Strategies to find and foster support for local level implementation are needed and it needs to be
recognised that this is a great barrier to rural development per se. Project management at this stage
needs a better understanding of overall service provider landscape and may need to seek international
support as appropriate and use such knowledge for the planning process.
Recommendation 20: At mid-term of the project it is clear that the initially foreseen implementation arrangements
for the PA-PASZ concept with ANGAP and SAGE as central Government agents are seen to be problematic. It is
recommended that this project facilitates a debate on the question of what type of institutional arrangements are
required to make the PA-PASZ concept successful esp. taking into consideration nation-wide up-scaling
commitments under MAP. Based on such a debate medium-term implementation arrangements for this project
shall be agreed to. Because this is a critical step for the project to move ahead it is recommended that this
discussion is initiated at the 2 day workshop on 16 & 17 June 2008, with agreements for project implementation
emerging at that time. Project specific proposals for implementation arrangements needs to be developed in light
of the available budget and the results framework set out in the ProDoc.
Recommendation 21: Concerning SAGE, it is clear that the APEX has made major contributions to the
implementation of the project to date. In-depth analysis of the organisations performance capacities and vision in
terms of the debate outlined in Recommendation 20 may be required. The Organisation should be invited to
engage in the discussion and make tangible proposals for consideration. It is anticipated that SAGEs initial
mandate a coordinator of CBNMR organisations and facilitator of local level implementation activities at the
project sites is highlighted in particular.
45
Recommendation 22: Mechanisms for coordinated outreach activities with ANGAP need to be established within
the project e.g. through a Joint Work Plan. ANGAP is an important discussion partner for furthering the regional
implementation arrangements and needs to be invited to such a debate.
Recommendation 23: Based on the evaluation consultations a first draft implementation structure, based on key
functions to be carried out through the UNDP/GEF project component and linked to the global GEF WB and
UNDP support, has been develop and should serve as basis for further discussions i.e. on 16 & 17 June 2008. It
is important to agree to a model earliest possible to not further delay project implementation.
Figure 7. Outline of proposed process for development of proposals for new local and regional project implementation
arrangements. To be discussed at 16 & 17 June workshop.
Slide 1: Need to prioritise outreach activities in project; cannot support all currently established Reference Sites and Partner CLBs with
intensive service delivery; also need to discuss ANGAP requests for NEW Reference Sites/ CLBs to be involved; need clear agreements. Can
design tier 1 and tier 2 intensity sites, meaning that tier 1 sites will become partners for very intensive project implementation, whilst tier
2 partners will be engaged in more general outreach activities related to communication, selected training, and regarded for upscaling;
would be eligible for Community Funds, for example.
Slide 2: Functions: Before deciding on a revised institutional and delivery mechanism for approach/ project implementation it is important to
recap the key functions that the projects aims to deliver on the regional and local level, and the linkages that are required to ensure
embedment and advancement linked to the national level. Based on these functions proposal can be brainstormed of which (i) existing
institutions, (ii) set up project structures exist to carry out key functions, and identify (iii) potentially new institutions/structures/positions that
strategically would ameliorate project implementation success and contribute to the long term sustainability of the PA-PASZ approach.
46
Slide 3: Based on the discussions (slide 5), key roles and responsibilities for the various identified potential implementation agents need to be
identified.
Slide 4: The new implementation arrangements can then be mapped out based on the previous decision and HR and other requirements can
be planned. It is proposed to institute a project Regional Coordinator to improve the current arrangements. Such a RC could be housed within
the Regional Government, regional decentralised Ministries, or in a organisation such as SAGE or even ANGAP, depending on the longterm
vision on the AP-ZAPP concept. Arrangements in the North and South do not necessarily need to be the same, and can be changed after a
testing phase. It is important to discuss the proposal with the relevant stakeholders to find best and sustainable solutions.
47
5. Lessons learned
Mid-term evaluations aim to identify best and worst practices in addressing issues relating to relevance,
performance and success of the project under assessment to provide relevant guidance for improvement or this
and other GEF interventions.
During the mid-term evaluation of the UNDP/GEF PA-PASZ project three significant lessons learned are
synthesised.
Lesson 1: Best practice local and regional governance structures are vital and often undervalued
The project has invested significantly into the setting up of local and regional governance structures for the project
and ultimately in support of the PA-PASZ concept and SNRM in bufferzones. The systematic support to the
formation of CBOs/CLBs is critical to facilitate local level outreach and successful project implementation. It is
further important that the approach is backed by relevant legislation and government policy, and integrated into
newly revolving structures, as such emerge (in the project case the new Regional Governance structures). It is
important to fully document the processes and lessons learnt to aide easy adaptation of the approaches. The
project has some very interesting successes and lessons learnt to demonstrate, which would need to be
synthesised in much more detail i.e. through the KM component of the project.
Lesson 2: Worst practice lack of common vision can derail project performance
Project implementation stands or falls with its leadership. It is important to ensure that all project partners have a
common project vision, and that especially the responsible management share the same vision. In the case of this
particular project the vision as spelled out in the initial ProDocs is not understood in the same way by key project
players. At the onset of a project is has to be ensured that the vision is clear and continuity in leadership is
required to ensure that a project is not derailed somewhere during implementation.
Lesson 3: Best practice the PA-PASZ concept a novel approach that needs visionary investments
Last and finally it can be said that the PA-PASZ concept in Madagascar is novel in its approach, and driven by the
urgency of reducing the mounting pressures on natural resources in the conservation areas and on adjoining
land. It is important to better communicate the concept and urgent action on the SNRM model development is
supported. The project design seems well attuned to the needs. In the longterm it needs to be realised that much
more intense investments are needed, esp. but not only in the ZAAPs. It is unrealistic to see EP3 and this specific
UNDP/GEF project as exit strategy phase.
48
Annexes
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
L
TOR
List of key documents reviewed
List of persons interviewed
Consultation methodology, incl. questionnaire/guidance used
Recommendations from 1st Year Evaluation (D. Roby)
Itinerary
Summary of evaluation work sessions (site visits)
Reference site summaries concept
Assessment: Performance on project objective and results
Knowledge/Awareness baseline concept
Capacity needs self-assessment elements concept
Draft brochure concepts (for decision makers; project promotional)
Photo library concept
49
ANNEX 1: TOR
TERMS OF REFERENCE
FOR
INDEPENDENT MID TERM REVIEW OF PROJECT
SUPPORT TO ENVIRONMENTAL PROGRAMME- PHASE III (EPIII)
Country:
UNDP GEF PIMS No.
Project Duration:
Beneficiary Country:
Estimated start:
Start:
Estimated ending:
Executing Agency:
GEF Focal Area:
GEF Strategic Priority:
Madagascar
2762
5 years
Madagascar
2004
June 2005
May 2010
- NEX : Cellule de Coordination du Programme Environnemental 3
- UNOPS
Biodiversity Conservation
Protected Area
In accordance with UNDP/GEF M&E policies and procedures, all projects with long implementation periods (e.g.
over 5 or 6 years) are strongly encouraged to conduct mid-term evaluations.
Mid-term evaluations are intended to identify potential project design problems, assess progress towards the
achievement of objectives, identify and document lessons learned (including lessons that might improve design
and implementation of other UNDP/GEF projects), and to make recommendations regarding specific actions that
might be taken to improve the project. It is expected to serve as a means of validating or filling the gaps in the
initial assessment of relevance, effectiveness and efficiency obtained from monitoring. The mid-term evaluation
provides the opportunity to assess early signs of project success or failure and prompt necessary adjustments.
Madagascar is recognized as one of the 17 greatest mega-diversity hotspots in the world for biodiversity, but
conservation of biodiversity outside of its protected area network remains highly problematic. Protected areas are
increasingly becoming islands of conservation surrounded by fields, grasslands and degraded and severely
degraded natural areas. The transfer of natural resource management rights to empowered communities was
begun under Madagascars Second Environment Program (EPII). This shows great promise, but participatory and
sustainable management of ecosystems and natural resources is severely constrained by the lack of viable
sustainable natural resource management models and the lack of economic incentives to communities for
sustainable management.
The project seeks to address systemic, institutional and individual barriers to sustainable natural resources
management (SNRM), working first at community-based field laboratories in protected areas support zones
(PASZ) to develop replicable productive SNRM models. Secondly, the project is also working at the national level
to mainstream SNRM as a conservation tool through the generation and sharing of knowledge on SNRM through
a network of SNRM practitioners and through a communication programme targeting policy and decision-makers.
SNRM model development is being undertaken in 13 field labs in coral reef/coastal, mangrove and dry
forest/spiny forest ecosystems in PASZ around Toliara in the southwest and around Nosy Be/Ambanja in the
northwest. Existing stakeholder platforms are being engaged to develop strategies for integrating PA, SNRM and
biodiversity conservation into the land use systems and economic life of the PASZ. SNRM marine models are
being directly integrated into the co-management of two new marine parks to be created in the two zones.
The Knowledge Management component is developing and implementing protocols for the systematic collection
and analysis of data on key economic, ecological/technical and institutional aspects of SNRM in bio diverse
50
ecosystems across the country. State-of-the-art summaries, lessons learned and tool kits will be widely
disseminated and policy briefs prepared and communicated to policy and decision makers. The project will allow
SNRM, to be developed as a much more effective tool for biodiversity conservation and sustainable livelihoods in
Madagascar.
1.
According to the UNDP/GEF rules and to the Project Document (PRODOC), a mid-term evaluation will be held.
The process is initiated by the Execution Agencies, CELCO and UNOPS.
As an integral part of the project cycle, the evaluation will analyze the achievements of the project against its
original objectives. The evaluation will consider the effectiveness, efficiency, relevant, impact and sustainability
of the project. It will also identify factors that have facilitated or impeded the achievement of the objectives.
This evaluation will be conducted further to a first support mission, which was completed in 2006. The current
evaluation will assess to what extend the recommendations of this support mission in 2006 have been followed.
While a thorough assessment of the progress of implementation to date is important, the evaluation is also
expected to result in recommendations and lessons learned to assist in defining the future direction of the project.
The following stakeholders will be considered in the mid-term evaluation:
- Ministry of Environment, Forest and Waters and Tourism,
- Local Communities,
- Regions, Districts and Local Authorities
- ANGAP (Association Nationale pour la Gestion des Aires Protges) and SAGE (Service dAppui la
Gestion de lEnvironnement) as the most relevant partners for the project implementation
- EPIII Implementing partners (NGOs, Civil Societies, etc.)
- EPIII National Implementing Agencies
- Private sector (e.g. : Mining Companies)
2.
Project Design review original project objectives and assess quality of design for delivery of planned
outputs.
(ii)
Project Impact assess achievements of the project to date against the original objectives, outputs and
activities using the indicators as defined by the project document. Assess progress towards attaining the
projects environmental objectives and outcomes at all levels.
(iii)
51
Evaluation of project achievements according to GEF Project Review Criteria covering: Implementation
approach, Country ownership/Driveness, Stakeholder participation/ Public Involvement, Sustainability,
Replication approach, Financial planning, Cost-effectiveness, Monitoring and evaluation.
3. Products expected from the Evaluation):
The Evaluation should produce a report that will include the assessment results of the following topics:
a. Implementation approach
Review the clarity of roles and responsibilities of the various individuals, agencies and institutions and the
level of coordination between relevant players. In particular, the capacity and performance of the Project
Manager and National/Regional Steering Committees will be reviewed.
Assess the level to which the Logical Framework Approach (LFA) and performance indicators have been used
as project management tools.
Evaluate any partnership arrangements established for implementation of the project with relevant
stakeholders involved in the country/region.
Describe and assess efforts of UNDP in support of the implementing agencies and national institutions.
Make recommendations as to how to improve project performance in terms of effectiveness and efficiency in
achieving impact on both capacity building and the targeted conservation concerns
b. Country ownership/drivenness
Assess the extent to which country representatives (including governmental official, civil society etc.) are
actively involved in project implementation.
Assess whether The Government of Madagascar has maintained financial commitment to the project.
c. Stakeholder Participation and benefits accrued
Assess the level of communities involvement in the project and comment as to whether communities
involvement has been appropriate to the goals of the project.
Review and evaluate the extent to which project impacts have reached the intended beneficiaries.
d. Sustainability
Assess the likelihood of the continuation of the project outcomes/benefits after completion of GEF funding;
and describe the key factors that will require attention in order to improve prospects for sustainability of
project outcomes.
Factors of sustainability that should be considered include; institutional capacity (systems, structures, staff,
expertise etc.), social sustainability, policy and regulatory frameworks that further the project objectives,
financial sustainability (including the options of a Trust Fund considered in development of the project).
e. Replication Approach
Assess the extent to which the projects activities and related opportunities are being taken to scale up lessons
and experiences emerging from the project. Make recommendations of how this could be achieved if
necessary.
Describe the main lessons that have emerged in terms of: strengthening country ownership/ drivenness;
strengthening stakeholder participation; application of adaptive management strategies; efforts to secure
sustainability; knowledge transfer; and the role of M&E in project implementation. In describing all lessons
learned, an explicit distinction needs to be made between those lessons applicable only to this project, and
lessons that may be of value more broadly.
f. Financial Planning
Assess the financial control systems, including reporting and planning, that allow the project management to
make informed decisions regarding the budget.
52
Assess the extent to which the flow of funds has been proper and timely both from UNDP and from the
project management unit to the field.
Evaluate the extent of due diligence in the management of funds and financial audits.
g. Cost effectiveness
Assess compliance with the incremental cost criteria (GEF funds used to finance a component of the project
that would not take place without GEF funding and securing co-funding and associated funding.
Assess the extent to which the project has completed the planned activities and met or exceeded the expected
outcomes according to schedule and as cost effectively as initially planned.
h. Monitoring and Evaluation
Review the projects reporting systems and there efficiency.
Review the implementation of the projects monitoring and evaluation plans including any adaptation to
changing conditions (adaptive management).
4. Evaluation approach
The Evaluator will be an International Consultant experienced in biodiversity issues and rural
development
Language skills: French and English
Assess the extent to which the project objectives have been met and where gaps are evident
Draw lessons learned from the experiences of the project, in particular those elements that have worked
well and those that have not
Provide recommendations to strengthen the effectiveness, efficiency, impact, implementation, execution
and sustainability of the project.
53
Annex I
Documents to be reviewed
1. Project document
2. Project implementation reports (PIRs) for 2006 and 2007
3. Project quarterly progress reports
4. Field visit reports
5. NEX project audit reports
Annex 2
Proposed Structure of the Report
TABLE OF CONTENTS
ACRONYMS AND TERMS
EXECUTIVE SUMMARY
Executive summary
Brief description of project
Context and purpose of the evaluation
Main conclusions, recommendations and lessons learned
Introduction
Purpose of the evaluation
Key issues addressed
Methodology of the evaluation
Structure of the evaluation
The project(s) and its development context
Project start and its duration
Problems that the project seek to address
Immediate and development objectives of the project
Main stakeholders
Results expected
Findings and Conclusions
Project formulation
Implementation approach
Country ownership/Driveness
Stakeholder participation
Replication approach
Cost-effectiveness
UNDP comparative advantage
Linkages between project and other interventions within the sector
Indicators
Management arrangements
Implementation
- Financial Planning
- Monitoring and evaluation
- Execution and implementation modalities
- Management by the UNDP country office
- Coordination and operational issues
Results
54
Attainment of objectives
Sustainability
Contribution to upgrading skills of the national staff
Recommendations
Corrective actions for the design, implementation, monitoring and evaluation of the project
Actions to follow up or reinforce initial benefits from the project
Proposals for future directions underlining main objectives
Lessons learned
Best and worst practices in addressing issues relating to relevance, performance and success
Annexes
- TOR
- Itinerary
- List of persons interviewed
- Summary of field visits
- List of documents reviewed
- Questionnaire used and summary of results
- Co-financing and Leveraged Resources
55
57
58
Organisation
MEEFT
MEEFT
MEEFT
MEEFT
MEEFT
PNUD
PNUD
PNUD
UNDP/GEF
CELCO
CELCO, PMU
CELCO, PMU
CELCO, PMU
CELCO, PMU
SAGE
SAGE
SAGE
SAGE
SAGE
SAGE
SAGE
SAGE
SAGE
ANGAP
ANGAP
ANGAP
ANGAP
Ocean
Consultant
Ocean
Consultant
Biodev
Madagascar
Consulting
Andry
International
Consulting
C3EDM
C3EDM
Rgion Sofia
Rgion Sofia
DREEFT, Sofia
DREFFT, Sofia
Rgion DIANA
DREEFT, Diana
Rgion Atsimo
Andrefana
Rgion Atsimo
Andrefana
Rgion Atsimo
Andrefana
Rgion Atsimo
Andrefana
Rgion Atsimo
Andrefana
USAID
Madagascar
Nom et fonction
Mme Anitry Ny Aina RATSIFANDRIHAMANANA, Directeur de Conservation
Dr. Christopher HOLMES, Conseiller Technique Principal
M.
Mme Olina Hajamaina, Programme Protection et Gestion Durable des
Ressources Naturelles
Dr. Pascal Lopes, Programme Protection et Gestion Durable des Ressources
Naturelles
M. Serge Rajaobeline, Secretaire executif
*Membres de PF-ZAAP Maromandia
*Membres de PFR ED Sud
*Membres de FIMIMANO - Comit intercommunal de dveloppement Anakao
*Membres de FIMAMI (Mikea)
*Membres de PFIR Nord
Prince Arana IV (Maromandia)
*Full lists of participants are available and will be included by the PMU in the meeting minutes.
59
Organisation
WWF
Madagascar
WCS
WCS
GTZ
GTZ
FANAMBY
Listings (indicative)
MINENVEF
CELCO
ANGAP
SAGE
UNDP
Committee de pilotage
(national level)
Science & Economics
Group of Experts
2. Associated services
Consultants/ Bureaux
de recherch or
service
3. Relevant
environmental
organisations & donors
WB
GTZ
USAID
CI
WCS
WWF
Fanamby
WWF
- project design
- project impact
- project
implementation
Qualitative inputs into
evaluation
- project design
- project impact
- project
implementation
- general directives
- participatory solution
finding
60
Methods
- initial
qualitative
consultations/
fact finding
- formal review
templates
- participants in
regional and
local level
consultations
- final debriefing
discussion
- qualitative
consultations/
focal discussion
- qualitative
consultations/
focal discussion
- qualitative
consultations/
focal discussion
2.2 Field consultations will take place in both the northern and southern target areas. On
the regional and local level it is the following project institutions that will be consulted
(see attached programme, Annex 1):
a. Committees de pilotage (2 regional)
b. Platforms (2 north, 1 south)
c. Selected pilot sites/ communities (out of 13)
The final representation/membership at each of these institutions is to be confirmed with
Project Coordinator, Ms. Hanta Rabefarihy and field staff of SAGE.
3. Elaboration of tools: regional and local level
3.1Meeting/ work session program
All regional and local interactions are facilitated on site by SAGE. Representatives of the
project management level and the international consultant take part in the field visits
and in elements of the programme.
Each meeting/ work session is designed to contain the following elements:
a. Introduction by Project Coordinator (incl. technical site introductions; see Annex 2
moved to ANNEX 6 of this report), supported by SAGE
b. Institutions self introduction and presentation
c. Evaluation session (mixed group work and individual private sessions)
d. Next steps future outlook, based on locally developed (and regional) workplans
and priorities
3.2Evaluation sessions
1. General
understanding
1.1 Project objective
1.2 Own role in project
1.3 Purpose of
evaluation exercise
2.Self description/
overview of project
activities so far
2.1 Local level
2.2 Regional level
2.3 National level
3. Performance
evaluation and
solution finding
where required
3.1 Project design
3.2 Project impact
3.3 Project
implementation
4. Next steps - future
Committees de
Pilotage
- group discussion
Platformes
- group discussion
- group discussion
- group discussion
- group discussion
- group discussion
61
Site de references
- in plenary; to be
outlook
- Prioritization of
activities based on
prepared plans und
current/ updated needs
facilitated by project
coordinator and SAGE
facilitated by project
coordinator and SAGE
facilitated by project
coordinator and SAGE
Sessions 1 and 2 primarily serve the setting of the scene to get all members warmed up
for the evaluation exercise (session 3). However, these sessions will also provide a
qualitative assessment of project understanding (technical and organisational/
management) and thus provide useful information on project impact and implementation
success.
Session 3 will provide a more systematic evaluation input and focus on:
Committees de Pilotage
Question domain:
A. General project impact on
Capacity of beneficiaries
(individual & institutional)
o Regional
o Local
Livelihood improvements
Conservation success in
AP
Improved conservation
and sustainable use
service delivery
(decentralised extension
services)
Platformes
Question domain:
A. General project impact on
Capacity of beneficiaries
(individual & institutional)
o Regional
o Local
Livelihood improvements
Conservation success in
AP
Improved conservation
and sustainable use
service delivery
(decentralised extension
services)
Methodology:
Powerpoint/printed
questionnaire
Ratings (probably GEF scale)
Qualitative
remarks/descriptions
Question domain:
B. Institutional development
and support & content
Reference sites
Platforms/service
providers
AP-ZAAP interface
Quality of NR monitoring
programmes (scientific
group)
Quality of economic/
development proposals
(economic group)
Mobilisation component
Regulations and
enforcement
Methodology:
Powerpoint/printed
questionnaire
Ratings (probably GEF scale)
Qualitative
remarks/descriptions
Question domain:
B. Institutional development
and support & content
Reference sites
Platforms/service
providers
AP-ZAAP interface
Quality of NR monitoring
programmes (scientific
group)
Quality of economic/
development proposals
(economic group)
Mobilisation component
Policy framework
Regulations and
enforcement
Methodology:
Powerpoint/printed
Methodology:
Powerpoint/printed
questionnaire
62
Site de references
Focus on local level
implementation
1. Formation
2. NR monitoring
3. NR and livelihoods projects
1. Formation
- Institution well established?
- Just representation?
- Statutes satisfactory?
- Opportunities to participate
and benefit?
- Benefit sharing
arrangements?
- Quality of facilitation
support ?
- Skills development?
- Information facilitation?
questionnaire
Ratings (probably GEF scale)
Qualitative
remarks/descriptions
Question domain:
C. Information and training
Reference sites
Platforms/service
providers
AP-ZAAP interface
NR monitoring (scientific
group)
Livelihood opportunities
(economic group)
Skills development
Project per se
Methodology:
Powerpoint/printed
questionnaire
Ratings (probably GEF scale)
Qualitative
remarks/descriptions
Needs assessment
Question domain:
D. Project implementation
and execution
Implementation
arrangements and
capacities (MINENVEF,
PMU, SAGE, ANGAP,
platform members)
Functioning of various
organs including
Committee de Pilotage
Methodology:
Powerpoint/printed
questionnaire
Ratings (probably GEF scale)
Qualitative
remarks/descriptions
Needs assessment
Question domain:
D. Project implementation
and execution
Implementation
arrangements and
capacities (MINENVEF,
PMU, SAGE, ANGAP,
platform members)
Functioning of various
organs including
Platforms
Methodology:
Powerpoint/printed
questionnaire
Ratings (probably GEF scale)
Qualitative
remarks/descriptions
Priority assessment
Methodology:
Powerpoint/printed
questionnaire
Ratings (probably GEF scale)
Qualitative
remarks/descriptions
Priority assessment
Question domain:
C. Information and training
Reference sites
Platforms/service
providers
AP-ZAAP interface
NR monitoring (scientific
group)
Livelihood opportunities
(economic group)
Skills development
Project per se
2. NR monitoring
- Participation possibility in
model development process?
- Model understandable?
- Model needed?
- Types of tools that would be
helpful?
- Methods for communication/
tool delivery?
- Advise for application and
adoptability?
- Who can help?
- Quota setting and regulation
responsibilities?
- Quality of facilitation of
component so far?
- Proposals for improvement?
- Potential additional
partners?
3. NR and livelihoods
projects
- Plans represent community
priorities?
- Economic study
known/useful?
- If deviating from plan proposals for own priorities?
- Key constraints
- Support needed
- Useful component?
- Quality of facilitation of
component so far?
- Proposals for improvement?
- Potential additional
partners?
Session 4 is included to ensure that the project represents itself proactively and forward
looking. This is important as evaluations are often misunderstood as being policing
rather than supportive. It is critical to instil some enthusiasm in all project members and to
set the scene for effective and dynamic continuation of implementation.
63
Reference sitesZAAP
AP
Sud
AP1
Nord
AP2
AP3
AP4
Name
Marine/terrestrial
Key ecosystems to be
protected
Key data/ information
Primary conservation
value
Key threats to
conservation
Name
Marine/terrestrial
Key ecosystems to be
protected
Key data/ information
Primary conservation
value
Key threats to
conservation
Name
Marine/terrestrial
Key ecosystems to be
protected
Key data/ information
Primary conservation
value
Key threats to
conservation
Name
Marine/terrestrial
Key ecosystems to be
protected
Key data/ information
Primary conservation
value
Key threats to
conservation
Site/communit
y1
Site/communit
y5
Site/communit
y7
Site/community
Background
Name
Key data/ information
(socio-economic)
Land use systems
Primary conservation
threats
Key NRM and
conservation
opportunities
10
TBC
TBC
TBC
Site/communit
y6
Site/communit
y8
Site/community
11
Site/communit
y9
Site/community
12
Project
interventions to
date
NR monitoring
programme
NR management
and livelihoods
projects identified
Priority activities
(to be filled out at
workshop)
.
Site/communit
y2
TBC
Site/communit
y3
TBC
TBC
TBC
TBC
Site/communit
y4
TBC
TBC
Site/community
13
TBC
TBC
64
65
R.1 Il est recommand que les noncs suivants des objectifs de dveloppement et immdiats
guident la planification, le suivi et lvaluation du projet :
Objectif de dveloppement du projet : La gestion des ressources naturelles et la protection de la
biodiversit dans les corgions critiques sont tablies sur des bases relles et durables avec la
participation active des populations locales et des autres parties concernes, en mme temps que
les dimensions environnementales sont effectivement intgres dans la prise de dcisions
politiques et les dcisions dinvestissement.
Objectif immdiat du projet : Des systmes de gestion durable des ressources naturelles sont
tablis et renforcs dans les zones dappui aux aires protges.
4.3
R.2 Il est recommand que les sites de rfrence soient dlimits pour circonscrire lespace au sein
duquel seront cibles les ressources naturelles qui feront lobjet des mesures de gestion et de
conservation par les communauts ainsi que du suivi et de lvaluation de lefficacit des mesures
de gestion et de conservation. Il est possible que certaines des mesures prendre en vue de
rduire les pressions majeures sur ces ressources doivent tre conues et appliques lextrieur
des sites de rfrence.
4.3.4 Modles reproductibles de gestion durable des ressources naturelles
R.3 Il est recommand que le projet cherche dvelopper des approches en vue de concevoir des
mesures transposables de gestion des ressources naturelles plutt que des modles reproductibles
de gestion des ressources.
Considrant quelles seront mises en uvre ou appliques par les communauts locales, ces
mesures doivent tre conues pour demeurer simples et requrir peu de moyens.
4.4
Gestion administrative
4.4.1 Dlais des procdures
Planification
4.5.1 Programmation annuelle
R.7 Il est recommand la CELCO dlaborer un PLAN DE REPRISE en se servant du plan global de
travail comme cadre pour effectuer la planification annuelle 2007 et reprogrammer les activits du
projet en vue dassurer latteinte des rsultats attendus.
R.8 Il est recommand la CELCO de prparer le plan de travail annuel de travail selon le modle
prsent lannexe 8 et de prparer les fiches de sous-rsultats selon le modle prsent
lannexe 9. La version lectronique des matrices a t transmise la direction de la CELCO.
R.9 Il est recommand la CELCO dtablir les termes de rfrence pour les ententes contractuelles
sur la base de la planification annuelle prpare de manire concerte avec lensemble des
intervenants.
R.10 Il est recommand au PNUD de donner la possibilit la CELCO de reprogrammer la ralisation
du projet et den assurer la mise en uvre jusqu lvaluation mi-parcours laquelle, en fonction
de la progression du projet, valuera la pertinence dune extension de la priode de mise en uvre.
4.6
Les indicateurs dimpact et deffet pertinents du projet FEM (ils sont indiqus dans le cadre de
mesure du rendement propos en annexe 5).
Les indicateurs correspondant aux questions pertinentes du GEF Tracking Tool for GEF
Biodiversity Focal Area Strategic Priority One: Catalyzing Sustainability of Protected Areas
dvelopp par la BM et le WWF doivent tre intgrs dans le systme de suivi du rendement du
projet comme indicateurs dimpact. Leur valuation doit tre faite conjointement avec lANGAP
au moment de la cration de laire protge, mi-parcours du projet et la fin du projet.
LANGAP a dj complt les valuations de base pour les aires protges de Lokobe et de
Mikea. Aucune valuation na encore t mene pour Sahamalaza et pour le littoral de Tular
cette valuation pourra tre mene conjointement par ANGAP et le projet. Les questions
spcifiquement pertinentes aux contributions du projet sont les suivantes : 5, 7, 10, 11, 21, 22,
23a, 23b, 23c, 27a, 27b, 29, 30.
4.6.2 Cadre de mesure du rendement
R.12 Il est recommand la CELCO
4.7
Communication
R.14 Il est recommand la CELCO dadopter une stratgie de communication pour le projet
rpondant des objectifs dfinis et dvaluer les ressources requises pour sa mise en uvre en
termes de ressources humaines et financires.
La stratgie a t labore conjointement avec la CELCO ; la tenue de latelier du 28
septembre en fait partie. Les cots de mise en uvre de la stratgie doivent encore tre
dtermins pour tre en mesure de faire les prvisions budgtaires affrentes. La stratgie
de communication est prsente lannexe 6.
R.15 Il est recommand la CELCO dassurer une reprsentation adquate du projet aux runions
du comit conjoint du PE III, en prvoyant au moins la participation de la coordination technique.
R.16 Il est recommand la CELCO de faire le suivi ncessaire pour dvelopper les collaborations et
rduire les empitements en fonction des informations rcoltes au cours de latelier de promotion
du projet tenu le 28 septembre 2006.
R.17 Il est recommand au CoTP dassurer lenvoi systmatique des rapports de progression du
projet (administratifs et financiers) au MINENVEF et de formaliser les contacts avec les
reprsentants du ministre sur le terrain.
5. Prise en compte des recommandations mises lors de la prparation du PE III
R.18 Il est recommand la CELCO de prsenter les recommandations des missions de suivi et
dvaluation du projet la Coordination Gnrale des Projets du MINENVEF et au Comit de pilotage
qui les examinera systmatiquement et verra assurer le suivi des recommandations quil
acceptera.
6. Synergie et complmentarit du projet et de lANGAP dans les zones dintervention
R.19 Il est recommand la CELCO et lANGAP daccentuer leurs efforts de communication, de
systmatiser les changes dinformation concernant les 4 aires protges vises par le projet FEM,
et lANGAP de simpliquer dans le comit de pilotage national du projet, les dclinaisons locales
du comit de pilotage pour la gestion des aires protges et, lorsque appropri, dans les runions
de coordination du projet.
R.20 Il est recommand que le projet examine le choix des sites de rfrence de terrain en
concertation avec ANGAP pour assurer que les produits (mesures de gestion durable des ressources
naturelles et mise en place des structures de concertation en priphrie des aires protges) seront
cohrents avec la gestion des aires protges et quils pourront tre transposs dans les plans de
gestion de conservation des aires protges marines et ctires.
R.21 Il est recommand que les collaborations ou partenariats concernant lune ou lautre des 4
aires protges vises par lappui du FEM, soient le Parc marin du rcif de corail de Toliara / NosyVe, laire protge terrestre de la Fort des Mikea, le Parc national de Lokobe et le Parc marin de
Sahamalaza / Nosy Radama, soient tablis pour tre complmentaires aux initiatives prvues dans
le cadre du projet conjoint FEM BM-PNUD et viter de sy substituer, moins quil en soit convenu
autrement par lANGAP et par la CELCO.
7. Coordination des activits ralises par les diffrents intervenants (SAGE,
Scientifiques, conomistes) en vue datteindre des rsultats communs dans le cadre du
projet PNUD-FEM
7.1
R.22 Il est recommand que chaque organisation qui intervient dans la mise en uvre des activits
du projet identifie un interlocuteur de haut niveau pour assurer la coordination. Si lorganisation est
membre du Comit de pilotage national, il serait prfrable que cet interlocuteur en soit aussi le
reprsentant au sein du comit.
R.23 Il est recommand la CELCO de dynamiser la mise en uvre du projet sur le terrain
pour que les changes ncessaires entre SAGE, ANGAP, les scientifiques et les conomistes
du projet, les gestionnaires communautaires, les structures de concertation aux diffrents
niveaux, les responsables administratifs locaux de la gestion des ressources naturelles, et
68
les autres partenaires du projet autour des questions concrtes de conception des mesures
de gestion durable des ressources naturelles et de dveloppement des filires soient
fructueux,
permettre que les contributions de chacun des acteurs intervenant dans le cadre du projet
soient coordonnes de manire opportune,
et coordonner leurs interventions auprs des communauts, des structures et des autorits
locales et rgionales.
R.24 Il est recommand que SAGE assume un rle de facilitation et de coordination locale des
acteurs du projet, notamment pour les interventions menes auprs des communauts
7.3
Assistance technique
R.25 Il est recommand la CELCO dvaluer les besoins en capacits dans les domaines
dintervention du projet et de recruter des experts internationaux pour des missions de court
moyen terme en vue dapporter leur expertise aux diffrentes quipes impliques dans le projet et
de contribuer dvelopper les capacits nationales dans les domaines o des lacunes existent.
9. Capacit des structures de concertation tre des co-gestionnaires en vue de la
conservation de la biodiversit
R.26 Raliser une tude pour dterminer quel serait le statut lgal appropri pour le noyau excutif
ou un sous-groupe actif dune structure de concertation qui leur permettrait de raliser des
prestations de services en vue de gnrer des bnfices dont un pourcentage fixe serait vers dans
un fonds propre la structure de concertation. De tels revenus pourraient assurer le
fonctionnement du bureau excutif et pourraient couvrir les frais ncessaires la mobilisation de la
structure de concertation lorsque cette mobilisation est requise. Ce droit de faire des bnfices
pourrait tre accord au noyau excutif ou un sous-groupe actif sous condition de poursuivre la
coordination et le suivi de la mise en uvre des activits ou des projets qui contribuent mettre en
oeuvre la planification environnementale effectue avec lappui du PE (II et III) et de dynamiser le
processus de concertation en assurant la mobilisation de lensemble des reprsentants prvus dans
la structure de concertation lorsque requis pour la planification et la mise en uvre du
dveloppement.
10. Orientations/recommandations relatives aux inventaires biologiques
R.27 Il est recommand au CoTP de sassurer que les termes de rfrence des scientifiques
concernant les travaux dinventaires biologiques permettront de fournir les informations prsentes
dans cette section et de sassurer de luniformisation des mthodes dinventaire dans les diffrents
sites de rfrence lorsquelles sappliquent aux mmes types de ressources.
Table : Responses to recommendations made during 1st Year Evaluation and their relevance to date (this is
complementary to a in-depth report prepared by the PMU)
Rec. Response
Rec. Response
R.1
The overall development objective is fine adn
R.15 Representation mainly through Head of
in line with the ProDoc.; for the project
CELCO; will/should now change in line with
objective it is recommended to accept the text
new project structures; it is recommended that
from the 1st Year evaluation, which has also
the PMU is directly represented;
been reflected in the PIRs
Committee Conjoindre has not been operational
for a while
R.2
Done by Scientific Group for 13 sites; new
R.16 Not clear
issues arise due to evolving needs by
ANGAP
R.3
Recommendation still valid; related to need for R.17 Still relevant; stronger peer mechanism required
common vision and understanding of SNRM
Models; needs to be revisited
R.4
Proposed project structures basically not
R.18 Not clear, but has probably taken place
operational; should be urgently revisited
(based on 1st Year and Mid-term evaluation
reports)
69
R.5
R.6
R.7
R.8
R.9
R.10
R.11
R.12
R.13
R.14
R.19
R.20
R.21
R.27
R.22
R.23
R,24
R.25
R.26
70
ANNEX 6: Itinerary
Draft field programme (prepared by Project Coordinator and SAGE in consultation with
others)
PROGRAMME DE MISSION DEVALUATION : ZONE NORD
JOUR
Lundi
Mardi
DAT
E
05
mai
06
mai
HEUR
E
04H
19H
09H
14H0
0
Mercre
di
Jeudi
Vendre
di
Samedi
07
mai
08
mai
09
mai
10
mai
09H0
0
15H0
0
10H0
0
16H0
0
08H3
0
11H3
0
12H3
0
09H0
0
20H0
0
ACTIVITE
Dpart dAntananarivo par voiture
Arrive Antsohihy
Rencontre avec la Rgion
(Chef de Rgion et DDR)
Rencontre avec DREEFT
Rencontre avec Maire
LIEU
Ramassage
domicile
Antsohihy
Maromandia
Maromandia
Ankitsika
Ambanja
Antsatrana
Ankify
Nosy-Be
Aroport de
Fascne
Ambanja
Mercre
di
Jeudi
Vendre
DAT
E
12
mai
13
mai
14
mai
15
mai
16
HEUR
E
04H0
0
09H0
0
14H0
0
09H3
0
10H0
0
07H0
ACTIVITE
Dpart dAntananarivo par voiture
Dpart dAntananarivo par avion
Rencontre avec la Rgion
(Chef de Rgion et DDR)
Rencontre avec DREEFT
Rencontre avec DIR/ANGAP
Visite de site de rfrence et changes avec les communauts
locales de base
Sance de travail avec la PF/ZAAP Mikea
Nuite Ifaty
Sance de travail avec la PF Rgionale sud
Rencontre avec la Rgion
(Chef de Rgion et DDR)
Dpart sur Nosy-Ve
71
LIEU
Ramassage
domicile
Ivato
Toliara
Ranobe
Ankililaoka
Ifaty
Toliara
di
mai
0
14H0
0
Samedi
17
mai
06H3
0
09H0
0
Nosy-Ve
Anakao
Nuite Anakao
Retour sur Toliara
Sance de travail avec le Comit de pilotage rgional sud
Retour sur Antananarivo par avion et/ou par terre
72
Toliara
3.
4.
Qualit des programmes de suivi des ressources naturelles (par les scientifiques)
Bonne qualit
5. formation
rien signaler
6.
Amlioration de la gestion
Connaissances des sites de rfrence
Plate-forme :
73
Sur le Projet :
Informations trs dtailles sur le Projet
Autres :
Connaissances des autres Projets oeuvrant dans le secteur Environnement dans la rgion
Octobre 2007
Collge : autorite/ notable/ oprateurs conomiques/ reprsentant bureaucrate/
agriculteurs/ leveurs/ associations
PROBLEMES RENCONTRES
Moyens de dplacement
Moyens financiers
Mesures daccompagnement insuffisantes par rapport la rduction des pressions au niveau
des ressources naturelles (exploitation de charbon de bois)
Solution propose par la Rgion : transformation des bois de la fort dAntanimieva
en charbon de bois
Existence de feux de brousse (feux sauvages et feux provoqus) lintrieur et lextrieur
de lAP
Dfrichement lintrieur de lAP
Exploitation illicite lintrieur de lAP surtout
Existence de voyants-voyants
Souhait du PF : mise en place permanent dun agent forestier dans la zone
Souhait du PF : mise en place rapide du ZUC et ZOC
Manque de sensibilisation pour le transfert de gestion / demande dj au niveau de lANGAP
MESURES ALTERNATIVES :
75
76
Sur le Projet :
Formation sur le management
Autres :
Formation pour toutes les parties prenantes
Autres partenariat
REEF DOCTOR
5.PRIORITS
Plein pouvoir pour le PF
Financement
Dotation en appareil relatif la conservation
(4) Platform Inter-regionale (PFIR) (Nord)
PFIR
Plate Forme Interrgionale SOFIA/DIANA
SANDOKO
PF/ZAAP ANKIBA
PFED NosyBe
CRADES Ambanja
ROSEDA Ambilobe
1re Commission
Planif/Suivi/Eval
- ZENY Jacques
- RasolofomananaR.
Bureau E.
1 Pdt
1 Vice Pdt
1 SG
1 Trsorier
PF/ZAAP SAHAMALAZA
AMIZA Akaramibe
Maetsamalaza Maromandia
MEVAMAMY Befotaka
VOLAMAITSO Ambolobozo
Tsaravintana
Anorontsangana
COMITE DE COORDINNATION
2me Commission
3me Commission
Gestion de conflits,
Communication Lobbying
Rglementation textes Plaidoyer
Dina
-
Donn
Arnaud
77
Toussaint J.P
DDR Sofia
- Edmond Ramadany
- TIARIM
- ZAMANY Ruffin
Lucie
Radinera
Camille
Abdel Kadert
Jean de Dieu
Boto Ignace
Robert Guy
Mandiny R.
A.G
B.E.
COMITE DE COORDINNATION
1re commission
2me commission
3me commission
78
79
AP
Reference sitesZAAP
Sud
AP1
Site/communit
y
Name : MIKEA
Marine/terrestrial : Terrestre
Key ecosystems to be protected : Forts sches et pineuses
Key data/ information : 170.000Ha en AP Temporaire
Primary conservation value : 140.000Ha de forts, population autochtone
Key threats to conservation : coupe illicite aux fins de charbon et champ de culture, trafic
des faunes endmiques, pntration de la civilisation moderne
Site/communit
y1
Site/communit
y2
Site/communit
y3
RANOBE
AMBOBOKA
SEPT LACS
Background
Name :
Key data/
information (socioeconomic)
96 tots 538
habitants
42% analphabtes
90% des mnages
vulnrables
(0,25USD per
capita/jour)
Inscurit (vol de
bufs)
Insuffisance eau
potable
Plusieurs groupes
ethniques
Cultures vivrires :
manioc, mas, patate
douce, lojy
Culture de rente :
canne sucre
Elevage : bovins,
ovins, caprins
Pche continentale
Collecte et vente RN
vondro (cypraces),
tubercules, katrafay,
miel
Exploitation du bois
(usage mnager,
mdicinal, rite
ancestral, vente)
Exploitation minire
par Ilmnite
Madagascar
Ressources
Primary conservation
threats
13,5Ha/an
dgradation pour
cause exploitation
illicite, sauvage, feu
96 tots 744
habitants
42% analphabtes
90% des mnages
vulnrables
(0,25USD per
capita/jour)
Inscurit (vol de
bufs)
Insuffisance eau
potable
Plusieurs groupes
ethniques
80
de brousse
Chasse pour
consommation des
lmuriens, tenrecs,
Key NRM and
conservation
opportunities
7.848,5ha de forts
avec 90 espces
floristiques dont 12
endmiques
faunes endmiques :
Amph.& reptiles :
87,5%
Oiseaux : 53%
Mammifres : 80%
Project
interventions to
date
NR monitoring
programme
Suivi technique :
Suivi cologique :
Suivi socioconomique
NR management
livelihoods
projects
identified
Diagnostic des
ressources et
milieux : menaces,
pressions
Inventaire biologique
Evaluation des
stocks
Identification des
filires
Etude de march
Suivi de
lexploitation : quota,
mthode de coupe,
dbardage,
stockage
Faune : observations
priodiques des
paramtres
biophysiques, , suivi
des impacts de
lexploitation sur
lcosystme
Flore : idem + suivi
des plantations de
remplacement
Observatoire socioconomique :
volution des
budgets du VOI,
mnages, gestion
des conflits)
Suivi intgration
rgionale de la filire
(commerce,
partenariat)
Rglementation de
lexploitation du bois
(rduction, arrt de
lexploitation
sauvage), Protection
des espces en voie
dpuisement (quota
de prlvement)
Rgnration et
reconstitution de
lhabitat (respect des
zones de coupe)
Appui en matire de
debouchs pour les
vondro, tubercules,
katrafay, miel
81
Appui
lamlioration des
techniques
dexploitation des
bois
Priority activities
(to be filled out at
workshop)
AP
Reference sitesZAAP
Nord
AP3
Site/communit
y
Site/communit
y1
Site/communit
y2
Site/communit
y3
SEPT LACS
ANKITSIKA
Ile de Berafia
Antsahampano
Antsatrana
Background
Name :
Key data/
information (socioeconomic)
516 habitants
97 pcheurs
188 agriculteurs
19 autres mtiers
Plusieurs ethnies
Inexistence
dinfrastructure de
sant de base
3200 habitants
540 mnages
998 pcheurs plein
temps
95 agriculteurs
Pche : crabes
essentiellement
(91), petits poissons
plagiques et
poissons deaux
ctires (17)
Culture de riz :
rizire et tavy
Culture vivrire :
mas, manioc
Elevage : zbus et
Plusieurs ethnies
Inexistence
dinfrastructure de
sant de base
82
chvres
Primary
conservation threats
Dgradation des
mangroves cause
de la coupe de bois
pour droit dusage
et destruction des
terriers des crabes
au crochet, peu de
repousse
Surexploitation des
ressources en
crevettes
Crise au niveau
mondial : forte
conccurrence, dclin
des prix du march
international
Dclin du
rendement de
production de petits
poissons
(surexploitation)
Pche aux crevettes
par les migrants
quips en engin de
pche
Key NRM and
conservation
opportunities
Superficie de
mangroves non
encore bien
dtermine avec
partie intrieure
encore intacte, sans
aucun signe
densablement ou
de pollution
Superficie de
1000Ha mangroves
avec partie intrieure
intacte et en bonne
sant
500ha de zone de
pche traditionnelle
1200 ha de forts
secondaires, de
ravinala et de zone
de culture
Flore :
04 espces de
paltuviers
Flore :
04 espces de
paltuviers
Project
interventions to
date
NR monitoring
programme
Suivi technique :
Faune : oiseau (5 sp
dont 3 endmiques)
mammifres
terrestres (2sp)
reptiles (2sp)
mollusques (4sp)
crustacs (4sp),
poissons (9sp)
Diagnostic des
ressources et
milieux : menaces,
pressions
Inventaire biologique
Evaluation des stocks
Identification des
filires
Etude de march
Faune : oiseau (1
sp) mollusques
bivalves (2 sp)
mollusques (1sp)
crustacs (4sp),
poissons (7sp)
Diagnostic des
ressources et
milieux : menaces,
pressions
Inventaire
biologique
Evaluation des
stocks
Identification des
filires
Etude de march
suivi journalier de la
production
halieutique
(2 fois par an HS et
suivi journalier de la
production
halieutique
(2 fois par an HS et
83
Suivi cologique :
Suivi socioconomique
NR management
BS)
Suivi permanent des
ressources (cahier
de pche et de
vente des pcheurs)
Inventaire des rcifs
et mangroves :
recherche des
espces
faunistiques
endmiques, rares
et vulnrables, des
espces
envahissantes
BS)
Suivi permanent des
ressources (cahier de
pche et de vente
des pcheurs)
Inventaire des rcifs
et mangroves :
recherche des
espces faunistiques
endmiques, rares et
vulnrables, des
espces
envahissantes
suivi biostatistique
aux fins de
propositions des
mesures
damnagement de
la pcherie de
chaque ressource
suivi biostatistique
aux fins de
propositions des
mesures
damnagement de
la pcherie de
chaque ressource
Enqute cadre
village :
Mode dexploitation,
dorganisation,
commerce,conflits
Prservation de
ltat de mangroves
Enqute cadre
village :
Mode dexploitation,
dorganisation,
commerce,conflits
Prservation de ltat
de mangroves
Application de
larrt ministriel
portant sur le mode
dexploitation des
crabes
Respect de larrt
ministriel portant
sur le gel de pche
sur la crevette ctire
dans la zone
Introduction de
nouvelles
techniques de
pches aux crabes
Retrait de lengin
pige, modification
du maillage des filets
Application de
larrt ministriel
portant sur le mode
dexploitation des
crabes
Maintien de leffort
de pche aux petits
poissons plagiques
et revue des mailles
des filets
Exploitation
rationnelle des
crabes encore
abondance par
lintroduction
dengins de pche
performants
(palangres, balance)
Mesure rgalienne
pour adresser la
surexploitation des
crevettes par les
pcheurs migrants
Oprationnalisation
du systme ZAC
travers les platesformes
And livelihoods
projects
identified
Priority activities
Reconversion de
certains pcheurs de
crevette en pcheurs
de crabes
Pche la ligne
palagrotte aux crabes
Pche au filet periky
aux poissons
Pche la ligne aux
poissons
Pche aux crabes
84
dans chenaux de
mangroves et en
mer (formation des
pcheurs, appui
lacquisition des
matriels de pche
et la
rgularisation du
circuit de collecte)
85
Baseli
ne
Target
Indicateur 1:
SNRM
not
part of
develo
pment
planni
ng in
comm
unties
At least
one fully
functioning
multistakeholde
r platform
with
capacities
for
integrated
developme
nt planning
exist for
each PASZ
10 Plans Communaux de
Dveloppement sont en cours de
rvision pour vrifier lintgration des
considrations environnementales et
sassurer que les plans de
dveloppement aux diffrents niveaux
au sein des zones dappui aux aires
protges sont cohrents avec
lapproche de gestion intgre des
zones ctires (GIZC).
La gestion
durable des
ressources
naturelles
compatible avec
la conservation
de la biodiversit
est intgre dans
les plans de
dveloppement
des zones
dappui aux aires
protges.
La reprsentativit de 4 structures de
concertation a t value en termes
gographique et de parties prenantes.
Leur capacit laborer des plans de
dveloppement conformes
lapproche GIZC a aussi t value.
No.(?) partner CLBs have been established in the four AP/ZAAP systems; Xxx of them have work plans
4 PF ZAAPs established with constitution and workplans
1 PFIR (North), 1 PFR (South) established; PFIR has workplan, PFR workplan to be established, priorities
identified
Inputs into PCDs; 10 Green PCD exist (by 2006 10 PCD vertes; same figure recorded in 2008)
4 GIZC plans integrate relevant communities (Nord 15, Sud 5; see reference in APR 2008)
Participatory evaluation with committee members at all levels indicates
o
Good ownership and interest
o
Understanding of project objective to be conservation of NRs & AP
o
Got involved in some very relevant work (esp. in relation to policy debate)
o
Need to now get more involved in practical work
o
More information and capacity support needed to address mandate
o
Seen as useful governance plat form by regional government (not necessarily limited to NR and
AP-ZAAP)
Capacity needs assessment partially reflected in workplans, and in outcomes of consultative meetings
(May 2008; reference meeting reports)
Strong work of SAGE to be recognised; needs reinforcement of outreach capacities
14
The PIR 2006 establishes baseline levels and target levels for all indicators; additional indicators and their baseline and targets were included in the PIR 2007; current indicator 7 was
newly introduced in PIR 2007
86
Indicateurs
Baseli
ne
Target
Indicateur 2:
Weak
instituti
onal
capacit
y and
seriou
s
govern
ance
issues
Strategies
for
improved
enforceme
nt &
oversight
of SNRM
related
laws/
regulations
are
completed
for each
PASZ
Dina system largely applied esp. in Northern areas; generally well accepted and seen as beneficial;
however some problems with lack of authority to prosecute offenders (e.g. people from outside that come
in to the Mangroves to cut wood at Sahamalaze) at this stage (participatory evaluation); absence of
systematic documentation and synthesis of experience, which should be a priority for GM
Mixed experiences and views on GELOSE experiences at sites beneficial (participatory evaluation); CLB
and other local and regional representatives found system generally useful and are interested in expanding
it, however major bottlenecks identified include (i) limited capacity by MEEFT/DREEFT to follow up on
M&E and extension of contracts, (ii) in certain areas no real benefits from Transfer of Management
realised, communities need guidance on how to capitalise on opportunity as well as guidance on
responsibilities; absence of systematic documentation and synthesis of experience, which should be a
priority for GM
ANGAP is experimenting with additional models (e.g. payment for services; to be included in
experimental design as appropriate (joint planning with ANGAP); absence of systematic documentation
and synthesis of experience, which should be a priority for GM
In Northern areas (through PFIR) addressing of mandate conflict in Mangrove areas, which are managed
by MAEP/DRDR whilst GELOSE is implemented under MEEFT/DREEFT; PFIR has facilitated dialogue
and furthered joint experimental approach; absence of systematic documentation and synthesis of
experience, which should be a priority for GM
Similar issues relating to MPA in Southern area (Nosy-Ve/Toliare) arising between MAEP/DRDR and
MEEFT/DREEFT, however still in the early identification phase; absence of systematic documentation and
synthesis of experience, which should be a priority for GM
SAGE, an association established during PE2 in support of MEEFT to facilitate community interaction and
engaged as project implementer of the PNUD-FEM component has successfully established the required
community structures; however the contract and annual workplan of SAGE for 2008 has not been
extended by MEEFT; at this stage (May 2008) there seems to be very limited political support for SAGE as
currently operating and sustainability issues of the approach need to be urgently addressed
Overall implementation capacity of STD (Extension Services) seen to be extremely limited, and an
improved strategy has to be put into place; MEEFT has recently taken new strong leadership on this
element (see letter to PNUD, dated early May); regional ownership and interest generally quite well
developed and could be strategically supported in future
87
Indicateurs
Baseli
ne
Target
Indicateur 3:
Les plans de
conservation sont
dvelopps et mis
en uvre
Isolatio
n of
Pas
surrou
nded
by
forest,
bush
field or
severe
ly
degrad
ed
ecosys
tems
that
are not
ebing
allocat
ed to
conser
vation
compa
tible
land
uses
Participator
y planning
and joint
manageme
nt of
PASZs
Local level (CLB) conservation plans integrated into overall CLB workplans; in certain cases (participatory
evaluation, qualitative) the conservation component seems very strong and an overall god understanding
of the conservation objective of the project and the AP-ZAAP system is quite well understood amongst
community members and other PF representatives (see knowledge/awareness baseline Annex 10)
Scientific support surveys were conducted during 2006/2007, and finalised in July 2007; they are basically
reports on inventory/status data and recommendations for monitoring methods, however since completion
of the baseline work no follow-up has taken place (since July 2007); this is probably for various reasons (i)
scientific baselines and methods, not applicable to participatory local level monitoring in current form; (ii)
could be used for STD, if institutions ready for such expert input; (iii) may need to commission follow-up
studies if current capacities not sufficient to embrace methodologies; project should seek for pragmatic
solution; at this stage simply blocked since about 1 year; seen to be very damaging for project
ANGAP has developed own methods, which at this stage seem not compatible/aligned with work
undertaken in this component (PNUD-FEM); recommendations for Joint Work Plan and closer technical
collaboration have been made during participatory evaluation; also true for work carried out by other
service providers (e.g. WWF, WCS); GM component should facilitate better coordination and exchanges to
ensure (i) limited duplication, (ii) high technical quality, (iii) efficient use of resources
88
Indicateurs
Baseli
ne
Target
Indicateur 4:
La superficie
couverte par les
mangroves dans
les 2 zones
dintervention du
projet est
maintenue au
niveau de celle de
2004
correspondant
2 209 km2
2,209
km2 in
2004
2,209 km2
No data provided.
However, overall SAGE has engaged with xxx CLBs and relevant CLB networks in the areas concerned (APZAAP Sahamalaze & Lokobe) and the participatory evaluation (qualitative) indicates an overall god level of
understanding of conservation value in the areas, as well as the overall notion is that conservation efforts have
increased and are successful (reference: minutes from workshops)
Indicators 4.a and 4.b proposed in PIR 2007 based on work of Scientific group:
Description
of indicator
4a.The
surface
within the PA
and the dry
and spiny
forests in the
PASZ is
maintained
at the 2006
level.
4b. The rate
of recovery
of living
coral is
maintained
at the 2006
level in the
southern
and northern
area of the
project
Baseline level
Target level
Forest surface:
140,000 ha, within a
surface of Protected
Area of 200,000 ha
Reference site
Forest in ha.
Amboboka: 1,286
Ranobe: 7,530
Sept Lacs: 4,513
Still to be determined
in agreement with
ANGAP
Southern Area:
Nosy Ve
Aquarium A: 30% of
2006
Ifaty
Jardin des Roses:
50% of 2006
Northern Area:
Degraded area reef
platform between
10% and 30%.
Area more or less
intact:
Reef front between
60% and 75%
Nosy Ve
Aquarium A: 40%
Ifaty
Jardin des Roses:
60%
Nosy Ve
Aquarium A: 30% of 2006
Ifaty
Jardin des Roses: 50% of 2006
Degraded area:
Reef platform
between 20 and 40%
Degraded area:
Reef platform
between 10 and 30%
Reference site
Forest in ha.
Amboboka: 1,286
Ranobe: 7,530
Sept Lacs: 4,513
No monitoring/assessment data available after June 2007! Activity discontinued/blocked since July 2007.
Mikea park boundaries verified since June 2007; Nosy Ve boundaries currently under revision.
Important to link to actual community and regional level conservation activities implemented; here baseline
model for M&E established.
The final M&E plan is required; some baseline values seem problematic, as well as targets seem not always
well set; god framework to work from, but could do with some improvement. Of course the actually monitoring is
NB. The quality of ANGAPs monitoring system needs to be established, as well as that of other indicated
partners.
89
Indicateurs
Indicateur 5:
Lvolution dans la
prsence et/ou
labondance
despces
indicatrices au
sein des niveaux
suprieurs de la
chane trophique,
telles les espces
prdatrices de
grande taille de la
famille des
Lutjanidae
Baseli
ne
Target
Target level
Nosy Ve
Aquarium A :
Family of Lutjanidae: 3
species; Lethrinidae: 2
species; 4 other families
Nosy Ve
Aquarium A :
Family of Lutjanidae: 3 species
Lethrinidae: 2 species
Families of Lutjanidae:10
species; Lethrinidae: 4
species
Families of Lutjanidae: 10
species; Lethrinidae: 4 species
No monitoring/assessment data available after June 2007! Activity discontinued/blocked since July 2007.
Although the indicator framework is generally rated as useful, certain questions arise e.g. in term of can we
actually expect the increase the families present over the time period? Is the established system practical?
Existing monitoring systems (e.g. ANGAP) need to be checked.
90
Indicateurs
Indicateur 6:
La
prsence/absence
despces
indicatrices
(maintenue,
accrue ou
diminue selon le
type despce
indicatrice15) dans
les sites o la
conservation et la
GDRN sont mises
en oeuvre
(indicateur dfini
sur la base des
recommandations
des scientifiques)
Baseli
ne
Target
Target level
Nb sp flore endemic
Amboboka: >=17
Ranobe
: >=12
Nb sp flore endemic
Amboboka: 17
Ranobe
: 12
Nb sp fauna endmic
Amboboka: 61
Ranobe
: 74
Zone South: EMC Nosy Ve
Aquarium A Degradation indicator
species:
- Acanthaster plancii: 06
individuals
- Echinometrix diadema: 25
individuals
Nb sp faune endemic
Amboboka: >=61
Ranobe
: >=74
Nb sp faune endemic
Amboboka: 61
Ranobe
: 74
Nosy Ve
Aquarium A
Degradation indicator species:
- Acanthaster plancii: 01
individual
- Echinometrix diadema: 10
individuals
Nosy Ve
Aquarium A
Indicator of degradation:
- Acanthaster plancii: 06 individuals
- Echinometrix diadema: 25
individuals
North Zone
Degradation indicator species
Diadema set osa
between 20 and 22 individuals/m2
Endangered species: 1 whale
specie (Megapteres)
Species under strong pressure
from fishing:
Family of Chanidae: 1 sp
Family of Holothuries: 5 sp
Family of Raies: 1 sp
Family of Crabs: 1 sp
Family of Lutjanidae 2 sp ;
Family of Lethrinidae: 2 sp
Family of Mugilidae: 1 sp
Family of Teraponidae:1sp
Family of Salmonidae:1 sp
No monitoring/assessment data available after June 2007! Activity discontinued/blocked since July 2007.
The indicator system seem quite strong, however can we actually expect the increase of endemic species over
the time period? Would we not rather need other indications like the 20 to 22 individuals per m2 seems okay. Is
the established system practical? Nedd to check also other existing monitoring systems (e.g. ANGAP).
Les espces indicatrices peuvent inclure des espces menaces dont on souhaite maintenir ou accrotre labondance par la
conservation, des espces qui subissent une pression non durable dont on souhaite maintenir ou accrotre labondance, des espces
indicatrices de la dgradation du milieu ou du dsquilibre de la chane trophique ou des espces introduites envahissantes dont on
souhaite rduire labondance. Ces espces et les objectifs de gestion et de conservation seront dtermins par les groupes de
scientifiques le plus tt possible.
91
15
Indicateurs
Indicateur 7:
Amlioration de
lindice defficacit
globale de gestion
des 4 aires
protges
appuyes par le
FEM
Baseli
ne
Target
Target level
Will be established by
ANGAP.
No monitoring/assessment data available after June 2007! Activity discontinued/blocked since July 2007.
Is the established system practical? How compatible are they with ongoing work at ANGAP?
92
Indicateurs
Baseli
ne
Target
Indicateur 8:
Nombre de
mnages dont les
revenus
proviennent de la
collecte de
ressources
sauvages et qui
participent la
gestion durable
des ressources
naturelles dans les
deux zones cibles
du projet
3,000
house
holds
21,500
households
Target level
21,500 households
Amboboka
Bois: 70 households
Typha: 100 households
Ranobe
Bois: 96
Typha: 96
Amboboka
Bois: 0 households
Typha: 29 households
Ranobe
Bois: 0 households
Typha: 77 households
Number of households:
>= 1,569
Number of households: 00
93
Indicateurs
Baseli
ne
Target
Indicateur 9:
Prise en compte
de la position des
communes dans la
gestion des aires
protges
travers des
structures de
gestion
participative
pleinement
oprationnelles,
illustr par le
pourcentage de
COSAP qui
respectent leurs
droits et
obligations tels
que dfinis dans
les plans de
gestion des aires
protges
0%
80%
PIR 2007 states following : In March 2007, Sahamalaza received official certification as a marine and coastal
protected area, with full support by local communities, thanks to intense work by IEC. The next phase,
establishment of the COSAP, being carried out progressively, with work and back up by IEC, and consequently,
is not yet, to date, fully operational.
Indicateur 10:
Renforcement des
communauts en
GDRN travers la
pleine excution
des dispositions
GELOSE/GCF, tel
que mesur par le
% des
communauts
ayant bnfici de
transferts et qui
ont protg leurs
ressources avec
succs la fin de
la priode de
probation de 3
ans. Le succs de
la protection des
ressources est
dtermin lors des
valuations
programmes
avant le
renouvellement
des contrats
0%
Comment on the indicator: Is it practical to establish %? How many COSAP are there and how many will be
established?
80%
PIR 2007 states following : The evaluation of the resource management transfers (GELOSE) of the 13 reference sites has
not yet been carried out. It is the responsibility of the Ministry of Environment, Water and Forests. The Ministry of
Environment, Waters and Forests Min. Env. EF-is informed of the situation. Within the context of internal
restructuring/reorganization, it is expected that the Minister carry out actions henceforth.
Comment on indicator: Is it practical to establish %?
94
Indicateurs
Baseli
ne
Target
Indicateur 11:
% des utilisateurs
qui considrent
que les services et
produits pour la
gestion des
connaissances en
GDRN rpondent
leurs besoins
0%
70%
PIR 2007 states following : The relocation of scientific and economic research vis a vis the communities and the local
and regional authorities has allowed one to judge the conformity of the stakeholders regarding the project. 89,22% are
globally satisfied.
Indicateur16
Comnent on PIR data: generally it is nonsense to establish a percentage such as 89,22% in this context
Comment on indicaotor: Is it practical to establish %? What is the reference point? Need acknowledge
awareness baseline (see Annex 10)
Comments from evaluation meetings: generally in May 2008 at local level no ownership and engagement
valuation
Ralisations au 31 Mai 2008
du progrs
Rsultat 1 La GDRN et la conservation de la biodiversit sont amliores dans les zones dappui aux aires protges par leur intgration dans la planification du dveloppement
Indicateur 12:
There exist:
At least 1 multi
Existing platforms (from PE2) re-structured and mandates
Une stratgie de renforcement des
- A plan for the
stakeholder
updated;
capacits ciblant les besoins spcifiques
Pourcentage
spiny forest
platform (forum)
16
Baseline
Targets
valuation
du progrs
Indicateur
Baseline
Targets
valuation
du progrs
Indicateur 13:
Diminution du
nombre
dinfractions
judiciaires grce
la mise en
vigueur des
textes relatifs
la GDRN et la
surveillance
effectue par les
plates-formes
des parties
prenantes
No historical
base-line data
on registered
legal
infractions on
environment.
% of conflicts
registered that
have been
resolved through
the multistakeholder
platforms.
valuation
du progrs
Rsultat 2 Les approches dveloppes dans les sites de rfrence de terrain pour dfinir les mesures appropries de conservation de la biodiversit, de GDRN et pour le dveloppement de filires de
biodiversit durables et rentables, sont reproduites dans les zones dappui aux aires protges
96
Indicateur
Baseline
Targets
Indicateur 14:
- 6 of the coral
reef
laboratories
have
established
basic rules
(dina) to put
an end to
destructive
practices
- 2 laboratories
in mangroves
have simple
community
based
management
systems
- some of the
laboratories in
the forests
have simple
zoning plans
Management
plans and systems
for biodiversity
compatible SNRM
systems are in
place in replication
(pilot) sites
Nombre de
structures de
gestion
communautaires
qui mettent en
oeuvre des
mesures durables
et rentables de
gestion des
ressources
naturelles qui
contribuent la
conservation de la
biodiversit dans
chaque
cosystme, en
plus des
communauts
concernes par
les 13 sites de
rfrence de
terrain
valuation
du progrs
None of the
baseline
initiatives can
show
ecological or
economic
sustainability.
97
valuation
du progrs
Indicateur
Baseline
Targets
Indicateur 15:
Diminution du taux
de perte de
couverture
forestire dans les
zones dappui aux
aires protges
relativement aux
tendances
observes pour la
priode de
rfrence.
Forest cover
loss rates in the
Toliara region
have always
been among
the highest
ones in the
country.
A SNRM system,
that includes a
monitoring and
evaluation
component thus
enabling the
measurement of
coverage, is kept
for each field lab.
(pilot area).
[expanded to
ecosystems in
PIR/ impact
indicators above/
apply here too]
No established
criteria for
defining
appropriate
institutions for
SNRM.
Capacity
assessments
are not done in
any organized
fashion
valuation
du progrs
The capacity of
community
institutions for
SNRM are
assessed annually
& modified as
needed.
Comments:
13 new reference sites have been proposed by ANGAP within
the Mikea PASZ in view of reinforcing scientific, economic and
socio-organisational support to the development of PA as well as
its conservation.
98
valuation
du progrs
Indicateur
Baseline
Targets
Indicateur 16:
Absence of
reliable
scientific data
on indicator
species
The presence of
indicative species
for the target
ecosystems is
verified.
Presence maintained
for health ecosystem
indicator species on
all field reference
sites.
Prsence ou
absence
despces
indicatrices de la
sant cologique
dans les sites de
rfrence de
GDRN
valuation
du progrs
99
valuation
du progrs
MU
Indicateur
Baseline
Targets
valuation
du progrs
Indicateur 18:
Lefficacit des
zones
prlvement zro
est dmontre par
lvolution dans la
prsence et/ou
labondance
despces
indicatrices des
niveaux
suprieurs de la
chane
alimentaire, telles
les espces
prdatrices de
grande taille de la
famille des
Lutjanidae, au
sein et hors des
zones de pche
100
valuation
du progrs
Indicateur
Baseline
Targets
Indicateur 19:
A fairly large
number of field
practitioners
are working on
SNRM
throughout the
country, but
without
systems which
are organized
for knowledge
generation and
sharing
A national facility
for collecting,
analyzing, and
distributing SNRM
related knowledge
for practitioners
and decision
makers is
established &
effective.
Un systme de
gestion des
connaissances
permet de
rassembler et
danalyser les
informations
conomiques,
cologiques,
sociales et
techniques
relatives la
GDRN pour les
principaux
cosystmes de
Madagascar.
Indicateur 20:
Suffisamment
dinformations et
de connaissances
sont accumules
pour permettre de
transposer les
approches
permettant de
concevoir des
mesures de
gestion durable et
rentable des
ressources
naturelles dans
les principaux
cosystmes
naturels de
Madagascar.
Inadequate
knowledge on
sustainable
natural
resource
community
based
management
among the
stakeholders
at various
levels,
regarding the
coral reefs, the
lagoons, the
spiny forests,
the
mangroves,
and the other
natural
ecosystems in
Madagascar.
valuation
du progrs
101
valuation
du progrs
Indicateur
Baseline
Targets
valuation
Ralisations au 31 Mai 2008
valuation
du progrs
du progrs
valuation globale du rsultat 4
MS
HI
Rsultat 5 Le partage des connaissances relatives la GDRN auprs des parties prenantes contribue amliorer lefficacit et la durabilit de la gestion
Indicateur 21:
No basic
An information
Les connaissances traditionnelles des
PIR 2007: First step is achieved:
survey has
management
diffrents acteurs impliqus dans la
The results of the research and work produced for the
% de praticiens de
been
system for sharing
gestion des ressources naturelles dans
development of sustainable natural resource management and
la GDRN qui sont
conducted,
knowledge on
les sites de rfrence de terrain sont
use are shared and explained to regional and local authorities,
satisfaits des
and there is no
SNRM with SNRM
values par SAGE.
ANGAP and decentralized state services at the regional
connaissances
appropriate
practitioners is
workshops. The electronic version of the results (CD) is offered
gnres et
formal training
established &
to allow their use at all levels.
partages.
provided in
functional.
102
to be able to develop well suited awareness raising and capacity development interventions, targeted
specifically at knowledge gaps and needs and specific target groups,
to establish a knowledge baseline and a Monitoring and Evaluation (M&E) plan, which would allow
measurement of improvements i.e. based on the project interventions (i.e. several project indicators
esp. under outcomes 4 and 5 would require a baseline assessment), and
to pace project interventions in line with the awareness and capacity building activities that are really
needs based.
In the context of the PA-PASZ project, it is proposed to utilise the transcripts of the intensive recent evaluation visit
to a majority of project intervention areas as a basis to establish a knowledge baseline for the project. The
meeting minutes and existing workplans e.g. of the various platforms should suffice to develop a sounds
communication strategy, that would entail awareness raising and capacity building aspects (capacity building is
further dealt with in ANNEX 11). The PMU should be responsible for documenting the discussions and integrate
them into work under Knowledge Management outcomes.
103
104
105
106
107
108
109
110