Professional Documents
Culture Documents
Senior Scientist, CSIR - Central Road Research Institute, New Delhi - 25.
Email: amrao_crri@yahoo.co.in
Senior Principal Scientist and Head, Traffic Eng ineering and Safety Div ision,
CSIR - Central Road Research Institute, New Delh i - 25.
E-mail: vms_04@yahooc.o.in; vms.crri@nic.in
Abstract
Maharashtra Public Works, Pune Region had felt the need to conduct a scientific study aimed at the
conduct of economic and financial evaluation for State Highway - 60 (SH-60) towards capacity augmentation as the
traffic load is gradually increasing gradually due to the intense development along the corridor. This paper presents
the details of the Classified Traffic Vo lu me Count (CVC) conducted at strategic locations on the study corridor,
Origin - Destination studies, speed characteristics assessment, estimat ion of base year through traffic, growth rates
and future traffic forecasts till the 20 year analysis period i.e. 2032. Thereafter, Four Technically Feasible
Alternatives were considered while carrying out the economic analysis. This analysis was accompl ished by
comparing with the Base Case i.e Business As Usual (BAU) Alternative for the road corridor using Highway
Design and Maintenance-IV (Version 2.0). Further, sensitivity analysis was carried out under the assumption for the
conceived alternatives that if the traffic forecast envisaged is lesser by 20% fro m the estimated value. Based on the
above exhaustive Economic Viability analysis carried out using the HDM -IV Software, it emerged that the Alt - 1 is
yielding the EIRR of 47.7 % and FIRR of 13 % and this is followed by Alt - 2 yielding EIRR of 36.2 % whereas
the FIRR for A lt -2 is 12%. Therefore, it is strongly recommended that the Maharashtra Public Works, Pune Reg ion
should consider the imp lementation of Alt-1 and the second best alternative is Alt-2 for the purpose of capacity
augmentation of SH-60.
Key words: Economic analysis, financial analysis, Economic Internal Rate of Return, HDM-IV
1. Background
On inter-urban highways, the capacity augmentation infrastructure projects such as roads is normally
considered with the aim to provide seamless travel for the through traffic without entailing traffic congestion. For
this purpose, it is essential to formu late the technically feasible alternatives considering the site conditions , travel
characteristics and formu lating imp lementable alternates thereafter, the chosen alternatives need to be subjected to
economic evaluation and subsequently, the alternatives yielding the tangible Econo mic Internal Rate of Return
(EIRR) can be subjected to financial evaluation. In th is regard, Maharashtra Public Works, Pune Region had felt the
need to conduct a scientific study aimed at assessing the need for capacity augmentation of State Highway - 60 (SH60) starting fro m Km 10/ 600 to Km 64/000 spanning over 54 km. This highway starts in the Pune district connecting
the city of Pune and Ahmednagar. At present, this stretch is a four lane div ided carriageway up to Sh irur passing
through several small townships like Wagholi, Koregaon, Bhima, Shikrapur and Ranajangaon containing a lot of
fertile agricu ltural belt as well. Despite this, the traffic load on this stretch is increasing gradually due to intense
development along the entire corridor warranting the expansion.
2. Literature review
It is impo rtant to identify the type of economic impact when perfo rming an economic analysis of road
projects. Types of impacts vary with project to project, as per Transportation Research Board (TRB) has provided a
[Type text]
standard classification system of three types of economic impacts: (1) generative, (2) red istributive, and (3) financial
transfer impacts. To evaluate these impacts, there are two basic types of economic impact analysis are there (1)
predictive and (2) evaluative. These two basic types of analysis can be disaggregated into numerous methods for
analyzing economic impacts of transportation projects. These methods include case studies, computer models, inputoutput models, statistical and non-statistical co mparisons, surveys, cost/benefit analysis, and others. It is important
to identify the correct method and procedure to avoid bias and obtain correct results. Increasingly computer models
are being used to provide results for government agencies. Although these programs can provide useful results for
decision makers, the accuracy of these results depends greatly on the dependability of the data and the ability of the
modeler to manipulate the program to correct ly represent specific situation(s)(G. Weisbrod, 2006). Evaluating the
economic impacts of a transportation project will allow agencies to better maximize the benefit to users and the
overall economy (G.G.Schultz , 2006, 2010). The literature rev iew also indicated that although there are many
deferent variables that are influenced by transportation projects, there are a few that are more impo rtant to the public
and government agencies. In the present study two variables were identified as key indicators for how transportation
project affects the economy. These include (1) Vehicle Operation Cost (VOC) and (2) Vehicle Operating Time
(VOT). These two indicators include factors that are most impo rtant to both the public and govern ment agencies.
These variables are estimated using software tool i.e. HDM -IV in the present study.
3. Study Area
Pune is one of the major metropolitan cities situated in the state of Maharashtra housing a population of
94,26,959 (Census, 2011), making it the fourth most populous district in India. SH-60 o rig inates in the Pune d istrict
connecting the city of Pune and Ahmednagar. It is a four lane divided carriageway passing through several small
townships like Wagholi, Koregaon, Bhima, Shikrapur, Ranajangaon and Shirur containing a lot of fertile agricultural
belt as well. Moreover, this stretch acts as a conduit connecting Mumbai Industrial Co rridor (MIDC) area with Pune
- Sanaswadi - Ranjangaon stretch, Pune Airport at Lohegaon and the vital part of Dighi - Pune - Indore section of the
Delh i - DM IC. More importantly, it also acts as a feeder fo r the international exh ibition centre located at Moshi and
Pilgrim towns of Alandi and Dehu. The study corridor is shown in figure I.
4. Objecti ves and scope of the study
The objectives and scope of the study are presented as under:
Assessment of the traffic and travel characteristics of the study corridor and estimation of future traffic for the
period of 20 years.
To evolve the technically feasible alternatives aimed at effecting capacity augmentation of the study section
considering the projected horizon year traffic.
Economic v iability analysis of the feasible alternatives using the HDM-IV software
Conduct of the sensitivity analysis for the economic analysis scenarios accounting for unforeseen uncertainties.
The scope of the study encompassed the conduct of classified traffic volu me count surveys at selected
locations on the study corridor and Origin - Destination (OD) survey at one location, sped and delay survey and
conduct the economic analysis.
[Type text]
[Type text]
Reconnaissance survey
Study initiation
FIELD STUDIES
Traffic vol ume counts
Origin Destination survey
Speed and delay study
Spot s peed studies
Study of vehicul ar
growth
8. Data analysis
A brief description of the traffic characteristic on the study corridor is exp lained below
8.1 Hourly variation and composition of traffic at mid block sections
The observed daily traffic volu me at Perne to ll plaza in the Pune to Sh irur direction is 18788 vehicles amounting
to 22018 PCUs whereas in the case of Shirur to Pune direction, the total volume is observed to be 15179
amounting to 19169 PCUs.
The peak hour traffic observed at Perne Pune to Shirur direct ion is between 15:00 to 16:00 hours catering to
about 1508 vehicles (1616 PCUs) whereas in the case of Shirur to Pune direct ion it is between 18:00 to 19:00
hours catering to about 1190 vehicles (1460 PCUs).
Big car and small car together account for 35.5% fo llo wed by 32.4% of t wo wheelers in the Pune to Shiru r
direction and similarly in the opposite direction, 38.3% of b ig and small cars followed by 24.5% of two wheelers
(figure III). This is due to the lot of real estate development along the road section generating the sizable
proportion of personalized passenger vehicles destined for work purpose trips to Pune city during the morning
hours and returning back fro m Pune in the wee hours of the day.
[Type text]
The overall share of the goods vehicles (contributed by LCV + 2 / 3 A xle Truck + MA V) is about 13.1% (7.4 +
4.2 + 1.5) in both directions of travel and buses and minibuses together constitute about 10.3 % (8.3+2.0) in Pune
to Shirur d irection whereas in the case of Shiru r to Pune direct ion it is found to be 14. 5% (12.1 + 2.4).
LCV MAV
7.4% 1.5%
Truck
4.2%
MAV
2.1%
Truck
4.6%
Small Cars
22.4%
2-Wh
32.4%
Tractors
0.4%
Three
wheelers
2.2%
Mini Bus
4.0%
Buses
7.1%
Shirur - Pune
Small Cars
19.4%
Big Cars
18.9%
Big Cars
13.1%
Pune - Shirur
Tata Magic
6.1%
2-Wh
24.5%
LCV
6.4%
Mini Bus
7.3%
Three
wheelers
3.0%
[Type text]
variation in the speed are substantial in the v icin ity of the urban settlement causing delays to the motorized t raffic
and such stopped delays are noted in both directions of travel at Sanaswadi uncontrolled intersection, Perne toll
plaza ( for plaza payment) and at Wagholi due to the weekly markets being in place on the roadside causing delays.
120
Delay (Sec.)
100
80
60
3 PM-4:30 PM
6 PM-7 PM
Large delays
observed at
uncontrolled
intersection near
Sanaswadi
6:30 PM-7:30 PM
40
20
0
Control Points
Figure IV Typical Delays Observed in Pune to Shirur Direction
Based on the above analysis, it can be inferred that the average journey speed on the study corridor in the
Pune to Shirur direction is 54 km/h r whereas in the Shirur to Pune direction it is observed to be 64 km/hr. The
journey speed from Lonikhand to Shikrapur section is lo w, whereas between Shikrapur to Shirur the speed is higher
side.
8.5 Origin -Destination Survey
Origin - Destination (O - D) survey conducted amongst the vehicle users helped in determining the trip
characteristics details including their orig in and destination from each of the traffic zones. Roadside interview
method was adopted for this study. O - D survey was conducted at Perne toll plaza deploying stratified rando m
sampling basis for 24 hours in tandem with the conduct of classified traffic volu me count during the same duration.
In this regard, entire country was divided into 22 traffic zones for the formu lation of Traffic Analysis Zones (TAZ)
and analysis of O - D data, out of the 22 zones identified in the study, 15 zones fall in the Pune district (figure V)
whereas five zones fall in the Maharashtra state and the remain ing two zones fall outside the state. Interviews of all
type of vehicle users were done on a random stratified sampling basis wherein 4.41% of the passenger vehicles and
17.59% o f the goods vehicles were interviewed.
[Type text]
Figure V : Spread of Traffic Zoning System Evolved for Pune District and Maharashtra State
60
50
40
30
20
10
0
Percentage
Percentage
Goods Vehicles
0-50
50-100
100-200
Distance (km)
40
20
0
0-50
50-100
100-200
Above 200
Distance (km)
Having analyzed the traffic flo w and speed characteristics on the study corridor, the succeeding section
focuses on the estimation of base year traffic with the specific focus on the estimation of through traffic presently
using the entire length of the study corridor.
[Type text]
16000
14000
Number of Vehicles
Number of Vehicles
14000
12000
12000
10000
10000
8000
8000
6000
6000
4000
4000
2000
2000
Figure VII: Estimated Traffic at Various Entry Points to the study Corridor
Alternative (Alt)
Identification
Base Case
Alt-1
[Type text]
Alt-2
Alt-3
Alt-4
Partly Elevated Road Section: elevated up to Markal Patak and from Bhima river to
Shikrapur with flyover at Ranjangaon village, six lane with ha rd shoulder 1.5 m width from
Markal Patak to Bhima river and six laning with hard shoulder 1.5 m width from Shikrapu r to
Shirur)
Elevated Entire Section i.e. from Lonikhand i.e. sta rt of section to Shirur bypass i.e end of the
section
Six laning of the entire study corridor
Table II: Summary of the Estimated Cost for Different Alternatives (Rs. in Crore)
S.
No.
1
2
3
4
Construction cost of
elevated alternatives
Cost of six
lane section
Land
acquisition
cost
Total cost
1462.00
259.39
81.20
1802.59
1602.96
247.07
163.17
2013.20
80.47
3297.20
125.90
596.02
3216.73
N.A.
470.11
[Type text]
software for the economic evaluation of the alternatives formu lated in this study. HDM 4 is an analytical tool for
engineering and economic assessment of road investments and maintenance alternatives. The software works on
physical and econo mic relationships derived fro m extensive research conducted on road deterioration. It models the
effects of maintenance activities and Vehicle Operation Costs (VOC) and Time Costs.
The results of the economic analysis performed for the various alternatives are presented in table III. It is
evident fro m table III that all the four alternatives were evaluated against the BAU with value o f t ime (VOT) shows
that the alternative 1 to 3 are econo mically v iable whereas the alternative 1 is yield ing high internal rate of return.
The Alt-4 yielding the FIRR and negative EIRR, this is due to high traffic is flying on the road and the capital cost
is low than other alternates which is yielding mo re FIRR but this alternate is have lower EIRR, hence this alternate
is not worth for implementation.
Table III presents the EIRR values evolved for various alternatives with and without considering the
value of time (VOT).
Table III: Summary of the Economic Analysis
S.No.
1
2
3
4
Alternatives
FIRR (in %)
Sensitivity analysis also carried out under the assumption that if the traffic forecast envisaged is less by
20% fro m the estimated value and the construction cost is increased by 10% which revealed that the Alt -1 (36.8%)
and Alt - 2 (27.8%) are feasib le alternatives fro m economic angle. Therefore, both these alternatives have been
subjected to financial evaluation considering the fact that the study corridor is envisaged to be developed under
Build Operate and Transfer (BOT) concept by the Maharashtra PWD.
11.6 Financial evaluation of alternatives
As mentioned earlier, the above selected alternatives were subjected to financial evaluation. The financial
analysis is carried out by considering the funding mechanism of govern ment, construction period, interests and
inflation in to consideration. Financial Internal Rate of Return (FIRR) is calculated for each alternative. The FIRR
for each alternative is also presented in table III which indicates the FIRR derived fo r the two alternatives namely
Alt 1 and Alt - 2.
12. Conclusion
Based on the above exhaustive economic v iability analysis carried out using the HDM-IV Software, it
emerged that the Alt - 1 is y ield ing the EIRR of 47.7 % and FIRR of 13 % and this is fo llo wed by Alt - 2 y ield ing
EIRR of 36.2 % whereas the FIRR fo r Alt -2 is 12%. Therefore, it is strongly recommended that the Maharashtra
Public Works, Pune Region should consider the imp lementation of A lt -1 and the second best alternative is Alt-2 for
the purpose of capacity augmentation of SH-60.
Acknowledgement
The authors wish to thank Public Works Region Pune division for sponsoring the project, the field staff
helped in co llect ing the data. The authors also wish to thank Dr. S Gangopadhyay, Director, Central Road Research
Institute (CRRI), New Delhi, India for h is mot ivation, guidance, suggestions and kind approval to publish this paper.
[Type text]
References
G. G. Schultz, J. S. McGee, and M. Saito, (2010) Economic development criteria for use in the project prioritization process of Utah, in
Proceedings of the Proceedings of the 7th Asia Pacic Conference on Transportation and the Environment (APTE 10), pp. 3646,
Semarang, Indonesia, 2010.
G. Weisbrod, (2006) Evolution of methods for assessing economic development impacts of proposed tran sportation projects, in Proceedings
of
the
3rd
International
Conference
on
T ransportation
and
Economic
Development,
2006,
http://www.edrgroup.com/images/stories/Transportation/weisbrod-evolution-of-mehtods-ted2006.pdf.
G.G. Schultz,M.Saito,A.L.Stewart,andC.Siler, (2006)Assessing the economic impacts of transportation improvement projects, Te ch. Rep.
UT -06.03, Utah Department of Trans- portation Research Division/Planning Division, Salt Lake City, Utah ,USA, 2006.
IRC:108 (1996 ) "Guidelines for Traffic Prediction on Rural Highways"
IRC:SP:30 (2009) "Manual on Economic Evaluation of Highway Projects in India"
Jianhua Li, Stephen T. Muench, Joe P. Mahoney, George C. White, Linda M. Pierce, Nadarajah Sivaneswaran (2004) Application of HDM-4
in the WSDOT Highway System Research Project
P. Perlich, Economic and demographic impacts of federally finnanced transportation infrastructure on the Wasatch Front, Economic and
Business Review, vol. 64, no. 9-10, 2004.
Project Performance Assessment report (2012)https://ieg.worldbankgroup.org/ Data/reports/IndiaGujratKarnatakaTransportPPAR_0. pdfT2695
Technical Report (2014) "Augmentation of existing facility on Pune - Shirur Road (SH 60) from Km 10/600 to Km 64/000 on DBFOT Basis"
Central Road Research Institute