For Power Failure in Chennai city - Contact: 1912 for BSNL users, 0441912 for non-BSNL users

Procedure for obtaining HT Service Connection


Apply for HT service connection in the prescribed form (Form-4) obtainable free of cost from the Circle
Office (SEs Office )
Enter all the particulars required in the application form.Produce proper documents/records as specified in
the form ( Form-4)
Metering point of supply shall be 30 meters from the main gate easily accessible visible and satisfactory

05-02-2015 AM 07:57

TNEB- Consumer Guidance- Procedure for HT Serivce Connection

2 of 2

http://www.tangedco.gov.in/proc2.php

with regard to security aspects .

The following documents shall be accompanied with the application:


(1) When the applicant is the owner of the premises:
Certified copy of the Sale deed for the premises executed in his favour (or)
Property Tax receipt for the premises in the name of the applicant.
(2) When the applicant is not the owner of the premises:
Consent letter from the owner of the premises (or)
Proof of legal occupation (including lease deed) with the following:
(a) Indemnity Bond in Form 6
(b) Letter of acceptance to pay security deposit at twice the normal rate.
(3) Partnership deed in case the applicant is a partnership firm or
(4) Memorandum/Articles of Association in case of companies registered under Companies Act.
(5) Letter/Resolution authorizing the signatory.
(6) Site plan.
(7) Compliance by the intending consumer of other laws of the State of Tamil Nadu relating to the obtaining
of permit or approval or sanction or consent from the appropriate authorities as mentioned in such laws
in regard to construction, alteration or repairs to buildings or establishment of new industries or
factories
or other establishments for which supply of electricity is required by such intending consumer.
(8) As per Division Bench Order dated 23.8.2006, for all special/multistoried buildings in Chennai
Metropolitan
area, Planning permit from competent authority has to be submitted along with application and
Completion
Certificate from competent authority has to be submitted while effecting supply.
Submit the application to the Circle Office in person or by post and obtain proper acknowledgement.
Pay the necessary Registration & EMD charges and registered the application.
Advice Slip/notice/Letter will be issued indicating the prescribed charges payable and to execute the
agreement in the prescribed form (Form-8) on the same day of payment of charges
within stipulated period from the date of receipt of advice.
On receipt of charges and execution of agreement only , extension works will be taken up
and executed and a notice will be sent to the intending consumer to avail the supply within a stipulated
time
Intending consumer shall permit the licensee ,free of cost the use of any land belonging to the
consumer which may be required for erecting poles, etc and also shall arrange at his own expense
necessary way leave for laying of lines, poles, etc. through a route proposed by the licensee involving
minimum cost.
Get all the wiring work done by authorised person specified by the authority. After completion of the
wiring, notice must be sent to the Engineer by the intending consumer (upon printed test report form
obtainable free of cost from the offices of the TNEB) that the installation has been completed and tested
and that the same is complete and ready for inspection and test by the Engineer.
A notice will be sent to the intending consumer to avail supply within stipulated period.
Intending consumer should obtain safety certificate for the HT installation from CEIG .Avail
Supply within the notice period
The intending consumer shall comply other laws of the State of Tamil Nadu relating to the obtaining of
permit or approval or sanction or consent from the appropriate authorities as mentioned in such laws in regard
to construction, alteration or repairs to buildings or establishment of new industries or factories or other
establishments for which supply of electricity is required by such intending consumer.
The intending consumer shall comply any decree or order or judgment of any civil court in regard to the
supply of electricity or other requirements mentioned in such decree or order or judgment.