Professional Documents
Culture Documents
Table of Contents
Introduction
Outline of the Damage sustained to CWSA systems and Installations
Restoration and Repair works
List of Pipes and Fitting used during disaster relief
List of construction materials used during disaster relief
List of Equipment and Machinery used during disaster relief
Labour force used during disaster relief
Introduction
On the 11th of April 2011 heavy rainfall in the Perseverance and Jennings
valley, 11 and 10 respectively, resulted in swollen rivers and severe
flooding that in turn caused significant damage to two of our major systems
on the windward side of the island. The affected systems were Jennings
Treatment and Supply system also known as the Windward Supply Project
and the Perseverance Treatment and Supply system that feeds Georgetown
and surrounding areas. The objective of this report is to document the post
disaster efforts of the Central Water and Sewerage Authority as it relates to
the rehabilitation works done on our systems and its interface with the
community in boosting its resilience to cope with intermittent water
shortages. An added expectation is that this report will assist in
supplementing a favourable institutional framework to strengthen even
further our disaster management plan.
At the 250,000 gallon storage tank overflow the pipes were swept
away and outlet valves were shifted as well as an accumulation of
sediments within the tanks chambers.
Level sensors and Flow meters from the water resources project were
swept away by the swollen river.
There was also scouring at the base of the storage tank that may
threaten the structural integrity of its foundation and degradation of
the slopes between the road and the tank that will require retaining
structures to stabilize same.
The road leading to our facilities was severely affected as high volumes
of water resulted in significant erosion as trenches as wide as 5 by 2to
3 in depth were present and in other cases a massive build up of
sediments and logs.
There was also the failure of a retaining wall that supported a portion
of road above the river between the first and second river crossing.
The gate and 394 of fencing at the treatment plant were swept away
by the action of water and landslides.
Level sensors and Flow meters from the water resources project were
also washed away by the swollen river.
The chlorination house was partially flooded and the floor covered with
mud and debris. There was also a breakage in the 1 chlorine line
thats operates the chlorinator as well as the chlorine sample point
stand pipe.
The bridges and river crossings were not as badly affected and were
mainly blocked hence affecting their functionality and not their
structural integrity.
There was also damage done to the 4 gate valve at the washout at
the river in Byrea on the 3rd of May while the 12 line was being
flushed.
As early as Tuesday April 12th our Treatment Plant Attendants were busy
walking the lines and relaying information on the damages to our systems.
Cleaning of the intake also begun on that day as well as shuttling of Pipes from
Belair Complex to Byrea as the Bridge at Mt. Young and consequently the bridge at
Byrea were impassable. Our assessments continued until Thursday the 14 th of April
by our Senior Technical Staff lead by The Engineering Manager and comprised of
Engineers, Superintendants, Area Supervisors, Engineering Technicians and
members of the Georgetown Crew who hiked through a maze of debris and logs to
provide a more comprehensive assessment.
One of our major challenges was accessing the treatment plants as a result of the
major damages to the roads and bridges. In order to expeditiously exercise our
restoration works we had to execute major road cleaning and in some cases rely on
temporary measures to make the roads motorable. This was done in conjunction
with BRAGSA who contracted the services of Mr. Austin Bullock who worked in the
Perseverance Valley and Mr. Joseph DaSilva who worked at the Jennings Valley, both
of whom operated Komatsu PC 200 Excavators. We also contracted a Mini excavator
Caterpillar 303 operated by Mr. Julian Bute and utilized the two of our JCB Backhoes;
TD 27 and G458. These temporary measures consisted of filling of eroded trenches
and cavities with stones, small works to divert water from the road surface, clearing,
grading, cutting and filling.
The following is a list of activities carried out in our repair and restoration
duties on the Perseverance System.
The first breakage on the 8 line from the intake to the treatment plant
was repaired on the 25th of April by refitting and repositioning two
lengths of 8 Bell and Plain D.I. Pipes and replacing a control valve. The
second break was restored by stepping down from 8 to 4 D.I. Pipes
and re routing the pipeline away from the current river course from the
21st to the 25th of April, 17 lengths (340) of 4 D.I. Pipes were utilised.
Concrete and masonry works were done on the 27 th of April for pipe
supports. Large Boulders from the river bed were then placed
strategically alongside the pipeline at an average distance of 5 to 6
feet to serve as a buffer in the event that the river level rises or
changes its course. There are also plans in place to cover the pipeline
with mould or sand from the river bed to act as a cushion and reduce
the vulnerability of the pipes with respect to the adjoining slope.
The fitting at the Storage tank overflow were replaced on the 27 th and
28th of April while the removal of debris and flushing of the tanks were
done on those days by labourers.
The Breakage on the 4 line at basin hole was repaired by the use of 5
lengths of 2 galvanised pipes and 3 lengths of 4 D.I. Pipes a total
of 160.
The Following is a summary of the restoration and repair works carried out
on the Jennings System:
D.I. from the treatment plant, concrete works were then carried out at
a later date.
Close to knights Bridge where originally there was Bell and Plain Pipes
that were washed away, 3 lengths of Flanged pipes were used as well
as welding to effect the anchors.
In the proximity of the hill above knights the two breakages required 6
lengths of Bell and Plain pipes to reinstate that segment, 2 and 4
lengths respectively.
Unit
Quantity
Overa
Unit rate
Total
Persevera
nce
Jennin
gs
ll
Quant
ity
12
12
lengt
h
Lengt
h
12" coupling
pcs
pcs
pcs
lengt
h
lengt
h
22
22
8" couplings
8" Anchor type
Adaptors
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
lengt
h
lengt
h
6" coupling
6" 90 Mechanical
bend
4" Bell and Plain D.I.
pipe
pcs
pcs
lengt
h
17
17
pcs
pcs
pcs
4" Flanged T
4" Flanged gasket
pcs
pcs
1
6
1
6
$
2,101.75
$
1,581.62
$
438.07
$
377.52
$
958.45
$
1,292.25
$
496.96
$
305.69
$
196.56
$
302.72
$
408.29
$
206.10
$
208.44
$
166.78
$
210.76
$
3 982.30
$
3 1,127.00
$
3 179.45
$
351.24
$
164.82
$
152.57
$
164.56
$
181.46
$
232.07
$
$
25,221.00
$
11,071.34
$
1,314.21
$
755.04
$
958.45
$
6,461.25
$
10,933.12
$
1,834.14
$
1,179.36
$
302.72
$
816.58
$
1,030.50
$
208.44
$
333.56
$
421.52
$
2,946.90
$
3,381.00
$
538.35
$
702.48
$
2,801.94
$
152.57
$
164.56
$
181.46
$
232.07
$
pcs
pcs
57
57
pcs
36
36
6.88
$
463.43
$
8.57
$
2.99
TOTAL
Quant
ity
Item
Description
D.I. Pipe
6"
2.5"
2"
1.5"
1"
.75"
.5"
G.I. Tee
2"
1.5"
1"
.5"
Union
Total
Size
4"
G.I. Pipe
Unit Cost
2.5"
2"
1.5"
$
6 1,127.00
$
2 667.56
$
4 138.56
$
14 108.10
$
35 76.22
$
14 48.38
$
1 31.96
$
23 24.70
$
1 15.17
$
1 10.27
$
1 4.58
$
2 2.25
$
1 53.22
$
5 22.37
4 $
$
6,762.00
$
1,335.12
$
554.24
$
1,513.40
$
2,667.70
$
677.32
$
31.96
$
568.10
$
15.17
$
10.27
$
4.58
$
4.50
$
53.22
$
111.85
$
41.28
$
463.43
$
488.49
$
107.64
$
75,043.40
1"
.5"
Valves
Nipples
Coupling
Reducing
bushing
Reducing Tees
Bends
4
11
6"
2.5"
2"
1.5"
.5"
2.5"
2"
1.5"
1"
.5"
6"
4"
2.5"
2.5" X
5"
2.5" X
1.5"
1" X .5"
.75" X .
5"
2.5" X .
5"
2" X
1.5"
2" X .5"
1.5" X .
5"
2": 45
1
1
1
4
1
1
2
13.52
$
7.94
$
6.00
$
705.96
$
135.70
$
211.28
$
122.51
$
37.31
$
12.13
$
8.13
$
4.44
$
2.70
$
1.45
$
183.50
$
103.16
$
89.47
$
10.62
$
9.37
$
1.73
$
1.38
$
1,612.00
$
16.39
$
9.91
$
7.44
$
54.08
$
31.76
$
66.00
$
705.96
$
135.70
$
1,690.24
$
122.51
$
186.55
$
48.52
$
56.91
$
26.64
$
5.40
$
7.25
$
367.00
$
206.32
$
89.47
$
10.62
$
9.37
$
5.19
$
1.38
$
6,448.00
$
16.39
$
29.73
$
7.44
$
2": 90
1.5":
90
.5": 90
Flange
Adaptor
6"
2
3
13
2
18.11
$
9.42
$
11.53
$
2.70
$
209.44
36.22
$
18.84
$
34.59
$
35.10
$
418.88
$
25,181.4
9
Unit
Jennin
gs
Overa
ll
Quant
ity
106
80
186
Quantity
Perseveran
ce
Portland Ordinary
Cement
sack
sand
yd
12
yd
12
yd
18
18
36
length
length
lacing wire
roll
sheet
2x4x16 RPP
length
15
15
Water Boots
pairs
12
16
Working Gloves
pairs
24
12
36
Unit
rate
$
22.00
$
34.50
$
69.00
$
20.00
$
19.00
$
14.00
$
13.00
$
97.00
$
37.95
$
53.40
$
8.75
TOTAL
Backhoe TD 27
Backhoe G458
Komatsu PC 200: Bullock
Buggy G464
Total
$
71.00
$
337.26
$
18,750.00
$
153.76
Remarks
Diesel cost
Diesel cost
Paid to
BRAGSA
Diesel cost
Total
$
4,092.00
$
414.00
$
828.00
$
720.00
$
152.00
$
56.00
$
26.00
$
388.00
$
569.25
$
854.40
$
315.00
$
8,414.65
Buggy G254
$
1,000.00
$
4,970.00
Concrete Mixer
Private Trucking
4 days @
$250
For
aggregates
$
563.81
$
G331 959.86
$
G592 604.76
TOTAL
Diesel cost
Diesel cost
Diesel cost
$
27,410.45
Regular hours
8323
OT 1.5
2910
OT 2.0
1486
OT 3.0
147
Number of Employees
Monthly paid
Temporary Employees
51
48
106
145,993.91
$
282,043.90
Fig 1.2 Broken 8 main at the 4th river crossing towards the Perseverance
treatment plant.
Fig 1.3 CWSA personnel at work on the realignment of the 8 main at the
4th River crossing.
Fig 1.4 Trenching for the realigned 8 Pipeline at the 4 th river crossing.
Fig 1.7 New 4 D.I. Pipeline that replaces the broken section of 8 D.I.
Pipeline.
Fig 2.2 Transportation of 12 D.I. Flanged pipeline after access had been
restored by CWSA personnel.
Fig 2.4 Thrust block separated from 11 1/4 mechanical bend on this 12
D.I. Transmission Pipeline.
Fig 2.5 Gate and Fence destroyed at the entrance to the treatment plant.
Fig 2.8 Repairs on the 6 Line from the intake to the Sedimentation tank.
Fig 2.9 Making the final connection on the 6 Line from intake to
sedimentation tank.
Fig 2.10 Repairs completed on the 12 D.I. flanged pipeline at the river
crossing at Byrea.