Professional Documents
Culture Documents
For
Procurement of
Country: BANGLADESH
IFB No. : GTCL/SCADA/EPC/01
Date: ----April, 2015
JICA Loan No.: BD-P71
Part 2 of 3
Table of Contents
Invitation for Bids: Following Prequalification
Single Stage Two Envelope Bidding
PART 1 - Bidding Procedures
Section I. Instruction to Bidders
Section II. Bid Data Sheet
Section III. Evaluation and Qualification Criteria (Following Pre-qualification)
Section IV. Bidding Forms
Section V. Eligible Source Countries of Japanese ODA Loans
PART 2 Employers Requirements
Section VI. Employers Requirements
PART 3 Conditions of Contract and Contract Forms
Section VII. General Conditions (GC)
Section VIII. Particular Conditions
Section IX. Contract Forms
TABLE OF CONTENTS
PART - 2
Section VI; Employers Requirements
TECHNICAL SPECIFICATIONS
TABLE OF CONTENTS
ABBREVIATIONS & DEFINITIONS
1.
GENERAL REQUIREMENTS...................................................................................................... 1
1.1
INTRODUCTION ....................................................................................................................... 1
1.2
BACKGROUND INFORMATION................................................................................................. 1
1.3
1.3.1
Introduction .................................................................................................................... 2
1.3.2
Design Outline................................................................................................................ 2
1.3.3
1.3.4
1.3.5
1.3.6
1.3.7
1.3.8
1.3.9
1.4
1.4.1
SCADA System............................................................................................................ 10
1.4.2
1.4.3
Instrumentation............................................................................................................. 11
1.4.4
1.4.5
Cabling ......................................................................................................................... 13
1.5
2.
1.5.1
1.5.2
1.5.3
1.6
1.7
1.8
INTRODUCTION ..................................................................................................................... 24
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
[1]
TABLE OF CONTENTS
2.2
2.3
2.4
2.5
MANUFACTURE .................................................................................................................... 31
2.6
2.7
2.8
INSTALLATION ...................................................................................................................... 31
2.9
2.10
COMMISSIONING ................................................................................................................... 32
2.11
2.12
2.13
TRAINING .............................................................................................................................. 32
2.14
2.14.1
General ......................................................................................................................... 32
2.14.2
2.14.3
2.14.4
2.14.5
2.14.6
2.14.7
Communication Facilities:............................................................................................ 37
2.14.8
Vehicles ........................................................................................................................ 37
2.14.9
Assistance ..................................................................................................................... 38
2.14.10
2.15
3.
3.1.1
Co-operation ................................................................................................................. 40
3.1.2
3.1.3
3.1.4
3.1.5
3.1.6
Provision of Standards.................................................................................................. 45
3.1.7
3.1.8
[2]
TABLE OF CONTENTS
3.1.9
3.1.10
Meetings ....................................................................................................................... 47
3.1.11
3.1.12
3.1.13
Reporting ...................................................................................................................... 48
3.2
3.2.1
Planning ........................................................................................................................ 49
3.2.2
Programming ................................................................................................................ 50
3.3
5.
6.
3.3.1
Principles ...................................................................................................................... 51
3.3.2
3.3.3
3.3.4
3.3.5
3.3.6
3.4
4.
4.2
4.3
MAINTAINABILITY ................................................................................................................ 56
4.4
EXPANDABILITY ................................................................................................................... 57
4.5
INTRODUCTION ..................................................................................................................... 58
5.2
PROCUREMENT ..................................................................................................................... 58
5.3
5.4
5.5
SCADA SYSTEM........................................................................................................................ 60
6.1
6.1.1
MCC ............................................................................................................................. 60
6.1.2
ACC .............................................................................................................................. 61
6.1.3
RTU .............................................................................................................................. 61
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
[3]
TABLE OF CONTENTS
6.1.4
6.2
6.2.1
General ......................................................................................................................... 62
6.2.2
Scalability: .................................................................................................................... 63
6.2.3
6.2.4
6.2.5
6.2.6
6.2.7
6.2.8
6.2.9
6.2.10
Data Validation............................................................................................................. 68
6.2.11
6.2.12
Trending ....................................................................................................................... 69
6.2.13
6.2.14
6.2.15
6.2.16
6.2.17
Cyber-security .............................................................................................................. 71
6.2.18
6.3
6.3.1
Server............................................................................................................................ 73
6.3.2
6.3.3
Printers.......................................................................................................................... 75
6.3.4
6.3.5
LAN .............................................................................................................................. 75
6.3.6
6.3.7
6.4
6.4.1
General ......................................................................................................................... 79
6.4.2
RTU Subsystem............................................................................................................ 80
6.4.3
6.4.4
6.4.5
[4]
TABLE OF CONTENTS
7.
6.4.6
Analog Outputs............................................................................................................. 82
6.4.7
6.4.8
Communications ........................................................................................................... 82
6.4.9
6.4.10
6.4.11
6.4.12
Labelling....................................................................................................................... 91
6.4.13
6.4.14
6.4.15
6.4.16
6.4.17
6.4.18
6.4.19
6.4.20
6.4.21
6.4.22
6.4.23
6.4.24
6.4.25
6.4.26
6.4.27
7.1.1
General ........................................................................................................................ 97
7.1.2
7.2
7.3
7.4
7.5
7.5.1
7.5.2
7.5.3
7.5.4
[5]
TABLE OF CONTENTS
8.
7.5.5
7.5.6
7.5.7
7.5.7.1
7.5.7.2
7.5.8
7.5.9
Software..................................................................................................................... 137
7.5.9.1
Integration..................................................................................................................... 137
7.5.9.2
7.5.9.3
7.5.9.4
7.5.9.5
7.5.9.6
7.5.9.7
8.2
8.3
8.4
8.4.1
8.4.2
8.5
8.6
8.7
8.8
8.9
8.10
8.11
8.12
8.12.1
9.
8.13
8.14
[6]
TABLE OF CONTENTS
9.2
9.2.1
Master Control Centre (MCC) and Auxiliary Control Centre (ACC) ........................ 156
9.2.2
9.2.3
9.2.4
9.3
9.3.1
Uninterruptible Power Supply (UPS) for MCC & ACC and Demra SCADA Office 159
9.3.2
9.3.3
9.3.4
9.3.5
9.3.6
9.3.7
9.3.8
9.3.9
9.3.10
9.3.11
9.3.12
9.3.13
9.3.14
9.4
ELECTRIC WORKS AT MCC, AGARGAON, DHAKA, ACC, ASHUGANJ, DEMRA SCADA
OFFICE (OLD MCC) AND OTHER MTS AND RTU SITES ............................................................ 168
9.4.1
9.4.2
9.4.3
9.4.4
9.5
9.5.1
9.5.2
9.5.3
9.5.4
9.5.5
9.5.6
9.5.7
[7]
TABLE OF CONTENTS
9.5.8
9.5.9
9.5.10
9.5.11
9.5.12
9.5.13
9.5.14
9.5.15
9.5.16
9.5.17
9.5.18
9.5.19
9.5.20
9.5.21
9.6
9.6.1
9.6.2
9.6.3
9.6.4
9.6.5
9.6.6
9.6.7
9.7
9.7.1
Construction.............................................................................................................. 186
9.7.2
9.7.3
9.7.4
9.7.5
9.7.6
9.8
9.8.1
9.8.2
9.9
9.9.1
[8]
TABLE OF CONTENTS
9.9.2
9.9.3
9.9.4
9.9.5
9.9.6
9.9.7
9.9.8
9.9.9
9.9.10
9.9.11
9.9.12
9.9.13
9.10
10.
10.1
10.1.1
10.1.2
10.1.3
10.2
10.2.1
10.2.2
10.3
10.3.1
10.3.2
10.4
10.4.1
The specifications for civil works of MCC shall be as under: ................................... 200
10.4.2
10.4.3
Civil Works for ACC and Demra SCADA Office (Old MCC)............................. 202
10.4.4
Air Conditioning Works for MCC,ACC and Demra SCADA Office .................. 203
10.4.5
Office Furniture and Equipment of MCC ,ACC and Demra SCADA Office .... 203
10.4.6
10.4.6.1
10.5
10.6.1
[9]
TABLE OF CONTENTS
10.5.2
10.6
10.6.1
10.6.2
Painting...................................................................................................................... 211
10.6.3
10.7
10.7.1
10.7.1.1
Earthing................................................................................................................. 213
10.7.1.2
10.8
10.8.1
11.
11.1
11.2
11.3
11.3.1
11.3.2
11.3.3
11.3.4
12.
12.1
12.2
12.2.1
12.2.2
12.3
12.4
12.5
12.6
13.
12.6.1
12.6.2
12.6.3
12.6.4
12.6.5
[10]
TABLE OF CONTENTS
TRAINING............................................................................................................................. 228
14.
14.1
14.2
14.3
14.3.1
14.3.2
14.3.3
14.3.4
14.3.5
Technicians................................................................................................................. 229
14.3.6
Trainers....................................................................................................................... 229
14.4
14.4.1
14.4.2
14.4.3
14.4.4
14.4.5
14.5
15.
14.5.1
14.5.2
14.5.3
[11]
TABLE OF CONTENTS
LIST OF ATTACHMENTS
ADB
BGFCL
BGDSL
CGS
DRS
FAT
FF
Fertilizer Factory
GMS
GTCL
HO
Head Office
IP-PBX
IOC
JICA
JGTDSL
KGDCL
MCC
MS
Metering Station
MTS
NMS
OCT
PS
Power Station
RMS
RTU
SAT
SCADA
SGFL
STS
TBS
TGTDCL
UPS
VS
Valve Station
WB
World Bank
Definitions
Access Point
Additional Site
Employer
Future Site
Original Site
Existing site which has been covered by The Existing System, and
shall be covered by The New System.
Project
Detail
design,
procurement,
construction,
installation,
commissioning and training for the rehabilitation and expansion of
The Existing System.
Site
The local radio station installed with New RTU that communicates
with Master Telemetry Station.
Study
The Engineer
1.
GENERAL REQUIREMENTS
1.1
INTRODUCTION
1.2
(1)
This document is the Functional and Performance Specification for 'Gas SCADA
System Rehabilitation and Expansion Project' for GTCL in Bangladesh and form Part-2,
Section-VI of the Invitation to Tender for the said Project.
(2)
Gas Transmission Company Ltd. (GTCL), Bangladesh is the Employer for this Contract
who own, control, operate and maintain the high pressure gas transmission trunk
pipelines that shall be covered by New SCADA and Communication System.
(3)
The purpose and objective of the project for Rehabilitation and Expansion of Existing
Supervisory Control and Data Acquisition (SCADA) of GTCL is to revamp, modernize
and expand the SCADA system of the country-wide GTCL gas pipeline network to
build an integrated SCADA-Communication system as a functional organ of Employer
to monitor and ensure a stable gas supply system and to secure efficient and effective
gas distribution to the whole country.
(4)
The Project is implemented under Japan's ODA (Official Development Assistance) loan.
BACKGROUND INFORMATION
The existing gas SCADA-Telecommunication system operated by GTCL was installed under
DFID (Department for International Development, UK Government) assistance during 19962003 for the efficient operation and monitoring of gas supply in Bangladesh. However, it is
currently malfunctioning due to the following major problems.
(1)
Since the installation of the Existing System, there has been a significant growth in the
gas sector. New gas fields have started production and new gas off-take points have
been connected. However, no expansion of the Existing System has taken place and all
newly developed gas sites have remained outside the coverage of the Existing System.
(2)
Due to the lack of maintenance support from the Contractor after the expiry of operation
& maintenance support service period, the Existing System has become old and
dilapidated.
(3)
(4)
Existing System, designed in 1995, is fast approaching the final stage of its lifetime. The
equipment / parts used for the system have become generation/s older and the
procurement of spare parts has become difficult, affecting maintenance work seriously.
(5)
-1-
GENERAL REQUIREMENTS
PROJECT DESCRIPTION
1.3.1
Introduction
(1)
This chapter provides information on the Project, the Employer, other operating
companies and the sites at which new SCADA and Communication System are to be
installed.
(2)
The Contractor shall provide new SCADA and Communication System through
rehabilitation and expansion of the existing SCADA and Telecommunication System
for effective operation / control of the nationwide gas pipeline network.
(3)
(4)
The New System shall consist of new RTUs & new SCADA Systems, new
Communication systems, new UPS systems, new Battery & Charger systems, new solar
systems for non AC powered sites, new field Instruments etc. specified in this
document.
(5)
The New System shall provide the Employer with a unified voice and data
communications system to support their operations including but not limited to the
following:
(6)
1.3.2
a)
b)
On-off Control of automatic gas flow control valves either remotely or in local
manual mode.
c)
Planning of optimum and strategic use of gas in accordance with gas production
and consumption.
d)
The Specification has been based on conceptual design to allow the requirements to be
adequately addressed by EPC Contractor. The detail design in terms of the System
architecture and configuration shall be the responsibility of Contractor in accordance
with the functional and performance requirements described in the Specifications.
Design Outline
The new SCADA system shall allow information to be easily shared between computer
systems and applications through open system design architecture. The system shall also
make it possible to support modular applications such as graphical display, alarming, logical
functions, analysis and data handling operations and shall communicate with enterprise or
external systems over network. Sharing of data should be permissible through web based
browsers as well as standard client viewers.
Design of the new SCADA system shall incorporate the state-of-the-art technologies for
enhanced performance and / or to maximize the reliability and availability of the system with
flexibility to ensure ease, safe operation and maintenance.
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
-2-
GENERAL REQUIREMENTS
1.3.3
Design Philosophy
(1)
The scope of the Project will include but shall not be limited to the following:
a)
b)
ii]
equipment,
iii]
Provide new systems into existing sites which were not covered by the
Existing System. In such case, all necessary items, to meet complete
functional requirement of SCADA-Communication system, instrument,
cables & accessories, shed / shelter construction, other associated civil and
Electrical works required for new system, shall be provided.
iv]
v]
Interface & connections to other zonal gas SCADA Systems, third party
ERP systems of GTCL and to other Automation system operated by IOCs.
ii]
(2)
The New System will be designed in accordance with the same operational philosophy
for pipelines as the one currently being used for the Existing System.
(3)
-3-
GENERAL REQUIREMENTS
b)
c)
d)
e)
(4)
All main components of the Existing System, such as servers, workstations, RTUs,
communication equipment, field instruments etc. are to be replaced with new one. The
existing field cabling, junction boxes and power supply cabling to RTU may be reused
where these are found to be in good condition.
(5)
All the existing Fifty four (54) Remote Terminal Units of GTCL need total replacement
by new generation sleek, smart and fast RTUs. In addition Thirty two (32) new RTUs
need to be installed for the additional new nodes that are yet to be brought into the
coverage of the SCADA network. Also, two (2) new RTUs are to be kept in readiness
for upcoming future sites. Over the existing capacity the SCADA network shall be
designed with higher capacity and traffic to accept future nodes.
(6)
(7)
Air conditioners installed in the Control room, Equipment room and UPS & Battery
room in MCC and ACC are of split architecture design. Air conditioner for Radio room
shall be window type. All the above air conditioners shall be replaced.
(8)
All design and construction works shall be prepared and carried out in accordance with
British Standards & codes of practice or any other recognized equivalent national
standards like ANSI, ASME, IEC, IEEE, ISO, DIN approved by the Engineer. Any
departure from these standards and codes shall be subject to approval by the Engineer.
Contractor shall be able to present the copies of the referred standard and codes of
practice at the request of the Engineer.
(9)
All works shall be carried out in accordance with recognized standards of Environment,
Health & Safety (EHS) British Standards / American Concrete Institute (ACI) Codes /
Bangladesh National Building Code (BNBC) or equivalent. The Engineer shall have the
power to instruct the Contractors EHS officer to comply with the codes requirements.
(10) EPC Contractor shall be responsible for the complete design and design check of the
Works which shall be submitted to the Engineer for approval.
(11) The Contractor shall ensure that the submitted design is adequate in all respects for
proper functioning of the System.
(12) The Contractor shall submit the Method Statement for the works that describes the
method & sequence of the construction work, work plan, quality assurance, referred
standards and codes of practice etc. for the approval of the Engineer.
(13) For any deviation from the approved specification and quality, the Engineer will have
the authority to instruct the Contractor to reinstate such work to the required standard.
-4-
GENERAL REQUIREMENTS
(14) The Contractor shall arrange suitably qualified competent Engineers at site to supervise
the work and shall ensure that the quality and progress of the works is achieved and
maintained. The site engineers shall be responsible for liaising with the Engineer.
(15) As a part of the Quality assurance and Quality check, Contractor's engineers shall
inspect and test the works to ensure that all works are done as per approved design,
standard and specification and shall submit the records of such inspections and tests to
the Engineer for approval.
(16) The Contractor shall also ensure that progress is maintained in accordance with the
work schedule.
(17) The Contractor shall coordinate with all agencies including the operating companies of
gas facilities where Contractor's works shall be carried out and ensure no disturbance to
the operations of existing gas facilities and also ensure no damage to the existing gas
facilities.
1.3.4
Project Geography
(1)
Gas development in Bangladesh is mostly restricted to the eastern half of the country.
(2)
Bangladesh is a predominantly a flat country with the presence of hilly areas being in
the Sylhet region starting at Hobigonj and in the south-east of Chittagong.
(3)
Prominent natural resource is water. The lands are being dominated by rivers and deltas.
Many parts of the Bangladesh are a flood prone zone.
(4)
Other geographical features are the high probability of extreme climatic and
meteorological conditions including prolonged periods of high temperature and
humidity, thunder storms and cyclones and a monsoon season.
(5)
Bangladesh has three seasons; winter, between November and February which is dry
and cool, the pre-monsoon season between March and May which exhibits increasing
temperatures and periodic thunderstorms and increasing rainfall and the monsoon
season itself from June to October which is warm and humid and in which more than
80% of the annual rainfall occurs.
(6)
(7)
The conditions of lowest atmospheric pressure occur in Bangladesh in June and July, the
storm season. Winds are mostly from the north and northeast in winter, blowing gently
in northern and central areas and somewhat more aggressively near the coast. During
the period of the northwesters (strong winds from the northwest) from March to May,
however, wind speed may rise to 40 miles (65 km) per hour.
(8)
Bangladesh receives heavy rainfall; except for some parts in the west, it generally
exceeds 60 inches (1,500 mm) annually. Large areas of the south, southeast, north, and
northeast typically receive from 80 to 100 inches (2,000 to 2,500 mm), and the northern
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
-5-
GENERAL REQUIREMENTS
and northwestern parts of the Sylhet area usually receive from 150 to 200 inches
(~3,800 to 5,000 mm). The maximum rainfall occurs during the monsoon period, from
June to September or early October.
(9)
Such conditions have a direct impact on the transport infrastructure within Bangladesh
with some roads becoming temporarily impassable or washed away in sections.
(10) The Contractor shall study the geographic and climatic conditions of Bangladesh and
address them in all areas of the System design.
(11) The Contractor shall consider the geographical, meteorological and environmental
conditions in the Project Plan and demonstrate that sufficient contingency has been
included to ensure the program is both realistic and achievable.
(12) All the equipment supplied under contract shall be suitable for continuous operation
under the environmental conditions prevailing at site. The equipment shall be suitable
for transportation under proper packed conditions by road, air, sea, conforming to
standards. The equipment shall also be resistant to termite, fungus, rodents and salty
environment. The equipment shall withstand continuous ambient temperature up to 60
deg. Centigrade, and humidity from 5 to 95% RH (non-condensing). All enclosed
equipment shall be constructed to allow free air flow for proper heat dissipation, and
ventilation grill shall not obstruct operation and maintenance of equipment. All
equipment shall withstand international standards for vibration under industrial
operation.
1.3.5
1.3.6
(2)
Operating Companies
There are several Operating Companies. Sites of those companies are to be monitored
by the New System and their main activities are described below.
(1)
(2)
b)
c)
BGSL's head office is located in Comilla where new OCT and extension
telephone shall be installed.
-6-
GENERAL REQUIREMENTS
(3)
(4)
(5)
a)
b)
c)
b)
c)
TGTDCL's head office is located in Dhaka where a new OCT and extension
telephone shall be installed.
BGFCL is a company of Petrobangla who owns and operates several gas fields in
the districts of Brahmanbaria, Comilla, Hobigonj, Narsingdi and Gazupur. Gas is
supplied to the Employer and also directly to TGTDCL.
b)
BGFCL's head office is located in Brahmanbaria where a new OCT and extension
telephone shall be installed.
SGFL is a company of Petrobangla who owns and operates several gas fields in
Sylhed Division. Gas is supplied to the Employer.
b)
SGFLs head office is located at Horipur gas field, Sylhet where a new OCT and
extension telephone shall be installed.
(6)
BAPEX: A Company of Petrobangla responsible for drilling gas fields and operation of
several gas fields.
(7)
(8)
Other Companies
There are some other companies operating or constructing gas facilities which shall be
covered by the new SCADA System such as
a)
b)
-7-
GENERAL REQUIREMENTS
1.3.7
1.3.8
Sections of the national gas grid that shall be covered by The New System are indicated
in Figure l.
Site Description
(1)
Introduction
There are several classifications of sites which are defined below. The Site List
(Appendix-1) identifies the classification of each site to be included in The New
System.
(2)
(3)
Master Control Centre (MCC): MCC will be located at GTCL Head office,
Agargaon, Dhaka.
b)
Auxiliary Control Centre (ACC): The Auxiliary Control Center (ACC) of the
New System is located at Ashuganj approximately 90 km northeast of Dhaka.
c)
d)
Both Control Centers enable the Employer to supervise and control the entire gas
pipeline network converged by the New System.
(4)
There are dozens of gas metering & regulating stations to be monitored by the
New System under different classifications as below.
GMS
CGS
TBS
RMS
DRS
CMS
MS
Metering Station
-8-
GENERAL REQUIREMENTS
b)
(5)
(6)
(7)
(8)
The New System shall monitor the gas flow volume at these sites.
Gas Field
a)
b)
The New System shall monitor the inlet gas volume from these sites.
Bulk Consumers
a)
Power stations (PS) and fertilizer factories (FF), which are the largest consumers
of gas in the industrial sector, are defined as bulk consumers to be monitored by
the New System.
b)
The New System shall monitor the outlet gas volume feeding the bulk consumers.
There are dozens of main line valve stations (VS) to be monitored by the New
System.
b)
The New System shall monitor the open / close status of these valves. Further
control these valves shall be provided.
1.3.9
The Employer will receive requests from distribution companies for the supply of gas at
their designated sites on a periodical basis.
(2)
The Employer will also establish the levels of gas to be provided to the National Gas
Grid by production companies on a regular basis.
(3)
The Employer will plan for the transmission of gas through the National Gas Grid in
accordance with the demand as put forward by "distribution companies under their
contract with the production companies.
(4)
The Employer will provide figures for the quantity of gas flowing into and out of the
National Gas Grid to Petrobangla and the other Operating Companies to support billing
and payment for gas and other financial systems such as periodic accounts or planning.
(5)
Proposed SCADA system shall cover the following main transmission pipe lines:
a)
b)
Rashidpur - Ashuganj
c)
-9-
GENERAL REQUIREMENTS
(6)
d)
e)
f)
Norsignhdi-Demra
g)
h)
i)
j)
Bibiyana-Dhanua pipeline
k)
Moheskhali-Anowara pipeline
1.4
1.4.1
SCADA System
(1)
1.4.2
The intended purpose of the SCADA System is to ensure for GTCL that the natural gas
transmission pipeline is:
a)
b)
Equipped with operational interfaces that will enable the efficient monitoring and
control of the natural gas transmission pipeline from both of the Master Control
Center (MCC) and the Auxiliary Control Center (ACC).
(2)
The SCADA System shall permit data acquisition and control functions to be performed
at remote locations while providing the capability to monitor and control distributed
functions from MCC and ACC.
(3)
The Master Control Center (MCC) shall be the central operating center to monitor and
control the pipeline network.
(4)
The Auxiliary Control Center (ACC) shall be the hot-standby operating center with the
same functionality and operating capability as the MCC.
Communication System
The intended purpose of the Communication System is to:
(1)
Acquire data from remote sites and send the aggregated data to Master Control Centre
and Auxiliary Control Centre for monitoring and supervisory actions and for generating
outputs for management use.
(2)
Provide adequate communication ability, ensuring that the GTCL natural gas
transmission pipeline is capable of being operated and maintained safely, effectively
and efficiently.
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 10 -
GENERAL REQUIREMENTS
1.4.3
(3)
Provide properly integrated communication interfaces among all sites and operating
companies.
(4)
Make the operating staff aware of any abnormal operating conditions in a timely and
effective manner to enable them to minimize consequential damage.
(5)
(6)
Instrumentation
Instrumentation consists of :
(1)
(2)
Temperature measurement
(3)
Pressure measurement
(4)
Flow Computers
(5)
Level measurements
(6)
(7)
Type of metering employed in the existing SCADA system for monitoring of process data are
as follows:
(i) Flow Measurement by Orifice
(ii) Flow Measurement by Turbine Flowmeter
(i) Flow measurement by Orifice
a)
b)
The above transmitters are connected to Flow computers for orifice flow
measurements.
c)
In most of the sites separate temperature tapping points may not be available for
taking temperature signals for the new SCADA system. Therefore, it may be
required to use the existing tapping point for SCADA system and the flow
measuring devices of the operating companies. Hence, Temperature Transmitters
shall have dual 4-20 mA output so that one output can be used for flow computer
of the SCADA System and other for operating companies.
d)
Original sites of GTCL where transmitters are directly installed on GTCL pipeline.
- 11 -
GENERAL REQUIREMENTS
b)
Original sites of Production and Distribution companies where GTCL transmitters are
already installed by constructing tee off on the impulse tube of measuring system of
Production and Distribution companies.
c)
There are some Original Sites that have undergone expansion and new streams have
been added with no instrumentation installed and therefore all instruments are to be
procured and installed at those sites.
d)
e)
Only supply of instruments for future sites is required. These can be installed during
operation & maintenance period.
Functionality of Field transmitters already installed at sites could not be ascertained as the
SCADA system itself is not working for a long time and the instruments are lying idle for
about 15 years. Therefore, all the above transmitters shall be replaced by new smart type
transmitters.
(ii) Flow measurement by Turbine Flowmeter.
Turbine type flowmeters installed at original sites are mostly owned and maintained by the
operating companies.
Turbine type flow metering scheme are as follows:
a)
At some site installations the turbine flowmeter, pressure transmitter and temperature
transmitter signals are hardwired interfaced with the Flow computers installed on the
panels at Local Control Rooms.
b)
At some sites turbine flowmeter and volume corrector / flow computers are installed
outdoor on an instrument stand and it is connected to RTU.
Rehabilitation of all the turbine type flow meters under Operating companies will be carried
out by replacing / repairing of these meters by themselves.
a)
Contractor shall supply and install Flow computers including volume corrector for
Turbine meter. Flow computers shall be connected to RTU.
c)
Pulse signal for Turbine meter to Flow computers shall be taken from the existing
Turbine meter using dual pick up sensor to be supplied and installed by the Contractor.
d)
Pressure and Temperature signal shall be taken from the existing pressure and
temperature tap near the Turbine meter.
e)
In most of the sites temperature separate tapping points may not be available for taking
temperature signals for the SCADA system. Therefore, it may be required to use the
existing tapping point for SCADA system and the flow measuring devices of the
operating companies. Hence, Temperature Transmitters shall have dual 4-20 mA output
so that one output can be used for flow computer of the SCADA System and other for
operating companies.
f)
GTCL will assist to make provisions for the tapping points on the pipe lines, if required
at original sites and additional sites.
- 12 -
GENERAL REQUIREMENTS
1.4.4
1.4.5
Open / closed status of the main line valve shall be monitored and necessary accessories
for the purpose shall be supplied by the contractor.
b)
Some main line valves and flow control valves shall be controlled under this SCADA
system. Solenoid valves and necessary accessories shall be supplied and installed to
control the valves by the contractor.
c)
Pressure transmitters will be installed upstream of each valve station for monitoring of
pressure
d)
Pressure transmitters will be installed at the inlet of each metering station for
monitoring inlet pressure
Cabling
a)
New power cable, circuit breaker and accessories for RTU location shall be supplied
and installed by the contractor.
b)
Instrument cable from transmitter to junction box shall be replaced by the contractor.
c)
Communication cable from RTU to radio room shall be replaced by the contractor.
d)
Existing cabling from Junction Box to RTU can be reused unless these are internally
damaged.
e)
New power cable for Radio room power connection from existing distribution board in
the gas office to Radio room shall be supplied and installed by the contractor.
1.5
1.5.1
At Original Sites
- 13 -
GENERAL REQUIREMENTS
All RTUs that are currently installed at original site shall be replaced with New RTU.
(2)
At Additional Sites
Currently no RTUs are installed at the Additional Sites, thus New RTUs shall be
installed.
(3)
At Future Sites
a)
GTCL and operating companies plan to construct some sites for gas transmission
operation. These planned sites may not be constructed during the completion of
the Project therefore RTUs shall be designed and supplied to the Employer.
b)
Batteries shall be installed in the RTU cabinet to provide power back up and
maintain equipment operation for a full 24 hours on loss of the public electricity
supply. Solar panels are equipped at some existing sites without public electricity
supply and these existing solar panels shall be replaced. At additional sites
without public electricity supply, solar panels shall be installed on the RTU
shelter roofs to provide the power necessary to energize the RTU equipment and
pipeline instrumentation.
c)
Field Instruments shall be installed for all the Additional Sites and Existing Sites.
d)
RTUs will be used for control and monitoring of pipeline parameters like flow,
pressure, temperature, valve open / close status, pig arrival indication through pig
signaler, electrical parameters etc. and update the MCC / ACC.
(2)
The Communication System shall be composed of following network, links and other
subsystems:
a)
GPRS Radio Modem link between RTU site and Service Providers Access Point
and subsequent WAN communication backbone network to MCC and ACC and
other points as per the tender requirement.
b)
Telemetry Radio Link between MTS and Slave Telemetry Station (STS)
c)
IP Radio link and OFC link based on STM-1/Router between Provider's Access
Point (AP) and Master Telemetry Station (MTS)
d)
e)
IP PBX
f)
g)
The GPRS Radio Modem shall collect the process data from RTU and will transmit the
same to Service Providers Access Point. The data will finally be transported to SCADA
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 14 -
GENERAL REQUIREMENTS
Server at MCC and ACC through Service Providers WAN network. This will be the
primary communication system.
(3)
As a secondary communication backbone for transmitting data for a few specific RTU
sites, the telemetry radio link shall be used to connect the MTS and the STS at those
RTU sites.
(4)
The leased E l circuits from the provider's network and an IP radio link shall form the
secondary SCADA backbone to connect the MTS and MCC/ACC so that in the event of
failure of the primary backbone, the secondary communication backbone shall deliver
the critical data from those sites to MCC and ACC.
(5)
Link from MSC of service provider to MCC and ACC: A leased bandwidth of
optical fiber operator / provider shall be used. Contractor is responsible to build up OFC
connectivity from MSC of service provider to nearest access point of the OFC network
of the third party. Again contractor shall establish connectivity from MCC and ACC to
nearest AP of OFC network of third party.
(6)
Demra SCADA office & WCC Elenga shall be connected to MCC Agargaon, Dhaka
through leased bandwidth of OFC network provided by third party. However contractor
shall establish connectivity using OFC from Demra SCADA office & WCC Elenga to
AP of OFC Network of the third party.
(7)
The IP PBX shall be located at ACC and shall connect the extension lines located at the
MCC, ACC, MTS and OCT through the SCADA backbone by using VoiP transmission.
(8)
The video conferencing system shall also be used for such purpose amongst the specific
user groups.
(9)
The network monitoring system shall monitor the equipment connected with the
network. A computer with adequate software for monitoring shall be installed at MCC
and ACC.
The intended SCADA system shall have connections to other SCADA systems operated
by IOCs or installed by other donors. The interface details with the other systems are
furnished as under. However, the information is tentative and shall be subject to
revisions at a later point of time.
(2)
Process data connectivity in between third party systems and the new SCADA system
are proposed as follows. Detail of communication link & protocol and hardware
requirement will be made final during detail engineering.
a)
For Chevron Gas fields (Moulabi Bazar, Bibiyana and Jalalabad):Selected plant data will be obtained through RTUs installed at respective Gas
Fields and from the Chevron web server at Dhaka through internet line.
b)
- 15 -
GENERAL REQUIREMENTS
modem shall be supplied and installed in the RTU of the western zone SCADA
system.
c)
For Bangura Gas Field operated by Tullow Bangladesh Co. Ltd.:PLC based control system (Allen Bradley make) is installed for local control and
monitoring. Process data from this PLC to GTCL SCADA will be carried out by
installing a RTU near PLC location. Connectivity from PLC to this RTU will be
serial Modbus / DNP-3 or repeat hardwired signal. Communication from this
RTU to SCADA will be through GPRS Radio modem and telemetry link.
d)
For Interface with Bakhrabad-Siddhirganj SCADA System:Process data will be obtained from the GTCL own SCADA gateway / server of
Bakhrabad - Siddhirganj SCADA System to be installed at Demra.
e)
For Interface with GTCL ERP System:Communication link of proposed SCADA system shall be made available at
GTCL Dhaka office for ERP system.
f)
g)
h)
i)
j)
1.6
APPLICABLE STANDARDS
(1)
- 16 -
GENERAL REQUIREMENTS
The design, execution and completion of the Works shall be governed by, but not
limited to, the applicable standards and codes listed in the following table:
Table 1.1 List of Applicable Standards and Codes
REFERECE
PUBLICATION TITLE
API1104
API 2530
API 2534
API RP 17A
API RP 500
API RP 550
API RP 551
API RP 554
API RP2003
API Spec 2B
API RP 750
ASME B l .20.l
ASME 816.5
ASMEB16.9
ASME B16.10
ASME B16.11
ASME B16.20
ASME B16.21
- 17 -
GENERAL REQUIREMENTS
REFERECE
PUBLICATION TITLE
ASME B16.22
ASME B16.25
ASME B16.36
Orifice Flanges
ASME B18.2.1
Square and Hex Bolts and Screws, Inch Series, including Hex
Cap Screws and Lag Screws
AS ME B18.2.2
ASME B46.1
Measurement Uncertainty
BS 7430
Earthing
BS 6031
BS EN 1992-1-1:2004
BS EN 1993-11:2005
DIN 10204
Certification Requirements
EN 10204
ERA 69-30
GPA 2172
GPA 2261
IEC 76
Power Transformers
IEC 79
IEC 79-10
IEC 79-13
IEC 228
IEC 331
IEC 332
IEC 364-5-54
- 18 -
GENERAL REQUIREMENTS
REFERECE
PUBLICATION TITLE
Arrangements and Protective Conductors
IEC 446
IEC 502
IEC 529
IEC584
Thermocouples
IEC 605
IEC 654
IEC 751
IEC 754
IEC 801
IEC 1034
IEC 60228
IEC 60502-1
XLPE
Outer sheath
IEC 61508
IEC TC 65
IEE Wiring
Regulations
IEEE C37.90.1
ISA S5.I
ISA S5.2
ISA S5.3
Symbols
for
Distributed
Control/Shared
Instrumentation, Logic and Computer Symbols
ISA S5.4
ISA S20
- 19 -
GENERAL REQUIREMENTS
Display
REFERECE
PUBLICATION TITLE
ISA S51.1
ISA RP-5517
ISA S71.04
Environmental Conditions
ISA SP84/E/E
ISO 1519
ISO 2632
IS0 2714
L1quid
hydrocarbons-Volumetric
Measurement
by
Displacement Meter Systems Other Than Dispensary Pumps
IS0 2808
IS0 3170
IS0 3511
ITU-T G711-G729
Wideband modems
ITU-TX21 serial
Interfaces
ITU-T X805
MSS SP-9
MSS SP-25
MSS SP-44
MSS SP-45
MSS SP-53
MSS SP-54
MSS SP-55
MSS SP-61
- 20 -
GENERAL REQUIREMENTS
REFERECE
PUBLICATION TITLE
MSS SP-80
MSS SP-82
MSS SP-92
NFPA 101
NFPA 110
NFPA 321
NFPA 496
OSHA
RS-222-C
UTM
(3)
The Contractor shall demonstrate compliance with all of the above standards and codes
at all stages of implementation of the Works. In the event of conflict between the
various listed standards, the stricter provisions shall prevail.
(4)
The Contractor shall comply with all Safety Legislation and Regulations prevailing in
Bangladesh insofar as they are applicable to the carrying out of the Works.
(5)
The Contractor shall be responsible for sourcing and obtaining copies of the latest
edition of all standards and codes, of which two copies of each shall be provided to the
Engineer.
(6)
The latest versions of the above standards and codes shall be applicable for
implementation purposes unless otherwise specifically stated elsewhere in this
document.
(7)
(8)
Where specific standards, codes of practice or industry norms are stated in this
document, the Contractor may however use any other standard that will result in the
quality of the Works being equivalent to or higher than the quality that would have
resulted through the application of the stated standard.
- 21 -
GENERAL REQUIREMENTS
(9)
All of the relevant standards are to be adhered to and used in the integrated and
interdependent manner in which the issuing body intended.
(10) In certain areas of science and engineering there are no published standards. In such
cases the Contractor is obliged to ensure that in the design, execution and completion of
the Works the Contractor has at all times complied with established "best practice". To
demonstrate compliance the Contractor may draw upon the latest technical references in
such areas and refer thereto in the preparation of the Design.
(11) The Contractors technical documents for their design, installation, commissioning and
testing shall identify the standards which are applied to.
1.7
UNITS OF MEASUREMENTS
The following units shall be used in this project:
Length
Mass
Temperature
Pressure
Differential Pressure
Flow rate - GAS
Flow rate - liquid (Large flows)
Flow rate - liquid (Small flows)
Flow rate - Gas & Air
Level
Viscosity
HC gas concentration
Toxic gas concentration
Velocity
Density
Area
Volume
Time
Gas Volume
1.8
Onshore
Minimum 5 deg.C
Maximum 55 deg.C
Minimum 85 %
Maximum 90 %
Generally, Zone-1, Gr. IIA/B Temperature Class T3.
However, Contractor to verify the exact site conditions during detailed engineering and supply all
instruments and systems suitable for those site conditions and area classifications.
All enclosed equipment structures to be supplied shall be constructed to allow free airflow to
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 22 -
GENERAL REQUIREMENTS
dissipate heat generated. Construction shall be such that ventilation grills will not be obstructed
when equipment is mounted in its installed position.
All equipment to be supplied shall withstand international standards of vibration for industrial
application.
- 23 -
GENERAL REQUIREMENTS
2.
SCOPE OF WORK
2.1
INTRODUCTION
(1)
(2)
The Contractor shall be liable for the correctness and completeness of design,
engineering, implementation and documentation in accordance with the requirements of
the EPC contract specifications and must demonstrate their ability to meet an acceptable
level of technical expertise, experience, and resources to provide a complete system.
(3)
The major Scope of Supply for SCADA and radio equipment shall include, but are not
limited to the following:
a)
b)
Supply of control equipment for 2 Control Centers MCC and ACC. Each
control center is equipped with Operating Terminals, Printers, Large size
monitor, Engineering stations, SCADA servers etc. and Application
servers for Load Balancing and Leak Detection.
2)
3)
2)
3)
c)
Survey Work for Radio path propagation for wireless Access link
d)
e)
f)
Supply of GPS based Time System for synchronization of entire SCADA System
(4)
The Contractor shall supply all items / equipment, tools & test equipment, software,
installation materials etc. as required to integrate and install the new SCADA systems
complete in all respects.
(5)
- 24 -
SCOPE OF WORK
(6)
(7)
EPC Contract Services defines the major scope of services to be undertaken by the EPC
Contractor for the engineering, procurement, construction, Pre-commissioning and
Commissioning of the Project.
Engineering
Procurement
Construction
Quality systems
The Contractor shall develop the Project Execution plans necessary for the
implementation of the project. These plans shall include, but shall not be limited to, the
following:
Project Management.
Construction.
(8)
The Site Information & Scope of Work is based on a conceptual design and provides
basic information of each site and an overview of each site's scope of work. The
Contract is a turnkey EPC Contract therefore; the Site Information & Scope of Work
does not relieve the Contractor of any responsibility for any aspects of the design and
implementation, nor for allowing for any variation between the Site information &
Scope of Work and the specific aspects of implementing the Contract Works.
(9)
The Contractor's responsibility at site shall include all the activities necessary to be
performed to complete the entire job as per the contract requirements including the
following as a minimum.
a) Receipt of hardware, software and checking the adequacy and completeness of
supply.
b) Storage, safety, security of the equipment & other materials including software at
site.
c) Installation of the complete system including power supply, earthing, cable
terminations,
d) Calibration,
e) Civil and electrical works.
f) Checking of equipment installation.
g) Checking of interconnection and overall system functionality.
h) On line / Offline debugging of the system.
i)
Coordination
interfacing
(including
- 25 -
obtaining
relevant
details)
SCOPE OF WORK
with
(10) The contractor shall complete all electrical works associated with the installation and
commissioning of the equipment, earthing of equipment at all sites. Powering of
equipment at all sites, termination of cables as required.
(11) The Contractor shall design and provide AC power and backup power supply for the
New SCADA System and New Communication System equipment. The existing rated
power supply is 230V AC single phase, 50 Hz.
(12) The Contractor shall carry out pre-installation civil works to provide foundations or to
prepare sites and buildings for the installation of the New System.
(13) The Contractor shall remove and dispose of unnecessary existing equipment for the
installation of the New System.
(14) The Contractor shall design and construct foundations and sunshades for new RTUs at
Additional Sites.
(15) The Contractor shall refurbish existing foundations and sunshades for the replacement
of existing RTUs at Original Sites, if necessary.
(16) The Contractor shall design and construct the instrument stands with foundations and
sunshades at sites where new instruments are installed.
(17) The Contractor shall refurbish existing instrument stands with foundations and
sunshades, if necessary, for the continuous use of existing instruments.
(18) The Contractor shall design and install antenna hoisting masts at RTU sites, as required.
(19) The Contractor shall refurbish existing equipment rooms to accommodate new SCADA
and Communication equipment according to the requirement.
(20) The Contractor shall carry out soil investigation BS 5930 or equivalent if it is required
for the design of foundations mentioned above.
(21) The Contractor shall furnish all documentation, drawings and other information required
by employer, operation & maintenance manuals, and handbook of inventory of all the
equipment supplied and installed in (hardcopy and softcopy) along with as built
documents, drawings and CDs of the complete project as per final EPC tender
requirements.
(22) The Contractor shall submit all necessary documents to indicate in details how he
proposes to plan, schedule, monitor and control progress of the work.
(23) The Contractor shall submit data related to execution plans, procedures and
organizational information dedicated to this project.
(24) The Contractor shall perform all drawings on appropriate CAD system and provide
GTCL with copies of the software utilized.
- 26 -
SCOPE OF WORK
(25) The BID documents shall be submitted in form of hard copies and electronic copies (in
PDF File Format for the whole documents in addition to CAD File Format for all
drawings).
(26) Contractors are also requested to submit drawings which summarize all the existing
SCADA systems and the expected expansions and modifications.
(27) All documents developed by the Contractor shall be subject to timely and Pre-defined
periods of approval by GTCL, and shall be submitted in Hard and Soft copies.
Master schedule.
Budget plan.
Engineering drawings.
Investment requirement.
Cost Estimation.
Mobilization plan.
Required purchases.
(28) The Contractor shall develop status and maintain a complete deliverables list that
indicates the current status of the following:
Description of Deliverables
(29) Upon award the contractor is requested to arrange a kick off meeting to initiate the
work, in addition to regular interim meetings to review and follow up the progress of
work, which shall preferably be carried out at various milestones of the work. Details of
discussion and the required information are to be mutually agreed in advance as
discussed in Cl. No. 3.1.10.
(30) In case statuary clearance / license is required for setting up / operating of the UHF
Telemetry radio system and IP Microwave radio system as well as leasing E1 lines, the
same shall be obtained by the contractor and all required liaison works shall be
undertaken by the Contractor. Necessary supporting documents and endorsement which
are essential for such procedures will be provided by the Employer.
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 27 -
SCOPE OF WORK
(31) The Contractor will, during the time of detail engineering and installation of the quoted
system, interact and coordinate with any other agency regarding collection / retrieval of
inputs / information / data and all such works shall be under the scope of this
Contractor.
(32) Any additional plant, equipment, material, services which are not specifically mentioned
here, but are required to make the system complete in every respect in accordance with
the intent and technical specification and for safe operation and guaranteed
performance, shall be deemed to be covered under the scope of this specification.
2.2
PROJECT MANAGEMENT
(1)
The Contractor shall be responsible for the Project Management, and nominate a single
Project Manager to be mainly based in Bangladesh. The Project Manager shall be the
point of contact during the Contract and shall be responsible for all aspects of the
Contractor's work including, but not limited to, program management, progress
reporting, finance, safety and technical compliance.
(2)
The Contractor shall produce a Project Plan as specified in Section 3.2.1. This shall
address both Bangladesh and overseas based activities.
(3)
The Contractor shall monitor performance against the Project Plan and produce monthly
reports detailing progress, activities undertaken, problems and future activities.
(4)
Number of
Engineers
One (1)
Project Engineer
Two (2)
SCADA Engineers
Two (2)
Instrumentation
and Control
Engineers
Two (2)
Qualification
Experience
(Minimum)
Graduate Engineer 12 years experience
or equivalent
in Project Execution
Work, out of which 6
years in SCADA /
Telecommunication /
Instrumentation /
Automation System
Graduate Engineer 6 years experience
or equivalent
in the field of
SCADA /
Telecommunication /
Instrumentation /
Automation System
Graduate in
4 years experience
Electrical /
in Design /
Electronics /
Installation /
Telecommunication Commissioning of
/ Computer
SCADA System
Engineering or
equivalent
Graduate in
4 years experience
Electrical /
in Design /
Electronics /
Installation /
Mechanical /
Commissioning of
- 28 -
SCOPE OF WORK
Electrical Engineer
One (1)
Civil Engineer
One (1)
One (1)
QA / QC Engineer
One (1)
10
Material controller
One (1)
Instrumentation /
Automation
Engineering or
equivalent
Graduate in
Electrical /
Electronics /
Telecommunication
/ Computer
Engineering or
equivalent
Graduate in
Electrical
Engineering
Graduate / Diploma
in Civil
Engineering
Graduate / Diploma
in Fire & Safety
Graduate Engineer
or equivalent
Diploma in
materials
management or
equivalent
Instrumentation &
Control System
4 years experience
in Design /
Installation /
Commissioning of
Telecommunication
System
4 years experience
in Electrical Works
4 years experience
in Civil Works
4 years experience
in Fire & Safety
works.
4 years experience
in QA / QC Works
4 years experience
in warehouse
management.
Contractor shall submit their organizational set-up and a list of key management and
specialist position for this project. The Contractor must also have suitably qualified
engineers in their design office for the above mentioned disciplines for complete detail /
design engineering of the SCADA project.
(5)
The Contractor shall monitor performance against the Project Schedule and produce
Weekly, Monthly & Quarterly reports detailing progress, activities undertaken,
problems and future activities. Contractor shall also prepare & submit any other reports
deemed necessary for proper execution of the project.
(6)
Contractor shall have materials management division for proper handling & storing of
materials.
(7)
The Contractor shall prepare and submit health, safety plan & programs. He shall ensure
that the construction work is carried out according to the safety plan as well as the
safety measures prescribed in the Safety Program.
The format and the contents of the reports must be approved by GTCL.
2.3
SITE INVESTIGATION
(1)
The Contractor shall be responsible for defining and implementing all necessary Site
investigations, including a sampling and testing program.
(2)
The purpose of the Site investigations shall be to identify and quantify those
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 29 -
SCOPE OF WORK
characteristics or properties of the materials found on or under the Site for use in the
design and execution of the Works. The definition of what investigation is required shall
take into account the data provided at the bid stage and any assumptions or conclusions
drawn from such data with respect to the characteristics or properties of materials.
2.4
The Contractor shall be responsible for the engineering and detailed design of the New
System in accordance with the requirements specified in this document. All drawings &
documents shall have Engineer approval.
(2)
Contractor shall prepare and submit basic and detail engineering drawings & documents
as required for the project. Drawing & Document deliverables shall not be limited to
submission of
a)
Inception report,
b)
c)
d)
e)
f)
g)
Cable list,
h)
i)
Hook up drawings,
j)
IO list,
k)
Instrument list,
l)
Equipment GA drawings,
m) Panel layout,
n)
Wiring diagrams,
o)
O&M Manuals,
p)
Quality plan,
q)
r)
s)
As-built drawings,
t)
All drawings and documents shall be prepared and submitted according to site list. A
Detailed list of Drawing & Document deliverables shall be furnished by the Contractor.
(3)
(4)
- 30 -
SCOPE OF WORK
2.5
MANUFACTURE
The Contractor shall manufacture the equipment required for the New System in accordance
with the design.
2.6
2.7
The Contractor shall perform the Factory Acceptance Test (FAT) of the equipment
manufactured for the New System before any item of the equipment is packed or
delivered from the manufacturer's factory. Other requirements further illustrated in Cl.
11.3.1.
(2)
Testing & calibration of all instruments and Factory Acceptance Test (FAT) shall be
carried out by the Contractor. For any instrument / equipment, if required, Range /
calibration span, set points, reports etc. shall be modified by the Contractor during FAT
and commissioning. Testing & Commissioning shall be carried out as per approved
procedures. No instrument shall leave manufacturers works without successful factory
acceptance test. All necessary changes shall be incorporated / implemented as suggested
by Employer and / or Engineer to meet tender requirement without any cost to
Employer. As build drawing / final documentation to be submitted by the contractor
shall contain all such changes.
(3)
The FAT shall be witnessed by the Employer and / or the Engineer. Employer / its
representative may witness testing of any or all items at various stages during
manufacture and / or at final stage before shipment at their discretion.
2.8
(1)
The Contractor shall refurbish existing rooms, foundations and sunshades where
equipment is installed prior to the installation works as specified in clause 10.
(2)
The Contractor shall construct the foundations and sunshades for new equipment prior
to the installation works as specified in clause 10.
(3)
The Contractor shall carry out all necessary cabling works prior to the installation works
as specified in Clause 9.
INSTALLATION
(1)
The requirements for delivery and installation are specified in greater detail in Section 5.
(2)
The Contractor shall be responsible for delivery of all equipment, materials and tools to
Bangladesh and onward to the sites.
(3)
The Contractor shall be responsible for providing adequate and appropriate storage
facilities for all equipment, materials and tools.
(4)
The Contractor shall install equipment in accordance with the design, specification,
safety plans and method statements.
- 31 -
SCOPE OF WORK
2.9
2.10
The requirements for SAT are specified in greater detail in Section 11.3.2.
(2)
The Contractor shall perform the Site Acceptance Test (SAT) of the equipment and
software for the New System after they are fully assembled / installed at sites.
(3)
Installation Tests shall be carried out on individual Subsystem location by location after
the completion of equipments physical installation.
(4)
COMMISSIONING
The Contractor shall carry out commissioning tests to demonstrate the satisfactory operation
of the New System prior to Taking-Over as specified in Section 11.3.3.
2.11
SYSTEM TAKING-OVER
Following satisfactory completion of the Final System Tests as specified in Section 11.3.4
and provided the other requirements have been met, the System Taking-Over shall take place
when the Employer commences full operation of the New System.
2.12
2.13
2.14
The requirements for the operation and maintenance support are specified in greater
detail in Section 12.
(2)
The Contractor shall support two years warranty period along with Operation and
Maintenance (O&M) support.
TRAINING
(1)
The requirements for training are specified in greater detail in Section 13.
(2)
2.14.1 General
(1)
The Contractor shall be fully responsible for all necessary temporary facilities for the
implementation of the Project.
(2)
The Contractor shall provide temporary office, messing and accommodation facilities at
four (04) suitable places within the area of the SCADA Rehabilitation Project. The
preferred locations are Demra / Narayanganj, Ashuganj, Sylhet and Chittagong.
(3)
The Contractor shall provide accommodation and food for the Employer and the
Engineer where travel back to Dhaka or temporary camps is not feasible in a day.
- 32 -
SCOPE OF WORK
(4)
The Contractor shall provide temporary office and accommodation facilities for the
Employer.
(5)
The Contractor shall be fully responsible for locating and arranging the use of sites for
the temporary facilities, temporary accommodation and such utilities as required by the
Contractor, the Employer and the Engineer.
(6)
The Contractor shall provide all Transport, Materials, Tools, Engineers, Supervisors,
Specialist, etc. as required for all temporary and for permanent works throughout the
project duration. Contractor shall also provide necessary transport facility for his
employees.
(7)
The Contractor shall provide and maintain an office at the Site, during Installation,
Testing & Commissioning phase, for his staff, and such office shall be open at all
reasonable hours to receive instructions, notice or other communications as per the
advice of the Employer / Engineer.
(8)
The Contractor shall provide all temporary camp facilities and transport facilities within
three (3) months from the effective date of the contract and with a demobilization period
of up to three (3) months after issuance of the Operational Acceptance Certificate.
(9)
Appropriate storage for the materials to be supplied in this contract will be arranged at
the site by the Contractor at various stations after the materials have been received. The
Contractor shall be responsible for the storage, security and safety of all materials, tools
etc. brought by the Contractor for the installation and commissioning of the system at
the site.
(10) Alcohol, liquor, firearms and drugs shall be strictly forbidden in the camp area and
construction site.
2.14.2 Local Site Facilities
In addition to that required by himself, the Contractor shall provide, in areas where travel
back to Dhaka / temporary camps is not feasible in a day, local site facilities for the Employer
and the Engineer including:
(1)
Indoor working space at site (or reasonably close to the site) with adequate office
furniture for the Employer and the Engineer (minimum 6 staff).
(2)
In addition to that required by himself, the Contractor shall further provide the following
facilities at each of Demra / Narayanganj, Ashuganj, Sylhet and Chittagong;
a) Project Office
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 33 -
SCOPE OF WORK
b) Computer equipment
for the exclusive use of the staff of the Employer and the Engineer during the
construction period and with a demobilization period of up to three (3) months after
issue of the Taking-Over Certificate.
(2)
All items in Sections 2.14.3.3 shall become the property of the Employer at the time of
issuance of the Taking-Over Certificate.
Two (2) nos. Air conditioned office rooms each aprrox. Size of 200 sq.ft.
(2)
(3)
(4)
Office furniture adequate for the entire office space mentioned above.
(5)
Kitchen with cold & hot water supply, refrigerator, table wares and other necessary
facilities for tea / coffee and light meal services.
(6)
(7)
(8)
(9)
Provision of all consumable items for daily office use throughout the Project.
(2)
(3)
(4)
4 Nos. photocopier
(5)
Latest version of following software shall be pre-loaded on all PCs mentioned above
and also provided on DVD-ROM:
a)
b)
c)
Microsoft Outlook
d)
Microsoft Office
e)
f)
Microsoft Project
g)
Anti-virus software
- 34 -
SCOPE OF WORK
h)
AutoCAD
(2)
Four air conditioned bedroom with attached bathroom at Demra / Narayanganj, Sylhet
and Chittagong.
(3)
(4)
Separate air conditioned site office of approximately 120 sq. meter total floor area and 3
meter high from floor to roof springing level, comprising 2 individual offices each of 12
sq. meter minimum floor area, one office of 22 sq. meter minimum floor area.
(5)
Each room shall be individually lockable dead locks and the external doors of the
building shall be fitted with dead locks. Each room shall have at least one insect
screened window, which shall have secure fastenings. All office rooms shall be air
conditioned and have at least two walls mounted, 3 pin, 15 amp electric socket outlets
and a minimum of two no. twin tube ceiling mounted fluorescent lights to provide
adequate illumination for work at night. There shall also be at least two shelves
250mmX1500 mm fitted to the walls of each office.
(6)
The contractor shall also be responsible for supplying necessary stationeries required for
camp office.
(7)
The Contractor shall be responsible for the supply, issuance, maintenance and
cleanliness of the camp, facilities and temporary accommodation, for himself and the
staff of the Employer, for the duration of the construction period up to three months
after issuance of the Operational Acceptance Certificate, and the dismantling and
removal of the same and reinstatement of the site upon completion of the period.
(8)
The site office and equipment supplied to the Employer are deemed to be part of the
Contractors camp facilities and temporary accommodation and as such, are subject to
approval in accordance with the contract. At least three western style toilets and three
hand basins complete with hot and cold running water shall be provided for the
exclusive use of Employer and the Engineer and his staff.
(9)
A common dining facility shall be centrally located for employers. All rooms shall be
fully lit and decorated and provided with curtains, linen, cutlery and crockery etc. all as
required to complete the accommodation to a fully first class condition.
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 35 -
SCOPE OF WORK
(10) The Contractor shall provide for daily cleaning of all accommodation and provision of
bed linen and laundry facilities.
(11) Hot water supply at all bathrooms and kitchen.
(12) Kitchen, Dinning and Lounge space
(13) Accommodation shall be on a full board basis, minimum 3 meals per day per person.
Food shall be 1st class Bangladeshi standards, served and prepared in a hygienic
manner.
(14) Satellite TV
(15) Fire extinguishers in accordance with local regulation.
(16) Three meals per day for all staff
(17) Cooks and bearers necessary for daily meal, cleaning and maintenance.
(18) Provision of all consumable items for general daily use.
(19) Adjacent parking space for minimum 2 vehicles.
2.14.5 Supply of Electricity and Water
(1)
The Contractor shall be solely responsible for all arrangements for, and charges
associated with, the provision and use of drinking quality mineral water and electrical
power (230V 50Hz) to the offices, living and messing accommodation for the duration
of the Construction Period until the issuance of the Taking-Over Certificate.
(2)
Drinking water quality shall be subject to independent laboratory tests at the expense of
the Contractor.
(3)
Attention is drawn to the non-reliability of electricity supplies from the National Power
Grid in Bangladesh. Supplies of power are often discontinuous for several hours during
each day. The Contractor shall provide and maintain an independent full capacity diesel
fuelled generator system, as standby, for supply of electricity to the offices, living and
messing accommodation.
Thickness gauges
(b)
Measuring tapes
(c)
Safety gaggles
(d)
Safety shoes
(e)
Helmets
(f)
Rain coats
(g)
Umbrella
- 36 -
SCOPE OF WORK
(h)
Hand globes
(i)
Ear plugs
The contractor shall provide for the exclusive use of the Employer or their staff, the
following vehicles from within 15 days of the effective date and for the duration of the
contract. These vehicles will become the property of the contractor at the time of
issuance of the Operational Acceptance Certificate.
(2)
Eight (8) nos. four wheel drive vehicles (five doors, minimum 2800 cc and seven seated
including driver with air conditioner) are to be supplied by the Contractor with POL and
driver during execution of the project.
(3)
All vehicles supplied by the Contractor shall be good and in a fully roadworthy
condition and make / model not below 2010. The Contractor shall pay all costs
including CD-VAT, tolls and other payments necessary to allow Employers personnel
to use them freely in all public highway between Employers Head office, Dhaka &
project areas and continue to make such payments until issuance of the Operational
Acceptance Certificate.
(4)
The Contractor shall insure all the above vehicles fully comprehensively for driver and
all passengers up to the issuance of the Operational Acceptance Certificate. The
insurance company shall be registered in Bangladesh and policies approved by the
Employer prior to delivery. Receipts of premium payments shall be submitted to the
Employer and copied to the Employer at the time of delivery of the vehicles, Full policy
documents shall be submitted to the Employer within 84 days of delivery.
(5)
The contractor shall provide fuel, oil, and other consumable for these vehicles
throughout the contract until the issuance of the Operational Acceptance Certificate.
(6)
The Contractor shall maintain all vehicles supplied by him in fully roadworthy
condition, including routine maintenance and all repairs and replacements as they
become necessary. Should any vehicle be off the road for maintenance purpose for more
than 24 hours, the contractor shall supply an equivalent vehicle at no extra cost for the
duration of the period of service. All the conditions in this Clause shall apply to the
replacement vehicle.
(7)
If any vehicle is lost, damaged or stolen whilst in the possession of the Employer, the
Contractor shall immediately provide an equivalent replacement vehicle, at his own
expenses. The Contractor shall assume responsibility for any legal and insurance
procedures resulting from any of the above eventualities.
- 37 -
SCOPE OF WORK
(8)
(9)
b)
c)
Shovel
d)
Hi-lift jack
e)
f)
g)
h)
i)
j)
(10) The Contractor shall insure all the above vehicles fully comprehensively for any driver
and all passengers up to 90 days after the issuance of the Taking-Over Certificate. The
insurance company shall be registered in Bangladesh and the policies approved by the
Employer prior to delivery. Receipts of premium payments shall be submitted to the
Employer with copy to the Engineer at the time of delivery of the vehicles. Full policy
documents shall be submitted to the Employer and copy to the Engineer within 30 days
of delivery.
(11) The Contractor shall provide fuel, oil and other consumables for these vehicles
throughout the Contract until the issuance of the Taking-Over Certificate.
2.14.9 Assistance
(1)
The Contractor shall render all necessary assistance to the Engineer and his staff in their
inspection, evaluation and supervision of the Works.
(2)
The Contractor shall also provide such other labour as required to attend night time
office security and cleaning and other requirements and where required to assist the
Engineer and his staff in measuring, supervising, testing, checking and examining the
Contractor's work whether by day or night.
The Employer shall be responsible for the payment of CD-VAT charges on items of
imported Materials and Plant incorporated in the Permanent Works.
(2)
The Contractor shall be responsible for the payment of CD-VAT and other duties and
charges of all imported items and consumables provided as required in this section 2.14.
- 38 -
SCOPE OF WORK
2.15
Undertakings by GTCL
a)
b)
(2)
Works by GTCL
a)
b)
For the detection of a gas leakage from the pipelines covered by the Project, the
precise measurement of gas flow at whole intake and off take points shall be
indispensable. Therefore, the current situation of the relevant points with respect
to the gas flow measuring capability shall be checked and necessary
countermeasures shall be taken by the Contractor. GTCL will provide required
assistance for successful implementation of leak detection.
c)
Detailed information, such as the type and exact location of whole intake
and off take points, valve stations, metering stations, etc., on GTCL and
other related gas pipeline networks
- 39 -
SCOPE OF WORK
3.
3.1
ADMINISTRATIVE MATTERS
3.1.1
Co-operation
The Contractor shall, as specified in the Contract or as instructed by the Engineer, allow
appropriate opportunities for carrying out work to:
(a) the Employers Personnel,
(b) any other contractors employed by the Employer, and
(c) the personnel of any legally constituted public authorities,
who may be employed in the execution on or near the Site of any work not included in the
Contract.
Any such instruction shall constitute a Variation if and to the extent that it causes the
Contractor to suffer delays and/or to incur Unforeseeable Cost. Services for these personnel
and other contractors may include the use of Contractors Equipment, Temporary Works or
access arrangements which are the responsibility of the Contractor.
If, under the Contract, the Employer is required to give to the Contractor possession of any
foundation, structure, plant or means of access in accordance with Contractors Documents,
the Contractor shall submit such documents to the Engineer in the time and manner stated in
the Specification.
3.1.2
Contractor's Documents
(1)
Certain Contractors Documents are specified in the Contract as being required by the
Engineer for review. The submission of such documents and the subsequent review
thereof shall be carried out under the provisions of Conditions of Contract.
(2)
In respect of any of those Contractor's Documents where the Contract is silent on the
need for submission, the Contractor is not required to submit such documents unless the
Engineer specifically requests the Contractor to do so. This is intended to ensure that the
Engineer is not inundated with data that is not critical to the review process, and the
Contractor is expected to cooperate with the Engineer to ensure that this intention is
realized in practice. The Contractor shall nevertheless provide or provide access to such
other documents when so requested, including the following:
- 40 -
(3)
a)
b)
c)
Microsoft Word
Spreadsheets
Microsoft Excel
Drawings
AutoCAD
Graphics
Database
Microsoft Access
Programming
Microsoft Project
(4)
Where the Contractor proposes to use software not listed above, then he shall seek the
Engineers approval of his proposal and provide two licensed copies of each type of
software and any upgrades thereof for the permanent use of the Employer's Personnel.
(5)
Contractors Documents shall be submitted in a manner that allows for the transmitted
data to be stored on a computer server and input into a database for monitoring the
subject and status of submissions. Where the editorial integrity of the content of the
document is of concern, the document may be provided in a protected format. In such
cases, a version of the document that allows the contents to be accessed and used by the
Employers personnel is also to be provided. In addition, paper hardcopies shall be
provided where stipulated.
(6)
All Contractor's Documents shall be stored and referenced by the Contractor in such a
manner as to allow the Employer's Personnel to readily locate, retrieve and inspect any
particular document. If the time for submission of a Contractors Document required for
review is not explicitly stated, then it shall be submitted in such order and at such times
as to allow it to be reviewed properly before implementation is required.
(7)
The specific requirements for Contractor's Documents arc identified in the relevant parts
of the Contract. The following section identifies the broad categories of such documents
- 41 -
Design Submissions
(1)
(2)
The purpose of the Design Submissions is to allow the Employer's personnel to:
a)
b)
Satisfy themselves that the design is being performed and verified in a competent,
professional manner
c)
Satisfy themselves that the design can be effectively and safely built
d)
Satisfy themselves that the Contractor is complying with any other obligation
under the Contract.
The Contractor is required to submit the design work required for review, including
specifications, in the following order of stages:
a)
b)
(3)
The Contractor is not authorized to proceed to the next stage of design until he has
received from the Engineer a notice of "no objection" for the stage of design under
review.
(4)
The Design Submissions shall be structured, referenced and presented in a manner that:
(5)
a)
b)
The Design Stage covered by the submission (either the Conceptual Design, the
Preliminary Design or the Detailed Design)
b)
c)
Where Facility references are applicable, the appropriate code for that part of the
Works forming the subject of the submission
d)
e)
(6)
Except as may otherwise be agreed with the Engineer, the Design Submission for each
respective Facility shall be comprehensive and cover the entirety of the design for that
Facility. Partial Design Submissions for a Facility will not be acceptable to the
Engineer. The review period for any Facility shall be deemed not to have commenced
until such time as the Contractor has submitted the full design according to the
requirements as stipulated herein.
(7)
Should the Engineer not require a particular aspect of the design to be submitted for
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 42 -
review, then this will be identified by the Engineer on a copy of the DSS returned to the
Contractor.
3.1.4
As-Built Documents
(1)
b)
c)
A copy of all Variations and Change orders issued by the Engineer during the
execution of the Works
d)
e)
f)
A copy of all Standards and Codes of Practice applicable to the Works, and
g)
(2)
(3)
A copy of all indicated software provided for operating and maintaining the completed
Works (i.e. software especially written or standard software customized by specialists),
together with all supporting documentation relating thereto (including "Help" files and
the like), shall be provided by the Contractor to complete the As-Built Documents
submission data.
(4)
The original design shall be clearly distinguishable from what has been built. On
drawings, this may be achieved by layer separation, line colour or line type, or a
combination thereof. In the Specifications, this shall be achieved by any changes being
identified in red. Where words have been deleted from the Specifications, the deleted
words shall remain in view but be struck through with a line.
(5)
Each change from the original design shall be referenced to the authorization giving rise
to that change.
(6)
- 43 -
3.1.5
The Contractor is required to prepare an operating and maintenance manual for the
System. Specifically, manuals must be prepared to explain how all items of equipment
and systems are to be correctly operated and maintained. The manuals are to be written
in English, and are to be fully illustrated. They are to be in a consistent format as agreed
with the Engineer to facilitate use, and are to form an integrated whole. Except where
otherwise identified in detail for specific items of equipment and systems, the manual
shall comprise of individual sections on all discrete areas of operations.
(2)
The manuals shall contain Maintenance Plans covering all aspects of the Works. Each
such plan shall be prepared to ensure that any design life requirements are met in full,
and it shall be prepared to maximize the service life. All items that are not considered to
be maintenance-free shall be identified, and recommendations shall be given for the
frequency and mode of inspection, the means of access, materials, tools and special
equipment required, and methods of carrying out the maintenance work. Where
proprietary materials and components are incorporated in the Works, details of the
manufacturer and supplier, including addresses, telephone numbers and Internet
information shall be provided.
(3)
Professionally printed and bound copies of each approved manual, in the numbers
required, together with a CD-ROM copy thereof, are to be supplied to the Engineer
before a Taking-Over Certificate is issued for that section of the Works in which the
relevant equipment or system is required to function. The first drafts in paper hard-copy
format of Operation and Maintenance Manuals, illustrating the structure and the nature
of the contents, shall be submitted at the Detailed Design Stage. The format of manuals
shall contain the following as a minimum requirement:
Index: An index which conveniently and logically sets out the format of the
Operating and Maintenance Manuals. Part of this index shall be a contents tick
sheet. This format is a minimum requirement. All items shall be listed regardless of
actual document contents. Items included are to have a tick in the appropriate box.
Operation: Operating instructions are required for all items of equipment and shall
contain the operating procedures of the systems, in addition to the emergency and
abnormal conditions procedures.
Login procedures
Report generation
- 44 -
3.1.6
A list of alarms detailing alarm initiator location and setting for alarm
operation and re-set.
Site Test Appendix: Manuals shall include an Appendix for insertion of site
commissioning and acceptance test results.
Software: All software associated with the project shall be included in CD/DVD
format as part of the Operation and Maintenance Manual (included in a DC wallet
with the hard copy)
Provision of Standards
Two copies in English (together with an additional copy of the original if not in English) of
all standards, guidelines, codes of practice or similar used by the Contractor are required. The
copies are to be provided in advance of, or with, any Design Submission or submission to
which they relate and, in general, in advance of when they may be required by the Engineer.
Where standards and the like are available from the issuing authority on CD-ROM, they shall
be provided to the Engineer in that format. Where the original standard is not in English, an
English translation shall be made and certified by a qualified translator.
3.1.7
The Drawings shall show information that is best or most conveniently presented in a
pictorial or tabular form, supplemented by appropriate notes thereon. The Specifications
shall provide all other necessary information in text, tables and figures with respect to
the materials to be used and the standard of workmanship required to enable the Works
to be manufactured, fabricated, constructed, installed, commissioned, tested and
operated as designed.
(2)
The Works shall be completed in full accordance with all Drawings and Specifications
that have been submitted for the Employers review and against which the Contractor
has not received notice from the Employer that such Drawings and / or Specifications
fail to comply with the requirements of the Contract.
- 45 -
3.1.8
Method Statements
(1)
Method statements describe how particular aspects, parts, stages and elements of the
Works are to be executed. The Contractor is required to prepare method statements in
detail for all significant elements of work, to comply with the explicit or implicit
requirements of the Quality Management System referred to in this Chapter and / or to
enable verification that all health, safety and environmental requirements are being
complied with.
(2)
Where the method of construction influences any stresses (including transient stresses)
in a part of the Permanent Works, the method statement shall refer to the design
calculations identifying such stresses and demonstrate that they are allowable.
Specifically, method-related health, safety and environmental mitigation measures shall
be included. The method statement shall also contain an assessment of the risk
associated with the method to be used, in terms of safety, cost and time, and the
measures to mitigate such risk.
(3)
Method statements to satisfy the "type (a)" requirement stated above shall describe the
overall method for the construction of a major aspect, part or stage of the Works and in
all cases shall be submitted to the Engineer without the need for the Engineer to request
them. They shall identify the resources required and the organization and application of
those resources. Temporary Works shall be identified, and the method statements shall
reference the design of the Temporary Works.
(4)
Typical topics that will need to be addressed under "type (a)" method statements are:
(5)
3.1.9
a)
b)
Transport, storage and handling procedures for major equipment and materials
c)
Installation of the System including mechanical completion and precommissioning tests, and interface coordination with the other SCADA & PLC
systems
d)
e)
- 46 -
(1)
The purpose of the management and validation of the system design by the Contractor is
to provide a systematic framework of activities and reporting that confirms the
convergence of the system design upon the fulfillment of the performance and
programme requirements.
(2)
b)
c)
d)
3.1.9.2 Methodology
The Employer requires that within the Contractors methodology for undertaking the design
process it can be clearly seen that:
(1)
The Contractor understands the complexity and interactive nature of the design task
(2)
The implementation plans and procedures are already fully developed and the
implementation methodology appears sound
(3)
The selection of technologies and subsystem specifications are based upon consistent
and coherent analysis
(4)
Design freeze(s) will be properly documented and will be fully auditable internally and
externally across the Contractor's organization
(5)
(6)
3.1.10 Meetings
(1)
Meetings shall be in either Dhaka or on the Site, as deemed appropriate by the Employer
/ Engineer. Meetings shall be attended by the Contractors personnel responsible for the
subjects under discussion, supported as necessary by the appropriate technical staff. The
types of meetings to be arranged and the personnel to be in attendance, including any
limitations on numbers in order to ensure that the meetings are productive, shall be
agreed between the Employer / Engineer and the Contractor from the outset of the
Contract. Ad hoc Meetings that are not part of the regular schedule of meetings may be
convened according to the requirements of the parties, but shall be restricted as far as
possible to only those necessary to progress the completion of the Works.
(2)
The convening party shall prepare and distribute an agenda by such time before the
meeting as is to be agreed between the Employer / Engineer and Contractor, together
with any information necessary for the proper conduct of the meeting. Progress and
coordination meetings shall be held regularly at intervals not exceeding one month, and
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 47 -
at such shorter intervals as may be dictated by the rate of progress or the need to resolve
matters that might otherwise result in delay to the Works.
3.1.11 Coordination with Other Persons and Organizations
(1)
Except where otherwise directed by the Engineer, all others working on the Site will be
required to attend a coordination meeting on a weekly basis. The purpose of the meeting
shall be to resolve any problems arising from the conflict of activities or access. In the
event that any such matters cannot be resolved by discussion, the Engineer's wishes or
decisions on the matter shall prevail. No claims for delays or additional costs will be
considered where arising from (i) shared possession of Site, (ii) failure to coordinate
properly with others having the right to be on the Site or (iii) a decision of the Engineer
on such matters. The Contractor will be expected to have assessed the risk of such
delays and costs, and to have allowed for the same in his bid. Such meetings are to be
considered as supplemental to the meetings held solely between the Contractor and
other persons and organizations that may be required for daily coordination.
(2)
The Contractor shall obtain details of all operations by utilities authorities that may
affect the Works, and keep the Engineer advised thereof.
(3)
The Contractor shall, at the reasonable request of the Engineer, make available for
inspection by other persons and organizations having the right to be on the Site any
drawings, specifications or data prepared for the purpose of the Contract, with the
exception of those that contain confidential details concerning proprietary methods of
construction or design.
The Contractor shall prepare such reports as may be required by the Engineer to explain
specific situations as they arise from time to time, in addition to the particular
requirements for reporting set out hereunder.
(2)
The Contractor shall submit a Monthly Progress Report to the Engineer within 7 days
following the end of each month. The topics covered shall include but not be limited to
the following:
a)
b)
Areas of Concern - description of any issue that could have a detrimental effect on
the Works and an impact on cost or schedule
c)
d)
- 48 -
(3)
(4)
b)
The Master Time Schedule, showing current schedule status against baseline
c)
d)
e)
Progress 'S' curves for each section of the Works and overall, showing planned
and actual percentages.
The Contractor shall also maintain a daily construction report in the form of a diary for
each separate working location on the Site, a copy of which shall be delivered on a daily
basis to the nearest Site office of the Employer's Personnel.
3.2
3.2.1
Planning
(1)
The Contractor shall ensure that the scope of work, programme and resource
requirements is clearly defined within the Project documentation.
(2)
The Project Manager shall break down the Project into manageable, discrete packages
of work and define these in a series of documents collectively called the Project Plan.
(3)
The Project Plan shall establish a clear and unambiguous understanding of interfaces,
responsibilities and standards by which the Project will be managed.
(4)
The Project Plan shall provide a resource profile showing the utilization of the staff
allocated to the job.
(5)
The Project Plan shall provide a single reference document throughout the life of the
project and shall be used to monitor the progress of the Project work.
(6)
The Contractor shall provide a Project Plan as described above. There are a variety of
influences, many particular to Bangladesh and the Project that will impact the Contract.
The Contractor shall evaluate and consider these in preparing the Project Plan and
reflect them in a realistic and balanced manner. These shall include but not be limited
to:
a)
The ownership of sites by several Operating Companies and other Third Parties.
b)
Approval for site works and access to sites from these Operating Companies and
other Third Parties.
c)
- 49 -
d)
e)
f)
g)
h)
i)
(7)
The Contractor shall appoint experienced management staff and proven project
management techniques to ensure that projects are completed to specification,
programme and cost.
(8)
The Contractor shall appoint a Project Manager who shall be responsible for all aspects
of the Project and shall act as the single point of contact for all communications with the
Engineer and the Employer.
(9)
The Project Manager shall be supported by a project team and ancillary staff to ensure
the successful execution of the Project.
(10) The Contractor shall appoint a full-time deputy to be based in Bangladesh from Award
of Contract and who will act as a point of contact for up to the commencement of
installation works whilst the Project Manager is in his home country.
(11) All Contract related correspondence from the Contractor shall be from the Project
Manager and addressed to the Employer / Engineer.
3.2.2
Programming
(1)
(2)
b)
c)
Identify demands on the Employer's staff and to arrange staff to meet those
demands
d)
Identify the impact of events that may give rise to delay to completion of the
Works or any part thereof
e)
Satisfy the Engineer that all aspects of planning and coordination are being
performed in a competent, professional manner
f)
Satisfy the Engineer that the methods of installation to be used for the execution
of the Works are planned and are in accordance with the Contract
g)
Satisfy the Engineer that the Contractor is complying with his obligations.
The Programme shall be structured and presented in a manner that achieves the intended
purpose. The Programme shall be developed using the latest version of "Microsoft
Project'' in such a manner that it can be effectively copied to and legitimately used by
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 50 -
the Engineer.
(3)
The Contractor shall provide the Programme that details the packages of work against
time, key milestones and payment milestones and identifies inter-dependencies between
the packages and progress to date.
(4)
The Programme shall be multi-leveled containing a high level phased overview and
lower level programmes detailing work packages.
(5)
b)
c)
d)
e)
Receipt of materials
f)
g)
h)
i)
j)
k)
l)
m)
Taking-Over
n)
Warranty Period
o)
Earliest and latest dates for the requisition of optional items in order to
incorporate them in the major item delivery Programme.
p)
The Programme shall be reviewed in each monthly report and progress against the
original Programme identified. In addition to this the Contractor shall review the
Programme in the light of developments and circumstances that have a bearing on
it monthly.
3.3
3.3.1
Principles
(1)
The basic principles that the Contractor is required to adhere to with respect to the
management of quality are as follows:
a)
The quality of (i) the design, execution and completion of the Works and (ii) the
management systems necessary to bring the Works into effect are both to be
assured through the operation of a QMS designed to monitor those activities.
b)
The Contractor shall establish, document, implement and maintain a QMS for use
under this Contract, and must continually improve its effectiveness based on lSO
- 51 -
900I :2000 (or such later version as may apply on the Base Date).
(2)
(3)
3.3.2
c)
The Contractor's QMS must embody the principles contained in the ISO 9000
series of international standards such as will provide full documentary evidence
that the Works comply with the Contract.
d)
The Contractor's QMS shall apply equally to the Contractor and all his
Subcontractors, sub-consultants and suppliers, and the Contractor shall be
responsible for ensuring that such Subcontractors, sub-consultants and suppliers
faithfully adhere to the requirements of the Contractor's QMS.
e)
The procedures contained within the Contractor's QMS must have been proven to
be effective on projects of a similar nature, size and complexity.
b)
c)
Changes to the manner in which the Works are to be designed, executed and
completed are to be assessed, recorded, monitored and controlled.
The Contractor's QMS must cover all aspects of the Contractor's undertakings under the
Contract including, but not limited to, the following activities:
a)
Management
b)
Procurement
c)
Design
d)
Manufacture
e)
Fabrication
f)
Installation
g)
Construction
h)
i)
Pre-commissioning
j)
Commissioning
k)
Completion
l)
Quality Control and verification systems shall ensure and record conformance of the
Works with the Contract requirements and the documented Quality Plans. This shall
include where appropriate, quality monitoring of subcontractors / suppliers,
manufacturers, goods, services and workmanship.
(2)
- 52 -
(3)
3.3.3
3.3.4
This team and its subordinate will identify the requirements with respect to how the
Contractor shall monitor the functioning and performance of the QMS, identify
problems and initiate corrective action.
(2)
The Contractor shall establish documented Procedures for monitoring and analyzing his
performance in relation to his objectives, product conformity and the satisfaction of
interested parties. The Procedures shall identify the issues for measurement and what
the needs are, and translate them into requirements. They shall identify what criteria are
applicable, what measurements are made and the methods of analyzing the data. The
issues for assessment shall include both achievement of performance objectives and
satisfaction of interested parties.
(3)
The Contractor shall identify actions for improvement from the monitoring and analysis
of his performance, and implement actions for continual improvement.
(4)
The Contractors monthly progress report shall include a summary of the monitoring
activities and results with an analysis of any trends and identification of improvement
actions.
(5)
The Engineer may at any stage of the Contract verify the correct application of the
Contractor's quality system by the application of Quality Audits during build and upon
completion of the manufacture of major items of equipment and upon completion of
major integration builds of software.
(6)
The Engineer may visit both the Contractor's and any of his Subcontractor's premises, at
mutually agreed times, in order to gain objective evidence that the level of quality
control is adequate to meet the requirements of the Contract. These visits may be in
addition to those necessary to undertake inspection and witness tests on completed
equipment or software.
QMS Reporting
(1)
(2)
The Contractor's monthly report to the Employer shall include a section on Quality
Management, which shall incorporate the following topics where applicable (not a11
topics listed are required every month):
a)
A summary of the status of QMS (including the status at the end of the last period,
with comments on progress, and the items anticipated during the next period)
b)
c)
d)
In the regular progress meetings with the Engineer and other Employer's Personnel, the
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 53 -
Contractor shall report the status of the above items as appropriate and, in addition,
discuss:
3.3.5
3.3.6
a)
b)
Items arising from the management review meetings that require revisions to the
Contractor's QMS.
QMS Documentation
(1)
The Contractor must submit all relevant records to the Employer when the Works or any
portions thereof are finally taken over. The specific contents of such records shall be as
required by the Engineer. The records shall be suitably indexed and labeled so that
records for specific sections or parts of the Works can be readily identified.
(2)
The Inspection and Test Plans may be in the Contractor's own format but shall include
as a minimum the following:
a)
The series of activities, including the inspections and tests performed in a logical
sequence appropriate to the type of work
b)
c)
d)
e)
The personnel allocation for performing the activities, inspections and tests
f)
g)
The type of verification document or check-sheet used to record the result of the
activity
h)
A facility for the Engineer to indicate his requirements to inspect or witness any
activities.
(3)
All records are to be made available for inspection by the Employer / Engineer. Copies
are to be submitted when so requested by the Employer / Engineer.
(4)
(5)
The Contractor shall comply in all respects with the requirements of the safe working
practices of the Employer, details of which will be provided on requisition in writing to
the Engineer.
(2)
No explosive or other dangerous substance shall be brought onto any site or used for
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 54 -
any purpose unless the Contractor has previously obtained the written approval of the
Engineer.
3.4
(3)
It shall be the Contractor's responsibility during the works to ensure that the handling,
storage and use of any dangerous substances follow the safe working procedures to
ensure the Health and Safety of all personnel and property.
(4)
The Contractor shall ensure, and give written details if so requested by the Engineer,
that the materials used in the construction of the works, or those required for operation
after take-over, does not in themselves or in any combination lead to the production of
other dangerous substances, materials or conditions.
changes to the quantities of any item of work included in the Contract (however,
such changes do not necessarily constitute a Variation),
b)
c)
changes to the levels, positions and / or dimensions of any part of the Works,
d)
e)
any additional work, Plant, Materials or services necessary for the Permanent
Works, including any associated Tests on Completion, boreholes and other testing
and exploratory work, or
f)
The Contractor shall not make any alteration and / or modification of the Permanent Works,
unless and until the Engineer instructs or approves a Variation.
- 55 -
4.
4.1
4.2
4.3
(1)
The design life of the system infrastructure shall be 15 years. The electronic equipment
shall have an operating life of 10 years minimum.
(2)
The SCADA System shall be designed, manufactured and installed such as will ensure
that modifications and / or extensions can be executed safely, with no disruption of the
operation of the Pipeline System.
(3)
Database in the SCADA servers of the MCC and the ACC shall form part of a
redundant pair arrangement or the like. The database of the MCC and the ACC shall be
synchronized to be maintained as a redundant pair database. Moreover, SCADA server
in MCC / ACC shall be configured each in redundant application.
(4)
In case of a failure on the SCADA server system of the MCC, a switch over to the
SCADA server system of the ACC shall take place to continue scanning and storing
data from the RTUs.
(5)
In the event of a communication failure between any RTU and the MCC / ACC, the
RTU shall continue scanning and storing data from the field devices and subsystems.
After such communication failure is rectified, all missing data at the MCC or the ACC
shall be transmitted from the respective RTU.
(6)
The MCC and ACC SCADA master computer shall generate reliability reports on
demand, including summaries, fault categories, trends and frequency of failure of
specific components.
The reliability of the SCADA System shall ensure that the monitoring and control
functions shall not contribute to degradation of operations due to the loss of control of
safety-critical functions. The architecture of the SCADA System shall effectively
exploit software and hardware redundancy to achieve high operational reliability.
(2)
The basic design of the SCADA System shall be based on a 24 hour per day, 365 day
per year operation. The availability of the SCADA System will be 99.7%.
MAINTAINABILITY
(1)
The SCADA System maintainability design shall be consistent with the availability
requirements. In particular, diagnostic time, replacement component availability,
software loading and validation shall be analyzed and defined in Design Submissions.
(2)
(3)
On-line error detection capabilities within the RTU and detailed reporting to the
connected stations of detected errors.
- 56 -
4.4
4.5
(4)
(1)
EXPANDABILITY
(1)
The SCADA shall support a scalable architecture for future expansions. It shall be
possible to add additional RTUs and HMI Workstations without the need for additional
servers. Expansions to database sizing shall be simple (such as entering a new
authorization code) and shall not require additional software installation. In addition, the
SCADA shall allow communications with a wide variety of control devices utilizing off
the shelf driver packages.
(2)
(3)
GTCL plans to expand their natural gas pipeline network. The other SCADA system
dedicated for those planned pipelines will be prepared. The SCADA System shall have
an interface with the other SCADA systems and capability to monitor whole pipeline
network expanded in the future. An OPC compliant server will be used for the SCADA
server.
SPARE CAPACITY
(1)
All parts of the system (I/O, operator stations, RTU interface etc.) shall have the
capability of further expansion by an additional 25% to cater for future expansion. This
includes all aspects including hardware, software, firmware and communications.
(2)
Sufficient point/tag software licenses shall be furnished to cover the entire initial scope
of the Project, including all configuration databases, control modules, I/O points and
HMI displays.
(3)
Point/tag licenses shall be provided for all spare I/O capacity, specified and included
with the system.
(4)
All operator stations must be capable of viewing all tags, databases, trends and HMI
displays.
- 57 -
5.
PROCUREMENT
REQUIREMENTS
5.1
INTRODUCTION
5.2
5.3
AND
CONSTRUCTION
INSTALLATION
GENERAL
(1)
This section covers the procurement and construction / installation of the system and its
components both at the factory and on site.
(2)
PROCUREMENT
(1)
The Contractor shall be responsible to the procurement and delivery including all related
activities for all equipment and materials to be supplied under this Contract into
Bangladesh and onwards to the final locations.
(2)
The Contractor shall prepare and submit a Procurement Plan to the Engineer outlining
the methods, procedures and schedules for all procurement and related activities
required for the Project. The Procurement Plan shall be submitted for the review of
Engineer no later than 45 days from the Commencement date, and it shall include a
sample of each standard form to be used for such activities.
(3)
The Contractor shall provide the Engineer with bi-weekly reports on the procurement
status of all equipment and materials, or more frequently when requested by the
Engineer. Any deviation from the schedule on any of these items must be reported
immediately to the Engineer with an explanation given for each deviation from the
schedule and the proposed action plan to correct the situation.
(4)
No deliveries to Sites shall be made without prior written approval by the Engineer. The
Contractor shall allow in his program a period of two weeks for this permission to be
given.
(5)
The Contractor shall make visits to site to identify the conditions for delivery and
temporary storage prior to installation.
The Contractor shall install all equipment and construct all associated facilities under
this Contract.
(2)
The Contractor shall be responsible for ensuring that any existing facilities at sites are
not damaged by Contractor's activities.
(3)
The Contractor shall be responsible for ensuring that any operations of existing gas
facilities at Sites are not interrupted by Contractor's activities.
(4)
The Contractor shall note that at many locations, new equipment is to be installed
alongside existing equipment which is operational and must continue to operate during
and after the installation.
(5)
The Contractor shall be responsible for the temporary power generation at remote Sites
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 58 -
5.4
5.5
(6)
The Contractor shall carry regular inspection of Sites to ensure that installation of
equipment and construction of associated facilities are in accordance with the specified
requirements.
(7)
The Engineer will carry out regular inspection of Sites to verify that installation of
equipment and construction of associated facilities are in accordance with the specified
requirements.
(8)
The Contractor shall rectify any installation or construction work identified by the
Engineer that is not in accordance with the specified requirements.
The Contractor shall set up the system for requesting access to Sites for the Engineer for
all visits required to complete the Contract Works.
(2)
Where the Contractor's staffs are required to be accompanied by the Employer or the
Engineer or the staff from another Operating Company, it shall be assumed that the
normal hours of work that they will be available for shall be Sunday to Thursday 09:00
to 17:00 hours inclusive of travel time to the agreed working place.
(3)
The Contractor shall ensure that Site is left in a clean, tidy and orderly state and all
equipment, materials and tools are stored in the designated location and waste materials
are removed on completion of a day of work or particular activity.
The Contractor shall be responsible to follow the safety procedure and regulation of
each Site operated by the Employer or other operating companies.
(2)
No explosive or other dangerous substance shall be brought onto any Site or used for
any purpose unless the Contractor obtains the written approval of the Engineer.
(3)
The Contractor shall be responsible to ensure that the handling, storage and use of any
dangerous substances follow the safe working procedures to ensure the Health and
Safety of all personnel and property.
(4)
The Contractor shall ensure, and give written details if so requested by the Engineer,
that the materials used in the construction of the works, or those required for operation
after take-over, does not in themselves or in any combination lead to the production of
other dangerous substances, materials or conditions.
- 59 -
6.
SCADA SYSTEM
The purpose of SCADA system is to ensure efficient, effective and reliable control,
management and supervision of pipeline from both the Master Control Center (MCC) and the
Auxiliary Control Center (ACC) using Remote Terminal Units located at suitable locations
along the pipeline.
The Master Control Center (MCC) shall be the central operating center to monitor and control
the pipeline network.
The Auxiliary Control Center (ACC) shall be the hot-standby operating center with the same
functionality and operating capability as the MCC.
The Communication between MCC SCADA Server at Dhaka and ACC SCADA Server at
Ashuganj shall be through redundant (1+1) high speed high bandwidth communication link to
be provided by suitable service provider.
RTUs will be used for control and monitoring of pipeline parameters like flow, pressure,
temperature, valve open / close status, pig arrival indication through pig signaler, CP
parameters, electrical parameters etc. and update the MCC / ACC SCADA stations. The
SACDA station will also be used for remote opening / closing of selected valves.
The data from the RTUs will be collected at respective MTS and transported to MCC and
ACC through a communication system described in Cl. No. 7.
There shall be a Web server for SCADA system at MCC and ACC. The communication link
between GTCL SCADA System and Operating Company Terminal (OCT) at ten (10)
locations of franchisees shall be established through web server of GTCL SCADA Server.
6.1
6.1.1
(1)
(2)
(3)
(4)
(5)
(6)
MCC
MCC shall be configured with the following system components as a minimum;
(1)
- 60 -
SCADA SYSTEM
(2)
(3)
(4)
1 No. pipeline application (leak detection and load balancing) console including
necessary sub-systems and components
(5)
(6)
2 Nos. 67 inch Large screen monitor (flat panel LCD monitor with LED backlight type)
(7)
(8)
The SCADA System shall have capability to accommodate the other SCADA system
prepared for new pipeline.
6.1.2
ACC
ACC shall be configured with the following system components as a minimum;
6.1.3
6.1.4
(1)
(2)
(3)
(4)
1 No. pipeline application (leak detection and load balancing) console including
necessary sub-systems and components
(5)
(6)
2 Nos. 67 inch Large screen monitor (flat panel LCD monitor with LED backlight type)
(7)
(8)
RTU
(1)
The RTU is a device that is required to be installed at each Site to collect data, code the
data into a format that is transmittable and transmit the data to the MCC and the ACC.
RTUs shall also collect information from the MCC and ACC and implement processes
that are directed by the MCC and ACC. RTUs shall be equipped with input channels for
sensing or metering, output channels for control, and a communication port.
(2)
- 61 -
SCADA SYSTEM
whole GTCL pipeline network operation accessing to the SCADA server at MCC /
ACC through communication backbone prepared by the Project.
SL.
NO.
CODE
SITE
20-CML-100T
10-ASH-204T
10-HOR-300T
30-PBG-500T
10-JAL-600T
30-PBG-700T
20-FAU-701T
20-FAU-702T
30-PBG-701T
10
30-DMR-401T
The following equipment shall be equipped as minimum for each of the above OCT:
a)
HMI: 1
b)
Color printer: 1
c)
The following equipment shall also be provided for monitoring at the head office at
Dhaka.
a)
HMI workstation : 2
b)
Engineering Workstation : 1
6.2
6.2.1
General
(1)
The SCADA System shall be based on a standard SCADA system including hardware
and software that must have been proven in use in one or more similar applications for
at least 2 years, and which is a Commercial Off-The-Shelf (COTS) system. The
application history shall include safety-critical systems.
(2)
All equipment to be provided for the SCADA System shall be provided with standard
interfaces and open system software to communicate with RTUs and other subsystems,
to enable system expansion and upgrade interconnection model or similar standard.
(3)
Monitoring and controlling the entire Pipeline System shall be a microprocessor based
SCADA System with personal computer-based and/or work station based operator
consoles configured with HMI software for operator interface.
- 62 -
SCADA SYSTEM
(4)
6.2.2
The SCADA System CPU load shall occupy a maximum of 60% when all programs for
the SCADA System are running simultaneously.
Scalability:
The SCADA software must have a modular structure. It shall be possible to expand the
SCADA system by adding additional redundant pairs of SCADA servers. All data from one
server must be seamlessly available from another SCADA server or clients of that other server
without the need to replicate any databases and do any double configuration. The system shall
be configured and expanded on-line without stopping the system. Online editing or
modification shall be provided for graphics, item (tag) definitions, reports and I/O drivers.
6.2.3
6.2.4
The SCADA shall provide data acquisition and control facilities to communicate with
RTUs using standard software drivers and shall not require any programming to
implement. All configurations shall be permissible while the server is on-line without
interruption to data acquisition and control on other channels.
(2)
collecting data;
(3)
Once a RTU is configured and placed in service, the SCADA shall automatically begin
background diagnostic scanning of the device to ensure that communications are
monitored independently of any data acquisition scanning. The SCADA software shall
have diagnostic tools for analyzing problems / running conditions and for optimizing
performance of the system.
(4)
b)
Report by exception (user request, alarm initiated by RTU, for remote control)
(5)
(6)
The SCADA system shall scan all RTU within less than 15 minutes.
- 63 -
SCADA SYSTEM
Custom graphics shall be provided by the Contractor as part of the Detailed Design
submission. The custom graphics shall include but not be limited to the following:
(1)
Pipeline overview
(2)
Schematics for each individual station, with process data and facilities status
(3)
Trend graphics
(4)
(5)
(6)
(7)
(8)
The SCADA system shall come with a set of standard displays to allow immediate
operation of points without need to develop any custom displays. Minimum displays to
be included:
Point Detail display for each type of point supported e.g., Analogue, Digital
Composite, Totalizer etc.
Faceplates / popups for operator control of each point type;
The SCADA system shall provide the ability to create custom system displays such as
point detail displays.
(10) The SCADA system shall provide a means to create a template configuration for a
complete piece of equipment (e.g., a pipeline compressor) to include all related SCADA
configuration for that type of equipment including at a minimum:
SCADA Points (could be 100s of points in one equipment) and the template
structure for creating point names, (i.e., naming convention based on equipment
details)
Trend definitions
Any algorithms / calculations
Key variables that are to be viewed by the operator in any summary tables of like
equipment
Display elements of equipment such as custom displays operators use to control the
equipment. Multiple displays should be available e.g. main display, diagnostic
display etc.
Relationships to other equipment e.g., upstream, downstream.
Task filters to allow an operator to quickly filter a list of similar equipment e.g.,
which compressors are under performing
- 64 -
SCADA SYSTEM
6.2.5
The SCADA System shall provide a display and print alarm messages and events as
alarm / event logging.
(2)
(3)
(4)
alarm priority;
alarm status;
date & time of the alarm event (internal or external time stamp);
item name;
alarm text.
Acknowledging of outstanding alarms shall have the main function to provide the
operator with a list of outstanding alarm messages. It shall be also possible to
acknowledge alarms within this overview. Outstanding alarms comprise:
Delayed alarms
Repeated alarms
Alarm groups
Alarm collection
First-out
First-up
(5)
(6)
The alarm and event management system shall be established based on area codes,
groups, alam11event types, alarm priorities, etc.
(7)
Actions such as status changes, setting and resetting of alarms, control operations and
operator actions shall be logged as events in the historical database.
(8)
The SCADA system shall natively provide the following alarm management
functionality:
(a) Separate displays for process alarms and SCADA system alarms allowing the
Operator to focus on alarms during an incident.
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 65 -
SCADA SYSTEM
(b) Alarm zone showing the highest priority unacknowledged alarm in the
Controllers scope of responsibility regardless of any filter being applied
(c) Alarm Icon for use in custom displays for consistent representation.
(d) Ability to aggregate alarm status of all alarms for a point up to an alarm status of
all points in an organizational unit. Be able to use the same alarm icon used in
displays for points to also show the alarm status of an organization unit.
(e) Comprehensive set of alarm types such as PV Low, PV High, Rate of Change,
Deviation, Uncontrolled event etc. including features such as alarm deadbands,
alarm on delay and off delay
(f) Automated alarm emailing / paging
(g) Automatic Event (including alarms) archiving
(h) Alarm overviews logging showing Outstanding alarm overview and Sequence Of
Events
6.2.6
Historical Data
(1)
The SCADA system shall able to support scan based and event based recording. A
historical database system shall record on hard disk the details of every event and alarm.
Analogue data shall be logged to trend records.
(2)
Maximum, minimum, average and other statistical values shall be available for
operator-definable time periods, to allow further analysis and reporting. The SCADA
system besides having the flexibility to configure to store the historical data in scan or
event based, it shall also have the capability to store the data base on the item based.
The SCADA system shall also support a playback function that allow user to view
historical data through operator displays.
(3)
Database displays, including the derived statistics, shall be fully searchable, sortable and
reportable, and pre-configured to provide trends and summaries of the data for specific
purposes as well as user-configured reports.
(4)
All historical data shall be stored in a nominated primary location. After a configurable
period of time data can either be moved to a secondary location for long-term storage
and analysis or deleted if the data is no longer required. The primary location shall
optionally be the local hard disk with the secondary location being a choice of local hard
disk, recordable CD / DVD or network disk. The amount of time that archives can be
maintained on the primary location before transferal to the secondary location shall only
be limited by the size of the hard disk. The SCADA shall allow the user to define the
specific intervals of history to be archived to avoid archiving of unnecessary data.
(5)
Hard disk storage capacity shall be adequate for the projected demands of the SCADA
System. Its sizing shall be fully justified and based on worst case calculations.
(6)
The storage shall be capable as for each data type identified in the following table:
CLASS OF DATA
Plant alarms
PERIOD
CURRENCY
Immediate
Until cleared
- 66 -
SCADA SYSTEM
CLASS OF DATA
PERIOD
CURRENCY
Immediate
Up to 24 hours
Up to 40 days
Up to 3 months
Indefinite
Immediate
Until cleared
Up to I month
6.2.7
(7)
All history information shall be able to be stored on disk. The storage units shall be
removed at the end of its lifetime and the storage unit shall either be backed-up or
deleted automatically. Before backup-up / deletion, however, a warning shall be given
to the operator or system manager backup/deletion at configurable time before
backup/deletion of the unit. The archived data can be restored from the backup medium
back onto the system. The restored data can be used transparently in trends, reports etc.
along with current data.
(8)
The SCADA System shall have a proven network management function to ensure
performance, scalability, easy maintenance, and open but secured interface. It must
cater to the following requirements.
Printer Management
(1)
The SCADA system shall include the printer management that allows the system
manager to use their HMI for configuring the printers that will be used by the SCADA,
and the printer management supports printer output via:
1. A printer queue
2. An application
3. A file on disk
(2)
6.2.8
The SCADA system shall support on-line changes, add printer destination if require any
report sending to different locations. The SCADA system shall also able to define
backup devices for a destination, which will be used when the main device is
unavailable.
A simulation function shall be provided to assist the operator in checking the safety and
feasibility of planned operations.
(2)
The function shall include the ability to check the validity of any planned operation and
identify any situations where operating constraints may be exceeded.
(3)
The training simulator shall be provided for operator training of a wide range of
operational scenarios, including emergencies.
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 67 -
SCADA SYSTEM
(4)
6.2.9
At least one of the HMI workstations shall be provided as the simulation / training
console at the MCC.
System Security
(1)
The system shall incorporate initial security for all users accessing the system as a first
layer of protection of the system from non-designated users.
(2)
The system shall support up to 6 levels of the system security providing proper degrees
of access to system operation and system configuration works based on the following
levels:
(3)
a)
Manager level
b)
Engineer level
c)
Supervisor level
d)
e)
Operator level
f)
Viewer level.
Each operator shall be assigned a user password including single and multi-user
passwords and any actions initiated by the operator shall be logged in the Database.
Workstation users shall be assigned to different levels of access, according to the
functional requirements of the users. The workstation levels shall restrict the users to
specific functions only of the control system. The limitations may be functional,
operational or geographic. Workstations mode shall generally be assigned to a user when
they log on. It will be pre-assigned for each possible user. The levels shall include:
View-only shall provide view-only functionality.
Operator Mode shall provide those functions, alarms / events and presentation applicable
to the operation of Gas stations and gas network. Set-points can be altered in this mode.
Supervisor Mode shall provide the operator mode functions as well as allowing this user
to configure operator settable parameters.
System Engineer / Programmer Mode allow access to all parts of the system including
Expert System control functions. Database and display maintenance, programming,
application module testing and system configuration changes shall be undertaken in this
mode.
Remote Access Mode via the web browser client allows corporate GTCL staff with the
correct authority, the capability of remotely accessing the graphic displays, events, alarms
and other system operational information. No supervisory control shall be allowed in this
mode and access shall be controlled by passwords.
Administrator Mode shall allow domain / system level administration privileges.
The SCADA System shall statistically check the data integrity of all data acquired from
the field.
- 68 -
SCADA SYSTEM
(2)
In the event that an invalid or timeout data or response is received, the data shall be
ignored, and the system shall record the transition as an error and signal an alarm to the
operator indicating the device or channel that is in error.
The SCADA System shall generate standard operation and maintenance reports
including a system alarm log and maintenance alarm log, which will be automatically
printed out on the network printers.
(2)
Custom operation reports shall be configured and generated including the following;
a)
Shift reports
b)
Daily reports
c)
Monthly reports
d)
Maintenance reports
e)
Event-based report
f)
g)
h)
i)
(3)
A report shall be scheduled for automatic generation. The time, date and even an
interval for report generations can be specified. Reports can be saved on disk for a given
period. After this period elapses, the reports shall be deleted.
(4)
Reports can be assigned priority. When more than one report shall be scheduled for
generation at the same time, the order in which they are generated shall depend on their
priority. The priority value ranges from 0 (lowest priority) to 9 (highest priority).
6.2.12 Trending
(1)
The SCADA shall provide trending capability with the following functions:
Historical trending
Trend Zooming
Trend between archived, real-time and historical data (e.g. year and batch
comparisons.). Comparisons between the same point offset in time, or different
points must be possible.
- 69 -
SCADA SYSTEM
Copying the currently displayed trend data to the clipboard for pasting into
MSExcel spreadsheet or documents for further processing.
(2)
All trend configurations shall be possible on-line without interruption to the SCADA.
Historization of data shall not be affected by changes to trend configuration. It shall be
possible to protect the configuration of some of the trends via a password.
(3)
For each trend set display it shall be possible for operators to configure the number of
historical samples and ranges displayed. Point values configured in trend sets shall be
configurable on-line.
Process control graphics shall allow the use of all of the open and standard technologies
of the World Wide Web (HTML, XML, ActiveX, JAVA, etc.). It must be possible to
copy graphics from web pages and other HTML documents to process graphics.
(2)
It shall be possible to view and use process control graphics in a standard Web browser
without the use of graphics translations or terminal services software.
(3)
It shall be possible to see all interlocks, sequences, and logic in the process controller
directly from the human interface, using pre-built detail displays. Custom interlock
displays or interlock displays that require the use of pre-built logic shall not be
acceptable.
(4)
The HMI environment shall be used both for configuring the application and creating
and modifying displays. From the HMI environment, displays can be started and test the
functionality on-line and go-back while the rest of the SCADA modules and database
keeps running in the background
(5)
Human interface shall allow operators to add information to active alarms, via free-form
comments. These comments shall be stored indefinitely, and be available at the alarm
screen, event archive, and in reports. Alarms that include comments shall be identified
on the standard alarm screen. The most recent alarm must be visible in at all times. The
full text of this alarm, priority, and type of alarm must be visible.
(6)
The HMI shall be capable of operating over LAN or WAN at any communication speed
from 19.2 kbaud to 1 GHz networks at any distance from the controllers. This includes
telephone modem connection. The HMI shall be the native application, not via CopyPC, Terminal Server or other similar MMI replication.
(7)
It shall be possible to transfer data samples shown in standard trends to a package such
as Microsoft Excel for further analysis.
(8)
History, alarms and SOE data of the entire system should be available at each operator
station. Each Operator node should have facility to view all History, alarms and SOE of
the entire system.
(9)
- 70 -
SCADA SYSTEM
(10) Operator station software furnished shall be fully functional and not subject to future
upgrade license fees for additional functionality. The following functions shall be
provided as standard - Historical Message Integration, Control & Logic Drawing
Display, Trend Viewer, Configured Information Reference, Advanced Alarm Filter,
Long Term Data Archive and Report Package
(11) For systems utilizing domain-based authentication, it shall be possible to integrate the
control system domain into a higher level domain structure such that the login
credentials for all users accessing the system be managed externally by the sites IT
department
6.2.14 System Time Adjustment
A system time adjustment function shall be installed to ensure time accuracy and
synchronization of all events and operations covering all the Sites. The SCADA System shall
be synchronized from GPS based Time System to be installed at MCC and ACC.
6.2.15 Interface to Other System
Chevron, one of the natural gas production companies has its own SCADA system for their
gas field operation. Chevron will prepare the web server to disclose their operation data at
their own responsibility to GTCL. The SCADA System shall have the function of collecting
the data from Chevron's web server through the secured lease line. Any hardware or software
necessary for interfacing shall fall under the scope of the Vendor.
6.2.16 Integration with other applications
The SCADA software shall have an open interface to connect to 3rd party products like
management information systems, batch tracking and leak detection systems, etc. The open
interface shall be based on the following industry standard interface protocols as minimum
shall be available:
ODBC
OPC
Beside these industry standard interfaces, the SCADA software shall allow the user to add
own customized interface via an Application Programmers Interface (API). The SCADA
shall have the provision to seamlessly integrate with building / facilities Control System,
Acess Control system, CCTV system etc.
6.2.17 Cyber-security
(1)
The managed Cyber Security shall address the security of SCADA plant assets and
include:
a)
user initiated communication tunnel for services and protect connections between
the corporate IT network and SCADA Network
b)
- 71 -
SCADA SYSTEM
(2)
c)
reports into the operation and cyber security status of SCADA components and
the network.
d)
e)
f)
The Cyber Security Patch management shall specifically include the following:
a)
b)
c)
(2)
The application software shall be based around a real-time dynamic model of the gas
pipeline network covered by the Project which shall provide a kernel for any additional
functionality required.
a)
b)
6.3
- 72 -
SCADA SYSTEM
6.3.1
Server
(1)
The SCADA servers to be installed in the MCC and the ACC shall be provided to
communicate with each RTU and be capable of performing the following tasks and
functions:
a)
b)
c)
Trending
d)
e)
Engineering tool
f)
Alarm management
g)
Reporting
(2)
All servers shall form part of a redundant pair arrangement and be equipped with full
Human-Machine Interface activities. The data from RTUs and other agencies will be
received at Server at MCC which shall act as primary and will be transmitted to Server
at ACC through a 1+1 redundant OFC network of a third party optical service provider.
In the event of failure of primary Server at MCC, the data received at MCC will be
routed to Server at ACC through switching network at MCC. Once the Server at MCC
becomes operative, the data flow is directed to it.
(3)
(4)
(5)
(6)
All Server / work station shall be provided with license for various system as well as
operational software.
(7)
(8)
(9)
Minimum requirements
Processor
Single CPU: 2.93 GHz Quad Core Intel Xeon (dual processor)
or faster
Minimum of 16 GB main RAM memory expandable up to 32
GB.
1024 x 768 65K colors
RAM
Video
resolution
Video RAM
8 MB
Operating
- 73 -
SCADA SYSTEM
system
Hard disc
DVD Drive
Network
Interface
Power Supply
Interface
At least Six (6) USB ports and minimum one RS232 port;
Audio output port and speakers.
101 key AT keyboard or equivalent keyboard and Keyboard
with wireless connectivity
Minimum 24, high resolution LCD monitors capable of a
resolution of 1920 x 1200 pixels PC speaker.
Keyboard
Display
6.3.2
HMI Workstations
(1)
The main operator interface of the SCADA System for control, monitoring and
shutdown shall be a software application. The application shall operate on personal or
desktop computers within local workstations. These workstations shall be 'clients' to the
main system communication controllers or 'servers'.
(2)
The number of client operator stations shall be such as will be capable of fully
controlling and monitoring all likely operating scenarios within the facilities.
(3)
The salient parameters of the local workstations shall be as under. The PCs shall be
currently available models at time of installation.
Parameter
Minimum requirements
Processor
RAM
Browser
Operating
system
Hard disc
DVD Drive
Network
Interface
Interface
At least Four (4) USB ports and minimum one RS232 port;
Audio output port and speakers.
- 74 -
SCADA SYSTEM
Keyboard
Display
6.3.3
Printers
High quality monochrome (black and white) laser printers and color laser printers, with a
minimum throughput rate of 20 pages a minute, shall be provided for printing reports at the
MCC and the ACC. Each printer shall be accessible from all workstations to provide flexible
use of network printers connected to the LAN.
6.3.4
WEB SERVER
The SCADA systems shall be WEB enabled. There shall be a Web server for SCADA system
at MCC and ACC. The users using Web browser software (e.g. Internet explorer, Netscape
Navigator or Mozilla browser) shall access the web server. The web server shall be able to
provide following facilities:
To view all the online SCADA HMI displays with automatic data updation.
To view reports in PDF format, to get the comments in the reports; and verification
confirmation from customers / suppliers through internet.
At a time 50 nos. of concurrent users shall be able to access the web server for SCADA
system.
6.3.5
LAN
Interconnection within the SCADA System at the MCC and the ACC shall be supported by a
redundant LAN, which shall conform to a recognized international open standard. There shall
be L3 Core Switch 1+1 redundant mode with optical and Ethernet ports and L2 Ethernet
Distribution switch 1+1 redundant mode with optical and Ethernet ports.
L3 Core Switch specification
(1) Port Density
(2) Performance
- 75 -
SCADA SYSTEM
(3) VLAN
(6) Security
SSH
remote
login,
BPDU
- 76 -
SCADA SYSTEM
(9)
Electrical
Approvals and
Compliances
(10) Environmental
Specifications
(11) Approvals
and
Compliances
(3) Switching
data
transfer method
CSMA/CD
(6) Routing
Multicast
and
SCADA SYSTEM
(8) Reliability
(10) Processor
&Memory
(11) Interface
connector
RJ-45
(13) Power
consumption
(14) IPv6
(15) Approvals
Compliances
6.3.6
A flat panel large screen monitor which will give an overview of information to all
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 78 -
SCADA SYSTEM
The monitor shall have a picture size of 67 inches diagonal with a screen aspect ratio
chosen to accommodate both the video formats and graphics resolution selected.
6.4
6.4.1
General
(1)
The RTU is a device that is required to be installed at each Site to collect data, code the
data into a format that is transmittable and transmit the data to the MCC and the ACC.
RTUs shall also collect information from the MCC and ACC and implement processes
that are directed by the MCC and ACCs. RTUs shall be equipped with input channels
for sensing or metering, output channels for control and a communication port.
(2)
The RTU's shall be 32/64 bit microprocessor based programmable units with both
erasable RAM and ROM memory. Each of the RTUs shall have its own processor,
memory, battery backed power supply unit & communication processors confirming to
communication protocol like Modbus, DNP 3, Ethernet etc. and I/O cards complete in
all respects. The RTUs shall have TCP/IP port and serial port for polling from Master
Station & Emergency Master Station. CPU shall have Dual core processor with a speed
of 600 MHz or more. It shall have at least 128 MB DRAM, 32 MB Flash RAM to
support current and future applications. The CPU shall also have a provision of 2
Ethernet ports so it can communicate with SCADA and simultaneously able to be
loaded with configuration from other / spare port.
(3)
All RTU shall be modular and from the same model product line with identical
capabilities. The RTU I/O Modules shall be interchangeable without any interruption.
RTU shall be reliable, field proven and evolutionary state of the art.
(4)
The I/O cards shall not be combined for the functionalities i.e. each card shall dedicated
modules for Analog input, Analog output, Digital Input, Digital output etc. The RTU's
shall be designed to function such that no single point of failure or the inadvertent
leaving of a printed circuit board out of the RTU shall cause a control mal-operation or
result in any false operation or continuous communication transmission.
(5)
The complete RTUs shall be supplied with all its components including the cabinets.
The cabinets should be weather proof and suitable for non-air-conditioned room. The
actual layout of RTU along with its internal wiring, mounting arrangement etc. shall be
carried out in detailed engineering. Proper illumination shall be provided inside the RTU
cabinet.
(6)
RTUs shall be outdoor self-stand type data acquisition and control units, with IP65
enclosure. RTUs shall be installed under the existing sunshades at the Existing Sites and
new sunshades shall be prepared by the Project at the Additional Sites for weather
protection.
(7)
- 79 -
SCADA SYSTEM
6.4.2
a)
b)
c)
d)
I/O interface,
e)
f)
g)
Display monitor for process data monitoring at specified site (refer to Section
6.5.8)
h)
i)
j)
RTU Subsystem
The RTUs shall comprise the following subsystems:
a)
b)
Analog input
c)
d)
e)
Analog Output
f)
2 Ethernet port for polling from MCC and ACC through TCP/IP
g)
Serial ports / Ethernet port to connect Portable Diagnostic Test Unit (PDT)
h)
Serial ports for connecting IEDs e.g. Flow computers, Gas chromatograph.
i)
j)
Diagnostic tools
k)
The RTU's shall be configured such that interdependence of function is minimized and failure
of any part of a RTU Module subsystem except the common logic subsystem shall not
directly affect the integrity of the unit, as a whole.
Each I/O channel shall have Transient Voltage Suppression of 600W peak pulse power
capability at 101000s waveform, repetition rate:0.01%
The RTU should be able to store alarm/ events in case of communication failure till the time
of communication restoration.
The RTU system software shall provide the overall management of the supervision,
monitoring and control function within the RTU and also manage the local Programmable
Diagnostic Test Unit, communications, comprehensive diagnostic facilities and RTU start up
procedures.
- 80 -
SCADA SYSTEM
The RTU shall be programmable and shall have facilities for developing logic to interface
with the IEDs as and when required. To this effect, all necessary tools, software and
documentation shall be part of supply of the RTUs within the scope of this document.
6.4.3
Digital Inputs
Typical specification of Digital Input Modules to be supplied is as given below:
6.4.4
Input Type
Contact Wetting
Resistance recognized
Resistance recognized
Isolation
Using optocouplers
Debounce circuitry
10 m/sec
Indicators
Digital Outputs
Typical specification of Digital Output Modules to be supplied is as given below:
6.4.5
Output Type
Indicators
Relay Type
Contact arrangement
Contact Rating
DO command activation
Analog Inputs
Typical specification of Analog Input Modules to be supplied is as given below:
Input Type
Ranges
4 - 20 mA, , 1-5V DC
Accuracy
The nominal input range shall with HART communication protocol for a smart transmitter.
The RTU should have On-board HART capability to communicate with smart transmitter
Analog/Digital
Conversion
Resolution
Repeatability
- 81 -
SCADA SYSTEM
6.4.6
Analog Outputs
A specification of Analog Output modules to be supplied is as given below:
6.4.7
6.4.8
Output type
Output Range
4-20 mA DC
Loading
Accuracy
0.1% of range
Repeatability
0.1% of range
Pulse Inputs
a)
Suitable for accepting through switch select either of the following inputs:
b)
Voltage free dry contact relay operation (Max.25 contact closures per second). Contact
bounce shall be suppressed.
c)
Magnetic pick-up coil of 1500 ohms impedance and output voltage and frequency (up
to 5 KHz) proportional to the flow rate, Voltage output varies from 250 mV to 25V.
Suitable sensitivity and dynamic signal range shall be incorporated.
d)
e)
Communications
The RTU shall support both internal and external communications functions.
The RTUs shall have the capability to support simultaneous communications with multiple
independent master stations, a local user maintenance interface and a local logger (printer).
Each RTU shall be able to support a minimum of four communication ports. Minimum two of
these ports, shall be capable of supporting communications to peripheral devices such as
multiple SCADA master stations, solid-state meters, microprocessor based device and
remote/local PCs; and the fourth port to be a dedicated maintenance port. Each
communication port shall have Transient Voltage Suppression of 600W peak pulse power
capability at 101000s waveform, repetition rate:0.01%
The communication network internal to the RTU shall be designed and implemented in such a
way that the passing of data and commands between modules shall not be prevented by the
failure of any module not directly involved in the communication exchange. In addition the
internal network shall not become overloaded under the heaviest traffic possible in the RTU's
ultimate expansion configuration.
The MCC / ACC shall initiate communications with a selected RTU by IP addressing
function. Each RTU shall recognize its own unique address and shall have the capability of
being assigned any address within a range of possible addresses. It shall be possible to address
all or selected number of RTUs from the MCC / ACC in order that global or broadcast
message may be sent.
RTU shall have two communication ports for simultaneous communication, one port for
communication with GPRS Modem and the other port for communication with UHF Slave
Radio.
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 82 -
SCADA SYSTEM
The RTU shall support Modbus / DNP 3.00 (TCP/IP) and any other open protocol for
communicating with SCADA system at MCC / ACC. This will be standard Protocol for all
the station communications.
The RTU shall be polled through Ethernet port from MCC/ACC.
The LED indication shall be provided in the RTU to check the health of RTU communication.
6.4.9
RTU Features
(1)
b)
c)
Field input initiated discrete control action. Discrete control action corresponding
to Remote Control Command reception.
d)
Operator initiated discrete control action with check before execute and time out
feature.
e)
f)
g)
h)
i)
j)
k)
Remote configurations of RTU from MCC / ACC through PDT / PC) Compatible
with IP based telecom system
(2)
(3)
The RTUs shall have a self-diagnostic feature and software watchdog timer devices to
monitor & report the healthiness of CPU, memory, power supply, comm. interfaces and
Input / Output modules at the local level. Further the RTUs shall support remote
diagnostics from MCC / ACC / various stations so that all these status shall be
transmitted to MCC / ACC and displayed in the RTU status graphic.
(4)
Analog input card and Analog output card shall be self-calibrating type and event shall
be sent to MCC / ACC for out of calibration. Analog input card shall generate an event,
if it is out of calibration, which shall be sent to MCC / ACC. Further if Analog output
card is not self-calibrating type then all Analog outputs shall be wired back as along
inputs and calculations performed on each channel to detect AO card out of calibration.
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 83 -
SCADA SYSTEM
This provision should be available in the SCADA system; however separate card (AO /
DO) is not required. This out of calibration shall be available as part of RTU status
graphics along with set point value displayed in the graphics, next to the corresponding
controller symbol.
(5)
It shall scan and acquire parameters from process as per programmed scan cycles.
(6)
Threshold value
Type of each I/O modules and time stamping requirements for points in
each module.
The mapping of RTUs data base to the Modbus / DNP3 Protocol address
space Software logic in RTUs
(iii) The configuration file shall be able to be transferred online from MCC / ACC /
various stations using the existing data channels to the corresponding RTU.
d) Time stamping of all exception reports.
However, the SCADA vender has the option to implement the features of Alarm
generation, association of the alarm priority and engineering unit conversion at the
RTU level or SCADA server level.
(7)
- 84 -
SCADA SYSTEM
a)
RTU shall be capable of updating process parameters data and configuration data
in its own built-in memory. Time stamping of all field values at RTU end shall be
required. In the event of failure or break of communication link, the RTU shall
continue to scan all parameters and update its database. RTU shall retain in its
database the complete analog and digital information of the field till it is
completely and correctly read by MCC / ACC / various stations in order to take
care of no loss of data in case of failure of MCC / ACC / various stations. The
RTU shall scan the field and the memory buffer is to be sized to store all the
changing data (i.e. new exception report for the data every poll time) and MCC /
ACC / various stations receive the same without any loss of data and alarms in the
SCADA system to take care of channels SCADA server switchover times.
b)
Further to take care of long term communication outage with MCC/ACC the
RTUs shall be designed to scan the field and store in the memory up to 1000 field's
exception reports during the period of communication outage for retrieval by MCC
subsequently.
c)
The RTU system shall have the facility to attach to each digital event signal a time
tag generated by the RTU local clock to enable the occurrence to be recorded and
transferred with the resolution of 1 ms.
d)
The RTU shall have on-board data logging and shall have provision to extend
duration of this data logging through SD memory card / local storage device of
minimum 32 GB. Internal data storage facility in SD card / local storage device
(capacity should not less than 32GB) shall be such that during GPRS and or UHF
communication and or Service Providers communication backbone failure for at
least 3 days, stored data must be automatically back filled to Server data base once
communication is restored.
e)
The RTU shall support remote on-line configuration, remote down loading, remote
uploading of stored data, and remote on-line data base modifications
(8)
It shall be possible to have highest priority of alarms, in order for the same to be sent to
MCC / ACC. The SCADA vender has the option to implement the feature of association
of the alarm priority at the RTU level or SCADA server level.
(9)
(10) Every control associated with the RTU shall report the status of the point after control
execution. In case the status has not changed within fixed specified time it shall report to
MCC / ACC / various stations for not having executed the control.
(11) RTU shall not generate any false control signal due to power supply on-off conditions.
(12) RTU shall support communication protocol supporting report by exception to prevent
unnecessary data communication when the data is not changing. The communication
protocol shall also support an update demand scan of all status data by master stations
regardless of the lack of any change in data.
The reply to an exception scan request for status points shall consist of an indication of
the presence or absence of a change of the status indication points in the RTU. A master
station will then request the input of the changed points. The RTU shall continue to
indicate exception changes until the master station acknowledges successful receipt of
the changed data. The RTU shall report the current state of all status indication points to
the master station in response to an update scan even if data has not changed.
(13) It shall provide error detection and control feature for data communication with MCC /
ACC to ensure data integrity.
(14) The RTU design shall facilitate isolation and correction of all failures. The features
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 85 -
SCADA SYSTEM
Self-diagnostic capabilities within each RTU, which can be initiated at the RTU
site.
b)
On-line error detection capabilities within the RTU and detailed reporting to the
connected master stations of detected errors.
c)
(15) It shall have feature of connecting a pluggable Programmable Diagnostic Test unit
(PDT) with keyboard & monitors diagnostic and programming aid to trouble shoot and
configuration tool for RTU and I/O boards. It shall be possible to exercise all the
functions of the RTU without disconnecting the RTU from process.
(16) RTU shall have provision for applying filtering on the input signals and scaling for
engineering units conversion.
(17) From MCC / ACC it shall be possible to off-scan complete RTU individually in addition
to off-scan RTU points. In case of failure of complete RTU or off-scan of complete
RTU only one alarm shall be generated and the RTU along & digital points shown in
various graphics and printed in reports shall correspondingly have data integrity
qualifier flag.
(18) The RTU shall be able to store the configuration data and the process database upon
power failure for at least one month. Upon restoration on the power, RTU shall resume
the normal operation automatically.
(19) The failed RTU once put online shall initiate service requirement to MCC/ACC for
initialization.
(20) RTU shall operate power supply (230 VAC or 24 V DC as define elsewhere) as per
power availability at site. Separate on/off power supply switch and fuse shall be
supplied with each RTU. SCADA Vendor shall indicate power consumption for all the
RTUs. Adequate isolation of input, output and power supply circuits shall be provided
along with over voltage and short circuit protection.
(21) Wherever 230V AC supply is provided for RTU, SCADA vendor shall carry out
necessary conversion to covert the AC voltages to 24V DC for supply to field
instrumentations and to RTU. The power to the field instrumentations is to be provided
through barriers and all the digital output has to be driven through 3-5 A interposing
relays. The necessary converter to covert the AC voltages to 24V DC, the barriers and
the imposing relays shall form the integral part of the RTU.
(22) Over voltage and under voltage protection shall be provided within the RTU power
supply to prevent the RTU internal logic from being damaged as a result of a component
failure in the power supply and to prevent the RTU internal logic from becoming
unstable and causing mal-operation as a result of voltage fluctuations.
(23) Terminations for connections of power supply should be of standard industrial type.
(24) All the field instrument connections for RTUs shall be terminated in the TIP (Telemetry
interface panel). The I/O point wires shall not be directly terminated on the RTU I/O
boards. Terminal blocks / panels are to be provided in the RTU cabinet. I/O termination
blocks shall have both male and female portions so that to isolate the field wiring at
RTU level, male / female termination block attached to be field wiring can be pulled out
instead of removing the wiring. Printed tube type Cross ferruling shall be done.
(25) The electronics in the RTU cabinet shall consist of plug-in PCB's or units with Gold
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 86 -
SCADA SYSTEM
plated edge connectors that utilize a wiping action for connection for PCB's to the back
frame wiring. SCADA Vender shall detail the shelf and inter-shelf wiring and the
termination of the wiring harness between the RTU and the terminal block area. Easy
access cabinet wiring, for maintenance purposes is essential. The PCBs and RTU
components shall be designed for high temp rating and low power consumption so that
air exchange with the ambient environment will not be required.
(26) The RTU shall be Immune to radio frequency interference generated by any nearby
source meeting the latest international standards in this regard (MIL, VDE etc.)
(27) The RTU equipment shall function continuously without requiring any preventive
maintenance.
(28) RTUs shall be multidropped on a pair of communication channels. Upon failure of
primary channels, RTU shall respond to MCC / ACC requests / interrogation on
secondary channel automatically without any loss of data & operation. System shall
provide status on the availability of each of the channels.
(29) It shall be possible to output any AI (Including serial data from IEDs) & DI point value
available in real time database at MCC / ACC, as AO (Including serial data from IEDs)
& DO to any RTU respectively. The relay contact configuration shall be provided up to
the RTU terminal block. The DO command contact closure duration shall be
configurable. It shall be possible to configure DO contact duration open or close for a
long duration as per the DI status. This provision should be available in the SCADA
system; however separate card (AO / DO) is not required.
(30) Within the scope of this document, SCADA vender shall down load Gas
Chromatograph value to those Flow Computers, in whose locations Gas Chromatograph
is not available, through the same serial link which is used for reading the Flow
Computer values. Source Gas Chromatograph and target Flow Computers will be
finalized during detail engineering.
(31) Non availability of any one of the two communication channels should not hamper the
functioning of the other RTUs multidropped on the pair of channels.
(32) RTU vender to ensure that the open/close status of valves (open state first wired and
thereafter close state) be wired consecutively in the RTUs.
(33) Interlocking Logic
The means to minimize the risk of incorrect operation or incorrect sequence of
operations can be included within the RTU as a logical interlocking function.
All the data shall be available in the engineering units in the RTU database. The RTU
vendor has the option to implement the feature of engineering unit conversion at the
RTU level.
(34) RTU Vendor shall detail the shelf and inter-shelf wiring and the termination of the
wiring harness between the RTU, the terminal block area and the field instrumentation.
Easy access to cabinet wiring, for maintenance purposes is essential. The RTU
components shall be designed for high temperature rating and low power consumption
so that air exchange with the ambient environment will not be required.
(35) Identification labels for RTUs, RTU card files, power distribution boards, terminations
etc. complete in all respects properly correlating with the drawings is to be ensured by
the RTU vendor.
(36) Scan Rates
- 87 -
SCADA SYSTEM
The local scan rate for the individual I/O modules shall be such that the time-tagging
resolution and system performance requirements are achieved.
Vendor to provide minimum & maximum SCAN time.
The consideration of scan times shall include the acquisition of data, processing and
updating of the RTU database. The overall RTU local scan shall be defined as the time
required to acquire field data and update the RTU database and the same shall be much
faster than RTU poll time by MCC / ACC. It is expected that scan rate shall not exceed
100 msec for direct I/Os
(37) Digital Output (Contact) Subsystem
The contact output subsystem shall provide momentary closure of potential free contact
relay output for the operation of valves. The subsystem shall fully support the
functional requirement of control
The relay contact configuration shall be provided up to the RTU terminal block.
The DO command contact closure duration shall be configurable. It shall be possible to
configure DO contact duration open or close for a long duration and all contacts shall
be voltage free.
It shall not be possible for the RTU to energize an output that has not been selected for
control.
A RTU restart, following an RTU power failure, shall not reset the output circuits, shall
not generate false control signal and shall cancel any pending control selection.
Set point controls:
All analog output control functions shall utilize the select-check-operate control
sequence associated with set point control.
(38) Each I/O shall be protected against the reverse polarity of the power voltage to I/O.
(39) Serial Link Requirement
a) The RTU shall be equipped with the RS 232 ports & RS 485 ports for polling the
IEDs as specified in the document elsewhere. Additionally one more RS 232C or
TCP/IP port shall be provided for connecting PDT for configuration of the RTU.
b) RTU vendor shall develop, configure and establish the communication for reading /
writing of data from / to the flow computers / CP Panel / Gas Chromatograph or other
IEDs. RTU vendor to configure RTUs for writing of GC data installed in one terminal
(and connected one RTU) to flow-computers kept at other terminal (and connected to
a different RTU) along the same pipeline. The client shall furnish to RTU vendor the
make & model no., protocol details of these devices during detailed engineering or
prior to FAT. RTU vendor shall simulate the above devices using protocol analyzers /
PC / other means to demonstrate during FAT.
c) RTU vendor shall provide all the software tools and programs (source code) used to
interface RTUs with Flow computer / PLCs / any other device. It shall be possible for
client to integrate other device with the RTU in future. To achieve the same the RTUs
shall have provision for integrating device and all necessary software, compilers,
tools etc. shall be supplied by the SCADA vendor. The alarms for power supply /
serial link failure / flow computer & other device malfunction through serial link shall
be implemented. The integration of devices (of any protocol not just modbus) with
the RTUs shall be totally end user configurable.
- 88 -
SCADA SYSTEM
d) The alarms for power supply / serial link failure / flow computer, CP panel & gas
chromatograph malfunction through serial link shall be implemented.
e) The RTU memory sizing shall be adequate for required nos. (as application) of flow
computers / gas chromatographs serially connected with the RTU.
f) The Flow computer / Gas Chromatograph data shall be scanned by the RTU much
faster than RTU poll time by MCC / ACC.
g) All the RTU shall be user programmable for interfacing with any kind of device FC /
GC / CP panel / Solar panel / UPS panel / PLC etc.
(40) Input / Output Points and serial ports for polling:
The RTU vendor shall supply the RTUs equipped with I/O cards, IP port & serial ports
as per the I/O count and serial ports requirement define elsewhere. The RTUs shall be
user programmable for interfacings with any kind of IED.
(41) Portable RTU Configuration and Diagnostic Test Unit
RTU shall have feature of connecting a pluggable Programmable configuration and
maintenance terminal along with all hardware and software necessary to interface to the
RTU. This unit will function as a diagnostic and programming aid to trouble shoot and
configure RTU and input / output boards. It shall be possible to exercise all the
functions of RTU's without disconnecting the RTU from process. This unit shall be a
note book PC with proper enclosure with key board and VDU. It shall operate on
integral rechargeable battery which shall be able to supply power for a minimum of 12
hours before recharge.
The PDT along with Servers at MCC to be installed with licensed RTU configurator
software along with all the cables & connectors required for configuration of RTU.
Also any additional software required for programming RTUs for dialup operation /
making logics etc. needs to be provided by the vendor.
The PDT as diagnostic aid to RTU shall be a notebook (laptop) with proper enclosure
and shall operate on integral battery which shall be rechargeable type. The battery shall
be able to supply power as a minimum for 3 hours before requiring recharging
operation. Also the PDT shall operate on 230 V AC power supply. Vendor shall
provide all the necessary converter / adaptor along with PDT.
The PDT shall consist of following as minimum.
a) Processor shall be Intel Quad Core or latest, clock speed- min. 2.93 GHz
b) 8 GB RAM expandable upto 16 GB
c) 17 color LCD monitor.
d)
- 89 -
SCADA SYSTEM
- 90 -
SCADA SYSTEM
A document pocket shall be provided in each cabinet for storage of documentation. The
configuration of all enclosures, electronic chassis, modules and cabling shall permit ease of
access to all serviceable equipment. Test equipment connections shall be adequately labeled
and shall be readily accessible without the need to remove any board or portion of the
equipment or power supply. All cabling, fastenings, fittings, screw heads, nuts and bolts shall
be International Standard sizes suitable for prolonged use .The equipment and all modules
therein shall be clearly labeled in English for ease of recognition without module removal.
Power cables shall enter the bottom of the cabinets via suitable termination assembles and
internal power distribution wiring shall be installed in separate conduits. Signal cables shall
enter though the bottom of the cabinets via suitable termination assemblies. No opening other
than cable entry points through glands shall be provided at bottom of cabinet.
The exposed surfaces of equipment enclosures shall exhibit a uniform finish and appearance.
The colour and finish texture of the equipment enclosures shall be subject to approval. All
metal parts shall be treated to prevent corrosion. Painted surfaces shall be cleaned, primed and
undercoated prior to painting to ensure a wear resistant finish. A preparatory powder coating
process is preferred.
For adequate light inside the cabinet tube shall be provided which shall operate on 24 V DC.
Exhaust fans shall be provided to remove heat and provide ventilation and these shall operate
on 24V DC.
6.4.11 Insulation and Isolation Requirements
The RTU, including all Status inputs, control outputs analog inputs, power supply inputs and
Communications inputs/outputs shall meet the following insulation and isolation levels
specified in IEC 255.
Insulation: The RTU shall be designed to withstand a Power withstand test voltage of 1.5 KV
rms and shall conform to IEC 255-5 test standards.
Isolation: The RTU shall have an isolation resistance of more than 5 Megohms. It shall also
pass an impulse withstand test of 5 kV and shall conform to IEC 255-4 test standards.
High Frequency Disturbance: The RTU shall be designed to pass a high frequency
disturbance test to a 5 kV impulse test voltage and shall conform to IEC 255 test standards.
6.4.12 Labelling
The bidder shall supply and install labels to identify all equipment in accordance with the
equipment identification on the Drawings finalized during detail engineering. Each site
cabinet shall have a site name label mounted on the door.
All labels shall be manufactured from SS or similar material with black lettering engraved on
a white background and secured using rivets. All engraved letters on labels shall be in block
capitals, with black letters on white background. RTU card files, power distribution boards,
terminations etc. complete in all respects properly correlating with drawings is to be ensured
by the vendor.
6.4.13 Terminations and Input / Output Wiring
The Vendor shall ensure clear and adequate segregation between terminals and cables in the
Following categories:
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 91 -
SCADA SYSTEM
Analog
Digital
Intrinsically Safe
Vendor shall supply, terminate, test all required cables, ferrules, cable glands from telemetry
interface cabinet to RTU at all the stations (vendor to carryout termination of cables at both
ends).
Terminal protection is to be provided as required by statutory regulations. The RTU shall
contain Terminal facilities for connection of field wiring. The terminations shall provide a
means of circuit isolation and test access without the need for disconnection of wires.
Captive screw and saddle compression connections made from parts that are suitably treated
to resist corrosion shall be used. The terminations shall be segregated according to signal
type. Each terminal shall be clearly marked using a permanent marker to provide for its
unique identification.
I/O board termination assemblies shall be of the plug-in variety using a suitable modular plug
and socket arrangement. It shall be possible to remove and replace a faulty board without the
need to individually unmake and remake each circuit connection. Ribbon cable connectors
shall not be used at the I/O termination boards.
The equipment shall make extensive use of plug in modules. Input and output modules shall
be capable of being removed from or inserted into a fully powered and operational rack
without risk of damage. Failure and subsequent replacement of an input or output module
shall not affect other modules or cause a system failure.
Modules shall be arranged so that they may be removed without unsoldering or unscrewing
wires or breaking any other kind of permanent fastening. The hardware shall be modular in
construction and replacements and adjustments can be made as far as possible with the system
on-line. The bidder shall deploy means to ensure that the wrong cards cannot be put into card
frame slots.
Sufficient space for terminations shall be provided within the enclosure to support the
maximum possible required capacity and future capacity as nominated elsewhere in the bid.
A single point earth shall be provided in the RTU in the form of a bolt compression type earth
lug capable of accommodating a standard stranded earthing cable. Wiring within the
enclosure shall be protected from wear and tear, against accidental cuts, and from contact with
enclosure parts or surfaces. The design, wiring and layout of the RTU enclosures shall be
subject to review and approval. No more than two wires to be connected to one terminals and
only wire to be connected to each side of the terminal block, except for terminal jumpers,
provided they are crimped together by the same cable lug or wire pin.
6.4.14 I/O Connections
The bidder shall include schematic diagrams showing proposed connection arrangements at
the I/O modules for analog input signals, MODBUS / digital input, voltage-free contacts and
digital output circuits (both DO and AO). Module power supply and communication
connections shall also be shown.
- 92 -
SCADA SYSTEM
b)
c)
d)
e)
Real-time clock to maintain calendar and time, and perform RTU timing functions.
f)
g)
During initialization, memory self-diagnostics shall occur and then initialize the system
hardware and various I/O devices.
h)
i)
j)
k)
Interrupt controller and interrupt servicing procedure shall prioritize and process
hardware interrupts as they occur.
l)
Debugging tools shall allow users, via a PC, to monitor functions, examine memory,
perform communication port loop back tests, adjust modem communication port settings,
check CPU usage, and process profiling.
m) All software shall be implemented according to established design and coding standards.
Purchaser reserves the right to reject any software that does not conform to these
standards. Complete and comprehensive documentation shall be provided for all
software. The software and the database shall be sized to accommodate growth within the
sizing parameters defined for the RTU without requiring software or database
regeneration. The design of the software and the database shall not restrict future
expansion beyond the sizing parameters. Expansion beyond the original design
parameters may require software or database regeneration.
At the time the RTU is accepted, all software delivered must be up to date and in final
form, including all standard software changes and field changes initiated by the
Contractor or the Contractor's suppliers prior to acceptance. The software documentation
must reflect these changes.
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 93 -
SCADA SYSTEM
n)
The Contractor shall use a non-proprietary operating system capable of managing the
distributed applications of the RTU. The operating system shall support multi-tasking
and multi-programming. The minimum real-time facilities to be provided shall include
process, job, database, and memory management, process synchronizing message
services for communication between jobs, and device and interrupt handling.
o)
Software shall provide automatic restart of the RTU upon power restoration, memory
party errors, hardware failures, and upon manual request. The software shall initialize the
RTU and begin execution of the RTU functions without intervention by master station.
All restarts shall be reported to the connected master stations.
p)
Software shall be provided to continuously monitor operation of the RTU and report
RTU hardware errors to the connected master stations. The software shall check for
memory, processor, and input / output errors and failures.
q)
The Contractor shall supply diagnostic software, which monitors and individually tests
each of the components of the RTU demonstrating all the capability of RTU as
mentioned in this section. The diagnostics shall provide comprehensive user interaction
and printout capabilities.
r)
The RTU shall support remote firmware upgrade over low bandwidth wireless networks
The following types of power supply will be applied for RTUs. Applicable power
supplies are referred to in the RTU List (Appendix-3).
a)
b)
c)
(2)
All RTUs shall be provided with battery backup systems to supply emergency loads
(RTU and radio equipment for communication network) for a period of 24 hours under
the condition of loss of AC commercial power.
(3)
Detailed specifications for RTU electric power are indicated in Section 9 "Electrical
Works Requirements".
(4)
Contractor shall convert to suitable power supply source (redundant) as required for
their system from above available supplies level.
(5)
(6)
(7)
A provision for display and monitoring of input and output voltages with the help of
onboard LEDs and test points respectively.
(8)
(9)
- 94 -
SCADA SYSTEM
(1)
The Bangladesh climate during the season of high humidity and high ambient
temperature can result in condensation occurring within the RTU. To mitigate this,
condensation prevention shall be provided in the RTU.
(2)
For the solar powered RTU, condensation prevention may be ignored due to power
supply condition.
RTUs installed at orifice metering site and turbine metering site shall calculate the gas
volume flow with the use of formula certified by the AGA gas report No.3 and No. 7
respectively.
(2)
The following parameters as a minimum for gas volume calculation can be inputted at
MCC/ACC and the display mounted on the RTU.
a)
b)
c)
Specific gravity
d)
Bas pressure
e)
Base Temperature
f)
Mol% of C0 2
g)
Mol% of Nitrogen
h)
Bas Compressibility
(2)
The RTU shall have sufficient interface functionality to communicate with Tullow's
PLC.
CODE
SITE
10-ASH-400
Ashuganj
- 95 -
SCADA SYSTEM
SL. NO.
CODE
SITE
20-BKB-101
Kutombopur
20-FAU-100
Faujdarhat
20-MJR-401
Barakubundu TBS
30-PBG-401
30-PBG-402
40-ELE-500
Elenga
40-MHD-500
Monohordi
At each RTU to be installed in the Site, a database storage facility shall be provided to
store all acquired data from field, control tuning data and other historical operating data
of every 30 minutes as a minimum, for a period of 15 days.
(2)
The database of the RTU shall be configured according to the master database to be
provided for the MCC and the ACC to enable recovery of missing data at the master
database in the event of communication failure between the RTUs and the MCC and the
ACC.
The Contractor shall provide four laptop computers suitable for the programming and
interrogation of RTUs. These shall be capable of preparing and modifying sequence
programs, editing RTU point and alarm configuration and displaying / retrieving
historical data and current data from RTU.
(2)
The RTU maintenance terminal shall be suitable for use in the environmental conditions
of temperature and humidity specified in the general equipment requirements for
outdoor Bangladesh. However, RTU environmental specification shall meet operating in
ambient temperature of (-)20 to +70 degC and RH of 5 to 95% (non-condensing) at 40
degC.
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 96 -
SCADA SYSTEM
7.
COMMUNICATION SYSTEM
7.1
7.1.1
General
(1)
The overall Communication System shall consist of data acquisition network from
RTUs to SCADA Server for archiving, reporting and control actions using the backbone
network of the service provider.
(2)
The communication system for SCADA network shall consist of two separate
communication system,as stated below:
a.
GPRS link
b.
Telemetry link
(3)
GPRS link:All RTU sites shall have GPRS Radio Modem which will be connected to
RTUs. The RTUs shall send the data from process instruments to SCADA Server
through Service Providers network. The transmission of data from service provider to
SCADA Servers at MCC and ACC shall be over a high bandwidth high speed network,
taken under lease from other OFC Serviced Provider. Also any control or supervisory
actions required at RTU end shall be sent to the corresponding RTU through GPRS
network of the Service Provider.
(4)
Telemetry link: RTUs will be connected to slave telemetry radios which will transmit
the data to master telemetry radio, located at MTS. The master telemetry radio will be
connected to L3/L2 Ethernet switch which in turn will send the data to MCC and ACC
through access link. The access link shall be established by using unlicensed IP
Microwave radio from MTS to Service Providers AP. The leased E l circuits from the
provider's network and an IP radio link shall form the secondary SCADA backbone to
connect the MTS and MCC/ACC so that in the event of failure of the primary backbone,
the secondary communication backbone shall deliver the critical data from those sites to
MCC and ACC
(5)
Link from MSC of service provider to MCC & ACC: A leased bandwidths of optical
fiber operator/provider shall be used. Contractor shall be responsible to build up OFC
connectivity from Switching Center of service provider (2 no of service provider) to
nearest access point of the OFC network of the third party. Again contractor shall
establish connectivity from MCC and ACC to nearest AP of OFC network of third
party.
(6)
Provision of OFC connectivity as a backup measure between the AP and the 10 (ten)
MTS shall be established. Depending on the distance of APs of Service Providers and
availability of OFC, some sites will be selected for OFC connectivity between AP and
MTS. As per the records available at present regarding availability of OFC, Elenga,
Ashuganj, Demra MTS shall be connected to MCC over leased OFC network.
In normal mode, these three MTS shall use the OFC link as the main communication
system with IP Radio , kept as the stand by for access network up to AP. However, in
the event of non-availability of the OFC link, IP Radio based access link shall be
established between MTS and AP of the service provider.
- 97 -
COMMUNICATION SYSTEM
Sl.
No.
(7)
The MCC and ACC shall be connected through a high speed leased bandwidth 1+1
redundant OFC link of a suitable Service Provider. The activities needed for extension
of the signals shall be conducted by the Contractor. The Contractor shall be responsible
for supply and commissioning of all necessary items like OFC, Router/STM-1,patch
panel etc.
(8)
The Server at MCC shall be configured as Primary and all data collected through GPRS
Radio modem and through telemetry radio link as a back up method will be fed to
Server at MCC. The Server at MCC shall transfer the data to Server at ACC, configured
as Secondary through 1+1 redundant OFC link between two locations. In the event of
failure of Primary Server, the data received at the router of MCC shall be routed to
Secondary Server at ACC through OFC network. Once the Server at MCC is
operational, the data traffic again will be routed to the Primary Server at MCC.
(9)
The location of the Master Telemetry sites / GTCL Access Sites and corresponding
providers access point (BTCL) are as follows :
MTS Location
MTS Location
Latitude
MTS Location
Longitude
Nearest BTCL
Location
BTCL
Location
Latitude
BTCL
Location
Longitude
Distance
MTS to
BTCL
AP (Km)
01
Jalalabad
(JGTDSL) H.O
N245300.8
E915304.9
Kazitola
N245213.1
E915245.9
02
Kailastilla
N235958
E910639
Golapgonj
N245055.2
E920415.8
03
Fenchuganj
N245055.2
E920415.8
Fenchugonj
N244158.6
E915616.8
2.31
04
Rashidpur
N244158.6
E915616.8
Hobigonj
N242259.9
E91250.0
21
05
Monohardihi
N242259.9
E91250.0
Monohordi
N24330.2
E90429.9
06
Mirasarai
N224215.8
E913646.6
Mirasarai Ex
N224736.4
E913352.6
10.27
N233819.4
E905615.5
Nandan Kanon,
N222021.4
E915003.51
N235958
E910639
12
07
Faujdarhat
Chittagong
08
Ashuganj
N232710.3
E910955
09
Elenga
N231416.8
E910741.7
Tangail
N241410.8
E89542.9
12
10
Bakhrabad
N24330.2
E90429.9
Murad Nagar
N233819.4
E905615.5
11
Demra
N234258.3
E902949.4
Demra
N234258.3
E902949.4
0.5
Brammonbaria
(10) The above MTS locations with the distribution of RTUs in those locations are
mentioned below.
SL. NO.
1.
QTY (NO.)
2
2.
Kailastilla
3.
Fenchuganj
4.
Rashidpur
- 98 -
COMMUNICATION SYSTEM
5.
Monohardihi
10
6.
Mirasarai
7.
Faujdarhat
8.
Ashuganj
13
9.
Elenga
10.
Bakhrabad
11.
Demra
15
TOTAL
74
(11) The above communication system shall operate in addition to GPRS network for such
selected MTS locations.
(12) The Communication System shall use IP / Ethemet signal transmission system and has
enough capacity for data transmission increase in future.
(13) The data from Ashuganj MTS will be transmitted to Server at MCC through leased
bandwidth 1+1 OFC link, provided by Third Party Optical Service Provider. However,
the activities needed for extension of the signals through series of stages shall be
conducted by the Contractor. The Contractor shall be responsible for supply and
commissioning of all necessary items like OFC, Router/STM-1,patch panel etc.
(14) The data from Demra MTS and Elenga MTS shall be transmitted to Server at MCC
through leased bandwidth OFC link, provided by Third Party Optical Service Provider.
However, the activities needed for extension of the signals through series of stages shall
be conducted by the Contractor. The Contractor shall be responsible for supply and
commissioning of all necessary items like OFC, Router/STM-1,patch panel etc.
(15) The data of Bakhrabad MTS shall be transmitted to Demra through specified cores in a
multicore OFC cable, laid between Demra and Bakhrabad by GTCL already under a
separate project. However, the activities needed for extension of the signals through
series of stages shall be conducted by the Contractor. The Contractor shall be
responsible for supply and commissioning of all necessary items like, Router/STM1,patch panel, pigtails and interconnecting cables etc.at both ends. The data from
Bakhrabad after being received at Demra will be sent to Server at MCC through OFC
link between Demra and MCC at Dhaka, as stated in above paragraph.
(16) The Contractor shall establish OFC link by supplying and commissioning of
Router/STM-1, OFC cable and accessories from MCC Agargaon to the nearest Access
Point of Third Party Optical Fiber Network
(17) The Contractor shall establish OFC link by supplying and commissioning of
Router/STM-1, OFC cable and accessories from the Switching Centers of the Service
Providers (minimum two) to the respective Access Points of Third Party Optical Fiber
Network to build the connectivity with MCC and ACC.
(18) The Contractor shall establish OFC link by supplying and commissioning of
Router/STM-1, OFC cable and accessories from ACC Ashuganj including MTS, Demra
MTS, Elenga MTS to the respective Access Points of Third Party Optical Fiber
Network
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 99 -
COMMUNICATION SYSTEM
(19) The Communication System is a closed network, however some part of the network will
be connected to WAN. Therefore security measures shall be required at the interface
points.
(20) The Contractor shall be responsible for the following aspects for Communication
System design:
a)
Network design
b)
c)
d)
(21) The contract for the lease of El circuits from service provider's network shall be made
between GTCL and the provider (BTCL is recommended). The Contractor shall be
responsible to provide GTCL with technical assistance for their Contract agreement as
well as necessary coordination during implementation of the Works. The Contractor
shall also be responsible for arrangement of the leased contract service with the GPRS
and OFC service providers
(22) The configuration of leased El circuits is illustrated in Figure 7.1.
7.1.2
System Configuration
2 No.STM-1 (1+0) Optical Transceiver / Router with accessories with single mode OFC
cable
(2)
(3)
(4)
(5)
(6)
1 No.STM-1 (1+0) Optical Transceiver / Router with accessories with single mode OFC
cable
(2)
(3)
- 100 -
COMMUNICATION SYSTEM
1 No.STM-1 (1+0) Optical Transceiver / Router with accessories with single mode OFC
cable
(2)
(3)
2 No.STM-1 (1+0) Optical Transceiver / Router with accessories with single mode OFC
cable
(2)
(3)
(4)
(5)
(6)
(2)
1 No. Master Telemetry Radio equipment with antenna and lightning protection
(3) 1 No.STM-1 (1+0) Optical Transceiver / Router and accessories with single mode OFC
cable
(4) 2 No. L3/L2 Ethernet Switch
(5)
(6)
(7)
(8)
The process signals received in Master UHF Radio at MTS from its surrounding RTUs
will be connected to L3/L2 switch. The RTUs at MTS location will also be connected to
same L3/L2 switch through direct cabling. The L3/L2 switch in turn will be connected
to STM-1 or Router / IP Radio for transmission of data through access link to MCC and
ACC.
- 101 -
COMMUNICATION SYSTEM
(6)
1 No. Slave Telemetry Radio Equipment with antenna and lightning protection
b)
c)
(2)
The slave telemetry radio equipment shall be installed inside of the RTU enclosure. 72
RTUs shall be equipped with the slave telemetry radio equipment, as shown in the RTU
list. Slave telemetry radio shall be connected to the second communication port of the
RTU.
(3)
Existing antenna masts at STS sites shall be used for new STS telemetry radios. In the
event of any antenna mast being not usable, new antenna mast of adequate height as per
the Radio Survey to establish reliable radio link to MTS telemetry master radio shall be
installed. New antenna masts shall be provided at Additional/Future Sites as shown in
the said RTU list. However, all antenna masts shall be provided with lightning
protection device.
(4)
For location at Bibiyana, new self supported antenna tower of 40 meter height from the
ground level shall be erected. The Master Telemetry Radio with 5 watt transmitter
power shall be provided at Bibiyana to establish reliable communication link with
Rashidpur MTS.A RTU Room (5 meterx5meterx3.5meter) shall be constructed at
Bibiyana site to house RTU and MTS radio and battery etc. In addition, GPRS Radio
modem shall be used with RTU at Bibiyana.
A Communication System shall be installed for the following ten (10) Operating
Company Terminals.
- 102 -
COMMUNICATION SYSTEM
SL.
NO.
(2)
CODE
SITE
20-CML-100T
10-ASH-204T
10-HOR-300T
30-PBG-500T
10-JAL-600T
30-PBG-700T
20-FAU-701T
20-FAU-702T
30-PBG-701T
10
30-DMR-401T
b)
Communication link between GTCL SCADA System and Operating Company Terminal at
ten (10) locations of franchisees shall be established through web server of GTCL SCADA
Server. The specified clients of ten (10) OCTs shall be defined in the SCADA Server at MCC
and ACC and access to SCADA system shall be allowed for such clients through internet..
7.1.2.10Chevron's Server at Chevron Head Office
(1)
(2)
(3)
Communication link between SCADA Server and Chevron Server shall be through web
server at MCC and ACC and WAN to collect given set of process data from Chevron system
and monitoring of the same at specified clients at GTCL SCADA system.
7.1.2.11GTCL ERP System
(1)
(2)
(3)
Communication link between GTCL ERP Server at Dhaka and GTCL SCADA Server shall
be through necessary Gateway / Protocol Converter and over the GTCL LAN system only.
L3/L2 Ethernet switch shall be connected to GTCL ERP LAN network.
- 103 -
COMMUNICATION SYSTEM
(2)
(3)
(4)
(5)
(6)
Selected set of signals from the Controller of Compressor system shall be extended from the
communication port of the Controller, earmarked for such purpose and connected to the RTU
which will direct the process signals to GPRS Radio Modem and slave telemetry radio set
through the L3/L2 Ethernet switch . The signals shall be available at MCC and ACC Server
through access network.
7.1.2.13 GTCL Compressor System at Elenga and Ashuganj
(1)
(4)
Selected set of signals from the Controller of Compressor system shall be extended from the
communication port of the Controller, earmarked for such purpose. The communication port
of the Controller of Compressor system shall be connected to the Gateway/Protocol Converter
for conversion of the SCADA protocol of GTCL Compressor System to that of GTCL
SCADA System. The output of the Gateway/Protocol Converter shall be connected to the
RTU. The RTU shall be connected to L3/L2 Ethernet switch thorough direct cable. The L3/L2
Ethernet switch in turn will be connected to STM-1 or Router/IP Radio for transmission of the
signals to MCC and ACC through Service Providers network.
7.1.2.14 Western Zone SCADA System at Elenga
(1)
Gateway/Protocol Converter
(2)
(3)
Communication link between Western Zone SCADA Server at Elenga and GTCL SCADA
Server at MCC and ACC shall be through necessary Gateway / Protocol Converter. The
communication port of the Western Zone SCADA Server shall be connected to the Gateway /
Protocol Converter for conversion of the SCADA protocol of Western Zone SCADA system
to that of GTCL SCADA System. The output of the Gateway / Protocol Converter shall be
connected to L3/L2 Ethernet switch. The L3/L2 Ethernet switch shall be connected to STM1/IP Radio at Elenga for transmission to MCC and ACC.
7.1.2.15 Bakhrabad-Siddhirganj SCADA System
(1)
- 104 -
COMMUNICATION SYSTEM
(2)
(3)
(2)
(3)
(6)
Selected set of signals from the Allen Bradley PLC based Control System of Bangura Gas
Field system shall be extended form the communication port of the Controller, earmarked for
such purpose and connected to the RTU through L3/L2 Ethernet switch.Signals from the RTU
shall be available at MCC and ACC Server through GPRS Radio Modem and slave telemetry
radio link.
7.2
IP Radio (1+1) with power conversion unit (DC-DC Converter), antenna, low loss
RF Coaxial cable and connector, programming & diagnostic software with all
accessories.
b)
UHF Telemetry Slave Radio (1+0) with power conversion unit (DC-DC
Converter), antenna, RF Low Loss Coaxial cable and connector programming &
diagnostic software with all accessories.
c)
UHF Telemetry Master Radio (1+1) with power conversion unit (DC-DC
Converter), antenna, RF Low Loss Coaxial cable and connector programming &
diagnostic software with all accessories.
d)
GPRS Radio modem with power conversion unit (DC-DC Converter) ,connecting
cord, RS232 serial cable, Antenna.
e)
Router/L2 Ethernet Switch and any other interface equipment with all connectors,
cables and accessories.
f)
Gateway / Protocol Converter with power conversion unit (DC-DC Converter) and
- 105 -
COMMUNICATION SYSTEM
h)
i)
j)
k)
l)
Multi Strand Copper wire for grounding All types of Interconnecting cables
o)
p)
q)
r)
s)
t)
u)
v)
Power Distribution Board fitted with protection device and other accessories
complete as per detailed technical specification in the tender document
w) Antenna masts at STS telemetry radio sites shall be reused. In the event of any
mast, found not usable, new MS pole duly grounded with RCC of adequate height
as per radio survey for such UHF Telemetry Slave Radio site shall be installed.
Especially for Bibiyana site, Self supported antenna tower of 40 meter height from
ground level shall be erected. Master Telemetry Radio shall be used at Bibiyana
site to establish reliable communication link with Rashidpur MTS.
x)
y)
z)
Firewall between SCADA Server and other systems with all necessary features
aa) Laboratory, testing and measuring instruments for UHF radios, IP Radios, STM-1,
Router,IP-E1 Converter, Ethernet switches etc
bb) Any other items which are not explicitly stated but required for proper functioning
of the equipment offered
7.3
Contractor will, during the time of detail engineering and installation of the quoted
system, interact and coordinate with any other agency regarding collection / retrieval of
inputs / information / data and all such interfacing works with other systems, as
described in other parts of this specification and attached documents shall be under the
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 106 -
COMMUNICATION SYSTEM
scope of this Contractor. If necessary, the Bidder shall contact the Employer before
submission of their quotation.
(2)
7.4
Bidder has to provide the services required for completeness of the system irrespective
of whether it is mentioned in the specification or not.
Contractor shall have their terminal points at the transmitting antenna of GPRS Modem
at RTU site. Subsequent reception of SCADA signals at Mobile Service Providers AP
and further transportation of signals to MCC / ACC shall be under the scope of
Contractor.
(2)
Contractor shall be responsible for supply, install, commission and testing of IP Radio,
Router,Antenna and laying, termination and connecting the RF Coaxial cable to the
equipment, to IP-E1 Converter and terminating the signal form IP-E1 Converter port to
Patch Panel port. Subsequent extension of signals from patch panel to Multiplexer /
Communication equipment shall be under the purview of BTCL / Service Providers.
Final installation, testing, commissioning and acceptance of the IP Radio, its accessories
and interfacing of signals from IP Radio to Multiplexer / STM-1 shall be under the
Contractor. However, the interfacing of two communication system (of the Contractor
and the Service Provider) shall be jointly conducted by Contractor and BTCL / Service
Provider. Supply, installation of the patch panel at AP and providing the termination
details to BTCL / Service Provider shall be the responsibility of the Contractor.
(3)
Final installation, testing, commissioning and acceptance of the STM, Router, OFC
cable, its accessories and interfacing of SCADA signals to the FOTS of Service
Provider at AP location shall be jointly conducted by both Contractor and Service
Provider. Supply, installation of the patch panel at AP and providing the termination
details to Service Provider shall be the responsibility of the Contractor.
(4)
Contractor shall be responsible for supply, install, commission and testing of STM1/Router at MTS location and at AP, laying, termination and connecting the OFC cable
from MTS location to Service Provider, terminating the signal from STM-1 /Router at
AP to the Patch Panel port at AP location. Subsequent extension of signals from patch
panel to STM equipment shall be under the purview of Service Providers. Final
installation, testing, commissioning and acceptance of the STM, Router,OFC cable, its
accessories and interfacing of SCADA signals to the FOTS of Service Provider at AP
location shall be jointly conducted by both Contractor and Service Provider. Supply,
installation of the patch panel at AP and providing the termination details to Service
Provider shall be the responsibility of the Contractor.
(5)
A 1+1 redundant leased bandwidths of optical fiber operator/provider shall be used for
connectivity between MCC & ACC Contractor is responsible to build up OFC
connectivity from MSC of service provider (2 no of service provider) to nearest access
point of the OFC network of the third party. Again contractor shall establish
connectivity from MCC and ACC to nearest AP of OFC network of third party. Final
installation, testing, commissioning and acceptance of the STM, OFC cable, its
accessories and interfacing of SCADA signals shall be jointly conducted by both
Contractor and BTCL / Service Provider.
(6)
Demra SCADA office & WCC Elenga shall be connected to MCC Agargaon, Dhaka
through leased bandwidths of OFC network provider by third party. However contractor
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 107 -
COMMUNICATION SYSTEM
shall establish connectivity using OFC from Demra SCADA office & WCC Elenga to
AP of OFC network of the third party. Final installation, testing, commissioning and
acceptance of the STM, OFC cable, its accessories and interfacing of SCADA signals
shall be jointly conducted by both Contractor and BTCL / Service Provider.
(7)
The tentative distances from different sites to access points of OFC network of third
party are as follows:
a)
b)
c)
d)
e)
f)
Server of Mobile Phone operator to Access point of optical fiber operator: 1 km.
(8)
Contractor shall be responsible for supply, install, interfacing, commission and testing
of SCADA signals from the Service Providers network to SCADA Servers at MCC and
ACC. Testing of the availability and integrity of the signals received at MCC and ACC
shall be jointly conducted by both Contractor and Mobile Service Provider and other
Service Provider. Supply, installation of the patch panel at MCC / ACC and providing
the termination details to Mobile Service Provider shall be the responsibility of the
Contractor.
(9)
(10) Contractor shall be responsible for interfacing, commission and testing of selected
process signals from the Compressor systems at Elenga and Ashuganj to SCADA
Servers at MCC and ACC. Extending the signals from the communication port of the
Controller of the Compressor system to the communication port of the RTU through
any intermediate converter, if required shall be responsibility of the Contractor. Testing
of the availability and integrity of the signals received at MCC and ACC shall be jointly
conducted by both Contractor and Compressor system supplier. Any interfacing
equipment, hardware, software, licence required for integrating signals between
Compressor systems at Elenga and Ashuganj and GTCL SCADA System shall fall
under the scope of this Contractor.
(11) Contractor shall be responsible for interfacing, commission and testing of selected
SCADA signals from the Western Zone Gas Pipeline SCADA system at Elenga to
SCADA Servers at MCC and ACC. Extending the signals from the communication port
of the Controller of the Western Zone Gas Pipeline SCADA system through Gateway /
Protocol Converter ,L3/L2 Ethernet switch, OFC shall be responsibility of the
Contractor. Testing of the availability and integrity of the signals received at MCC and
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 108 -
COMMUNICATION SYSTEM
ACC shall be jointly conducted by both Contractor and Western Zone Gas Pipeline
SCADA system supplier. Any interfacing equipment, hardware, software, licence etc.
required for integrating signals between Western Zone Gas Pipeline SCADA system
and GTCL SCADA System shall fall under the scope of this Contractor.
(12) Contractor shall be responsible for interfacing, commission and testing of selected
SCADA signals from the Bakhrabad-Siddhirganj SCADA System Server at Demra to
SCADA Servers at MCC and ACC through OFC network. Extending the signals from
the communication port of the Controller of the Bakhrabad-Siddhirganj SCADA
System to GTCL SCADA Server through Gateway / Protocol Converter ,L3/L2
Ethernet switch, OFC shall be responsibility of the Contractor. Testing of the
availability and integrity of the signals received at MCC and ACC shall be jointly
conducted by both Contractor and Bakhrabad-Siddhirganj SCADA System supplier.
Any interfacing equipment, hardware, software, licence etc. required for integrating
signals between the Bakhrabad-Siddhirganj SCADA System and GTCL SCADA
System shall fall under the scope of this Contractor.
(13) Contractor shall be responsible for interfacing, commission and testing of selected
process signals from the Bangura Gas Field PLC System at Bakhrabad to SCADA
Servers at MCC and ACC. Extending the signals from the communication port of the
PLC Controller of the Bangura Gas Field system to the communication port of the RTU
and GPRS Modem through any intermediate converter, if required shall be under the
purview of the Contractor. Any interfacing equipment, hardware, software, licence
required for integrating signals between PLC System at Bangura Gas Field and GTCL
SCADA System shall fall under the scope of this Contractor. Testing of the availability
and integrity of the signals received at MCC and ACC shall be jointly conducted by
both Contractor and PLC System supplier.
(14) Contractor shall be responsible for interfacing, commission and testing of selected
SCADA signals from the SCADA system of Moheskhali Anowara pipe line to
SCADA Servers at MCC and ACC. Extending the signals from the communication port
of the Controller of the SCADA system of Moheskhali Anowara pipe line to the
GPRS Radio Modem through Gateway / Protocol Converter through any intermediate
converter, if required shall be responsibility of the Contractor. Testing of the availability
and integrity of the signals received at MCC and ACC shall be jointly conducted by
both Contractor and SCADA system of Moheskhali Anowara pipe line supplier. Any
interfacing equipment, hardware, software, licence etc. required for integrating signals
between SCADA system of Moheskhali Anowara pipe line and GTCL SCADA
System shall fall under the scope of this Contractor.
(15) Contractor shall be responsible for interfacing, commission and testing of GTCL ERP
System Server at Dhaka to SCADA Servers at MCC and ACC. Supply, installation and
commissioning and interfacing of the Protocol Converter for ERP system to SCADA
System shall fall under the scope of the Contractor. Testing of the availability and
integrity of the signals received at ERP Server from SCADA Server at MCC and ACC
shall be jointly conducted by both Contractor and ERP System supplier. Any interfacing
equipment, hardware, software, licence required for integrating signals between the
GTCL ERP System and GTCL SCADA System shall fall under the scope of this
Contractor.
(16) Contractor shall supply, install, test and commission RTUs with GPRS Radio Modem at
Chevron Gas Fields (Moulabi Bazar, Bibiyana and Jalalabad) for collection of data from
three locations at SCADA Server at MCC and ACC.
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 109 -
COMMUNICATION SYSTEM
(17) Contractor shall be responsible for supply, install, commission communication gateway,
other hardware and software etc. and establishing communication link between Chevron
Web-Server at Dhaka to GTCL SCADA System. The specified clients of these SCADA
systems shall be defined in the Chevron Server and access to Chevron system shall be
allowed for such clients. Defining the allowable clients of GTCL SCADA system shall
be the responsibility of supplier of Chevron system. All necessary arrangements and
formalities viz. meetings, visits etc. with concerned agencies regarding interfacing
SCADA system with Chevron system shall be organized by the Employer. Testing of
the availability and integrity of the signals received at SCADA Server from Chevron
Server shall be jointly conducted by both Contractor and Chevron System supplier. Any
interfacing equipment, hardware, software, licence required for integrating signals
between the Chevron System and GTCL SCADA System shall fall under the scope of
this Contractor.
(18) Depending on availability of OFC and nearness of Access Point of Service Providers to
MTS, the STM-1/Router and OFC link shall be used a primary access link with IP
Radio as stand by link. In the event of non-availability of OFC network, the IP Radio
will be used as primary link.
(19) Contractor shall be responsible for supply, install, commission of communication
gateway, Web Server, other hardware and software, licences etc. and establishing
communication link between this GTCL SCADA System and Operating Company
Terminal (OCT) at ten (10) locations of franchisees. The specified clients of these OCTs
shall be defined in the SCADA Server at MCC and ACC, access to SCADA system
shall be allowed for such clients and all such essential activities shall be under the scope
of the Contractor. All necessary arrangements and formalities regarding interfacing
SCADA system with OCT shall be organized by the Employer.
(20) Contractor shall be responsible for arranging and obtaining any license, software,
hardware, converter, protocol converter, gateway and any other item necessary for
interfacing with Server and system of any other external agency. Any item not explicitly
quoted in the tender specification or BOQ but required for proper functioning of the
system and fulfilling the tender requirement shall be under the scope of supply and
commissioning of the Contractor.
7.5
7.5.1
7.5.1.1 The Contractor shall carry out a radio path survey of the proposed communications routes.
This shall be commenced within 2 weeks of the Award of Contract.
7.5.1.2 The radio path survey shall also encompass UHF Telemetry.
7.5.1.3 The Contractor shall prepare a Radio Path Engineering Report which shall include the
proposed Telecommunications System design, supported by detailed design and performance
calculations. Link performance shall be designed to meet the appropriate CCIR and CCITT
recommendations.
7.5.1.4 This report shall be submitted to the Employer for approval prior to commencement of
manufacturing.
7.5.1.5 Link Design Criteria
(a)
The Microwave Radio System, and individual kinks thereof, shall be designed in
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 110 -
COMMUNICATION SYSTEM
accordance with CCIR Report 930 (Performance for Digital Radio Relay systems) and
the appropriate CCIR recommendations for medium grade digital circuits (and those
CCITT Recommendations that they cross reference).
(b)
(c)
Links shall be designed for a pro-data availability figure of 99.7% per annum for a
2500 km hypothetical reference digital path as defined in CCIR Recommendations 5561 (Hypothetical Reference Digital Path for Radio-Relay System) and 557 (Availability
Objectives for Radio-Relay Systems Over a Hypothetical Reference Circuit and a
Hypothetical Reference Digital Path).
(d)
Bit error rates (BER) for receiver thresholds shall be determined against CCIR
Recommendations 594 (Allowable Bit Error Rate at the Output of the Hypothetical
Reference Digital Path).
The Contractor shall submit a Radio Path Engineering Report which shall include, but
not be limited to the following:
(i) Path profiles for each link.
(ii) Link analysis for each of the proposed radio links.
(iii) Frequency Allocation Plan.
(iv) Radio performance details.
(v) Geographic, urban and are traffic impacts.
(vi) Interference on and from other systems.
(b)
7.5.2
IP Radio Equipment
7.5.2.1 The data furnished hereunder are the basic minimum requirements. The Bidder shall carry out
the necessary calculations based on the site data and site survey activities for some parameters
so that functional requirements and specifications in this document are complied with.
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 111 -
COMMUNICATION SYSTEM
7.5.2.2 The IP radio equipment shall be operated with a 5.2/5.7 GHz non-licenses band. The
frequency band shall be selected in accordance with the radio link distance and the required
transmission capacity. However it is preferable that all radio links use the same frequency
band for easy maintenance.
7.5.2.3 The IP radio link shall have 1+1 standby protection.
7.5.2.4 The antenna size (gain) for the radio link shall have suitable size (gain) to keep the radio link
reliability.
7.5.2.5 The IP radio link shall have security measures for protection from serpents.
7.5.2.6 At the BTCL's/Service Providers AP, the media converter (E l to/from IP) shall be installed.
7.5.2.7 For maintenance purposes, an amount of spare equipment shall be supplied to MCC and
ACC. Quantities shall be stated by the Contractor, considering the Equipment MTBF (Mean
Time Between Failure).
7.5.2.8 The IP radio equipment to be installed at MCC / ACC shall be operated with 230V AC, and
the IP radio equipment to be installed at the other stations shall be operated with 24V DC
negative ground. If equipment operated by different voltage is adopted, adequate power
supply adapter shall be supplied.
7.5.2.9 The IP radio consists of IDU (Indoor Unit) and ODU (Outdoor Unit). The primary power for
the ODU shall be supplied through the cable connected between IOU and ODU.
7.5.2.10 The IP radio equipment (IDU) shall be installed in existing radio room.
7.5.2.11 The IP radio equipment shall have the visual indications and terminals for monitoring of the
equipment conditions such as operating / fault etc.
7.5.2.12 The Contractor shall submit the radio path calculation sheets describing following items, but
not be limited to:
a)
b)
Required output power, receiving level, threshold margin, antenna gain, antenna
height
c)
d)
Link reliability
Frequency band
(2)
Output power
25 dBm nominal
(3)
Modulation method
OFDM
(4)
Interface
(5)
Transmission speed
12 Mb/s minimum
(6)
(7)
- 112 -
COMMUNICATION SYSTEM
7.5.3
(8)
Mechanical configuration
ODU+IDU
(9)
Antenna size/gain
(10)
Equipment Protection
IP65
(11)
Operating Temperature
-10 to 65C
(12)
Humidity
(13)
Wind Survival
190 km/hr
7.5.3.1 The data furnished hereunder are the basic minimum requirements. The Bidder shall carry out
the necessary calculations based on the site data and site survey activities for some parameters
so that functional requirements and tender specifications are complied with.
7.5.3.2 The telemetry radio equipment shall be operated in 382-392 MHz band.
7.5.3.3 The master telemetry radio equipment shall have 1+ 1 standby protection.
7.5.3.4 The master/slave telemetry radio equipment shall have IP/Ethernet interface port. Also it shall
have RS 232C port and USB serial port for local programming etc.
7.5.3.5 To reduce the power consumption, the transmitter output power shall be adjusted depending
on the radio link distance.
7.5.3.6 The rise up time for the transmitter of slave telemetry radio equipment shall be as short as
possible for the polling operation method. The contractor shall state the rise up time, and also
state whether the master station transmitter can operates intermittently.
7.5.3.7 As distances of some links between MTS and STS are over 10 km, the Contractor shall select
suitable antenna gain for STS and suitable antenna heights for MTS.
7.5.3.8 The telemetry radio equipment to be installed at MCC/ACC shall be operated with AC 230V
AC. The telemetry radio equipment to be installed at the other stations shall be operated with
24V DC negative ground. If the equipment operated with different voltage is adopted,
adequate power supply adapter shall be supplied.
7.5.3.9 The power consumption of radio equipment shall be as small as possible. The contractor shall
state the power consumption of the base/slave radio equipment.
7.5.3.10The master telemetry radio equipment shall be installed at the existing radio room.
7.5.3.11An antenna mast with lightning protection for the slave telemetry radio equipment as well as
for RTUs shall be provided. The Contractor shall decide its height in accordance with the
radio path calculation.
7.5.3.12The Contractor shall submit the radio path calculation sheet for the locations where the
distances between MTS and STS at RTU sites shall be more than 5Km.
7.5.3.13The calculation sheets shall include the following items, but not be limited to:
a)
- 113 -
COMMUNICATION SYSTEM
b)
Required output power, receiving level, threshold margin, antenna gain, antenna
height
c)
d)
Link reliability
e)
f)
g)
b)
The slave telemetry radio equipment receives its own address, and the transmitter
of master telemetry radio equipment shall be enabled to send data from RTU to
the SCADA System.
c)
Each transmitter of slave telemetry radio equipment shall be activated only when
the slave telemetry radio equipment is addressed.
02.
Operation mode
Simplex, half-duplex
03.
Protection
04.
Output power
05.
Modulation method
Digital, CPFSK
06.
Output Impedance
50 Ohms
07.
Interface
08.
Transmission speed
09.
Receiver Sensitivity
10.
Receiver Selectivity
60dB minimum
11.
Duty Cycle
Continuous
- 114 -
COMMUNICATION SYSTEM
12.
40 dB nominal
13.
14.
15.
Antenna size/gain
16.
Equipment Protection
IP65
17.
Operating Temperature
-10 to 65C
18.
Humidity
19.
Height, strength
and material
b)
Foundation
c)
Lightning
system
7.5.4.1 GPRS modem shall be of standard GSM 900/1800/1900MHz having auto bauding facility
and complaint with ETSI (European Telecommunications Standards Institute). GSM Phase
2+ standard shall be operated at Class 4 (2W) 900 MHz and Class 1(1W) 1800/1900MHz
with suitable memory of minimum 4 GB and further having facility of error correction 40
characters command buffer, Non-Transparent data transmission at 1200/2400/4800/9600 bps
and auto dial feature.
7.5.4.2 The modem shall support Short Messaging Service Feature, Point to Point transmission and
Cell Broadcast features, GSM data feature - CSD Asynchronous non transparent up to
9.6kbps and HSCSD (High speed circuit switched data) (2+1) up to 28.8kbps, serial binary
and asynchronous data format for data transfer
7.5.4.3 The data enabled SIM cards will be provided by the Employer. However, all necessary
coordination and arrangement for issuance of the cards by the Service Provider shall be
undertaken by Bidder at their own responsibility.
7.5.4.4 A SMA (Sub Miniature version -A for connectors and coaxial RF connectors) interface shall
be provided on the GSM modem to which either a fixed removable or wired Dual Band
Antenna with gain of 5.5 dB can be connected.
7.5.4.5 General Constructional Requirements
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 115 -
COMMUNICATION SYSTEM
Operation
(2)
Antenna Connector
(3)
(4)
(5)
Consumption
transmission (Tx)
(6)
2W(900Mhz), 1W(1800Mhz)
(7)
EMC
(8)
integral part
(9)
Data Features
during
- 116 -
COMMUNICATION SYSTEM
(10)
Interfaces
(11)
Degree of Protection :-
IP65
(12)
Operating temperatures
10 to +65 C
(13)
Humidity :-
b)
c)
Interface offered shall have RS 232 port with a D type 9 pin connector or RJ 11
connector.
d)
GSM engine should not get affected under heat, electromagnetic fields, electrostatic
fields, magnetic fields, electromagnetic induction etc. The GSM engine should be of
Wavecom, Siemens, Sony Ericsson, Nokia, Simcom and Motorola. If any other make
of GSM engine is being used then it should get prior approval from the Employer.
e)
f)
Modem should have a Real time Clock (RTC) as an integral part and should be
demonstrated if demanded.
g)
h)
Protocols for communication with Server ETSI GSM Phase 2+, GPRS Enabled,
DOTA 3 Enabled.
i)
The Baud rate for data transfer shall be at 9600 kbps programmable. The modem
should be flexi speed in nature that means they should be able to operate at different
baud rate without any hindrance in their communication properties.
j)
The modem shall configure at any baud rate up to a maximum of 9600 baud rate
through the terminals of desktop/laptop using Windows Operating System / Industry
standard open protocol UNIX / LINUX etc. No proprietary software should be used
for configuration of modem at the desired baud rate.
k)
The modem should have outbound dialing facility to a particular GSM number
(server) at specified time (daily / weekly / monthly, etc.) for the purpose of sending
data. This configuration of the modem shall be made available to the user through the
Contractor provided software. If modem could not establish connection to modem
placed at central station at specified time then it shall retry the same as configured
l)
The Intelligent modem shall have sufficient memory up to 256 KB + 32KB to store
resident software and separate memory up to 4MB Flash for data storage. The
modem memory shall be non-volatile so that the registered parameters and stored
data are not affected by loss of power. The non-volatile memory shall have a
minimum retention time of 10 years.
m) Data Features:
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 117 -
COMMUNICATION SYSTEM
Modem should use standard AT Command set (GSM 07.05 ,GSM07.07) for
settings of the modem
Full GSM or GSM/GPRS software stack
Data circuit asynchronous, transparent and non-transparent
Max. Baud Rate : for GSM Operation - 9600 bits/sec for GPRS operation 14400 bits/sec
GPRS packet data features:
GPRS Class2 or class 10 support of PBCCH/PCCCH Coding Schemes: CS1
to CS4
7.5.5
n)
o)
Power: Maximum Power Output should be 2 W at 900 MHz and 1W at 1800 MHz &
the RF functionalities should The RF functionalities should comply with the phase II
EGSM 900 / GSM 1800 recommendation. VA Burden of the Modem should not
exceed 3.5 VA during data communication.
p)
The GPRS module in the modem shall have a real time clock and calendar with a
battery backup totally independent of power supply. The meter time or GPRS time
shall be synchronized in both the modem and central server to take care of RTC drift
variations.
q)
Modem should be capable of continuous working for 24 hours every day under field
conditions, even when enclosed in Metering Cubicles at Consumer Sites
IP PBX Equipment
7.5.5.1 The telephone system shall employ VoIP technology and shall provide voice communication
through the network.
7.5.5.2 The telephone system shall consist of IP PBX, extension telephone sets and associated cabling
in the buildings of the master telemetry stations and in the MCC/ACC room. At MCC,
uninterrupted power supply (UPS) is available, so a standby power supply system for IP PBX
is not required. The telephone system configuration is shown in Figure 7.4.
7.5.5.3 Access to the public switched telephone network (PSTN) shall be provided at MCC.
7.5.5.4 The capacity of IP PBX shall be as follows:
a) PSTN line
6 lines
b) Extension line
c) Trunk line
7.5.5.5 The IP PBX shall be modular construction and designed to have 100% expansion capability.
7.5.5.6 The IP PBX shall be non-blocking digital switches, operating under stored program control.
7.5.5.7 All common control equipment shall be duplicated.
7.5.5.8 PSTN Connection
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 118 -
COMMUNICATION SYSTEM
a)
In the case where the PSNT connection is a digital circuit, the interface condition
shall be compliant with relevant ITU-T Rec. and other regulations.
b)
The IP PBX shall have facilities to restrict dialing access from any telephone
extension to the PSTN.
c)
Access to the PSTN shall be done through direct dialing where configured, and
shall be permitted to the selected extension lines.
A supervisory system shall be provided for IP PBX that allows the performance to
be analyzed as well as providing configuration facilities and fault information and
diagnostics.
b)
The IP PBX shall prepare, store and collate information on call logging, traffic
analysis and fault analysis. A hard copy printout shall be available at IP PBX
installation on dedicated printers.
7.5.5.10General Requirements
a)
The Telephone System shall be designed to provide voice and data services. The
telephone System shall offer reliable and resilient means of transmission of voice
communication within the external locations via IP and PSTN connectivity
interfaces.
b)
The System shall be based on IP based telephony (IPT). The main IP Server shall
be connected to 2Mbps E1 link at Dhaka MCC. The PSTN lines shall also be
connected at MCC through suitable interface which will be provided by
Contractor.
c)
d)
The system software should be protected against data loss/corruption in the event
of power failure, unauthorized command or other faulty conditions.
e)
f)
The telephone system shall be configured to ensure that the system availability is
equal to or greater than 99.99%, with no complete loss of telephone service under
any circumstance. Contractor shall support the system and equipment availability
through appropriate calculations.
b)
c)
- 119 -
COMMUNICATION SYSTEM
e)
f)
7.5.5.12The exact quantities and locations of the VoIP extension telephone set are furnished as under
and also shown in Figure 7.4.
a)
20 VoIP sets
b)
Demra MTS
8 VoIP sets
c)
Ashuganj ACC
12 VoIP sets
d)
Elenga MTS
5 VoIP sets
e)
Kailastilla MTS
2 VoIP sets
f)
Jalalabad HO (JGDSL)
2 VoIP sets
g)
Fenchuganj MTS
2 VoIP sets
h)
Rashidpur MTS
2 VoIP sets
i)
Manohardihi MTS
2 VoIP sets
j)
Bakhrabad MTS
3 VoIP sets
k)
Mirasarai MTS
2 VoIP sets
l)
Faujdarhat MTS
2 VoIP sets
Outside lines
16 minimum
(2)
Extension lines
512 maximum
(3)
Power supply
(4)
Backup battery
Not required
(5)
Mechanical construction
- 120 -
COMMUNICATION SYSTEM
(6)
Features
Station Call
a)
b)
Abbreviated Dialing
c)
Authorization Codes
d)
e)
f)
g)
h)
i)
Class of Restriction
j)
Auto Attendant
k)
l)
Distinctive Ringing
m)
Music on Hold
n)
o)
p)
q)
4 Party conferencing
r)
s)
t)
Hotline Facility
u)
Fixed-Mobile Interface
Operation
VoIP on LAN
(2)
Interface
(3)
Line key
(4)
Speaker phone
(5)
Display
(6)
Protocol
(7)
Call Log
- 121 -
COMMUNICATION SYSTEM
(8)
(9)
Power Supply
7.5.5.15Telephone Cabling
The contractor shall be responsible for the installation of telephones and associated cabling
inside of the room at MCC/ACC and also inside the radio building at MTS. The telephone
cabling shall be made of Ethernet cable.
7.5.5.16Maintenance PC
The PC for the maintenance purpose shall be supplied. It shall be able to interface with IP
PBX in order to upgrade or renew the programs installed in IP PBX memory.
7.5.6
Network System
(2)
The media converter shall be operated with 24V DC negative ground. If the equipment
operated with different voltage is adopted, a DC/DC converter shall be supplied.
(3)
signal
of
a)
(2) Number
required port
For MCC's AP
1 nos. IP/Ethernet : 10 nos. E1
Min.
b)
For ACC's AP
1 nos. IP/Ethernet : 10 nos. E1
Min.
HDB-3
(4) E1
Electrical
Interface
ITU-T G.703
(5) Jitter
ITU-T G.823
IEEE 802.3
(9) Power
- 122 -
COMMUNICATION SYSTEM
consumption
(10) Mechanical
construction
To connect with the branching network, a HUB or Router shall be provided to each
MTS and MCC/ACC.
(2)
The Contractor shall select an adequate branching device from the HUB or Router to get
the best performance of the network.
(3)
The HUB/Router to be installed at MCC/ACC shall be operated with 230V AC. The
HUB/Router to be installed at the other stations shall be operated with 24V DC negative
ground. If the equipment operated with different voltage is adopted, an adequate power
supply adapter shall be supplied.
(3) Switching
data
transfer method
CSMA/CD
(6) Routing
Multicast
and
IP
Filtering,Stateful
Inspection
Firewall,NAT-T,SMTP
&
HTTP
Proxy,Authentication: RADIUS, TACACS,
MD5, PAP, CHAP,SSH, SSLv1,VPN L2TP, GRE, IPSec, IKE, ISAKMP,
PKI,Encryption:
DES,
3DES,
AES,Microsoft Windows XP VPN client
interoperability,Authentication:
RADIUS,TACACS,
MD5,
PAP,
CHAP,VPN/Encryption,DES,AES,
3DES
encryption,Min.5,000 configured IPsec VPN
tunnels ,HW accelerated IPsec performance:
Up to 500Mbps,Supports industry standard
- 123 -
COMMUNICATION SYSTEM
(10) Processor
&Memory
533MHz
or
better,Internal
security
encryption engine,64MB Ram or better
,16MB Flash or better
(11) Interface
connector
RJ-45
(13) Power
consumption
(14) IPv6
(15) Approvals
Compliances
b)
12fiber strands.
c)
Fibres shall conform to ITU-T G.652 or G.655 recommendation for Single Mode
Fiber Optic Cable.
d)
Fibres shall conform to ITU-T G.651 or G.651.1 recommendation for Multi Mode
Fiber Optic Cable.
- 124 -
COMMUNICATION SYSTEM
e)
Optical path discrete reflectance and return loss in accordance with requirements of
table 4, ITUG.957.
Specifications of FO Cable
PARAMETER
SPECIFICATION
01.
70 mm to 100 mm
02.
Fiber Count
12
03.
Core Covering
Non-hygroscope tape
04.
05.
Armour Material
06.
Armour Thickness
18 mm
07.
Temperature Range
-10 to + 80 C
08.
09.
Numerical Aperture
200 mm
10.
< 1270 nm
11.
3.5 ps/nm. Km
12.
13.
- 125 -
COMMUNICATION SYSTEM
PARAMETER
SPECIFICATION
14.
15.
16.
Yes
17.
Splice Type
Contractor to indicate
18.
0.05 dB
19.
Connector Type
Contractor to indicate
20.
0.3 dB
All CAT-6 cable shall be used for connecting the equipment and device to Ethernet
switches. These will be used in MCC, ACC, Service Providers Access Points etc.
(2)
Compliant Standards
Values
02.
No. of pairs
4 pair
03.
Conductor
04.
Conductor Diameter
23AWG
05.
Nominal DC Resistance
67 Ohms /1Km
06.
Nominal Impedance
07.
Nominal Capacitance
46pf/ m
08.
Nominal Velocity of
propagation
68%
- 126 -
COMMUNICATION SYSTEM
09.
Nominal Attenuation
10.
Insulation Materials
11.
6.45 mm
Low loss coaxial cable shall be used for connecting the telemetry master and slave radio
equipment and IP radio equipment to respective antenna. These will be used in RTU
sites, MTS locations and Service Providers Access Points etc.
(2)
The RF Low loss coaxial cable shall have low density foam dielectric and dielectric
material shall be Polyethylene Foam.
Specification of RF Low loss coaxial Cable
01.
Weight of cables
0.45Kg/m minimum
02.
Tensile Strength
140 N/m
03.
255 mm
04.
Nominal DC Resistance
67 Ohms /1Km
50 Ohms
06.
Nominal Capacitance
74pf/ m nominal
07.
08.
Nominal Attenuation
05.
09.
Insulation Resistance
100000 Meg-Ohms
11.
6.45 mm
12.
Nominal Size:
7/8 inches
13.
10.
- 127 -
COMMUNICATION SYSTEM
The PC with software for NMS shall be provided at MCC and ACC.
Monitor PC for NMS Specifications
7.5.7
(1)
Type of PC
Laptop Type
(2)
Display size
15 inches or more
(3)
OS
(4)
CPU
(5)
HD capacity
500GB or more
(6)
Media Drive
Built-in, CD / DVD
The Total solution shall provide for Normal, Presentation and Web Casting
conferencing facility. In Normal Conferencing mode, number of users spread across
various locations should be able to participate. In Broadcast Conferencing mode the
speaker should be able to broadcast his/her message to all other locations having the
facility. The speaker in this case must occupy the full screen at all the end user
locations. It shall also provide the Presentation facility to the speaker, whereby one can
present a topic to the wider audience using Conferencing facility. The users from
Internet shall be able to participate in the conference using their wireless devices like
Laptop/Mobile etc. Web Conferencing inter-alia will involve users either from the
Internet or from intranet, participating in the proposed Video Conferencing facility in
GTCL using the desktop PC/any standard web conferencing software like Net Meeting
etc.
(2)
The total solution shall provide for simultaneous multi-conferencing using IP and PRI
ISDN, in all combination. In a mixed IP/ISDN video conference, there should not be
perceptible difference in the video/audio received.
(3)
This Master Controller can define conference numbers and allot host and time slot for
each. Host shall be able to invite participants to the meeting, and manage them.
(4)
This system shall enable users through wireless keyboard/remote device to manipulate
the camera angle, focus and various parameters to suit the user requirements. The voiceactivated facility shall be provided for camera control.
(5)
The Total Solution shall connect using the LAN port available in the conference room
locally and it shall use the bandwidth available in the Company's backbone network,
which is using Leased Lines and PRI ISDN, seamlessly.
(6)
The Total Solution shall work in present-presenter mode, i.e., the system have the
requisite software and hardware interfaces to provide for computer connectivity to
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 128 -
COMMUNICATION SYSTEM
enable making Presentations, sharing of files, etc. across multiple locations. The Total
solution shall have duo video capabilities i.e. both Presenter and Presentation shall be
displayed. Either one display device splitting the area to display both, or two separate
displays like monitor and LCD shall be possible.
(7)
Dial-out service shall have a programmable retry facility, wherein the system will try to
reconnect automatically in case the receiving lines are in a busy/ no response condition.
The number of retry shall be configurable. The video output shall support minimum two
monitors and enable connectivity to a VCR or similar recording device.
(8)
There shall be automatic web enabled updation of the Video conferencing software for
the latest version/patches/upgrades.
(9)
(10) The Contractor shall supply the necessary hardware, software for setting up the Video
Conferencing facility, including design, setup, operationalize and maintain the same at
all the locations to meet the requirements of the Company.
(11) Contractor must submit the list of Ports and Services require to be opened on the
Network equipment like Firewall, Router etc. at all the locations for implementing the
Total solution.
7.5.7.2 Technical Specification
a)
Against some items, Functional requirement and Technical specifications of MCU (Multi
Conferencing Unit) are given. The Functional requirement needs to be complied mandatorily.
1. Functional Requirement
(1)
(2)
Will be Full High Definition video capacity (1920x1080), and support users of same or
lower capacity i.e. 128 Kbps to 4 Mbps per user (port), and voice call.
(3)
Lower speed connection shall not affect higher speed connections (independent port
transcoding).
(4)
Will support IP and SIP protocols, and having 1 PRI Gateway scalable to 2 PRI.
(5)
Will be of open standards technology to allow connection from any other brand /
technology of MCU, end point or desktop Unit, including existing SD models.
(6)
(7)
Network interface minimum 10/100 Mbps, and manageable on network, SNMP supported
(8)
- 129 -
COMMUNICATION SYSTEM
(9)
Shall be possible to initiate session recording from the MCU onto recording server, and
streaming / webcasting from the Server.
(10) Shall be IPv6 compliant or shall be software upgradable to IPv6 compliance in future at no
extra cost.
2. Equipment Specification
(1)
The MCU shall be real-time media conferencing platform providing a high performance,
scalable, IP-network (H.323) solution with feature-rich easy-to-use multipoint video and
integrated (video, audio, and content) conferencing features.
(2)
Bidders shall quote a hardware based standalone platform for MCU; software based
MCU and embedded MCU on video end points are not acceptable.
(3)
Capacity
(4)
a)
Up to 30 media and audio (H.323) resources with dedicated encode and decode
streams.
b)
High Definition
Full High Definition (HD) refers to high-quality picture resolution. An HD-compliant
endpoint shall connect to a conference at a resolution of 1920x1080 and the bit rate of 128
Kbps~4 Mb.
(5)
(6)
(7)
(8)
Video Support
a)
b)
c)
d)
e)
f)
g)
h)
i)
Audio Support
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 130 -
COMMUNICATION SYSTEM
(9)
a)
b)
c)
d)
DTMF support
Management Tools
a)
b)
c)
d)
e)
f)
On-board scheduling option or scheduling and gate keeping functions via external
server
b)
c)
d)
(11) Transcoding
a)
Audio algorithms
b)
Video algorithms
c)
Networks
d)
Resolution
e)
Frame rates
f)
(12) IP QoS
a)
b)
Diff Serv
c)
IP Precedence
d)
(13) Security
a)
- 131 -
COMMUNICATION SYSTEM
b)
b)
c)
d)
e)
f)
Personal layout
g)
Auto layout
h)
i)
Using DTMF and FECC user shall be able to perform actions on the conference
j)
k)
l)
m)
Camera Control
n)
Video Force
o)
p)
Mute Video
q)
Drop Participant
r)
Terminate Conference
s)
Video Invite
t)
Layout skins
u)
v)
Conference profiles
w)
x)
y)
Up to 40 Meeting Rooms
z)
aa)
bb)
cc)
- 132 -
COMMUNICATION SYSTEM
dd)
(15) H.239
The H. 239 protocol compliant endpoint can simultaneously send and receive two channels
of conference video streams : dynamic conference video and PC screen content.
(16) Media Encryption
The system shall provide the AES 128-based media encryption mode, so the conferencing
connection is more secure. There shall be no port loss when AES encryption is turned on.
(17) IVR-Enabled Conferencing
The Interactive Voice Response (IVR) function lets participants perform various operations
during ongoing conferences according to voice prompts. The participants use their
endpoints keypads and remote control to interact with the conferences menu-driven scripts
using DTMF codes.
(18) Recording Link
The MCU shall support the function of recording link. It can work with the Recording and
Streaming Server to record the content of the conference at the MCU.
(19) Setting up conferences
a)
b)
Meeting Room - The meeting room is stored in the MCU memory, without
occupying any resource. It can be activated anytime.
c)
Reserve a Conference (optional) - The reserved conference is stored at the MCU and
occupies resource. The system automatically convenes the conference according to
the reservation time.
Web Interface
The system provides the Web-based user-friendly operation interface on Windows
and Mac / Industry standard open protocol UNIX / LINUX etc. To simply and
conveniently manage and monitor conferences, and maintain the device, the user
only needs to access the Web client program of the MCU by using the IE browser
at the PC. The Web interface is designed for the administrator and operator.
b)
a)
The MCU shall have three levels : Chair Person - A Chairperson can only manage ongoing conferences and
participants. The Chairperson does not have access to the MCU configurations
and utilities.
- 133 -
COMMUNICATION SYSTEM
Operator - An Operator can perform all the MCU tasks a Chairperson does. In
addition, Operators can also view the MCU configurations.
Administrator - An Administrator can perform all the tasks of Chairpersons
and Operator users. In addition, Administrators can perform all configuration
and maintenance tasks.
(21) Hardware Monitoring
Control function to monitor the usage of the system CPU, memory and resource usage and
other hardware parts of MCU.
(22) Signaling Monitoring
Monitors the LAN port connection status and gateway registration information of the device
you are using.
(23) Operating System
Linux or equivalent
(24) CDR
MCU shall support the Call Detail Record (CDR) utility, which enables you to view
summary information about conferences, and retrieve full conference information and
archive it to a file. The file can be used to produce reports or can be exported to external
billing programs. MCU shall be able to store details of up to 200 conferences.
b)
VC End Point
The proposed video conferencing system must include using a remote control interface or touch
panel control. The architecture must be based on industry standards wherever possible. This
includes standards such as the H.323 and SIP umbrella standards for IP-based audio/video and
H.320 umbrella standard for ISDN-based audio/video.
3. Functional Requirements
(1)
Will provide multi-conferencing for minimum 1+3 users concurrently in HD mode, with
upto4 Mbps on IP/SIP, and ISDN PRI / BRI port.
(2)
Will be High Definition video capacity (1280x1024), and support users of same or lower
capacity i.e. 128 Kbps to 2 Mbps per user (port), and voice calls through MCU.
(3)
Shall have PTZ camera, minimum 10X optical zoom, and 2 numbers microphones.
(4)
Lower speed connection shall not affect higher speed connections (independent port
transcoding).
(5)
Will be of open standards technology to allow connection from any other brand /
technology of MCU, end point or desktop Unit.
(6)
Will allow video and Data concurrently, from camera, computer and document camera on
input side, and to Display, Projector (i.e. dual display) and recorder on output side.
(7)
Network interface minimum 10/100 Mbps, and manageable on network, SNMP supported.
(8)
Shall have conference scheduling and management, directory management, call logging,
etc for the End Point.
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 134 -
COMMUNICATION SYSTEM
(9)
Shall be possible to initiate session recording from the End Point onto any recording
server.
(10) Shall be IPv6 compliant or shall be software upgradable to IPv6 compliance in future at no
extra cost
(11) The distribution of end points shall be as under:
i. Agargaon: 5 No.
ii. Petrobangla H.O: 5 No.
iii. Ashuganj: 2 No.
iv. Demra: 2 No.
7.5.8
Microwave/IP Radio will be used for access link. Non licensed frequency available in
BTRC will be used for this Radio Link. However as a stand by communication link, FOC
access link shall also be used. The access link using Optical fiber shall be based on SDH
STM-1 equipment.
(2)
If FOC is used from MTS to BTCLs/Service Providers AP, SDH/Router and Ethernet
node will be installed at MTS end. Process signal from RTU will be interfaced with SDH
system/Router at electrical level 10/100 Base T level.
(3)
All the SDH equipment will be connected at STM-1 (1+0) optical level.
(4)
The Contractor shall supply, install and commission the FOC based Access Link as per
the scope of work, which broadly includes the following system packages:
(5)
Its aggregate rate shall be STM-1, and it will support tributary interfaces with various bit
rates including PDH, SDH and Ethernet interfaces. It will have higher order and lower
order cross-connect capability to realize various networking topology structures such as
ring and chain. It shall support 1:2 protection function of E1 card. Its functions and
technical specifications shall comply with the requirements of ITU-T recommendations
and other relevant standards.
(6)
(7)
This unit offers three power supply options. Options for the power supply to the equipment
include:
a) Dual DC - 48V Inputs (range -18V DC ~ -72V DC), for power input redundancy. b)
(8)
- 135 -
COMMUNICATION SYSTEM
G.703
G.707
G.781
G.782
G.783
G.813
- 136 -
COMMUNICATION SYSTEM
G.825
Control of Jitter and Wander within Digital Networks Which are Based on the
Synchronous Digital Hierarchy (SDH)
G.957
G.958
Digital line systems based on the Synchronous digital hierarchy for use on
optical fiber cables
(9)
155.52 Mbps
ITU-T G.703 Compliant
75 Ohms resistive
1 + 0.1 V
< 2 ns
12.7dB at 78MHz
As per ITU-T G.825
CMI
BNC Coaxial
155.52 Mbps
ITU-T G.957 STM-1
NRZ
LC
Laser Diode
850nm / 1310nm / 1550nm
Dual Fiber (standard)
Single Fiber Bi-directional (optional)
Provided - User selectable option
As per SFP used
As per SFP used
7.5.9
Working
temperature
Relative humidity
Software
7.5.9.1 Integration
- 137 -
COMMUNICATION SYSTEM
(11) Bidder shall provide an open-architecture system that shall allow for future integration
of other systems that use standardized system interfaces.
(12) The System shall be capable of operating as a stand-alone system but shall have the
capability of integrating with existing and/or other types of Radio systems. Bidder shall
provide clearly defined test documents that demonstrate the capability to connect to
additional systems. Bidder shall describe all aspects of the expansion capabilities for future
connections.
(13) Bidder shall be responsible for the integration and overall system functionality of the new
systems with any Employer system, including Site Acceptance Test.
7.5.9.2 Overall Software Requirements
(1)
Bidder shall ensure that a complete set of support software and documentation is delivered
with the Radio System; this includes all disks, CDs and manuals that were received with
the original package.
(2)
All Commercial off the Shelf (COTS) software shall be the most current version at the
time of installation.
(3)
After initial system installation, all subsequent software development, configuration, and
testing shall occur without interfering with normal system operations.
(4)
Any custom developed software shall be programmed in a single, industry standard, highlevel language (Such as C) regardless of the platform.
(5)
Operating System (OS) environment for all computers shall be a recognised industry
standard operating system available off the shelf. The preferred operating system shall be
the latest licensed version of Windows NT (or XP) / Industry standard open protocol
UNIX / LINUX etc.
(2)
Bidder shall supply the source code and unlimited license for any custom application
software developed under this contract (This requirement does not apply to COTS).
(2)
Bidder shall provide a full set of technical manuals in books and CDs for all COTS
software. The application software shall require no source code modification to the
delivered operating system.
(3)
All software interfaces with the operating system shall be via OS interface standards.
- 138 -
COMMUNICATION SYSTEM
incorporate any or all of the new software products into the System this shall be undertaken at
no additional cost to Employer.
7.5.9.6 Maintenance Utilities
(1)
The support software shall consist of all compilers, editors, loaders, debugging aids,
linkers, libraries, cross-reference, hardware diagnostic routines and other utilities required
in the generation, maintenance and modification of all system software and hardware.
(2)
Bidder shall provide software and hardware maintenance and diagnostic utilities.
(3)
Bidder shall also provide a list of these utilities cross-referenced by the sub-system to
which they apply and shall be part of database in which when report is needed; printing
will be available for the list.
(4)
Utilities shall allow the maintenance role to be carried out by individuals with little or no
understanding of, or experience with, the operations system. The utilities shall be user
friendly and require little training to use effectively.
- 139 -
COMMUNICATION SYSTEM
8.
INSTRUMENTATION REQUIREMENTS
8.1
INTRODUCTION
Field Instruments like Differential pressure transmitter, Pressure transmitter, Temperature
transmitter, Turbine flow meter, Flow computer etc. will be used to measure and monitor gas
parameters at various sites on the GTCL pipeline network. The open / close status of gas
valves will be monitored and some main line valves and flow control valves will also be
controlled under this SCADA system.
Remote Telemetry Units (RTU) will be located closed to these field instrumentation devices
which in turn will report to the centralized SCADA system at MCC / ACC through suitable
communication system.
8.2
8.3
GENERAL
(1)
All electronic instruments requiring separate power supply shall generally operate on
24V DC.
(2)
Electronic transmitters shall generally be two-wire type. These shall have transmission /
output signal of 4-20 mA DC and shall be capable of delivering rated current into
external load of at least 600 ohm when powered with 24 V DC nominal voltages.
(3)
(4)
All field instruments shall be suitable for reliable and continuous operation under the
project environmental conditions specified. The field electronic instruments and
Junction boxes shall be certified weatherproof to IEC-60529 classification IP 65 as
minimum for protection against moisture or dust ingress. All Junction boxes, cable
glands & accessories shall be certified weather proof to minimum IP65 and Flame proof
suitable for hazardous area classification IEC Zone 1, Gr. IIA, IIB, T3.
(5)
All field transmitters shall be weather proof to minimum IP65 and suitable for
hazardous area classification IEC Zone 1, Gr. IIA, IIB, T3.
(6)
Hand held configurator shall be provided for remote calibration, remote configuration
and remote diagnostics of the transmitters.
PRESSURE TRANSMITTERS
(1)
The Contractor shall verify the process connection for pressure instruments at the sites.
As a reference, process connections for pressure instruments are normally 1/2" NPT.
(2)
At some sites, the Contractor shall make a branch on the existing impulse tubing as a
tapping point for pressure instruments. The Contractor shall survey the installation
condition, make hook-up drawings and install the pressure transmitters.
(3)
- 140 -
INSTRUMENTATION REQUIREMENTS
24VDC with 4-20 mA output and an integral digital indicator meter in both SI and FPS
engineering units.
(4)
(5)
Material for construction for wetted parts shall be SS 316L as a minimum, except '"here
process conditions require more stringent materials. Materials for construction shall be
suitable for the process media and based upon the piping specification.
(6)
Pressure transmitters shall have minimum accuracy 0.075% of the calibrated span.
Transmitters shall have independent external screws for zero and span adjustment.
Working Principle
Smart
02.
Type
2-Wire
03.
Output signal
04.
05.
Measuring element
Capsule/Diaphragm
06.
Element material
07.
Over Pressure
08.
Turn-down ratio
09.
10.
Enclosure
11.
Output Indicator
LCD type
12.
Body
13.
Operating Voltage
24 V DC 10%
14.
Load
15.
Performance :a)
Accuracy
b)
Repeatability
- 141 -
INSTRUMENTATION REQUIREMENTS
c)
Response time
d)
e)
Stability
0.1% of calibrated span for six months for ranges upto and
including 70 Kg/ sq.cm.
0.25% of calibrated span for six months for ranges more
than 70 Kg/ sq.cm (g).
16.
Process connection
NPT (F)
17.
Sealing / Isolation
18.
Nameplate
19.
Accessories
a)
b)
c)
d)
8.4
TEMPERATURE TRANSMITTERS
8.4.1
Thermowells
8.4.2
(1)
Temperature measuring instruments shall be provided with thermowell. The boss on the
pipeline as a process connection for thermowell will be prepared by the Employer. The
Contractor shall verify the information of process connection and design suitable thermo
well.
(2)
Thermowells shall be constructed from one-piece bar stock, and machined to get a
smooth and tapered profile with no sharp edges. All insertion type temperature
instruments and indicators shall be provided with a thermowell. The thermowell
immersion depth in the pipe shall be between one-third and two-thirds of the internal
diameter of the pipe.
Temperature Transmitter
(1)
Resistance temperature detectors (RTDs) shall be used for centralized and multi-point
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 142 -
INSTRUMENTATION REQUIREMENTS
indication. The RTDs shall be grade II. Platinum 100 ohms at 0 C (32 F).
(2)
A detector with head mounted transmitters shall be used with dual output 4-20 mA
signal directly proportional and linear to temperature.
Type
02.
Resistance
03.
Base
04.
Wiring
3 /4 Wire
05.
Protecting Tube
:-
a)
O.D.
8 mm
b)
Material
SS-316, Seamless
c)
Filling
06.
Calibration
07.
Characteristics
08.
Head :
09.
10.
a)
Type
b)
Material
c)
Terminal blocks
d)
Cable connection :
e)
f)
Others
Accessories
a)
b)
Compression fittings/unions
c)
d)
e)
Nameplate
Thermowell
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 143 -
INSTRUMENTATION REQUIREMENTS
01.
Material
02.
Process connection
M33 X 2 (M).
03.
04.
Bore Connection
5% wall thickness
05.
Identification Mark
06.
Surface Treatment
07.
Element Connection
NPT (F)
08.
Certification
09.
Accessories
Working Principle
Smart
02.
Type
Two wire
03.
Input
04.
Isolation
500V AC
05.
Output Signal
06.
Signal Processing
Circuitry
07.
08.
Enclosure Class
09.
Output Indicator
LCD type
10.
Span Adjustability
Yes
11.
Nameplate
12.
Body
13.
Operating Voltage
16-48 V dc
14.
Load
15.
Performance
a)
Accuracy
0.4% of span
b)
Repeatability
0.05% of span
c)
Cold Junction
Compensation:
Built-in
- 144 -
INSTRUMENTATION REQUIREMENTS
d)
16.
8.5
Calibration
Accessories
a)
b)
c)
Type
02.
Output Signal
Pulse
03.
Material of
Construction
a)
b)
c)
04.
As required.
05.
Linearity
+
_ 0.25% or better.
06.
Repeatability
+
_ 0.02% or better.
07.
Mounting
On-Line, flanged
08.
Enclosure
IP 65
Transmitter
01.
Electronics
Solid State
02.
Power Supply
03.
Input
04.
Display
05.
Output
Isolated 4-20mA DC
- 145 -
INSTRUMENTATION REQUIREMENTS
8.6
06.
Measuring Accuracy
+
_ 0.5% of full scale range
07.
Totalized Value
Required
08.
Housing
09.
Nameplate
10.
Accessories
a)
b)
FLOW COMPUTER
The flow computers shall be microprocessor based, with digital display, data entry keypad
and alphanumeric display with AGA firmware for natural gas flow measurement. Flow
computer electronics shall be protected from industrial interferences; and shall be shock and
vibration proof shall have low power consumption.
The flow computers shall compute and display the instantaneous and totalized flow rate for
each stream corrected for pressure and temperature variations. The flow computers receive
data from the Gas chromatograph for calculation of compressibility factor as per AGA-8
detail method. The flow computers shall be linked to the RTU for providing the flow
measurements of the individual stream runs and related process variables.
The flow computer shall be certified for custody transfer applications by laboratory /
institutes authorized by weights and measures authorities of their country.
The flow computers shall have an audit trail facility. It should be able to store data for 30
days.
Contractor has to submit the flow chart for FDS (Functional Design Schematic) of the flow
computer.
All the licensed configuration software shall be supplied with flow computers.
Mounting shall be Flush panel type in General purpose enclosure.
POWER SUPPLY: 230 V AC 10%, 50 Hz 3% (UPS) or 24 VDC or in some cases Solar
powered with battery back-up suitable for 30 no-sunny days. The system shall be designed
for supplying power to field mounted electronic instruments like PTs, TTs, DPTs etc.
INPUT SIGNAL CAPABILITY:
a)
b)
4-20 mA D.C. (2 wire) superimposed with digital signal (HART protocol) from
SMART differential pressure transmitter representing differential pressure across
orifice for flow measurement.
c)
4-20 mA D.C. (2 wire) superimposed with digital signal (HART protocol) from
- 146 -
INSTRUMENTATION REQUIREMENTS
4-20 mA D.C. (2 wire) superimposed with digital signal (HART protocol) from
SMART temperature transmitter representing line temperature.
e)
INTERFACE CAPABILITY:
Contractor shall provide serial links along with cables and connectors at both ends for all the
signals with MODBUS protocol. The communication between flow computers and on line
RTU & SCADA, shall be through serial communication and also through GPRS enabled
GSM modem in-built or separately installed with the flow computers.
Flow computers shall be interfaced with Employers RTU for flow metering and gas
composition data such as gas temperature and pressure, energy flow rate and total energy,
corrected volumetric flow rate and total flow, last days cumulative energy and volume,
current days running volumetric total and energy total, volume and energy integrated at 6
a.m., gas composition (C1, C2, C3, iC4, nC4, iC5, nC5, C6+, Specific gravity, Calorific
value, mol% of N2, CO2) etc. Contractor to note that SCADA Sub Contractor / Contractors
shall provide RS 485 serial link at the RTUs for interfacing of intelligent electronic devices
like flow computers. For flow computer interface to RTU, Contractor shall accordingly
provide RS 485 link (Modicon Modbus ASCII & RTU protocol supporting IEEE single
precision floating point no. with user configurable register).
The digital and analog data shall be made available to RTU (SCADA) and it shall be mapped
in the contiguous registers so that data can be fetched / written in minimum transactions.
Flow computer shall have provision to configure an IEEE floating point in two 16 bit modbus
register. Provision shall also be kept at flow computer for writing data from RTU e.g. in some
Flow computer there will be requirement of downloading gas compositions, calorific value
and flow set point etc. from RTU.
Contractor shall furnish all details like pin configuration and signal wise MODBUS address
mapping list etc. for smooth interfacing of this communication link with RTU (SCADA).
Contractor shall also furnish the details of implemented MODBUS protocol like function
codes for read and write, CRC implementation, BCC implementation, register addressing
methods / mapping etc. during detail engineering for serial interfaces to SCADA (RTU).
Contractor shall supply 25 meter of interface cable between the Flow computers and RTU
along with connectors at both ends & necessary converters and other cables accordingly for
each flow computer.
KEYPAD CAPABILITY:
The data entry keypad shall have the provision to enter the following:
a)
b)
c)
d)
e)
f)
Calorific value
- 147 -
INSTRUMENTATION REQUIREMENTS
g)
Flow, pressure, temperature and density values and give compensated flow for any
external conditions
h)
Gas Compressibility
i)
The flow computer shall have provision to enter default values of all inputs (inclusive of gas
chromatograph) low / high alarms for all inputs (inclusive of gas chromatograph) and shall be
user configurable. The flow computer shall use the default values in case any input goes
beyond low/high limit.
OUTPUT CAPABILITY:
a)
4-20 mA compensated volume flow rate output & Flow set point (as external remote
set point) for flow controller, energy rate (or mass flow rate),
b)
Contact alarms output for unit malfunction, process alarm etc. (3 nos.).
c)
RS 485 serial output link for telemetry link for all signals as specified
d)
e)
Other standard outputs available (Minimum 2 nos. 4-20mA analog output for
pressure & temperature) (Galvanic isolation is required for all inputs and outputs)
COMPUTATIONAL CAPABILITY:
a)
Volume flow rate at standard, normal or operator specified base conditions (Sm3/hr)
b)
c)
d)
e)
f)
Generation of standard and user defined reports at ticket printer. All reports shall be
user configurable.
g)
Co-efficient of deviation from ideal gas law as per AGA 8 on the basis of specific
gravity, temperature, pressure and mol % of N2 and CO2 and other compositions for
all flow computers
h)
Previous days flow / energy (i.e. yesterdays 6.00 A.M total volume / energy to
todays 6.00 A.M total volume / energy) & current running total for the day (i.e.
volume tantalizer/ integrator value at 6.00 A.M from first day) to be stored in a
separate location (register) and these shall be user configurable.
i)
Todays accumulated flow /energy (running total since morning 6.00 A.M to current
time) and shall be user configurable.
j)
Generation of reports for totalized volume & energy at daily (6 am), weekly,
fortnightly & monthly intervals etc. shall be user configurable.
k)
All the above data shall also be made available by Contractor in the serial links to
RTU.
STANDARDS USED:
For the above, applicable standards are:
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 148 -
INSTRUMENTATION REQUIREMENTS
a)
AGA report 3 and 7 for flow rate and total flow for all tags for Orifice meter and
turbine type flow meter (as applicable).
b)
c)
AGA Report 5 for energy rate and integrated energy & if any other statutory
standard required.
ENGINEERING UNITS:
Volume flow rate - MMSCFD, Mass - kg/hr, Pressure - PSIG / BARG, Temperature -C / F,
Energy - Kcal
MEMORY TYPE : Non-Volatile
A/D AND D/A CONVERTORS:
Calculation accuracy shall be better than 0.05% of full scale including linearity, Hysteresis,
repeatability and resolution. Accuracy for analogue inputs to be minimum 0.05% and for
analogue outputs accuracy shall be minimum 0.1%.
SCAN PROCESSING TIME:
a)
The interval between computer readings of Process variables shall not exceed 1 sec.
b)
The interval between each cycle for computation of instantaneous flow rate and
totalized flow shall be less than 1 sec.
c)
Algorithm and rounding off error for computation shall be with in 0.001% of
computed value.
SECURITY:
Key lock shall be provided for prevention of unauthorized data entry. One hardware and two
software security levels shall be provided.
DISPLAY CAPABILITY:
The flow computer shall have the capability to display any two of the following parameters at
a time:
Uncompensated volume flow rate, Compensated volume flow rate, Integrated volume
(corrected and not corrected), Mass flow rate, Integrated mass, Density/Specific gravity,
Pressure, Temperature, Energy rate & total energy, Complete gas composition, Calculated
parameters (compressibility factor etc.), Current accumulation, previous day accumulation,
Data entry, Error codes, Selected parameter codes, Alarms (process and systems) including
diagnostic message, Engineering units as per selected parameter, Other standard displays
available, Custody transfer flow computers shall have audit trail, All the above data shall also
be made available by Contractor in the serial links to RTU.
DISPLAY TYPE: Alphanumeric LCD display
DIAGNOSTICS:
- 149 -
INSTRUMENTATION REQUIREMENTS
Flow computers shall have elaborate and sufficient on-line diagnostics to ascertain accurate
and proper functioning of the flow computer. Results of diagnostics / checking shall be
displayed. Facility for easy testing of the accuracy shall be provided. Provision for high and
low limit check for each input, sensor break, saturation and alarms shall be provided.
8.7
LIMIT SWITCH
Limit switches for open / close valve position indication shall be of proximity type. The
switch enclosure shall be copper free cast aluminum, weather proof (NEMA 4X) and it shall
be intrinsically safe.
8.8
8.9
SOLENOID VALVE
01.
Operating Principle
Electromagnetic (noiseless)
02.
24 V DC
03.
04.
Ways
05.
Port size
06.
Body
SS Bar Stock
07.
Trim
AISI SS-316
08.
Manual Operator
In built
09.
Duty
10.
Sealing
11.
Ambient Temperature
0 - 55 OC
12.
Fluid Temperature
0-150 OC (approx.)
13.
Coil Enclosure
Stainless Steel
14.
Insulation
Class-H
15.
Coil Casing
IP-65
16.
Mounting
17.
Cable Connection
NPT
18.
Accessories
19.
Special feature
LED indication
TUBING SYSTEM
- 150 -
INSTRUMENTATION REQUIREMENTS
8.10
(1)
Stainless steel ANSI 316 tubing and fittings shall be used for the instrument gas supply
distribution system. Double compression fittings shall be used. Pneumatic devices shall
be stainless steel. Tubing shall be protected so that no galvanic corrosion will occur.
(2)
The tubing system shall be capable of continuously withstanding the design pressure
and temperature.
(3)
All materials for pressure lead pipe including valves, regulators and accessories, shall be
stainless steel. Pressure lead pipes and fittings shall be 316 SS with double compression
fittings.
(4)
Contractor shall supply 1/2" OD x 0.065" thick ASTM A 269 TP 316 stainless steel
fully annealed, cold drawn and seamless tubes as a minimum for impulse lines upto 600
# class. Higher thickness according to pressure rating shall be considered for higher pipe
classes.
(5)
Junction boxes shall be of intrinsically safe types. Material for construction of junction
boxes shall be LM-6 cast aluminum.
(2)
Terminals shall be vibration proof, mounted on nickel-plated steel rails complete with
end covers and clamps for each row. All terminals shall be suitable for accepting a
minimum 2.5 mrn2 copper conductor in general. Sizing shall be done with due
consideration for accessibility and maintenance.
(3)
(4)
Cable glands shall be double compression type for use with armored cables. They shall
be made of Nickel plated brass. All cable glands shall be provided with rubber cable
hood. All cable glands shall be supplied to suit the cable dimensions. Various
components like rubber rings, metallic rings, metallic cones and the outer/inner nuts,
etc. shall be capable of being adjusted according to the cable tolerances.
01.
Type of enclosure
02.
No. of ways
03.
Material
04.
Type of cover :
05.
Gasket
Neoprene
06.
Mounting
Surface
07.
Cable entry
Cable glands
08.
Grounding
09.
At bottom capped.
- 151 -
INSTRUMENTATION REQUIREMENTS
8.11
8.12
10.
Identification
11.
Colour
12.
Accessories
a)
c)
Cable gland
d)
e)
Transmitters / instruments / devices located in the field shall be grouped together and
shall be installed in Open Type Rack with canopy. Racks shall be factory prefabricated
& painted and complete with internal piping, tubing, manifold valve, isolation valves,
blowdown valves, integral explosion-proof junction box, wiring, illumination etc.
b)
The local instrument racks shall be free standing type constructed from suitable 3 mm
thick channel frame of steel and shall be provided with a canopy at top to protect the
equipment mounted in racks from falling objects, direct sun and water etc. The canopy
shall not be less than 3 mm thick steel and extended beyond the ends of the rack.
c)
The ex-proof junction box for racks shall conform to IP 65 protection class. Junction
box shall be complete with DIN rail mounted terminals, MCB, receptacles and earth
bar. All wiring shall be laid in PVC cable tray. Cable gland plate shall be provided for
cable entry from bottom. Earth bar shall be made of tinned copper continuous and of 25
X 6 MM size.
d)
Each rack shall be provided with receptacle, light fixture with wire guard and lighting
switch. Light fixtures shall be installed on the ceilings of rack.
e)
Contractor shall furnish the drawings showing detail arrangement of racks and hook up
along with instrument grouping at detailing stage for Owners approval.
INSTRUMENT CABLING
Instrumentation Cable (Screened Multi Pair Cable)
0.6/1 KV screened low smoke flame retardant cable
a)
Conductor
b)
Size
c)
Insulation
d)
Pair Formation
- 152 -
INSTRUMENTATION REQUIREMENTS
e)
Screen
f)
Drain wire
g)
Inner sheath
h)
Armour
i)
Outer Sheath
j)
Cable Identification
Manufacturer's standard
k)
Standard
BS 5308
CABLE GLANDS
(1)
The Contractor shall supply air cable glands required for glanding the above mentioned
cables both at field instrument and local control panel locations, junction box locations
and at control room locations.
(2)
All cables glands shall be made of nickel-plated brass and they shall be double
compression type suitable for armored cables.
(3)
Cable Gland
8.14
01.
Type
Double compression
02.
Entry Thread
NPT
03.
Material
Brass
04.
Finish
Nickel Plated.
05.
Protection
IP 65 or better
06.
Accessories
INSTALLATION
- 153 -
INSTRUMENTATION REQUIREMENTS
(1)
Contractor shall be responsible for installation of all the items in their scope of supply
including supply, fabrication and erection of all installation / erection material. The
scope of installation shall include all field instruments and control systems like field
instruments, flow computers, gas detector systems, control system equipment i.e
SCADA system in MCC / ACC including supply / fabrication / erection / installation of
all erection material i.e. cables, cable glands, junction boxes, cable ducts, Trays,
conduits, instrument supports, trenches, instrument road crossing as required
completing the job in all respect.
(2)
(3)
(4)
(5)
(6)
Installation of cable tray / ladder tray, ducts and miscellaneous support materials, clips
as required for supporting aboveground instrument cable, tube etc.
(7)
Installation of suitable cable clamps / tray for multicore cables just before termination
into the junction box or panel such that the weight of cables is not supported by the
cable glands.
(8)
Marker, gland and connect all instrument cables, supply and install markers / ferrules
etc for cable identification in accordance with the specification.
(9)
(10) The capillary of all capillary type instruments shall be supported properly and shall be
protected against mechanical damage.
(11) All pressure / differential pressure instruments shall be provided with block and bleed /
by-pass, drain / vent valves etc. as per the installation standards, and shall have
accessibility.
(12) All primary piping / tubing (impulse lines) shall have a slope of 1 in 12 on the
horizontal run.
(13) All welding shall be carried out as per the relevant codes with proper electrodes. Any
testing (non-destructive) like D.P. test and radiography on root weld and final weld shall
be carried out as per PMS. All consumables shall be part of Contractor's scope of
supply. Any pre / post weld treatment as required by the relevant codes and piping
material specification shall be carried out. All non-destructive tests shall be carried out
as per piping material specification.
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 154 -
INSTRUMENTATION REQUIREMENTS
- 155 -
INSTRUMENTATION REQUIREMENTS
9.
9.1
GENERAL REQUIREMENTS
The Contractor shall design and provide AC power and backup power supply for the New
SCADA System and New Communication System equipment. The existing rated Power
supply is 230V single phase 2 wire, 50Hz.
Power supply rated for the SCADA equipment viz. HMI, Severs, Networks equipment etc. at
MCC & ACC shall be 230V AC, single phase, 2 wire, 50Hz. Existing UPS systems shall be
replaced and New 230V AC, 50Hz UPS systems shall be provided for this purpose.
Power supply system for RTUs at sites where AC mains power exist shall be 24V DC to be
derived from 230V AC, single phase, 2 wire mains supply and 24V DC backup battery &
battery charger system. Slave telemetry radio equipment and GPRS Modem to be installed
within RTU enclosure will be powered from the 24V DC system of RTU. Power supply
system to the RTU at sites where AC mains power do not exist shall be obtained from solar
panel. Diesel generator sets shall be provided at selected sites for emergency charging of
batteries.
Power supply for Communication system including Telemetering equipment at MCC & ACC
shall be 48V DC to be derived from 230V AC, single phase, 2 wire mains supply and 48V DC
backup battery & battery charger system. Telemetry equipment in Master Telemetry Station
(MTS) will be powered from 48V DC battery charger system. Portable standby Diesel
generator sets shall be provided at selected sites to meet complete power requirement of MTS
in emergency situation.
Power supply systems shall have adequate surge protection device to protect the downstream
equipment from excessive power swing which is normal with the mains power available and
severe climatic condition i.e. thunder storm and lightning in Bangladesh.
9.2
9.2.1
The Contractor shall install Uninterruptible Power Supply (UPS) systems at MCC and at
ACC to provide 8 hours backed-up power supply for the New SCADA and
Communication Systems and 4 hours backed-up power supply for building emergency
lighting in the event of a failure or outage of the incoming main AC power. The
capacity of the respective UPSs shall be 15 kVA (minimum) or more.
(2)
The Contractor shall install Uninterruptible Power Supply (UPS) systems at Demra
SCADA Office (old MCC) to provide 4 hours backed-up power supply for the New
SCADA and Communication Systems and 2 hours backed-up power supply for building
emergency lighting in the event of a failure or outage of the incoming main AC power.
The capacity of the respective UPSs shall be 10 kVA (minimum) or more.
(3)
Existing Power Distribution Panels (DP) shall be made available by the Employer, at
MCC, ACC and Demra SCADA Office Buildings, to provide incoming power supplies
to all the SCADA and Communication equipment to be installed at MCC, ACC and
Demra SCADA Office Buildings. All cabling including conduit / raceway / fittings /
glands / all other cables accessories from existing distribution panels to the
Contractors new distribution panels and all cabling from the new distribution panels to
- 156 -
each piece of SCADA & Communication equipment shall be designed and installed by
the Contractor.
9.2.2
RTUs
All Existing RTUs that are presently installed at Original Sites shall be replaced and New
RTUs shall be installed at that place. New RTUs shall be provided at all additional sites where
at present RTUs & associated Power supply systems are not installed. New power supply
arrangement shall be made for all new RTUs.
Necessary double insulated armored cable with MCB shall be provide to feed power from the
existing power source. MCB units shall be provided within RTU enclosure to provide power
to each piece of 15A power receptacle for maintenance works, Space heater & Thermostat,
Power modules of RTU, Slave radio / Modem of Telemetry system, GPRS Modem etc. Each
RTU including Future RTUs shall be provided with rechargeable battery and battery charger
system. Battery shall have adequate capacity to provide backed-up power at rated voltage and
current for at least 24 hrs. In the event of the battery voltage drops below a certain level, an
alarm signal shall be sent to MCC and ACC to protect batteries against over discharge.
Portable standby diesel generator sets shall be provided at some selected sites to cater
emergency charging of batteries for the sites where AC mains power is not available.
Power supply arrangement for RTUs shall be made as follows:
(1)
Power supply to the New RTUs at original sites where AC power exists:
Existing RTU is connected to AC power feeder (Single Phase, 230 V, 50Hz) of existing
power Distribution Panel (DP) located in a building. New RTU will be connected to
Contractors new power Distribution Panel (DP). Necessary MCBs and cabling from
existing DP to the new DP shall be installed. Existing Power supply cable from existing
DP to existing RTU shall normally be re-used at original site. Presently, these power
cables appear to be good. However, contractor shall verify himself about quality of the
cable by conducting tests such as Insulation, Continuity check etc. prior to its reuse. In
case of any defect found, the same cable shall be replaced by a new cable to be provided
by the Contractor.
(2)
Power supply to the New RTUs at the original site where AC power does not exist:
At present there is no AC mains power available at smaller site. Existing RTUs in the
sites are powered from the Solar Panels installed on the roof of RTUs sunshade.
Existing solar panels and solar controller along with associated cabling shall be replaced
with a new solar panels and solar charge/discharge controller & associated cabling. The
solar controller shall be equipped with necessary charging/discharging equipment for
24V DC backup battery system.
(3)
Power supply to the New RTUs at the Additional Site where AC power exists:
Moulded Case Circuit Breaker (MCB) Box shall be installed adjacent to the
existing DP installed in building at the Additional Site. Cabling from the existing
DP to the MCB Box and from the MCB Box to the New RTU shall be installed.
(4)
Power supply to the New RTUs at the Additional Site where AC power does not
exist:
- 157 -
Solar panels shall be installed on the roof of the new RTU shed. Solar controller
and cabling from the solar panel to the New RTU shall be installed. The solar
controller shall be equipped with necessary charging equipment for 24V DC
backup battery system.
9.2.3
9.2.4
Communications Equipment
(1)
(2)
(3)
- 158 -
according to the new supplied communication equipment and will have the capacity to
cater emergency power for a period of 24 hours in case of mains AC power fails. AC
Power supply will be derived from existing DB. Necessary double insulated armoured
cable (3 Phase,4 wire) with MCB shall be provide to feed power from the existing
power source. Required MCBs and cabling in between existing DB to Contractors DB
and to Telecommunication panels will be supplied and installed by the Contractor.
9.3
TECHNICAL SPECIFICATIONS
9.3.1
Uninterruptible Power Supply (UPS) for MCC & ACC and Demra SCADA Office
(1)
General
The capacity of each UPS shall be designed by the Contractor based on the proposed
equipment's power consumption. The UPS shall be manufactured in accordance with
IEC or equivalent standards as below.
Uninterruptible power systems (UPS) - Part 1: General and safety requirements for UPS.
Uninterruptible power systems (UPS) - Part 2: Electromagnetic compatibility (EMC)
requirements.
Uninterruptible power systems (UPS) - Part 3: Method of specifying the performance
and test requirements
UPS shall be configured in parallel redundant configuration.
(2)
Components of UPS
The UPS system shall comprise the following major components:
(3)
a)
Battery charger
b)
Static inverter
c)
Bypass switch
d)
Battery
e)
Rating
Output
Nominal Output Voltage
Capacity
Efficiency
Recovery time
Audible noise
< 65dBA
- 159 -
Enclosure
Cooling
Input Voltage
Frequency
:
:
Power factor
Input
(4)
Battery Charger
a)
The battery charger shall be automatic solid state type, capable of rated output
with an input voltage tolerance of+10% to -15% and input frequency 10%.
b)
c)
Voltage regulation :
1%
d)
Ripple
1% (without batteries)
2% (with batteries)
(5)
Static Inverter
The inverter shall be solid state static type, capable of supplying full load, continuously
with overload capability, performance characteristics shown below are for 0 to 100%
load at 80% power factor, and for input variations from battery discharged value to
charger maximum output value:
(6)
a)
Voltage regulation
b)
Frequency regulation
c)
Wave shape
:
possible operating conditions.
d)
Efficiency
e)
Power factor
Bypass Switch
a)
Static bypass switch shall be solid state type and provide no-break transfer of AC
loads from the inverter to the alternative supply (in <4 msec in synch. mode) and
back to the inverter, and have performance characteristics equal to those of the
inverter.
- 160 -
b)
(7)
A manual bypass switch (make before break) shall be provided and be mounted in
the same cubicle/section as the static switch to allow manual transfer in the event
of maintenance or failure of equipment.
Batteries
a)
b)
The battery capacity shall be 20% in excess of what is required to achieve the
specified emergency discharge duty.
c)
The battery back-up power supply duration is 8 hours for SCADA and
Communication Systems and 4 hours for building emergency lighting.
(8)
(9)
LCD display shall be provided on the panel for the followings metering and alarm
annunciation:
Electrical Parameters as follows:
Voltage
Input
Alternate
Battery
Inverter
Load
Current
Frequency
Input
Alternate
Battery Charging /
Discharging
Inverter
Load
Input
Alternate
X
Inverter
Load
Battery
Inverter
Overvoltage
Discharging
Overload
Under
voltage
End of
Discharge
Low battery
Under
Voltage
Alternate
Static
Switch
Over voltage Transfer to
Alternate
Under
Voltage
Frequency
out of Limit
System
Service mode
Access
DC Ground
In addition to above at least following alarm shall be generated during UPS fault:
DC Overvoltage, Inverter Over-voltage, Inverter Overload Trip, CPU fault, OverTemperature etc.
All alarms shall be with audible and flashing display. A common alarm contact O/P
shall be provided for remote alarm in SCADA.
9.3.2
Backup Battery
- 161 -
(1)
(2)
General
a)
The Contractor shall provide battery backup for all RTUs and Master Telemetry
Stations (MTS) and Service Providers Access Point. Nominal battery voltage will
be DC 24V for RTUs and DC 48V for MTS and Service Providers Access Point
respectively.
b)
The backup duration of the batteries for the RTU and Providers Base station is 24
hours. The backup duration of the batteries for the Master Telemetry Station 48
hours. The Contractor shall design the capacity (kVA) of the batteries based on
the power consumption of the relevant equipment.
c)
The batteries for the RTUs shall be housed within RTUs Enclosures and the
batteries for the Master Telemetry Stations shall be mounted on a steel rack. The
steel rack shall be epoxy painted to resist the corrosive properties of the
electrolyte.
d)
Batteries and chargers shall be complete with control panels. The battery charger
panel shall incorporate an input switch and an output switch to allow the charger
to be readily isolated for maintenance.
Batteries
b.
c.
d.
(3)
For MTS: Maintenance free Nickel cadmium high performance stationary type
batteries shall be employed and the guaranteed life of battery shall be a minimum
of 15 years.
For RTU:and Service Providers Access Point ,Maintenance free sealed lead acid
high performance stationary type shall be used and the guaranteed life of each
batteries 10 years.
The battery capacity shall be 20% in excess of what is required to achieve the
specified emergency discharge duty.
Battery Charger
a)
The charger shall be suitable for supplying the initial charging requirements, boost
charging a battery subsequent to an emergency discharge, supplying the
maximum DC load during float charging of both batteries and providing 20%
spare capacity.
b)
DC output shall be suitable for DC24 / 48V nominal load voltage with float and
boost charging.
c)
d)
The charger shall be provided with protection devices such as over-voltage and
under-voltage cut relays to protect the equipment against fluctuation in voltage.
e)
f)
Charger shall have voltage regulation (Float mode) of 1% with supply voltage
variation of 10%.
g)
- 162 -
h)
9.3.3
Solar Panels
(2)
General
Solar panels are to be installed in a very limited space (on the roof of the RTU
shed). The Contractor shall design a solar panel that has the smallest solar panel
footprint.
(3)
a)
The solar panel shall be of a durable construction and designed for use in a
tropical environment.
b)
The Contractor shall design the exact number of solar panels required based on
the solar radiation of Bangladesh and required power consumption of the
equipment in the RTU to keep continuous operation of the RTU. Regarding
tentative battery capacity, 24 hours as specified, the Contractor shall design the
specified capacity based on the solar panel output and power consumption. All
calculation data shall be submitted to the Engineer prior to install the equipment.
b)
The charging and discharging controller shall be provided with an AC 230V input
terminal for boost charge of the battery. The boost charge will be carried out by
using a portable type AC 230 V generator.
Common remote alarm shall be provided.
9.3.4
Output
Nominal Output Voltage
- 163 -
Output Frequency
Input Voltage
Input Frequency
50 Hz 10%
Surge Protection
to be provided
(3)
Capacity
(4)
Battery
(5)
Unattended shutdown
(2)
Input
9.3.6
Emergency Generator
a)
Frequency
50 Hz
b)
Output
15 kVA
c)
Rated Voltage
d)
Power Factor
0.8 (lagging)
e)
Voltage Regulation
f)
Excitation
g)
Engine
h)
Panel
4 sets of emergency generators shall be provided and will be kept at the selected Master
Telemetry Stations.
- 164 -
9.3.7
Frequency
50Hz
b)
Output
l kVA
c)
Rated Voltage
7 sets of generators shall be provided and will be kept at the Master Telemetry Stations
monitoring RTUs without AC power supply.
9.3.8
MCB Box
The Contractor shall provide a MCB Box for feeding AC 230V to the New RTU.
9.3.9
a)
Rated MCB
required
2 pole 50 A / 20 A as
b)
Box
Cables
(1)
General
The cables shall be flame retardant low smoke cable and shall have copper conductors
with minimum cross section area shall be as follows:
(2)
a)
Power Cable
: 2.5 mm
b)
Control Cable
: 1.5 mm
c)
Instrumentation cable
: 1.0 mm
b)
Conductor
c)
Insulation
d)
Core Identification
e)
Inner Sheath
f)
Armour
- 165 -
g)
Overall Sheath
Cables laid directly in the ground shall have the following depth of cover:
a)
Power cable
500 mm
b)
Control cable
500 mm
Cables shall be installed correctly spaced in the trench. Pipe sleeves shall be provided at
cross-overs like roads, drains etc. and relevant drawings shall be approved by Engineerin-charge. Before laying of cable, the trench bottom shall be filled with 100 mm layer of
sand and leveled. Each layer of cables shall be covered with 150 mm of sand on top and
sand shall be lightly pressed. A protective covering of 75 mm thick second class red
bricks shall be placed flat on the final layer of sand. The remaining portion of the trench
shall be then back filled with soil compacted and leveled. On completion of every group
/ layer of cable laying and before sand filling, every cable shall be given insulation test
and test result shall be certified by Engineer-in-charge. Any cable proved to be defective
shall be replaced before the next group of cables is laid. Pipe sleeves shall be made of
Galvanized Iron. Free space of 40% shall be provided in pipe sleeves.
Cable route markers at every 20 meter interval, indicating number of cables, depth and
direction, shall be provided to identify the buried route including crossovers / turnings
etc.
Cable tags shall be provided on each cable at every 5 meter interval. Tags shall also be
provided at each end of road crossing, turning, bridge etc.
(2)
Cable Tray
a)
All tray work and accessories shall be heavy duty and sized to provide 25%
additional free space.
b)
The minimum clearance behind the tray shall be sufficient to allow for fixing of
cables, which shall relate to tray width, but shall not be less than 25 mm.
c)
The galvanized cable tray shall be perforated, heavy-duty return flange type, hot
dipped galvanized after manufacturing. All cut ends shall be made good to equal
protection as uncut lengths, using "galvanized" paints. It shall be used at all sites
except for gas field sites.
d)
The plastic coated cable tray shall be diamond pattern, and covered with heavy
duty, black PVC. It shall only be used where, for reasons of corrosion, galvanized
tray work is impracticable. It shall generally be used at gas field sites which are
generally corrosive areas.
e)
Stainless steel tray shall generally be used inside the buildings such as in Master
Control Centre, Auxiliary Control Centre, Operating Company Terminals and
Control Centre at Dhaka etc. for durable, corrosion free, aesthetic view.
- 166 -
f)
(3)
The rigid PVC cable tray shall be manufactured from rigid un-plasticized PVC
having a thickness of not less than 3 mm. It shall be perforated and have provision
for a cover. The manufacturing material shall be self-extinguishing and nonflammable and suitable for use in ambient temperatures of 00C to 800C.
Conduit
a)
The steel conduit shall be heavy duty, welded, screwed and galvanized to Class 4
of the relevant British Standard.
b)
c)
d)
They shall be securely fixed by means of distance saddles not more than 400 mm
apart. 6 mm clearance between the conduit and the building wall shall be
maintained to avoid accumulation of dust.
All new power cables from the existing distribution board to the MCB Box and the
MCB Box to the New RTU shall be of 3 cores (Live, Neutral and Earth). The earth core
shall be terminated at the SCADA earth star point.
(2)
All equipment enclosures to which an electrical power supply is connected shall have a
main earth connection point suitable for a 10 mm2 wire. The exposed metal cases of all
electrical apparatus shall be connected to the SCADA earth star point unless the
apparatus is nearer to the system earth point, in which case the connection shall be
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 167 -
directly to the system earth point. The protective and non-live metal work of the panel
shall have a maximum resistance not exceeding 10 milliohms to the SCADA earth star
point. An earth cable shall then be taken from the SCADA star point earth to the system
earth point within the building containing the SCADA equipment. The maximum
resistance between the SCADA star point earth and the system earth shall not exceed 10
milliohms.
(3)
All equipment to be earthed shall be connected to the SCADA earth star point using
green/yellow PVC insulated cable of the appropriate size.
(4)
The steel wire armored power cable shall not be used as the earthing conductor.
(5)
Equipment shall not be earthed to its chassis but shall have the earth points brought to
an insulated point from which the connection to a special logic earth can be made.
(6)
Provision shall be made for the termination of signal screens, or to maintain the
continuity of isolated screens as required.
(7)
(8)
(9)
All towers shall be earthed in accordance with international standard and earthing
resistance measured less than 01 ohm.
9.4
(1)
A steel wire armored (SWA) cable shall be terminated by using a cable gland. The cable
gland shall be suitable for the environment in which they are to be used, and shall be
complete with PVC shrouds, back nuts and bonded earth tags. Generally cable gland
shall have protection of IP-65.
(2)
(3)
Instrument cable cores and internal connection cores shall be terminated with polyamide
type terminals, having socket screw clamp connections with a knife-edge switch
disconnection.
- 168 -
The Contractor shall supply and install the power cables, circuit breakers etc. from the
existing substation to Battery Room at MCC, ACC and Demra SCADA Office.
The Contractor shall supply and install the power cables, circuit breakers etc. from the
existing DB to MTS.
Power cables sizing shall be as under .
a. MCC at Agargaon, Dhaka: 4x150 sq. mm approximately 300 ft.
b. ACC at Ashuganj:
d. MTS locations:
Dismantling of existing electrical wiring and electrification system shall be under the scope of
the Contractor.
9.4.1
9.4.2
9.4.3
Samples
a) Samples of conduit, cables, bends, socket outlets, fans, luminaries, switched sockets,
steel installation boxes, various fittings, etc, shall be submitted to the Employer for
his approval prior to use. Materials actually used in the work shall conform to such
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 169 -
approved sample.
9.4.4
Progress of Work
a) The Contractor shall be responsible for completion of all electrical works before the
building finishing work. Fitting of conduit pipe and recessed boards shall be done
before plastering.
9.5
Material Specification
9.5.1
PVC Conduit
a) PVC conduit shall conform to NEMA TC-2 and WL 651 designed for installation
underground in slabs, encases or exposed. PVC Conduit shall not be threaded. There
shall be no taper to the conduit unless one end is formed as a fitting and is especially
suitable for the purpose. The material shall be such that when bends are formed, the
conduit shall not break, crack or be deformed. Limits on the wall thickness and
diameter of PVC conduits shall be as below:
9.5.2
Nominal
Size (mm)
Outside
Diameter (mm)
Inside
Diameter (mm)
Wall
Thickness
(mm)
Pipe Weight
(kg)
12.7
21.54
16.00
2.77
0.238
19.1
26.92
21.18
2.87
0.327
25.4
33.66
26.90
3.38
0.476
38.1
48.56
41.20
3.68
0.774
50.8
60.63
52.81
3.91
1.027
Nominal Size
(mm)
Outside
Diameter
(mm)
Inside
Diameter
(mm)
Wall
Thickness
(mm)
Pipe
Weight
(kg)
25.4
33.66
26.90
3.38
2.50
- 170 -
9.5.3
38.1
48.56
41.20
3.68
4.05
50.8
60.63
52.81
3.91
5.44
63.5
73.03
65.25
5.16
8.63
76.2
88.90
77.93
5.49
11.29
9.5.4
- 171 -
Diameter of Conduit
(mm)
9.5.5
19.05
114.30
38.10
25.40
146.05
47.62
31.75
184.15
50.80
38.10
209.55
50.80
50.80
241.30
50.80
63.50
266.70
76.20
76.20
330.20
79.38
Locknuts
Conduit Size
(mm)
Thickness
(mm)
Outside Diameter
(mm)
No. of Threads
19.05
26.99
25.58
25.40
30.16
31.75
Conduit Size
(mm)
Thickness
(mm)
Outside Diameter
(mm)
No. of Threads
19.05
22.23
8.73
25.40
28.58
10.72
Bushes
- 172 -
9.5.6
9.5.7
Cable work
a) The cable distribution from bus bar to switch boards through different stages are
furnished as under:
9.5.8
i)
ii)
4X25 sq.mm
iii)
4X16 sq.mm
iv)
10 sq.mm
4X35 sq.mm
Material specification
a) Single Core Electrical Cable and Conductor
i)
Single-core low voltage cables and conductors shall be as per BS 600, or BS 6346
(1977), or equivalent VDE specifications, of copper conductor, and PVC
insulated. Conductors shall have 600/1000 volt grade of PVC insulation. All sizes
over 2.5 sq. mm shall be stranded.
ii)
All flexible cables shall be as per BS 6004 (1975) unless otherwise specified.
Multi-core low voltage cables shall be PVC insulated PVC sheathed nonarmoured direct burial type, termite proof, made and tested according to VDE
0472/6.65 and VDE 0472/3.69 for this type of installation, rated voltage being
600/1000 volts.
- 173 -
i)
The subscriber cables shall be suitable for earth laying and shall be made
according to VDE 0816, of 0.6 sq. mm/0.8 sq. mm (as applicable) copper
conductors, with PE (Polyethylene) insulated and laminated PE sheathed, starquad formation, basic unit stranding and core wrapping.
ii)
The cables shall be tested (at 20C) for voltage not less than 500 volts (RMS)
wire to wire and 2000 volts (RMS) wire to shield with operating voltage of 150
volts (RMS), shall have minimum insulation resistance (tested with min. 100 volt
DC) of 500 mega ohm/km, and mutual capacitance of not more than 50 Farad/km
for both 0.6 sq. mm and 0.8 sq. mm.
d) Cable Colour
i)
ii) All cables used shall be coloured as per the following table:
CONDUCTOR
Phase/Switch
Neutral
Three Wire
Two Phase AC
System
3 or 4 Wire Three
Phase AC System
Two Wire DC
System
Red
Black
Common Return
Black
Black
Negative
Earth
Black
Green / Yellow Striped
e) Earth Trench
i) The size of the trench shall be of minimum 650 mm depth and 450 mm width for
HV incoming cable and of 400 mm depth and 200 mm width for telephone
incoming cable.
ii) A 150 mm thick cushion of sand of FM 1.6 is to be placed over bed of the trench
over which cables are to be laid. After laying of cable first class brick on edge of
flat are to be placed as separators in between the cables. After placement of brick
separators, sand filling is to be done up to 150 mm from the top of the bigger cable.
Then two layers of first class brick flats are to be placed along the length and
breadth of the trench as a protection against injury and indications that a power
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 174 -
cable is laid. The rest of the trench shall be filled with earth, watered and rammed
at 150 mm layers. After cables are laid the original ground conditions shall be
restored. But if brick pavement drain, concrete road or bituminous carpeted road
are cut across or damaged, they shall be remedied and restored to the original
specification.
f) Concrete Trench
i) Trench for running cables shall be made of concrete (1:2:4) base and first class
brick walls (1:4) with inside plastering (1:4) including neat cement finishing and as
per dimension shown in the drawings. Trench shall be constructed with a slope of
about 1:600 starting from some midpoint of the trench for disposal of sewage, if
any, at out side the building including taking proper care for final disposal of
sewage. Specification for materials and construction for trench shall be the same as
provided for similar works in the specification of civil works.
ii) Trench shall have cover with slip resisting checked steel plates of minimum 13 mm
inch thickness and non-corrosive surface. Cover plates shall be of stiffened type to
have sufficient strength to take care of vehicle load. Cover plates shall be placed in
such a way that those can easily be opened and surface level remains in the same
plane of the floor having smooth finishing.
9.5.9
Cable Laying
a) The cable route shall be as direct as possible and shall receive the Employers
Representative's approval before excavation.
b) All cables bends shall have a radius of not less than 2 times diameter of the cable
drum, or 25 times the diameter of the cable, whichever is greater.
c) GI pipes shall be provided for all road and drain crossing. These pipes shall be laid
direct in the ground without any sand bed, sand layer, brick or cable covers.
d) Cables shall always be laid out or laid into the ground through GI pipe of size as
indicated in the drawing or as decided by the Employer. The length of the pipes over
the ground shall not be less than 1200 mm. The exposed end of the pipes shall be
sealed using PVC or wooden plugs.
e) Great care is to be exercised in handling the cable and avoid forming kinks. The cable
drum shall preferably be conveyed on wheeled cable drum carried and unrolled and
laid directly from the drum carrier. Carriage by trailer or trucks can be allowed only if
proper care is taken during unloading the drums, and unrolling is done after placing
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 175 -
the drum on drum-jacks and spindle. The cables shall be unrolled in the direction
indicated on the drum by the manufacturer.
f) A cable marker on GI plate shall be installed at every control point of the trench.
g) After the cable is laid, it shall be tested in presence of the Employer. If the test is
unsatisfactory, the cable shall be repaired/replaced as decided by the Employer.
h) All the surplus earth shall be removed to the indicated place. Any damage done to any
other services for the cable laying operation shall be made good.
i)
Insulation Test
j)
Insulation test of the whole installation shall be carried out using 1000 volt megger, in
presence of and to the approval of the Employer.
k) Traywork
l)
All traywork and accessories shall be heavy duty and sized to provide 25% additional
free space above that required for the Contract.
m) The minimum clearance behind the tray shall be sufficient to allow for fixing of
cables, which will relate to tray width, but shall not be less than 25 mm.
n) At structural expansion joints, tray runs shall be broken with joints bridged and
bonded with a flexible earth continuity conductor capable of absorbing all movement
without strain.
o) Galvanised cable tray shall be perforated, heavy duty return flange type, hot dipped
galvanised after manufacture.
- 176 -
a) Where trunking is specified it shall be constructed from zinc coated mild steel with a
minimum thickness for the steel of 1.65 mm. It shall have a removable cover
throughout its length with centre screw latch fixings. Trunking shall be rigidly fixed
and supplied complete with purpose manufactured fittings, connectors, dividers,
flanges, cable retaining clips, racks and copper earth continuity links.
b) As an alternative, if approved, a proprietary brand of heavy duty plastic trunking may
be acceptable. When submitting details for approval, full installation instructions as
recommended by the manufacture shall be included in the details.
c) All cables installed in trunking shall be labelled and identified in an approved
manner. Clips shall be at 600 mm centres. Vertical cable trunking shall be fitted with
cable pin racks arranged to avoid any strain on the cables.
d) All metal trunking shall be rust proofed, primed and painted and fixed at intervals not
greater than 1.0 metre.
e) All trunking shall be suitably earthed.
9.5.11 EARTH CONTINUITY CONDUCTOR
1)
Material Specification
Earth continuity conductors shall be electrolytic annealed copper of 100 percent
conductivity at 20C, International Annealed Copper Standard (IACS), with weight
resistivity of 0.15328 ohm-gram/m2 at 20C and density of 5.746 gram/m3, for meeting
requirements of BS 6360:1969 or its metric adoption.
2)
Installation
The earth continuity conductor and earthing lead shall be run in accordance with the
drawings and direction, and all metal fittings shall be earthed with continuity conductors.
All the earth continuity conductors from the various circuit, sockets, etc. shall be
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 177 -
connected to the earthing block located near the CDB/MDB/DB/SDB. Sizes of the earth
continuity conductors shall be as stated in drawings. All CDB/MDB/DB/SDB/ESDB
shall be inter-connected with earth continuity conductor. The earth continuity conductor
shall be drawn along with the cables and no joints shall be allowed from earthing block to
the respective earth point. Light and fan points, except where indicated, shall not be
earthed.
9.5.12 LIGHT FITTINGS
1)
Material Specification
a) The light fitting shall be constructed as per schedule, and shall comply with the
relevant requirements of applicable BS including BS 4533 or VDE 0710.
b) The chokes, if applicable, shall comply with the requirement of BS 2818 or VDE
0712, and shall have appropriate power factor correction capacitor 220 volts, 3.0
micro Farad for 20 watt and 40 watt tubes, 7 micro Farad for 65 watt tubes, and 8
micro Farad for 80 watt tubes.
c) The starter shall be 91 watt lamp type and shall have built-in radio interference
suppresser capacitor.
d) All incandescent light fittings, except where specifically stated otherwise, shall have
un-switched brass holder for BS 22/25 x 26 lamp caps complying with BS 52:1963
(1978).
e) Appropriate sample of light fittings with chokes and starter (if any) shall be submitted
prior to installation.
- 178 -
Material Specification
a) Distribution Board shall be as per drawings shall be safely dead-front fixed type
having circuit breakers and isolators. The Distribution Board shall have three
phase/single phase energy meter, ammeter and voltmeter with phase selector switch,
on/off indicating lamp. The meters shall be installed in a separate compartment in the
Distribution Board and provision shall be made such that the meters can be read
directly without opening the front cover of the boards by providing glass/transparent
perplex covering on the meter opening or by installing the meter scales flushed with
the door. Panels shall be designed for operation on a 220/400 volts 50 Hz 3 phase 4
wire system. Breakers shall have inverse time tripping with thermal magnetic trip
elements.
b) All circuit breakers shall be trip-free and shall be of the indicating type. The panels
shall have the phase clearly marked, and where required, shall have solid neutral
buses. The panels shall be constructed as per schedule, and shall comply with relevant
requirements of BS including BS 4649 or VDE 0100, where applicable, and would be
painted with 2 (two) coats of grey Duco, with standard concentric knockouts of
required sizes all round. The panels shall have directory frames and printed directory
on/in side of door. The door is to be provided with flush lock and handle. All doors
are to be keyed alike. All hinges shall be concealed.
c) The MCB/MCCBs shall be quick-make, quick-break type, and shall have inverse
time limit characteristics with instantaneous magnetic trip elements functioning on
overloads above the normal operating range. All circuit breakers shall be trip-free.
Ratings and frame sizes of breakers shall be in accordance with schedule. All lugs
shall be of the solderless mechanical type.
d) The miniature circuit breakers shall comply with BS 3871 Part 1 (1965) category M4
(5A-60A) or VDE 0660 with rated voltage 220/400 AC 50 Hz interrupting capacity
4000 amps, capable of providing overload and short circuit protection through
thermal and magnetic trip actions respectively; temperature rating, 40 degrees C,
tropicalised (moisture, fungus, corrosion treated), with contacts of silver alloy.
e) The MCCB shall comply with BS 3871 Part 2 (1966) or VDE 0660 with rated voltage
of 600 V AC 50 Hz with magnetic tripping action; interrupting capacity as indicated
in the schedule, temperature rating 40C, tropicalised (moisture, fungus, corrosion
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 179 -
treated).
f) The busbar shall be of copper having the rating as per schedule of items and the
unrestricted short circuit current of 25 kA at 0.25 PF for 1 sec.
9.5.15 SWITCH BOARD
1)
Material Specification
a) Switch boards and fan regulators box shall be as per drawing and shall have
rocker/piano switches. The rocker/ piano switches shall be vertical single pole (1 way
or 2 way) 6 amps AC architrave rocker/piano operated switches white in colour,
complying to BS 3676:1963 and the test requirement for inductive, fluorescent or
resistive loads specified, and satisfy the best requirements of the circuits or three
types in fluorescent lamp circuits, up to the ratings or these switches, as set out in BS
3676 amendment 3:1969. The switches shall have a minimum clearance of 3 mm
between the contacts, and a similar minimum creepage distance. All contacts shall be
faced with pure silver or silver cadmium oxide alloy. The switch operating member
shall pivot independently of the rocker, making the speed make and break
independent of the speed at which the rocker is operated. Terminal capability shall be
minimum 2 x 2.5 mm2 conductors for each end. Appropriate sample shall be
submitted prior to installation of switches.
b) Each board shall have an earthing block of copper/brass of size 50 x 10 x 10 mm with
8 x 5 mm drilled holes and 8 x 3 mm machine screw tapped hole for 10 threads per
cm. The box of switch boards shall be made of 16 SWG sheet steel and shall be
painted with three coats of approved anti-corrosive grey paint. Box ears shall be at
least 14 SWG for connecting ground wires.
Material Specification
a) All socket outlets, except the shaver sockets, shall be 13 A, 3 square pin type, double,
switched, white in colour, conforming to British Standard. The socket shall be self
adjusting for pitch with non expanding size limiting entry to protect the internal
contacts from distortion. All sockets and switches (where applicable) shall have silver
or silver cadmium oxide alloy contacts in which contact pressure shall be
permanently maintained by subsidiary helical compression springs. All mouldings
shall be made of aminoplastic urea moulding powders to BS 1322:1956 and shall
possess high track resisting qualities. These shall be supplied with countersunk
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 180 -
cadmium plated fixing screws and mounted in 16 SWG hammer painted sheet steel
box having brass earth point as per drawing and direction.
b) The controlled sockets of MCB/MCCB, if applicable, shall be unswitched and the
box shall have earth point.
9.5.17 LIGHTNING PROTECTION
1)
Material Specification
a) Air Terminal/Surge Diverter
Air terminal shall be of copper of grade required for commercial electrical works,
generally designate as being of 98 per cent conductivity when annealed. The Air
Terminal shall be 1.0 metre long 19 mm copper solid rod electroplated 3 mm thick
pointed at upper end and threaded and welded at lower end along with base plate of
size 150 x 100 x 13 mm. The terminal shall be spot welded at the base.
b) Roof Conductor
Roof conductor shall be made of copper of 98% conductivity commercial grade and
of size 16 mm2 unless otherwise specified in the drawing as indicated in the drawing
and schedule.
c) Down Lead
Down earthing lead from roof shall consist of copper conductor, bare stranded of size
16 mm2 (6 SWG). All terminal lugs shall be copper and nut-bolts of brass. Down
earth lead will take the shortest route to the mesh point as shown in the drawing and
shall be plaster covered. The other end of the copper shall be welded with the
grounding network by means of welding.
d) Test Point
The test point shall be made as per schedule and detail drawing. The conductor
terminals shall be provided with copper lugs of size as detailed in the schedule and
drawings.
- 181 -
- 182 -
9.6.1
General
a) The earthing of all equipment shall be in accordance with the IEE Recommendation
No. 80:1976 - Guide for Safety in Alternating Current Sub-station Grounding, the
British Standard Code for Practice CP 1013:1965 or other approved standard.
b) The Contract includes the provision of materials and installation of the complete
substation earthing system, including the earth connections of all equipment supplied
under this Contract, earth connections to panels and any other auxiliary equipment,
commissioning and testing of the earthing system.
c) The Contractor shall prepare installation drawings and schedules of material to be
provided for the earthing system. These shall include calculations of resistance,
potentials and current rating for current flowing into or out of the ground. Stop and
touch voltages both inside and outside the station shall not exceed 110 V. These
drawings and schedules shall be submitted to the Employers Representative for
approval together with calculations of step, touch and mesh potentials.
9.6.2
Earthing System
a) The earthing system shall be based on soil resistivity of 1 ohm-metre for wet soil and
10 ohm-metre for dry soil.
b) Earthing points shall be provided such that the combined resistance of the earth
network and earthing points does not exceed 1.0 ohm under any climatic conditions.
c) The operating mechanisms of isolators, earth switches and circuit breaker kiosks not
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 183 -
integral with the circuit breaker shall be connected to the earth system by a branch
entirely separate from that employed to earth their bases. The bench is to be installed
such that the connection would pass beneath where an operator would stand, so as to
minimise step potential.
d) Connections to plant and equipment shall be made using the earthing terminals
specified in the Contract. Where a strip has to be drilled to fit an earth terminals, the
diameter of the hole shall not be greater than half the width of the strip.
e) Joints in earthing strip shall employ chemical welding or high compression joints of
clamps.
9.6.3
9.6.4
Earthing Block
a) The earthing block shall be of solid electrolytic copper, cast and machined, of size as
per schedule, having at least 15 Nos. 6.35 mm dia. drilled holes for accommodating
the terminal of the earth continuity conductor. Requisite number of brass nuts and
bolts shall also be provided.
9.6.5
9.6.6
Earth Electrode
a) Pipe Electrode
- 184 -
i) Where applicable, the pipe earth electrode shall be buried below ground level, as
per schedule, by tube-wall sinking method. the earthing lead from the substation to
the main earth electrode shall be installed in GI pipe of specified diameter. The
terminal connected to the earth electrode shall use a brass clamp. After making the
connection, the clamp shall be covered with bitumen poured hot and covered with
jute cloth.
b) Plate Electrode
i) Where applicable, the plate earth electrode shall be buried below ground level as
per schedule and installed in an upright position and completely surrounded by a
bed of at least one foot of charcoal mixed with sodium chloride salt, lime and
packed hard as per drawing. Distance between any two earth electrodes shall be at
least 7.62 m or as per direction of the Employer.
c) Earthing Leads
i) The earthing leads from the earth electrode shall be connected to the earthing block
HT and LT panels. A double run of specified copper conductor shall be brought out
as earth lead for the earth electrode through GI pipe from the electrode and
connected to the earth blocks. There shall be no joint in the copper earth lead. All
earthing lead shall follow the shortest and most direct route to earth electrode and
sharp bends and joints shall be avoided. The earthing leads shall be connected to
the earth electrode as per drawings. The joints shall be made mechanically strong
and electrically continuous with minimum of resistance.
9.6.7
- 185 -
9.7
Control Panel
9.7.1
Construction
a) The panel shall be suitable for installation in a non air conditioned concrete block
built or pre-fabricated switch room in the ambient conditions stated and being
protected to IP42/BS5420 (IEC 144).
b) The panel may be standing alone, an addition or extension to or part of the main LV
switchboard/MCC at the discretion of the Contractor.
c) In either case responsibility for ensuring overall continuity and compatibility of
ratings, size, layout style, finish, standards etc. shall rest with the Contractor.
9.7.2
(ii)
(iii)
(iv)
(v)
(vi)
Alarm Annunciator System, of the new signal/new alarm type with separate
first failure indication.
(ii)
(iii)
Voltmeter for battery voltage (If not fitted on a separate charging unit).
(iv)
- 186 -
(v)
(vi)
(vii)
(viii)
(ix)
Push buttons (The start push button to be functional only when the control
selector switch is at the manual position.)
9.7.4
Contactor Open
(Red)
Contactor Closed
(Green)
Increase Speed
(White)
Decrease Speed
(White)
Start
(White)
Stop
(White)
Sequence Reset
(White)
Lockout Reset
(White)
Check Alarm
(White)
Lamp Test
(White)
(White)
(White)
(White)
(White)
(White)
h) Charging Fail
i)
Push buttons and lamp indicators may be combined together where appropriate (eg.
Check Alarm/Alarms Checked).
9.7.5
- 187 -
b) Emergency engine and generator shutdown from alarms as specified shall activate
engine lock out and generator circuit breaker trip.
c) Monitoring and control relays as necessary.
9.7.6
Overall Testing
a) The complete system including gas engine driven generators control panel shall
undergo a combined performance and functional test at the suppliers works. Such
tests will be witnessed by the Employer and the Contractor shall give a minimum of
two weeks notice of the impending test date.
9.8
INSPECTION
9.8.1
General
a) Every installation shall, on completion and before being energised or commissioned,
be inspected and tested in accordance with the requirements of IEE Wiring
Regulations 611 to 614 to verify, as far as practicable, that the requirements of these
regulations have been made.
b) The methods of test shall be such that no danger to persons or property or damage to
equipment can occur even if the circuit tested is defective.
9.8.2
Visual Inspection
a) An inspection shall be made to verify that the installed electrical equipment is:
(i)
(ii)
(iii)
TESTING
9.9.1
General
a) The following items, where relevant, shall be tested in the sequence indicated whether
or not mentioned in any part of the specification of installation and sub-station and in
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 188 -
(ii)
(iii)
(iv)
Insulation Resistance.
(v)
(vi)
(vii)
(viii)
(ix)
Polarity.
(x)
(xi)
(xii)
b) In the event of any test indicating failure to comply, that test and those preceding, the
results of which may have been influenced by the fault indicated, shall be repeated
after the fault has been rectified.
9.9.2
9.9.3
9.9.4
9.9.5
Insulation Resistance
1)
The tests described in regulations 613-6 to 613-8 shall be made before the installation is
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 189 -
permanently connected to the supply. For these tests installations may be divided into
groups of outlets, each containing not less than 50 outlets. For the purpose of this
regulation the term outlet includes every point and every switch except that a socket
outlet, appliance or luminaries incorporating a switch as an outlet. A DC voltage not less
than twice the nominal voltage of the circuit concerned (RMS value for an AC supply)
shall be applied for the measurement of insulation resistance, provided that the test
voltage need not exceed 500 volts DC for installation rated up to 500 volts, or 1000 volts
DC for installation rated above 500 V up to 1000 V.
2)
When measured with all fuse links in place, all switches (including, if practicable, the
main switch) closed and, except the TN-C system, all poles or phases of the wiring
electrically connected together, the insulation resistance to Earth shall be not less than 1
mega ohms.
3)
When measured between all the conductors connected to any one phase or pole of the
supply and, in turn, all conductors connected to each other phase or pole, the insulation
resistance shall not less than 1 mega ohm. Where practicable, so that all parts of the
wiring may be tested, all lamps shall be removed and all current using equipment shall be
disconnected and all local switches controlling lamp or other equipment shall be closed.
Where the removal of lamps and/or the disconnection of current using equip is
impracticable, the local switches controlling such lamps and/or equipment shall be open.
Particular attention shall be given to the presence of electronic devices connected in the
installation and such devices shall be isolated so that they are not damaged by the test
voltage.
4)
Where equipment is disconnected for the tests prescribed in regulations 613-6 and 613-7,
and the equipment has exposed conductive parts required by these regulations to be
connected to protective conductors, the insulation resistance between the exposed
conductive parts and all live parts of the equipment shall be measured separately and
shall comply with the requirements of the appropriate British Standard for the equipment.
If there is no appropriate BS the insulation resistance shall be not less than 0.5 mega
ohm.
9.9.6
- 190 -
voltage test equivalent to that specified in the BS for similar factory built equipment.
Where protection against indirect contact is provided by supplementary insulation applied
to equipment during erection in accordance with regulation 413-18 to 413-26, it shall be
verified by test that the insulating enclosure affords a degree of protection not less than
IP2X (BS 5490), and that the insulating enclosure is capable of withstanding, without
breakdown or flash over, an applied voltage test equivalent to that specified in the BS for
similar factory built equipment.
9.9.7
9.9.8
9.9.9
- 191 -
intended to comply with Regulations 413-27 to 413-31 and 471-19, the resistance of the
floors and walls of the location to the main protective conductor of the installation shall
be measured at not less than three points on each relevant surface, one of which shall not
less than 1m and not more than 1.2m from any extraneous conductive part in the location.
Any insulation or insulating arrangement of extraneous conductive parts intended to
satisfy Regulation 413-31(a) item (iii) shall be able to withstand a test voltage of at least 2
kV, and shall not pass a leakage current exceeding 1 milli-amperes in normal condition of
use.
9.9.10 Polarity
A test of polarity shall be made and it shall be verified that all fuses and single pole
control devices are connected in the phase conductor only, that centre-contact bayonets
and Eddison type screw lamp holders in circuits having an earthed neutral conductor have
their outer or screwed contacts connected to that conductor, and that wiring has been
correctly connected to socket outlets.
9.9.11 Earth Fault Loop Impedance
Where protective measures are used which require a knowledge of earth fault loop
impedance, the relevant impedance shall be measured, or determined by an equally
effective method.
9.9.12 Earth Continuity Conductor
Earth continuity conductor or the entire earthing network shall be tested to verify the
earth continuity.
9.9.13 Operation of Residual Current Operated Devices
Where protection against indirect contact is to be provided by a residual current device its
effectiveness shall be verified by a test simulating an appropriate fault condition and
independent of any test facility incorporated in the device.
9.10
All MTS locations and RTU Room at Bibiyana shall be equipped with air condition
units with capacity of 1.5 Ton.
2)
Air condition units, split (Inverter) type shall be provided for newly built MCC at
Agargaon, Dhaka. The capacity of A.C unit shall be minimum 3 Ton. Server Room,
- 192 -
System Management Room, Battery Room etc. shall have stand by A.C units as back
up. The qty of A.C units shall be twenty nos. (20) as a minimum.
3)
Air condition units, split (Inverter) type of minimum 3 Ton capacity shall be provided
for Demra SCADA Office (Old MCC) and ACC at Ashuganj The quantity of A.C units
shall be twenty nos. (20) for each location as a minimum.
- 193 -
10.
10.1
GENERAL INFORMATION
10.1.1 Introduction
This part provides a general description of the civil works required for the Project.
10.1.2 Scope of Work
(1)
The Contractor shall design, construct and furnish all buildings to support GTCLs
operations, accommodate the SCADA operator positions and associated equipment or
house SCADA and Telecommunications equipment as appropriate.
(2)
The Contractor shall also carry out pre-installation civil works to provide foundation or
to prepare sites and buildings for the installation of the System, whenever required.
(3)
The Contractor shall carry out refurbishment, repair, painting, replacement of existing
false ceilings, false floorings, building earthing and all other necessary civil and
architectural works.
(4)
The Contractor shall conduct refurbishment of existing all antenna masts, towers
,earthing system of masts and towers at all RTU sites, twenty MTS locations.
(5)
The Contractor shall provide both temporary and permanent facilities which shall
include but not be limited to:
(6)
a)
b)
Local site facilities in areas where return to either Dhaka or Temporary Site
camps is not practical at the end of the working day.
b)
c)
d)
e)
f) All other works as described and / or implied in the Tender Documents to complete
the Contract.
g)
The works shall also include if required the refurbishment of existing buildings
where equipment is installed at GTCL and Network Providers end under this
Contract.
h)
- 194 -
(2)
The Contractor shall carry out all geotechnical investigations (as per BS 5930 or
equivalent) necessary and submit the reports to Employers Representative for approval
within two (2) months of award of contract. A Geotechnical Report giving bore hole
logs, all test results and a summary of recommended allowable ground bearing
pressures, anticipated settlements, depth and capacities of piles to provide for the design
of foundations shall be produced by the Contractor. The Contractor shall evaluate
liquefaction resistance of sands as per latest international Practice. The Contractor shall
use the approved Geotechnical Reports for designing all foundations.
(3)
Associated facilities of the existing system, such as communication towers and radio
rooms are still in usable condition. Therefore, these existing facilities will be
refurbished and used for the new system.
(4)
Foundation of the Antenna masts of existing as well as new RTUs (wherever required
for microwave communication with MTS) will be refurbished / constructed to suit new
system.
(5)
All designs shall be prepared in accordance with International Standards and codes of
practice or other equal national standards approved by the Employer, except for
earthquake design which shall be in accordance with Indian Standard IS 1893:1984. In
particular reservoir and liquid retaining pits/chambers shall be designed in accordance
with BS 8007. Any departure from these standards and codes shall be subject to
approval by the Employer.
(6)
All work is to be carried out in accordance with recognized standards of safety. The
Employer shall have the power to instruct the Contractor to comply with the safety
requirements. This shall not relieve the Contractor of any of his obligations under the
contract.
(7)
The Main Control Centre building shall be architecturally compatible and conform to an
overall architectural concept. They shall be suitable for the operating and climatic
conditions at the site.
(8)
During the refurbishment works,the design of Walls, roof membranes, windows and
doors shall take into account the effects of monsoon rains and cyclones and shall
provide adequate protection from solar gain and glare. Windows and doors shall be well
recessed into walls, fitted with glass and shaded by projecting surrounds or canopies.
Where opening windows are provided security metallic grills shall be fitted. All
windows shall be designed to be easily cleaned. Windows in rooms shall be fitted with
Venetian blinds.
(9)
Foundation shall be designed to suit the ground conditions and in compliance with the
associated soil investigation report.
(10) Through inspections, meetings and discussions the Employer will ensure that the
Contractor executes the construction work through competent and strict supervision of
his workforce. For any deviation from the approved specification and quality, the
Employer will have the authority to instruct the Contractor to reinstate such work to the
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 195 -
10.2.1 General
(1)
New stands, foundations and sunshades shall be designed and constructed for the
installation of new RTUs and instrument for the Project at Additional and Original Sites.
(2)
(3)
A typical indicative plan and elevation for new stand, foundation and sunshade are
shown in Figure 10.1.
- 196 -
10.2.2 Requirements
(1)
The Contractor shall design and construct reinforced concrete foundation as per BS
8004/ACI 318-2011 or equivalent with sunshade for New RTU at Additional Sites.
(2)
The Contractor shall remove and dispose the existing RTU, and refurbish the existing
foundation and sunshade of existing RTU, in order to install New RTU at Original
Sites.
(3)
The Contractor shall design and construct new Instrument Stand with reinforced
concrete foundations as per BS 8004 / ACI 318-2011 or equivalent and sunshades for
new instruments installation at Original and Additional Sites.
(4)
The Contractor shall refurbish the existing Instrument Stand with foundation and
sunshade for the existing instrument(s), if necessary for the continuous use of the
existing instrument(s).
(5)
The new foundation shall be designed to suit ground conditions and to resist possible
loads on the structure per BS 8004 / BNBC or equivalent.
(6)
New sunshades shall be designed to adequately house the RTUs and instruments to
provide ample protection against sunlight and rain.
(7)
Ducts for cables shall be properly embedded into reinforced concrete foundations.
(8)
At remote sites without commercial power supply, new sunshades for RTUs shall be
designed to support solar power panels on the roof.
(9)
New RTU Room, 5 meterx5 meterx3.5 meter shall be built at Bibiyana gas field.New
tower for installing radio antenna of height 40 meter from the ground level with
necessary pile foundation shall be built at Bibiyana gas field.
10.3
10.3.1
General
(1)
There are a total of eleven (11) existing radio rooms / buildings at Master Telemetry
Stations to be refurbished for the installation of new communication equipment
collecting natural gas process data from RTUs and sending it to Control Centers through
BTCL's leased network.
(2)
The existing radio rooms / buildings are listed in Table 10.1 with further details.
Table 10.1 Radio Rooms and Buildings at Master Telemetry Stations
Old
Site
Code
608
New Site
Code
Master
Station
10-JALJalalabad
600T
- 197 -
3.1m x
2.9m
10m x 6m
Old
Site
Code
405
604
302
400
120A
118
New Site
Code
Master
Station
- 198 -
4.1m x
3.5m
3.1m x
2.9m
10.6m x
4.6m
4.1m x
3.5m
3.1m x
2.9m
10.6m x
4.6m
4.1m x
3.5m
3.1m x
2.9m
10.6m x
4.6m
4.1m x
3.5m
3.1m x
2.9m
8.5m x
4.6m
4.1m x
3.5m
3.0m x
2.9m
10.6m x
4.6m
3.0m x
3.0m
3.1m x
1.8m
10.7m x
4.7m
Old
Site
Code
New Site
Code
Master
Station
105
20-FAU100M
109
30-DMRDemra
100M
510
40-MHDMonohordi
500M
508
40-ELE500M
10.3.2
Faujdarhat
Elenga
3.5m x
2.4m
3.0m x
2.0m
7.8m x
4.1m
3.0m x
2.7m
3.5m x
2.8m
5.0 x 4.9m
6.3m x
3.9m
3.3m x
3.0m
Not
Applicable
Requirements
(1)
The Contractor shall remove and dispose of the existing radio equipment that is no
longer required for the new Communication System.
(2)
The Contractor shall examine the condition of the existing radio room and repair defects
if they are found in bad condition.
(3)
The Contractor shall clean and neatly touch-up the external and internal finish of
existing radio rooms / buildings to accommodate new radio equipment.
(4)
The Contractor shall make the provision of storing the removed and disposable radio
equipment, antenna, cable, battery, battery charger, antenna fixtures, cabinets etc which
are dismantled and non-usable materials from RTU sites in newly constructed store
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 199 -
house. Such store houses shall be built in four locations viz. Ashuganj, Demra,Feni and
Foujdarhat/Mirasarai within the Employers land area. The stores shall have brick walls
and covered top with for protection of stored materials and also protection against theft.
There shall be brick wall of height 2 meters from ground level around the store house.
The floors in store room shall have cement flooring. The dimension of the store house
shall be 30 meterx30meter x5meter. A complete lighting system for the total floor of
store houses and its surroundings shall be provided to maintain service illumination.
Lighting shall be designed to produce adequate visual performance, safety and amenity.
Single-phase, 13A, 3 square-pin double socket outlets shall be installed at suitable
height above floor level. The number of sockets in each room/area shall be determined
during the detailed design.
10.4
c)
Equipment Room
d)
e)
Workshop Room
f)
g)
h)
i)
j)
k)
l)
o)
Cleaners Store
p)
Reception Office
- 200 -
c. The Contractor shall design simple frame structure of Thai aluminum partition of
each rooms of the MCC floor except. Equipment room and Electrical, Battery & UPS
Room.
d. Equipment room and Electrical, Battery & UPS Room shall be designed with Brick
wall.
e. The Control Room shall be designed in accordance with ISO, Ergonomic Design of
Control Centre.
f. Internal walls shall be separated using Thai aluminium/Brick partition.
g. The dimensions of all the rooms of the MCC floor shall be adequate for proper
operation and maintenance of all plant and equipment and shall make allowance for
the future expansion facilities.
2.
Rooms
a. All internal walls shall be of Thai aluminum/Brick wall (with plastering and other
necessary works for completeness of rooms) partition, quality & color shall be
approved by the Employer.
b. All Rooms shall be free from exposed internal columns.
c. All offices shall be fully furnished with standard office furniture appropriate to the
proposed occupancy.
3.
4.
- 201 -
refrigerator, Modern high quality energy saving microwave oven, Modern gas
cooker/Electrical Induction Cooker with air filter, Modern Electrical Kettle and all
necessary utensils, cutlery(SS) and crockery (Best Quality) as a minimum consistent
with the occupancy of the building.
10.4.3 Civil Works for ACC and Demra SCADA Office (Old MCC)
A) General Requirements for ACC:
a) The Contractor shall carryout survey work necessary for ACC and Demra SCADA
Office building design work.
b) The entire area of the ACC and Demra SCADA Office building shall be cleared of all
debris and levelled to provide a uniform formation fixed level at a value to be advised
according to Public Works Department (PWD) Datum.
c) Equipment room and Electrical, Battery & UPS Room shall be refurbished.
B) Rooms
a) All internal walls of the building shall be refurbished. Necessary plustering and
painting of the rooms shall be carried out by the Contractor.
C) Flooring and Ceilings
a) Floors in equipment room, office and other occupied rooms shall have high quality of
paint & refurbishment.
b) The false floor and ceiling shall be used in the Control Room. Roof and Ceiling voids
shall be of 1 meter.
c) The old false ceiling of each room the building shall be change with new one.
d) The false Roof and Ceiling shall use hard-wood or ply-wood timber with on the
Carpet, each timber tiles (2' x 2') shall be a minimum 25 mm thick and mineral fiber,
acoustical, non-combustible board with tiles hung by MS/metal suspension grid in
reveal T-bar section with T-bar, cross T-bar, hold-down frame/clip, MS/hang-wire
suitable for control Room as approved by the Employer.
e) Galvanized steel cable trays shall be fixed above the false ceiling. All cabling run in
the false ceiling shall be run on cable tray.
D) Kitchen and Rest Room
a) The Kitchen shall be fully equipped with double sink, double wash basin, draining
- 202 -
- 203 -
positions and two (2) printer positions to complement the specified the equipment.
Additional furniture shall be provided to fully equip the Control Room for operational
use.
B) Engineers Rooms
a) Furniture shall be provided to complement the specified equipment.
b) Two suites fire-proof cabinets to store and safeguard software, backups and
associated documentation shall be provided.Two suites/cabinets shall be provided,
One suite shall be used for the storage of duplicate software etc. for the Auxiliary
Control Centre (ACC).
C) Equipment Room
a) Hard-wood or composite desks for technician and engineering terminals, housing for
printers, 3 high backed adjustable swivel chairs and lockable cabinets for
documentation, software and hardware shall be provided.
D) Workshop
a) Work benches for two persons, chairs, cupboards, desks, comprehensive set of tools
suitable for electronic equipment, adequate shelving/racking and also lockable storage
cabinets shall be provided.
E) Senior Executives Office
a) A hard-wood or composite desk, high backed, adjustable swivel arm chair, visitors
chairs (at least four), and executive style table, filing cabinets, glass door fronted book
case and open shelving for files shall be provided.
(ii)
(iii)
cache.
(iv)
(v)
Graphics Sub system with driver s/w: PCI VGA with Latest maximum GB
RAM
(vi)
(vii)
- 204 -
(viii)
Internal/External modem
(ix)
(x)
(xi)
UPS
(xii)
c) The latest release of the following software shall be pre-loaded on the PC system and
also provided on CD-ROM:
(i)
(ii)
(iii)
(iv)
Microsoft Project
(v)
On access licensed virus checking software, with updates provided for the
Contract duration
(vi)
F) Engineers Office
a) A hard-wood or composite desk, high backed, adjustable swivel arm chair, visitors
chairs (at least four) and executive style table, filing cabinets, glass door fronted book
case and open shelving for files shall be provided.
(ii)
(iii)
(iv)
(v)
Graphics Sub system with driver s/w: PCI VGA with Latest maximum GB
RAM
(vi)
(vii)
(viii)
Internal/External modem
(ix)
(x)
(xi)
UPS
- 205 -
(xii)
c) The latest release of the following software shall be pre-loaded on the PC system and
also provided on CD-ROM:
(i)
(ii)
(iii)
(iv)
(v)
On access licensed virus checking software, with updates provided for the
Contract duration
(vi)
G)
a)
Four hard-wood or composite desks, four arm chairs, book case with glass front
and open shelving cabinet suitable for files, and lockable filing cabinets shall be
provided.
b)
c)
(ii)
(iii)
(iv)
(v)
Graphics Sub system with driver s/w: PCI VGA with Latest maximum GB
RAM
(vi)
(vii)
- 206 -
(viii)
Internal/External modem
(ix)
(x)
(xi)
UPS
(xii)
(c) The latest release of the following software shall be pre-loaded on the PC system and
also provided on CD-ROM:
(i)
(ii)
(iii)
(iv)
(v)
On access licensed virus checking software, with updates provided for the
Contract duration
(vi)
I)
J)
- 207 -
(a) Suitable facilities for safe keeping of all keys shall be provided. A set of three (3)
keys for each lock and set of master keys shall be provided.
O) Labeling
(a) All equipment shall be fitted with labels. Size, text, material, fixing etc., shall be
approved by the Employer.
P) Signs
(a) Signs for the building and surrounds shall be provided. Size, text, material, fixing,
etc. shall be approved by the Employer.
Q) Inventory
(a) An inventory of all items shall be provided by the Contractor.
R) Office Consumables
(a) Office consumables shall be provided by the Contractor until three (3) months after
the issuance of the Taking-Over Certificate
10.4.6 Electrical Works
10.4.6.1
General
(a) The electrical installation shall be carried out in conformance with the Electricity
Rule of the Government of Bangladesh and International standard code of Practice.
Any special requirement of the Electrical Inspector, Government of Bangladesh,
Power Development Board, Dhaka Electric Supply Authority, or the Electrical
Licensing Board or any other legal authority within Bangladesh shall also be
complied with.
(b) The Contractor shall establish the total loads of the MCC and surroundings.
(c) Single-phase, 13A, 3 square-pin double socket outlets shall be installed at suitable
height above floor level. The number of sockets in each room/area shall be
determined during the detailed design.
(d) The socket outlets in the kitchen shall be at 1.2 m height from the floor or 0.25 m
above a work-surface. The number shall be adequate for a modern office kitchen.
- 208 -
(e) Calling bell and push buttons shall be provided with all necessary fittings and cabling
for all rooms except the kitchen which shall accommodate the control panel.
10.4.6.2Lighting
(a) A complete lighting system for the total floor of MCC and its surroundings shall be
provided to maintain service illumination. Lighting shall be designed to produce
adequate visual performance, safety and amenity and shall be free from excessive
glare, stroboscopic effects and flicker from discharge lamps.
(b) Light fittings shall generally be fluorescent type and in accordance with IEC
Publication No.-162. they shall be complete with instant start control gear, 2-pin lamp
holders with totally enclosed pins, of minimum width beams and suitable for flush
mounting in the false ceiling and surface mounting on the ceilings of other areas. On
walls, incandescent lamp fittings shall be installed at proper height.
(c) Fluorescent light fitting shall be in accordance with IEC Publication No. 81 and shall
have color rendering values of x=0.335 (ie. color) and y=0.342 on the IEC chromatic
scales.
(d) The lighting system shall include provision for ease of erection, maintenance,
cleaning, lamp replacement and future extension. Lamp replacement and maintenance
should, unless otherwise approved be possible without outage of the main supply.
(e) All light fittings, sockets, fixtures cables shall be best quality, designed to ensure
satisfactory operation and service life under all service load frequency, temperature
and variations.
(f) In the event of mains failure of the lighting system, the illumination level in the
Control Room, Equipment Room and Engineers Room shall be maintained at the
specific level. For other rooms/areas general lighting shall be provided to ensure the
safe movement of personnel enable essential operations to be carried out at all times.
(g) Minimum level of illumination in different areas shall be as follows:
Area
Illumination Level
10.4.6.3
500-550 Lux
Workshop
300-350 Lux
200-250 Lux
- 209 -
(a) All rooms/areas of the MCC shall be equipped with fire, smoke and heat detectors,
manual call points and firefighting equipment in accordance with a recognized
international standard, NFPA/local rules or equivalent.
(b) A fire, smoke and heat alarm system panel with mimic showing the MCC area
shall be provided in Control Room within easy viewing distance of the operators.
One audio level horn shall be provided to sound on fire. A common repeat fire
contact shall alarm on the SCADA System.
(c) Firefighting equipment shall be provided to enable MCC, ACC, Demra SCADA
Office building personnel to deal with fires. The equipment shall conform to local
fire fighting rules. Firemans personal equipment such as breathing apparatus and
ladders shall be provided.
(d) Portable fire extinguishers shall be provided in all areas of the MCC, ACC, Demra
SCADA Office building of the relevant type consistent with function of the area.
10.5
10.5.1
General
(1)
10.5.2
There are two existing Control Centers for the Existing System. One is the Main Control
Center located at Agargaon, Dhaka and the other is the Auxiliary Control Center located
at Ashugonj. The old MCC located at Demra. Existing equipment of these control
centers shall be replaced with new equipment. Therefore the existing equipped rooms
shall be refurbished for the installation of new equipment after the removal of existing
equipment.
Requirements
(1)
The Contractor shall remove and dispose of existing SCADA equipment that is no
longer required for the new SCADA System and transport it to the designated storage
locations of the Employer.
(2)
The Contractor shall examine the present condition of the following existing rooms at
both Control Centers and repair defects if they are found in bad condition.
a)
b)
Equipment Room
c)
Battery Room
(3)
The Contractor shall clean and neatly touch-up the internal finishes of these rooms at
old control centers at Demra and Auxiliary control center at Ashugonj. Both Control
Centers shall accommodate the new SCADA equipment.
(4)
The Contractor shall refurbish existing radio rooms prior to installation of new
equipment. The refurbishment work shall include roofs, walls and floors, but not be
limited to:
a)
- 210 -
b)
c)
Repair or replace defective doors, windows, shutters, frames and other fittings.
d)
Make safe electrical installation, wiring, and earthing system and bring up to
standard necessary for the new telecommunications equipment.
e)
10.6
10.6.1
General
(1)
The Contractor shall remove and dispose of the Antenna masts ( which are unusable) of
existing as well as new RTUs.
(2)
The Contractor shall examine the condition of existing microwave Tower Foundations
and rectify the defects (if any) for all twenty MTS locations.
(3)
The contractor shall replace Guy wire, nut bolt ,clamps and necessary accessories and
install the mast within proper and safe working condition as per the international safety
rules.
(4)
The Contractor shall dismantle existing feeder cable, antenna and accessories from
existing MTS sites and shall install new antenna, feeder cable of new radio systems.
(5)
The Contractor shall paint all existing antenna masts at RTU sites and towers at MTS
locations with epoxy paints.
(6)
Radio and other equipment at all MTS locations shall be dismantled and stored in the
designated storage locations of GTCL.
(7)
Antenna, cable, batteries and accessories shall be removed from all RTU sites and taken
to designated storage locations of GTCL.
(8)
Unused RTU rack & unused radio rack shall be transported to designated storage
locations of GTCL.
10.6.2 Painting
(1)
The Contractor shall remove the existing painting ,carry out all requisite pre painting
works such as using primer etc and shall paint all masts, towers with high quality epoxy
paints.
10.6.3 Requirements
(1)
The Contractor shall design and construct / erect the Antenna masts of existing as well
as new RTUs for this Project.
(2)
The Contractor shall clean the steel surfaces of the existing microwave steel Towers
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 211 -
with iron brush / emery papers and apply zinc-rich paints on the steel surfaces of
Towers.
(3)
10.7
The Contractor shall design and construct / erect the Self Supported Antenna tower of
40 meter height at Bibiyana Gas field with proper foundation.
New Towers for the Radio System shall be located at Bibiyana and other specified
locations.
b)
Where new Towers are specified, the Contractor shall be responsible for their design,
supply, construction and commissioning.
c)
The number of tower required and height of each tower shall be determined by the
Contractor and identified in the Radio Path Engineering Report. The height of the
tower as a minimum shall be 40 meter from the ground level at Bibiyana Gas field.
d)
Tower shall be designed to support both microwave antennas and UHF radio Aerials.
e)
The following investigations shall be undertaken for each new tower site:
f)
i)
ii)
Construction
i)
The new towers shall be four legged self supporting and designed,
constructed and installed in accordance with EIA -222 or equivalent. Tower
loading shall be calculated in accordance with EIA-222
ii)
Antenna towers shall be designed to support at least twice the initial design
load to provide for antenna loads of future requirements.
f) Where new Masts are required, the Contractor shall be responsible for their design,
supply, construction and commissioning. The number of masts required and height of
each masts shall be determined by the Contractor and identified in the Radio Path
Engineering Report.
a)
b)
The Contractor shall determine the tower height and tower loading (antenna size and
- 212 -
number) and design the self supporting tower foundation to support at least twice the
specified loading.The minimum height of tower at Bbiyana shall be 40 meter from the
ground level.
c)
d)
Trenches for pipes or cables shall be provided in reinforced concrete construction and
with connections to the site drainage system to allow dispersal of unforeseen water
within the trench, and shall be fitted with manually removable well fitting covers such
that they will stand all loading from traffic without rocking or excessive leakage.
Ducts for cables shall be properly surrounded with concrete. Cable trays for
communication cables shall be made of galvanised steel.
10.7.1.1 Earthing
a)
All Tower shall be earthed in accordance with the MPT-1331 and EIA 222 with the
former taking precedence. Earthing components shall conform to BS - 6651 or
equivalent.
10.7.1.2 Tests
a)
The detailed log shall be made of each bore hole showing the various types of strata
encountered. The following tests shall be undertaken:
i)
ii)
iii)
iv)
v)
- 213 -
vi)
vii)
Water level to be
ix)
Any other tests necessary for ground improvement and/or piling works.
x)
10.8
10.8.1 General
a)
At Mirasarai and Bibiyana, new Radio Room/RTU Room shall be constructed to
house the radio equipment.
(b)
(c)
Radio /RTU rooms shall be single story buildings and shall have air conditioning and
electrical power facilities. A typical indicative plan of a Radio Room is shown in
Figure
10.8.1.1
New Construction
(a)
(b)
The building shall be suitably sized and furnished to accommodate all equipment and
associated supervisory personnel.
(e)
(f)
Hardwood flush doors in timber frames, complete with door furniture of robust
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 214 -
(h)
The building shall be provided with proper Earthing and lighting protection in
accordance with the BS 6651 or local standard as per National Building Code.
(i)
Provision shall be made for cabling to enter and be terminated within the building.
(j)
(k)
(l)
Security and suitable fire fighting equipment shall be provided in all rooms.
The Contractor shall refurbish existing radio rooms prior to installation of new
equipment. The refurbishment work shall include roofs, walls and floors, roofs but
not be limited to:
(i)
(ii)
(iii)
(iv)
Make safe electrical installation, wiring, and earthing system and bring up to
standard necessary for the new telecommunications equipment.
(v)
- 215 -
11.
11.1
GENERAL
(1)
At stages throughout the Contract, formal tests shall be carried out and all test result
shall be submitted by the Contractor. These test procedures shall be designed to show
that the System meets the requirements of the Specifications, and shall be completed to
the satisfaction of the Engineer before subsequent stages can proceed.
(2)
The procedures shall define detailed test method and procedures, measuring items,
testing equipment to be used and recording forms for test results, and shall contain
design values and tolerances which will be treated as the criteria for evaluation of each
test. The test procedure shall be submitted to the Engineer for approval prior to
respective test.
(3)
All equipment and components of the system shall be subjected to inspection and testing
both during and upon completion of manufacturing and at site. Contractor shall provide
full details of all type tests carried out on boards and modules and tests normally carried
out in their works including to what standards these are carried out. These test
preferably in accordance with International / National Standards.
(4)
(5)
Employer / Engineer shall have free entry and access at all phases of the project to all
parts of Contractor's facilities associated with manufacturing and testing of system.
(6)
Contractor shall invite Employer / Engineer well in advance with minimum 2 months
notice of the date at which the system is ready for testing.
(7)
The equipment will not be shipped before they have been officially released in the form
of release notes by Employer / Engineer.
(8)
Contractor shall provide Employer / Engineer with all reasonable facilities necessary to
determine compliance to the system specification.
(9)
Contractor to note that acceptance of the equipment and the system of inspection and
testing shall in no way absolve the Contractor of his responsibility to deliver the
equipment meeting all the requirements specified in the specification. Contractor shall
be responsible till the completion of the warranty, for any corrections / modifications
including supply and implementation of hardware & software to fulfil the requirements
of the contract. If after acceptance of the system certain changes are required such as
debugging of the software supplied or any other related issues which cannot be
ascertained during the final handover of the system, these changes shall be carried out
by the Contractor at their cost.
(10) Contractor personnel shall be actively involved during factory acceptance and site
acceptance testing
(11) The Factory Acceptance Test (FAT), Site Acceptance Test (SAT), Commissioning Test
and the Final System Test to be carried out by the Contractor shall include but are not
limited to the following:
a)
Visual check
- 216 -
11.2
b)
c)
Dimensional check
d)
e)
f)
g)
Functional test
h)
Operation test
i)
Performance test
j)
Checking of system loading w.r.t CPU, memory, disk, as per the requirements.
k)
Checking of system diagnostics for all the equipment as per the requirements,
power failure and system restarts.
l)
m)
Pipeline shutdown and various sequences and interlocks as per pipeline Operation
and Control Philosophy.
(2)
11.3
The Contractor shall provide for the purpose of the tests all equipment and services
required for testing, including but not limited to:
a)
b)
c)
d)
Consumables
e)
All test instruments shall be subject to routine inspection testing and calibration, by the
Contractor. All test instruments shall be subject to approval by the Engineer, and if
required by the Engineer shall be calibrated at the expense of the Contractor by an
approved standards laboratory.
TESTS
The following tests shall be carried out by the Contractor
(1)
(2)
(3)
Commissioning Test
(4)
- 217 -
(1)
Before any item of the equipment is packed or delivered from the manufacturer's
factory, all tests itemized in the relevant sections of these Technical Specifications shall
be carried out by the Contractor as far as practicable to prove compliance with the
requirements of the Specifications. All parts of the SCADA and Telecommunication
System shall be assembled in the manufacturer's factories prior to shipment and tests
shall be performed by the Contractor as may be required to demonstrate the adequacy of
the systems and its component parts. All tests should simulate normal operating
conditions as closely as possible.
(2)
The Contractor shall prepare FAT documentation covering all hardware, software
including SCADA software and system functionalities including system expansion
requirements and submit it 3 months in advance for Employer / Engineer review and
approval. Factory acceptance test will be done based on the stipulations in the approved
FAT document, which shall completely fulfil the contract requirements and approved
SCADA/RTU FDS documents.
(3)
The Employer / Engineer shall be free to request any specific test on any equipment and
the system considered necessary by him, although not listed in the testing documents to
verify the compliance with the specifications.
(4)
In order to successfully conduct the FAT, it is advisable that the Contractor conducts a
PRE-FAT test to ensure that the system performs in compliance with the specification
requirements .These tests shall enable the Contractor to detect and correct most design,
integration and performance problems before FAT. The signed and approved Pre-FAT
reports shall be submitted to the purchaser. Based on these reports the clearance for
conducting FAT shall be given by the purchaser.
(5)
The Contractor shall give the call regarding FAT well in advance with a minimum of 30
days notice of the date at which the system is ready for testing.
(6)
FAT shall be carried out in SCADA / RTU Contractor's premises. FAT shall cover the
testing & Integrated SCADA / RTU System with RTUs.
Testing shall systematically, fully and functionally test all the hardware and software in
the presence of Employer / Engineer inspectors to ascertain compliance with the
contract document and approved FDS documents. Test Bed shall be prepared with all
the equipment (SCADA Servers, HMI, RWSs, RTUs, Routers, and Peripherals etc.)
interconnected to actual configuration to perform the testing of integrated SCADA
system. All the workstation desks, cabinets with mounting, wiring, interconnection of
the equipment shall be available for this testing.
The equipment to be supplied shall be type-tested for electromagnetic compatibility.
The SAT shall be carried out on all equipment and software supplied under the
Contract.
(2)
The SAT shall be carried out after the equipment has been installed at the site.
- 218 -
(3)
The SAT shall be performed with equipment at the locations in which they will
eventually operate, or in a typical location in the case of portable equipment.
(4)
The SAT shall demonstrate that the overall design of the System meets the requirements
of the Specification in the field, using the actual communications network, including
equipment supplied by others.
(5)
The installation shall be inspected to ensure compliance with the installation manual and
cable drawings and to verify satisfactory condition of all equipment.
(6)
SAT shall involve integrated testing of complete RTU / SCADA system. Site
Acceptance Testing will be done based on the stipulations in the approved SAT
document. Once the test is successfully performed, then the system would be ready for
commencement of test run.
The Contractor shall carry out the Commissioning Tests in the presence of the
Employer's Personnel and the Engineer to demonstrate that all guarantees and technical
particulars as listed in the Contract Documents are satisfied and that all the equipment is
properly installed.
(2)
The Commissioning Test shall be conducted on all equipment and software supplied
under the Contract in accordance with the SAT document approved by the Employer.
(3)
The Commissioning Test shall establish all aspects of functionality, including proving
of all types of communication link.
(4)
The Commissioning Test shall include both polling of the RTU by the SCADA Server
and generating an alarm in the RTU to ascertain it can initiate a call to the Server. The
necessary test software / configuration to perform the above shall be supplied by the
Contractor.
(5)
Whenever all or part of a SCADA system is modified, repaired or replaced, recommissioning is required to verify that the portions of the system affected function
correctly and that the work has not affected other portions of the system. The extent of
re-commissioning required should be determined from the extent of the modifications.
The Final System Test shall be carried out to confirm continuous functional operation of
the systems with the required system reliability and availability. This test aims at
keeping the complete integrated system operating for 24 hours a day for a period of 14
days.
(2)
In case of failure, the tests shall be restarted till the system operates without failure of
any system functionality for 14 days.
(3)
Failure of test shall be limited to such system failures which will affect system
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 219 -
availability and reliability and shall not be dependent upon established failure of third
party supplied items. Employer / Engineer shall have the right to reject the complete
system or part thereof in the event of two successive failures of test run.
(4)
Functional performance testing for system certification must take place without operator
intervention in the processor from beginning to end of the test. For this reason it is
highly recommended that a complete pre-test be conducted, using the full functional
performance test procedure, prior to undertaking the certification test.
(5)
The Final System Test shall be carried out in accordance with a test plan and procedures
approved by the Employer.
(6)
The test result obtained during the Final System Test shall be documented in the form of
report and submitted to the Employer for approval within 15 days of completion of Test
Run.
- 220 -
12.
12.1
INTRODUCTION
The New System is required to provide full operational facilities for a minimum of ten (10)
years. The Contractor shall ensure that supplier is able to provide spares for 10 years.
12.2
OPERATION SUPPORT
12.2.1 General
(1)
In addition to or as part of the staff required for maintenance support and training, the
Contractor shall provide two engineers in Bangladesh for the 24 months period from
System Take-over to Contract Completion. The two engineers shall be a SCADA
engineer and a communication engineer
(2)
The engineers shall be based amongst Agargaon MCC, Ashuganj ACC and Demra
SCADA Office. In addition they will be required to travel to all sites covered by the
Contract as and when required. The engineers shall work under the direction of the
Engineer and / or as directed by the Employer. Each engineer shall work a minimum of
42 working weeks per year in Bangladesh. At all times at least one engineer shall be
working in Bangladesh.
12.3
(1)
The said two engineers shall be degree qualified with a minimum of five years practical
experience in the relevant area.
(2)
The SCADA engineer shall have experience in SCADA systems configuration and
maintenance, and shall advise and assist the Employer in configuring and maintaining
the System.
(3)
MAINTENANCE PHILOSOPHY
(1)
The Contractor shall provide all maintenance services for the System during the two
years warranty period following System Taking-Over.
(2)
The system shall be guaranteed to give specified performance of 99.99% for a period of
24 months from the date of acceptance of the system by the Employer. This warranty
shall start from the date of acceptance of the system.
(3)
During the warranty, the Contractor shall use his own instrument, spares, man-hour,
communication facilities, hardware, software, materials, etc. for the rectification of any
problem.
(4)
System Warranty including all services and spares including consumables for operation
and maintenance of the system.
- 221 -
12.4
12.5
(5)
On completion of the warranty period, the Employer will enter maintenance contracts
for all maintenance activities for the System and the provision of spare parts.
(6)
The Contractor shall support these maintenance contracts through the Contractor and/or
relevant maintenance service provider for the following services:
a)
Routine maintenance
b)
c)
d)
Emergency call-out
e)
Software maintenance
(7)
First level maintenance and support shall include identification of faults down to module
or card level and on-line replacement of faulty equipment.
(8)
Notwithstanding this requirement to maintain the System, the Contractor shall provide
documentation and training of the Employer's staff during the Contract period, to a level
that would allow first level and routine maintenance to be performed.
The System shall have remote and local diagnostic facilities to allow for identification
of faults necessary for first level maintenance.
(2)
(3)
Peripheral equipment shall be easily removable from service and either replaced by
standby equipment or spare equipment without affecting System operation.
SPARE PARTS
(1)
For Mandatory Spares, Contractor to supply 10% of total installed quantity (rounded
off to 2 nos. as minimum) for electronic cards / modules of each type of each system,
subsystem of SCADA, RTU and Communication Equipment, IPPBX, Video
Conferencing System, UPS, Power Supply System, Battery & Battery Charger System,
Solar Power System etc.
10% spare instruments or minimum one of each range, type and material of construction
for Field instruments and Flow computers.
100 % spares shall be provided for consumables e.g. fuses, lamps, plugs, clamps etc.
However, any other mandatory spares not mentioned above but required for any item
shall also be supplied by Bidder.
Bidder shall provide a list of mandatory spares at the time of offer and price of these
spares will be included in main offer.
(2)
During two (2) years O & M period, the Contractor shall provide all spare parts and
consumables required for maintaining the System (O & M Spares).
- 222 -
(3)
Contractor to note that the mandatory spares are the inventory of the spares to be kept
by the Employer and the same shall not be utilized by the Contractor at any stage of the
project till completion of warranty, without Employer's prior concurrence. Any
mandatory spares utilized by the Contractor during Warranty period shall be replenished
within 45 days.
(4)
The Commissioning spares for all the items / equipment shall be included along with
commissioning services as required to commission the complete system. The
consumable required during commissioning of system shall be included as part of
commissioning spares.
(5)
The Commissioning spares shall be arranged by the Contractor to cater to the needs /
requirement during installation, commissioning, site acceptance testing, trial run and
warranty period. These spares will be the part of the tender. These spares shall be
readily available with the Contractor. If the spares not used they may be retained by the
Contractor for maintenance.
These commissioning spares are different from Mandatory spares and Contractor
shall not use mandatory spares as commissioning spares, whatsoever.
Bidder shall provide a list of commissioning spares (with Serial & Part number for each
system, sub-system) at the time of offer and price of these spares will be included in
main offer.
(6)
For spares Contractor shall provide the address, contact person, fax and telephone
numbers of the manufacturer for spare parts. The Contractor shall warrant that spare
part for the system would be available for minimum of 10 years after warranty
period after system commissioning. After this period if the Contractor discontinues
the production of the spare parts, then he shall give at least 12 months notice prior
to such discontinuation so that Employer may order the requirements of spares in
one lot.
In the bid, the Contractor shall provide unit price (year wise and % escalation per year)
of each Spare Module card, which shall be valid for the procurement of the spares for
operation and maintenance in subsequent years.
(7)
All spare parts shall be identical, electrically and mechanically, to the corresponding
parts in the equipment provided and shall be suitably packed and clearly marked, ready
for storage.
(8)
Spare or replacement parts shall be fully compatible with and necessarily similar to
items previously supplied.
(9)
The Contractor shall furnish full contact address of all the equipment suppliers with
their (supplier's) commitment letter to support spares provision to the Employer, the
local associate or any other party undertaking maintenance contracts with the Employer
to maintain the System availability for its lifetime.
(10) The Contractor shall guarantee that the suppliers shall maintain the availability of spares
or replacement parts for the System lifetime.
(11) The Contractor shall guarantee, if the supplier intends to discontinue the manufacture of
spare or replacement parts for the works during the maintenance Contract with the
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 223 -
Employer, the supplier shall supply such spare or replacement parts required to maintain
the System availability for the remainder of the maintenance Contract to the local
associate. This shall include any repair service that may be discontinued.
(12) The Contractor shall guarantee, if the supplier intends to discontinue the manufacture of
spare or replacement parts for the works, the supplier shall either:
12.6
a)
Forthwith give notice to the Employer of such intention and afford the Employer
the opportunity of ordering all spare or replacement parts required to maintain the
System availability for its lifetime.
b)
MAINTENANCE CONTRACTS
12.6.1 General
(1)
The maintenance Contractor shall provide maintenance contracts for all System
hardware and software:
(2)
(3)
Software maintenance contracts shall be to the Model Form of License Agreement for
the use of Computer Software Products of the Institute of Purchasing and Supply, IPS
Model L 1987, The Contract shall provide remedial maintenance to a specified standard
of service.
(2)
The maintenance Contractor shall be responsible for detailing the necessary procedures
to be carried out to fully comply with the Manufacturers recommended preventive
maintenance requirements.
(3)
During routine maintenance visits, the maintenance Contractor shall replace or repair
any defective equipment at his own expense.
(4)
The maintenance Contractor shall provide a detailed report on all findings within seven
calendar days of a routine maintenance visit.
(5)
To the extent that the Standard of the works has not been specified in the Contract, the
Contractor shall use good quality materials, techniques and standards and execute the
Contract with the care, skill and diligence required in accordance with best engineering
practice.
- 224 -
A remedial maintenance service that takes the form of fault diagnosis and repair or
replacement of defective parts of the System shall be provided
(2)
The coverage and response time period shall be 7 days a week 24 hours a day; however
the contract shall provide different call out charges for weekdays, weekends and visits
outside of normal working hours. The Contractor shall attend to the site within 24 hours
or as directed by the Employer of the report of a fault.
(3)
The Contractor shall be responsible for attending sites with all relevant spare parts and
test equipment to enable a speedy and effective repair.
(4)
If a replacement unit is supplied under the maintenance contract it will remain in the
equipment under normal circumstances. In such cases the original unit in the equipment
shall be vested in the Contractor and become his absolute property at the time of
replacement, and the replacement unit shall be vested in the Employer and become their
absolute property at that time.
(5)
The Contractor shall not have access to the Employer's system manuals and or drawings.
(6)
The Contractor shall make repairs within an MTTR (Mean Time To Repair) specified in
the maintenance contract.
(7)
The Contractor shall provide a detailed written report of the visit, which shall only be
certified by the designated maintenance engineer.
A software remedial maintenance service that takes the form of fault diagnosis and
correction of software shall be provided.
(2)
The coverage and response time period shall be 7 days a week 24 hours a day however
the contract shall provide different call out charges for weekdays, weekends and visits
outside of normal working hours. The Contractor shall attend to site within 24 hours of
the report of a fault.
(3)
The Contractor shall be responsible for attending sites with all relevant equipment to
enable a speedy and effective repair.
(4)
The Contractor shall not have access to the Employer's system manuals and or drawings.
The Contractor shall make repairs within an MTTR specified in the maintenance
contract.
(5)
The Contractor shall provide a detailed written report of the visit, which shall only be
certified by the designated maintenance engineer.
(6)
In the case of non-critical software errors or faults, the Employer will agree with the
Contractor on a mutually convenient time for the Contractor to attend the site and be
granted access to the System.
(7)
All successful Software Remedial Maintenance will be documented and included on all
system working and back-up copies of the software.
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 225 -
12.6.5 Consumables
The Contractor shall offer to provide all consumables such as printer paper, floppy disks,
printer ribbons, plotter pens, streamer tapes etc., with spare parts.
- 226 -
13.
(2)
All equipment inscription, labels, nameplates, tags, instruction and warning plates
necessary for the identification and safe operation of the equipment shall be in the
English languages.
(3)
Stainless steel plate with the following details engraved shall be permanently fixed on
the equipment / instrument
a)
b)
c)
Tag number;
d)
e)
(4)
Packing must be such to protect all goods from possible impacts and foreign matters;
moreover, it must limit the influence of both the climate and the environment, and be
suitable for the kind of shipping provided for.
(5)
In packing the equipment / instrument and accessories all necessary precautions will
have to be taken to avoid any damage to the accessories during transport and delivery.
(6)
All items supplied shall be packed for long storage under the climatic conditions
prevailing at the site. Small items shall be packed in sealed transparent plastic bags with
desiccator packs as necessary. Each item shall be clearly marked with its description,
purpose and site designation code as applicable. When more than one item is packed in
a single case a general description of the contents is to be shown on the outside of each
case and a detailed list enclosed. All cases and other packages must be suitably marked
and numbered for identification purposes.
(7)
The Contractor shall be responsible for ensuring that all the instruments are carefully
and / or suitably packed for shipment, so that they arrive at site in good condition and
remain so during storage at site. Before dispatch, all exposed surface shall be protected
by applying anti rust primer (two coats) and suitable cover shall be provided for the
instruments to be supplied
(8)
The Contractor will be responsible for all damages due to improper preparation of the
goods for shipment.
(9)
(10) Contractor shall make shipment using the minimum number of shipping containers
consistent with the requirements of safe transit, available modes of transportation and
routing. It shall be Contractors responsibility to determine that packing as done is
adequate to assure that all equipment shall arrive at destination in an undamaged
condition and ready for the intended use.
- 227 -
IDENTIFICATION, MARKING,
PACKING AND STORING
14.
TRAINING
14.1
INTRODUCTION
The Contractor shall provide a program of training courses and training to enable the
installation, operation, management and maintenance of the System to be effectively carried
out.
14.2
14.3
14.3.1 General
Training shall be provided making due provision for the abilities and needs of the attendees.
To this end the following categories of user should be noted by the Contractor.
14.3.2 Managers
This group of personnel is those charged with responsibility for the safe and efficient running
of the plant. Knowledge on the System operation is needed to enable appreciation of the
benefits and limits of the information available and assist the decision making process. Their
involvement is essentially at an executive level.
14.3.3 Engineers
(1)
Engineers will require detailed knowledge of the supplied System to ensure that it
becomes a sustainable and supportable system.
(2)
Training in both software and hardware shall be given to cover both the maintenance
function and to deliver the capability for effecting future enhancements.
- 228 -
TRAINING
14.3.4 Operators
(1)
Operators have knowledge of gas transmission operations and use of the System as their
main operational tool based at a control centre.
(2)
Their responsibility is continuous supervision of the National Gas Grid in a safe and
efficient manner and typical duties include:
a)
Reporting the performance of the pipeline operations, for example how much gas
is available, and from where.
b)
c)
14.3.5 Technicians
Technicians perform maintenance and modification duties under the direction of an engineer.
Training should be given in all aspects of system support including planned maintenance and
minor configuration changes.
14.3.6 Trainers
In order to ensure effective in service training and to ensure sustainability of training after the
Contractor's warranty period is over, staff will be identified who in addition to other duties
will be designated as trainers and undergo a 'Training to the Trainers' program. These trainers
will then be assigned to provide in-service training to new staff.
14.4
- 229 -
TRAINING
In addition to SCADA & RTU system, the Contractor shall provide hardware, software and
operation maintenance training on other systems such as IP PBX, Video Conferencing etc.
14.4.2 Training Schedule:
The training schedule shall coincide with the delivery of the equipment to Employer. Training
shall be provided in at least three different sessions to accommodate personnel attendance.
The training course shall be an optimum mix of classroom and laboratory training.
14.4.3 Training course Requirement:
Employers Training course requirement are described below in terms of the contents of each
course to be provided. Training shall be provided on GTCL Data base for the application of
software course, the dispatchers training course and the associate training course.
14.4.4 Data base and Display building course:
The Data base and display building course shall be first course to be given in the overall
training sequence, it shall be a hands-on course using the GTCL systems. The course shall be
given immediately following delivery and installation of the system. The course shall be
designed to train Employers personnel in how to use the system to development the data
bases, displays, reports for each Control Centre computer system.
Course objectives shall include:-
a)
b)
How to identify data base fields, entries, records, table and contents.
c)
d)
e)
f)
g)
h)
How to maintain symbol libraries, display colour group and display string lists.
On course completion, all participants shall be able to prepare the necessary input data to
define the system operating environment, build the system data base and displays, and prepare
the data base administrator to maintain and modify the data base and its structures.
14.4.5 SCADA & RTU Course:
The contractor shall provide SCADA & RTU course that covers the following subjects as a
minimum:
f)
g)
Operational procedures for various mode of operation, including diagnostic tests and
interpretation of the associated tests results.
h)
i)
- 230 -
TRAINING
14.5
j)
Demonstration of complete SCADA & RTU tests set use, including tests sets connection
and set up for all possible modes of operation, all operational procedures, the exercise of
each command or feature associates with each mode of operation the interpretation of
results , and how to use the tests set to diagnose and isolate SCADA & RTU problems.
k)
Disconnection and replacement of all SCADA & RTU equipment, including all modules
within the SCADA & RTU.
l)
TRAINING REQUIREMENTS
The Contractor shall provide training in suitable premises at locations of their choice. It
is envisaged that the training will take place within Bangladesh and overseas locations
also.
(2)
The Contractor shall provide technology transfer training where members of the
Employers staff shall visit an overseas gas transmission company with an established
SCADA system in use for a total duration of ten (10) man-months.
(3)
The Contractor shall provide all accommodation, travel costs and subsistence for the
Employer's staff both for Bangladesh and abroad, except for Dhaka based training
where only travel and subsistence costs shall be provided. The Contractor shall maintain
records of topics covered, records of who has carried out training and who has attended.
The Contractor shall provide technology transfer training for members of the
Employer's staff and visit to an overseas gas transmission company with an established
SCADA system in use. The visit shall consist of seminars, site visit and time spent
within control rooms viewing operations. The course shall demonstrate the benefits and
problems encountered when operating a complex gas transmission grid.
The training shall consist of
a)
b)
c)
SCADA Industry and Control Centre Visit and viewing live operations
d)
- 231 -
TRAINING
CODE
TITLE/CONTENT/OUTCOME
1
System Safety (1 day duration)
ATTENDEES
All Staffs
EXPERIENCE
None
Engineering
Degree Qualified.
Gas
Industry
experience
Sufficient
experience in the
gas
industry,
particularly gas
transmission.
It
shall familiarize
those
personnel with
responsibilities for managing plant operations or using
the data which is provided by the SCADA system.
Attendance
at
Course
2
Engineering
Degree Qualified.
Gas
Industry
Experience
- 232 -
TRAINING
CODE
5
TITLE/CONTENT/OUTCOME
ATTENDEES
for expansion or simple variations to the system.
SCADA Hardware Maintenance (4 weeks duration) SCADA
Hardware
The course shall be designed for technicians and
Technicians
engineers who are responsible for hardware
and Engineers
maintenance and troubleshooting of the SCADA
system. Hardware configuration shall be covered.
Upon completion participants shall be able to repair
and maintain SCADA equipment and commission new
equipment.
Instrument Technicians Course (4 weeks duration) Instrument
Technicians
The course shall be designed to familiarize technicians
with equipment such as energy metering, gas analysis
and intrinsic safety devices.
Upon completion technicians shall be able to carry out
calibration and simple maintenance operations.
Store Keepers
Material Control - Handling (1 week duration)
The course shall cover the essential materials control
handing activities such as inventory control, safe
handling and custody of materials. Handling of
equipment and stock keeping.
10
EXPERIENCE
Attendance
at
Course 2 Degree
qualified
in
electronics
/
electrical
engineering.
Attendance at
Course 2
Electrical
Engineering
Diploma
Experience
in
store keeping and
security
Experience
gained within the
gas sector at the
supervisor level.
- 233 -
TRAINING
CODE
11
TITLE/CONTENT/OUTCOME
ATTENDEES
quality audits, manage the calibration process and
prepare simple work instructions.
Operators
Leak Detection (2 weeks duration)
The course shall cover the Leak Detection application
software.
12
13
EXPERIENCE
Attendance in
course 2.
Engineering
Degree qualified.
Gas industry
experience.
- 234 -
TRAINING
15.
(PRICE SCHEDULE 1, 2, 3 AND 4 OF PART 1 SHALL BE FURNISHED BY THE BIDDER FOLLOWING THIS TABLE)
SL.
NO.
1
DESCRIPTION
LOCAL
COST IN
BDT
COST IN
USD
(MILLIONS)
REMARKS, IF ANY
SCHEDULE 1
PLANT & MANDATORY SPARES
SUPPLIED FROM ABROAD
Equipment Cost for SCADA System
including Factory Acceptance Test
(FAT), Quality Management System
(QMS) and Material Handling
Charges (Refer Equipment List 1)
Equipment Cost for Instrumentation
System
including
Factory
Acceptance Test (FAT), Quality
Management System (QMS) and
Material Handling Charges (Refer
Equipment List 2)
Equipment
Cost
for
Telecommunication
System
including Factory Acceptance Test
(FAT), Quality Management System
(QMS) and Material Handling
Charges (Refer Equipment List 3)
Equipment Cost for Electrical
System
including
Factory
Acceptance Test (FAT), Quality
Management System (QMS) and
Material Handling Charges (Refer
Equipment List 4)
Mandatory Spare Parts and Special
Tools & Tackle for SCADA,
Instrumentation, Telecommunication
and Electrical System
SCHEDULE 2
PLANT & MANDATORY SPARES
SUPPLIED FROM WITHIN THE
EMPLOYERS COUNTRY
Equipment Cost for SCADA System
including Factory Acceptance Test
(FAT), Quality Management System
(QMS) and Material Handling
Charges (Refer Equipment List 1)
Equipment Cost for Instrumentation
System
including
Factory
Acceptance Test (FAT), Quality
Management System (QMS) and
TECHNICAL SPECIFICATION : PART 2
SECTION VI. EMPLOYERS REQUIREMENTS
- 235 -
PRICE BREAK-UP
(PRICE SCHEDULE 1, 2, 3 AND 4 OF PART 1 SHALL BE FURNISHED BY THE BIDDER FOLLOWING THIS TABLE)
SL.
NO.
3
a
b
c
d
e
f
4
a
b
c
DESCRIPTION
LOCAL
COST IN
BDT
COST IN
USD
(MILLIONS)
REMARKS, IF ANY
- 236 -
PRICE BREAK-UP
(PRICE SCHEDULE 1, 2, 3 AND 4 OF PART 1 SHALL BE FURNISHED BY THE BIDDER FOLLOWING THIS TABLE)
SL.
NO.
DESCRIPTION
LOCAL
COST IN
BDT
COST IN
USD
(MILLIONS)
REMARKS, IF ANY
g
h
i
j
k
l
NOTES:
1.
For complete Scope of Work, Bidders are requested to refer other parts of Section-VI,
Part-2 of the Bid document.
2.
Bidder may add additional heads in the above table, if required to meet the entire scope of
work as available in Bid document.
3.
For Estimated BOQ, please refer to attached sheets. The items which are not covered in the
estimated BOQ but mentioned elsewhere in Section-VI, Part-2 of the Bid and any item
required to complete the scope of supply, works and services has to be included in the BOQ
of Bidder.
4.
5.
Contractor shall bring all installation tools, accessories, special tools, spares part etc. at his
own cost as required for the successful completion of the job.
- 237 -
EQUIPMENT LIST 1
(PRICE LIST FOR EACH ITEM TO BE FURNISHED BY THE BIDDER FOLLOWING THIS BOQ)
Description
1.
Quantity
Set
Set
Set
Set
Set
Set
(a1.7) Laser Colour Printer (Size: A3 size, Print : 20 pages / minute &
Network compatible)
Set
Set
(a1.9) Larger Screen Monitor (67 inch diagonal) with operator station
(Type : Flat panel LCD monitor with LED backlight)
Set
Lot
Set
Set
Set
Set
Set
Set
(a2.7) Laser Colour Printer (Size: A3 size, Print : 20 pages / minute &
Network compatible)
Set
Set
(a2)
- 238 -
(a2.9) Larger Screen Monitor (67 inch diagonal) with operator station
(Type : Flat panel LCD monitor with LED backlight)
(a2.10) Ethernet Cat-6 LAN Cables & Network components
including L3 core switch (1+1) configuration and L2 distribution
switch (1+1) configuration and patch panels, patch cords etc. in a
redundant LAN network
(a3) Monitoring 3 at Operating Companies HQ (OCT)
Set
Lot
(a3.1)
10
(a3.2)
10
Set
(a3.3)
10
Set
Set
Set
Set
32
Set
54
Set
Set
25
Set
(a4)
Set
(b) RTU
(b1) RTU (New Installation)
(b2) RTU (Remove and Installation)
(b3) RTU (Material Supply)
(b4)
Solar Panel
Set
EQUIPMENT LIST 2
(PRICE LIST FOR EACH ITEM TO BE FURNISHED BY THE BIDDER FOLLOWING THIS BOQ)
Instruments
1)
Pressure Transmitter
193
Set
2)
Temperature Transmitter
142
Set
3)
Differential Transmitter
208
Set
4)
33
Set
5)
127
Set
6)
61
Set
7)
Solenoid Valve
52
Set
8)
Junction Box
92
Set
9)
4000
meter
- 239 -
10)
11000
meter
11)
3000
meter
EQUIPMENT LIST 3
(PRICE LIST FOR EACH ITEM TO BE FURNISHED BY THE BIDDER FOLLOWING THIS BOQ)
EQUIPMENT FOR COMMUNICATION SYSTEM
(a) Communication System for MTS
(a1.1) 5.0-7.0 GHband IP radio & installation materials at MTS
location
11
Set
11
Set
(a1.3) 100 mtr long LDF-550A Coaxial cable with connector &
Lightning Arrestor
(a1.4) Telemetry Radio(Master) 382-392 MHz & installation
materials
11
Set
11
Set
11
Set
11
Set
11
Set
11
Set
11
Lot
11
Set
Set
Set
11
Set
11
Set
11
Set
11
Set
11
Set
11
Set
11
Set
11
Set
11
Lot
- 240 -
11
Set
11
Set
88
Set
88
Set
88
Set
88
Set
88
Set
88
Set
Set
Set
Set
Set
Set
Set
Set
Set
Set
10
Set
10
Set
Set
- 241 -
Set
25
Set
Set
25
Set
74
Set
Set
h. Tower
h1.40 meter high 4 legged self- supported tower with foundation
h2. Guy wire & necessary nut bolt accessories
h3.Supply of Ear thing cables (50 rm)
h4. Aircraft warning light system (5 no light with controller) &
necessary electric cable
EQUIPMENT LIST 4
Set
Lot
km
17
Set
(PRICE LIST FOR EACH ITEM TO BE FURNISHED BY THE BIDDER FOLLOWING THIS BOQ)
EQUIPMENT FOR Electrical SYSTEM
a.
Set
Set
Set
Set
Set
Set
Set
Set
Set
Set
Set
Set
Lot
Lot
b.
ACC, Ashuganj
c.
- 242 -
Set
d.
MTS location.
1.
10
Set
2.
Batteries
10
Lot
3.
10
Set
10
Lot
4.
e.
1.
10
Set
2.
Batteries
10
Lot
3.
10
Set
10
Lot
4.
f.
1.
88
Set
2.
Batteries
88
Lot
63
Lot
25
Set
3.
4.
NOTES:
1.
Bidder may add additional items in the above tables, if required to meet the entire scope of
work as available in Bid document.
- 243 -
TECHNICAL SCHEDULE TO BE
FILLED BY THE BIDDER
The information sought out in this Section shall be furnished by the Tenderer in the format specified by
typing out answers to the questionnaire at the appropriate spaces allotted. The authorized representative
of the Tenderer must properly sign these as verification of the data submitted. These signed pages shall
be a part of the Tenderers original Proposal. Other copies of the proposal shall contain prints of these
sheets duly filled in. Failure to comply with the above requirement may result in rejection of the
Proposal.
Additional sheets may be used, if necessary.
TECHNICAL PARTICULARS
REMOTE TERMINAL UNIT (RTU)
Sl.
No.
Description
Bidder Compliance
Make
Model No.
Processor
Communication Speed
RAM
Display Monitor
MTBF / MTTR
10
Battery Back-up
11
Communication Ports
12
Communication Protocol
13
Accuracy
1 of 26
TECHNICAL SCHEDULE TO BE
FILLED BY THE BIDDER
Sl.
No.
Description
Isolation
14
15
16
Bidder Compliance
Load
Accuracy
Isolation
Isolation
Interposing Relays
17
18
Degree of Protection
19
20
Operating RH Range
2 of 26
TECHNICAL SCHEDULE TO BE
FILLED BY THE BIDDER
Sl.
No.
Description
Bidder Compliance
21
22
Doors
23
Terminal Blocks
24
Indicators
25
26
27
28
29
30
Description
01.
Make
02.
Model No.
03.
Operating System
04.
CPU (*)
05.
Cache (*)
06.
RAM (*)
07.
08.
Display
Bidder Compliance
3 of 26
TECHNICAL SCHEDULE TO BE
FILLED BY THE BIDDER
Sl.
No.
Description
Bidder Compliance
09.
DVD drive
10.
Power Supply
11.
Expansion Slots
12.
Interface (*)
13.
Wireless Connectivity
14.
Keyboard
15.
Durability Features
16.
Security Features
17.
Note: (*) Bidder shall supply latest hardware and software configuration available at the time of actual
supply.
SCADA SERVER AND WEB SERVER (*)
Sl. No.
Description
01.
Make
02.
Model No.
03.
Operating System
04.
CPU (*)
05.
Cache (*)
06.
RAM (*)
07.
08.
Display
09.
DVD drive
10.
Power Supply
Bidder Compliance
4 of 26
TECHNICAL SCHEDULE TO BE
FILLED BY THE BIDDER
Sl. No.
Description
Bidder Compliance
11.
Expansion Slots
12.
Interface (*)
13.
Wireless Connectivity
14.
Keyboard
15.
Durability Features
16.
Security Features
17.
Note: (*) Bidder shall supply latest hardware and software configuration available at the time of actual
supply.
HMI WORK STATIONS
a)
CPU
Sl. No.
Description
01.
Processor
02.
Memory
03.
Hard drive
04.
Floppy drive
05.
06.
Audio controller
07.
Operating system
b)
Bidder Compliance
Monitor
Sl. No.
Description
01.
Type
02.
Screen diagonal
03.
Display
Bidder Compliance
5 of 26
TECHNICAL SCHEDULE TO BE
FILLED BY THE BIDDER
Sl. No.
Description
04.
Resolution
05.
Degree of protection
06.
External Controls
07.
Power supply
08.
Version
c)
Bidder Compliance
Sl. No.
Description
Bidder Compliance
01.
Type
02.
Life Expectancy
03.
Version
04.
Mouse
LASER PRINTER
Sl. No.
Description
Bidder Compliance
01.
Type
02.
Paper size
03.
Speed
04.
Resolution
05.
Duty cycle
06.
07.
08.
Communication port
09.
Accessories
6 of 26
TECHNICAL SCHEDULE TO BE
FILLED BY THE BIDDER
Port Density
Performance
VLAN
Multicast Support
Quality Of Service
Security
01.
02.
03.
04.
05.
06.
Resiliency
07.
Management Feature
08.
Electrical Approvals and Compliances
09.
10.
Environmental Specifications
11.
LAN interface
Access method
Address table
01.
02.
03.
04.
05.
Routing and Multicast
06.
Security and other important features
07.
Reliability
08.
Quality of Service (QoS)
09.
10.
Processor &Memory
11.
Interface connector
12.
Power supply
13.
14.
15.
Power consumption
IPv6
Approvals and Compliances
7 of 26
TECHNICAL SCHEDULE TO BE
FILLED BY THE BIDDER
FLOW COMPUTER
Sl.
No.
Description
Bidder Compliance
Make
Model No.
Processor
Display Type
Interface
Keypad
Output
Computation
Standards Complied
10
Engineering Units
11
Scan Time
12
Security
13
Diagnostic
14
Power Supply
15
Degree of Protection
16
17
Operating RH Range
Description
01.
Working Principle
Bidder Compliance
:
8 of 26
TECHNICAL SCHEDULE TO BE
FILLED BY THE BIDDER
Sl. No.
Description
Bidder Compliance
02.
Type
03.
Output signal
04.
05.
Measuring element
06.
Element material
07.
Over Pressure
08.
Turn-down ratio
09.
10.
Enclosure
11.
Output Indicator
12.
Body
13.
Operating Voltage
14.
Load
15.
Performance :a)
Accuracy
b)
Repeatability
c)
Response time
d)
e)
Stability
16.
Process connection
17.
Sealing / Isolation
18.
Nameplate
19.
Process connection
20.
Sealing / Isolation
21.
Nameplate
22.
Accessories
9 of 26
TECHNICAL SCHEDULE TO BE
FILLED BY THE BIDDER
Sl. No.
Description
Bidder Compliance
Description
Bidder Compliance
01.
Type
02.
Output Signal
03.
Material of Construction
04.
05.
Linearity
06.
Repeatability
07.
Mounting
08.
Enclosure
Transmitter
Sl. No.
Description
01.
Electronics
02.
Power Supply
03.
Input
04.
Display
05.
Output
06.
Measuring Accuracy
07.
Totalized Value
08.
Housing
09.
Nameplate
Bidder Compliance
10 of 26
TECHNICAL SCHEDULE TO BE
FILLED BY THE BIDDER
10.
Accessories
Description
Bidder Compliance
01.
Type
02.
03.
Movement Material
04.
Case Material
05.
Dial Size
06.
Scale
07.
Window
08.
Range Selection
09.
Over-range Protection
10.
Adjustment
11.
Element Connection
12.
Process Connection
13.
Performance
14.
Safety Feature
15.
Accessories
16.
Applicable standard
17.
18.
Nameplate
TEMPERATURE GAUGE
Sl. No.
Description
01.
Type
Bidder Compliance
:
11 of 26
TECHNICAL SCHEDULE TO BE
FILLED BY THE BIDDER
Sl. No.
Description
Bidder Compliance
02.
03.
Stem Diameter
04.
Stem Material
05.
06.
Case Material
07.
Dial Size
08.
Scale
09.
Pointer
10.
Dampener
11.
Mounting
12.
13.
Dial connection
14.
Range
15.
Zero adjuster
16.
Window
17.
Accuracy
18.
Enclosure Class
19.
Accessories
20.
Nameplate
Description
01.
Type
02.
Resistance
03.
Base
Bidder Compliance
12 of 26
TECHNICAL SCHEDULE TO BE
FILLED BY THE BIDDER
Sl. No.
Description
04.
Wiring
05.
Protecting Tube :-
Bidder Compliance
:
a)
O.D.
b)
Material
c)
Filling
06.
Calibration
07.
Characteristics
08.
Head :a)
Type
b)
Material
c)
Terminal blocks
d)
Cable connection
e)
Instrument connection to
well
f)
Others
09.
Accessories
10.
Nameplate
THERMOWELL
Sl. No.
Description
01.
Material
02.
Process connection
03.
04.
Bore Connection
05.
Identification Mark
06.
Surface Treatment
07.
Element Connection
08.
Certification
Bidder Compliance
13 of 26
TECHNICAL SCHEDULE TO BE
FILLED BY THE BIDDER
Sl. No.
Description
09.
Accessories
Bidder Compliance
:
Description
01.
Working Principle
02.
Type
03.
Input
04.
Isolation
05.
Output Signal
06.
07.
08.
Enclosure Class
09.
Output Indicator
10.
Span Adjustability
11.
Nameplate
12.
Body
13.
Operating Voltage
14.
Load
15.
Performance :-
16.
Bidder Compliance
a)
Accuracy
b)
Repeatability
c)
Cold
Compensation
d)
Calibration
Junction
Accessories
:
:
:
14 of 26
TECHNICAL SCHEDULE TO BE
FILLED BY THE BIDDER
Description
Bidder Compliance
01.
Type
02.
Configuration
03.
Charger
04.
05.
Battery
06.
Backup time
07.
Inverter capacity
08.
Overload capacity
09.
Sizing
10.
11.
Harmonic
12.
Efficiency
13.
Synchronization limit
14.
Inverter protection
15.
Load sharing
16.
Static switch
17.
18.
Diagnostic alarms:
19.
Accessories
20.
Description
Type of enclosure
TECHNICAL SPECIFICATION : PART 2
Bidder Compliance
:
15 of 26
TECHNICAL SCHEDULE TO BE
FILLED BY THE BIDDER
Sl. No.
Description
Bidder Compliance
02.
No. of ways
03.
Material
04.
Type of cover
05.
Gasket
06.
Mounting
07.
Cable entry
08.
Grounding
09.
10.
Identification
11.
Accessories
12.
CABLE GLAND
Sl. No.
Description
Bidder Compliance
01.
Type
02.
Entry Thread
03.
Material
04.
Finish
05.
Protection
06.
Accessories
07.
Description
Bidder Compliance
01.
Material
02.
Thickness
16 of 26
TECHNICAL SCHEDULE TO BE
FILLED BY THE BIDDER
Sl. No.
Description
Bidder Compliance
03.
Finish
04.
Perforation
05.
Cover
06.
IP RADIO
Sl. No. Description
Bidder Compliance
01.
Frequency band
02.
Output power
03.
Modulation method
04.
Interface
05.
Transmission speed
06.
07.
08.
Mechanical configuration
07.
Antenna size/gain
07.
Equipment Protection
07.
Operating Temperature
07.
Humidity
07.
Wind Survival
TELEMETRY RADIO
Sl. No. Description
Bidder Compliance
01.
02.
Operation mode
17 of 26
TECHNICAL SCHEDULE TO BE
FILLED BY THE BIDDER
Sl. No.
Description
Bidder Compliance
03.
Protection
05.
Output power
06.
Modulation method
07.
Output Impedance
08.
Interface
09.
Transmission speed
10.
Receiver Sensitivity
11.
Receiver Selectivity
12.
Duty Cycle
13.
14.
15.
16.
Antenna size/gain
17.
Equipment Protection
18.
Operating Temperature
19.
Humidity
20.
Bidder Compliance
18 of 26
TECHNICAL SCHEDULE TO BE
FILLED BY THE BIDDER
Sl. No.
Description
01.
Operation
02.
Antenna Connector
03.
05.
06.
07.
08.
EMC
09.
10.
Data Features
11.
Serial interfaces
12.
Degree of Protection :-
13.
Operating temperatures
14.
Humidity :-
15.
Operation
16.
Antenna Connector
17.
18.
19.
20.
21.
EMC
22.
23.
Data Features
24.
Serial interfaces
25.
Degree of Protection :-
26.
Operating temperatures
Bidder Compliance
19 of 26
TECHNICAL SCHEDULE TO BE
FILLED BY THE BIDDER
Sl. No.
Description
27.
Humidity
Bidder Compliance
IP PABX
Sl. No. Description
Bidder Compliance
01.
Outside lines
02.
Extension lines
03.
Power supply
05.
Backup battery
06.
Mechanical construction
07.
Features
a) Station Call
b) Abbreviated Dialing
c) Authorization Codes
d) Automatic Call Back
e) Voice Guided Assistance
Announcement System
f) Malicious Call Tracing / Record
g) Direct Inward / Outward Station
Access
h) Class of Service, Direct Inward /
outward Dialing
i)
Class of Restriction
j)
Auto Attendant
Distinctive Ringing
m) Music on Hold
n) System Traffic Reports
20 of 26
TECHNICAL SCHEDULE TO BE
FILLED BY THE BIDDER
Sl. No.
Description
Bidder Compliance
Hotline Facility
u) Fixed-Mobile Interface
Bidder Compliance
01.
02.
07.
EI signal format
09.
E1 Electrical Interface
10.
Jitter
11.
13.
Ethernet standard
14.
Power supply
15.
Power consumption
16.
Mechanical construction
17.
18.
Bidder Compliance
01.
Weight of cables
02.
Tensile Strength
21 of 26
TECHNICAL SCHEDULE TO BE
FILLED BY THE BIDDER
Sl. No.
Description
03.
05.
Nominal DC Resistance
06.
07.
Nominal Capacitance
09.
10.
Nominal Attenuation
11.
Insulation Resistance
12.
13.
14.
Nominal Size:
15.
SEAL OF THE
COMPANY
Bidder Compliance
Signature
....................................................
Name
....................................................
Designation
....................................................
22 of 26
TECHNICAL SCHEDULE TO BE
FILLED BY THE BIDDER
SL.NO.
QUANTITY OFFERED
01.
02.
03.
04.
05.
06.
07.
08.
09.
10.
SEAL OF THE
COMPANY
Signature
....................................................
Name
....................................................
Designation
....................................................
23 of 26
TECHNICAL SCHEDULE TO BE
FILLED BY THE BIDDER
The Tenderer shall tabulate below the item wise list of Drawings to be furnished by him for the
equipment / items supplied under this Specification. Add more sheets, if required. Tenderer shall strictly
follow this format.
Sl.No.
Description of Drawings
01.
02.
03.
04.
05.
06.
07.
08.
09.
10.
The Tenderer shall also furnish the time in weeks for resubmission of reviewed / commented drawings
from Owner from date of receipt.
SEAL OF THE
COMPANY
Signature
....................................................
Name
....................................................
Designation
....................................................
24 of 26
TECHNICAL SCHEDULE TO BE
FILLED BY THE BIDDER
PROGRESS SCHEDULE
The Bidder shall indicate the time required for different phases of work in the fashion below. Time shall
be mentioned in weeks taking the date of issue of Letter of Intent as datum.
SL NO.
DESCRIPTION
01.
02.
03.
Start manufacture
04.
05.
06.
Complete manufacture
07.
08.
09.
Start Shipment
10.
Complete Shipment
11.
Start Erection
12.
Complete Erection
13.
14.
SEAL OF THE
COMPANY
Signature
....................................................
Name
....................................................
Designation
....................................................
25 of 26
TECHNICAL SCHEDULE TO BE
FILLED BY THE BIDDER
DEVIATION SHEET
If the proposal submitted by Bidder has got any deviation from the stipulations in the tender document,
Bidder shall tabulate below the full particulars of these deviations and shall sign below. Additional
sheets may be added, if necessary. Terms such as refer covering sheet / catalogue etc. shall not be
accepted. In absence of any duly filled in complete Deviation Sheet, it will be understood and agreed
that Bidder has no deviation whatsoever with regard to specification and stipulation of the specification
will be binding on Bidder in case of any discrepancy between the specification and the proposal
submitted by Bidder. Bidder shall strictly follow this format.
Serial No.
Bid /
Specification
Section
Specification
Clause No. /
Page No.
Technical Deviation
Remarks
Notes:
1.
Bidder shall furnish a consolidated list of deviations / clarifications / comments of all sections of
the bid package, which for an appropriate offer are considered unavoidable by him.
2.
Deviations / clarifications mentioned elsewhere in the offer shall not be binding on the Client /
Consultant and any such deviations if indicated elsewhere other than this form will render the offer
non-responsive and shall liable to be rejected.
3.
Bidder shall state the reasons for the deviations in the Remarks column.
SEAL OF THE
COMPANY
Signature
......................................................
Name
......................................................
Designation
......................................................
26 of 26
TECHNICAL SCHEDULE TO BE
FILLED BY THE BIDDER