SARAYA AQABA PROJECT

AQABA HASHEMITE KINGDOM OF JORDAN

VOLUME 2
SPECIFICATIONS
DIVISION 1 GENERAL REQUIREMENTS

Employer:

SARAYA AQABA REAL ESTATE COMPANY

Prepared by:

D. G. JONES & PARTNERS (M.E.) LTD

MAY 2012

Saraya Aqaba

Specifications
VOLUME 2 SPECIFICATIONS
TABLE OF CONTENTS

DIVISION 1 - GENERAL REQUIREMENTS


01100
01230
01310
01320
01322
01330
01400
01420
01500
01600
01700
01731
01770
01781
01782
01810
01815
01820

SUMMARY
ALTERNATES
PROJECT MANAGEMENT AND COORDINATION
CONSTRUCTION PROGRESS DOCUMENTATION
PHOTOGRAPHIC DOCUMENTATION
SUBMITTAL PROCEDURES
QUALITY REQUIREMENTS
REFERENCES
TEMPORARY FACILITIES AND CONTROLS
PRODUCT REQUIREMENTS
EXECUTION REQUIREMENTS
CUTTING AND PATCHING
CLOSEOUT PROCEDURES
PROJECT RECORD DOCUMENTS
OPERATION AND MAINTENANCE DATA
GENERAL COMMISSIONING REQUIREMENTS
HVAC COMMISSIONING REQUIREMENTS
DEMONSTRATION AND TRAINING

This document contains the general requirements for the whole project and shall be read in conjunction with all
other Specifications Divisions 2 to 16 (inclusive) issued separately.

TABLE OF CONTENTS
Volume 2

TOC Page 1 of 1
May 2012

Saraya Aqaba

Specifications

SECTION 01100 - SUMMARY

PART 1 - GENERAL

1.1

RELATED DOCUMENTS
A.

1.2

Drawings and general provisions of the Contract, including General and Particular Conditions and
other Division 1 Specification Sections, apply to this Section.

SUMMARY
A.

B.

1.3

This Section includes the following:1.

Work covered by the Contract Documents.

2.

Type of the Contract.

3.

Work phases.

4.

Work under other contracts.

5.

Use of premises.

6.

Work restrictions.

7.

Specification formats and conventions.

8.

Pricing and measurement issues

Related Sections include the following:1.

Division 1 Section "Temporary Facilities and Controls" for limitations and procedures
governing temporary use of Employer's facilities.

2.

All other Sections from Division 2 to revision 16.

WORK COVERED BY CONTRACT DOCUMENTS


A.

Project Location: Aqaba in Hashemite Kingdom of Jordan

B.

Project Identification:1.

Some works have already been executed. Work under this Contract comprises the execution
and completion of all the remaining works.

2.

Project comprises the following:-

SUMMARY
Volume 2

a.

Infrastructure - Zone J
1)
Edge Fence
2)
North, South and East Gates
3)
Remaining Infrastructure Works

b.

Lagoon - Zone Y
1)
Lagoon
2)
Submerged Breakwater
3)
Lighthouse
4)
Marine Walls
5)
Water Ways
6)
Water Taxi
Note: Ruins are still indicated on drawings but are cancelled as per Employers
request.
01100 Page 1 of 7
May 2012

Saraya Aqaba

Specifications
c.

Pump House - Zone Y


1)
Pump House and Culvert
2)
Intake Pipeline

d.

Hotels
1)
Qasr Hotel - Zone A and on shore villa(s)
2)
Qalaa Hotel - Zone F
3)
Harbor Hotel - Zone V
4)
Lighthouse Hotel - Zone W and on shore villa(s)

e.

Villas and Townhouses


1)
Villas - Zone E
2)
Villas - Zone G
3)
Villas - Zone H
4)
Townhouses - Zone S

f.

Residential
1)
Residential Buildings - Zone I3
2)
Residential Buildings - Zone K
3)
Residential Buildings - Zone R
4)
Residential Buildings - Zone R1

g.

Mixed Use
1)
Conference Center - Zone B
2)
Offices Building - Zone L
3)
Old City - Zone M
4)
Beach Club - Zone T

h.

Other Complexes
1)
Water Park - Zone I12
2)
Sports Complex - Zone P
3)
Technical Building - Zone U
4)
Staff Facilities

C.

Employer: Saraya Aqaba Real Estate Development Company PSC.

D.

Design Consultants: As indicated on drawings for each Zone. These Design Consultants may require
approval by the Employer in case the Contractor desires to engage any of them for remaining
designs/redesigns required under the Contract.

E.

Project Background:-

F.

1.

The Saraya Aqaba Project consists of a 5 star resort/village development to be constructed


around a man-made lagoon with white sand beaches on the shores of the Red Sea on
approximately a 617,345 square meters on-site parcel of land, and staff facilities parcel of
land. Overall, the development will include luxurious facilities that include 5-star hotels and
staff facilities, a mix of residential units ranging from villas to town houses and apartments, a
mixed use area comprising beach club, old City Souq, conference center, office building, and
a water park, technical area, and sports complex; more particularly described in the Contract
Documents. Given the tight schedule, the Project delivery method is fast track.

2.

Jumeirah - the Dubai-based luxury hospitality group will operate 2 out of the four 5-star
luxury hotels, in addition to the water park. Starwood hotels & resorts worldwide will operate
the two remaining 5-star hotels under its "Luxury Collection" and Westin brands.

3.

The Project is a collaboration of the private and public sectors, with the ultimate purpose of
enhancing the physical, economic and social well-being of Jordan, thereby playing a crucial
role in driving the growth and sophistication of the Jordanian tourism sector.

Critical Elements of the Works:1.

SUMMARY
Volume 2

The Contractor shall be fully capable, equipped and qualified and shall take into
consideration, provide solutions, handle and resolve issues related to the following critical
items that might affect the Works during the Project life cycle including, without limitation:
01100 Page 2 of 7
May 2012

Saraya Aqaba

Specifications
a.
b.
c.
d.

G.

H.

Project Scope:1.

The Contractor shall provide all design/redesign (as required under the Contract), procurement
and construction services including designs, drawings, specifications, consultant engineers,
specialty consultants, architectural, interior decorating designers, lighting and acoustic
consultants, landscape consultants, supervision team, quality control team and construction
methodologies & operations. In addition to testing and commissioning, labor, materials, and
equipment needed to completely construct and operate the Project in accordance with the
Contract Documents and international codes / specifications.

2.

The Contractor shall scrutinize the following requirements for Project goals. The Project
Work includes, but is not limited to the following items:

The Project Site:1.

I.

Earthquake fault zone which lies within the site boundaries;


The western boundary of the site adjacent to the Royal family palace complex;
Archaeological sites within the Project Site boundaries;
Marine works environmental and hydrological issues, the quality of water, and overall
environmental regulations at / around the Project Site and as per the approved
Environmental Impact Assessment.

The Project Site is located along the northern coastline of the Gulf of Aqaba. The Project Site
includes parking areas, roads, electro-mechanical. services, in addition to excavation and
construction of a lagoon surrounded with white sand beaches. The scope of the Works
includes the design and construction of staff facilities that will be used to accommodate the
Operators staff (approximately 4,000 Employees) and various Projects services..

Buildings and Structures:1.

The buildings to be constructed on the Project Site and staff facilities land comprise a mix of
luxury hotels, luxury residential, Grand Villas, Villas, Townhouses, Duplexes, Apartments,
Lofts, Sports & Leisure, Water Park, Old Souk, Offices, Conference Center, Commercial &
Civic, retail and leisure facilities together with the associated technical and ancillary buildings
and staff facilities in addition to other items. Some building, structures, and other works are
existing on Site and have been executed by other contractors previously employed by the
Employer. All Buildings and Structures (including Civil and Infrastructure Work) shall be
operated by the Employer; with the exception of those Operators listed below. Buildings and
structures are listed below:
a.

Hotels:
1)

The hotels shall be executed according to five stars international codes &
standards accepted. In addition, Operators manuals, design guides, brand
standards, codes and requirements shall be considered and complied with
during the execution of the hotels. The hotels are:
Qalaa Hotel Zone F
Qasr Hotel Zones A and A1
Harbor Hotel Zone V
Lighthouse Hotel Zones W and X

2)

b.

More details are listed in Operators Manuals & Requirements regarding the
hotels design criteria, specification, standards, codes and manuals.

Residential Buildings:
1)

SUMMARY
Volume 2

Operated by Jumeirah Hotel Group


Operated by Jumeirah Hotel Group
Operated by Starwood Group
Operated by Starwood Group

The residential buildings are a mix of grand villas, villas, townhouses, duplexes,
lofts and apartments that shall be executed to the highest quality standard and
shall comply with all applicable international standards and with the Contract
Documents. The residential buildings are located within a number of residential
01100 Page 3 of 7
May 2012

Saraya Aqaba

Specifications
zones, which have extensive landscape and waterways in keeping with the
prestigious nature of the Project.
c.

Commercial and Civic Facilities:


1)

d.

Sports and Leisure Facilities:


1)

e.

J.

K.

The sports and leisure facilities shall include an outdoor sports complex,
amphitheater, a water park, and a beach club associated with the lagoon. The
sports and leisure facilities shall be executed to a high quality standard in
accordance with the prestigious nature and Operator requirements of the Works.
The water park shall be operated by Jumeirah Hotel Group.

Technical and Ancillary Buildings:


1)

f.

The commercial and civic buildings and facilities shall include a conference
center, old city souks, retail and offices, that shall be executed to a high quality
standard and shall fit within the overall theme of the project.

Technical and ancillary buildings are required for the efficient management and
operation of the Project. These buildings will include plant rooms, other service
and operation and maintenance buildings in addition to security facilities. Note:
Part of technical Zone U is used for the District Cooling Plant.

Staff Facilities:
1)

Staff facilities are to be designed and constructed on a site to be provided by the


Employer. The facilities shall comprise residential accommodation for
Operators staff (approximately 4,000 employees) and various facilities for
hotel operations.

2)

The standard and design criteria of the buildings shall be in accordance with the
Contracts and Operators Requirements.

Civil and Infrastructure Works:1.

The Project is to be contained within a secured gated complex. A lagoon with a white sand
beach side areas shall be provided and connected to a network of channels and ponds located
in the residential zones including all associated marine works onshore and offshore. An
underground tunnel has been built to access cars to underground parking. The Works shall
include all services networks comprising of high & medium voltage, low voltage, street
lighting, communication systems, low current distribution, storm water, sewage, domestic
water, fire fighting, irrigation, chilled water and other systems.

2.

Some civil and infrastructure works are existing on Site and have been executed by other
contractors previously employed by the Employer.

3.

Civil and infrastructure works shall be executed to a high quality in keeping with the overall
prestigious development and in accordance with all applicable local and international codes
and standards.

Scope Delivery Plan:1.

SUMMARY
Volume 2

The Contractor shall make sure that the scope of the Project includes all design, works and
processes required to ensure that the Project is completed successfully.

01100 Page 4 of 7
May 2012

Saraya Aqaba
1.4

Specifications

TYPE OF CONTRACT
A.

1.5

Refer to the Conditions of Contract.

WORK PHASES
A.

1.6

Refer to the Conditions of Contract.

WORK UNDER OTHER CONTRACTS


A.

1.7

Refer to the Conditions of Contract.

USE OF PREMISES
A.

1.8

Use of Site: Limit use of premises to areas within the Contract limits indicated. Do not disturb
portions of Project site beyond areas in which the Work phasing is indicated.
1.

Employer Occupancy: Allow for Employer occupancy of Project site for other work
operations, comply with the terms of Conditions of Contract.

2.

Driveways and Entrances: Keep driveways, parking areas, loading areas, and entrances
serving premises clear and available to Employer, Engineer and their employees and
emergency vehicles at all times. Do not use these areas for parking or storage of materials.
a.

Schedule deliveries to minimize use of driveways and entrances.

b.

Schedule deliveries to minimize space and time requirements for storage of materials
and equipment on-site.

WORK RESTRICTIONS
A.

On-Site Work Hours: Work shall be generally performed during normal business working hours as
indicated or stipulated in the Conditions of Contract.

B.

Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Employer or
others unless permitted under the following conditions and then only after arranging to provide
temporary utility services according to requirements indicated:

1.9

1.

Notify Engineer not less than two days in advance of proposed utility interruptions.

2.

Do not proceed with utility interruptions without Engineers written permission.

SPECIFICATION FORMATS AND CONVENTIONS


A.

Specification Format: The Specifications are organized into Divisions and Sections using the 16division format and CSI/CSC's "MasterFormat" numbering system.
1.

Section Identification: The Specifications use Section numbers and titles to help crossreferencing in the Contract Documents. Sections in the Project Specifications are in numeric
sequence; however, the sequence is incomplete because all available Section numbers are not
used. Consult the table of contents at the beginning of the Project Specifications to determine
numbers and names of Sections in the Contract Documents.

2.

Division 1: Sections in Division 1 govern the execution of the Work of all Sections in the
Specifications.

3.

Terms in Division 1 shall not take precedence over the terms of the Conditions of Contract.

SUMMARY
Volume 2

01100 Page 5 of 7
May 2012

Saraya Aqaba
B.

Specifications

Specification Content: The Specifications use certain conventions for the style of language and the
intended meaning of certain terms, words, and phrases when used in particular situations. These
conventions are as follows:
1.

Abbreviated Language: Language used in the Specifications and other Contract Documents is
abbreviated. Words and meanings shall be interpreted as appropriate. Words implied, but not
stated, shall be inferred as the sense requires. Singular words shall be interpreted as plural, and
plural words shall be interpreted as singular where applicable as the context of the Contract
Documents indicates.

2.

Imperative mood and streamlined language are generally used in the Specifications.
Requirements expressed in the imperative mood are to be performed by Main Contractor.
Occasionally, the indicative or subjunctive mood may be used in the Section Text for clarity to
describe responsibilities that must be fulfilled indirectly by Main Contractor or by others when
so noted.
a.

1.10
A.

PRICING AND MEASUREMENT ISSUES


Method of Measurement Used
1.

B.

C.

D.

The words "shall," "shall be," or "shall comply with," depending on the context, are
implied where a colon (:) is used within a sentence or phrase.

The quantities contained in the Bills of Quantities have been prepared in accordance with the
Principles of Measurement (International) for Works of Construction, June 1979 POMI as
published by the Royal Institution of Chartered Surveyors and as amended or amplified in the
Pricing and Measurement Preambles section in the Bills of Quantities. The Contractor is
deemed to have interpreted the intent of this document and understood all the nuances to
enable each and every item included in the Bills of Quantities to be fully and correctly priced,
since no claim will be entertained in the event of misinterpretation.

Measurements Generally
1.

All quantities contained in the Bills of Quantities are provided in good faith to give a
reasonable indications of the works shown on the Drawings.

2.

The quantities given in the Bills of Quantities shall not be used as a basis for ordering
materials. The Contractor shall make his own assessment of quantities of materials to be
ordered based upon the drawings and specifications.

3.

Quantities shall NOT be re-measured. The Contract is a LUMP SUM CONTRACT. The
Contractor shall be responsible to check the quantities before submitting his tender. In case of
discrepancies, the Contractor shall prepare schedule of omissions and additions to be added in
a separate document attached to his offer. Re-measurement will be carried out ONLY for
variation purposes.

4.

Unless otherwise stated, all works have been measured net. No allowances have been made
for waste, working space, bulking, shrinkage and the like.

Prime Cost (P.C.) Rates and (P.C.) Sums


1.

Where Prime Cost (P.C.) rate or P.C. sum are given in an item description in the Bills of
Quantities, it shall mean that the P.C. rate or P.C. sum is ONLY for the anticipated cost of
material to be selected ex-factory. The Contractor shall add to this P.C. rate or P.C. sum the
on-costs such as transport, customs, waste, cutting, handling, fixing accessories, polishing,
grouting, pointing, sealants, grooves, throats, perforations, installation, profit, overheads, etc...

2.

Should the P.C. rate or P.C. sum vary, the other costs as mentioned here above or any other
costs shall not be varied in any way.

Provisional Sums (P.S.)

SUMMARY
Volume 2

01100 Page 6 of 7
May 2012

Saraya Aqaba

E.

Specifications

1.

Provisional Sums are sums provided for work or for costs which cannot be entirely foreseen,
defined or detailed at the time the tendering documents are issued.

2.

The Provisional Sum shall cover the total cost of a section of work known to be required but
the extent of which is uncertain and shall be spent totally, in part or not at all at the discretion
of the Engineer pursuant to the provisions of the Contract.

Pricing Generally
1.

The Contractor shall, during his study of the Tender, address his queries, if any, to the
Engineer, who will study and clarify all such queries. Should the Contractor during his study
of the Tender, consider that there is any shortage, error or inconsistency in the Contract
Documents, which would affect the rates of his Tender, or the value of the works, the
Contractor must have all such points clarified by the Engineer before submitting his Tender.

2.

The Contractor shall satisfy himself as to the meaning of every item in the Bills of Quantities
and the rates and prices inserted by him will be deemed to cover all his obligations under the
Contract (Specifications, Drawings, Conditions of Contract, any Addenda, and other contract
documents) and all matters and things necessary for the proper construction, completion and
maintenance of the works including (but not by way of limitation), for all temporary work
required (including any that may be required by Sub-Contractors, whether nominated or
otherwise).

3.

The Contractor's price shall include for all materials and labour, storage and handling
transportation, samples, testing coordination and for the provision and use of all plant, whether
mechanical or non-mechanical, required for carrying out of the works, in their proper
sequence, for shifting, altering and adapting such temporary work and plant as may be
required the progress of the works, and for removing plant and temporary works at completion
and making good any surfaces disturbed.

4.

The Contractor's price shall include for the Guarantees and bonds required; for the costs of
preparing a tender; for the final account; for overheads and profit; for customs and import
duties; for temporary services and for all other statutory tax and establishment charges and
costs of whatever nature. No claim for additional payment will be allowed for any error or
misunderstanding by the Contractor in these respects.

PRODUCTS (Not Used)

PART 2 - EXECUTION (Not Used)

END OF SECTION 01100

SUMMARY
Volume 2

01100 Page 7 of 7
May 2012

Saraya Aqaba

Specifications

SECTION 01230 - ALTERNATES

PART 1 - GENERAL

1.1

RELATED DOCUMENTS
A.

1.2

Drawings and general provisions of the Contract, including General and Particular Conditions and other
Division 1 Specification Sections, apply to this Section.

SUMMARY
A.

This Section includes administrative and procedural requirements for:


1.
2.
3.
4.

Any designs/redesigns required from the Contractor for Alternates due to Value Engineering (VE)
or Cost Saving proposals included in the Contract;
Finalizing, as per the Contract, the existing designs by the Contractor;
Any designs/redesigns required from the Contractor, as per the Contract, for any part of the
Permanent Works; or
Design proposals or solutions provided by the Contractor.
All the above are deemed included in the Contract Amount and shall be performed, at the
Contractors cost, in accordance with the Conditions of Contract, the Specifications, and other
Contract Documents and requirements, Design Briefs, to the approval of the Employer, Engineer
and if applicable the Operators who are concerned with the designs.

1.3

DEFINITIONS
A.

1.4

Alternates: Finalization, changes and savings proposed during tendering due to Value Engineering (VE)
or Cost Saving proposals, accepted by the Employer and Operator and incorporated into the Contract,
either in the design or construction to be completed or in the products, materials, equipment, systems, or
installation methods described in the Contract Documents.

PROCEDURES
A.

Coordination: Modify or adjust affected adjacent work as necessary to completely integrate into the
Project the works of approved alternates and other approved designs/redesigns described under item 1.2
above.
1.

Include miscellaneous devices, accessory objects, and similar items incidental to or required for a
complete installation whether or not indicated as part of the approved alternates or other approved
designs/redesigns described under item 1.2 above.

B.

Notification: Immediately following award of the Contract, notify each party involved, in writing, of the
status of each alternate, and include a complete description of alternates.

C.

Execute accepted alternates and other approved designs/redesigns under the same conditions as other
work of the Contract.

ALTERNATES
Volume 2

01230 Page 1 of 32
May 2012

Saraya Aqaba

Specifications

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.

DESIGN / REDESIGN REQUIREMENTS


A.

3.1

This section applies, as applicable, for any design (including redesign) required or to be performed by the
Contractor under the Contract or described under item 1.2 above.

DESIGN COORDINATION
A.

3.2

The Contractor shall prepare designs, specifications, and calculations for the approval of the Engineer and
Operator and shall keep the Engineer informed of Design development, changes, or Operators
Requirements.

REQUIREMENTS OF CONTRACTORS TEAM


A.

The Contractor shall engage as part of its services, and at its own cost and expense, such reputable and
qualified architects, design sub-consultants, engineers, interior decorators, lighting, acoustic and
landscape consultants and other professionals, specialists and consultants as may be necessary or
desirable to complete the Project, including all aspects of design, architecture, construction FF&E, SOE
and Operators equipment for the Project as required by the Contract Documents in accordance with the
Operators Requirements attached thereto. The appointment of consultants is subject to the approval of
the Employer, Engineer and if applicable the Operators who are concerned with the designs. The plans
and specifications shall be prepared by duly licensed architects and engineers, at the Contractors
expense, and in compliance with the Contract Documents, the laws and regulations of ADC, ASEZA and
Jordan.

B.

As at the date of the Contract, the Employer has approved the professionals, specialists and consultants
mentioned Division 1 Section "Summary who had previously performed some design works for the
contractor previously employed by the Employer, but such approval does not affect the Contractors
responsibility for all consultants, suppliers and sub-contractors appointed by him.

3.3

DESIGN PROCESS MANAGEMENT


A.

The Contractor shall provide design management services and shall coordinate the efforts and inputs of
all architectural and engineering disciplines. The Contractor, as part of his implementation of a design
management process shall:
1.

Establish detailed design functional programs and agree on design deliverables including
drawings, calculations, specifications and reports;

2.

Prepare detailed design schedules and identify critical milestones and major decision points;

3.

Monitor design progress, identify program divergence and recommend remedial actions;

4.

Issue submissions and collect and consolidate comments and monitor follow-up action and ensure
implementation;

ALTERNATES
Volume 2

01230 Page 2 of 32
May 2012

Saraya Aqaba

3.4

5.

Report on cost and time effects of design changes if requested by the Engineer;

6.

Set up regular design team meetings to resolve outstanding matters;

7.

Monitor the performance of all the consultants employed by the Contractor in respect of the
production of any deliverables necessary to meet the Project Schedule;

8.

Organize workshops for the design team and the Employer/Engineer/Operators to exchange ideas
and examine alternatives for the proposed design concepts;

9.

Enforce changes to the proposed and approved concepts and alternatives;

10.

Ensure that relevant information is exchanged and coordinated between the consultants;

11.

Coordinate all design and technical issues across projects;

12.

Implement and enforce standardization of standards to be complied with by design teams /


consultants;

13.

Provide all necessary design management not listed above but required for the proper and timely
delivery of all design services for the project.

DESIGN REVIEW PROCEDURES


A.

3.5

Specifications

The Contractor shall implement a Design Review Procedure as follows:


1.

Based on the Project Schedule, the Contractor shall provide an advance submissions schedule
indicating when to expect receipt of certain submissions. (This will help the various parties
organize its time better and put reviewers on notice).

2.

The Contractor shall provide all submissions in electronic format (both original files such as
drawings and high resolution jpegs and pdfs) including transmittal form listing content of each
submission.

3.

The Contractor shall provide hardcopies of all submissions delivered directly to their final
destination. Prior to a submission, the Engineer will agree with the Contractor on the distribution
list and the number of requested copies to be delivered to each address.

4.

Immediately after each submission or re-submission of the concept/schematic design (if any), the
Contractor shall schedule a presentation of the submitted material by its authors to the Engineer (if
deemed necessary by the Engineer) and where appropriate to the Employer and Operators.

5.

The Contractor will seek, co-ordinate and obtain approvals from the Operator, Engineer and
Employer. The Operator will need review periods as stated in the Technical Services Agreements
and the Engineer and Employer will need at least 10-15 business days to turn around their
comments to the Contractor from date of receipt by them.

6.

A workshop (if deemed necessary by the Engineer, Employer or Operators) is then scheduled to
review any outstanding comments and agree on next steps forward.

DESIGN REVIEWS

ALTERNATES
Volume 2

01230 Page 3 of 32
May 2012

Saraya Aqaba

A.

3.6

Specifications

The Engineer, Employer and/or the Operators and other consultants employed by these parties will
perform reviews of design submissions to verify adherence to Contract requirements and to the Contract
Documents and related criteria. The Contractor shall also give local code officials the opportunity to
review and comment on submissions as applicable. Design reviews are not to be interpreted as resulting
in an approval of the Contractors apparent progress toward meeting the Contract requirements or
complying with code requirements; but rather, they are intended to discover any information which can
be brought to the Contractors attention which might prevent costly errors and misdirection. The
Contractor shall remain completely responsible for all designs, required or to be performed by the
Contractor under the Contract, in full to accord with the Contract requirements. Disapproved materials
will be required to be resubmitted after correction, at no additional cost to the Employer. The Contractor
shall coordinate all disciplines as appropriate to reflect the Engineers comments.

MEETINGS, CONFERENCES AND PRESENTATIONS


A.

B.

3.7

Beside routine, operational Project management meetings required under the Contract, the Contractor
shall be responsible for meeting with and making presentations to the Engineer, Employer, Operators,
officials, boards of directors, and other parties as determined by the Engineer. The following is a list of
required meetings and presentations:
1.

One kick-off meeting / visioning work session at the beginning of each design phase or change of
consultants and after each major milestone;

2.

Progress meetings with the Engineer and Employers management staff every month during which
the monthly progress report shall be presented by the Contractor;

3.

Review meetings with the Engineer, Employer and/or the Operators following submission of
deliverables as agreed or required.

This section is not intended to list every meeting the Contractor may need to conduct during the execution
of their services. During the progress of the Project, the Contractor is responsible for conducting whatever
routine meetings the Contractor, the Engineer, the Employer or the Operators feel necessary to collect /
present data, obtain decisions and generally carry out the tasks of this Contract, so that the Project
Schedule can be adhered to.

COMPLIANCE WITH CODES AND STANDARDS


A.

3.8

Services to be performed by the Contractor and its consultants and sub-contractors under the Contract
shall conform to all applicable codes and standards as well as all requirements and criteria set forth in the
Contract. The Contractor shall compile a complete list of standards and criteria that are applicable to the
completion of the Project. The Engineer may add to this list any other standards and criteria that are
applicable. This list should be compiled and submitted as part of the Concept Design (if any) or as
requested by the Engineer.

LOCAL & NATIONAL LEGISLATION, CODES, REGULATIONS, STANDARDS, & GUIDELINES


A.

All Design work shall comply with the latest revisions (and metric versions) of these documents in use at
the time the Contractors Documents are submitted. Any and all local, city, country and international (as
the case may be) codes or regulations, including utility company, Operators Requirements, relating to
design, construction, and occupancy, or for obtaining inspections or permits, are applicable. It is the
Contractors responsibility to research and comply with these regulations and inform the Engineer of any
requirements for reviews, inspections, approvals, fees, and/or permits. In the event of conflict or
inconsistency between the local codes and reference standards, those which are more stringent, if

ALTERNATES
Volume 2

01230 Page 4 of 32
May 2012

Saraya Aqaba

Specifications

determinable, shall govern. If stringency is not applicable, the most recent standard shall govern. All
requests for waivers or interpretation of codes and regulations shall be made in writing and submitted to
the Engineer for decision.

3.9

CODE ANALYSIS
A.

3.10
A.

3.11
A.

3.12
A.

The Contractor shall prepare a full code analysis specifically tailored to the subject building or work
related by the Project description. The codes shall be related but not limited to buildings, zoning,
finishing, structure, mechanical including plumbing & HVAC , all electrical disciplines, seismic, fire,
quality, safety and environmental. The analysis will entail the following work:
1.

The Contractor shall compile a list of latest applicable codes;

2.

The Contractor shall list applicable design document review authorities including the method,
process and durations;

3.

The Contractor shall prepare a comprehensive analysis that references each of the specific
subsections and paragraphs in the governing code.

DESIGN CRITERIA CONSIDERATIONS


The planning and design of any part or element in the Project shall be the most economical and shall be
consistent with both the expected use and life of the Project. Designs shall be consistent with established
master plan and / or programming documents, as applicable. Life safety, accessible design for persons
with disabilities, security, fire protection, and energy conservation shall be essential considerations.

SPACE PROGRAMS
If any design performed by the Contractor requires change to a certain space program, then the Contractor
shall prepare a revised/final space program for the affected zone(s) or part of it. Each space program shall
be test fitted taking into account the Contract Documents and requirements, Project Site conditions and
operational processes. Test fit results shall be presented to the Engineer, the Employer and the Operators
and all outstanding issues and or inability to meet the set design criteria brought to the Engineers
attention. Also, final functional programs are to be presented to the Engineer, the Employer and
Operators for approval and sign-off.

DRAWINGS
Design deliverables for each part of the works are to be organized with full drawings, documents,
specifications, BOQs, calculations, etc. Final drawings shall be produced on ACAD. All drawings and
documents produced in connection with the Contract shall consistently be of the same size and shall use
cover sheets, title blocks, scale layouts, symbols, and details in a standard format. In addition to PDF files
and Hard copies of all submitted documents, original files of all documents in their native format (i.e. the
original file type used in creating said document) are to be submitted to the Engineer, the Employer and
Operators on a labeled and indexed DVD disk.
1.

Drawing size: All drawings for the Project must be a uniform standard size, as designated below:
Designation
A0

ALTERNATES
Volume 2

Size (mm)
1189 x 841
01230 Page 5 of 32
May 2012

Saraya Aqaba

Specifications

A1
A2
A3
A4

841 x 594
594 x 420
420 x 297
297 x 210

2.

Drawing title block: All drawings for the Project shall use standard title block sheets for each
drawing size to be approved by the Engineer prior to implementation.

3.

Drawing lettering: Lettering on drawings must be legible when drawings are reduced to half size.
This applies to Concept, Schematic and Design Development drawings as well as Construction
Drawings and Documents.

4.

Drawing scale:
a.

b.

5.

All drawings are to be created at full scale and plotted at a selected scale. The drawings or
views (such as details) should include numeric and graphic scales. The scale selected
should be appropriate for high resolution and legibility to include reduced copies (such as
half-sized).
There are nine preferred metric scales: 1:1 (full size), 1:5, 1:10, 1:20, 1:50, 1:100, 1:200,
1:500, and 1:1000. Other scales may be used as needed (such as 1:2 half full size). In
general, floor plan drawings should be plotted at 1:100.

CAD standards:
a.

b.

c.

US/International standards guidelines should be followed for all CAD drawing formatting
and as per the Engineers approval. The submission requirements listed here apply to all
Project designs, whether design services are performed by architects and engineers under
contract to the Contractor or by the Contractors in-house staff.
These requirements are the minimum standards; all submissions in each phase of work are
required to be submitted to the Engineer in drawing or written form and on computer disk
softcopy files.
The Contractor shall prepare a CAD guidelines document standardizing the layering
system to be adopted across the board for the Project and complied with by all consultants
and disciplines preparing CAD drawings. The Contractor shall submit a CAD guidelines
document to the Engineer for approval prior to implementation.

6.

Dimensioning: The millimeter is the only unit of measurement to appear on Construction


Documents for building plans and details for all disciplines except civil engineering, which shall
be stated in meters. However, buildings elevation references are stated in meters. Use of
millimeters is consistent with how dimensions are specified in major international codes used. No
dimension requires the mm label. On the drawings the unit symbol is eliminated and only an
explanatory note such as: All dimensions are shown in millimeters or All dimensions are
shown in meters, is provided. Whole numbers always indicate millimeters; decimal numbers
taken to three places always indicate meters.

7.

Each sheet of the Construction Documents submitted to the Engineer, the Employer or Operators
must bear the signature of the originating design professional. Submissions to official authorities
having jurisdiction over the project shall be prepared in accordance with the prevailing local and
national requirements of such authorities and per the requirements of ASEZA and the Jordanian
Association of Architects and Engineers.

8.

Cover Sheet: The Contractor shall provide code certification statement for compliance with
specified codes and standards by each discipline with the professional seal and signature. The
intent is to formally recognize the responsibility for compliance.

ALTERNATES
Volume 2

01230 Page 6 of 32
May 2012

Saraya Aqaba

9.

3.13

Specifications

Reports: The Contractor shall submit all graphics, text, photos, and any other electronic materials
used to create any reports in original format on a single, clearly indexed compact disc. One file
shall be titled Index; this file shall be in standard desktop software (MS Office). This file shall
clearly list and identify each file and the disc, with the file name, content of the document, and the
page(s) where it appears in the document. Also on this disc, the Contractor shall include a single
PDF copy of the entire report for printing. Note: The Contractor is also expected to provide
intermediate drafts of all reports and drawings as needed. In general, no more than (6) six copies
of any report will be required.

DESIGN NARRATIVES AND CALCULATIONS

A.

The Contractor shall prepare and submit typed and electronic, bound narratives for each design discipline.
(MS Word and MS Excel files to be submitted in addition to PDF files and hardcopies)

B.

Narratives serve to explain the Design intent and to document decisions made during the Design process.
Like drawings and specifications, narratives are an important permanent record of the Projects Design.
Drawings and specifications are a record of WHAT systems, materials and components the Project
contains; narratives should record WHY they were chosen. The narrative of each submittal may be based
on the previous submittal, but it must be revised and expanded at each stage to reflect the current state of
the Design.

C.

The Design narrative will have standard headings to indicate the Zone(s) or any part thereof, the type of
computation, the name and date of the designer, and the checker. Each area in the narrative will include,
but not be limited to, the following:
1.

Short description of the work involved.

2.

The designers assumptions for the design.

3.

Listing the standard works or references used on computations as they occur.

4.

The equations, tables, or curves used or developed in all the detail needed to establish the design,
with references cited where they are taken from non-standard sources.

5.

Suitable free-hand sketches to illustrate the designers intent, such as steel sizing and arrangement,
pipe arrangement, beam layout, etc.

6.

Selected size of equipment, even where computations are not involved; where necessary,
statements to show the basis for the selection shall be included.

7.

All calculations and sources of information shall be shown in an orderly and logical manner to
permit review and final checking.

8.

Include product data sheets on all major items, including all mechanical and electrical items.

9.

Manual and/or computer based calculations should accompany narratives where required to
support technical analysis. Each set of calculations should start with a summary sheet, which
shows all assumptions, references applicable codes and standards, and lists the conclusions.

10.

Calculations should include engineering sketches as an aid to understanding by reviewers.

11.

The calculations for each submittal should be cumulative, so that the final submittal contains all
related calculations.

ALTERNATES
Volume 2

01230 Page 7 of 32
May 2012

Saraya Aqaba

12.

3.14

Specifications

Calculations submitted at early stages of the project must be revised later to reflect the final
design. Calculations must refer to code, paragraph of code used, standards, text books used for
specific portion of calculation; refer to drawing number where the results of the calculations have
been used.

SPECIFICATIONS

A.

Specifications should be produced according to the CSI division format. Each page should be numbered
and should include a header identifying the section and a footer referencing the applicable division
number and content. Specifications should be bound and include a table of contents.

B.

It is the Contractors responsibility to edit all specifications to reflect the design intent, the Contract
Requirements and local / national law. Specifications must be carefully coordinated with drawings to
ensure that everything shown on the drawings is specified. Specification language that is not applicable to
the Project shall be deleted.

3.15
A.

3.16
A.

3.17
A.

BILLS OF QUANTITIES
If required, Bills of Quantities (BOQs) should be produced according to the CSI Master format and at the
greatest detail that the drawings and specifications would support. BOQs shall be prepared in accordance
with the Principles of Measurement (International) for Works of Construction, June 1979 POMI as
published by the Royal Institution of Chartered Surveyors.

PRESENTATION MATERIALS
The Contractor shall provide the Engineer and the Employer copies of any final presentation materials
including mounted boards, handouts, and electronic or slide presentations, models and renderings. The
Contractor shall provide base electronic model used to generate 3-D renderings and animations. Original
files (Photoshop, 3d Studio, etc...) used in preparing presentation drawings and renderings shall be
submitted to the Engineer. The cost of presentation materials shall be deemed to be included in the
Accepted Contract Amount.

PROJECT DESIGN DOCUMENTS MANAGEMENT


The following documents are required to be submitted by the Contractor for the design and construction
phases.
1.

Detailed time schedule: The Contractor shall submit a schedule of services, in bar chart format,
which identifies Project milestones, target dates, design activities and required submissions,
formal presentations, duration of phases/tasks, concurrent activities, and other information
required under the Contract. This schedule shall be presented by the Contractor at Project
commencement and shall be updated monthly or as requested by the Engineer.

2.

Responses to the Engineer comments: The Contractor shall provide written responses to each of
the Engineers comments made on the previous submission's review.

3.

Recording of minutes: The Engineer shall be responsible for recording all meetings attended and
official telephone conferences made in reference to the Project. These shall be submitted to the
various involved parties for review and approval within five (5) working days of the occurrences.

ALTERNATES
Volume 2

01230 Page 8 of 32
May 2012

Saraya Aqaba

Specifications

If required, they shall be revised and then submitted by the Engineer in final form for distribution
to the appropriate parties.

3.18
A.

4.

Meeting agenda: The Engineer, in coordination with the Employer and the Contractor (if
required), shall prepare an agenda for all meetings. The Contractor, in coordination with the
Engineer and the Employer, shall prepare an agenda for all presentations to be made by the
Contractor. A draft copy shall be submitted to the appropriate parties for review as soon as and
before a meeting and/or a presentation is scheduled.

5.

Document control system: During all phases of the Project from beginning to end, the Contractor
shall implement document issuance, numbering, coding and distribution system and manage an
electronic project-wide document control system that includes all types of documents (word files,
excel spreadsheets, drawings.)

6.

Mail and document submittal:


a.

Mail: All documents such as plans, specifications, BOQs, design analysis,


correspondence, etc., shall be hand delivered or sent via Federal Express or other fast
delivery.

b.

Electronic Copies: The Contractor shall provide a DVD disk containing the completed
drawings, specifications, reports, narratives, design analyses, BOQs, etc... for all design
phases and packages.

7.

Submittal of documents: The Contractor shall furnish one original and six (6) copies of the
required material for the Engineers review. The Engineer will provide a transmittal list of
addresses to the Contractor prior to the submittal. The Contractor is to distribute submittals to
provided addresses.

8.

Transmittal: A transmittal sheet listing all submitted documents is to accompany each submittal.

DESIGN PROCESS
As applicable, the Design process shall be as follows:
1.

The Contractor shall engage or cause others to engage all required consultants and disciplines to
deliver the Project.

2.

The Contractor shall submit to the Engineer copies of the scope of services to be performed by
each consultant for each discipline for information.

3.

A master plan (if applicable) is to be prepared and submitted to the relevant authorities for
approval.

4.

Based on the preliminary approval of the master plan concept/schematic designs are to be
prepared.

5.

Upon approval of the architectural concept/schematic design by the Engineer, a detailed


development brief is to be prepared and issued by the Contractor to individual consultants
assigned to further develop the Design. The design brief shall include and consider the common
area components such as infrastructure, marine works, water features and lagoon, white sand
beaches, site security, landscape design, etc...

ALTERNATES
Volume 2

01230 Page 9 of 32
May 2012

Saraya Aqaba

B.

Specifications

6.

The Contractor shall issue a copy of the development brief to the Engineer for approval prior to
handing over to assigned consultants.

7.

The Contractor shall implement a Design management process to coordinate all design and
technical issues across the board and ensure consistency and high standards across all disciplines,
Zone(s) and any part thereof.

8.

In turn each consultant shall, for each discipline, further develop their assigned project component
through concept/schematic design, design development, and construction documents and permit
documents.

9.

The Contractor shall furnish all design, procurement and construction services including designs,
drawings, specifications, BOQs, consultant engineers, specialty consultants, architectural, interior
decorating designers, supervision team, quality control team, construction methodologies and
operations.

10.

The Contractor shall, where applicable and once concept/schematic design has been approved by
the Engineer, coordinate through the Engineer with the Employer and Operators all technical
matters and issues, and shall ensure full incorporation of their requirements in the Design Phases
accordingly. The Contractor shall be fully responsible for meeting the Employers and Operators
design standards and obtaining approvals in a timely manner. The Contractor shall keep the
Engineer informed of design progress and meetings with the Employer and the Operators.

The following is a general list of anticipated disciplines. A complete list along with a responsibility
matrix indicating the name, Zone(s) or part thereof, and scope for each consultant shall be provided by
the Contractor for approval by the Engineer:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.

ALTERNATES
Volume 2

Architecture (International)
Local Architect / Engineers
Technical Control / Site Supervision
Testing & Commissioning
Architectural Theming
Interior Design (International)
FF&E (Furniture, Fixtures and Equipments)
SOE (Small Operating Equipments)
Retail / Merchandising
Landscape and Horticulture
Waterpark Theming
Waterpark Design & Engineering
Waterworks / Pools & Fountains
Civil
Infrastructure
Central District Cooling / Heating
Marineworks
Geotechnical
Structural & Seismic
Mechanical
Electrical
Plumbing
Fire Protection + Life Safety / Code
Telecommunication / IT
Vertical Transportation
Building Automation / BMS
Lighting
Acoustics
01230 Page 10 of 32
May 2012

Saraya Aqaba

29.
30.
31.
32.
33.
34.
35.
36.
37.
38.
39.
40.
41.
42.
43.
44.
45.
46.
47.
48.
49.
50.

3.19

Specifications

Audio Visual
Security
Spa & Fitness
Food Services
Materials Handling
Laundry
Window Washing
Traffic and Parking
Transportation / Water Taxis
Environmental / EIS
Hydrology
Archaeology (If Needed)
Way finding / Signage / Graphics
Art Work
Lagoon Show
Value Engineering
Quantity Surveying
Cost Estimating
Scheduling
Other Consultants
Other Specialty Consultants
Specialist Sub-Contractors

DESIGN PHASES

A.

As applicable, the following descriptions represent the minimum range of design Consultant Services
the Contractor shall provide. It is understood that these descriptions are general and are intended to give a
general overview of what is expected from the Contractor in the provision of design services. For each
Zone(s) or part thereof requiring design from the Contractor, the Contractor shall prepare and submit a
more specific scope of work that provides supplemental requirements and a complete list of deliverables
to be agreed on with the Engineer. The Contractor shall provide all design services necessary to deliver
the Project.

B.

Design Phase Services:


1.

Data Gathering and Review: The Contractor shall gather, review and analyze all existing
information made available by the Employer as well as all applicable codes, standards,
regulations, etc. from concerned bodies, utility companies and local and national authorities.

2.

Field Work and Site Analysis: The Contractor shall visit the Project Site prior to commencing any
design and shall perform all fieldwork necessary to determine the existing conditions at the Project
Site that may impact on the Design. The Contractor shall provide detailed topographic, site
boundary, geotechnical, hydrological, soils analysis, wind, sun, seismic information, marine
surveys / analyses and other site information deemed necessary for the execution of the project.

3.

Existing Conditions Survey requires researching, assembling, reviewing, and supplementing


existing documentation, as well as field verification. The survey shall include archival research
and field measurements, photography, videography and selective demolition may also be required.
Investigation of existing conditions is a required task for every design project. The Contractor
shall update existing conditions notes when known changes take place between the initial survey
and the final submission of construction documents and drawings.

4.

Programming and Space Planning:

ALTERNATES
Volume 2

01230 Page 11 of 32
May 2012

Saraya Aqaba

Specifications

a.

The Contractor shall as part of his programming and space planning services include
preparing and collecting detailed technical, spatial, and programmatic requirements for
interior and exterior facility spaces, including architectural, engineering, FF&E and SOE
needs; analyzing program functions, access/circulation, security; presentation of findings
and recommendations; providing and evaluating spatial relationships of program elements
with block diagrams, stacking diagrams, circulation/space flow diagrams, adjacency
diagrams, space plans and other analyses prior to design.

b.

The Contractor shall review any additional programming documentation prepared by others
for completeness and accuracy. Based on that review, the Contractor will itemize areas,
elements or relationships that require further definition. The Contractor will brief the
Engineer on these items and the Engineer will arrange for work sessions with the Employer
and appropriate Operators or users to address the open issues.

c.

Prior to initiating each phase of design, the Contractor, the Engineer, and the Employer,
and appropriate Operators should meet to review design program expectations and to
exchange ideas, lessons-learned, and concerns. Such technical partnering sessions allow
a clearer definition of expectations while remaining within the Projects scope and the
Accepted Contract Amount.

5.

Schematic Design: If required, the Contractor shall prepare architectural and engineering
responses to the project's program. These studies shall describe organizational concepts, themes,
and/or the architectural parti, as well as major building or engineering systems concepts. Once
the Engineer selects a design direction in which to proceed, the Contractor shall prepare designs
that illustrate the general scope and the relationship between the various Zone(s) of the Project.
Drawings shall be schematic in character, based on the programmatic and conceptual requirements
developed and agreed upon by the Engineer. In general, this submission shall consist of drawings
and sketches, a narrative report that addresses major site and building systems, gross and net area
calculations, and a massing model (as appropriate). The Contractor shall provide a submission
that will demonstrate compliance with the buildings program (space tabulation of buildings
program) including all adjacency and functional requirements. This submission will also show that
the proposed design is within the zoning area, and that the buildings and massing are compatible
with the surroundings. The aesthetics should support the projects overall design theme. Buildings
systems and buildings envelopes appropriate for the schematic designs should be defined in order
that they can be evaluated early for effectiveness and efficiency related to operation, maintenance
and energy consumption. See Design Deliverables below.

6.

Design Development: The Contractor shall prepare design development phase documents which
reflect accurate existing conditions at the Project Site as well as proposed work identified in the
schematic design phase. Design development documents should be a mock-up or outline of the
working drawing set and are prepared at the scale(s) and sheet size needed for Contractors
Documents. All schematic phase decisions and instructions approved by the Engineer during
review shall be incorporated in the design development phase documents. All disciplines shall
exhibit generally equivalent levels of completeness and coordination, and display approximately
35% development of the information required for construction. The Contractor shall provide a set
of submissions that will finalize the selection of all systems with respect to type, size and other
material characteristics. Systems are not only structural, mechanical, fire protection and electrical,
but include all other buildings components such as the buildings envelopes (wall, window and
roof), interior construction (flooring, ceiling and partitions), service spaces, elevators, etc. The
design submission will consist of a combination of drawings, narrative and calculations. Although
final design development plans, sections and elevations must be to scale, drawings made in the
analysis stage to illustrate various options may be freehand. See Design Deliverables below.

7.

Value Engineering (VE):

ALTERNATES
Volume 2

01230 Page 12 of 32
May 2012

Saraya Aqaba

Specifications

a.

Value Engineering (VE) is a process which identifies opportunities to remove


unnecessary costs while assuring that quality, reliabilities, performance and other critical
factors will meet or exceed the Employers Expectations.

b.

VE is a process that is somewhat continuous throughout the design but its greatest
emphasis should be in the early stages of the design (schematic and design development).
Initially it should focus on buildings systems and materials in a general sense during
schematics. As the Design is developed the focus will shift to detailed aspects of the earlier
decisions during design development. Diagrams, narratives, and sketches with calculations
to demonstrate the life-cycle cost effectiveness of the system should be prepared and
received during this phase. This approach requires a diligent effort and commitment by all
design team members early in the project to systems and materials that make sense
economically and allow quality and durability.

8.

Construction Permit Documents: For each Zone(s) or parts thereof requiring a construction permit,
the Contractor shall prepare and submit a set of permit documents in accordance with the
concerned authorities requirements. The Contractor shall have all permit documents duly
stamped and sealed by authorized architects and engineers of record in accordance with all
statutory requirements. The Contractor shall make all necessary revisions, arrangements, and
follow-up until all construction permits have been obtained. The Contractor shall also translate all
drawings and documents as required.

9.

Detailed Design Documents: The Contractor shall prepare a full set of Detailed Design
Documents. A Detailed Design Set Submission is a complete submission of design documents and
supporting materials that clearly demonstrate project design progress, adherence to project scope
and design criteria, and coordination between disciplines. All disciplines shall exhibit equivalent
levels of completeness. The Detailed Design Documents shall be complete in every Design
aspect. Only very minor revisions should be required after review. All previous comments made
by the Engineer shall be accounted for. The Contractor shall provide a set of detailed and
coordinated submissions to the Engineer, the Employer and Operators for review. The notes on
these should result in a single interpretation of a specific set of data or facts. Detailed Design
Documents should avoid using terms that the design specialist may know, but which have nothing
to do with the purchase and installation of a product. Reviews may be both formal and informal
(onboard). Language between specifications and notes on the drawings must be consistent and
complementary. See Design Deliverables below.

10.

Final Design Documents: All prior submission documents shall be revised/corrected to incorporate
the Engineers, Employers and Operators review comments and shall be resubmitted as final
design documents. The final submission of documents shall include the following completed
items:

ALTERNATES
Volume 2

a.

Final design drawings with professional seals and signatures of the registered architect(s)
and engineer(s), which shall be the basis for Construction Drawings described under SubClause 1.15.1 (Construction Drawings) of the Conditions of Contract.

b.

Detailed specifications (Including the construction submittal/sample list where applicable).

c.

Supporting Materials (analyses and calculations).

d.

Computer CD(s) containing the Specifications, Drawings, et

e.

Other Contractors Documents.

01230 Page 13 of 32
May 2012

Saraya Aqaba

3.20

Specifications

FURNITURE, FIXTURES, AND EQUIPMENT (FF&E) AND SMALL OPERATING EQUIPMENT


(SOE)

A.

The Contractor shall coordinate all FF&E and SOE requirements with the Engineer, the Employer,
Operators, and interior designers of each Project component. In addition, the Contractor shall be
responsible for the Design (as applicable), procurement and installation of all fit-out, FF&E and SOE
items, including artwork. The Contractor shall obtain the Engineers, Employers and Operators
approval at each stage of the interior design, FF&E and SOE Design development, including colors
selections, standards and specification of the materials & equipments in addition to the installation
procedures.

B.

As applicable, the Contractor shall prepare designs of various furniture, fixtures, and special equipment
items, including but not limited to:

3.21
A.

3.22
A.

1.

Preparation of plans and specifications, "color" boards indicating finish materials, fabrics and
colors, fit-out schedules for fabrication and installation, review and administration services during
fabrication, delivery and installation.

2.

Design of custom or special furniture, fixtures, and equipment for lobby, hotel rooms, conference,
retail, and other areas; selection of furniture finishes, colors, and fabrics.

3.

Selection of specialized equipment.

4.

Design of project signage, interior and/or exterior, for room identification, building identification
and directory, directional signage, special plaques, accessible signage, and others.

5.

Preparation of full size mock-up drawings for hotel rooms, model residential suites and other
significant project components as may be determined by the Engineer/Employer/Operators.

SIGN-OFF
The return or deemed return of any submitted item of any reviewable Design data or Submission
approved or signed-off by the Engineer, the Employer, or the Operator shall mean that the relevant
submitted item may be used or implemented by the Contractor for the purposes for which it is intended
by the Contractor but, such return or deemed return of any submitted item shall not relieve the Contractor
of its obligations under the Contract nor is it an acknowledgement by the Engineer, the Employer, or the
Operators that the Contractor has complied with such obligations.

DESIGN DELIVERABLES
As applicable, the following is a general outline of the Design Deliverables to be prepared by the
Contractor and submitted to the Engineer, Employer, and Operators for review. The list of deliverables is
intended to demonstrate the general scope and level of information to be provided as part of each
submission and by no means includes all deliverables required to fully satisfy the Contract requirements.
It is organized by project phase and only covers the major disciplines. All other unlisted deliverables for
each discipline required to undertake the design and construction of the Works and deliver them in
accordance with the project scope and Contract requirements shall be at a scale and level of detail
commensurate with the applicable design phase. The drawings and documents listed below represent
requirements for the Engineers, Employers, and Operators review and do not constitute any limitation
on the documentation required to properly design and construct the project, or limit the professional
design liability for errors and omissions. More specific deliverables and requirements may be contained
in each Operators standards and design guides. At the beginning of each design phase for any part of the

ALTERNATES
Volume 2

01230 Page 14 of 32
May 2012

Saraya Aqaba

Specifications

Project, the Contractor shall provide a list of Deliverables and the various disciplines involved to the
Engineer.
B.

Schematic Design: The Contractor shall consider the minimum following items & information in the
Schematic Design submittal. Where so approved, the existing design drawings may fulfill the
requirements of this clause.
1.

ALTERNATES
Volume 2

Site Planning and Landscape Design:


a.

Drawings: Site plan, describing:

Site boundaries, approximate topography, existing buildings, setbacks and


easements.

Buildings orientation with respect to path of sun /Shade study.

Buildings massing and relationship to massing of surrounding buildings.

Future Buildings expansion potential.

Location of on-site and off-site utilities.

Grading and drainage.

General landscape design, showing location of major features.

Pedestrian and vehicular circulation. (Include direction of traffic on adjoining


streets.)

Parking and service areas.

Fire protection, water supplies, fire hydrants, and fire apparatus access roads.

b.

Narrative: The Contractor shall consider the minimum following items in the Description
of site and landscape Schematic design.

Circulation.

Parking.

Paving.

Landscape design.

Irrigation.

Utility distribution and collection systems.

Method for storm water detention or retention.

Landscape maintenance Schematic.

Fire protection, water supplies, fire hydrants, and fire apparatus access roads.

Accessibility path for the physically disabled.

Site statement, describing:


Project Site features.
Climatic conditions.
Topography and drainage patterns.
Any existing erosion conditions.
Wetlands and locations of flood plains.
Surrounding buildings (style, scale).
Circulation patterns around site.
Site access.
Noise/visual considerations.
Local zoning restrictions.
Jordanian Aviation Agency requirements.
Hazardous waste.
Pollution.
Potential archeological artifacts.
Historic preservation considerations, if applicable.

Project Site photographs, showing contiguous areas and effected preservation zones.

Existing major site utilities.

01230 Page 15 of 32
May 2012

Saraya Aqaba

Specifications

2.

ALTERNATES
Volume 2

Description of each architectural design scheme, explaining:


Organizational concept.
Expansion potential.
Buildings efficiency.
Energy considerations.
Advantages and disadvantages.
Historic preservation considerations, if applicable.
Sustainable design considerations.
Baseline mechanical system and strategy.
Fire protection design considerations.

Architectural Drawings:
a.
Drawings:

Floor plans, showing as a minimum:


Work areas, lobbies, corridors, entrances, stairways, elevators, front of the
house and back of the house rooms, special spaces and service spaces (with
the principal spaces labeled).
Dimensions for critical clearances, such as vehicle access, should be
indicated.
Proposed layouts down to the level of detail verifying the integration
between the approved program and the Buildings Schematic is achievable.
Proposed interior layouts:

Proposed Furniture layout.

Elevations of major Buildings faades, showing:


Fenestration.
Exterior materials.
Cast shadows.

Elevations of major interior spaces, showing:


Lobby/Atrium.
Typical public elevator lobby.
Typical guestroom elevations.

Buildings sections (as necessary), showing:


Adequate space for structural, mechanical and electrical, telecommunications
and fire protection systems.
Mechanical penthouses.
Floor-to-floor and other critical dimensions.
Labeling of most important spaces.
Labeling of floor and roof elevations.

Color renderings.

Model: Provide a model of the Schematic design with sufficient detail to convey the
architectural intent of the design.
b.

The Contractor shall Provide Finish Boards for both public and interior areas and Finish
Boards of exterior finishes composed of actual material samples and color coded plans,
sections and elevations of major space showing their use.

c.

Narrative:

Architectural program requirements:


Show in tabular form how the Schematic design meets the program
requirements for each critical function.

Description of Schematic, explaining:


Buildings floor efficiency.(net/gross)
Conveying systems design (elevators, escalators).
Design strategy to attain the assigned energy goal.
01230 Page 16 of 32
May 2012

Saraya Aqaba

Specifications

3.

Structural Drawings, Plans, showing: Framing plans of the proposed structural system showing
column locations; bay sizes; and location of expansion and seismic joints.
a.

b.

4.

Narrative:

Identification of any unusual local code requirements.

Code compliance statement:


Name of model Buildings code followed.
Buildings classification.
Identification of Region of Seismicity, wind speed, etc.
Identification of special requirements, such as high-rise.
Structural Engineering: Statement certifying that the structural engineer has reviewed the
Buildings configuration for seismic adequacy. This statement must be signed by the
structural engineer and the architect.

Mechanical: For the system approved and selected from the alternatives presented, the Contractor
shall provide the following:
a.

ALTERNATES
Volume 2

Treatment of historic archeological zones if applicable.


Operations and maintenance goals (exterior and interior window washing,
relamping, etc.).
Vertical transportation analysis (elevators and escalators).
Code statement: The Contractor shall provide a brief statement from each design
team discipline member regarding the Code requirements that relate to the site and
occupancy use. For example, items such as, but not limited to:
Classification of construction and occupancy group(s), fire resistance
requirements and general egress requirements, etc. would be prepared by the
design team fire protection engineer.
Construction cost of alternative schemes.
Verify that each design scheme presented can be constructed within the
Accepted Contract Amount.
Space Program Statement/Reconciliation
Preliminary Energy Analysis
Code analysis:
The Code criteria shall be reviewed by each design team discipline member
to the degree of detail necessary to assure that tasks accomplished in this
phase meet all Code and the Contract requirements.
A Code/Criteria analysis shall be prepared by each design team discipline
member that documents an investigation of the applicable codes that will
govern the design of a specific project. This analysis should alert the
Contractor, the Engineer, the Employer and local authorities to any conflicts
in the Projects design criteria so that they can be resolved early. The
analysis should also provide a common perspective for the design and review
of the Project.
Identify architectural systems alternatives which will be analyzed during design
development for life cycle cost analysis.

Drawings:

Floor Plan(s):
Identification of equipment spaces for major equipment.
Location of major equipment, including size, weight, and clearance
requirements.

Flow Diagram(s):
Air flow diagrams representing Schematic of systems for each major space.
Air flow diagrams representing final concept of Buildings system.

01230 Page 17 of 32
May 2012

Saraya Aqaba

Specifications

b.

c.

5.

Fire Protection: Fire protection and life safety submission requirements shall be identified as a
separate Fire Protection section.
a.

b.

c.

6.

b.

ALTERNATES
Volume 2

Drawings: Plans showing:

Equipment spaces for fire protection systems (e.g., fire pump, fire alarm, etc.).

Fire protection water supplies, fire hydrant locations, fire apparatus access roads,
and fire lanes.
Narrative:

Description of the buildings proposed fire protection systems including the egress
system.

Code compliance analysis


The design team fire protection engineer shall prepare an analysis of the applicable codes
and criteria that will govern the design of the specific project. For example, items such as,
but not limited to: classification of construction and occupancy group(s), rating of
structural components, fire resistance requirements, interior finish, occupant load
calculations, exit calculations, identification of areas to receive automatic sprinkler systems
and/or automatic detection systems, smoke control systems, etc. would be prepared by the
design team fire protection engineer as necessary to provide a complete fire protection and
life safety analysis for the Schematic Design .

Electrical Drawings:
a.

7.

Water flow diagrams of the main mechanical system in the mechanical


room(s) and throughout the Buildings.
Narrative: A written narrative describing the selected mechanical system and equipment,
including:

Design conditions.

Ventilation rates, dehumidification and pressurization criteria.

Equipment capacities, weights, sizes and power requirements.

Description of heating, cooling, ventilating, and dehumidification systems for each


major functional space.

Fuel and utility requirements.

A code compliance statement.


Calculations and Energy Analysis:

Buildings load calculations.

Psychometric calculations for full load and partial load utilization in summer,
winter, spring, and fall.

Energy and life cycle cost analysis.

Fuel consumption estimates.

Plans showing equipment spaces for all electrical equipment to include: panels;
switchboards; transformers; UPS; and generators.
Narrative:

Description and General Characteristics of at least two potential electrical systems.

Proposed special features of electrical system.

Code compliance statement.

VE decisions and commitments that were made during this phase by the Project
team.

In bullet form, identify how proposed design features will support performance
expectations of the project.

Specifications: Table of Contents identifying specifications to be used on the project.

01230 Page 18 of 32
May 2012

Saraya Aqaba

8.

C.

Specifications

Schematic Design BOQs: Priced BOQs/cost estimates must be provided at this stage, to the
approval of the Engineer, verifying that the Schematic design can be constructed within the
Accepted Contract Amount.

Design Development: The Contractor shall consider the minimum following items & information in the
Design Development / Preliminary Design submittal. Where so approved, the existing design drawings
may fulfill the requirements of this clause.
1.

Site Planning and Landscape Design:


a.

Calculations:

Site storm drainage combined with Buildings storm drainage, and sanitary sewer
calculations.

Storm water detention calculations.

Parking calculations.

Dewatering calculations:
Calculations modeling dewatering rates during dry and wet season
excavation. Calculations must take into account effect of dewatering on
adjacent structures and improvements.
Calculations must assume a specific shoring system as part of a
comprehensive excavation system.

b.

Narrative:

Site circulation Schematic , explaining:


Reasons for site circulation design and number of site entrances.
Reasons and/or calculations for number of parking spaces provided.
Reasoning for design of service area(s), including description of number and
sizes of trucks that can be accommodated.
Proposed scheme for waste removal.
Proposed scheme for fire apparatus access and fire lanes.

Site utilities distribution Schematic:


Brief description of fire protection water supplies.
Brief description of fire hydrant locations.

Drainage design Schematic:

Landscape design Schematic , explaining:


Reasoning for landscape design, paving, site furnishings, and any water
features.
Reasoning for choice of plant materials.
Proposed landscape maintenance plan and water conservation plan.
Brief operating description of irrigation system.

Site construction description: Brief description of materials proposed for pavements


and utilities.
Code analysis:

The Code criteria shall be reviewed by each design team discipline member to the
degree of detail necessary to assure that tasks accomplished in this phase meet all
the Code requirements.

Identify local zoning and all Buildings code requirements and provide a complete
analysis as they pertain to the project.
Drawings:

Site layout plan, showing:


All buildings, roads, walks, parking and other paved areas (including type of
pavement).

c.

d.

ALTERNATES
Volume 2

01230 Page 19 of 32
May 2012

Saraya Aqaba

Specifications

2.

Architectural Drawings:
a.

b.

ALTERNATES
Volume 2

Accessible route from parking areas and from public street to main facility
entrance.
Fire apparatus and fire lanes.
Grading and drainage plan, showing: Site grading and storm drainage inlets,
including storm water detention features.
Site utilities plan, showing: Sizes and locations of domestic and fire protection
water supply lines, sanitary sewer lines, and chilled water supply and return lines, as
applicable.
Landscape design plan, showing: General areas of planting, paving, site furniture,
water features, etc.
Irrigation plan.

Architectural Calculations:

Acoustical calculations.

Dew point location.

Toilet fixture count.


Narrative:

Buildings Schematic, explaining:


Reasons for Buildings massing, entrance locations and service locations.
Buildings circulation and arrangement of major spaces.
Interior design.
Energy conservation design elements.
Water conservation considerations.
Explanation of how all these design considerations are combined to provide
a well integrated cohesive Design.

Analysis of refuse removal, recycled materials storage and removal, and


maintenance requirements.

Buildings construction description, explaining:


Structural bay size.
Exterior materials, waterproofing, air barriers/vapor retarders, and insulation
elements.
Roofing system(s).
Exterior glazing system.
Interior finishes, with detailed explanation for public spaces.
Potential locations for artwork.

Review of Project for code compliance.

Code criteria should be reviewed by each discipline to the degree of detail necessary
to assure that tasks accomplished in this phase meet the code requirements.

Buildings maintenance, explaining:


How unique and tall architectural spaces such as atriums or grand staircases
will be cleaned, have their light fixtures maintained, have interior and
exterior glass surfaces cleaned and typical maintenance performed.
How, dining facilities and other assembly spaces with fixed seating,
multilevel spaces or with sloped floors will have their ceilings, lights and
other ceiling elements maintained and repaired.
Proposed scheme for window washing equipment.
Consideration and prevention of bird nesting on exterior surfaces.
How major mechanical and electrical equipment can be serviced and/or
replaced in future years.

Review of buildings for compliance with Project specific design criteria such as
Operators manuals and standards.

01230 Page 20 of 32
May 2012

Saraya Aqaba

Specifications

c.

ALTERNATES
Volume 2

Description of process for servicing and replacement of equipment given the


necessary dimension clearances.

Program Status and Reconciliation Report.

Report verifying the current designs compliance with the approved space program.
Any deviations must be clearly reported.

Curtain wall Report:


In projects with complex curtain wall systems describe size and locations of
major movement joints to accommodate structural drift due to seismic and/or
wind loading. Describe proposed curtain wall attachment methods to
accommodate these lateral movements.
Describe water migration, and fire safety systems.
Describe typical interfaces between exterior wall system and interior
finishes.
Describe interfaces between major enclosure assemblies such as glass
curtain wall to precast or stone panels.

Buildings Keying and Signage Report:


Report must fully define the keying hierarchy for the entire Buildings
incorporating various levels of access, security, and fire egress.
Signage system and room numbering system must be integrated with keying
system.

Provide Finish Boards for both public and interior areas and Finish Boards of
exterior finishes composed of actual material samples and color coded plans,
sections and elevations of major space showing their use.
Drawings:

Buildings floor plans, showing:


Spaces individually delineated and labeled.
Enlarged layouts of special spaces.
Dimensions.
Planning module.

Buildings reflected ceiling plans, showing:


Enlarged layouts of special spaces.
Spaces individually delineated.
Materials labeled.
Ceiling heights labeled.
Lighting fixture types indicated and scheduled.

Buildings roof plan, showing:


Drainage design, including minimum roof slope.
Dimensions.
Membrane and insulation configuration of the roofing system.

Elevations, showing:
Entrances, window arrangements, doors.
Exterior materials with major vertical and horizontal joints.
Roof levels.
Raised flooring and suspended ceiling space.
Dimensions.

Interior Elevations, showing:


Lobby, atrium.
Public corridors.
Restrooms.
Typical public elevator lobby.
Typical guestroom elevations.
Typical corridors.
Typical conference rooms.

Longitudinal and transverse Sections, showing:


01230 Page 21 of 32
May 2012

Saraya Aqaba

Specifications

3.

Floor-to-floor dimensions.
Stairs and elevators.
Typical ceiling heights.
General roof construction.
Exterior wall sections, showing:
Materials of exterior wall construction, including flashing, connections,
method of anchoring, insulation, vapor retarders, and glazing treatments.
Vertical arrangement of interior space, including accommodation of
mechanical and electrical services in the floor and ceiling zones.
Proposed room finish schedule, showing:
Floors, bases, walls and ceilings.
Finish schedule (may be bound into narrative).
Perspective sketches, renderings and presentation model.
Proposed site furniture / proposed FF&E showing:
Site furniture cut sheets or photos
Proposed locations.
Diagrams illustrating the ability to access, service and replace mechanical/electrical
equipment showing the pathway with necessary clearance.
Location of accessible pathways and services for the physically disabled.
Placement of Art- elements.
Design of typical Buildings signage including way finding and room identification,
Buildings directory, exterior Buildings signage and major interior Buildings
identification.

Structural Calculations:

Gravity load and lateral load calculations, with tabulated results showing framing
schedules.

Foundation calculations.

Vibration calculations.
A narrative of the input and results for computer generated calculations for the recommended
structural Schematic.

4.

a.

Narrative:

Code criteria should be reviewed by each discipline to the degree of detail necessary
to assure that tasks accomplished in this phase meet the code requirements.

Description of recommended structural Schematic , including:


Choice of framing system, including lateral load resisting elements, and
proposed foundation design.
Verification of adequacy of all assumed dead and live loads.

Identify all code requirements and provide a complete analysis as it pertains to this
project including but not limited to:
Required fire-resistance rating of structural elements.
Summary of special requirements resulting from applicable local codes.

Proposed methods of corrosion protection, if applicable.

Geotechnical Engineering Report, including boring logs.

Geologic Hazard Report.

b.

Drawings:

Framing plans and key details.

Mechanical:
a.

ALTERNATES
Volume 2

HVAC Drawings:
01230 Page 22 of 32
May 2012

Saraya Aqaba

Specifications

b.

c.

d.

ALTERNATES
Volume 2

Floor plan(s):
Single line piping and ductwork schematic layout.
Show terminal air devices.
Perimeter terminal units.
Drawings of mechanical equipment room(s) showing all mechanical
equipment serving the project, including equipment access and service
requirements.
Roof plan showing all roof mounted equipment.
Show adequate access from mechanical equipment room(s) to freight
elevators.
Show adequate access to roof-mounted equipment.

Single line schematic flow and riser diagram(s):


Airflow quantities and balancing devices for all heating/cooling equipment.
Water flow quantities and balancing devices for all heating/cooling
equipment.
Flow/energy measuring devices for water and air systems for all cooling,
heating and terminal equipment.

Automatic Temperature Control Diagram(s):


Control flow diagrams showing all sensors, valves, and controllers (analog
and digital).
Sequence of operations of all the systems and its operation (occupied and
unoccupied).
Buildings Automation Systems and their descriptions.

Schedules:
Provide schedules of major equipment that includes chillers (as applicable),

Boilers, pumps, air handling units, and terminal units:


Air Terminal Devices
Air Balance Relationships between Spaces
Plumbing Drawings:

Floor plan(s)
Proposed Buildings zoning and major piping runs.
Locations of proposed plumbing fixtures and equipment.
Systems schematics and flow diagrams.
HVAC Narrative:

A written narrative describing the final mechanical system and equipment selection
including:
Design conditions.
Ventilation rates, dehumidification and pressurization criteria.
Equipment capacities, weights, sizes and power requirements.
A complete description of the air side and water side systems and the
associated components including operating characteristics, ranges, and
capacities, spaces served and special features.
Description of occupied and unoccupied and related sequence of operations.
Fuel and utility requirements.

Calculations and Energy Analysis.


HVAC:

Buildings load calculations.

Heat and air balance calculations.

Psychometric calculations for full load and partial load utilization in summer,
winter, spring, and fall. (Partial loads at 50% and 25%, and unoccupied hours.)

Detailed energy analysis. Output shall indicate energy consumption of the system
and total Buildings energy summary.

Fuel consumption estimates.

01230 Page 23 of 32
May 2012

Saraya Aqaba

Specifications

e.

5.

Additional life cycle cost analyses as required to optimize equipment selections,


heat recovery/ storage, and control/zoning options.

Selection cut sheets of equipment and control systems.

Calculations for duct losses.

Calculations for piping losses.


Plumbing:

Proposed plumbing system, Include lists of typical fixtures.

Evaluation of alternate sources for preheating of domestic water (solar or heat


recovery).

Fire Protection: Fire protection and life safety submission requirements shall be identified as a
separate Fire Protection section as outlined in this document.
a.

6.

Calculations:

Occupant load and egress calculations.

Fire protection water supply calculations, Includes water supply flow testing data.

Fire pump calculations where applicable.

Smoke control calculations where applicable (e.g., atrium, etc.).

Stairway pressurization calculations where applicable.

Calculations to sound attenuation through doors and walls for placement and
location of fire alarm system audible notification appliances.
b.
Narrative:

Buildings egress system, Includes egress calculations and stairway exit capacities,
remoteness exit discharge, etc.

All Buildings fire alarm and suppression systems.

Smoke control system(s), where applicable.

Special fire protection systems (e.g., kitchen extinguishing system), where


applicable.

Fire resistance rating of Buildings structural elements. Coordinate with structural


engineer.

Fire alarm system.

Interface of fire alarm system with Buildings Automation systems and Security
Systems.

Review of Buildings for compliance with life safety requirements and Buildings
security requirements.

Interior finish requirements as they pertain to the life safety requirements.


c.
Drawings:

Floor Plans showing:


Equipment spaces for fire protection systems (e.g., fire pump, fire alarm,
etc.)
Fire protection water supply lines, fire hydrant locations, fire apparatus
access roads, and fire lanes.
Standpipes and sprinkler risers.
Riser diagrams for sprinkler system.
Riser diagram for fire alarm system.
Remoteness of exit stairways.
Location of firewalls and smoke partitions.
Identification of occupancy type of every space and room in Buildings.
Calculated occupant loads for every space and room in the Buildings.
Location of special fire protection requirements (e.g., kitchens, computer
rooms, storage, etc.)
Electrical:
a.

ALTERNATES
Volume 2

Electrical Calculations:
01230 Page 24 of 32
May 2012

Saraya Aqaba

Specifications

b.

c.

ALTERNATES
Volume 2

Lighting calculations for a typical 110-200 cm. plan with system furniture.
Lighting calculations for a typical one person private room in addition to typical
guest room and special functions.

Power calculations from Buildings entry to branch circuit panel.

Load calculations.

Life cycle cost analysis of luminary /l amp system and associated controls.
Narrative:

Description of alternative power distribution schemes.

Compare the advantages and disadvantages of each approach. Include the source of
power, potential for on-site generation, most economical voltage and primary versus
secondary metering.

Proposed power distribution scheme.

Provide a detailed description and justification for the selected scheme. Address
special power and reliability requirements, including emergency power and UPS
systems.

Proposed lighting systems.


Discuss typical lighting system features, including fixture type, layout, and
type of controls.
Discuss special spaces such as lobbies, meeting rooms, conference rooms,
Ballroom, guest rooms, restaurants, etc...
Discuss exterior lighting scheme.

Interface with Buildings Automation System.

Methods proposed for energy conservation and integration with Buildings


Automation System.

Engineering analysis for demand limit controls.

Description of each proposed signal system.

Description of proposed security systems features and intended mode of operation.


Proposed zone schedule.
Proposed card access controls, CCTV assessment and intrusion protection
system, etc...

Proposed Telecommunications Infrastructure. Systems proposed for infrastructure


and cabling to accommodate the communications systems.

Code criteria should be reviewed by each discipline to the degree of detail necessary
to assure that tasks accomplished in this phase meet the code requirements.
Drawings:

Site plan.

Proposed site distribution for power and communications, proposed service entrance
and location of transformers, generators, and vaults, etc.

Floor plans, proposed major electrical distribution scheme and locations of


electrical closets.

Floor plans, proposed major routing of communications system, communications


equipment rooms and closets.

Floor plans, plan layouts of electrical rooms, showing locations of major equipment,
including size variations by different manufacturers.

Single line diagram of the Buildings power distribution system.

Plan of typical guestrooms and office lighting layout.

Single line diagram of other signal system including telephones, security, public
address, and others.

Security system site plan. Proposed locations for CCTV, duress alarm sensors, and
access controls for parking lots.

Security system floor plans. Proposed locations for access controls, intrusion
detection devices, CCTV local panels, etc.

01230 Page 25 of 32
May 2012

Saraya Aqaba

D.

Specifications

7.

Specifications: Assemble all project related construction guide specifications and mark out all
content that does not apply to the project.

8.

Design Development BOQs: Priced BOQs/cost estimates must be provided at this stage, to the
approval of the Engineer, verifying that the Preliminary design can be constructed within the
Accepted Contract Amount. Address what value engineering items were incorporated from the
Schematic Value Engineering workshops. Document all VE workshop sessions during design
development and show what is to be incorporated into the final design.

Detailed Design: The construction documents must be complete coordinated between disciplines,
readable and buildable, with no room for unreasonable additional interpretation. The drawings listed
below represent requirements for Contractor review, and do not constitute any limitation on the
documentation required to properly construct the project, or limit the professional design liability for
errors and omissions. One of the guidelines to insure inter-discipline and intradiscipline coordination is
included under each category of work and is referred to as the Review Checklist. The Contractor should
make sure that all of these items, and others that pertain to good project coordination, are reviewed and
addressed before submission of the documents to the Engineer. Update of Code Analysis. The Code
criteria shall be reviewed by each design team discipline member to the degree of detail necessary to
assure that tasks accomplished meet all the Code requirements.
1.

Site Planning and Landscape Design Drawings:


a.

ALTERNATES
Volume 2

General: The plans listed below are required to be provided:

Demolition plans where applicable.

Site layout plan:


Location of all buildings, roads, walks, accessible routes from parking and
public street to Buildings entrances, parking and other paved areas, and
planted areas.
Limits of construction.
Locations and sizes of fire protection water supply lines, fire hydrants, fire
apparatus access roads, and fire lanes.
Location of floodplains and wetlands.

Grading and drainage plan, showing:


Existing and new contours.
Spot elevations at all entrances and elsewhere as necessary.
Elevations for walls, ramps, terraces, plazas and parking lots.
All surface drainage structures.
Water storage retainage and conservation.

Site utilities plan, showing: All utilities, including inlets, manholes, clean-outs and
invert elevations.

Planting plan, showing:


Buildings outline, circulation, parking and major utility runs.
Size and location of existing vegetation to be preserved (include protection
measures during construction).

Location of all new plant material (identify function, such as windbreak or visual
screen where appropriate):
Erosion control.

Planting schedule, showing:

Quantity of plants, botanical names, planted size and final size.

Irrigation plans. Include schematic of irrigation control system.

Planting and construction details, profiles, sections, and notes as necessary to fully
describe design intent.

Construction phasing.

01230 Page 26 of 32
May 2012

Saraya Aqaba

Specifications

b.

2.

Architectural Drawings:

a.
b.

3.

Project title sheet, drawing index.


Floor plans.
Show planning grids and raised access floor grid, if applicable.
Reflected ceiling plans.
Show ceiling grid and location of all elements to be placed in the ceiling.
Buildings sections.
Vertical zoning for electrical and mechanical utilities must be indicated on sections.
Roof plans.
Roof plans must show slopes, low points, drains and scuppers, equipment, equipment
supports, roof accessories and specialty items, if applicable.
Exterior elevations.
Wall sections.
Interior elevations.
Details.
Schedules: Diagrams illustrating proper clearance for servicing and replacement of
equipment.
Specifications:

Room finish, ceiling types, floor finish, color and door schedules. These can be
incorporated into either the specifications or drawings.

Call for assembly of mock-ups for spaces such as guestrooms and sample special
spaces fit outs, as may be required operators.

Provide lighting fixture type schedule.

Structural Drawings:

ALTERNATES
Volume 2

Survey of surrounding buildings, structures and improvements in both wet and dry
season to document pre-construction elevations.

Archaeological artifacts, as applicable.


Calculations:

Final drainage calculations, including storm water detention.

Final parking calculations.

Pipe sizing calculations for water and sewer pipes.

Pavement design calculations.

Demolition plans (where applicable).


Full set of structural construction drawings:
- Drawings must be fully dimensioned, noted and detailed for accurate construction.
- Load criteria for all floor live loads, roof live load, wind load, earthquake design data,
and special loads must be shown on drawings. Live load reduction of the uniformly
distributed floor live loads, if used in the design, shall be indicated.
- Basic wind speed: Wind importance factor I, and Buildings category as per the
applicable codes, Wind exposure, the applicable internal pressure coefficient must be
indicated.
- Seismic design criteria, such as Seismic use group, Site class, Basic seismic-forceresisting system, Design base shear, and analytical procedure must indicated.
Additional information may be required by the local Buildings official.
- Soil bearing pressure and lateral earth pressure must be indicated.
- Properties of basic materials must be indicated.
- Indicate the codes and standards used to develop the project.

01230 Page 27 of 32
May 2012

Saraya Aqaba

Specifications

a.
b.

c.

d.

4.

Mechanical Drawings:
a.

ALTERNATES
Volume 2

Schedules: Schedules for foundations, columns, walls, beams, slabs, and decks, as
applicable.
Structural details: (All typical details must be shown on the drawings)

Include details for steel connections.

Include details for all fire-rated assemblies, indicating Underwriters Laboratories


Inc. or other nationally recognized testing laboratory fire resistance directory design
numbers.

Include details for anchorage of building system equipment and nonstructural


building elements (maybe shown on mechanical, electrical, or architectural
drawings, as applicable).
Calculations: For any computer generated results, submit a model of the input data and all
pertinent program material required to understand the output. A narrative of the input and
results should be contained in the calculations as well.

Final structural calculations, including:


Gravity loads.
Lateral loads.
Foundations.
Thermal loads where significant.
Vibration propagation.
Supports for nonstructural elements, including mechanical and electrical
equipment.
Steel connections
Provide sketches showing framing plans with dimensions and grid lines, Free body/force
diagram in support of the calculations. Refer to drawing numbers where the calculated
items are shown on the drawing.

HVAC:

The construction documents must be complete, coordinated between disciplines,


readable and buildable, with no room for unreasonable additional interpretation.

The drawings listed below represent requirements for the Engineers review, and do
not constitute any limitation on the documentation required to properly construct the
project, or limit the professional design liability for errors and omissions.

One of the guidelines to insure inter-discipline and intra-discipline coordination is


included under each category of work and is referred to as the Review Checklist.

The consultants should make sure that all of these items, and others that pertain to
good project coordination, are reviewed and addressed before submission of the
documents to the Engineer.

Single line schematic flow and riser diagram(s):


Airflow quantities and balancing devices for all heating/cooling equipment.
Water flow quantities and balancing devices for all heating/cooling
equipment.
Flow/energy measuring devices for water and air systems for all cooling,
heating and terminal equipment.

Automatic temperature control diagram(s):


Control flow diagrams showing all sensors, valves, and controllers (analog
and digital inputs for controllers, front end equipment and system
architecture).
Sequence of operations of all the systems and its operation (occupied and
unoccupied).
Building Automation Systems and their descriptions.
Energy flow/metering devices for major equipment such as chillers, boilers,
pumps, and other terminal equipment.
01230 Page 28 of 32
May 2012

Saraya Aqaba

Specifications

b.

ALTERNATES
Volume 2

Diagram to show control signal interface, complete with sequence of


operation.
BMS Software requirements.
Show location of energy metering devices and their connection to central
processor.

Schedules:
Provide schedules of major equipment that includes chillers, boilers, pumps,
air handling units, and terminal units.
Air Terminal Devices
Air Balance Relationships between Spaces

System load and supply air calculations (for VAV and VRV systems).

System pressure static analysis at peak and minimum block loads (for VAV and
VRV systems).

Acoustical calculations (for VAV and VRV systems, use peak air flow).

Calculations for duct losses.

Calculations for piping losses.

Flow and head calculations for pumping systems.

Selection of equipment, cut sheets of selected equipment.

Psychometric calculations for full load and partial load utilization in summer,
winter, spring, and fall. (Partial loads at 50% and 25%, and unoccupied hours.)

Detailed energy analysis. Output shall indicate energy consumption of the system
and total Buildings energy summary.

Fuel consumption estimates.

Additional analyses as required to optimize equipment selections, heat


recovery/storage, and control/zoning options.

Sizing of fuel storage and distribution and vibration isolation.

Systems must be fully drawn and sized to permit accurate construction.

HVAC piping and equipment plans:


All valves must be shown. Indicate locations where temperature, pressure,
flow, contaminant/ combustion gases, or vibration gauges are required, and if
remote sensing is required.
Mechanical room piping layout shall be double line.

HVAC duct and equipment plans:


Single line piping and double line ductwork layout.
Show terminal air devices.
Perimeter terminal units.
Drawings of mechanical equipment room(s) showing all mechanical
equipment serving the project including equipment access and service
requirements. (The layout shall indicate the spaces allocated for maintenance
and removal.)
Air balancing of systems.
Roof plan showing all roof-mounted equipment.
Show adequate access from mechanical equipment room(s) to freight
elevators.
Show adequate access to roof-mounted equipment.
Mechanical details.
All dampersboth fire dampers and volume control dampersmust be
shown.

Ductwork ahead of the distribution terminal must be indicated in true size (double
line).
Plumbing: Piping riser diagrams floor plans:

Plumbing layout and fixtures; large-scale plans should be used where required for
clarity.

Riser diagrams for waste and vent lines.


01230 Page 29 of 32
May 2012

Saraya Aqaba

Specifications

c.

d.

5.

Fire Protection: Fire protection and life safety submission requirements shall be identified as a
separate Fire Protection section as outlined in this document.
a.

b.

c.

d.

ALTERNATES
Volume 2

Riser diagrams for domestic cold and hot water lines.

Plumbing fixture schedule.


Narrative: A written narrative describing the final mechanical system and equipment
selection including:

Updated narrative submitted during design development.

Updated ductwork and piping loss calculations.

Updated equipment selections with capacities, weights, sizes and power


requirements

Updated psychometrics.

Updated design conditions.

Updated Ventilation rates, updated dehumidification and pressurization conditions.

Updated description of the airside and waterside systems and the associated
components, including operating characteristics, ranges, and capacities, spaces
served and special features.

Updated description of occupied, partial occupancy, and unoccupied related


sequence of operations.

Updated fuel and utility requirements.

A code compliance statement.


Calculations and Energy Analysis: Plumbing calculations:

Include entire Buildings , including roof drainage calculations and hot water heating
calculations.

Water supply calculations, including pressure.

Roof drainage calculations.

Sanitary waste sizing calculations.

Drawings:

Full set of fire protection construction drawings. Drawings must be carefully


dimensioned, noted and detailed for accurate construction.

Fire Protection details. (All typical details must be shown on the drawings.)
Buildings Construction:
Buildings construction type .
Firewalls and smoke partitions.
Panel and curtain walls.
Fire stopping configurations. Include details of all openings between the
exterior walls (including panel, curtain, and spandrel walls) and floor slabs,
openings in floors, and shaft enclosures.
Life Safety
Each stair.
Horizontal exits.
Each required fire door.
Stairway pressurization fans.
Security door hardware, including operation procedures.
Water Supply:

Fire pump configuration.

Anchorage of underground fire protection water supply lines.

Standpipe riser.
Water Based Fire Extinguishing Systems:

Installation of water flow switches and tamper switches.

Sprinkler floor control valves, sectional valves, and inspector text assembly.
Non-Water Based Fire Extinguisher Systems:

01230 Page 30 of 32
May 2012

Saraya Aqaba

Specifications

e.

f.

6.

Electrical Drawings:
a.

ALTERNATES
Volume 2

Special fire extinguishing systems (e.g., wet chemical, etc.).


Fire Alarm System:

Fire alarm riser.

Typical firefighter telephone station.

Typical firefighter telephone jack.

Electrical closets for fire alarm system panels.

Fire alarm telephone panel (includes voice paging microphone and firefighter
telephone system).

Visual indicating device control and power detail, typical for floors (state location).

Amplifier rack (state location).

Typical location of duct smoke detectors.

Outdoor fire alarm speaker.

Wall mounted cone fire alarm speaker.

Typical terminal cabinet.

Lay in ceiling mounted fire alarm speaker.

Lay in ceiling mounted fire alarm combination speaker/strobe.

Wall mounted strobe device.

Typical manual fire alarm box installation.

Fire alarm system input/output matrix.

Graphic annunciator panel.

Installation of the graphic annunciator.

Fire command center showing the locations of each panel to be installed.


Calculations: For any fire modeling generated results, submit a copy of the input data and
all pertinent program material and assumptions required to understand the output and the
analysis. A narrative of the input and results shall be part of the calculations.

Final occupant load and egress calculations.

Final fire protection water supply calculations. Includes water supply flow testing
data.

Final fire pump calculations where applicable.

Final smoke control calculations where applicable (e.g., atrium, etc.).

Final stairway pressurization calculations.

Fire modeling.

Final calculations for sound attenuation through doors and walls for placement and
location of fire alarm system audible notification appliances.

General: Systems must be fully drawn and sized to permit accurate construction:

Floor plans. Show lighting, power distribution and communications raceway


distribution and locations of fire alarm and annunciator panels.

Single-line diagram of primary and secondary power distribution. Include normal


power, emergency power and UPS.

Single-line diagram of fire alarm system.

Single-line diagram of telecommunications system.

Circuit layout of lighting control system.

Details of under floor distribution system, as applicable.

Site plan. Indicate service locations, manholes, duct banks and site lighting.

Layout of electrical equipment spaces. Show all electrical equipment. Include


elevations of substation transformers and disconnect switches.

Schedules for switchgear, switchboards, motor control centers, panel boards and
unit substations.

Grounding diagram.

Complete phasing plan (as required).


01230 Page 31 of 32
May 2012

Saraya Aqaba

Specifications

b.

Security systems site plan, final locations of all security devices and conduit runs.

Security system floor plans, layout of all security systems.

Storage areas for electrical equipment/spare parts.


Calculations:

Illumination level calculations.

Short circuit calculations.

Voltage drop calculations.

Overcurrent coordination study.

Generator calculations, Include starter loads.

7.

Specifications: Final Specifications set shall be submitted to the Engineer and completely edited
version of each specification section to be used on the Project. Additional specification
requirement may be provided by Engineer, Employer, or Operators for inclusion

8.

Detailed Design BOQs: A final, detailed and priced BOQs must be provided at this stage, to the
approval of the Engineer, confirming that the Detailed design will be constructed within the
Accepted Contract Amount.

END OF SECTION 01230

ALTERNATES
Volume 2

01230 Page 32 of 32
May 2012

Saraya Aqaba

Specifications

SECTION 01310 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1

RELATED DOCUMENTS
A.

1.2

Drawings and general provisions of the Contract, including General and Particular Conditions and
other Division 1 Specification Sections, apply to this Section.

SUMMARY
A.

This Section includes administrative provisions for coordinating construction operations on Project
including, but not limited to, the following:
1.
2.
3.
4.

B.

1.3

Coordination.
Administrative and supervisory personnel.
Project meetings.
Requests for Interpretation (RFIs).

Related Sections include the following:


1.
Division 1 Section "Construction Progress Documentation" for preparing and submitting
Contractor's Construction Schedule.
2.
Division 1 Section "Execution Requirements" for procedures for coordinating general
installation and field-engineering services, including establishment of benchmarks and control
points.
3.
Division 1 Section "Closeout Procedures" for coordinating closeout of the Contract.

DEFINITIONS
A.

1.4

RFI: Request from Contractor seeking interpretation or clarification of the Contract Documents.

COORDINATION
A.

Coordination: Coordinate construction operations included in different Sections of the Specifications


to ensure efficient and orderly installation of each part of the Work. Coordinate construction
operations, included in different Sections, that depend on each other for proper installation,
connection, and operation.

B.

Administrative Procedures: Coordinate scheduling and timing of required administrative procedures


with other construction activities to avoid conflicts and to ensure orderly progress of the Work. Such
administrative activities include, but are not limited to, the following:
1.
2.
3.
4.
5.
6.
7.

1.5

Preparation of Contractor's Construction Schedule.


Preparation of the Schedule of Values.
Installation and removal of temporary facilities and controls.
Delivery and processing of submittals.
Progress meetings.
Preinstallation conferences.
Project closeout activities.

ADMINISTRATIVE AND SUPERVISORY PERSONNEL


A.

General: In addition to Project superintendent, provide other administrative and supervisory


personnel as required for proper performance of the Work.

PROJECT MANAGEMENT AND COORDINATION


Volume 2

01310 Page 1 of 7
May 2012

Saraya Aqaba
1.
B.

Include special personnel required for coordination of operations with other Contractors.

Key Personnel Names: Within 14 days of starting construction operations, submit a list of key
personnel assignments, including superintendent and other personnel in attendance at Project site.
Identify individuals and their duties and responsibilities; list addresses and telephone numbers,
including home and office telephone numbers. Provide names, addresses, and telephone numbers of
individuals assigned as standbys in the absence of individuals assigned to Project.
1.

1.6

Specifications

Post copies of list in Project meeting room, in temporary field office, and by each temporary
telephone. Keep list current at all times.

CONTRACTORS RESOURCES INFORMATION


A.

The Contractor shall make sure that it uses processes required to make the most effective use of the
people and materials involved with the project. The Contractor shall demonstrate good organizational
planning, staff acquisition and team development as required to perform the project activities as per
the Contract. In addition to demonstrating efficient planning of material & equipments delivery to the
Project site, the Contractor shall check and coordinate the project resources and establish the Project
Records System & Archives and monitor the performance reporting & change to the scope.

B.

The Contractor shall provide detailed systemized information and efficient plans related to the
categories below:

1.7

1.

Labor Resource Histogram: The labor resource histogram shall show all manpower working in
all the Project Zones including those for the Contractor, Sub-Contractor, suppliers and
Engineering companies that are working on the project site. The histogram shall show the
resource leveling procedures.

2.

Project Team Directory: The Contractor shall submit a Project Team Directory showing all
stakeholders involved in the Project / Zones. The directory shall include names of key
personnel, official and liability address, phones and contact addresses of all stakeholders
including main subcontractors, designers, engineering offices involved in the project,
suppliers, etc..

3.

Roles and Responsibility Matrix for the Contractor Team: The Contractor shall submit a roles
and responsibility matrix for the overall Project as well as each Zone to the Engineer for his
review. Each Zone matrix shall show all stake holders involved in the design and construction
of said Zone.

4.

Organization & Project Chart: The Contractor shall submit for the Engineers review and
information an Organization Chart and Project Chart for each Zone of the Saraya Aqaba
Project.

PROJECT MEETINGS
A.

General: Schedule and conduct meetings and conferences at Project site, unless otherwise indicated.
1.

2.
3.

B.

Attendees: Inform participants and others involved, and individuals whose presence is
required, of date and time of each meeting. Notify Engineer of scheduled meeting dates and
times.
Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.
Minutes: Record significant discussions and agreements achieved. Distribute the meeting
minutes to everyone concerned, including Engineer, within three days of the meeting.

Preconstruction Conference: Schedule a preconstruction conference before starting construction, at a


time convenient to Engineer and Employer, but no later than 15 days after execution of the
Agreement. Hold the conference at Project site or another convenient location. Conduct the meeting
to review responsibilities and personnel assignments.

PROJECT MANAGEMENT AND COORDINATION


Volume 2

01310 Page 2 of 7
May 2012

Saraya Aqaba
1.

2.

Specifications
Attendees: Authorized representatives of Engineer, Employer, and their consultants;
Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties
shall attend the conference. All participants at the conference shall be familiar with Project
and authorized to conclude matters relating to the Work. The meeting shall be chaired by the
Engineer.
Agenda: Discuss items of significance that could affect progress, including the following:
a.
b.
c.
d.
e.
f.
g.
h.
i.
j.
k.
l.
m.
n.
o.
p.
q.
r.
s.
t.
u.
v.
w.
x.
y.
z.
aa.
bb.
cc.
dd.
ee.
ff.
gg.
hh.
ii.
jj.

3.
C.

Contract Time: Notice to Proceed date and Date for Completion.


Tentative construction schedule.
Phasing.
Mobilization and staging.
Access to the Project Site.
Access routes.
Critical work sequencing and long-lead items.
Designation of key personnel, their duties and lines of communication.
Procedures for processing field decisions and Variation Orders.
Procedures for RFIs.
Procedures for testing and inspecting.
Procedures for processing Applications for Payment.
Distribution of the Contract Documents.
Scheduling and submittals.
Submittal procedures.
Preparation of Record Documents.
Use of the premises.
Work restrictions.
Environment control / Environmental Management Plan EMP.
Owner's occupancy requirements.
Responsibility for temporary facilities and controls.
Construction waste management and recycling.
Parking availability.
Office, work, and storage areas.
Equipment deliveries and priorities.
First aid.
Security requirements (List of Contractor's Personnel).
Emergency procedures and phone numbers.
Protection of site and archaeological site.
Progress cleaning.
Working hours.
Safety requirements.
Utility interruptions, relocating.
Pre-Condition survey of the site.
Accessibility requirements.
Quality assurance.

Minutes: Engineer will record and distribute meeting minutes.

Preinstallation Conferences: Conduct a pre-installation conference at Project site before each


construction activity that requires coordination with other construction.
1.

2.

Attendees: Installer and representatives of manufacturers and fabricators involved in or


affected by the installation and its coordination or integration with other materials and
installations that have preceded or will follow, shall attend the meeting. Advise Engineer of
scheduled meeting dates.
Agenda: Review progress of other construction activities and preparations for the particular
activity under consideration, including requirements for the following:
a.
b.
c.
d.
e.
f.

The Contract Documents.


Options.
Related RFIs.
Related Variation Orders.
Purchases.
Deliveries.

PROJECT MANAGEMENT AND COORDINATION


Volume 2

01310 Page 3 of 7
May 2012

Saraya Aqaba

Specifications
g.
h.
i.
j.
k.
l.
m.
n.
o.
p.
q.
r.
s.
t.
u.
v.
w.
x.
y.
z.
aa.
bb.

3.
4.
5.

D.

Submittals.
Review of mockups.
Possible conflicts.
Compatibility problems.
Time schedules.
Weather limitations.
Manufacturer's written recommendations.
Warranty requirements.
Compatibility of materials.
Acceptability of substrates.
Temporary facilities and controls.
Space and access limitations.
Regulations of authorities having jurisdiction.
Testing and inspecting requirements.
Installation procedures.
Coordination with other work.
Required performance results.
Protection of adjacent work.
Protection of construction and personnel.
Protection of environment.
Safety and health.
Security

Record significant conference discussions, agreements, and disagreements, including required


corrective measures and actions.
Reporting: Engineer will distribute minutes of the meeting to each party present and to parties
who should have been present.
Do not proceed with installation if the conference cannot be successfully concluded. Initiate
whatever actions are necessary to resolve impediments to performance of the Work and
reconvene the conference at earliest feasible date.

Progress Meetings: Conduct progress meetings at by-weekly intervals, or weekly if deemed necessary
by the Engineer. Coordinate dates of meetings with preparation of payment requests.
1.

2.

Attendees: In addition to representatives of Engineer, Employer and Contractor, each


subcontractor, supplier, and other entity concerned with current progress or involved in
planning, coordination, or performance of future activities shall be represented at these
meetings. All participants at the conference shall be familiar with Project and authorized to
conclude matters relating to the Work. The meeting shall be chaired by the Engineer.
Agenda: Review and correct or approve minutes of previous progress meeting. Review other
items of significance that could affect progress. Include topics for discussion as appropriate to
status of Project.
a.

Contractor's Construction Schedule: Review progress since the last meeting.


Determine whether each activity is on time, ahead of schedule, or behind schedule, in
relation to Contractor's Construction Schedule. Determine how construction behind
schedule will be expedited; secure commitments from parties involved to do so.
Discuss whether schedule revisions are required to ensure that current and subsequent
activities will be completed within the Contract Time.
1)

b.

Review schedule for next period.

Review present and future needs of each entity present, including the following:
1)
2)
3)
4)
5)
6)
7)

Interface requirements.
Sequence of operations.
Status of submittals.
Procurement and deliveries.
Off-site fabrication.
Access.
Site utilization.

PROJECT MANAGEMENT AND COORDINATION


Volume 2

01310 Page 4 of 7
May 2012

Saraya Aqaba

Specifications
8)
9)
10)
11)
12)
13)
14)
15)
16)
17)
18)
19)
20)
21)
22)

3.
4.

Minutes: Engineer will record and distribute to Contractor the meeting minutes.
Reporting: Distribute minutes of the meeting to each party present and to parties who should
have been present.
a.

E.

Temporary facilities and controls.


Work hours.
Hazards and risks.
Progress cleaning.
Quality and work standards.
Status of correction of deficient items.
Field observations.
RFIs.
Status of proposal requests.
Pending changes.
Status of Variation Orders.
Pending claims and disputes.
Documentation of information for payment requests.
Safety and health.
Security.

Schedule Updating: Revise Contractor's Construction Schedule after each progress


meeting where revisions to the schedule have been made or recognized. Issue revised
schedule concurrently with the report of each meeting.

Coordination Meetings: Conduct Project coordination meetings at weekly intervals. Project


coordination meetings are in addition to specific meetings held for other purposes, such as progress
meetings and preinstallation conferences.
1.

2.

Attendees: In addition to representatives of Engineer, Employer and Contractor, each


subcontractor, supplier, and other entity concerned with current progress or involved in
planning, coordination, or performance of future activities shall be represented at these
meetings. All participants at the conference shall be familiar with Project and authorized to
conclude matters relating to the Work.
Agenda: Review and correct or approve minutes of the previous coordination meeting.
Review other items of significance that could affect progress. Include topics for discussion as
appropriate to status of Project.
a.

b.

c.

Combined Contractor's Construction Schedule: Review progress since the last


coordination meeting. Determine whether each contract is on time, ahead of schedule,
or behind schedule, in relation to Combined Contractor's Construction Schedule.
Determine how construction behind schedule will be expedited; secure commitments
from parties involved to do so. Discuss whether schedule revisions are required to
ensure that current and subsequent activities will be completed within the Contract
Time.
Schedule Updating: Revise Combined Contractor's Construction Schedule after each
coordination meeting where revisions to the schedule have been made or recognized.
Issue revised schedule concurrently with report of each meeting.
Review present and future needs of each Sub-Contractor present, including the
following:
1)
2)
3)
4)
5)
6)
7)
8)
9)
10)
11)
12)

Interface requirements.
Sequence of operations.
Status of submittals.
Deliveries.
Off-site fabrication.
Access.
Site utilization.
Temporary facilities and controls.
Work hours.
Hazards and risks.
Progress cleaning.
Quality and work standards.

PROJECT MANAGEMENT AND COORDINATION


Volume 2

01310 Page 5 of 7
May 2012

Saraya Aqaba

Specifications
13)

3.

1.8

Variation Orders.

Reporting: Record meeting results and distribute copies to everyone in attendance and to
others affected by decisions or actions resulting from each meeting.

REQUESTS FOR INTERPRETATION (RFIs)


A.

Procedure: Immediately on discovery of the need for interpretation of the Contract Documents, and
if not possible to request interpretation at Project meeting, prepare and submit an RFI in the form
specified.
1.
2.

B.

RFIs shall originate with Contractor. RFIs submitted by entities other than Contractor will be
returned with no response.
Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or
work of subcontractors.

Content of the RFI: Include a detailed, legible description of item needing interpretation and the
following:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.

Project name.
Date.
Name of Employer.
Name of Engineer.
Name of Contractor.
RFI number, numbered sequentially.
Specification Section number and title and related paragraphs, as appropriate.
Drawing number and detail references, as appropriate.
Field dimensions and conditions, as appropriate.
Contractor's suggested solution(s). If Contractor's solution(s) impact the Contract Time or the
Contract Sum, Contractor shall state impact in the RFI.
Contractor's signature.
Attachments: Include drawings, descriptions, measurements, photos, Product Data, Shop
Drawings, and other information necessary to fully describe items needing interpretation.
a.

C.

Hard-Copy RFIs: form provided by Engineer.


1.

D.

Identify each page of attachments with the RFI number and sequential page number.

Software-Generated RFIs: Software-generated form with substantially the same content as indicated
above.
1.

E.

Supplementary drawings prepared by Contractor shall include dimensions, thicknesses,


structural grid references, and details of affected materials, assemblies, and
attachments.

Attachments shall be electronic files in Adobe Acrobat PDF format.

Engineer's Action: Engineer will review each RFI, determine action required, and return it. Allow
fourteen working days for Engineer's response for each RFI. RFIs received after 1:00 p.m. will be
considered as received the following working day.
1.

The following RFIs will be returned without action:


a.
b.
c.
d.
e.
f.

Requests for approval of submittals.


Requests for approval of substitutions.
Requests for coordination information already indicated in the Contract Documents.
Requests for adjustments in the Contract Time or the Contract Sum.
Requests for interpretation of Engineer's actions on submittals.
Incomplete RFIs or RFIs with numerous errors.

PROJECT MANAGEMENT AND COORDINATION


Volume 2

01310 Page 6 of 7
May 2012

Saraya Aqaba
2.
3.

Specifications
Engineer's action may include a request for additional information, in which case Engineer's
time for response will start again.
Engineer's action on RFIs that may result in a change to the Contract Time or the Contract
Sum may be eligible for Contractor to submit Change Proposal."
a.

If Contractor believes the RFI response warrants change in the Contract Time or the
Contract Sum, notify Engineer in writing within 10 days of receipt of the RFI response.

F.

On receipt of Engineer's action, update the RFI log and immediately distribute the RFI response to
affected parties. Review response and notify Engineer within seven days if Contractor disagrees with
response.

G.

RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number. Submit
log weekly. Form provided by Engineer. Include the following: Software log with not less than the
following:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.

Project name.
Name and address of Employer.
Name and address of Engineer.
Name and address of Contractor.
RFI number including RFIs that were dropped and not submitted.
RFI description.
Date the RFI was submitted.
Date Engineer's response was received.
Identification of related Minor Change in the Work, Construction Change Directive, and
Proposal Request, as appropriate.
Identification of related Field Order, Work Change Directive, and Proposal Request, as
appropriate.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01310

PROJECT MANAGEMENT AND COORDINATION


Volume 2

01310 Page 7 of 7
May 2012

Saraya Aqaba

Specifications

SECTION 01320 - CONSTRUCTION PROGRESS DOCUMENTATION

PART 1 - GENERAL

1.1

RELATED DOCUMENTS
A.

1.2

Drawings and general provisions of the Contract, including General and Supplementary Conditions
and other Division 1 Specification Sections, apply to this Section.

SUMMARY
A.

This Section includes administrative and procedural requirements for documenting the progress of
construction during performance of the Work, including the following:
1.
2.
3.
4.
5.
6.
7.

B.

1.3

Submittals Schedule.
Preliminary Construction Schedule.
Contractor's Construction Schedule.
Daily construction reports.
Material location reports.
Field condition reports.
Special reports.

Related Sections include the following:


1.
Division 1 Section "Project Management and Coordination" for submitting and distributing
meeting and conference minutes.
2.
Division 1 Section "Submittal Procedures" for submitting schedules and reports.
3.
Division 1 Section "Photographic Documentation" for submitting construction photographs.
4.
Division 1 Section "Quality Requirements" for submitting a schedule of tests and inspections.

DEFINITIONS
A.

Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and
controlling the construction project. Activities included in a construction schedule consume time and
resources.
1.
2.
3.

Critical activities are activities on the critical path. They must start and finish on the planned
early start and finish times.
Predecessor Activity: An activity that precedes another activity in the network.
Successor Activity: An activity that follows another activity in the network.

B.

CPM: Critical path method, which is a method of planning and scheduling a construction project
where activities are arranged based on activity relationships. Network calculations determine when
activities can be performed and the critical path of Project.

C.

Critical Path: The longest connected chain of interdependent activities through the network schedule
that establishes the minimum overall Project duration and contains no float.

D.

Event: The starting or ending point of an activity.

E.

Float: The measure of leeway in starting and completing an activity.


1.
Free float is the amount of time an activity can be delayed without adversely affecting the
early start of the successor activity.
2.
Total float is the measure of leeway in starting or completing an activity without adversely
affecting the planned Project completion date.

CONSTRUCTION PROGRESS DOCUMENTATION


Volume 2

01320 Page 1 of 9
May 2012

Saraya Aqaba

Specifications

F.

Fragnet: A partial or fragmentary network that breaks down activities into smaller activities for
greater detail.

G.

Major Area: A story of construction, a separate building, or a similar significant construction


element.

H.

Milestone: A key or critical point in time for reference or measurement.

I.

Network Diagram:
relationships.

J.

Resource Loading: The allocation of manpower and equipment necessary for the completion of an
activity as scheduled.

1.4

A graphic diagram of a network schedule, showing activities and activity

SUBMITTALS
A.

Qualification Data: For scheduling consultant.

B.

Submittals Schedule: Submit three copies of schedule. Arrange the following information in a
tabular format:
1.
2.
3.
4.
5.
6.

C.

Scheduled date for first submittal.


Specification Section number and title.
Submittal category (action or informational).
Name of subcontractor.
Description of the Work covered.
Scheduled date for Engineer's final release or approval.

Preliminary Construction Schedule: Submit three copies.


1.

Approval of preliminary construction schedule will not constitute approval of Schedule of


Values for cost-loaded activities.

D.

Preliminary Network Diagram: Submit three copies, large enough to show entire network for entire
construction period. Show logic ties for activities.

E.

Contractor's Construction Schedule: Submit three copies of initial schedule, large enough to show
entire schedule for entire construction period.
1.

F.

Submit an electronic copy of schedule, using software indicated, on CD-R, and labeled to
comply with requirements for submittals. Include type of schedule (Initial or Updated) and
date on label.

CPM Reports: Concurrent with CPM schedule, submit three copies of each of the following
computer-generated reports. Format for each activity in reports shall contain activity number, activity
description, cost and resource loading, original duration, remaining duration, early start date, early
finish date, late start date, late finish date, and total float in calendar days.
1.
2.
3.
4.

Activity Report: List of all activities sorted by activity number and then early start date, or
actual start date if known.
Logic Report: List of preceding and succeeding activities for all activities, sorted in ascending
order by activity number and then early start date, or actual start date if known.
Total Float Report: List of all activities sorted in ascending order of total float.
Earnings Report: Compilation of Contractor's total earnings from commencement of the Work
until most recent Application for Payment.

G.

Daily Construction Reports: Submit two copies at weekly intervals.

H.

Material Location Reports: Submit two copies at weekly intervals.

CONSTRUCTION PROGRESS DOCUMENTATION


Volume 2

01320 Page 2 of 9
May 2012

Saraya Aqaba

Specifications

I.

Field Condition Reports: Submit two copies at time of discovery of differing conditions.

J.

Special Reports: Submit two copies at time of unusual event.

1.5

QUALITY ASSURANCE
A.

Scheduling Consultant Qualifications: An experienced specialist in CPM scheduling and reporting,


with capability of producing CPM reports and diagrams within 48 hours of Engineer's request.

B.

Prescheduling Conference: Conduct conference at Project site to comply with requirements in


Division 1 Section "Project Management and Coordination." Review methods and procedures related
to the Preliminary Construction Schedule and Contractor's Construction Schedule, including, but not
limited to, the following:
1.
2.
3.
4.
5.
6.
7.
8.
9.

1.6

Review software limitations and content and format for reports.


Verify availability of qualified personnel needed to develop and update schedule.
Discuss constraints, including phasing, work stages and area separations.
Review time required for review of submittals and resubmittals.
Review requirements for tests and inspections by independent testing and inspecting agencies.
Review time required for completion.
Review and finalize list of construction activities to be included in schedule.
Review submittal requirements and procedures.
Review procedures for updating schedule.

COORDINATION
A.

Coordinate preparation and processing of schedules and reports with performance of construction
activities and with scheduling and reporting of separate Contractors.

B.

Coordinate Contractor's Construction Schedule with the Schedule of Values, list of subcontracts,
Submittals Schedule, progress reports, payment requests, and other required schedules and reports.
1.
2.

Secure time commitments for performing critical elements of the Work from parties involved.
Coordinate each construction activity in the network with other activities and schedule them in
proper sequence.

PART 2 - PRODUCTS

2.1

SUBMITTALS SCHEDULE
A.

Preparation: Submit a schedule of submittals, arranged in chronological order by dates required by


construction schedule. Include time required for review, resubmittal, ordering, manufacturing,
fabrication, and delivery when establishing dates.
1.
2.

Coordinate Submittals Schedule with list of subcontracts, the Schedule of Values, and
Contractor's Construction Schedule.
Initial Submittal: Submit concurrently with preliminary bar-chart schedule. Include submittals
required during the first 60 days of construction. List those required to maintain orderly
progress of the Work and those required early because of long lead time for manufacture or
fabrication.
a.

3.

At Contractor's option, show submittals on the Preliminary Construction Schedule,


instead of tabulating them separately.

Final Submittal: Submit concurrently with the first complete submittal of Contractor's
Construction Schedule.

CONSTRUCTION PROGRESS DOCUMENTATION


Volume 2

01320 Page 3 of 9
May 2012

Saraya Aqaba
2.2

Specifications

CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL


A.

Procedures: Comply with procedures contained in the Contract Conditions.

B.

Time Frame: Extend schedule from date established for commencement of the Work to date of
Substantial Completion.
1.

C.

Activities: Treat each story or separate area as a separate numbered activity for each principal
element of the Work. Comply with the following:
1.
2.

3.

4.
5.

D.

Contract completion date shall not be changed by submission of a schedule that shows an
early completion date, unless specifically authorized by the Engineer.

Activity Duration: Define activities so no activity is longer than 20 days, unless specifically
allowed by Engineer.
Procurement Activities: Include procurement process activities for the following long lead
items and major items, requiring a cycle of more than 60 days, as separate activities in
schedule. Procurement cycle activities include, but are not limited to, submittals, approvals,
purchasing, fabrication, and delivery.
Submittal Review Time: Include review and resubmittal times indicated in Division 1 Section
"Submittal Procedures" in schedule. Coordinate submittal review times in Contractor's
Construction Schedule with Submittals Schedule.
Testing Time: Include not less than seven days for testing.
Substantial Completion: Indicate completion in advance of date established for Substantial
Completion, and allow time for Engineer's administrative procedures necessary for
certification of Substantial Completion (Taking-Over Certificate).

Constraints: Include constraints and work restrictions indicated in the Contract Documents and as
follows in schedule, and show how the sequence of the Work is affected.
1.
2.
3.
4.

Phasing: Arrange list of activities on schedule by phase.


Products Ordered in Advance: Include a separate activity for each product. Include delivery
date. Delivery dates indicated stipulate the earliest possible delivery date.
Employer-Furnished Products: Include a separate activity for each product. Include delivery
date. Delivery dates indicated stipulate the earliest possible delivery date.
Work Restrictions: Show the effect of the following items on the schedule:
a.
b.
c.
d.
e.
f.
g.
h.

5.

Coordination with existing construction.


Limitations of continued occupancies.
Uninterruptible services.
Partial occupancy before Substantial Completion.
Use of premises restrictions.
Provisions for future construction.
Seasonal variations.
Environmental control.

Work Stages: Indicate important stages of construction for each major portion of the Work,
including, but not limited to, the following:
a.
b.
c.
d.
e.
f.
g.
h.
i.
j.
k.
l.

Subcontract awards.
Submittals.
Purchases.
Mockups.
Fabrication.
Sample testing.
Deliveries.
Installation.
Tests and inspections.
Adjusting.
Curing.
Placement into final use and operation.

CONSTRUCTION PROGRESS DOCUMENTATION


Volume 2

01320 Page 4 of 9
May 2012

Saraya Aqaba
6.

Specifications
Area Separations: Identify each major area of construction for each major portion of the
Work. Indicate where each construction activity within a major area must be sequenced or
integrated with other construction activities to provide for the following:
a.
b.

Structural completion.
Substantial Completion (Taking-Over).

E.

Milestones: Include milestones indicated in the Contract Documents in schedule, including, but not
limited to, the Notice to Commence, Taking Over and Performance Certificates.

F.

Cost Correlation: At the head of schedule, provide a cost correlation line, indicating planned and
actual costs. On the line, show currency volume of the Work performed as of dates used for
preparation of payment requests.
1.

2.
3.

Contractor shall assign cost to construction activities on the CPM schedule. Costs shall not be
assigned to submittal activities unless specified otherwise but may, with Engineer's approval,
be assigned to fabrication and delivery activities. Costs shall be under required principal
subcontracts for testing and commissioning activities, operation and maintenance manuals,
punch list activities, Project Record Documents, and demonstration and training (if
applicable).
Each activity cost shall reflect an accurate value subject to approval by Engineer.
Total cost assigned to activities shall equal the total Contract Sum.

G.

Contract Modifications: For each proposed contract modification and concurrent with its submission,
prepare a time-impact analysis using fragnets to demonstrate the effect of the proposed change on the
overall project schedule.

H.

Computer Software: Prepare schedules using a program that has been developed specifically to
manage construction schedules.
1.

2.3

Primavera latest version, for Windows XP operating system.

PRELIMINARY CONSTRUCTION SCHEDULE


A.

Bar-Chart Schedule: Submit preliminary horizontal bar-chart-type construction schedule within seven
days of date established for commencement of the Work.

B.

Preparation: Indicate each significant construction activity separately. Identify first workday of each
week with a continuous vertical line. Outline significant construction activities for first 60 days of
construction. Include skeleton diagram for the remainder of the Work and a cash requirement
prediction based on indicated activities.

2.4

CONTRACTOR'S CONSTRUCTION SCHEDULE (GANTT CHART)


A.

Gantt-Chart Schedule: Submit a comprehensive, fully developed, horizontal Gantt-chart-type,


Contractor's Construction Schedule within 21 days of date established for commencement of the
Work. Base schedule on the Preliminary Construction Schedule and whatever updating and feedback
was received since the start of Project.

B.

Preparation: Indicate each significant construction activity separately. Identify first workday of each
week with a continuous vertical line.
1.

2.5

For construction activities that require 3 months or longer to complete, indicate an estimated
completion percentage in 10 percent increments within time bar.

CONTRACTOR'S CONSTRUCTION SCHEDULE (CPM SCHEDULE)


A.

General: Prepare network diagrams using AON (activity-on-node) format.

CONSTRUCTION PROGRESS DOCUMENTATION


Volume 2

01320 Page 5 of 9
May 2012

Saraya Aqaba

Specifications

B.

Preliminary Network Diagram: Submit diagram within 14 days of date established for
commencement of the Work. Outline significant construction activities for the first 60 days of
construction. Include skeleton diagram for the remainder of the Work and a cash requirement
prediction based on indicated activities.

C.

CPM Schedule: Prepare Contractor's Construction Schedule using a computerized, cost- and
resource-loaded, time-scaled CPM network analysis diagram for the Work.
1.

Develop network diagram in sufficient time to submit CPM schedule so it can be accepted for
use no later than 21 days after date established for commencement of the Work.
a.

2.

3.
4.

D.

Conduct educational workshops to train and inform key Project personnel, including
subcontractors' personnel, in proper methods of providing data and using CPM schedule
information.
Establish procedures for monitoring and updating CPM schedule and for reporting progress.
Coordinate procedures with progress meeting and payment request dates.
Use "one workday" as the unit of time. Include list of nonworking days and holidays
incorporated into the schedule.

CPM Schedule Preparation: Prepare a list of all activities required to complete the Work. Using the
preliminary network diagram, prepare a skeleton network to identify probable critical paths.
1.

Activities: Indicate the estimated time duration, sequence requirements, and relationship of
each activity in relation to other activities. Include estimated time frames for the following
activities:
a.
b.
c.
d.
e.
f.
g.
h.
i.

2.
3.

4.

Preparation and processing of submittals.


Mobilization and demobilization.
Purchase of materials.
Delivery.
Fabrication.
Utility interruptions.
Installation.
Work by Engineer or Employer that may affect or be affected by Contractor's
activities.
Testing.

Critical Path Activities: Identify critical path activities, including those for interim completion
dates. Scheduled start and completion dates shall be consistent with Contract milestone dates.
Processing: Process data to produce output data on a computer-drawn, time-scaled network.
Revise data, reorganize activity sequences, and reproduce as often as necessary to produce the
CPM schedule within the limitations of the Contract Time.
Format: Mark the critical path. Locate the critical path near center of network; locate paths
with most float near the edges.
a.

E.

Failure to include any work item required for performance of this Contract shall not
excuse Contractor from completing all work within applicable completion dates,
regardless of Engineer's approval of the schedule.

Subnetworks on separate sheets are permissible for activities clearly off the critical
path.

Initial Issue of Schedule: Prepare initial network diagram from a list of straight "early start-total
float" sort. Identify critical activities. Prepare tabulated reports showing the following:
1.
2.
3.
4.
5.
6.

Contractor or subcontractor and the Work or activity.


Description of activity.
Principal events of activity.
Immediate preceding and succeeding activities.
Early and late start dates.
Early and late finish dates.

CONSTRUCTION PROGRESS DOCUMENTATION


Volume 2

01320 Page 6 of 9
May 2012

Saraya Aqaba
7.
8.
9.
10.
F.

Activity duration in workdays.


Total float or slack time.
Average size of workforce.
Currency value of activity (coordinated with the Schedules).

Schedule Updating: Concurrent with making revisions to schedule, prepare tabulated reports
showing the following:
1.
2.
3.
4.
5.
6.
7.

G.

Specifications

Identification of activities that have changed.


Changes in early and late start dates.
Changes in early and late finish dates.
Changes in activity durations in workdays.
Changes in the critical path.
Changes in total float or slack time.
Changes in the Contract Time.

Value Summaries: Prepare two cumulative value lists, sorted by finish dates.
1.
2.
3.
4.

In first list, tabulate activity number, early finish date, dollar value, and cumulative currency
value.
In second list, tabulate activity number, late finish date, dollar value, and cumulative currency
value.
In subsequent issues of both lists, substitute actual finish dates for activities completed as of
list date.
Prepare list for ease of comparison with payment requests; coordinate timing with progress
meetings.
a.
b.

2.6

In both value summary lists, tabulate "actual percent complete" and "cumulative value
completed" with total at bottom.
Submit value summary printouts one week before each regularly scheduled progress
meeting.

REPORTS
A.

Daily Construction Reports: Prepare a daily construction report recording the following information
concerning events at Project site:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.

List of subcontractors at Project site.


List of other contractors working at Project site.
List of construction work activities and operations performed at the Project Site, referenced to
locations and CPM schedule activity number.
Count and trade classification of workmen at Project Site, allocated to CPM schedule activity
numbers.
Count, category and status (working, idle, under maintenance) of contracting equipment at
project site, allocated to CPM schedule activity number.
Material deliveries.
High and low temperatures and general weather conditions.
Accidents.
Meetings and significant decisions.
Unusual events (refer to special reports).
Stoppages, delays, shortages, and losses.
Meter readings and similar recordings.
Emergency procedures.
Orders and requests of authorities having jurisdiction.
Variation Orders received and implemented.
Work Change Directives received and implemented.
Site instructions received.
Services connected and disconnected.
Equipment or system tests and start ups.
Engineers inspections.

CONSTRUCTION PROGRESS DOCUMENTATION


Volume 2

01320 Page 7 of 9
May 2012

Saraya Aqaba
21.
22.
23.

Specifications
Partial Completions and occupancies.
Taking-Over Certificates issued.
Any other general or specific information, requested by the Engineer to be reported.

B.

Material Location Reports: At monthly intervals, prepare and submit a comprehensive list of
materials delivered to and stored at Project site. List shall be cumulative, showing materials
previously reported plus items recently delivered. Include with list a statement of progress on and
delivery dates for materials or items of equipment fabricated or stored away from Project site.

C.

Field Condition Reports: Immediately on discovery of a difference between field conditions and the
Contract Documents, prepare and submit a detailed report. Submit with a request for interpretation on
format provided by Engineer. Include a detailed description of the differing conditions, together with
recommendations for changing the Contract Documents.

2.7

SPECIAL REPORTS
A.

General: Submit special reports directly to Engineer within one day of an occurrence with copy to
Employer. Distribute copies of report to parties affected by the occurrence.

B.

Reporting Unusual Events: When an event of an unusual and significant nature occurs at Project site,
whether or not related directly to the Work, prepare and submit a special report. List chain of events,
persons participating, response by Contractor's personnel, evaluation of results or effects, and similar
pertinent information. Advise Engineer when these events are known or predictable.

PART 3 - EXECUTION

3.1

CONTRACTOR'S CONSTRUCTION SCHEDULE


A.

Scheduling Consultant: Engage a consultant to provide planning, evaluation, and reporting using
CPM scheduling.
1.

2.

B.

Contractor's Construction Schedule Updating: At monthly intervals, update schedule to reflect actual
construction progress and activities. Issue schedule one week before each regularly scheduled
progress meeting.
1.

2.
3.
C.

In-House Option: Engineer may waive the requirement to retain a consultant if Contractor
employs skilled personnel with experience in CPM scheduling and reporting techniques.
Submit qualifications.
Meetings: Scheduling consultant shall attend all meetings related to Project progress, alleged
delays, and time impact.

Revise schedule immediately after each meeting or other activity where revisions have been
recognized or made. Issue updated schedule concurrently with the report of each such
meeting.
Include a report with updated schedule that indicates every change, including, but not limited
to, changes in logic, durations, actual starts and finishes, and activity durations.
As the Work progresses, indicate Actual Completion percentage for each activity.

Distribution: Distribute copies of approved schedule to Engineer, Employer, other contractors, testing
and inspecting agencies, and other parties identified by Contractor with a need-to-know schedule
responsibility.
1.
2.

Post copies in Project meeting rooms and temporary field offices.


When revisions are made, distribute updated schedules to the same parties and post in the
same locations. Delete parties from distribution when they have completed their assigned
portion of the Work and are no longer involved in performance of construction activities.

CONSTRUCTION PROGRESS DOCUMENTATION


Volume 2

01320 Page 8 of 9
May 2012

Saraya Aqaba

Specifications

END OF SECTION 01320

CONSTRUCTION PROGRESS DOCUMENTATION


Volume 2

01320 Page 9 of 9
May 2012

Saraya Aqaba

Specifications

SECTION 01322 - PHOTOGRAPHIC DOCUMENTATION

PART 1 - GENERAL

1.1

RELATED DOCUMENTS
A.

1.2

Drawings and general provisions of the Contract, including General and Particular Conditions and
other Division 1 Specification Sections, apply to this Section.

SUMMARY
A.

This Section includes administrative and procedural requirements for the following:
1.
2.
3.

B.

Related Sections include the following:


1.

1.3

Preconstruction photographs.
Periodic construction photographs.
Final Completion construction photographs.

Division 1 Section "Closeout Procedures" for submitting photographic negatives and digital
media as Project Record Documents at Project closeout.

SUBMITTALS
A.

Qualification Data: For photographer.

B.

Key Plan: Submit key plan of Project site and buildings with notation of vantage points marked for
location and direction of each photograph. Indicate elevation or story of construction. Include same
label information as corresponding set of photographs.

C.

Construction Photographs: Submit three prints of each photographic view within seven days of
taking photographs.
1.

2.

Format: 203-by-254-mm smooth-surface matte prints on single-weight commercial-grade


photographic paper, mounted on linen or card stock to allow a 25-mm- wide margin and
enclosed back to back in clear plastic sleeves that are punched for standard 3-ring binder.
Identification: On back of each print, provide an applied label or rubber-stamped impression
with the following information:
a.
b.
c.
d.
e.
f.
g.
h.
i.

3.

4.

Name of Project.
Name and address of photographer.
Name of Employer.
Name of Engineer.
Name of Contractor.
Name of Sub-Contractor.
Date photograph was taken if not date stamped by camera.
Description of vantage point, indicating location, direction (by compass point), and
elevation or story of construction.
Unique sequential identifier.

Negatives: Submit a complete set of photographic negatives in individually protected negative


sleeves with each submittal of prints as a Project Record Document. Identify negatives with
label matching photographic prints.
Digital Images: Submit a complete set of digital image electronic files with each submittal of
prints as a Project Record Document on CD-ROM. Identify electronic media with date
photographs were taken. Submit images that have same aspect ratio as the sensor, uncropped.

PHOTOGRAPHIC DOCUMENTATION
Volume 2

01322 Page 1 of 4
May 2012

Saraya Aqaba
1.4

Specifications

QUALITY ASSURANCE
A.

1.5

Photographer Qualifications: An individual who has been regularly engaged as a professional


photographer of construction projects for not less than three years.

COORDINATION
A.

1.6

Auxiliary Services: Cooperate with photographer and provide auxiliary services requested, including
access to Project site and use of temporary facilities, including temporary lighting required to produce
clear, well-lit photographs without obscuring shadows.

USAGE RIGHTS
A.

1.7

Obtain and transfer copyright usage rights from photographer to Contractor for unlimited
reproduction of photographic documentation.

EXTRA PRINTS
A.

Negatives: Photographer shall retain photographic negatives for three years after date of Substantial
Completion. During this period, photographer shall fill orders by Engineer or Contractor for extra
prints. Photographer shall price extra prints at prevailing local commercial prices.

B.

Extra Prints: If requested by Engineer, photographer shall prepare extra prints of photographs.
Photographer shall distribute these prints directly to designated parties who will pay the costs for
extra prints.

PART 2 - PRODUCTS

2.1

PHOTOGRAPHIC MEDIA
A.

Photographic Film: 35 mm, medium speed (ISO 100-200).

B.

Digital Images: Provide images in uncompressed TIFF format, produced by a digital camera with
minimum sensor size of 4.0 megapixels, and at an image resolution of not less than 1600 by 1200
pixels.

PART 3 - EXECUTION

3.1

CONSTRUCTION PHOTOGRAPHS
A.

Photographer: Engage a qualified commercial photographer to take construction photographs.

B.

General: Take photographs using the maximum range of depth of field, and that are in focus, to
clearly show the Work. Photographs with blurry or out-of-focus areas will not be accepted.
1.

C.

Maintain key plan with each set of construction photographs that identifies each photographic
location.

Film Images:
1.

Date Stamp: Unless otherwise indicated, date and time stamp each photograph as it is being
taken so stamp is integral to photograph.

PHOTOGRAPHIC DOCUMENTATION
Volume 2

01322 Page 2 of 4
May 2012

Saraya Aqaba
2.

D.

Field Office Prints: Retain one set of prints of progress photographs in the field office at
Project site, available at all times for reference. Identify photographs same as for those
submitted to Engineer.

Digital Images: Submit digital images exactly as originally recorded in the digital camera, without
alteration, manipulation, editing, or modifications using image-editing software.
1.
2.

E.

Specifications

Date and Time: Include date and time in filename for each image.
Field Office Images: Maintain one set of images on CD-ROM in the field office at Project
site, available at all times for reference. Identify images same as for those submitted to
Engineer.

Preconstruction Photographs: Before commencement of construction, take sufficient color and digital
photographs of Project site and surrounding properties, including existing items to remain during
construction, from different vantage points, as directed by Engineer. Take additional photographs in
sufficient number and detail to:
1.

2.

3.
4.

Show conditions of existing buildings, structures, site improvements and features on and/or
adjacent to Project Site, accurately recording any physical condition before starting the Work,
that might otherwise be misconstrued as damage caused by subsequent demolition or
construction operations.
Show conditions of existing buildings, structures, assemblies, features either on or adjoining
property to accurately record physical conditions at start of construction or other components
scheduled for selective demolition or dismantling, accurately recording physical condition, for
subsequent reconstruction, restoration or rehabilitation.
Take additional photographs as required to record settlement or cracking of adjacent
structures, pavements, and improvements.
Flag excavation areas before taking construction photographs.

F.

Periodic Construction Photographs: At least 50 color, digital progress photographs of each building /
Zone shall be taken monthly, with timing each month adjusted to coincide with the cutoff date
associated with each Application for Payment. Select vantage points to show status of construction
and progress since last photographs were taken. The actual number and location of views shall be
directed by the Engineer.

G.

Engineer-Directed Construction Photographs: From time to time, Engineer will instruct photographer
about number and frequency of color, digital photographs and general directions on vantage points.
Select actual vantage points and take photographs to show the status of construction and progress
since last photographs were taken.

H.

Time-Lapse Sequence Construction Photographs: Take sufficient color, digital photographs as


indicated, to show status of construction and progress since last photographs were taken.
1.
2.

Frequency: Take photographs weekly, with timing each month adjusted to coincide with the
cutoff date associated with each Application for Payment.
Vantage Points: Following suggestions by Engineer and Contractor, photographer to select
vantage points. During each of the following construction phases, take not less than two of the
required shots from same vantage point each time to create a time-lapse sequence as follows:
a.
b.
c.
d.

I.

Commencement of the Work, through completion of sub-grade construction.


Above-grade structural framing.
Exterior building enclosure.
Interior Work, through date of Substantial Completion (Taking-Over).

Final Completion Construction Photographs: Take sufficient color photographs after date of
Substantial Completion for submission as Project Record Documents. Engineer will direct
photographer for desired vantage points.
1.

Do not include date stamp.

PHOTOGRAPHIC DOCUMENTATION
Volume 2

01322 Page 3 of 4
May 2012

Saraya Aqaba
J.

Specifications

Additional Photographs: Engineer may issue requests for additional photographs, in addition to
periodic photographs specified. Additional photographs will not be paid for.
1.
2.
3.

Three days' notice will be given, where feasible.


In emergency situations, take additional photographs within 24 hours of request.
Circumstances that could require additional photographs include, but are not limited to, the
following:
a.
b.
c.
d.
e.
f.

K.

Special events planned at Project site.


Immediate follow-up when on-site events result in construction damage or losses.
Photographs to be taken at fabrication locations away from Project site. These
photographs are not subject to unit prices or unit-cost allowances.
Substantial Completion of a major phase or component of the Work.
Extra record photographs at time of final acceptance.
Contractor's request for special publicity photographs.

Web Based Cameras: The Contractor shall install web cameras on site and the recording shall be
continuous 24 hours a day. Records shall be filed on a weekly basis. All digital photos shall be on
CDs and properly archived, documented and submitted to the Engineer on a monthly basis.

END OF SECTION 01322

PHOTOGRAPHIC DOCUMENTATION
Volume 2

01322 Page 4 of 4
May 2012

Saraya Aqaba

Specifications

SECTION 01330 - SUBMITTAL PROCEDURES

PART 1 - GENERAL

1.1

RELATED DOCUMENTS
A.

1.2

Drawings and general provisions of the Contract, including General and Particular Conditions and
other Division 1 Specification Sections, apply to this Section.

SUMMARY
A.

This Section includes administrative and procedural requirements for submitting Shop Drawings,
Product Data, Samples, and other submittals.

B.

Related Sections include the following:


1.
Division 1 Section "Project Management and Coordination" for submitting and distributing
meeting and conference minutes and for submitting Coordination Drawings.
2.
Division 1 Section "Construction Progress Documentation" for submitting schedules and
reports, including Contractor's Construction Schedule and the Submittals Schedule.
3.
Division 1 Section "Photographic Documentation" for submitting construction photographs.
4.
Division 1 Section "Quality Requirements" for submitting test and inspection reports.
5.
Division 1 Section "Closeout Procedures" for submitting warranties.
6.
Division 1 Section "Project Record Documents" for submitting Record Drawings, Record
Specifications, and Record Product Data.
7.
Divisions 2 through 16 Sections for specific requirements for submittals in those Sections.

1.3

DEFINITIONS
A.

Action Submittals: Written and graphic information that requires Engineer's responsive action.

B.

Informational Submittals: Written information that does not require Engineer's responsive action.
Submittals may be rejected for not complying with requirements.

1.4

SUBMITTAL PROCEDURES
A.

General: Electronic copies of CAD Drawings of the Contract Drawings will be provided by Engineer
for Contractor's use in preparing submittals.

B.

Coordination: Coordinate preparation and processing of submittals with performance of construction


activities.
1.
2.

Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and
related activities that require sequential activity.
Coordinate transmittal of different types of submittals for related parts of the Work so
processing will not be delayed because of need to review submittals concurrently for
coordination.
a.

C.

Engineer reserves the right to withhold action on a submittal requiring coordination


with other submittals until related submittals are received.

Submittals Schedule: Comply with requirements in Division 1 Section "Construction Progress


Documentation" for list of submittals and time requirements for scheduled performance of related
construction activities.

SUBMITTAL PROCEDURES
Volume 2

01330 Page 1 of 8
May 2012

Saraya Aqaba
D.

Processing Time: Allow enough time for submittal review, including time for re-submittals, as
follows. Time for review shall commence on Engineer's receipt of submittal. No extension of the
Contract Time will be authorized because of failure to transmit submittals enough in advance of the
Work to permit processing, including re-submittals.
1.

2.
3.
4.
5.

E.

Specifications

Initial Review: Allow 14 days for initial review of each Civil & Structural submittals and 21
days for all other submittals. Allow additional time if coordination with subsequent submittals
is required. Engineer will advise Contractor when a submittal being processed must be
delayed for coordination.
Intermediate Review: If intermediate submittal is necessary, process it in same manner as
initial submittal.
Re-submittal Review: Allow 14 days for review of each re-submittal.
Sequential Review: Where sequential review of submittals by Engineers or Employer's
consultants, or other parties is indicated, allow 21 days for initial review of each submittal.
Concurrent Consultant Review: Where the Contract Documents indicate that submittals may
be transmitted simultaneously to Employer and to Employer's consultants, allow 21 days for
review of each submittal. Submittal will be returned to Engineer before being returned to
Contractor.

Identification: Place a permanent label or title block on each submittal for identification.
1.
2.
3.

Indicate name of firm or entity that prepared each submittal on label or title block.
Provide a space approximately 150 by 200 mm on label or beside title block to record
Contractor's review and approval markings and action taken by Engineer.
Include the following information on label for processing and recording action taken:
a.
b.
c.
d.
e.
f.
g.
h.
i.
j.
k.

Project name.
Date.
Name and address of Employer.
Name and address of Engineer.
Name and address of Designer.
Name and address of Contractor.
Name and address of any Sub-Contractor.
Name and address of subcontractor.
Name and address of supplier.
Name of manufacturer.
Submittal number or other unique identifier, including revision identifier.
1)

l.
m.
n.
o.
p.

Submittal number shall use Specification Section number followed by a decimal


point and then a sequential number (e.g., 06100.01). Re-submittals shall
include an alphabetic suffix after another decimal point (e.g., 06100.01.A).

Number and title of appropriate Specification Section.


Drawing number and detail references, as appropriate.
Location(s) where product is to be installed, as appropriate.
Other necessary identification.
The fit for purpose statement.

F.

Deviations: Highlight, encircle, or otherwise specifically identify deviations from the Contract
Documents on submittals.

G.

Additional Copies: Unless additional copies are required for final submittal, and unless
Engineer observes noncompliance with provisions in the Contract Documents, initial submittal may
serve as final submittal.
1.
2.

Submit two copies of submittal to concurrent reviewer in addition to specified number of


copies to Engineer.
Additional copies submitted for maintenance manuals will not be marked with action taken
and will be returned.

SUBMITTAL PROCEDURES
Volume 2

01330 Page 2 of 8
May 2012

Saraya Aqaba
H.

Specifications

Transmittal: Package each submittal individually and appropriately for transmittal and handling.
Transmit each submittal using a transmittal form. Engineer will discard submittals received from
sources other than Contractor.
1.
2.

Transmittal Form: Use form provided by Engineer.


Transmittal Form: Provide locations on form for the following information:
a.
b.
c.
d.
e.
f.
g.
h.
i.
j.
k.
l.
m.

3.

I.

Project name.
Date.
Destination (To:).
Source (From:).
Names of subcontractor, manufacturer, and supplier.
Category and type of submittal.
Submittal purpose and description.
Specification Section number and title.
Drawing number and detail references, as appropriate.
Transmittal number, numbered consecutively.
Submittal and transmittal distribution record.
Remarks.
Signature of transmitter.

On an attached separate sheet, prepared on Contractor's letterhead, record relevant


information, requests for data, revisions other than those requested by Engineer on previous
submittals, and deviations from requirements in the Contract Documents, including minor
variations and limitations. Include same label information as related submittal.

Re-submittals: Make re-submittals in same form and number of copies as initial submittal.
1.
2.
3.

Note date and content of previous submittal.


Note date and content of revision in label or title block and clearly indicate extent of revision.
Resubmit submittals until they are marked with approval notation from Engineer.

J.

Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers,


fabricators, installers, authorities having jurisdiction, and others as necessary for performance of
construction activities. Show distribution on transmittal forms.

K.

Use for Construction: Use only final submittals with mark indicating approval notation from
Engineer taken by Engineer.

PART 2 - PRODUCTS

2.1

ACTION SUBMITTALS
A.

General: Prepare and submit Action Submittals required by individual Specification Sections.
1.

B.

Submit electronic submittals directly to extranet specifically established for Project.

Product Data: Collect information into a single submittal for each element of construction and type
of product or equipment.
1.
2.
3.

If information must be specially prepared for submittal because standard printed data are not
suitable for use, submit as Shop Drawings, not as Product Data.
Mark each copy of each submittal to show which products and options are applicable.
Include the following information, as applicable:
a.
b.
c.
d.

Manufacturer's written recommendations.


Manufacturer's product specifications.
Manufacturer's installation instructions.
Standard color charts and cuts.

SUBMITTAL PROCEDURES
Volume 2

01330 Page 3 of 8
May 2012

Saraya Aqaba

Specifications
e.
f.
g.
h.
i.
j.
k.
l.
m.
n.
o.
p.

4.
5.

Manufacturer's catalog cuts: original publication or digitally-scanned electronic copy in


JPEG, or PDF format.
Roughing-in diagrams and templates.
Standard wiring diagrams showing factory-installed wiring.
Printed performance curves.
Operational range diagrams.
Mill reports.
Standard product operation and maintenance manuals.
Compliance with specified referenced standards.
Compliance with recognized trade association standards.
Testing by recognized testing agency.
Application of testing agency labels and seals.
Notation of coordination requirements.

Submit Product Data before or concurrent with Samples.


Number of Copies: Submit six copies of Product Data, unless otherwise indicated. Engineer
will return two copies. Mark up and retain one returned copy as a Project Record Document.

C.

Construction Drawings. The Construction and all other Drawings to generally follow the format
described below for Shop Drawings. The Construction and all other Drawings shall be produced in
time to meet the construction program and allow for a full approvals process.

D.

Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop
Drawings on reproductions of the Contract Documents or standard printed data, unless submittal of
Engineer's CAD Drawings are otherwise permitted.
1.

Preparation: Fully illustrate requirements in the Contract Documents. Include the following
information, as applicable:
a.
b.
c.
d.
e.
f.
g.
h.
i.
j.
k.
l.
m.
n.
o.

2.
3.

E.

Dimensions; in SI units unless otherwise indicated or directed.


Identification of products.
Fabrication and installation drawings.
Roughing-in and setting diagrams.
Wiring diagrams showing field-installed wiring, including power, signal, and control
wiring.
Shopwork manufacturing instructions.
Templates and patterns.
Schedules.
Design calculations.
Design mix formulas.
Compliance with specified standards.
Notation of coordination requirements.
Notation of dimensions established by field measurement.
Relationship to adjoining construction clearly indicated.
Seal and signature of professional Engineer if specified.

Sheet Size: Except for templates, patterns, and similar full-size drawings, submit Shop
Drawings on sheets at least 215 by 280 mm but no larger than 750 by 1000 mm.
Number of Copies: Submit six (bond) copies of each submittal. Engineer will return two
copies. Mark up and retain one returned copy as a Project Record Document.

Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these
characteristics with other elements and for a comparison of these characteristics between submittal
and actual component as delivered and installed.
1.
2.

Transmit Samples that contain multiple, related components such as accessories together in
one submittal package.
Identification: Attach label on unexposed side of Samples that includes the following:
a.
b.

Generic description of Sample.


Product name and name of manufacturer.

SUBMITTAL PROCEDURES
Volume 2

01330 Page 4 of 8
May 2012

Saraya Aqaba

Specifications
c.
d.

3.

Disposition: Maintain sets of approved Samples at Project site, available for quality-control
comparisons throughout the course of construction activity. Sample sets may be used to
determine final acceptance of construction associated with each set.
a.

b.

4.

Samples that may be incorporated into the Work are indicated in individual
Specification Sections. Such Samples must be in an undamaged condition at time of
use.
Samples not incorporated into the Work, or otherwise designated as Employer's
property, are the property of Contractor.

Samples for Initial Selection: Submit manufacturer's color charts consisting of units or
sections of units showing the full range of colors, textures, and patterns available.
a.

5.

Sample source.
Number and title of appropriate Specification Section.

Number of Samples: Submit one full set of available choices where color, pattern,
texture, or similar characteristics are required to be selected from manufacturer's
product line. Engineer will return submittal with options selected.

Samples for Verification: Submit full-size units or Samples of size indicated, prepared from
same material to be used for the Work, cured and finished in manner specified, and physically
identical with material or product proposed for use, and that show full range of color and
texture variations expected. Samples include, but are not limited to, the following: partial
sections of manufactured or fabricated components; small cuts or containers of materials;
complete units of repetitively used materials; swatches showing color, texture, and pattern;
color range sets; and components used for independent testing and inspection.
a.

Number of Samples: Submit three sets of Samples. Engineer will retain two Sample
sets; remainder will be returned. Mark up and retain one returned Sample set as a
Project Record Sample.
1)

2)

F.

Submit a single Sample where assembly details, workmanship, fabrication


techniques, connections, operation, and other similar characteristics are to be
demonstrated.
If variation in color, pattern, texture, or other characteristic is inherent in
material or product represented by a Sample, submit at least three sets of paired
units that show approximate limits of variations.

Product Schedule or List: As required in individual Specification Sections, prepare a written


summary indicating types of products required for the Work and their intended location. Include the
following information in tabular form:
1.
2.
3.
4.

Type of product. Include unique identifier for each product.


Number and name of space.
Location within space.
Number of Copies: Submit six copies of product schedule or list, unless otherwise indicated.
Engineer will return two copies.
a.

Mark up and retain one returned copy as a Project Record Document.

G.

Contractor's Construction Schedule: Comply with requirements specified in Division 1 Section


"Construction Progress Documentation" for Engineer's action.

H.

Submittals Schedule: Comply with requirements specified in Division 1 Section "Construction


Progress Documentation."

I.

Subcontract List: Prepare a written summary identifying individuals or firms proposed for each
portion of the Work, including those who are to furnish products or equipment fabricated to a special
design. Use form provided by Engineer. Include the following information in tabular form:

SUBMITTAL PROCEDURES
Volume 2

01330 Page 5 of 8
May 2012

Saraya Aqaba
1.
2.
3.
4.

Specifications
Name, address, and telephone number of entity performing subcontract or supplying products.
Number and title of related Specification Section(s) covered by subcontract.
Drawing number and detail references, as appropriate, covered by subcontract.
Number of Copies: Submit six copies of subcontractor list, unless otherwise indicated.
Engineer will return two copies.
a.

2.2

Mark up and retain one returned copy as a Project Record Document.

INFORMATIONAL SUBMITTALS
A.

General: Prepare and submit Informational Submittals required by other Specification Sections.
1.
2.

3.

Number of Copies: Submit four copies of each submittal, unless otherwise indicated.
Engineer will not return copies.
Certificates and Certifications: Provide a notarized statement that includes signature of entity
responsible for preparing certification. Certificates and certifications shall be signed by an
officer or other individual authorized to sign documents on behalf of that entity.
Test and Inspection Reports: Comply with requirements specified in Division 1 Section
"Quality Requirements."

B.

Contractor's Construction Schedule: Comply with requirements specified in Division 1 Section


"Construction Progress Documentation."

C.

Qualification Data: Prepare written information that demonstrates capabilities and experience of firm
or person. Include lists of completed projects with project names and addresses, names and addresses
of Employer, Engineer and Contractors, and other information specified.

D.

Welding Certificates: Prepare written certification that welding procedures and personnel comply
with requirements in the Contract Documents. Submit record of Welding Procedure Specification
(WPS) and Procedure Qualification Record (PQR) on AWS forms. Include names of firms and
personnel certified.

E.

Installer Certificates: Prepare written statements on manufacturer's letterhead certifying that Installer
complies with requirements in the Contract Documents and, where required, is authorized by
manufacturer for this specific Project.

F.

Manufacturer Certificates: Prepare written statements on manufacturer's letterhead certifying that


manufacturer complies with requirements in the Contract Documents. Include evidence of
manufacturing experience where required.

G.

Product Certificates: Prepare written statements on manufacturer's letterhead certifying that product
complies with requirements in the Contract Documents.

H.

Material Certificates: Prepare written statements on manufacturer's letterhead certifying that material
complies with requirements in the Contract Documents.

I.

Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency's
standard form, indicating and interpreting test results of material for compliance with requirements in
the Contract Documents.

J.

Product Test Reports: Prepare written reports indicating current product produced by manufacturer
complies with requirements in the Contract Documents. Base reports on evaluation of tests
performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests
performed by a qualified testing agency.

K.

Research/Evaluation Reports: Prepare written evidence, from a model code organization acceptable
to authorities having jurisdiction, that product complies with building code in effect for Project.
Include the following information:
1.

Name of evaluation organization.

SUBMITTAL PROCEDURES
Volume 2

01330 Page 6 of 8
May 2012

Saraya Aqaba
2.
3.
4.
5.
6.
7.

Specifications
Date of evaluation.
Time period when report is in effect.
Product and manufacturers' names.
Description of product.
Test procedures and results.
Limitations of use.

L.

Schedule of Tests and Inspections:


"Quality Requirements."

M.

Preconstruction Test Reports: Prepare reports written by a qualified testing agency, on testing
agency's standard form, indicating and interpreting results of tests performed before installation of
product, for compliance with performance requirements in the Contract Documents.

N.

Compatibility Test Reports: Prepare reports written by a qualified testing agency, on testing agency's
standard form, indicating and interpreting results of compatibility tests performed before installation
of product. Include written recommendations for primers and substrate preparation needed for
adhesion.

O.

Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard
form, indicating and interpreting results of field tests performed either during installation of product
or after product is installed in its final location, for compliance with requirements in the Contract
Documents.

P.

Design Data: Prepare written and graphic information, including, but not limited to, performance and
design criteria, list of applicable codes and regulations, and calculations. Include list of assumptions
and other performance and design criteria and a summary of loads. Include load diagrams if
applicable. Provide name and version of software, if any, used for calculations. Include page
numbers.

Q.

Manufacturer's Instructions: Prepare written or published information that documents manufacturer's


recommendations, guidelines, and procedures for installing a product. Include name of product and
name, address, and telephone number of manufacturer. Include the following, as applicable:
1.
2.
3.
4.
5.
6.

R.

Comply with requirements specified in Division 1 Section

Preparation of substrates.
Required substrate tolerances.
Sequence of installation or erection.
Required installation tolerances.
Required adjustments.
Recommendations for cleaning and protection.

Manufacturer's Field Reports: Prepare written information documenting factory-authorized service


representative's tests and inspections. Include the following, as applicable:
1.
2.
3.
4.
5.
6.
7.

Name, address, and telephone number of factory-authorized service representative making


report.
Statement on condition of substrates and their acceptability for installation of product.
Statement that products at Project site comply with requirements.
Summary of installation procedures being followed, whether they comply with requirements
and, if not, what corrective action was taken.
Results of operational and other tests and a statement of whether observed performance
complies with requirements.
Statement whether conditions, products, and installation will affect warranty.
Other required items indicated in individual Specification Sections.

S.

Insurance Certificates and Bonds: Prepare written information indicating current status of insurance
or bonding coverage. Include name of entity covered by insurance or bond, limits of coverage,
amounts of deductibles, if any, and term of the coverage.

T.

Construction Photographs: Comply with requirements specified in Division 1 Section "Photographic


Documentation."

SUBMITTAL PROCEDURES
Volume 2

01330 Page 7 of 8
May 2012

Saraya Aqaba
U.

Specifications

Material Safety Data Sheets (MSDSs): Submit information directly to Engineer; do not submit to
Engineer, except as required in "Action Submittals" Article.
1.

Engineer will not review submittals that include MSDSs and will return the entire submittal
for re-submittal.

PART 3 - EXECUTION

3.1

CONTRACTOR'S REVIEW
A.

Review each submittal and check for coordination with other Work of the Contract and for
compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval
stamp before submitting to Engineer.

B.

Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and
location, submittal number, Specification Section title and number, name of reviewer, date of
Contractor's approval, and statement certifying that submittal has been reviewed, checked, and
approved for compliance with the Contract Documents.

3.2

ENGINEER'S / ACTION
A.

General: Engineer will not review submittals that do not bear Contractor's approval stamp and will
return them without action.

B.

Action Submittals: Engineer will review each submittal, make marks to indicate corrections or
modifications required, and return it. Engineer will stamp each submittal with an action stamp and
will mark stamp appropriately to indicate action taken.

C.

Informational Submittals: Engineer will review each submittal and will not return it, or will return it
if it does not comply with requirements. Engineer will forward each submittal to appropriate party.

D.

Partial submittals are not acceptable, will be considered nonresponsive, and will be returned without
review.

E.

Submittals not required by the Contract Documents may not be reviewed and may be discarded.

END OF SECTION 01330

SUBMITTAL PROCEDURES
Volume 2

01330 Page 8 of 8
May 2012

Saraya Aqaba

Specifications

SECTION 01400 - QUALITY REQUIREMENTS

PART 1 - GENERAL

1.1

RELATED DOCUMENTS
A.

1.2

Drawings and general provisions of the Contract, including General and Particular Conditions and
other Division 1 Specification Sections, apply to this Section.

SUMMARY
A.

This Section includes administrative and procedural requirements for quality assurance and quality
control.

B.

Testing and inspecting services are required to verify compliance with requirements specified or
indicated. These services do not relieve Contractor of responsibility for compliance with the Contract
Document requirements.
1.

2.

3.

C.

1.3

Specific quality-assurance and -control requirements for individual construction activities are
specified in the Sections that specify those activities. Requirements in those Sections may
also cover production of standard products.
Specified tests, inspections, and related actions do not limit Contractor's other qualityassurance and -control procedures that facilitate compliance with the Contract Document
requirements.
Requirements for Contractor to provide quality-assurance and -control services required by
Engineer, or authorities having jurisdiction are not limited by provisions of this Section.

Related Sections include the following:


1.
Division 1 Section "Construction Progress Documentation" for developing a schedule of
required tests and inspections.
2.
Divisions 2 through 16 Sections for specific test and inspection requirements.

DEFINITIONS
A.

Quality-Assurance Services: Activities, actions, and procedures performed before and during
execution of the Work to guard against defects and deficiencies and substantiate that proposed
construction will comply with requirements.

B.

Quality-Control Services: Tests, inspections, procedures, and related actions during and after
execution of the Work to evaluate that actual products incorporated into the Work and completed
construction comply with requirements. Services do not include contract enforcement activities
performed by Engineer.

C.

Mockups: Full-size, physical assemblies that are constructed on-site. Mockups are used to verify
selections made under sample submittals, to demonstrate aesthetic effects and, where indicated,
qualities of materials and execution, and to review construction, coordination, testing, or operation;
they are not Samples. Approved mockups establish the standard by which the Work will be judged.

D.

Laboratory Mockups: Full-size, physical assemblies that are constructed at testing facility to verify
performance characteristics.

E.

Preconstruction Testing: Tests and inspections that are performed specifically for the Project before
products and materials are incorporated into the Work to verify performance or compliance with
specified criteria.

QUALITY REQUIREMENTS
Volume 2

01400 Page 1 of 7
May 2012

Saraya Aqaba

Specifications

F.

Product Testing: Tests and inspections that are performed by a testing agency qualified to conduct
product testing and acceptable to authorities having jurisdiction, to establish product performance and
compliance with industry standards.

G.

Source Quality-Control Testing: Tests and inspections that are performed at the source, i.e., plant,
mill, factory, or shop.

H.

Field Quality-Control Testing: Tests and inspections that are performed on-site for installation of the
Work and for completed Work.

I.

Testing Agency: An entity engaged to perform specific tests, inspections, or both. Testing laboratory
shall mean the same as testing agency.

J.

Installer/Applicator/Erector: Contractor or another entity engaged by Contractor as an employee,


Subcontractor, or Sub-subcontractor, to perform a particular construction operation, including
installation, erection, application, and similar operations.
1.

K.

1.4

Using a term such as "carpentry" does not imply that certain construction activities must be
performed by accredited or unionized individuals of a corresponding generic name, such as
"carpenter." It also does not imply that requirements specified apply exclusively to trades
people of the corresponding generic name.

Experienced: When used with an entity, "experienced" means having successfully completed a
minimum of five previous projects similar in size and scope to this Project; being familiar with
special requirements indicated; and having complied with requirements of authorities having
jurisdiction.

CONFLICTING REQUIREMENTS
A.

General: If compliance with two or more standards is specified and the standards establish different
or conflicting requirements for minimum quantities or quality levels, comply with the most stringent
requirement. Refer uncertainties and requirements that are different, but apparently equal, to Engineer
for a decision before proceeding.

B.

Minimum Quantity or Quality Levels: The quantity or quality level shown or specified shall be the
minimum provided or performed. The actual installation may comply exactly with the minimum
quantity or quality specified, or it may exceed the minimum within reasonable limits. To comply with
these requirements, indicated numeric values are minimum or maximum, as appropriate, for the
context of requirements. Refer uncertainties to Engineer for a decision before proceeding.

1.5

SUBMITTALS
A.

Qualification Data: For testing agencies specified in "Quality Assurance" Article to demonstrate their
capabilities and experience. Include proof of qualifications in the form of a recent report on the
inspection of the testing agency by a recognized authority.

B.

Schedule of Tests and Inspections: Prepare in tabular form and include the following:
1.
2.
3.
4.
5.
6.
7.
8.
9.

C.

Specification Section number and title.


Description of test and inspection.
Identification of applicable standards.
Identification of test and inspection methods.
Number of tests and inspections required.
Time schedule or time span for tests and inspections.
Entity responsible for performing tests and inspections.
Requirements for obtaining samples.
Unique characteristics of each quality-control service.

Reports: Prepare and submit certified written reports that include the following:

QUALITY REQUIREMENTS
Volume 2

01400 Page 2 of 7
May 2012

Saraya Aqaba

Specifications

1.
2.
3.
4.
5.
6.
7.
8.
9.
10.

Date of issue.
Project title and number.
Name, address, and telephone number of testing agency.
Dates and locations of samples and tests or inspections.
Names of individuals making tests and inspections.
Description of the Work and test and inspection method.
Identification of product and Specification Section.
Complete test or inspection data.
Test and inspection results and an interpretation of test results.
Record of temperature and weather conditions at time of sample taking and testing and
inspecting.
Comments or professional opinion on whether tested or inspected Work complies with the
Contract Document requirements.
Name and signature of laboratory inspector.
Recommendations on retesting and re-inspecting.

11.
12.
13.
D.

1.6

Permits, Licenses, and Certificates: For Engineer's records, submit copies of permits, licenses,
certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee
payments, judgments, correspondence, records, and similar documents, established for compliance
with standards and regulations bearing on performance of the Work.

QUALITY ASSURANCE
A.

General: Qualifications paragraphs in this Article establish the minimum qualification levels
required; individual Specification Sections specify additional requirements.

B.

Installer Qualifications: A firm or individual experienced in installing, erecting, or assembling work


similar in material, design, and extent to that indicated for this Project, whose work has resulted in
construction with a record of successful in-service performance.

C.

Manufacturer Qualifications: A firm experienced in manufacturing products or systems similar to


those indicated for this Project and with a record of successful in-service performance, as well as
sufficient production capacity to produce required units.

D.

Fabricator Qualifications: A firm experienced in producing products similar to those indicated for this
Project and with a record of successful in-service performance, as well as sufficient production
capacity to produce required units.

E.

Professional Engineer Qualifications: A professional engineer who is legally qualified to practice in


jurisdiction where Project is located and who is experienced in providing engineering services of the
kind indicated. Engineering services are defined as those performed for installations of the system,
assembly, or product that are similar to those indicated for this Project in material, design, and extent.

F.

Specialists: Certain sections of the Specifications require that specific construction activities shall be
performed by entities who are recognized experts in those operations. Specialists shall satisfy
qualification requirements indicated and shall be engaged for the activities indicated.
1.

Requirement for specialists shall not supersede building codes and regulations governing the
Work.

G.

Testing Agency Qualifications: An independent agency with the experience and capability to conduct
testing and inspecting indicated, as documented according to ASTM E 548; and with additional
qualifications specified in individual Sections; and where required by authorities having jurisdiction,
that is acceptable to authorities.

H.

Factory-Authorized Service Representative Qualifications: An authorized representative of


manufacturer who is trained and approved by manufacturer to inspect installation of manufacturer's
products that are similar in material, design, and extent to those indicated for this Project.

QUALITY REQUIREMENTS
Volume 2

01400 Page 3 of 7
May 2012

Saraya Aqaba
I.

Specifications

Preconstruction Testing: Where testing agency is indicated to perform preconstruction testing for
compliance with specified requirements for performance and test methods, comply with the
following:
1.

Contractor responsibilities include the following:


a.
b.
c.

d.
e.
f.

2.

J.

Testing Agency Responsibilities: Submit a certified written report of each test, inspection, and
similar quality-assurance service to Engineer with copy to Contractor. Interpret tests and
inspections and state in each report whether tested and inspected work complies with or
deviates from the Contract Documents.

Mockups: Before installing portions of the Work requiring mockups, build mockups for each form of
construction and finish required to comply with the following requirements, using materials indicated
for the completed Work:
1.
2.
3.
4.

Build mockups in location and of size indicated or, if not indicated, as directed by Engineer.
Notify Engineer seven days in advance of dates and times when mockups will be constructed.
Demonstrate the proposed range of aesthetic effects and workmanship.
Obtain Engineers, Employer's, and Operators approval of mockups before starting work,
fabrication, or construction.
a.

5.
6.
7.

K.

1.7

Provide test specimens representative of proposed products and construction.


Submit specimens in a timely manner with sufficient time for testing and analyzing
results to prevent delaying the Work.
Provide sizes and configurations of test assemblies, mockups, and laboratory mockups
to adequately demonstrate capability of products to comply with performance
requirements.
Build site-assembled test assemblies and mockups using installers who will perform
same tasks for Project.
Build laboratory mockups at testing facility using personnel, products, and methods of
construction indicated for the completed Work.
When testing is complete, remove test specimens, assemblies, mockups, and laboratory
mockups; do not reuse products on Project.

Allow 21 days for initial review and each re-review of each mockup.

Maintain mockups during construction in an undisturbed condition as a standard for judging


the completed Work.
Demolish and remove mockups when directed, unless otherwise indicated.
The Contractor shall provide on Site for approval full-size physical assemblies, which include
a fully assembled Room Mockup for each Hotel, Apartment Mockup for each type of
Residential units, and other significant project components as may be determined by the
Employer, the Engineer, and the Operators. Such mockups shall be constructed in accordance
with the Contract to show construction details, finished appearance, FF&E , SOE and/or
performance.

Laboratory Mockups: Comply with requirements of preconstruction testing and those specified in
individual Sections in Divisions 2 through 16.

QUALITY CONTROL
A.

Engineer or Employer Responsibilities: Where quality-control services are indicated as Engineers or


Employer's responsibility, a qualified testing agency will be engaged Engineer/Employer to perform
these services.
1.

2.

Engineer will furnish Contractor with names, addresses, and telephone numbers of testing
agencies engaged and a description of types of testing and inspecting they are engaged to
perform.
Payment for these services will be made for testing and inspecting by the Contractor.

QUALITY REQUIREMENTS
Volume 2

01400 Page 4 of 7
May 2012

Saraya Aqaba
3.

B.

Specifications
Costs for retesting and re-inspecting construction that replaces or is necessitated by work that
failed to comply with the Contract Documents will be charged to Contractor.

Tests and inspections not explicitly assigned to Engineer or Employer are Contractor's responsibility.
Unless otherwise indicated, provide quality-control services specified and those required by
authorities having jurisdiction. Perform quality-control services required of Contractor by authorities
having jurisdiction, whether specified or not.
1.

Where services are indicated as Contractor's responsibility, engage a qualified testing agency
to perform these quality-control services.
a.

2.
3.
4.
5.

Contractor shall not employ same entity engaged by Engineer/Employer, unless agreed
to in writing by Engineer/Employer.

Notify testing agencies at least 48 hours in advance of time when Work that requires testing or
inspecting will be performed.
Where quality-control services are indicated as Contractor's responsibility, submit a certified
written report, in duplicate, of each quality-control service.
Testing and inspecting requested by Contractor and not required by the Contract Documents
are Contractor's responsibility.
Submit additional copies of each written report directly to authorities having jurisdiction,
when they so direct.

C.

Manufacturer's Field Services: Where indicated, engage a factory-authorized service representative to


inspect field-assembled components and equipment installation, including service connections.
Report results in writing as specified in Division 1 Section "Submittal Procedures."

D.

Retesting/Re-inspecting: Regardless of whether original tests or inspections were Contractor's


responsibility, provide quality-control services, including retesting and re-inspecting, for construction
that replaced Work that failed to comply with the Contract Documents.

E.

Testing Agency Responsibilities: Cooperate with Engineer and Contractor in performance of duties.
Provide qualified personnel to perform required tests and inspections.
1.
2.
3.
4.
5.
6.

F.

Notify Engineer and Contractor promptly of irregularities or deficiencies observed in the


Work during performance of its services.
Determine the location from which test samples will be taken and in which in-situ tests are
conducted.
Conduct and interpret tests and inspections and state in each report whether tested and
inspected work complies with or deviates from requirements.
Submit a certified written report, in duplicate, of each test, inspection, and similar qualitycontrol service through Contractor.
Do not release, revoke, alter, or increase the Contract Document requirements or approve or
accept any portion of the Work.
Do not perform any duties of Contractor.

Associated Services: Cooperate with agencies performing required tests, inspections, and similar
quality-control services, and provide reasonable auxiliary services as requested. Notify agency
sufficiently in advance of operations to permit assignment of personnel. Provide the following:
1.
2.
3.
4.
5.
6.
7.

Access to the Work.


Incidental labor and facilities necessary to facilitate tests and inspections.
Adequate quantities of representative samples of materials that require testing and inspecting.
Assist agency in obtaining samples.
Facilities for storage and field curing of test samples.
Delivery of samples to testing agencies.
Preliminary design mix proposed for use for material mixes that require control by testing
agency.
Security and protection for samples and for testing and inspecting equipment at Project site.

QUALITY REQUIREMENTS
Volume 2

01400 Page 5 of 7
May 2012

Saraya Aqaba
G.

Coordination: Coordinate sequence of activities to accommodate required quality-assurance and control services with a minimum of delay and to avoid necessity of removing and replacing
construction to accommodate testing and inspecting.
1.

H.

Schedule times for tests, inspections, obtaining samples, and similar activities.

Schedule of Tests and Inspections: Prepare a schedule of tests, inspections, and similar qualitycontrol services required by the Contract Documents. Submit schedule within 21 days of date
established for commencement of the Work.
1.

1.8

Specifications

Distribution: Distribute schedule to Engineer, testing agencies, and each party involved in
performance of portions of the Work where tests and inspections are required.

SPECIAL TESTS AND INSPECTIONS


A.

Special Tests and Inspections: Engineer/Employer will engage a qualified testing agency to conduct
special tests and inspections required by authorities having jurisdiction as the responsibility of
Employer, and as follows:
1.

2.
3.

B.

Engineer will furnish Contractor with names, addresses, and telephone numbers of testing
agencies engaged and a description of types of testing and inspecting they are engaged to
perform.
Payment for these services will be made for testing and inspecting by the Contractor.
Costs for retesting and re-inspecting construction that replaces or is necessitated by work that
failed to comply with the Contract Documents will be charged to Contractor.

Special Tests and Inspections: Conducted by a qualified testing agency as required by authorities
having jurisdiction, as indicated in individual Specification Sections, and as follows:
1.
2.
3.
4.
5.
6.

Verifying that manufacturer maintains detailed fabrication and quality-control procedures and
reviewing the completeness and adequacy of those procedures to perform the Work.
Notifying Engineer and Contractor promptly of irregularities and deficiencies observed in the
Work during performance of its services.
Submitting a certified written report of each test, inspection, and similar quality-control
service to Engineer with copy to Contractor and to authorities having jurisdiction.
Submitting a final report of special tests and inspections at Substantial Completion, this
includes a list of unresolved deficiencies.
Interpreting tests and inspections and stating in each report whether tested and inspected work
complies with or deviates from the Contract Documents.
Retesting and re-inspecting corrected work.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1

TEST AND INSPECTION LOG


A.

Prepare a record of tests and inspections. Include the following:


1.
2.
3.
4.

B.

Date test or inspection was conducted.


Description of the Work tested or inspected.
Date test or inspection results were transmitted to Engineer.
Identification of testing agency or special inspector conducting test or inspection.

Maintain log at Project site. Post changes and modifications as they occur. Provide access to test and
inspection log for Engineer's reference during normal working hours.

QUALITY REQUIREMENTS
Volume 2

01400 Page 6 of 7
May 2012

Saraya Aqaba
3.2

Specifications

REPAIR AND PROTECTION


A.

General: On completion of testing, inspecting, sample taking, and similar services, repair damaged
construction and restore substrates and finishes.
1.

Provide materials and comply with installation requirements specified in other Specification
Sections. Restore patched areas and extend restoration into adjoining areas with durable seams
that are as invisible as possible.

B.

Protect construction exposed by or for quality-control service activities.

C.

Repair and protection are Contractor's responsibility, regardless of the assignment of responsibility
for quality-control services.

END OF SECTION 01400

QUALITY REQUIREMENTS
Volume 2

01400 Page 7 of 7
May 2012

Saraya Aqaba

Specifications

SECTION 01420 - REFERENCES

PART 1 - GENERAL

1.1

RELATED DOCUMENTS
A.

1.2

Drawings and general provisions of the Contract, including General and Particular Conditions and
other Division 1 Specification Sections, apply to this Section.

DEFINITIONS
A.

General: Basic Contract definitions are included in the Conditions of the Contract.

B.

"Approved": When used to convey Engineer's action on Contractor's submittals, applications, and
requests, "approved" is limited to Engineer's duties and responsibilities as stated in the Conditions of
the Contract.

C.

"Directed": A command or instruction by Engineer. Other terms including "requested," "authorized,"


"selected," "approved," "required," and "permitted" have the same meaning as "directed."

D.

"Indicated": Requirements expressed by graphic representations or in written form on Drawings, in


Specifications, and in other Contract Documents. Other terms including "shown," "noted,"
"scheduled," and "specified" have the same meaning as "indicated."

E.

"Regulations": Laws, ordinances, statutes, and lawful orders issued by authorities having jurisdiction,
and rules, conventions, and agreements within the construction industry that control performance of
the Work.

F.

"Furnish": Supply and deliver to Project site, ready for unloading, unpacking, assembly, installation,
and similar operations.

G.

"Install": Operations at Project site including unloading, temporarily storing, unpacking, assembling,
erecting, placing, anchoring, applying, working to dimension, finishing, curing, protecting, cleaning,
and similar operations.

H.

"Provide": Furnish and install, complete and ready for the intended use.

I.

"Project Site": Space available for performing construction activities. The extent of Project site is
shown on Drawings and may or may not be identical with the description of the land on which
Project is to be built.

1.3

INDUSTRY STANDARDS
A.

Applicability of Standards: Unless the Contract Documents include more stringent requirements,
applicable construction industry standards have the same force and effect as if bound or copied
directly into the Contract Documents to the extent referenced. Such standards are made a part of the
Contract Documents by reference.

B.

Publication Dates: Comply with standards in effect as of date of the Contract Documents, unless
otherwise indicated.

C.

Copies of Standards: Each entity engaged in construction on Project should be familiar with industry
standards applicable to its construction activity. Copies of applicable standards are not bound with the
Contract Documents.

REFERENCE
Volume 2

01420 Page 1 of 2
May 2012

Saraya Aqaba
1.

Specifications
Where copies of standards are needed to perform a required construction activity, obtain
copies directly from publication source.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01420

REFERENCE
Volume 2

01420 Page 2 of 2
May 2012

Saraya Aqaba

Specifications

SECTION 01500 - TEMPORARY FACILITIES AND CONTROLS

PART 1 - GENERAL

1.1

RELATED DOCUMENTS
A.

1.2

SUMMARY
A.

This Section includes requirements for temporary utilities, support facilities, and security and
protection facilities.

B.

Related Sections include the following:


1.
Division 1 Section "Submittal Procedures" for procedures for submitting copies of
implementation and termination schedule and utility reports.
2.
Division 1 Section "Execution Requirements" for progress cleaning requirements.

1.3

USE CHARGES
A.

General: Cost or use charges for temporary facilities shall be included in the Accepted Contract
Amount. Provide and maintain temporary services and facilities, including, but not limited to,
Employer, Engineer, Operators and all their appointed consultants and employees, occupants of
Project, testing agencies, and authorities having jurisdiction.

B.

Sewer Service: Pay sewer service use charges for sewer usage by all entities for construction
operations.

C.

Water Service:
operations.

D.

Electric Power Service: Pay electric power service use charges for electricity used by all entities for
construction operations.

E.

Telephone and internet Service: Pay all charges and bills for local and international telephone (and
mobiles) calls and internet used by all entities for construction operations.

1.4

Pay water service use charges for water used by all entities for construction

SUBMITTALS
A.

1.5

1.6

Drawings and general provisions of the Contract, including General and Particular Conditions and
other Division 1 Specification Sections, apply to this Section.

Site Plan: Show temporary facilities, utility hookups, staging areas, and parking areas for construction
personnel.

QUALITY ASSURANCE
A.

Electric Service: Comply with NECA, NEMA, and UL standards and regulations for temporary
electric service.

B.

Tests and Inspections: Arrange for authorities having jurisdiction to test and inspect each temporary
utility before use. Obtain required certifications and permits.

PROJECT CONDITIONS

TEMPORARY FACILITIES AND CONTROLS


Volume 2

01500 Page 1 of 11
May 2012

Saraya Aqaba
A.

Specifications

Temporary Use of Permanent Facilities: Installer of each permanent service shall assume
responsibility for operation, maintenance, and protection of each permanent service during its use as a
construction facility before Engineer's acceptance, regardless of previously assigned responsibilities.

PART 2 - PRODUCTS

2.1

TEMPORARY FACILITIES
A.

Field Offices shall be fully fitted out, equipped, and serviced for proper operations, inclusive of
furniture, equipment, consumables, etc.

B.

Contractors Field Office: Prefabricated or mobile units with serviceable finishes, temperature
controls, and foundations adequate for normal loading.
1.

Do not allow the Contractors employees or those of his Sub-Contractors to maintain any
temporary or permanent living quarters within the construction site.

C.

Existing Field Offices: Some Field Offices are existing on Site and on a rented land near the Site. The
Contractor shall buy from the Employer these offices for the Contractors use regardless of whether
the Contractor uses them. The amount of these offices shall be deducted in Bill No. 1 (General
Requirements) from the Tender Sum.. Employer will transfer the rents of the land near the Site to the
Contractor, and then the Contractor shall be responsible for its rental costs, and to adapt existing field
offices, expand and provide whatever field offices necessary to carry out the construction operations
on Site.

D.

Employers Field Offices, General: Construct a high quality reinforced concrete building on the
former Radisson SAS land Plot No. 594, with serviceable finishes, temperature controls, and
foundations adequate for normal loading. The field offices for the Employer representatives on Site
shall be fully furnished and equipped with a total built up area of 315 m2 (refer to layout in Volume 4
of the Contract Documents). Employers offices shall be ready for its intended use not later than 3
months from the commencement date. The work shall include but not limited to the following:
1.

Construction:
a.
b.
c.
d.
e.
f.
g.
h.
i.
j.

k.

l.

m.
n.

Earthworks
Reinforced concrete foundations, column and wall necks, and 20 cm thick solid slab.
External block walls comprising of a cavity block wall (15cm x5cm x10cm),with 5cm
thermal insulation.
Thermal and Moisture insulation
Internal and External Plaster work for walls.
Internal and External Paint for walls.
Anti-Slip Ceramic Tiles for floors.
Ceramic Tiles for bathroom and kitchen walls.
Gypsum Tiles for Ceilings.
Aluminum-framed glazed windows in thermally broken powder coated sections and
profile, sealed double glass comprising 6mm thick tempered toughened clear inner
pane / 12mm void / 6mm thick tempered toughened clear outer pane, hardware and all
necessary accessories (Color of Aluminum and glass to be approved by the Employer).
Flush wood doors, leaf thickness 45mm in semi-solid ,softwood core 60% formation
with 6mm thick MDF facing with, including solid wenge wood frame and ironmongery
and all necessary accessories for internal doors.
Double leaf Aluminum-framed glazed door in thermally broken powder coated
sections and profile, hermetically sealed double glass comprising 6mm thick tempered
toughened clear inner pane / 12mm void / 6mm thick tempered toughened clear outer
pane, hardware and all necessary accessories (Color of Aluminum and glass to be
approved by the Employer) for entrance door.
Toilet Accessories.
Kitchen units and cabinets(including kitchen equipment ( Refrigerator Micro-wave and
oven and SOEs).

TEMPORARY FACILITIES AND CONTROLS


Volume 2

01500 Page 2 of 11
May 2012

Saraya Aqaba

2.

Specifications

(315) m office comprising but not limited to:a.


b.
c.
d.
e.
f.
g.
h.
i.

One office for the General Manager.


One office for the Project Director.
4 Offices, each for one Person.
Meeting Room for 12 persons.
Reception Area with a model show room.
Work station for 6 persons.
Storage room.
1 Kitchen fully equipped.
4 Toilets for completely fitted.

3.

Furniture comprising desks, chairs, Meeting table, workstations,, filing cabinets, drawing
racks open shelves, and Pin Boards (Subject to the Employers approval).

4.

One Qualified Office Clerk

5.

Continuous supply of adequate stationary.

6.

Photocopying and 2 printer machines with automatic feeder A3/A4 reduce/enlarge, sorter,
multi-copy.

7.

Telephone and facsimile machine.

8.

12 No. full computers (Specifications and soft wares will be advise in due course).

9.

Maintenance service, spare parts, consumables such as toner, ink, paper, CDs, DVDs, etc...
and the running cost for the office equipment for the whole construction period.

10.

Adequate HVAC and lighting systems for each room

11.

All fenestration shall have Venetian blinds.

12.

Two separate external telephone lines with extension lines to all other office desk positions,
facsimile and computer internet. Each office shall be provided with two socket outlet power
points and adequate fluorescent lighting in addition to operable windows with blinds and fly
screens. All charges and local telephone and email bills shall be paid by the Contractor.

13.

Qualified Office Clerk.

14.

Provide and maintain all necessary and required services and utilities, including but not
necessarily limited to:
a.
b.
c.
d.
e.
f.
g.
h.
i.
j.
k.
l.
m.
n.
o.

Sewers and drainage.


Water service and distribution.
Sanitary facilities, including toilets, wash facilities, and drinking-water facilities and
fixtures.
Air-conditioner heating and cooling.
Ventilation.
Electric power service.
Lighting.
Telecommunications (voice, high speed internet, etc)
Fire-fighting appliances and extinguishers.
Janitorial services and facilities.
Security.
Insurance.
Access.
Office supplies.
Office equipment.

TEMPORARY FACILITIES AND CONTROLS


Volume 2

01500 Page 3 of 11
May 2012

Saraya Aqaba

Specifications
p.
q.

Computers.
Vehicles

Provide daily cleaning and full time attendance of the site office accommodation including providing
one tea boy to attend upon the requirements of the staff. The cost of cleaning materials and
consumable such as, paper towels, paper tissues, toilet rolls, cookery and cutlery, tea, coffee, sugar,
etc. shall be paid for by the Contractor. The services of the tea boy, the provision of consumables and
cleaning materials and the maintenance of the site office shall be extended to cover the construction
duration until completion. Consumables shall be supplied and delivered to the site at regular intervals
as directed by the Employer or his representatives.
The Employers offices shall become the Employers property at Substantial Completion subject to
the offices being in satisfactory condition.
E.

Vehicles for Employers Use: Deliver to the Employer within 7 days of the Commencement Date,
together with spare keys, registration papers, insurance certificate and other related documentation:
New; air-conditioned, automatic transmission motor vehicles as follows:
1.

(4) vehicles 44 (to be approved by the Employer).

2.

Arrange for and pay all charges and costs arising in connection with the delivery, maintenance
and running of vehicles, including but not limited to:
a.
b.
c.
d.

3.

Delivery charges, license fees, road taxes and certificates.


Fully comprehensive insurance cover for any driver at all times.
Regular service maintenance and repairs as necessary to keep the vehicles at all times
in good roadworthy condition.
Supply of fuel, lubricants, replacement parts and other consumables.

Provide an acceptable replacement vehicle during any period that a vehicle is unavailable for
any reason, including maintenance and/or repair.
Vehicle shall, unless otherwise indicated, be returned to the Contractor within one month after
the date of issue of the Taking-Over Certificate for the whole of the Work.

F.

Temporary car-port shade structure for 8 dedicated parking spaces adjacent to the Employers, Field
Offices, including temporary paved vehicular access, car-port hard standing and walkways.

G.

Engineers, Operators and Consultants Field Offices, General: Provide on Site a high quality
prefabricated units with serviceable finishes, temperature controls, and foundations adequate for
normal loading. Offices should be prefabricated, mobile units or job-built construction, with lockable
entrances, operable windows, serviceable finishes and robust secure fittings; insulated, weather tight,
heated and air conditioned. The field offices for the Engineers, Operators and Consultants
representatives on Site shall be fully furnished, serviced, and equipped to the approval of the
Engineer. Total Area for the offices mentioned below will be distributed on zones according to
Engineers requirements and will be provided according to the Engineers deployment schedule
which will be advised in due course by the Employer. Provide and maintain the following as a
minimum:
1.

(750) m Office comprising but not limited to:


a.
b.
c.
d.
e.
f.
g.
h.
i.
j.

10 offices for Managers


13 offices for 2 persons
6 offices for 3 persons
2 conference rooms for 14 persons
Reception areas
Secretarial offices
Multi-Purpose rooms
Store rooms
8 toilets completely fitted for
2 kitchens fully equipped

TEMPORARY FACILITIES AND CONTROLS


Volume 2

01500 Page 4 of 11
May 2012

Saraya Aqaba

Specifications

2.

3 full time drivers.

3.

2 Qualified Office Clerks.

4.

Furniture comprising desks, chairs, filing cabinets, drawing racks and open shelves.

5.

Continuous supply of adequate stationary.

6.

2 color photocopying, 4 color Laser printer, and 4 color Inkjet printer machines with
automatic feeder A3/A4 reduce/enlarge, sorter, multi-copy.

7.

1 color Plotters and 4 color scanning machines (A0).

8.

Telephone and facsimile machines.

9.

40 No. full computers (Specifications and softwares will be advised in due course).

10.

Maintenance service, spare parts, consumables such as toner, ink, paper, CDs, DVDs, etc...
and the running cost for the office equipment for the whole construction period.

11.

2 External telephone lines with extension lines to all other office desk positions, facsimile and
computer internet. Each office shall be provided with two socket outlet power points and
adequate fluorescent lighting in addition to operable windows with blinds and fly screens. All
charges and local telephone and email bills shall be paid by the Contractor.

12.

Provide and maintain all necessary and required services and utilities, including but not
necessarily limited to:
a.
b.
c.
d.
e.
f.
g.
h.
i.
j.
k.
l.
m.
n.
o.
p.
q.

Sewers and drainage.


Water service and distribution.
Sanitary facilities, including toilets, wash facilities, and drinking-water facilities and
fixtures.
Air-conditioner heating and cooling.
Ventilation.
Electric power service.
Lighting.
Telecommunications (voice, high speed internet, etc)
Fire-fighting appliances and extinguishers.
Janitorial services and facilities.
Security.
Insurance.
Access.
Office supplies.
Office equipment.
Computers.
Vehicles

Provide daily cleaning and full time attendance of the site office accommodation including providing
four tea boys to attend upon the requirements of the staff. The cost of cleaning materials and
consumable such as, paper towels, paper tissues, toilet rolls, cookery and cutlery, tea, coffee, sugar,
etc. shall be paid for by the Contractor. The services of the tea boy, the provision of consumables and
cleaning materials and the maintenance of the site office shall be extended to cover the construction
duration until completion. Consumables shall be supplied and delivered to the site at regular intervals
as directed by the Engineer, Operator and Consultant or their representatives.
H.

Vehicles for Engineers Use: to be delivered to the Engineer together with spare keys, registration
papers, insurance certificate and other related documentation: New; air-conditioned and automatic
transmission motor vehicles. Vehicles delivery shall be according to the Engineers deployment
schedule which will be advised in due course by the Employer. Vehicles to be delivered to the
Engineer are as follows:

TEMPORARY FACILITIES AND CONTROLS


Volume 2

01500 Page 5 of 11
May 2012

Saraya Aqaba

Specifications

1.

10 vehicles 44 (to be approved by the Employer).

2.

Arrange for and pay all charges and costs arising in connection with the delivery, maintenance
and running of vehicles, including but not limited to:
a.
b.
c.
d.

3.

Delivery charges, license fees, road taxes and certificates.


Fully comprehensive insurance cover for any driver at all times.
Regular service maintenance and repairs as necessary to keep the vehicles at all times
in good roadworthy condition.
Supply of fuel, lubricants, replacement parts and other consumables.

Provide an acceptable replacement vehicle during any period that a vehicle is unavailable for
any reason, including maintenance and/or repair.
Vehicle shall, unless otherwise indicated, be returned to the Contractor within one month after
the date of issue of the Taking-Over Certificate for the whole of the Work.

I.

Temporary car-port shade structure for 20 dedicated parking spaces adjacent to the Engineers,
Operators and Consultants Field Offices, including temporary paved vehicular access, car-port hard
standing and walkways.

J.

Storage and Fabrication Sheds: Provide sheds sized, furnished, and equipped to accommodate
materials and equipment for construction operations.
1.

K.

2.2

Store combustible materials apart from building.

Accessibility For Physically Disabled Persons: The Contractor shall provide temporary constructions
at the site as necessary to maintain access for physically disabled persons.

EQUIPMENT
A.

Fire Extinguishers: Portable, UL rated; with class and extinguishing agent as required by locations
and classes of fire exposures.

B.

HVAC Equipment: Provide vented, self-contained, HVAC equipment with individual space
thermostatic control for each room of the offices.

PART 3 - EXECUTION

3.1

INSTALLATION, GENERAL
A.

Locate facilities where they will serve Project adequately and result in minimum interference with
performance of the Work. Relocate and modify facilities as required by progress of the Work.

B.

Provide each facility ready for use when needed to avoid delay. Do not remove until facilities are no
longer needed or are replaced by authorized use of completed permanent facilities.

3.2

TEMPORARY UTILITY INSTALLATION


A.

General: Install temporary service or connect to existing service.


1.

B.

Arrange with utility company, Engineer, and existing users for time when service can be
interrupted, if necessary, to make connections for temporary services.

Sewers and Drainage: Provide temporary utilities to remove effluent lawfully.

TEMPORARY FACILITIES AND CONTROLS


Volume 2

01500 Page 6 of 11
May 2012

Saraya Aqaba
1.

Specifications
Connect temporary sewers to private system indicated as directed by authorities having
jurisdiction.

C.

Water Service: Install water service and distribution piping in sizes and pressures adequate for
construction.

D.

Permanent Water Service: If use of permanent water service facilities is permitted, service, clean and
maintain in a condition acceptable to the Engineer. At Taking-Over, restore these facilities to
condition existing before initial use.

E.

Sanitary Facilities: Provide temporary toilets, wash facilities, and drinking water for use of
construction personnel. Comply with authorities having jurisdiction for type, number, location,
operation, and maintenance of fixtures and facilities.

F.

Water fixtures: Comply with regulations and health codes, number, location, operation, and
maintenance of facilities and fixtures. Provide separate toilet facilities for male and female personnel.
Install where facilities will best serve Staff needs, including relocation whenever necessary.

G.

Permanent Sanitary Facilities: Temporary use of permanent toilets and wash facilities is not
permitted. Apply and strictly enforce non-use by all entities engaged in construction activities at
Project site.

H.

Temporary Site Toilets: Install self-contained toilet units. Shield toilets to ensure privacy.

I.

Wash facilities: Install wash facilities supplied with potable water at convenient locations for
personnel who handle materials that require wash up. Dispose of drainage properly. Supply cleaning
compounds appropriate for each type of material handled.

J.

Heating and Cooling: Provide temporary heating and cooling required by construction activities for
curing or drying of completed installations or for protecting installed construction from adverse
effects of low temperatures or high humidity. Select equipment from that specified that will not have
a harmful effect on completed installations or elements being installed. Maintain a minimum
temperature of 10 deg C in permanently enclosed portions of building for normal construction
activities, and 18 deg C for finishing activities and areas where finished Work has been installed.

K.

Ventilation and Humidity Control: Provide temporary ventilation required by construction activities
for curing or drying of completed installations or for protecting installed construction from adverse
effects of high humidity. Select equipment that will not have a harmful effect on completed
installations or elements being installed. Coordinate ventilation requirements to produce ambient
condition required and minimize energy consumption.

L.

Electric Power Service to the Site Offices: Review supply requirements, modify, alter, adapt and
supplement existing electric power service and distribution as necessary to provide adequate and
uninterrupted service, independent of other temporary facilities and construction operations to the
satisfaction of the Engineer.

M.

Electric Power Service: Provide weatherproof, grounded electric power service and distribution
system of appropriate and sufficient size, capacity, and power characteristics required for use during
construction, including necessary start-up, testing and commissioning of building operating systems
and equipment. Include meters, transformers, overload-protected disconnecting means automatic
ground-fault interrupters, and main distribution switchgear.
1.
2.
3.

N.

Install electric power service underground, unless overhead service must be used.
Install power distribution wiring overhead and rise vertically where least exposed damage.
If at any time, temporary electric power service is interrupted or inadequate for the Project
requirements, provide and operate back-up electric generators as necessary.

Permanent Electric Power Service: If use of permanent electric power service is permitted maintain
equipment in a condition acceptable to the Engineer. At Substantial Completion, restore equipment to
condition existing before initial use.

TEMPORARY FACILITIES AND CONTROLS


Volume 2

01500 Page 7 of 11
May 2012

Saraya Aqaba

Specifications

O.

Electric Distribution: Provide receptacle outlets adequate for connection of power tools and
equipment. Cords if single lengths will not reach areas where construction activities are in progress
do not exceed safe length-voltage ratio.

P.

Lighting: Provide temporary lighting with local switching that provides adequate illumination for
construction operations, observations, inspections, and traffic conditions.
1.
2.

Q.

Install and operate temporary lighting that fulfills security and protection requirements
without operating entire system.
Install lighting for Project identification sign.

Telephone Service: Provide temporary telephone service in common-use facilities for use by all
construction personnel. Install at least two telephone line(s) for each field office.
1.

Provide additional telephone lines for the following:


a.

2.

At each telephone, post a list of important telephone numbers.


a.
b.
c.
d.
e.
f.
g.
h.

3.

R.

Police and fire departments.


Ambulance service.
Employers office.
Engineers office.
Contractor's office.
Consultants' offices.
Operators' office.
Principal subcontractors' field and home offices.

Provide superintendent with cellular telephone or portable two-way radio for use when away
from field office.

Electronic Communication Service: Provide temporary electronic communication service, including


electronic mail, in common-use facilities.
1.

3.3

Provide a dedicated telephone line for each facsimile machine and computer in each
field office.

Provide DSL in primary field office.

SUPPORT FACILITIES INSTALLATION


A.

General: Comply with the following:


1.
2.

Provide incombustible construction for offices, shops, and sheds located within construction
area or within 9 m of building lines. Comply with NFPA 241.
Maintain support facilities until near Substantial Completion. Remove before Substantial
Completion. Personnel remaining after Substantial Completion will be permitted to use
permanent facilities, under conditions acceptable to Engineer.

B.

Site laboratory: Provide temporary site laboratory facility of sufficient size to accommodate,
conduct, perform and report on-site sampling and testing of materials as prescribed and specified in
various Specification Sections. Furnish and equip as necessary. Employ qualified laboratory
technicians familiar with specified industry standards and skilled in the testing of construction
materials and associated administrative procedures.

C.

Temporary Roads and Paved Areas: Construct and maintain temporary roads and paved areas
adequate for construction operations. Locate temporary roads and paved areas within construction
limits indicated on Drawings.
1.

Provide dust-control treatment that is nonpolluting and non-tracking. Reapply treatment as


required to minimize dust.

TEMPORARY FACILITIES AND CONTROLS


Volume 2

01500 Page 8 of 11
May 2012

Saraya Aqaba
D.

Specifications

Traffic Controls: Comply with requirements of authorities having jurisdiction.


1.
2.

Protect existing site improvements to remain including curbs, pavement, and utilities.
Maintain access for fire-fighting equipment and access to fire hydrants.

E.

Parking: Provide temporary parking areas for construction personnel.

F.

Dewatering Facilities and Drains: Comply with requirements of authorities having jurisdiction.
Maintain Project site, excavations, and construction free of water.
1.

G.

Dispose of rainwater in a lawful manner that will not result in flooding Project or adjoining
properties nor endanger permanent Work or temporary facilities.

Project Identification and Temporary Signs: Provide Project identification (To be coordinated with
and approved by Engineer in advance of installation) and other signs. Install signs where indicated to
inform public and individuals seeking entrance to Project. Unauthorized signs are not permitted.
1.

Engage an experienced sign manufacturer to apply graphics for project identification signs.
Write sign in both English and Arabic, and include:
a.
b.
c.
d.
e.

2.
3.

Project name.
The Employers name and logo.
The Engineers name and logo.
Contractors name and logo.
Such other names, details and information as approved and/or directed by the Engineer.

Provide temporary, directional signs for construction personnel and visitors.


Maintain and touchup signs so they are legible at all times.

H.

Waste Disposal Facilities: Provide waste-collection containers in sizes adequate to handle waste from
construction operations. Comply with requirements of authorities having jurisdiction. Comply with
Division 1 Section "Execution Requirements" for progress cleaning requirements.

I.

Janitorial services: Provide janitorial cleaning services on a daily basis for all temporary offices,
toilets, wash facilities, and similar areas.

J.

Lifts and Hoists: Provide facilities necessary for hoisting materials and personnel.
1.

Truck cranes and similar devices used for hoisting materials are considered "tools and
equipment" and not temporary facilities.

K.

Temporary Stairs: Until permanent stairs are available, provide temporary stairs where ladders are
not adequate.

L.

Construction aids and miscellaneous facilities: Provide all necessary aids and miscellaneous facilities
incidental and ancillary to the safe and efficient execution of construction operations and the carrying
out of work in a proper workmanlike manner, including but not necessarily limited to:
1.
2.
3.
4.
5.
6.
7.

Scaffolds, ladders, walkways, platforms and guardrails.


Protective screens, chutes, coverings and roofs.
Small tools; hand and power operated.
Mechanical plant, machinery and equipment; stationary and mobiles.
Tower cranes.
Transportation equipment and vehicles; on and off site.
Protective clothing, including helmets, goggles, ear protectors and steel-toed safety boots.

The Contractor shall erect temporary scaffolding in accordance with the ACI 301 and BS standards.
The Contractor shall provide landing platforms with stairways or ladders for proper access and egress
to all work areas.
For all frame scaffolding greater than 4 m in height, the Contractor shall submit and have working
drawings. A certified professional shall review and approve the working drawings.

TEMPORARY FACILITIES AND CONTROLS


Volume 2

01500 Page 9 of 11
May 2012

Saraya Aqaba

Specifications

During non-working hours, the Contractor shall close and lock the scaffolding with a physical barrier
to prevent access by unauthorized persons.

3.4

SECURITY AND PROTECTION FACILITIES INSTALLATION


A.

Security And Protection Facilities Installation: Provide security guards, and full responsibility for
Security and Protection Facilities installations.
1.
2.

Provide continued maintenance, support and service, including final removal.


Supplement, extend, relocate, modify, alter and adapt as necessary to comply with
requirements indicated and specified, and accommodate construction operations under this
Contract.

B.

Environmental Protection: Provide protection, operate temporary facilities, and conduct construction
in ways and by methods that comply with environmental regulations and that minimize possible air,
waterway, and subsoil contamination or pollution or other undesirable effects.

C.

Temporary Erosion and Sedimentation Control: Provide measures to prevent soil erosion and
discharge of soil-bearing water runoff and airborne dust to adjacent properties and walkways,
according to requirements of authorities having jurisdiction.

D.

Storm-water Control: Comply with authorities having jurisdiction. Provide barriers in and around
excavations and sub-grade construction to prevent flooding by runoff of storm-water from heavy
rains.

E.

Tree and Plant Protection: Unless otherwise indicated, install temporary fencing located outside the
drip line of trees to protect vegetation from construction damage. Protect tree root systems from
damage, flooding and erosion.

F.

Pest Control: Engage pest-control service to recommend practices to minimize attraction and
harboring of rodents, roaches, and other pests and to perform extermination and control procedures at
regular intervals so Project will be free of pests and their residues at Substantial Completion. Obtain
extended warranty for Employer. Perform control operations lawfully, using environmentally safe
materials.

G.

Site Enclosure Fence: Temporary fence around the site is existing. Contractor shall take over the
temporary fence from the Employer, adapt as necessary during construction and, furnish and install
required additional site enclosure fence with material similar to the existing fence in a manner that
will prevent people and animals from easily entering site except by entrance gates. Maintain the
enclosure fence throughout the duration of the contract.
1.
2.
3.

Extent of Fence: Adapt fence and provide additional fence as required to enclose entire
Project site or portion determined sufficient to accommodate construction operations.
Adjust the existing temporary fence in line with the insurance requirements (i.e. close all the
openings)
Maintain security by limiting number of keys and restricting distribution to authorized
personnel. Provide Engineer and Employer with one set of keys for each.

H.

Security Enclosure and Lockup: Install substantial temporary enclosure around partially completed
areas of construction. Provide lockable entrances to prevent unauthorized entrance, vandalism, theft,
and similar violations of security.

I.

Secure storage: Where materials and/or equipment are of high value or attractive for theft, provide a
secure lockup. Enforce discipline in connection with the installation and release of such materials
and/or equipment to minimize the opportunity for theft.

J.

Barricades, Warning Signs, and Lights: Comply with requirements of authorities having jurisdiction
for erecting structurally adequate barricades, including warning signs and lighting.

TEMPORARY FACILITIES AND CONTROLS


Volume 2

01500 Page 10 of 11
May 2012

Saraya Aqaba
K.

Covered Walkway: Erect structurally adequate, protective, covered walkway for passage of
individuals along adjacent public street(s). Coordinate with entrance gates, other facilities, and
obstructions. Comply with regulations of authorities having jurisdiction.
1.
2.

3.
4.

3.5

Specifications

Construct covered walkways using scaffold or shoring framing.


Provide wood-plank overhead decking, protective plywood enclosure walls, handrails,
barricades, warning signs, lights, safe and well-drained walkways, and similar provisions for
protection and safe passage.
Extend back wall beyond the structure to complete enclosure fence.
Paint and maintain in a manner approved by Engineer.

OPERATION, TERMINATION, AND REMOVAL


A.

Supervision: Enforce strict discipline in use of temporary facilities. To minimize waste and abuse,
limit availability of temporary facilities to essential and intended uses.

B.

Maintenance: Maintain facilities in good operating condition until removal.


1.

Maintain operation of temporary enclosures, humidity control, ventilation, and similar


facilities on a 24-hour basis where required to achieve indicated results and to avoid
possibility of damage.

C.

Operate Project-identification-sign lighting daily from dusk until 12:00 midnight.

D.

Temporary Facility Changeover: Do not change over from using temporary security and protection
facilities to permanent facilities until Substantial Completion.

E.

Termination and Removal: Remove each temporary facility when need for its service has ended,
when it has been replaced by authorized use of a permanent facility, or no later than Substantial
Completion. Complete or, if necessary, restore permanent construction that may have been delayed
because of interference with temporary facility. Repair damaged Work, clean exposed surfaces, and
replace construction that cannot be satisfactorily repaired.
1.

2.
3.

4.

Upon completion of the works, the Project Identification and Temporary Signs, the Site
Enclosure Fence and the Employers, Engineers, and Consultants Field Offices shall be the
property of the Employer.
Other materials and facilities that constitute temporary facilities are the property of
Contractor.
Remove temporary paving not intended for or acceptable for integration into permanent
paving. Repair or replace street paving, curbs, and sidewalks at temporary entrances, as
required by authorities having jurisdiction.
At Substantial Completion, clean and renovate permanent facilities used during construction
period. Comply with final cleaning requirements specified in Division 1 Section "Closeout
Procedures."

END OF SECTION 01500

TEMPORARY FACILITIES AND CONTROLS


Volume 2

01500 Page 11 of 11
May 2012

Saraya Aqaba

Specifications

SECTION 01600 - PRODUCT REQUIREMENTS

PART 1 - GENERAL

1.1

RELATED DOCUMENTS
A.

1.2

Drawings and general provisions of the Contract, including General and Particular Conditions and
other Division 1 Specification Sections, apply to this Section.

SUMMARY
A.

This Section includes administrative and procedural requirements for selection of products for use in
Project; product delivery, storage, and handling; manufacturers' standard warranties on products;
special warranties; product substitutions; and comparable products.

B.

Where specific materials, products or items are selected by the design consultants, giving reference to
specific manufacturer(s), supplier(s) or article number(s), subject to compliance with design and performance requirements, equal alternatives may be selected subject to the approval of Engineer.

C.

Related Sections include the following:


1.
Division 1 Section "References" for applicable industry standards for products specified.
2.
Division 1 Section "Closeout Procedures" for submitting warranties for Contract closeout.
3.
Divisions 2 through 16 Sections for specific requirements for warranties on products and
installations specified to be warranted.

1.3

DEFINITIONS
A.

Products: Items purchased for incorporating into the Work, whether purchased for Project or taken
from previously purchased stock. The term "product" includes the terms "material," "equipment,"
"system," and terms of similar intent.
1.

2.
3.

Named Products: Items identified by manufacturer's product name, including make or model
number or other designation shown or listed in manufacturer's published product literature,
that is current as of date of the Contract Documents.
New Products: Items that have not previously been incorporated into another project or
facility. Products salvaged or recycled from other projects are not considered new products.
Comparable Product: Product that is demonstrated and approved through submittal process,
or where indicated as a product substitution, to have the indicated qualities related to type,
function, dimension, in-service performance, physical properties, appearance, and other
characteristics that equal or exceed those of specified product.

B.

Substitutions: Changes in products, materials, equipment, and methods of construction from those
required by the Contract Documents and proposed by Contractor.

C.

Basis-of-Design Product Specification: Where a specific manufacturer's product is named and


accompanied by the words "basis of design," including make or model number or other designation,
to establish the significant qualities related to type, function, dimension, in-service performance,
physical properties, appearance, and other characteristics for purposes of evaluating comparable
products of other named manufacturers.

1.4

SUBMITTALS
A.

Product List: Submit a list, in tabular from, showing specified products. Include generic names of
products required. Include manufacturer's name and proprietary product names for each product.

PRODUCT REQUIREMENTS
Volume 2

01600 Page 1 of 6
May 2012

Saraya Aqaba
1.
2.

Specifications
Coordinate product list with Contractor's Construction Schedule and the Submittals Schedule.
Form: Tabulate information for each product under the following column headings:
a.
b.
c.
d.
e.
f.
g.
h.

3.

Initial Submittal: Within 28 days after date of commencement of the Work, submit 4 copies
of initial product list. Include a written explanation for omissions of data and for variations
from Contract requirements.
a.

4.

5.

B.

Specification Section number and title.


Generic name used in the Contract Documents.
Proprietary name, model number, and similar designations.
Manufacturer's name and address.
Supplier's name and address.
Installer's name and address.
Projected delivery date or time span of delivery period.
Identification of items that require early submittal approval for scheduled delivery date.

At Contractor's option, initial submittal may be limited to product selections and


designations that must be established early in Contract period.

Completed List: Within 56 days after date of commencement of the Work, submit 4 copies of
completed product list. Include a written explanation for omissions of data and for variations
from Contract requirements.
Engineer's Action: Engineer will respond in writing to Contractor within 14 days of receipt of
completed product list for Civil & Structural items and within 21 days for all other items.
Engineer's response will include a list of unacceptable product selections and a brief
explanation of reasons for this action. Engineer's response, or lack of response, does not
constitute a waiver of requirement to comply with the Contract Documents.

Substitution Requests: Submit four copies of each request for consideration. Identify product or
fabrication or installation method to be replaced. Include Specification Section number and title and
Drawing numbers and titles.
1.
2.

Substitution Request Form: Use Form provided by Engineer.


Documentation: Show compliance with requirements for substitutions and the following, as
applicable:
a.
b.

c.

d.
e.
f.
g.
h.
i.

j.
k.

Statement indicating why specified material or product cannot be provided.


Coordination information, including a list of changes or modifications needed to other
parts of the Work and to construction performed by Employer and separate contractors,
that will be necessary to accommodate proposed substitution.
Detailed comparison of significant qualities of proposed substitution with those of the
Work specified. Significant qualities may include attributes such as performance,
weight, size, durability, visual effect, and specific features and requirements indicated.
Product Data, including drawings and descriptions of products and fabrication and
installation procedures.
Samples, where applicable or requested.
List of similar installations for completed projects with project names and addresses
and names and addresses of employers/owners.
Material test reports from a qualified testing agency indicating and interpreting test
results for compliance with requirements indicated.
Research/evaluation reports evidencing compliance with building code in effect for
Project, from a model code organization acceptable to authorities having jurisdiction.
Detailed comparison of Contractor's Construction Schedule using proposed substitution
with products specified for the Work, including effect on the overall Time for
Completion. If specified product or method of construction cannot be provided within
the Time for Completion, include letter from manufacturer, on manufacturer's
letterhead, stating lack of availability or delays in delivery.
Cost information, including a proposal of change, if any, in the Contract Price.
Contractor's certification that proposed substitution complies with requirements in the
Contract Documents and is appropriate for applications indicated.

PRODUCT REQUIREMENTS
Volume 2

01600 Page 2 of 6
May 2012

Saraya Aqaba

Specifications
l.

3.

Engineer's Action: If necessary, Engineer will request additional information or


documentation for evaluation within 14 days of receipt of a request for substitution. Engineer
will notify Contractor of acceptance or rejection of proposed substitution within 14 days of
receipt of request for Civil & Structural items and within 21 days for all other items, or within
14 days of receipt of additional information or documentation, whichever is later.
a.

b.

C.

Engineer's Action: If necessary, Engineer will request additional information or


documentation for evaluation within 14 days of receipt of a comparable product request.
Engineer will notify Contractor of approval or rejection of proposed comparable product
request within 14 days of receipt of request for Civil & Structural items and within 21 days for
all other items, or within 14 days days of receipt of additional information or documentation,
whichever is later.
a.
b.

1.5

Form of Acceptance: Variation Order; however, should any proposed substitution be


accepted, any increase in cost shall be borne by the Contractor and any saving shall be
to the benefit of the Employer, and no Extension of Time shall be granted to the
Contractor.
Use product specified if Engineer cannot make a decision on use of a proposed
substitution within time allocated.

Comparable Product Requests: Submit four copies of each request for consideration. Identify product
or fabrication or installation method to be replaced. Include Specification Section number and title
and Drawing numbers and titles.
1.

D.

Contractor's waiver of rights to additional payment or time that may subsequently


become necessary because of failure of proposed substitution to produce indicated
results.

Form of Approval: As specified in Division 1 Section "Submittal Procedures."


Use product specified if Engineer cannot make a decision on use of a comparable
product request within time allocated.

Basis-of-Design Product Specification Submittal: Comply with requirements in Division 1 Section


"Submittal Procedures." Show compliance with requirements.

QUALITY ASSURANCE
A.

1.6

Compatibility of Options: If Contractor is given option of selecting between two or more products for
use on Project, product selected shall be compatible with products previously selected, even if
previously selected products were also options.

PRODUCT DELIVERY, STORAGE, AND HANDLING


A.

Deliver, store, and handle products using means and methods that will prevent damage, deterioration,
and loss, including theft. Comply with manufacturer's written instructions.

B.

Delivery and Handling:


1.
2.
3.

4.

C.

Schedule delivery to minimize long-term storage at Project site and to prevent overcrowding
of construction spaces.
Coordinate delivery with installation time to ensure minimum holding time for items that are
flammable, hazardous, easily damaged, or sensitive to deterioration, theft, and other losses.
Deliver products to Project site in an undamaged condition in manufacturer's original sealed
container or other packaging system, complete with labels and instructions for handling,
storing, unpacking, protecting, and installing.
Inspect products on delivery to ensure compliance with the Contract Documents and to ensure
that products are undamaged and properly protected.

Storage:

PRODUCT REQUIREMENTS
Volume 2

01600 Page 3 of 6
May 2012

Saraya Aqaba
1.
2.
3.
4.
5.
6.
7.

1.7

Specifications
Store products to allow for inspection and measurement of quantity or counting of units.
Store materials in a manner that will not endanger Project structure.
Store products that are subject to damage by the elements, under cover in a weather-tight
enclosure above ground, with ventilation adequate to prevent condensation.
Store cementitious products and materials on elevated platforms.
Comply with product manufacturer's written instructions for temperature, humidity,
ventilation, and weather-protection requirements for storage.
Protect stored products from damage.
Provide a secure location and enclosure at Project site for storage of materials and equipment.
Coordinate location with Engineer.

PRODUCT WARRANTIES
A.

Warranties specified in other Sections shall be in addition to, and run concurrent with, other
warranties required by the Contract Documents. Manufacturer's disclaimers and limitations on
product warranties do not relieve Contractor of obligations under requirements of the Contract
Documents.
1.
2.

B.

Special Warranties: Prepare a written document that contains appropriate terms and identification,
ready for execution. Submit a draft for approval before final execution.
1.
2.

C.

Manufacturer's Warranty: Preprinted written warranty published by individual manufacturer


for a particular product and specifically endorsed by manufacturer to Employer.
Special Warranty: Written warranty required by or incorporated into the Contract Documents,
either to extend time limit provided by manufacturer's warranty or to provide more rights for
Employer.

Manufacturer's Standard Form: Modified to include Project-specific information and properly


executed.
Refer to Divisions 2 through 16 Sections for specific content requirements and particular
requirements for submitting special warranties.

Submittal Time: Comply with requirements in Division 1 Section "Closeout Procedures."

PART 2 - PRODUCTS

2.1

PRODUCT SELECTION PROCEDURES


A.

General Product Requirements: Provide products that comply with the Contract Documents, that are
undamaged and, unless otherwise indicated, that are new at time of installation.
1.
2.

3.
4.
5.
6.
7.

B.

Provide products complete with accessories, trim, finish, fasteners, and other items needed for
a complete installation and indicated use and effect.
Standard Products: If available, and unless custom products or nonstandard options are
specified, provide standard products of types that have been produced and used successfully in
similar situations on other projects.
Engineer reserves the right to limit selection to products with warranties not in conflict with
requirements of the Contract Documents.
Where products are accompanied by the term "as selected," Engineer will make selection.
Where products are accompanied by the term "match sample," sample to be matched is
Engineer's.
Descriptive, performance, and reference standard requirements in the Specifications establish
"salient characteristics" of products.
Or Equal: Where products are specified by name and accompanied by the term "or equal" or
"or approved equal" or "or approved," comply with provisions in Part 2 "Comparable
Products" Article to obtain approval for use of an unnamed product.

Product Selection Procedures:

PRODUCT REQUIREMENTS
Volume 2

01600 Page 4 of 6
May 2012

Saraya Aqaba
1.
2.
3.

4.
5.
6.

7.

8.

9.

10.

Specifications
Product: Where Specifications name a single product and manufacturer, provide the named
product that complies with requirements.
Manufacturer/Source: Where Specifications name a single manufacturer or source, provide a
product by the named manufacturer or source that complies with requirements.
Where specific materials, products or items are selected by the design consultants, giving
reference to specific manufacturer(s), supplier(s) or article number(s), subject to compliance
with design and performance requirements, equal alternatives may be selected subject to the
approval of Engineer.
Products: Where Specifications include a list of names of both products and manufacturers,
provide one of the products listed that complies with requirements.
Manufacturers: Where Specifications include a list of manufacturers' names, provide a product
by one of the manufacturers listed that complies with requirements.
Available Products: Where Specifications include a list of names of both products and
manufacturers, provide one of the products listed, or an unnamed product, that complies with
requirements. Comply with provisions in Part 2 "Comparable Products" Article for
consideration of an unnamed product.
Available Manufacturers: Where Specifications include a list of manufacturers, provide a
product by one of the manufacturers listed, or an unnamed manufacturer, that complies with
requirements. Comply with provisions in Part 2 "Comparable Products" Article for
consideration of an unnamed product.
Product Options: Where Specifications indicate that sizes, profiles, and dimensional
requirements on Drawings are based on a specific product or system, provide the specified
product or system. Comply with provisions in Part 2 "Product Substitutions" Article for
consideration of an unnamed product or system.
Basis-of-Design Product: Where Specifications name a product and include a list of
manufacturers, provide the specified product or a comparable product by one of the other
named manufacturers. Drawings and Specifications indicate sizes, profiles, dimensions, and
other characteristics that are based on the product named. Comply with provisions in Part 2
"Comparable Products" Article for consideration of an unnamed product by the other named
manufacturers.
Visual Matching Specification: Where Specifications require matching an established Sample,
select a product that complies with requirements and matches Engineer's sample. Engineer's
decision will be final on whether a proposed product matches.
a.

11.

Visual Selection Specification: Where Specifications include the phrase "as selected from
manufacturer's colors, patterns, textures" or a similar phrase, select a product that complies
with other specified requirements.
a.

b.

2.2

If no product available within specified category matches and complies with other
specified requirements, comply with provisions in Part 2 "Product Substitutions"
Article for proposal of product.

Standard Range: Where Specifications include the phrase "standard range of colors,
patterns, textures" or similar phrase, Engineer will select color, pattern, density, or
texture from manufacturer's product line that does not include premium items.
Full Range: Where Specifications include the phrase "full range of colors, patterns,
textures" or similar phrase, Engineer will select color, pattern, density, or texture from
manufacturer's product line that includes both standard and premium items.

PRODUCT SUBSTITUTIONS
A.

Timing: Engineer will consider requests for substitution if received within 56 days after
commencement of the Work. Requests received after that time may be considered or rejected at
discretion of Engineer.

B.

Conditions: Engineer will consider Contractor's request for substitution when the following
conditions are satisfied. If the following conditions are not satisfied, Engineer will return requests
without action, except to record noncompliance with these requirements:

PRODUCT REQUIREMENTS
Volume 2

01600 Page 5 of 6
May 2012

Saraya Aqaba
1.

2.
3.
4.
5.
6.
7.
8.
9.

2.3

Specifications
Requested substitution offers Employer a substantial advantage in cost, time, energy
conservation, or other considerations, after deducting additional responsibilities Employer
must assume. Employer's additional responsibilities may include compensation to Employer
for redesign and evaluation services, increased cost of other construction by Employer, and
similar considerations.
Requested substitution does not require extensive revisions to the Contract Documents.
Requested substitution is consistent with the Contract Documents and will produce indicated
results.
Substitution request is fully documented and properly submitted.
Requested substitution will not adversely affect Contractor's Construction Schedule.
Requested substitution has received necessary approvals of authorities having jurisdiction.
Requested substitution is compatible with other portions of the Work.
Requested substitution has been coordinated with other portions of the Work.
Requested substitution provides specified warranty.

COMPARABLE PRODUCTS
A.

Conditions: Engineer will consider Contractor's request for comparable product when the following
conditions are satisfied. If the following conditions are not satisfied, Engineer will return requests
without action, except to record noncompliance with these requirements:
1.

2.

3.
4.
5.

Evidence that the proposed product does not require extensive revisions to the Contract
Documents, that it is consistent with the Contract Documents and will produce the indicated
results, and that it is compatible with other portions of the Work.
Detailed comparison of significant qualities of proposed product with those named in the
Specifications. Significant qualities include attributes such as performance, weight, size,
durability, visual effect, and specific features and requirements indicated.
Evidence that proposed product provides specified warranty.
List of similar installations for completed projects with project names and addresses and
names and addresses of employers/owners, if requested.
Samples, if requested.

PART 3 - EXECUTION (Not Used)

END OF SECTION 01600

PRODUCT REQUIREMENTS
Volume 2

01600 Page 6 of 6
May 2012

Saraya Aqaba

Specifications

SECTION 01700 - EXECUTION REQUIREMENTS

PART 1 - GENERAL

1.1

RELATED DOCUMENTS
A.

1.2

Drawings and general provisions of the Contract, including General and Particular Conditions and
other Division 1 Specification Sections, apply to this Section.

SUMMARY
A.

This Section includes general procedural requirements governing execution of the Work including,
but not limited to, the following:
1.
2.
3.
4.
5.
6.
7.

B.

Related Sections include the following:


1.
2.
3.

1.3

Construction layout.
Field engineering and surveying.
General installation of products.
Progress cleaning.
Protection of the Project Site during construction.
Protection of installed construction.
Correction of the Work.

Division 1 Section "Project Management and Coordination" for procedures for coordinating
field engineering with other construction activities.
Division 1 Section "Submittal Procedures" for submitting surveys.
Division 1 Section "Closeout Procedures" for submitting final property survey with Project
Record Documents, recording of Engineer-accepted deviations from indicated lines and levels,
and final cleaning.

SUBMITTALS
A.

Qualification Data: For land surveyor and professional engineer.

B.

Certificates: Submit certificate signed by land surveyor and professional engineer certifying that
location and elevation of improvements comply with requirements.

C.

Certified Surveys: Submit three copies signed by land surveyor and professional engineer.

D.

Final Property Survey: Submit 10 copies showing the Work performed and record survey data.

1.4

QUALITY ASSURANCE
A.

Land Surveyor Qualifications: A professional land surveyor who is legally qualified to practice in
jurisdiction where Project is located and who is experienced in providing land-surveying services of
the kind indicated.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

EXECUTION REQUIREMENTS
Volume 2

01700 Page 1 of 6
May 2012

Saraya Aqaba
3.1

Specifications

EXAMINATION
A.

Existing Conditions: The existence and location of site improvements, utilities, and other
construction indicated as existing are not guaranteed. Before beginning work, investigate and verify
the existence and location of mechanical and electrical systems and other construction affecting the
Work.

B.

Existing Utilities: The existence and location of underground and other utilities and construction
indicated as existing are not guaranteed. Before beginning site-work, investigate and verify the
existence and location of underground utilities and other construction affecting the Work.

C.

Acceptance of Conditions: Examine substrates, areas, and conditions, with Installer or Applicator
present where indicated, for compliance with requirements for installation tolerances and other
conditions affecting performance. Record observations.
1.

Written Report: Where a written report listing conditions detrimental to performance of the
Work is required by other Sections, include the following:
a.
b.
c.
d.

2.
3.
4.
5.

3.2

Description of the Work.


List of detrimental conditions, including substrates.
List of unacceptable installation tolerances.
Recommended corrections.

Verify compatibility with and suitability of substrates.


Examine roughing-in for mechanical and electrical systems to verify actual locations of
connections before equipment and fixture installation.
Examine walls, floors, and roofs for suitable conditions where products and systems are to be
installed.
Proceed with installation only after unsatisfactory conditions have been corrected. Proceeding
with the Work indicates acceptance of surfaces and conditions.

PREPARATION
A.

Existing Utility Information: Furnish information to local utility that is necessary to adjust, move, or
relocate existing utility structures, utility poles, lines, services, or other utility appurtenances located
in or affected by construction. Coordinate with authorities having jurisdiction.

B.

Field Measurements: Take field measurements as required to fit the Work properly. Recheck
measurements before installing each product. Where portions of the Work are indicated to fit to other
construction, verify dimensions of other construction by field measurements before fabrication.
Coordinate fabrication schedule with construction progress to avoid delaying the Work.

C.

Space Requirements: Verify space requirements and dimensions of items shown diagrammatically on
Drawings.

D.

Review of Contract Documents and Field Conditions: Immediately on discovery of the need for
clarification of the Contract Documents, submit a request for information to Engineer. Include a
detailed description of problem encountered, together with recommendations for changing the
Contract Documents.

3.3

CONSTRUCTION LAYOUT
A.

Verification: Before proceeding to lay out the Work, verify layout information shown on Drawings,
in relation to the property survey and existing benchmarks. If discrepancies are discovered, notify
Engineer promptly.

B.

General: Engage a land surveyor or professional engineer to lay out the Work using accepted
surveying practices.

EXECUTION REQUIREMENTS
Volume 2

01700 Page 2 of 6
May 2012

Saraya Aqaba
1.
2.
3.
4.
5.
6.

Specifications
Establish benchmarks, site level zero point and control points to set lines and levels at each
story of construction and elsewhere as needed to locate each element of Project.
Establish dimensions within tolerances indicated. Do not scale Drawings to obtain required
dimensions.
Inform installers of lines and levels to which they must comply.
Check the location, level and plumb, of every major element as the Work progresses.
Notify Engineer when deviations from required lines and levels exceed allowable tolerances.
Close site surveys with an error of closure equal to or less than the standard established by
authorities having jurisdiction.

C.

Building Lines and Levels: Locate and lay out control lines and levels for structures, building
foundations, column grids, and floor levels. Transfer survey markings and elevations for use with
control lines and levels. Level foundations and piers from two or more locations.

D.

Record Log: Maintain a log of layout control work. Record deviations from required lines and
levels. Include beginning and ending dates and times of surveys, weather conditions, name and duty
of each survey party member, and types of instruments and tapes used. Make the log available for
reference by Engineer.

3.4

FIELD ENGINEERING
A.

Identification: Engineer will identify existing benchmarks, control points, and property corners.

B.

Reference Points: Locate existing permanent benchmarks, control points, and similar reference points
before beginning the Work. Preserve and protect permanent benchmarks and control points during
construction operations.
1.

2.

C.

Do not change or relocate existing benchmarks or control points without prior written
approval of Engineer. Report lost or destroyed permanent benchmarks or control points
promptly. Report the need to relocate permanent benchmarks or control points to Engineer
before proceeding.
Replace lost or destroyed permanent benchmarks and control points promptly. Base
replacements on the original survey control points.

Benchmarks: Establish and maintain a minimum of two permanent benchmarks on Project site,
referenced to data established by survey control points. Comply with authorities having jurisdiction
for type and size of benchmark.
1.
2.
3.

Record benchmark locations, with horizontal and vertical data, on Project Record Documents.
Where the actual location or elevation of layout points cannot be marked, provide temporary
reference points sufficient to locate the Work.
Remove temporary reference points when no longer needed. Restore marked construction to
its original condition.

D.

Certified Survey: On completion of foundation walls and other work requiring field-engineering
services, prepare a certified survey showing dimensions, locations, angles, and elevations of
construction and sitework.

E.

Initial Property Survey: Prepare an initial property survey based upon existing As-Built Drawings
showing significant features (real property) for the existing Works. Include on the survey a
certification, signed by land surveyor and professional engineer, that principal metes, bounds, lines,
and levels of the existing Works are accurately positioned as shown on the survey.
1.
2.

F.

Show boundary lines, monuments, streets, adjoining properties and the distance and bearing
from a site corner to a legal point.
Recording: Have the initial property survey recorded by or with authorities having
jurisdiction as the official "property survey."

Final Property Survey: Prepare a final property survey showing significant features (real property)
for Project. Include on the survey a certification, signed by land surveyor and professional engineer,

EXECUTION REQUIREMENTS
Volume 2

01700 Page 3 of 6
May 2012

Saraya Aqaba

Specifications

that principal metes, bounds, lines, and levels of Project are accurately positioned as shown on the
survey.
1.
2.

3.5

Show boundary lines, monuments, streets, adjoining properties and the distance and bearing
from a site corner to a legal point.
Recording: At Substantial Completion, have the final property survey recorded by or with
authorities having jurisdiction as the official "property survey."

INSTALLATION
A.

General: Locate the Work and components of the Work accurately, in correct alignment and
elevation, as indicated.
1.
2.

Make vertical work plumb and make horizontal work level.


Where space is limited, install components to maximize space available for maintenance and
ease of removal for replacement.

B.

Comply with manufacturer's written instructions and recommendations for installing products in
applications indicated.

C.

Install products at the time and under conditions that will ensure the best possible results. Maintain
conditions required for product performance until Substantial Completion.

D.

Conduct construction operations so no part of the Work is subjected to damaging operations or


loading in excess of that expected during normal conditions of occupancy.

E.

Tools and Equipment: Do not use tools or equipment that produce harmful noise levels.

F.

Templates: Obtain and distribute to the parties involved templates for work specified to be factory
prepared and field installed. Check Shop Drawings of other work to confirm that adequate provisions
are made for locating and installing products to comply with indicated requirements.

G.

Anchors and Fasteners: Provide anchors and fasteners as required to anchor each component
securely in place, accurately located and aligned with other portions of the Work.
1.
2.
3.

Mounting Heights: Where mounting heights are not indicated, mount components at heights
directed by Engineer.
Allow for building movement, including thermal expansion and contraction.
Coordinate installation of anchorages. Furnish setting drawings, templates, and directions for
installing anchorages, including sleeves, concrete inserts, anchor bolts, and items with integral
anchors, that are to be embedded in concrete. Deliver such items to Project site in time for
installation.

H.

Joints: Make joints of uniform width. Where joint locations in exposed work are not indicated,
arrange joints for the best visual effect. Fit exposed connections together to form hairline joints.

I.

Hazardous Materials: Use products, cleaners, and installation materials that are not considered
hazardous.

3.6

PROGRESS CLEANING
A.

General: Clean Project site and work areas daily, including common areas. Coordinate progress
cleaning for joint-use areas where more than one installer has worked. Enforce requirements strictly.
Dispose of materials lawfully.
1.
2.

Comply with requirements in NFPA 241 for removal of combustible waste materials and
debris.
Do not hold materials more than 7 days during normal weather or 3 days if the temperature is
expected to rise above 27 deg C.

EXECUTION REQUIREMENTS
Volume 2

01700 Page 4 of 6
May 2012

Saraya Aqaba
3.
4.

5.

6.

Specifications
Containerize hazardous and unsanitary waste materials separately from other waste. Mark
containers appropriately and dispose of legally, according to regulations.
Regularly clean up the work areas and at all times maintain the Project Site in as neat and
orderly a manner as is consistent with normal operations. Debris resulting from construction
operations shall be removed from the Project Site daily by the Contractor. The Contractor
shall keep all access, haul routes, and site areas free of dirt, debris, and other materials
resulting from construction activities.
Under no circumstances shall any rubbish or waste be dropped or thrown from one level of
scaffolding to another or within or outside the Buildings. Rubbish may be lowered by way of
chutes, taken down on hoists, or lowered in receptacles.
The Contractor shall provide enclosed trash receptacle(s) in quantity and size necessary to
meet project needs. Trash receptacles shall be placed in proper locations and shall be cleaned
out on daily basis.

B.

Site: Maintain Project site free of waste materials and debris.

C.

Work Areas: Clean areas where work is in progress to the level of cleanliness necessary for proper
execution of the Work.
1.
2.

Remove liquid spills promptly.


Where dust would impair proper execution of the Work, broom-clean or vacuum the entire
work area, as appropriate.

D.

Installed Work: Keep installed work clean. If specific cleaning materials are not recommended, use
cleaning materials that are not hazardous to health or property and that will not damage exposed
surfaces.

E.

Concealed Spaces: Remove debris from concealed spaces before enclosing the space.

F.

Exposed Surfaces in Finished Areas: Clean exposed surfaces and protect as necessary to ensure
freedom from damage and deterioration at time of Substantial Completion.

G.

Waste Disposal: Burying or burning waste materials on-site will not be permitted. Washing waste
materials down sewers or into waterways will not be permitted.

H.

During handling and installation, clean and protect construction in progress and adjoining materials
already in place. Apply protective covering where required to ensure protection from damage or
deterioration at Substantial Completion.

I.

Clean and provide maintenance on completed construction as frequently as necessary through the
remainder of the construction period.

J.

Limiting Exposures: Supervise construction operations to assure that no part of the construction,
completed or in progress, is subject to harmful, dangerous, damaging, or otherwise deleterious
exposure during the construction period.

3.7

PROTECTION OF THE PROJECT SITE DURING CONSTRUCTION


A.

The Contractor shall provide adequate protection for all parts of the Project site including the white
sand beaches, lagoon area, all main, and service buildings in addition to all interior and exterior
surfaces, its occupants and contents, and all grounds wherever work under this Contract is performed.

B.

Plan for Protection of the Project Site, White Sand Beaches, Lagoon Area and all Main and Service
Buildings: The Contractor shall submit a plan for the protection of the site, white sand beaches,
lagoon area and all main and service buildings to the Engineer. As a minimum, the plan shall
describe:
1.
2.
3.

Proposed method, location, and construction of temporary enclosures.


Routes of access and egress, including those for people with disabilities.
Location and maintenance of emergency exits.

EXECUTION REQUIREMENTS
Volume 2

01700 Page 5 of 6
May 2012

Saraya Aqaba
4.
5.

Specifications
Methods of protection of existing surfaces.
Means of connection of temporary enclosures/surfaces to existing services, structures, and
buildings.

C.

Temporary enclosures shall be constructed to prevent unauthorized access or egress. Dust and fume
barriers shall be constructed, as needed.

D.

Dust and air quality control:


1.

2.

3.
E.

3.8

The Contractor shall execute the Works by methods that minimize dust raised by construction
operations. The Contractor will provide positive means to prevent objectionable odors and
air-borne dust from dispersing into the atmosphere.
Dust barriers shall be erected where necessary to protect adjacent areas from dust infiltration.
Dust barriers within buildings shall be rigid and visually opaque and shall seal the work area
by affixing to the structure on all sides (i.e. ceiling, walls, and floor).
No open fires or burning of trash are permitted on the Project Site.

Noise control: The Contractor shall comply with the regulations of all relevant Local Authorities and
all other regulations relative to noise control.

PROTECTION OF INSTALLED CONSTRUCTION


A.

Provide final protection and maintain conditions that ensure installed Work is without damage or
deterioration at time of Substantial Completion.

B.

Comply with manufacturer's written instructions for temperature and relative humidity.

3.9

CORRECTION OF THE WORK


A.

Repair or remove and replace defective construction. Restore damaged substrates and finishes.

B.

Restore permanent facilities used during construction to their specified condition.

C.

Remove and replace damaged surfaces that are exposed to view if surfaces cannot be repaired
without visible evidence of repair.

END OF SECTION 01700

EXECUTION REQUIREMENTS
Volume 2

01700 Page 6 of 6
May 2012

Saraya Aqaba

Specifications

SECTION 01731 - CUTTING AND PATCHING

PART 1 - GENERAL

1.1

RELATED DOCUMENTS
A.

1.2

Drawings and general provisions of the Contract, including General and Particular Conditions and
other Division 1 Specification Sections, apply to this Section.

SUMMARY
A.

This Section includes procedural requirements for cutting and patching.

B.

Related Sections include the following:


1.
Divisions 2 through 16 Sections for specific requirements and limitations applicable to cutting
and patching individual parts of the Work.

1.3

DEFINITIONS
A.

Cutting: Removal of in-place construction necessary to permit installation or performance of other


Work.

B.

Patching: Fitting and repair work required to restore surfaces to original conditions after installation
of other Work.

1.4

SUBMITTALS
A.

Cutting and Patching Proposal: Submit a proposal describing procedures at least 10 days before the
time cutting and patching will be performed, requesting approval to proceed. Include the following
information:
1.
2.

3.
4.
5.

6.

7.

1.5

Extent: Describe cutting and patching, show how they will be performed, and indicate why
they cannot be avoided.
Changes to In-Place Construction: Describe anticipated results. Include changes to structural
elements and operating components as well as changes in building's appearance and other
significant visual elements.
Products: List products to be used and firms or entities that will perform the Work.
Dates: Indicate when cutting and patching will be performed.
Utility Services and Mechanical/Electrical Systems: List services/systems that cutting and
patching procedures will disturb or affect. List services/systems that will be relocated and
those that will be temporarily out of service. Indicate how long services/systems will be
disrupted.
Structural Elements: Where cutting and patching involve adding reinforcement to structural
elements, submit details and engineering calculations showing integration of reinforcement
with original structure.
Engineers Approval: Obtain approval of cutting and patching proposal before cutting and
patching. Approval does not waive right to later require removal and replacement of
unsatisfactory work.

QUALITY ASSURANCE
A.

Structural Elements: Do not cut and patch structural elements in a manner that could change their
load-carrying capacity or load-deflection ratio.

CUTTING AND PATCHING


Volume 2

01731 Page 1 of 4
May 2012

Saraya Aqaba
1.

B.

Including but not limited to foundations, slabs on grade, suspended slabs, concrete walls and
columns.

Operational Elements: Do not cut and patch operating elements and related components in a manner
that results in reducing their capacity to perform as intended or that results in increased maintenance
or decreased operational life or safety. Operating elements include the following:
1.
2.
3.
4.
5.
6.
7.
8.
9.

C.

Specifications

Primary operational systems and equipment.


Air or smoke barriers.
Fire-suppression systems.
Mechanical systems piping and ducts.
Control systems.
Communication systems.
Conveying systems.
Electrical wiring systems.
Operating systems of special construction in Division 13 Sections.

Miscellaneous Elements: Do not cut and patch miscellaneous elements or related components in a
manner that could change their load-carrying capacity, that results in reducing their capacity to
perform as intended, or that results in increased maintenance or decreased operational life or
safety. Miscellaneous elements include the following:
1.
2.
3.
4.
5.
6.

Water, moisture, or vapor barriers.


Membranes and flashings.
Exterior curtain-wall construction.
Equipment supports.
Piping, ductwork, vessels, and equipment.
Noise- and vibration-control elements and systems.

D.

Visual Requirements: Do not cut and patch construction in a manner that results in visual evidence of
cutting and patching. Do not cut and patch construction exposed on the exterior or in occupied spaces
in a manner that would, in Engineer's opinion, reduce the building's aesthetic qualities. Remove and
replace construction that has been cut and patched in a visually unsatisfactory manner.

E.

Cutting and Patching Conference: Before proceeding, meet at Project site with parties involved in
cutting and patching, including mechanical and electrical trades. Review areas of potential
interference and conflict. Coordinate procedures and resolve potential conflicts before proceeding.

1.6

WARRANTY
A.

Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged
during cutting and patching operations, by methods and with materials so as not to void existing
warranties.

PART 2 - PRODUCTS

2.1

MATERIALS
A.

General: Comply with requirements specified in other Sections.

B.

In-Place Materials: Use materials identical to in-place materials. For exposed surfaces, use materials
that visually match in-place adjacent surfaces to the fullest extent possible.
1.

If identical materials are unavailable or cannot be used, use materials that, when installed, will
match the visual and functional performance of in-place materials.

PART 3 - EXECUTION
CUTTING AND PATCHING
Volume 2

01731 Page 2 of 4
May 2012

Saraya Aqaba
3.1

Specifications

EXAMINATION
A.

Examine surfaces to be cut and patched and conditions under which cutting and patching are to be
performed.
1.
2.

3.2

Compatibility: Before patching, verify compatibility with and suitability of substrates,


including compatibility with in-place finishes or primers.
Proceed with installation only after unsafe or unsatisfactory conditions have been corrected.

PREPARATION
A.

Temporary Support: Provide temporary support of Work to be cut.

B.

Protection: Protect in-place construction during cutting and patching to prevent damage. Provide
protection from adverse weather conditions for portions of Project that might be exposed during
cutting and patching operations.

C.

Adjoining Areas: Avoid interference with use of adjoining areas or interruption of free passage to
adjoining areas.

D.

Existing Utility Services and Mechanical/Electrical Systems: Where existing services/systems are
required to be removed, relocated, or abandoned, bypass such services/systems before cutting to
prevent interruption to occupied areas.

3.3

PERFORMANCE
A.

General: Employ skilled workers to perform cutting and patching. Proceed with cutting and patching
at the earliest feasible time, and complete without delay.
1.

B.

Cutting: Cut in-place construction by sawing, drilling, breaking, chipping, grinding, and similar
operations, including excavation, using methods least likely to damage elements retained or adjoining
construction. If possible, review proposed procedures with original Installer; comply with original
Installer's written recommendations.
1.

2.
3.
4.
5.

6.
C.

Cut in-place construction to provide for installation of other components or performance of


other construction, and subsequently patch as required to restore surfaces to their original
condition.

In general, use hand or small power tools designed for sawing and grinding, not hammering
and chopping. Cut holes and slots as small as possible, neatly to size required, and with
minimum disturbance of adjacent surfaces. Temporarily cover openings when not in use.
Finished Surfaces: Cut or drill from the exposed or finished side into concealed surfaces.
Concrete and Masonry: Cut using a cutting machine, such as an abrasive saw or a diamondcore drill.
Excavating and Backfilling: Comply with requirements in applicable Division 2 Sections
where required by cutting and patching operations.
Mechanical and Electrical Services: Cut off pipe or conduit in walls or partitions to be
removed. Cap, valve, or plug and seal remaining portion of pipe or conduit to prevent
entrance of moisture or other foreign matter after cutting.
Proceed with patching after construction operations requiring cutting are complete.

Patching: Patch construction by filling, repairing, refinishing, closing up, and similar operations
following performance of other Work. Patch with durable seams that are as invisible as possible.
Provide materials and comply with installation requirements specified in other Sections.
1.
2.

Inspection: Where feasible, test and inspect patched areas after completion to demonstrate
integrity of installation.
Exposed Finishes: Restore exposed finishes of patched areas and extend finish restoration
into retained adjoining construction in a manner that will eliminate evidence of patching and
refinishing.

CUTTING AND PATCHING


Volume 2

01731 Page 3 of 4
May 2012

Saraya Aqaba

Specifications
a.
b.

3.

Floors and Walls: Where walls or partitions that are removed extend one finished area into
another, patch and repair floor and wall surfaces in the new space. Provide an even surface of
uniform finish, color, texture, and appearance. Remove in-place floor and wall coverings and
replace with new materials, if necessary, to achieve uniform color and appearance.
a.

4.
5.

D.

Clean piping, conduit, and similar features before applying paint or other finishing
materials.
Restore damaged pipe covering to its original condition.

Where patching occurs in a painted surface, apply primer and intermediate paint coats
over the patch and apply final paint coat over entire unbroken surface containing the
patch. Provide additional coats until patch blends with adjacent surfaces.

Ceilings: Patch, repair, or re-hang in-place ceilings as necessary to provide an even-plane


surface of uniform appearance.
Exterior Building Enclosure: Patch components in a manner that restores enclosure to a
weather tight condition.

Cleaning: Clean areas and spaces where cutting and patching are performed. Completely remove
paint, mortar, oils, putty, and similar materials.

END OF SECTION 01731

CUTTING AND PATCHING


Volume 2

01731 Page 4 of 4
May 2012

Saraya Aqaba

Specifications

SECTION 01770 - CLOSEOUT PROCEDURES

PART 1 - GENERAL

1.1

RELATED DOCUMENTS
A.

1.2

Drawings and general provisions of the Contract, including General and Particular Conditions and
other Division 1 Specification Sections, apply to this Section.

SUMMARY
A.

This Section includes administrative and procedural requirements for contract closeout, including, but
not limited to, the following:
1.
2.
3.
4.
5.
6.

B.

1.3

Taking-Over procedures.
Defects Notification.
Performance Certificate.
Warranties.
Final cleaning.
Tests after Completion.

Related Sections include the following:


1.
Division 1 Section "Photographic Documentation" for submitting Final Completion
construction photographs and negatives.
2.
Division 1 Section "Execution Requirements" for progress cleaning of Project site.
3.
Division 1 Section "Project Record Documents" for submitting Record Drawings, Record
Specifications, and Record Product Data.
4.
Divisions 2 through 16 Sections for specific closeout and special cleaning requirements for the
Work in those Sections.

TAKING-OVER PROCEDURES
A.

Preliminary Procedures: Before requesting inspection for determining date of Substantial Completion
(Taking-Over), the Contractor shall complete the following:
1.

2.

3.
4.
5.

6.
7.
8.

9.

Prepare, in a tabular format acceptable to the Engineer, a list of items to be completed and
corrected (punch or snag list). Include the value for each item on the list, and reasons why the
work is not complete, and indicate the time frame within which it will be completed.
Submit a written undertaking in a form acceptable to the Engineer, to complete and/or correct
all items contained in the defects list to the satisfaction of the Engineer, within 28 days from
date of issue of the Taking-Over Certificate.
Advise the Engineer, of impending insurance changeover requirements.
Submit warranties, bonds, maintenance service agreements, final certifications, and similar
documents.
Obtain and submit releases permitting Employer, Engineer, and Operators unrestricted use of
the work and access to services and utilities. Include occupancy permits, operating certificates,
and similar releases as applicable.
Prepare and submit Project Record Documents, As- Built documents, and operation and
maintenance manuals.
Submit final construction photographs and photographic negatives, damage or settlement
surveys, property surveys, and similar final record information.
Deliver according to Contract Documents, manufacturers recommendations, Operators
Requirements, Operation and Maintenance Manuals all required tools, original spare parts,
extra materials, and similar items to locations designated by the Engineer. Label with
manufactures name and model number where applicable.
Make final changeover of permanent locks and deliver keys to the Engineer.

CLOSEOUT PROCEDURES
Volume 2

01770 Page 1 of 6
May 2012

Saraya Aqaba

Specifications

10.
11.
12.
13.

Advise the Engineers Personnel of changeover in security provisions.


Complete startup testing of systems.
Submit test/adjust/balance records.
Terminate and remove temporary facilities from project site, together with mockups (if not
forming part of the permanent Works), construction tools, and similar elements.
Advise the Engineer of any pending changeover in utilities.
Submit changeover information related to Engineer, Employer, Operators and end user
occupancy, use, operation, and maintenance.
Touch up and otherwise repair and restore exposed finishes to eliminate visual defects.
Commence instruction of the Employer / Operators Personnel in operation, adjustment, and
maintenance of systems and equipment, and maintenance of products. Schedule training
sessions for the Employer / Operators personnel.
Install of all signage, including accessibility related signs, equipment instructions,
identification labels, and permanent directional signs.
Remove all waste, rubbish, and temporary facilities and services. Means of access to all areas
of the work to be inspected by the Engineer shall be maintained.
Arrange for permanent utility connections and billing responsibility transfer to the Employer.
Arrange for transfer of security responsibility for the Project Site and changeover of locks at
completion of all of the Works.
Complete final cleaning requirements.

14.
15.
16.
17.

18.
19.
20.
21.
22.
B.

Submission of Operation and Maintenance Manuals: Prior to requesting Taking-Over inspections, the
Contractor shall submit to the Engineer Operation and Maintenance manuals for all systems and
equipment, as specified. The Contractor shall have completed the adjusting and balancing of the
HVAC systems, as specified. Furthermore, the Contractor shall:
1.

2.
3.

4.

5.

C.

Inspection: Submit a written request for inspection for Substantial Completion. On receipt of request,
Engineer will either proceed with inspection or notify Contractor of unfulfilled requirements.
Engineer will prepare the Certificate of Substantial Completion after inspection or will notify
Contractor of items, either on Contractor's list or additional items identified by Engineer, that must be
completed or corrected before certificate will be issued.
1.

1.4

Provide for the Project / Section an inventory for all items to be handed over to the Employer.
The Inventory shall include detailed and organized lists of components and shall be itemized
in accordance with the CSI code.
Submit the Project Maintenance Procedures / Manuals for the Engineers review and consent
including routine, preventive and corrective Maintenance Procedures Manuals.
Provide As Built Drawings / Record Documents shall be organized, itemized, provided and
submitted to the Engineer in accordance with the CSI code and shall be clearly filed for the
Engineers easy access, reference and use.
Provide training for the Employers / Operators Staff during the warrantee period to maintain
and operate all the Projects Sections, parts, buildings, services, facilities including Marine
Works, Water Park, Water Features & Lagoon and the off-site facilities. The training shall
cover categories such as operation activities, routine maintenance, preventive & corrective
maintenance, use and refer to the As Built Drawings & Record Documents, and other
categories recommended by the Operators Requirements / Project stakeholders.
The Contractor shall provide the required Operation & Maintenance Staff matrix showing the
required number of staff, staff specialties and the staff positions for each Section / part of the
Project and as per the recommendations of the Operators Requirements / Maintenance &
Operations Manuals / Stakeholders.

Re-inspection: Request re-inspection when the Work identified in previous inspections as


incomplete is completed or corrected.

DEFECTS NOTIFICATION
A.

Incomplete contract requirements identified during the Taking-Over Inspection will form an initial
basis for a defects list for final acceptance. All defects items must be completed by the Contractor
within the Defects Notification Period. If additional days are needed to complete the defects list

CLOSEOUT PROCEDURES
Volume 2

01770 Page 2 of 6
May 2012

Saraya Aqaba

Specifications

items beyond the Defects Notification Period, then the Contractor shall submit, prior to the end of the
Defects Notification Period, a written request to the Engineer stating:
1.
2.
3.

1.5

PERFORMANCE CERTIFICATE
A.

Preliminary Procedures: Before requesting final inspection and as part of the Performance Certificate
requirements for determining date of Final Completion, the Contractor shall provide and complete the
following:
1.
2.
3.
4.

B.

2.

3.
4.
5.
6.
7.
8.
9.

C.

Certification signed and submitted by the Contractor stating that all contract requirements,
including contract modifications have been met.
Release of assignment of claims or consent of surety submitted, as necessary.
All security ID badges and parking permits returned.
As-Built Drawings and Record Documents submitted.

Request for Performance Certificate: When all items on the defects list have been corrected to the
satisfaction of the Engineer/Employer/Operators and additional requirements as described below have
been satisfied, the Contractor shall submit a written request for the Performance Certificate after
completing the following:
1.

Submission of a copy of prior defects-list stating that each item has been completed or
otherwise resolved for acceptance.
Provision of Instructions to the Employer Personnel; furnish, without additional expense to the
Employer, the services of competent instructors, who will give full instruction in the care,
adjustment, and operation, and maintenance of the systems and equipment, and maintenance
of products to designated the Employer/Operator employees.
Submission of construction progress photographs, property Survey, and similar final record
information.
Submission of evidence of payment and transfer date of utility company accounts for those
utilities previously billed to the Contractor during construction, as necessary.
Submission of evidence that all regulatory agency permit and code requirements have been
completed and recorded, as necessary.
Submission of a signed, written statement that no damage has occurred to the site as
documented by the pre-condition survey report.
Submission of evidence of final, continuing insurance coverage complying with Insurance
requirements.
Submission of pest control final inspection report and warranty.
Submission of certified copy of Performance Certificate inspection list of items to be
completed or corrected (defects) endorsed and dated by the (Site Supervision Team). The
certified copy of the list shall state that each item has been completed or otherwise resolved
for acceptance.

Inspection: Submit a written request for inspection for the Performance Certificate. On receipt of
request, Engineer will either proceed with inspection or notify Contractor of unfulfilled requirements.
1.

1.6

Items requiring additional time.


Amount of time needed to complete each item.
Reasons why the items cannot be completed by the Contract completion date.

The performance Certificate will not be issued until the successful Completion of all testing
and commissioning requirements including those for Marine Works, Water Features, Lagoon,
Water Park including all related civil / electrical / mechanical works, pumping stations,
filtration and cleaning systems, etc... All mentioned items and Project components shall meet
performance criteria and specifications. The Contractor shall meet all Environmental
regulations & codes, local authorities requirements and other parties concerns related to
designing, constructing, operating and maintaining the Marine Works, Water Park and Water
Features and other Project Sections, parts, and elements.

LIST OF INCOMPLETE ITEMS (PUNCH/SNAG LIST)

CLOSEOUT PROCEDURES
Volume 2

01770 Page 3 of 6
May 2012

Saraya Aqaba
A.

Specifications

Preparation: Submit four copies of list. Include name and identification of each space and area
affected by construction operations for incomplete items and items needing correction including, if
necessary, areas disturbed by Contractor that are outside the limits of construction.
1.
2.
3.

Organize list of spaces in sequential order, starting with exterior areas first and proceeding
from lowest floor to highest floor.
Organize items applying to each space by major element, including categories for ceiling,
individual walls and floors.
Include the following information at the top of each page:
a.
b.
c.
d.
e.
f.

1.7

Project name.
Date.
Name of Contractor.
Name of Engineer.
Name of Employer.
Page number.

WARRANTIES
A.

Submittal Time: Submit original written warranties on request of Engineer for designated portions of
the Work where commencement of warranties other than date of Substantial Completion is indicated.

B.

Partial Occupancy: Submit properly executed warranties within 14 days of completion of designated
portions of the Work that are completed and occupied or used by Employer during construction
period by separate agreement with Contractor.

C.

Organize warranty documents into an orderly sequence based on the table of contents of the Project
Manual.
1.
2.

3.
4.

Bind warranties and bonds in heavy-duty, 3-ring, vinyl-covered, loose-leaf binders, thickness
as necessary to accommodate contents, and sized to receive 215-by-280-mm paper.
Provide heavy paper dividers with plastic-covered tabs for each separate warranty. Mark tab
to identify the product or installation. Provide a typed description of the product or
installation, including the name of the product and the name, address, and telephone number
of Installer, subcontractors, suppliers, and manufacturers.
Identify each binder on the front and spine with the typed or printed title "WARRANTIES,"
Project name, and name of Contractor.
Each warranty certificate or bond shall identify the date(s) for:
a.
b.
c.

D.

Taking-Over status in accordance with project closeout requirements.


Beginning and ending of the warranty period.
The Contractor shall provide any coincidental product warranty which is available on a
product incorporated in the Work, but for which the warranty is not specifically
required by the Contract Documents.

Warranty of Construction: The Contractor shall warrant that the works performed under this contract,
including all existing works, conform to the contract requirements and are free of any defect in
equipment, materials, design furnished, or workmanship performed at any time by the Contractor or
any subcontractor or supplier or any previous contractors employed by the Employer. The warranty
of the Work shall continue for the period provided for in the relevant Jordanian Laws.
1.

The Warranty shall include all of the works in the project, including all existing works
previously executed by other contractors employed by the Employer.

PART 2 - PRODUCTS

2.1

MATERIALS

CLOSEOUT PROCEDURES
Volume 2

01770 Page 4 of 6
May 2012

Saraya Aqaba
A.

Specifications

Cleaning Agents: Use cleaning materials and agents recommended by manufacturer or fabricator of
the surface to be cleaned. Do not use cleaning agents that are potentially hazardous to health or
property or that might damage finished surfaces.

PART 3 - EXECUTION

3.1

FINAL CLEANING
A.

General: Provide final cleaning. Conduct cleaning and waste-removal operations to comply with
local laws and ordinances.

B.

Cleaning: Employ experienced workers or professional cleaners for final cleaning. Clean each
surface or unit to condition expected in class A Luxury high standard building cleaning and
maintenance program. Comply with manufacturers written instruction.
1.

Complete the following cleaning operations before requesting inspection for certification of
Substantial Completion for entire Project or for a ortion of Project:
a.

b.
c.
d.
e.
f.
g.
h.
i.
j.

k.
l.
m.
n.
o.
p.
q.

3.2

Clean Project site, yard, and grounds, in areas disturbed by construction activities,
including landscape development areas, of rubbish, waste material, litter, and other
foreign substances.
Conduct cleaning and waste removal to comply with local laws, ordinances and local
environment and antipollution regulations.
Remove tools, construction equipment, machinery, and surplus material from Project
site.
Remove debris and surface dust from limited-access spaces including roofs, plenums,
shafts, trenches, equipment vaults, manholes, attics and similar spaces.
Sweep and dust all surfaces and wash all finished surfaces to appear new and free of all
stains, soil marks, dirt, and other forms of defacement.
Sweep concrete floors broom clean in unoccupied spaces.
Remove labels which are not required as permanent labels.
Clean transparent materials, including mirrors and window/door glass, to a polished
condition, removing substances which are noticeable as vision-obscuring materials.
Replace broken glass and damaged transparent materials.
Clean exposed exterior and interior hard-surfaced finishes to a dirt-free condition, free
of dust stains, films, and similar noticeable substances. Except as otherwise indicated,
avoid disturbance of natural weathering of exterior surfaces. Restore reflective
surfaces to original reflective condition.
Rake grounds that are neither planted nor paved to a smooth, even textured surface.
Sweep exterior paved areas to a broom-clean condition; remove stains, petrochemical
spills and other foreign deposits.
Wipe surfaces of equipment clean. Remove excess lubrication and other substances.
Wet-mop concrete and clean other hard-surface floors according to manufacturers'
recommendations.
Vacuum clean carpeted surfaces and similar soft surfaces.
Clean plumbing fixtures to a sanitary condition, free of stains including those resulting
from water exposure.
Leave Project clean and ready for occupancy.

C.

Pest Control: Engage an experienced, licensed exterminator to make a final inspection and rid Project
of rodents, insects, and other pests. Prepare a report.

D.

Comply with safety standards for cleaning. Do not burn waste materials. Do not bury debris or excess
materials on Employer's property. Do not discharge volatile, harmful, or dangerous materials into
drainage systems. Remove waste materials from Project site and dispose of lawfully.

TESTS AFTER COMPLETION

CLOSEOUT PROCEDURES
Volume 2

01770 Page 5 of 6
May 2012

Saraya Aqaba

Specifications

A.

The Contractor shall perform all tests and inspections required in accordance with the specialized
Consultants recommendations / Operators Requirements / Operation and Maintenance Manuals to
ensure that the Marine Works / Water Park / Lagoon & Water Features and other Project elements are
functioning according to design, specifications, safety and Environmental regulations and fit for
purpose.

B.

Upon completion the Contractor shall obtain written acknowledgment from the Engineer that the
required tests are completed.

C.

Unless otherwise required or approved, the tests shall be given during the regular work week after the
equipment has been installed and turned over to the Employer for regular operation. Where
significant changes or modifications in equipment are made under the terms of the Contract,
additional tests shall be provided as may be necessary to acquaint the operating personnel of the
changes or modifications. Unless otherwise stated, at least half of the time allocated for tests shall be
"hands-on," using the actual system installed.

D.

The Contractor shall request re-test when the Work identified in previous tests as incomplete is
completed or corrected.

E.

Posting of operating tests, approved by the Engineer for each system and each principal piece of
equipment.

F.

The Contractor shall include wiring and control diagrams showing the complete layout of the entire
system including equipment, piping, valves, and control sequence framed under clear laminated
plastic, and posted where directed by the Engineer. Printed or engraved operating tests for each
principal piece of equipment including start-up, proper adjustment, operating lubrication, shut-down
safety precautions, procedure in the event of equipment failure, and any other necessary items of tests
as recommended by the manufacturer of the unit shall be attached to or posted adjacent to the piece of
equipment. Operating tests exposed to the weather or wet or humid conditions shall be made of
weather-resisting materials or shall be suitably framed and enclosed to be weather protected.
Operating tests shall not fade when exposed to sunlight and shall be secured to prevent easy removal
or peeling. The Contractor shall coordinate the location of posted tests with the Engineer.

G.

Each instructor shall be familiar with all parts of the system on which he or she is to give tests and
shall be knowledgeable about the systems' operation and required maintenance. Trained instructors,
who are certified, shall be employed wherever practical and available.

H.

Provision of equipment demonstrations for each equipment item. The Contractor shall coordinate
scheduling of all demonstrations through the Engineer.

END OF SECTION 01770

CLOSEOUT PROCEDURES
Volume 2

01770 Page 6 of 6
May 2012

Saraya Aqaba

Specifications

SECTION 01781 - PROJECT RECORD DOCUMENTS

PART 1 - GENERAL

1.1

RELATED DOCUMENTS
A.

1.2

Drawings and general provisions of the Contract, including General and Particular Conditions and
other Division 1 Specification Sections, apply to this Section.

SUMMARY
A.

This Section includes administrative and procedural requirements for Project Record Documents,
including the following:
1.
2.
3.

B.

1.3

Record Drawings.
Record Specifications.
Record Product Data.

Related Sections include the following:


1.
Division 1 Section "Closeout Procedures" for general closeout procedures.
2.
Divisions 2 through 16 Sections for specific requirements for Project Record Documents of
the Work in those Sections.

SUBMITTALS
A.

Record Drawings: Comply with the following:


1.

Number of Copies: Submit copies of Record Drawings as follows:


a.

b.

c.

Initial Submittal: Submit one set of plots from corrected Record CAD Drawings and
one set of marked-up Record Prints. Engineer will initial and date each plot and mark
whether general scope of changes, additional information recorded, and quality of
drafting are acceptable. Engineer will return plots and prints for organizing into sets,
printing, binding, and final submittal.
Final Submittal: Submit one set of marked-up Record Prints, one set of Record
Transparencies, and six copies printed from Record Transparencies. Print each
Drawing, whether or not changes and additional information were recorded.
Final Submittal: Submit one set of marked-up Record Prints, one set(s) of Record
CAD Drawing files, one set of Record CAD Drawing plots, and six copies printed
from record plots. Plot and print each Drawing, whether or not changes and additional
information were recorded.
1)

2.

Electronic Media: DVD or CD-R.

During the progress of the work the Contractor shall maintain a complete and up-to-date set of
As Built and Record prints, open to inspection by the Engineer at any time. These Drawings /
Prints shall provide a complete and accurate as-built record of all changes to the Contract
Drawings and Shop Drawings, including rerouting of runs, relocation of items or control
points, and all other modifications. The exact location of pipes, conduit, ducts or other features
concealed underground, under concrete, in chases, or above ceilings shall be shown by
perpendicular dimensions from at least two available landmarks. As Built drawings shall be
neatly marked with colored pencils or ink, marked "As-Built," and signed and dated by the
Contractor. In addition to CAD Drawings the Contractor shall submit to the Engineer scanned
color PDF files and produced as-built record drawings sized the same as the Contract
Drawings. As built drawings shall be for Architectural, Interior Design, Structural,
Mechanical, Electrical and all other engineering categories.

PROJECT RECORD DOCUMENTS


Volume 2

01781 Page 1 of 4
May 2012

Saraya Aqaba

3.

Specifications

The Contractor shall submit As-Built Survey and Drawings of all Underground Utilities
including those previously executed by other contractors employed by the Employer. The
Contractor shall furnish to the Engineer an acceptable and accurately dimensioned survey
showing location and elevation of underground storage tanks, all utility lines for water, gas,
electrical, sewer, chilled water, etc., including valves, connections and changes in direction, as
installed, within the property lines and outside the Buildings walls. Points where utility lines
emerge from the Buildings shall be located from lot monuments. The survey shall be made to
scale and same size as the contract drawings and shall be marked "As-Built" and signed and
dated by the Contractor.

B.

Record Specifications:
contract modifications.

Submit three copies of Project's Specifications, including addenda and

C.

Record Product Data: Submit three copies of each Product Data submittal.

D.

Electronic and hard copy documentation on all Project Elements and buildings systems should be
provided for the guidance of the buildings engineering staff and long-term Asset Management of the
Employer. Documents should show the actual elements that have been installed, how they performed
during testing, and how they operate as a system in the completed facility.

PART 2 - PRODUCTS

2.1

RECORD DRAWINGS
A.

Record Prints: Maintain one set of blue- or black-line white prints of the Contract Drawings and
Shop Drawings.
1.

Preparation: Mark Record Prints to show the actual installation where installation varies from
that shown originally. Require individual or entity who obtained record data, whether
individual or entity is Installer, subcontractor, or similar entity, to prepare the marked-up
Record Prints.
a.
b.
c.

2.

Content: Types of items requiring marking include, but are not limited to, the following:
a.
b.
c.
d.
e.
f.
g.
h.

3.

4.
5.

Give particular attention to information on concealed elements that would be difficult


to identify or measure and record later.
Accurately record information in an understandable drawing technique.
Record data as soon as possible after obtaining it. Record and check the markup before
enclosing concealed installations.

Dimensional changes to Drawings.


Revisions to details shown on Drawings.
Depths of foundations below first floor.
Changes made by Variation Order.
Changes made following Engineer's written Instructions.
Details not on the original Contract Drawings.
Field records for variable and concealed conditions.
Record information on the Work that is shown only schematically.

Mark the Contract Drawings or Shop Drawings, whichever is most capable of showing actual
physical conditions, completely and accurately. If Shop Drawings are marked, show crossreference on the Contract Drawings.
Mark record sets with erasable, red-colored pencil. Use other colors to distinguish between
changes for different categories of the Work at same location.
Mark important additional information that was either shown schematically or omitted from
original Drawings.

PROJECT RECORD DOCUMENTS


Volume 2

01781 Page 2 of 4
May 2012

Saraya Aqaba
6.

B.

Note alternate numbers, Variation Order numbers, and similar identification, where
applicable.

Record Transparencies: Before inspection for Taking-Over, review marked-up Record Prints with
Engineer. When authorized, prepare a full set of corrected transparencies of the Contract Drawings
and Shop Drawings.
1.
2.
3.

C.

Specifications

Incorporate changes and additional information previously marked on Record Prints. Erase,
redraw, and add details and notations where applicable.
Refer instances of uncertainty to Engineer for resolution.
Print the Contract Drawings and Shop Drawings for use as Record Transparencies. Engineer
will make the Contract Drawings available to Contractor's print shop.

Record CAD Drawings: Before inspection for Taking-Over, review marked-up Record Prints with
Engineer. When authorized, prepare a full set of corrected CAD Drawings of the Contract Drawings,
as follows:
1.
2.
3.
4.
5.

Format: Same CAD program, version, and operating system as the original Contract
Drawings.
Format: DWG, Version, operating in Microsoft Windows operating system.
Incorporate changes and additional information previously marked on Record Prints. Delete,
redraw, and add details and notations where applicable.
Refer instances of uncertainty to Engineer for resolution.
Engineer will furnish Contractor one set of CAD Drawings of the Contract Drawings for use
in recording information.
a.
b.

D.

Newly Prepared Record Drawings: Prepare new Drawings instead of preparing Record Drawings
where Engineer determines that neither the original Contract Drawings nor Shop Drawings are
suitable to show actual installation.
1.
2.

E.

Neither the Engineer nor the Employer makes any representations as to the accuracy or
completeness of CAD Drawings as they relate to the Contract Drawings.
CAD Software Program: The Contract Drawings are available in CAD program on
Windows XP operating system.

New Drawings may be required when a Variation Order is issued as a result of accepting an
alternate, substitution, or other modification.
Consult Engineer for proper scale and scope of detailing and notations required to record the
actual physical installation and its relation to other construction. Integrate newly prepared
Record Drawings into Record Drawing sets; comply with procedures for formatting,
organizing, copying, binding, and submitting.

Format: Identify and date each Record Drawing; include the designation "PROJECT RECORD
DRAWING" in a prominent location.
1.
2.

3.

4.

Record Prints: Organize Record Prints and newly prepared Record Drawings into manageable
sets. Bind each set with durable paper cover sheets. Include identification on cover sheets.
Record Transparencies: Organize into unbound sets matching Record Prints. Place
transparencies in durable tube-type drawing containers with end caps. Mark end cap of each
container with identification. If container does not include a complete set, identify Drawings
included.
Record CAD Drawings: Organize CAD information into separate electronic files that
correspond to each sheet of the Contract Drawings. Name each file with the sheet
identification. Include identification in each CAD file.
Identification: As follows:
a.
b.
c.
d.
e.

Project name.
Date.
Designation "PROJECT RECORD DRAWINGS."
Name of Contractor.
Name of Employer.

PROJECT RECORD DOCUMENTS


Volume 2

01781 Page 3 of 4
May 2012

Saraya Aqaba

Specifications
f.

2.2

Name of Engineer.

RECORD SPECIFICATIONS
A.

Preparation: Mark Specifications to indicate the actual product installation where installation varies
from that indicated in Specifications, addenda, and contract modifications.
1.
2.
3.
4.
5.

2.3

Give particular attention to information on concealed products and installations that cannot be
readily identified and recorded later.
Mark copy with the proprietary name and model number of products, materials, and
equipment furnished, including substitutions and product options selected.
Record the name of manufacturer, supplier, Installer, and other information necessary to
provide a record of selections made.
For each principal product, indicate whether Record Product Data has been submitted in
operation and maintenance manuals instead of submitted as Record Product Data.
Note related Variation Orders, Record Product Data, and Record Drawings where applicable.

RECORD PRODUCT DATA


A.

Preparation: Mark Product Data to indicate the actual product installation where installation varies
substantially from that indicated in Product Data submittal.
1.
2.
3.

2.4

Give particular attention to information on concealed products and installations that cannot be
readily identified and recorded later.
Include significant changes in the product delivered to Project site and changes in
manufacturer's written instructions for installation.
Note related Variation Orders, Record Specifications, and Record Drawings where applicable.

MISCELLANEOUS RECORD SUBMITTALS


A.

Assemble miscellaneous records required by other Specification Sections for miscellaneous record
keeping and submittal in connection with actual performance of the Work. Bind or file miscellaneous
records and identify each, ready for continued use and reference.

PART 3 - EXECUTION

3.1

RECORDING AND MAINTENANCE


A.

Recording: Maintain one copy of each submittal during the construction period for Project Record
Document purposes. Post changes and modifications to Project Record Documents as they occur; do
not wait until the end of Project.

B.

Maintenance of Record Documents and Samples: Store Record Documents and Samples in the field
office apart from the Contract Documents used for construction. Do not use Project Record
Documents for construction purposes. Maintain Record Documents in good order and in a clean, dry,
legible condition, protected from deterioration and loss. Provide access to Project Record Documents
for Engineer's reference during normal working hours.

END OF SECTION 01781

PROJECT RECORD DOCUMENTS


Volume 2

01781 Page 4 of 4
May 2012

Saraya Aqaba

Specifications

SECTION 01782 - OPERATION AND MAINTENANCE DATA

PART 1 - GENERAL

1.1

RELATED DOCUMENTS
A.

1.2

Drawings and general provisions of the Contract, including General and Particular Conditions and
other Division 1 Specification Sections, apply to this Section.

SUMMARY
A.

This Section includes administrative and procedural requirements for preparing operation and
maintenance manuals in both hard copies and soft copies, including the following:
1.
2.
3.
4.

B.

Operation and maintenance documentation directory.


Emergency manuals.
Operation manuals for systems, subsystems, and equipment.
Maintenance manuals for the care and maintenance of products, materials, and finishes
systems and equipment.

Related Sections include the following:


1.
2.
3.
4.

Division 1 Section "Submittal Procedures" for submitting copies of submittals for operation
and maintenance manuals.
Division 1 Section "Closeout Procedures" for submitting operation and maintenance manuals.
Division 1 Section "Project Record Documents" for preparing Record Drawings for operation
and maintenance manuals.
Divisions 2 through 16 Sections for specific operation and maintenance manual requirements
for the Work in those Sections.

C.

The warranty period, O&M training shall not start prior to the submittal / approval of the O&M
Manuals.

D.

The following requirements apply to both the new and existing Works regardless of who designed or
carried out the Works and whether such design or Works were approved.

1.3

DEFINITIONS
A.

System: An organized collection of parts, equipment, or subsystems united by regular interaction.

B.

Subsystem: A portion of a system with characteristics similar to a system.

1.4

SUBMITTALS
A.

Initial Submittal: Submit 3 draft copies in soft and hard format of each manual at least 35 days
before requesting inspection for Taking Over. Include a complete operation and maintenance
directory. Engineer will return one copy of draft and mark whether general scope and content of
manual are acceptable.

B.

Final Submittal: Submit 3 copies in soft and hard format of each manual in final form at least 21
days before requesting inspection for Taking Over. Engineer will return copy with comments within
14 days after inspection. Electronics manuals final submission should be subsequent to the final
approval of the hard copy.

OPERATION AND MAINTENANCE DATA


Volume 2

01782 Page 1 of 9
May 2012

Saraya Aqaba
1.

1.5

Specifications
Correct or modify each manual to comply with Engineer's comments. Submit 3 original sets
and 3 copies in soft and hard format of each corrected manual within 7 days of receipt of
Engineer's comments.

COORDINATION
A.

1.6

Where operation and maintenance documentation includes information on installations by more than
one factory-authorized service representative, assemble and coordinate information furnished by
representatives and prepare manuals.

QUALITY ASSURANCE
A.

The O&M manuals shall be compiled by a specialized firm with minimum of 10 years experience in
this field and on similar projects.

B.

The Contractor shall provide the necessary information, drawings, catalogues, data, etc and shall
keep the Engineer informed of any changes that affects the O&M manuals.

PART 2 - PRODUCTS

2.1

OPERATION AND MAINTENANCE DOCUMENTATION DIRECTORY


A.

Organization: Include a section in the directory for each of the following:


1.
2.
3.
4.

List of documents.
List of systems.
List of equipment.
Table of contents.

B.

List of Systems and Subsystems: List systems alphabetically. Include references to operation and
maintenance manuals that contain information about each system.

C.

List of Equipment: List equipment for each system, organized alphabetically by system. For pieces
of equipment not part of system, list alphabetically in separate list.

D.

Tables of Contents: Include a table of contents for each emergency, operation, and maintenance
manual.

E.

Identification: In the documentation directory and in each operation and maintenance manual,
identify each system, subsystem, and piece of equipment with same designation used in the Contract
Documents. If no designation exists, assign a designation according to ASHRAE Guideline 4,
"Preparation of Operating and Maintenance Documentation for Building Systems."

2.2

MANUALS, GENERAL
A.

General format:
1.
2.
3.
4.

Language: Simple, direct, universally accepted terminology and nomenclature shall be used to
facilitate comprehension.
Units of Measure: Units of measure shall be in Systems International d'Unites (SI units).
Tables and figures: shall be numbered consecutively by section.
Illustrations, tables, and drawings:
a.
b.

Illustrations, tables, and drawings necessary for clarity shall be included. All
illustrations, tables, and drawings shall be mentioned in the text.
Illustrations, tables, and drawings shall be numbered consecutively within each section
in the order mentioned 'in the text'. Each illustration, table, and drawing shall be placed

OPERATION AND MAINTENANCE DATA


Volume 2

01782 Page 2 of 9
May 2012

Saraya Aqaba

Specifications

c.

B.

Organization: Unless otherwise indicated, organize each manual into a separate section for each
system and subsystem, and a separate section for each piece of equipment not part of a system. Each
manual shall contain the following materials, in the order listed:
1.
2.
3.

C.

Subject matter included in manual.


Name and address of Project.
Name and address of Employer.
Name and address of Engineer.
Date of submittal.
Name, address, and telephone number of Contractor.
Name and address of Installer, subcontractors, suppliers, and manufacturers.
Cross-reference to related systems in other operation and maintenance manuals.

Table of Contents: List each product included in manual, identified by product name, indexed to the
content of the volume, and cross-referenced to Specification Section number in Project Manual.
1.

E.

Title page.
Table of contents.
Manual contents.

Title Page: Enclose title page in transparent plastic sleeve. Include the following information:
1.
2.
3.
4.
5.
6.
7.
8.

D.

as close as possible to the page of the text on which it is first mentioned or shall be
placed at the end of the applicable section, if appropriate to facilitate use.
Illustrations, tables and drawings contained in the body of the manual shall be black
and white.

If operation or maintenance documentation requires more than one volume to accommodate


data, include comprehensive table of contents for all volumes in each volume of the set.

Manual Contents: Organize into sets of manageable size. Arrange contents alphabetically by system,
subsystem, and equipment. If possible, assemble instructions for subsystems, equipment, and
components of one system into a single binder.
1.

Binders: Heavy-duty, 3-ring, vinyl-covered, loose-leaf binders, in thickness necessary to


accommodate contents, sized to hold A4 paper; with clear plastic sleeve on spine to hold label
describing contents and with pockets inside covers to hold folded oversize sheets.
a.

b.

2.

3.
4.
5.

If two or more binders are necessary to accommodate data of a system, organize data in
each binder into groupings by subsystem and related components. Cross-reference
other binders if necessary to provide essential information for proper operation or
maintenance of equipment or system.
Identify each binder on front and spine, with printed title "OPERATION AND
MAINTENANCE MANUAL," Project title or name, and subject matter of contents.
Indicate volume number for multiple-volume sets.

Dividers: Heavy-paper dividers with plastic-covered tabs for each section. Mark each tab to
indicate contents. Include typed list of products and major components of equipment included
in the section on each divider, cross-referenced to Specification Section number and title of
Project Manual.
Protective Plastic Sleeves: Transparent plastic sleeves designed to enclose diagnostic
software diskettes for computerized electronic equipment.
Supplementary Text: Prepared on A4 white bond paper.
Drawings: Attach reinforced, punched binder tabs on drawings and bind with text.
a.
b.

If oversize drawings are necessary, fold drawings to same size as text pages and use as
foldouts.
If drawings are too large to be used as foldouts, fold and place drawings in labeled
envelopes and bind envelopes in rear of manual. At appropriate locations in manual,
insert typewritten pages indicating drawing titles, descriptions of contents, and drawing
locations.

OPERATION AND MAINTENANCE DATA


Volume 2

01782 Page 3 of 9
May 2012

Saraya Aqaba
F.

Specifications

Contractual and Legal Guides:


1.

List the contractual and legal records of the installation which should include:
a.
b.
c.
d.
e.
f.

2.

For each item of plant and equipment installed within the building and contained in the list of
services covered by O&M manual, copies of the following documents should also be
provided, where applicable:
a.
b.
c.
d.
e.

3.

Test certificates.
Manufacturers guarantees and warranties.
Insurance inspection reports.
Safety and fire certificates.
Safety instructions.

A clear statement shall be made in this section concerning those hazards and safety
precautions of which the operators and maintainers of the installations need to be made aware.
This should include the following:
a.
b.
c.
d.
e.

G.

The name and address of the installation.


Details of ownership etc.
Details of local and public authority consent.
Details of the design teams, consultants, installation contractors and associated
subcontractors.
Dates for the start of the installation, for hand over (Taking Over) and for the expiry of
the defects liability period.
Information on all guarantees affecting components, systems and plant items, together
with expiry dates and names, addresses and telephone numbers of relevant contacts.

Any known feature or operational characteristic of the equipment or systems installed


which may produce a hazard.
Any known hazards against which protection can be provided.
Any mandatory requirements relating to safety.
Any other safety precautions which should be observed.
Any other relevant warnings.

Description: Provide a general overview of the original design intent and a detailed description of
each engineering system installed. It should include:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.

The parameters and conditions within which it has been designed to operate, including known
hazards.
The type of each service (gas, electricity, water) required to operate the system.
The intended method of control.
The system type (eg cold water supply).
The system location and what it serves.
What the system depends upon in order to function.
Design data, basic design parameters, basic assumptions made during design.
Reasons for selecting particular plant.
Expected service life (where available).
Planned operational efficiency.

H.

Equipment Schedule: The type, model number and serial number of all component items within the
system should be listed, together with the names of their respective manufacturers or suppliers.

I.

Commissioning Data: The results of all commissioning work and associated tests shall be included or
referred to. This shall include:
1.
2.
3.
4.
5.

Measured data.
Measurement points.
Test equipment used.
Calibration certificate details.
A statement of whether design requirements were achieved.

OPERATION AND MAINTENANCE DATA


Volume 2

01782 Page 4 of 9
May 2012

Saraya Aqaba
2.3

Specifications

EMERGENCY MANUALS
A.

Content: Organize manual into a separate section for each of the following:
1.
2.
3.

B.

Type of emergency.
Emergency instructions.
Emergency procedures.

Type of Emergency: Where applicable for each type of emergency indicated below, include
instructions and procedures for each system, subsystem, piece of equipment, and component:
1.
2.
3.
4.
5.
6.
7.
8.

Fire.
Flood.
Gas leak.
Water leak.
Power failure.
Water outage.
System, subsystem, or equipment failure.
Chemical release or spill.

C.

Emergency Instructions: Describe and explain warnings, trouble indications, error messages, and
similar codes and signals. Include responsibilities of Employer's and Operators operating personnel
for notification of Installer, supplier, and manufacturer to maintain warranties.

D.

Emergency Procedures: Include the following, as applicable:


1.
2.
3.
4.
5.

2.4

Instructions on stopping.
Shutdown instructions for each type of emergency.
Operating instructions for conditions outside normal operating limits.
Required sequences for electric or electronic systems.
Special operating instructions and procedures.

OPERATION MANUALS
A.

Content: In addition to requirements in this Section, include operation data required in individual
Specification Sections and the following information:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.

B.

Descriptions: Include the following:


1.
2.
3.
4.
5.
6.
7.
8.
9.

C.

System, subsystem, and equipment descriptions.


Performance and design criteria if Contractor is delegated design responsibility.
Operating standards.
Operating procedures.
Operating logs.
Wiring diagrams.
Control diagrams.
Piped system diagrams.
Precautions against improper use.
License requirements including inspection and renewal dates.

Product name and model number.


Manufacturer's name.
Equipment identification with serial number of each component.
Equipment function.
Operating characteristics.
Limiting conditions.
Performance curves.
Engineering data and tests.
Complete nomenclature and number of replacement parts.

Operating Procedures: Include the following, as applicable:

OPERATION AND MAINTENANCE DATA


Volume 2

01782 Page 5 of 9
May 2012

Saraya Aqaba

Specifications

1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.

Startup procedures.
Recommended strategy for operation and control
Outline of the general operating mode.
Equipment or system break-in procedures.
Routine and normal operating instructions.
Regulation and control procedures.
Instructions on stopping.
Normal shutdown instructions.
Seasonal and weekend operating instructions.
Required sequences for electric or electronic systems.
Special operating instructions and procedures.
Control data (location, effect, object, sequence, limits of capability, modes, set points).
Procedures and sequences for start-up, running and shut-down, under both normal and
emergency conditions.
Interlocks between plant items.
Operating procedures for stand-by plant.
Precautions necessary to overcome known hazards.
Means by which any potentially hazardous plant may be made safe.
Forms for recording plant running hours, energy consumption and energy costs.
Sequence of Operation (as applicable).

14.
15.
16.
17.
18.
19.
D.

Systems and Equipment Controls: Describe the sequence of operation, and diagram controls as
installed.

E.

Piped Systems: Diagram piping as installed, and identify color-coding where required for
identification.

2.5

PRODUCT MAINTENANCE MANUAL


A.

Content: Organize manual into a separate section for each product, material, and finish. Include
source information, product information, maintenance procedures, repair materials and sources, and
warranties and bonds, as described below.

B.

Source Information: List each product included in manual, identified by product name and arranged
to match manual's table of contents. For each product, list name, address, and telephone number of
Installer or supplier and maintenance service agent, and cross-reference Specification Section number
and title in Project Manual.

C.

Product Information: Include the following, as applicable:


1.
2.
3.
4.
5.

D.

Product name and model number.


Manufacturer's name.
Color, pattern, and texture.
Material and chemical composition.
Reordering information for specially manufactured products.

Maintenance Procedures: Include manufacturer's written recommendations and the following:


1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.

Inspection procedures.
Types of cleaning agents to be used and methods of cleaning.
List of cleaning agents and methods of cleaning detrimental to product.
Schedule for routine cleaning and maintenance.
Repair instructions.
Isolation and return to service of plant and equipment.
Adjustments, calibration and testing.
Dismantling and re-assembly.
Exchange of components and assemblies.
Dealing with hazards which may arise during maintenance.
Nature of deterioration and the defects to be looked for.
Special tools, test equipment and ancillary services.

OPERATION AND MAINTENANCE DATA


Volume 2

01782 Page 6 of 9
May 2012

Saraya Aqaba

Specifications

E.

Repair Materials and Sources: Include lists of materials and local sources of materials and related
services.

F.

Warranties and Bonds: Include copies of warranties and bonds and lists of circumstances and
conditions that would affect validity of warranties or bonds.
1.

2.6

Include procedures to follow and required notifications for warranty claims.

SYSTEMS AND EQUIPMENT MAINTENANCE MANUAL


A.

Content: For each system, subsystem, and piece of equipment not part of a system, include source
information, manufacturers' maintenance documentation, maintenance procedures, maintenance and
service schedules, spare parts list and source information, maintenance service contracts, and
warranty and bond information, as described below.

B.

Source Information: List each system, subsystem, and piece of equipment included in manual,
identified by product name and arranged to match manual's table of contents. For each product, list
name, address, and telephone number of Installer or supplier and maintenance service agent, and
cross-reference Specification Section number and title in Project Manual.

C.

Manufacturers' Maintenance Documentation: Manufacturers' maintenance documentation including


the following information for each component part or piece of equipment:
1.
2.
3.
4.

D.

Maintenance Procedures:
maintenance procedures:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.

E.

Standard printed maintenance instructions and bulletins.


Drawings, diagrams, and instructions required for maintenance, including disassembly and
component removal, replacement, and assembly.
Identification and nomenclature of parts and components.
List of items recommended to be stocked as spare parts.
Include the following information and items that detail essential

Test and inspection instructions.


Troubleshooting guide.
Precautions against improper maintenance.
Disassembly; component removal, repair, and replacement; and reassembly instructions.
Aligning, adjusting, and checking instructions.
Isolation and return to service of plant and equipment.
Adjustments, calibration and testing.
Dismantling and re-assembly.
Exchange of components and assemblies.
Dealing with hazards which may arise during maintenance.
Nature of deterioration and the defects to be looked for.
Special tools, test equipment and ancillary services.
Demonstration and training videotape, if available.

Maintenance and Service Schedules: Include service and lubrication requirements, list of required
lubricants for equipment, and separate schedules for preventive and routine maintenance and service
with standard time allotment.
1.
2.

Scheduled Maintenance and Service: Tabulate actions for daily, weekly, monthly, quarterly,
semiannual, and annual frequencies.
Maintenance and Service Record: Include manufacturers' forms for recording maintenance.

F.

Fault Finding: Procedures for the logical diagnosis correction of faults should be provided.

G.

Spare Parts List and Source Information: Include lists of replacement and repair parts, with parts
identified and cross-referenced to manufacturers' maintenance documentation and local sources of
maintenance materials and related services and equipment.

OPERATION AND MAINTENANCE DATA


Volume 2

01782 Page 7 of 9
May 2012

Saraya Aqaba

Specifications

H.

Maintenance Service Contracts: Include copies of maintenance agreements with name and telephone
number of service agent.

I.

Warranties and Bonds: Include copies of warranties and bonds and lists of circumstances and
conditions that would affect validity of warranties or bonds.
1.

Include procedures to follow and required notifications for warranty claims.

J.

Lubrication: A schedule of all plant/accessories/equipment requiring lubrication should be provided


together and method and frequency of application.

K.

Disposal Instructions: Where relevant, information should be provided detailing:


1.
2.
3.

Any known dangers likely to arise during the disposal.


Methods for safety disposing.
Sources from which further advice can be obtained.

PART 3 - EXECUTION

3.1

MANUAL PREPARATION
A.

Operation and Maintenance Documentation Directory: Prepare a separate manual that provides an
organized reference to emergency, operation, and maintenance manuals.

B.

Emergency Manual: Assemble a complete set of emergency information indicating procedures for
use by emergency personnel and by Employer's and Operators operating personnel for types of
emergencies indicated.

C.

Product Maintenance Manual: Assemble a complete set of maintenance data indicating care and
maintenance of each product, material, and finish incorporated into the Work.

D.

Operation and Maintenance Manuals: Assemble a complete set of operation and maintenance data
indicating operation and maintenance of each system, subsystem, and piece of equipment not part of
a system.
1.
2.

E.

Engage a factory-authorized service representative to assemble and prepare information for


each system, subsystem, and piece of equipment not part of a system.
Prepare a separate manual for each system and subsystem, in the form of an instructional
manual for use by Employer's and Operators operating personnel.

Manufacturers' Data: Where manuals contain manufacturers' standard printed data, include only
sheets pertinent to product or component installed. Mark each sheet to identify each product or
component incorporated into the Work. If data include more than one item in a tabular format,
identify each item using appropriate references from the Contract Documents. Identify data
applicable to the Work and delete references to information not applicable.
1.

Prepare supplementary text if manufacturers' standard printed data are not available and where
the information is necessary for proper operation and maintenance of equipment or systems.

F.

Names and addresses of manufacturers and their local representatives should be provided in details
along with all references.

G.

Drawings: Prepare drawings supplementing manufacturers' printed data to illustrate the relationship
of component parts of equipment and systems and to illustrate control sequence and flow diagrams.
Coordinate these drawings with information contained in Record Drawings to ensure correct
illustration of completed installation.
1.
2.

Do not use original Project Record Documents as part of operation and maintenance manuals.
Comply with requirements of newly prepared Record Drawings in Division 1 Section "Project
Record Documents."

OPERATION AND MAINTENANCE DATA


Volume 2

01782 Page 8 of 9
May 2012

Saraya Aqaba

Specifications

H.

Comply with Division 1 Section "Closeout Procedures" for schedule for submitting operation and
maintenance documentation.

I.

Electronic Version:
1.

2.
3.

4.

Upon notification from the Engineer that the final review is complete and that the O&M
manuals are complete and satisfactory, the Contractor shall prepare and submit to the Engineer
the final manuals in a standard CD/DVD Rom format. The Contractor shall submit two copies
of each CD/DVD complete for all manual and drawings (AutoCAD format).
All data/catalogues/images/tables etc should be included in the CD/DVD.
A table of contents shall be incorporated on the CD/DVD and shall be the key documents for
the structure of the CD/DVD. All volumes divisions, sections and sub-sections of the manuals
as well as drawings shall be addressed from this document and every entry in the table of
contents shall contain hypertexts link to the corresponding volume, section or chapter of the
manuals. The user shall be able with one key stroke to return to the table of contents from any
page of the manuals and shall be able to quick search for any requested section or division.
The electronic version of the O&M manuals shall include also all the as-built drawings of the
project.

END OF SECTION 01782

OPERATION AND MAINTENANCE DATA


Volume 2

01782 Page 9 of 9
May 2012

Saraya Aqaba

Specifications

SECTION 01810 - GENERAL COMMISSIONING REQUIREMENTS

PART 1 - GENERAL

1.1

RELATED DOCUMENTS
A.

1.2

Drawings and general provisions of the Contract, including General and Particular Conditions and
other Division 1 Specification Sections, apply to this Section.

SUMMARY
A.

This Section includes general requirements that apply to implementation of commissioning without
regard to systems, subsystems, and equipment being commissioned.

B.

Related Sections include the following:


1.

C.

1.3

The following requirements apply to both the new and existing Works regardless of who designed or
carried out the Works and whether such design or Works were approved.

DEFINITIONS
A.

BoD: Basis of Design.

B.

CxA: Commissioning Authority: Authorities or Approved Third Party (whichever is applicable).


Employer has the right to engage, at the Contractors Cost, the CxA under a separate contract.

C.

OPR: Employer's Requirements, Operators Requirements, and Contract Requirements.

D.

Systems, Subsystems, and Equipment: Where these terms are used together or separately, they shall
mean "as-built" systems, subsystems, and equipment.

E.

TAB: Testing, Adjusting, and Balancing.

1.4

COMMISSIONING TEAM
A.

Members Appointed by Contractor(s): Individuals, each having authority to act on behalf of the
entity he or she represents, explicitly organized to implement the commissioning process through
coordinated actions. The commissioning team shall consist of, but not be limited to, representatives
of Contractor, including Project superintendent and subcontractors, installers, suppliers, and
specialists deemed appropriate by the CxA.

B.

Members Appointed by Engineer, Employer, Operators, and their Consultants:


1.
2.
3.

1.5

Division 1 Section "HVAC Commissioning Requirements" for specific requirements for


commissioning HVAC systems.

CxA: The designated person, company, or entity that plans, schedules, and coordinates the
commissioning team to implement the commissioning process.
Representatives of the facility user and operation and maintenance personnel.
Engineer, Employer, Operators, other consultants appointed by them, and engineering design
professionals.

ENGINEER'S RESPONSIBILITIES

GENERAL COMMISSIONING REQUIREMENTS


Volume 2

01810 Page 1 of 7
May 2012

Saraya Aqaba

Specifications

A.

Provide the OPR documentation to the CxA and Contractor for use in developing the commissioning
plan; systems manual; operation and maintenance training plan; and testing plans and checklists.

B.

In coordination with the Employer, Operators, and other Consultants, assign operation and
maintenance personnel and schedule them to participate in commissioning team activities including,
but not limited to, the following:
1.
2.
3.
4.

Coordination meetings.
Training in operation and maintenance of systems, subsystems, and equipment.
Testing meetings.
Demonstration of operation of systems, subsystems, and equipment.

C.

Provide, at the Contractors Cost, utility services required for the commissioning process.

D.

Provide the BoD documents, prepared by Employers designers and approved by Employer, to the
CxA and Contractor for use in developing the commissioning plan, systems manual, and operation
and maintenance training plan.

1.6

CONTRACTOR'S RESPONSIBILITIES
A.

Provide utility services required for the commissioning process.

B.

Provide the BoD documents, prepared by the Contractor or its designers and approved by
Engineer/Employer, to the CxA and Engineer for use in developing the commissioning plan, systems
manual, and operation and maintenance training plan.

C.

Contractor shall assign representatives with expertise and authority to act on behalf of the Contractor
and schedule them to participate in and perform commissioning team activities including, but not
limited to, the following:
1.
2.
3.
4.
5.
6.
7.

D.

Participate in design- and construction-phase coordination meetings.


Participate in maintenance orientation and inspection.
Participate in operation and maintenance training sessions.
Participate in final review at acceptance meeting.
Certify that Work is complete and systems are operational according to the Contract
Documents, including calibration of instrumentation and controls.
Evaluate performance deficiencies identified in test reports and, in collaboration with entity
responsible for system and equipment installation, recommend corrective action.
Review and approve final commissioning documentation.

Subcontractors shall assign representatives with expertise and authority to act on behalf of
subcontractors and schedule them to participate in and perform commissioning team activities
including, but not limited to, the following:
1.
2.
3.
4.
5.

6.
7.
8.
9.
10.

Participate in design- and construction-phase coordination meetings.


Participate in maintenance orientation and inspection.
Participate in procedures meeting for testing.
Participate in final review at acceptance meeting.
Provide schedule for operation and maintenance data submittals, equipment startup, and
testing to CxA for incorporation into the commissioning plan. Update schedule on a weekly
basis throughout the construction period.
Provide information to the CxA for developing construction-phase commissioning plan.
Participate in training sessions for Employer's and Operators operation and maintenance
personnel.
Provide updated Project Record Documents to the CxA on a daily basis.
Gather and submit operation and maintenance data for systems, subsystems, and equipment to
the CxA, as specified in Division 1 Section "Operation and Maintenance Data."
Provide technicians who are familiar with the construction and operation of installed systems
and who shall develop specific test procedures and participate in testing of installed systems,
subsystems, and equipment.

GENERAL COMMISSIONING REQUIREMENTS


Volume 2

01810 Page 2 of 7
May 2012

Saraya Aqaba
1.7

1.8

Specifications

CxA'S RESPONSIBILITIES
A.

Organize and lead the commissioning team.

B.

Prepare a construction-phase commissioning plan. Collaborate with Contractor and with


subcontractors to develop test and inspection procedures. Include design changes and scheduled
commissioning activities coordinated with overall Project schedule. Identify commissioning team
member responsibilities, by name, firm, and trade specialty, for performance of each commissioning
task.

C.

Review and comment on submittals from Contractor for compliance with the OPR, BoD, Contract
Documents, and construction-phase commissioning plan. Review and comment on performance
expectations of systems and equipment and interfaces between systems relating to the OPR and BoD.

D.

Convene commissioning team meetings for the purpose of coordination, communication, and conflict
resolution; discuss progress of the commissioning processes. Responsibilities include arranging for
facilities, preparing agenda and attendance lists, and notifying participants. The CxA shall prepare
and distribute minutes to commissioning team members and attendees within five workdays of the
commissioning meeting.

E.

At the beginning of the construction phase, conduct an initial construction-phase coordination


meeting for the purpose of reviewing the commissioning activities and establishing tentative
schedules for operation and maintenance submittals; operation and maintenance training sessions;
TAB Work; and Project completion.

F.

Observe and inspect construction and report progress and deficiencies. In addition to compliance with
the OPR, BoD, and Contract Documents, inspect systems and equipment installation for adequate
accessibility for maintenance and component replacement or repair.

G.

Prepare Project-specific test and inspection procedures and checklists.

H.

Schedule, direct, witness, and document tests, inspections, and systems startup.

I.

Compile test data, inspection reports, and certificates and include them in the systems manual and
commissioning report.

J.

Certify date of acceptance and startup for each item of equipment for start of warranty periods.

K.

Review Project Record Documents for accuracy. Request revisions from Contractor to achieve
accuracy. Project Record Documents requirements are specified in Division 1 Section "Project
Record Documents."

L.

Review and comment on operation and maintenance documentation and systems manual outline for
compliance with the OPR, BoD, and Contract Documents. Operation and maintenance
documentation requirements are specified in Division 1 Section "Operation and Maintenance Data."

M.

Prepare operation and maintenance training program and provide qualified instructors to conduct
operation and maintenance training. Operation and maintenance training is specified in Division 1
Section "Demonstration and Training."

N.

Videotape and edit training sessions.

O.

Videotape construction progress including hidden shafts.

P.

Prepare commissioning reports.

Q.

Assemble the final commissioning documentation, including the commissioning report and Project
Record Documents.

COMMISSIONING DOCUMENTATION

GENERAL COMMISSIONING REQUIREMENTS


Volume 2

01810 Page 3 of 7
May 2012

Saraya Aqaba

Specifications

A.

Index of Commissioning Documents: CxA shall prepare an index to include storage location of each
document.

B.

OPR: A written document that details the functional requirements of Project and expectations of how
it will be used and operated. This document includes Project and design goals, measurable
performance criteria, budgets, schedules, success criteria, and supporting information.

C.

BoD Document: A written document that records concepts, calculations, decisions, and product
selections used to meet the OPR and to satisfy applicable regulatory requirements, standards, and
guidelines. The document includes both narrative descriptions and lists of individual items that
support the design process.

D.

Commissioning Plan: A document, prepared by CxA, that outlines the schedule, allocation of
resources, and documentation requirements of the commissioning process, and shall include, but is
not limited to the following:
1.

2.

3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.

E.

Plan for delivery and review of submittals, systems manuals, and other documents and reports.
Identification of the relationship of these documents to other functions and a detailed
description of submittals that are required to support the commissioning processes. Submittal
dates shall include the latest date approved submittals must be received without adversely
affecting commissioning plan.
Description of the organization, layout, and content of commissioning documentation
(including systems manual) and a detailed description of documents to be provided along with
identification of responsible parties.
Identification of systems and equipment to be commissioned.
Description of schedules for testing procedures along with identification of parties involved in
performing and verifying tests.
Identification of items that must be completed before the next operation can proceed.
Description of responsibilities of commissioning team members.
Description of observations to be made.
Description of requirements for operation and maintenance training, including required
training materials.
Description of expected performance for systems, subsystems, equipment, and controls.
Schedule for commissioning activities with specific dates coordinated with overall
construction schedule.
Identification of installed systems, subsystems, and equipment, including design changes that
occurred during the construction phase.
Process and schedule for documenting changes on a continuous basis to appear in Project
Record Documents.
Process and schedule for completing prestart and startup checklists for systems, subsystems,
and equipment to be verified and tested.
Step-by-step procedures for testing systems, subsystems, and equipment with descriptions for
methods of verifying relevant data, recording the results obtained, and listing parties involved
in performing and verifying tests.

Test Checklists: CxA, with assistance of Engineer, shall develop test checklists for each system,
subsystem, or equipment including interfaces and interlocks, and include a separate entry, with space
for comments, for each item to be tested. Prepare separate checklists for each mode of operation and
provide space to indicate whether the mode under test responded as required. Provide space for
testing personnel to sign off on each checklist. Specific checklist content requirements are specified
in Division 1 Section "HVAC Commissioning Requirements." Each checklist, regardless of system,
subsystem, or equipment being tested, shall include, but not be limited to, the following:
1.
2.
3.
4.
5.
6.
7.
8.

Name and identification code of tested item.


Test number.
Time and date of test.
Indication of whether the record is for a first test or retest following correction of a problem or
issue.
Dated signatures of the person performing test and of the witness, if applicable.
Individuals present for test.
Deficiencies.
Issue number, if any, generated as the result of test.

GENERAL COMMISSIONING REQUIREMENTS


Volume 2

01810 Page 4 of 7
May 2012

Saraya Aqaba

Specifications

F.

Certificate of Readiness: Certificate of Readiness shall be signed by each Contractor,


Subcontractor(s), Installer(s), and CxA certifying that systems, subsystems, equipment, and
associated controls are ready for testing. Completed test checklists signed by the responsible parties
shall accompany this certificate.

G.

Test and Inspection Reports: CxA shall record test data, observations, and measurements on test
checklists. Photographs, forms, and other means appropriate for the application shall be included
with data. CxA shall compile test and inspection reports and test and inspection certificates and
include them in systems manual and commissioning report.

H.

Corrective Action Documents: CxA shall document corrective action taken for systems and
equipment that fail tests. Include required modifications to systems and equipment and revisions to
test procedures, if any. Retest systems and equipment requiring corrective action and document retest
results.

I.

Issues Log: CxA shall prepare and maintain an issues log that describes design, installation, and
performance issues that are at variance with the OPR, BoD, and Contract Documents. Identify and
track issues as they are encountered, documenting the status of unresolved and resolved issues.
1.

Creating an Issues Log Entry:


a.
b.
c.
d.
e.
f.
g.
h.
i.
j.
k.

2.

Documenting Issue Resolution:


a.
b.
c.
d.
e.
f.

3.

Log date correction is completed or the issue is resolved.


Describe corrective action or resolution taken. Include description of diagnostic steps
taken to determine root cause of the issue, if any.
Identify changes to the OPR, BoD, or Contract Documents that may require action.
State that correction was completed and system, subsystem, and equipment is ready for
retest, if applicable.
Identify person(s) who corrected or resolved the issue.
Identify person(s) documenting the issue resolution.

Issues Log Report: On a periodic basis, but not less than for each commissioning team
meeting, CxA shall prepare a written narrative for review of outstanding issues and a status
update of the issues log. As a minimum, CxA shall include the following information in the
issues log and expand it in the narrative:
a.
b.
c.
d.

J.

Identify the issue with unique numeric or alphanumeric identifier by which the issue
may be tracked.
Assign a descriptive title of the issue.
Identify date and time of the issue.
Identify test number of test being performed at the time of the observation, if
applicable, for cross-reference.
Identify system, subsystem, and equipment to which the issue applies.
Identify location of system, subsystem, and equipment.
Include information that may be helpful in diagnosing or evaluating the issue.
Note recommended corrective action.
Identify commissioning team member responsible for corrective action.
Identify expected date of correction.
Identify person documenting the issue.

Issue number and title.


Date of the identification of the issue.
Name of the commissioning team member assigned responsibility for resolution.
Expected date of correction.

Commissioning Report: CxA shall document results of the commissioning process including
unresolved issues and performance of systems, subsystems, and equipment. The commissioning
report shall indicate whether systems, subsystems, and equipment have been completed and are
performing according to the OPR, BoD, and Contract Documents. The commissioning report shall
include, but is not limited to, the following:

GENERAL COMMISSIONING REQUIREMENTS


Volume 2

01810 Page 5 of 7
May 2012

Saraya Aqaba
1.

2.
3.
4.
5.
6.
7.
8.
K.

Lists and explanations of substitutions; compromises; variances in the OPR, BoD, and
Contract Documents; record of conditions; and, if appropriate, recommendations for
resolution. This report shall be used to evaluate systems, subsystems, and equipment and shall
serve as a future reference document during Employers and Operators occupancy and
operation. It shall describe components and performance that exceed requirements of the
OPR, BoD, and Contract Documents and those that do not meet requirements of the OPR,
BoD, and Contract Documents. It may also include a recommendation for accepting or
rejecting systems, subsystems, and equipment.
OPR and BoD documentation.
Commissioning plan.
Testing plans and reports.
Corrective modification documentation.
Issues log.
Completed test checklists.
Listing of off-season test(s) not performed and a schedule for their completion.

Systems Manual: CxA shall gather required information and compile systems manual. Systems
manual shall include, but is not limited to, the following:
1.
2.
3.
4.
5.

1.9

Specifications

OPR and BoD, including system narratives, schematics, and changes made throughout the
Project.
Project Record Documents as specified in Division 1 Section "Project Record Documents."
Final commissioning plan.
Commissioning report.
Operation and maintenance data as specified in Division 1 Section "Operation and
Maintenance Data."

SUBMITTALS
A.

Commissioning Plan Pre-final Submittal: CxA shall submit four hard copies of pre-final
commissioning plan. Deliver one copy to Contractor, and three copies to Engineer. Present
submittal in sufficient detail to evaluate data collection and arrangement process. One copy, with
review comments, will be returned to the CxA for preparation of the final construction-phase
commissioning plan.

B.

Commissioning Plan Final Submittal: CxA shall submit four hard copies and four sets of
electronically formatted information of final commissioning plan. Deliver three hard copies and
three sets of discs to Engineer. The final submittal must address previous review comments. The
final submittal shall include a copy of the pre-final submittal review comments along with a response
to each item.

C.

Test Checklists and Report Forms: CxA shall submit sample checklists and forms to Contractor
quality-control manager and subcontractors for review and comment. Submit four copies of each
checklist and report form.

D.

Certificates of Readiness: CxA shall submit Certificates of Readiness.

E.

Test and Inspection Reports: CxA shall submit test and inspection reports.

F.

Corrective Action Documents: CxA shall submit corrective action documents.

G.

Pre-final Commissioning Report Submittal: CxA shall submit four hard copies of the pre-final
commissioning report. Include a copy of the preliminary submittal review comments along with
CxA's response to each item. CxA shall deliver three copies to Engineer. One copy, with review
comments, will be returned to the CxA for preparation of final submittal.

H.

Final Commissioning Report Submittal: CxA shall submit four hard copies and four sets of
electronically formatted information of the final commissioning report. CxA shall deliver three hard
copies and three sets of discs to Engineer. The final submittal must address previous review
comments and shall include a copy of the pre-final submittal review comments along with a response
to each item.

GENERAL COMMISSIONING REQUIREMENTS


Volume 2

01810 Page 6 of 7
May 2012

Saraya Aqaba
1.10

Specifications

QUALITY ASSURANCE

A.

Instructor Qualifications: Factory-authorized service representatives, experienced in training,


operation, and maintenance procedures for installed systems, subsystems, and equipment.

B.

Test Equipment Calibration: Comply with test equipment manufacturer's calibration procedures and
intervals. Recalibrate test instruments immediately whenever instruments have been repaired
following damage or dropping. Affix calibration tags to test instruments. Instruments shall have
been calibrated within six months prior to use.

1.11

COORDINATION

A.

Coordinating Meetings: CxA shall conduct weekly coordination meetings of the commissioning team
to review progress on the commissioning plan, to discuss scheduling conflicts, and to discuss
upcoming commissioning process activities.

B.

Pretesting Meetings: CxA shall conduct pretest meetings of the commissioning team to review startup
reports, pretest inspection results, testing procedures, testing personnel and instrumentation
requirements, and manufacturers' authorized service representative services for each system,
subsystem, equipment, and component to be tested.

C.

Testing Coordination: CxA shall coordinate sequence of testing activities to accommodate required
quality-assurance and -control services with a minimum of delay and to avoid necessity of removing
and replacing construction to accommodate testing and inspecting.
1.

D.

Schedule times for tests, inspections, obtaining samples, and similar activities.

Manufacturers' Field Services: CxA shall coordinate services of manufacturers' field services.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1

OPERATION AND MAINTENANCE TRAINING REQUIREMENTS


A.

Training Preparation Conference: Before operation and maintenance training, CxA shall convene a
training preparation conference to include Employer's and Operators operation and maintenance
personnel, Contractor, and subcontractors. In addition to requirements specified in Division 1
Section "Demonstration and Training," perform the following:
1.
2.
3.
4.
5.
6.
7.
8.
9.

B.

Review the OPR and BoD.


Review installed systems, subsystems, and equipment.
Review instructor qualifications.
Review instructional methods and procedures.
Review training module outlines and contents.
Review course materials (including operation and maintenance manuals).
Inspect and discuss locations and other facilities required for instruction.
Review and finalize training schedule and verify availability of educational materials,
instructors, audiovisual equipment, and facilities needed to avoid delays.
For instruction that must occur outside, review weather and forecasted weather conditions and
procedures to follow if conditions are unfavorable.

Training Modules: Develop an instruction program that includes individual training modules for each
system, subsystem, and equipment as specified in Division 1 Section "Demonstration and Training."

END OF SECTION 01810


GENERAL COMMISSIONING REQUIREMENTS
Volume 2

01810 Page 7 of 7
May 2012

Saraya Aqaba

Specifications

SECTION 01815 - HVAC COMMISSIONING REQUIREMENTS

PART 1 - GENERAL

1.1

RELATED DOCUMENTS
A.

1.2

Drawings and general provisions of the Contract, including General and Particular Conditions and
other Division 1 Specification Sections, apply to this Section.

SUMMARY
A.

This Section includes requirements for commissioning the HVAC system and its subsystems and
equipment. This Section supplements the general requirements specified in Division 1 Section
"General Commissioning Requirements."

B.

Related Sections include the following:


1.

C.

1.3

Division 1 Section "General Commissioning Requirements" for general requirements for


commissioning processes that apply to this Section.

The following requirements apply to both the new and existing Works regardless of who designed or
carried out the Works and whether such design or Works were approved.

STANDARDS
A.

1.4

All works and procedures shall comply to the latest editions either of National standards for total
systems balance (AABC) or National environmental balancing bureau (NEBB) in case of conflict
between applied standards requirements and specs, the standard requirements have the priority.

DEFINITIONS
A.

BoD: Basis of Design.

B.

BoD-HVAC: HVAC systems basis of design.

C.

CxA: Commissioning Authority: Authorities and / or Approved Third Party (whichever is


applicable). Employer has the right to engage, at the Contractors Cost, the CxA under a separate
contract.

D.

OPR: Employer's Requirements, Operators Requirements, and Contract Requirements.

E.

Systems, Subsystems, and Equipment: Where these terms are used together or separately, they shall
mean "as-built" systems, subsystems, and equipment.

F.

TAB: Testing, Adjusting, and Balancing.

1.5

CONTRACTOR'S RESPONSIBILITIES
A.

The following responsibilities are in addition to those specified in Division 1 Section "General
Commissioning Requirements."

B.

Contractor:
1.

Attend procedures meeting for TAB Work.

HVAC COMMISSIONING REQUIREMENTS


Volume 2

01815 Page 1 of 7
May 2012

Saraya Aqaba
2.
C.

Specifications
Certify that TAB Work is complete.

Mechanical Subcontractor:
1.
2.

Attend TAB verification testing.


Provide measuring instruments and logging devices to record test data, and data acquisition
equipment to record data for the complete range of testing for the required test period.

D.

HVAC Instrumentation and Control Subcontractor: With the CxA, review control designs for
compliance with the OPR and BoD, controllability with respect to actual equipment to be installed,
and recommend adjustments to control designs and sequence of operation descriptions.

E.

TAB Subcontractor:
1.

Contract Documents Review: With the CxA, review the Contract Documents before
developing TAB procedures.
a.

Verify the following:


1)
2)
3)
4)

5)

b.
c.

2.

F.

Identify discontinuities and omissions in the Contract Documents.


This review of the Contract Documents by the TAB Subcontractor satisfies
requirements for a design review report as specified in Division 15 Section "Testing,
Adjusting, and Balancing."

Additional Responsibilities: Participate in tests specified in Division 15 Sections "HVAC


Instrumentation and Controls" and "Sequence of Operation."

Electrical Subcontractor:
1.
2.

1.6

Accessibility of equipment and components required for TAB Work.


Adequate number and placement of duct balancing dampers to allow proper
balancing while minimizing sound levels in occupied spaces.
Adequate number and placement of balancing valves to allow proper balancing
and recording of water flow.
Adequate number and placement of test ports and test instrumentation to allow
reading and compilation of system and equipment performance data needed to
conduct both TAB and commissioning testing.
Air and water flow rates have been specified and compared to central
equipment output capacities.

With the Mechanical Subcontractor, coordinate installations and connections between and
among electrical and HVAC systems, subsystems, and equipment.
Attend TAB verification testing.

COMMISSIONING DOCUMENTATION
A.

The following are in addition to documentation specified in Division 1 Section "General


Commissioning Requirements."

B.

BoD HVAC: Engineer will provide BoD-HVAC documents, prepared by Employers designers and
approved by Employer, to the CxA and Contractor for use in developing the commissioning plan,
systems manual, and operation and maintenance training plan.

C.

BoD HVAC: Contractor will provide BoD-HVAC documents, prepared by the Contractor or its
designers and approved by Employer, to the CxA and Engineer for use in developing the
commissioning plan, systems manual, and operation and maintenance training plan.

D.

Test Checklists: CxA with assistance of Engineer shall develop test checklists for HVAC systems,
subsystems, and equipment, including interfaces and interlocks with other systems. CxA shall prepare
separate checklists for each mode of operation and provide space to indicate whether the mode under

HVAC COMMISSIONING REQUIREMENTS


Volume 2

01815 Page 2 of 7
May 2012

Saraya Aqaba

Specifications

test responded as required. In addition to the requirements specified in Division 1 Section "General
Commissioning Requirements," checklists shall include, but not be limited to, the following:
1.
2.

3.
4.
5.
6.
7.
8.
9.
10.
11.
12.

1.7

Calibration of sensors and sensor function.


Testing conditions under which test was conducted, including (as applicable) ambient
conditions, set points, override conditions, and status and operating conditions that impact the
results of test.
Control sequences for HVAC systems.
Strength of control signal for each set point at specified conditions.
Responses to control signals at specified conditions.
Sequence of response(s) to control signals at specified conditions.
Electrical demand or power input at specified conditions.
Power quality and related measurements.
Expected performance of systems, subsystems, and equipment at each step of test.
Narrative description of observed performance of systems, subsystems, and equipment.
Notation to indicate whether the observed performance at each step meets the expected results.
Interaction of auxiliary equipment.
Issues log.

SUBMITTALS
A.

The following submittals are in addition to those specified in Division 1 Section "General
Commissioning Requirements."

B.

Testing Procedures: CxA shall submit detailed testing plan, procedures, and checklists for each series
of tests. Submittals shall include samples of data reporting sheets that will be part of the reports.

C.

Certificate of Readiness: CxA shall compile certificates of readiness from Contractor certifying that
systems, subsystems, equipment, and associated controls are ready for testing.

D.

Certificate of Completion of Installation, Prestart, and Startup: CxA shall certify that installation,
prestart, and startup activities have been completed. Certification shall include completed checklists
provided by TAB Subcontractor as specified in Division 15 Section "Testing, Adjusting, and
Balancing."

E.

Certified Pipe Cleaning and Flushing Report: CxA shall certify that pipe cleaning, flushing,
hydrostatic testing, and chemical treating have been completed.

F.

Test and Inspection Reports: CxA shall compile and submit test and inspection reports and
certificates, and shall include them in systems manual and commissioning report.

G.

Corrective Action Documents: CxA shall submit corrective action documents.

H.

Certified TAB Reports: CxA shall submit verified, certified TAB reports.

PART 2 - PRODUCTS

2.1

TAB AND COMMISSIONING


A.

Contractor shall submit to the Engineer prior to any words the list of instruments and tools used for
TAB activity along with the calibration certificate for each instrument and tool.

B.

Calibration and maintenance of instruments shall be in accordance with the applicable standard
requirements.

C.

Instruments used in the performance of the work must have been calibrated within 3 months
preceding the date of usage. Calibration history for each instrument shall be available for
examination.

HVAC COMMISSIONING REQUIREMENTS


Volume 2

01815 Page 3 of 7
May 2012

Saraya Aqaba

Specifications

D.

Instruments should be recalibrated when calibration certificate is expired. The Contractor is not
allowed to use any instrument having an expired calibration certificate.

E.

Accuracy of measurements shall amply with the applied standard requirements.

F.

All the above should be approved by the Engineer prior to any work commencement.

PART 3 - EXECUTION

3.1

TESTING PREPARATION
A.

Prerequisites for Testing:


1.

2.

3.
4.
5.

6.
7.

8.
9.
10.

Certify that HVAC systems, subsystems, and equipment have been completed, calibrated, and
started; are operating according to the OPR, BoD, and Contract Documents; and that
Certificates of Readiness are signed and submitted.
Certify that HVAC instrumentation and control systems have been completed and calibrated;
are operating according to the OPR, BoD, and Contract Documents; and that pretest set points
have been recorded.
Certify that TAB procedures have been completed, and that TAB reports have been submitted,
discrepancies corrected, and corrective work submitted and approved by the Engineer.
Test systems and intersystem performance after approval of test checklists for systems,
subsystems, and equipment.
Set systems, subsystems, and equipment into operating mode to be tested (e.g., normal shut
down, normal auto position, normal manual position, unoccupied cycle, emergency power,
and alarm conditions).
Verify each operating cycle after it has been running for a specified period and is operating in
a steady-state condition.
Inspect and verify the position of each device and interlock identified on checklists. Sign off
each item as acceptable, or failed. Repeat this test for each operating cycle that applies to
system being tested.
Check safety cutouts, alarms, and interlocks with smoke control and life-safety systems during
each mode of operation.
Annotate checklist or data sheet when a deficiency is observed.
Verify equipment interface with monitoring and control system and TAB criteria; include the
following:
a.
b.
c.
d.

11.

Verify proper responses of monitoring and control system controllers and sensors to include
the following:
a.

b.
12.

B.

Operation of terminal units in both heating and cooling cycles.


Minimum outdoor-air intake in each operational mode and at minimum and maximum
airflows.
Total exhaust airflow and total outdoor-air intake.
Operation of indoor-air-quality monitoring systems.

For each controller or sensor, record the indicated monitoring and control system
reading and the test instrument reading. If initial test indicates that the test reading is
outside of the control range of the installed device, check calibration of the installed
device and adjust as required. Retest malfunctioning devices and record results on
checklist or data sheet.
Report deficiencies and prepare an issues log entry.

Verify that HVAC equipment field quality-control testing has been completed and approved.
CxA shall direct, witness, and document field quality-control tests, inspections, and startup
specified in individual Division 15 Sections.

Testing Instrumentation: Install measuring instruments and logging devices to record test data for the
required test period. Instrumentation shall monitor and record full range of operating conditions and
shall allow for calculation of total capacity of system for each mode of operation. For individual

HVAC COMMISSIONING REQUIREMENTS


Volume 2

01815 Page 4 of 7
May 2012

Saraya Aqaba

Specifications

room cooling tests, provide temporary heaters to impose a cooling load indicated in BoD.
Operational modes include the following:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.

3.2

Occupied and unoccupied.


Warm up and cool down.
Economizer cycle.
Emergency power supply.
Life-safety and safety systems.
Smoke control.
Fire safety.
Temporary upset of system operation.
Partial occupancy conditions.
Special cycles.

TAB VERIFICATION
A.

TAB Subcontractor shall coordinate with CxA for work required in Division 15 Section "Testing,
Adjusting, and Balancing." TAB Subcontractor shall copy CxA with required reports, sample forms,
checklists, and certificates.

B.

Contractor, HVAC Subcontractor, and CxA shall witness TAB Work.

C.

TAB Preparation:
1.

TAB Subcontractor shall provide CxA with data required for "Pre-Field TAB Engineering
Reports" specified in Division 15 Section "Testing, Adjusting, and Balancing."
a.

D.

Ductwork Air Leakage Testing:


1.

2.

E.

CxA shall use this data to certify that prestart and startup activities have been
completed for systems, subsystems, and equipment installation.

Engineer will identify, for HVAC Subcontractor and CxA, portions of duct systems to have
ductwork air leakage testing. Ductwork air leakage testing shall be performed according to
Division 15 Section "Metal Ducts," and shall be witnessed by the CxA.
On approval of preliminary ductwork air leakage testing report, the CxA shall coordinate
verification testing of ductwork air leakage testing. Verification testing shall include random
retests of portions of duct section tests, reported in preliminary ductwork air leakage testing
report. The HVAC Subcontractor shall perform tests using the same instrumentation (by
model and serial number) as for original testing; the CxA shall witness verification testing.

Verification of Final TAB Report:


1.
2.

3.

CxA shall select, at random, 10 percent of report for field verification.


CxA shall notify TAB Subcontractor 10 days in advance of the date of field verification;
however, notice shall not include data points to be verified. The TAB Subcontractor shall use
the same instruments (by model and serial number) that were used when original data were
collected.
Failure of an item is defined as follows:
a.

For all readings other than sound, a deviation of more than 10 percent.
1)

4.
F.

For sound pressure readings, a deviation of 3 dB.


background noise must be considered.)

(Note:

Variations in

Failure of more than 10 percent of selected items shall result in rejection of final TAB report.

If deficiencies are identified during verification testing, CxA shall notify the HVAC Subcontractor,
and shall take action to remedy the deficiency. Engineer shall review final tabulated checklists and
data sheets to determine if verification is complete and that system is operating according to the
Contract Documents.

HVAC COMMISSIONING REQUIREMENTS


Volume 2

01815 Page 5 of 7
May 2012

Saraya Aqaba
G.

3.3

Specifications

CxA shall certify that TAB Work has been successfully completed.

TESTING
A.

Test systems and intersystem performance after test checklists for systems, subsystems, and
equipment have been approved.

B.

Perform tests using design conditions whenever possible.


1.

2.
3.

C.

Simulate conditions by imposing an artificial load when it is not practical to test under design
conditions and when written approval for simulated conditions is received from CxA. Before
simulating conditions, calibrate testing instruments. Set and document simulated conditions
and methods of simulation. After tests, return settings to normal operating conditions.
Alter set points when simulating conditions is not practical and when written approval is
received from CxA.
Alter sensor values with a signal generator when design or simulating conditions and altering
set points are not practical. Do not use sensor to act as signal generator to simulate conditions
or override values.

Scope of HVAC Subcontractor Testing:


1.

2.

Testing scope shall include entire HVAC installation, from central equipment for heat
generation and refrigeration through distribution systems to each conditioned space. It shall
include measuring capacities and effectiveness of operational and control functions.
Test all operating modes, interlocks, control responses, responses to abnormal or emergency
conditions, and verify proper response of building automation system controllers and sensors.

D.

Detailed Testing Procedures: CxA, with HVAC Subcontractor, TAB Subcontractor, and HVAC
Instrumentation and Control Subcontractor, shall prepare detailed testing plans, procedures, and
checklists for HVAC systems, subsystems, and equipment.

E.

Boiler Testing and Acceptance Procedures: Testing requirements are specified in Division 15 boiler
Sections. CxA shall review and comment on submittals, test data, inspector record, and boiler
certification and shall compile information for inclusion in systems manual.

F.

HVAC Instrumentation and Control System Testing:


1.

2.

G.

Field testing plans and testing requirements are specified in Division 15 Sections "HVAC
Instrumentation and Controls" and "Sequence of Operation." The CxA, HVAC Subcontractor,
and the HVAC Instrumentation and Control Subcontractor shall collaborate to prepare testing
plans.
CxA shall convene a meeting of appropriate entities to review test report of HVAC
instrumentation and control systems.

Pipe cleaning, flushing, hydrostatic tests, and chemical treatment requirements are specified in
Division 15 piping Sections. HVAC Subcontractor shall prepare pipe system cleaning, flushing, and
hydrostatic testing. CxA shall review and comment on plan and final reports. CxA shall certify that
pipe cleaning, flushing, hydrostatic tests, and chemical treatment have been completed. Plan shall
include the following:
1.

2.
3.
4.

Sequence of testing and testing procedures for each section of pipe to be tested, identified by
pipe zone or sector identification marker. Markers shall be keyed Drawings for each pipe
sector showing the physical location of each designated pipe test section. Drawings keyed to
pipe zones or sectors shall be formatted to allow each section of piping to be physically
located and identified when referred to in pipe system cleaning, flushing, hydrostatic testing,
and chemical treatment plan.
Description of equipment for flushing operations.
Minimum flushing water velocity.
Tracking checklist for managing and ensuring that all pipe sections have been cleaned,
flushed, hydrostatically tested, and chemically treated.

HVAC COMMISSIONING REQUIREMENTS


Volume 2

01815 Page 6 of 7
May 2012

Saraya Aqaba
H.

Energy Supply System Testing: HVAC Subcontractor shall prepare a testing plan to verify
performance of systems and equipment. Plan shall include the following:
1.

2.
I.

Sequence of testing and testing procedures for each equipment item and pipe section to be
tested, identified by pipe zone or sector identification marker. Markers shall be keyed to
Drawings for each pipe sector showing the physical location of each designated pipe test
section. Drawings keyed to pipe zones or sectors shall be formatted to allow each section of
piping to be physically located and identified when referred to in system testing plan.
Tracking checklist for managing and ensuring that all pipe sections have been tested.

Heat-Generation System Testing: HVAC Subcontractor shall prepare a testing plan to verify
performance of boilers and auxiliary equipment. Plan shall include the following:
1.

2.
J.

Specifications

Sequence of testing and testing procedures for each item of equipment and section of pipe to
be tested, identified by identification marker. Markers shall be keyed to Drawings for each
pipe sector showing the physical location of each item of equipment and pipe test section.
Drawings shall be formatted to allow each item of equipment and section of piping to be
physically located and identified when referred to in the system testing plan.
Tracking checklist for managing and ensuring that all pipe sections have been tested.

HVAC Distribution System Testing: HVAC Subcontractor shall prepare a testing plan to verify
performance of air, steam, and hydronic distribution systems; special exhaust; and other distribution
systems. Include HVAC terminal equipment and unitary equipment. Plan shall include the
following:
1.

2.

Sequence of testing and testing procedures for each item of equipment and section of pipe to
be tested, identified by identification marker. Markers shall be keyed to Drawings showing
the physical location of each item of equipment and pipe test section. Drawings shall be
formatted to allow each item of equipment and section of piping to be physically located and
identified when referred to in the system testing plan.
Tracking checklist for managing and ensuring that all pipe sections have been tested.

K.

Vibration and Sound Tests: HVAC Subcontractor shall prepare testing plans to verify performance
of vibration isolation and seismic controls. CxA shall witness and certify tests and inspections.

L.

Deferred Testing:
1.

2.

M.

If tests cannot be completed because of a deficiency outside the scope of the HVAC system,
the deficiency shall be documented and reported to Engineer. Deficiencies shall be resolved
and corrected by appropriate parties and test rescheduled.
If the testing plan indicates specific seasonal testing, appropriate initial performance tests shall
be completed and documented and additional tests scheduled.

Testing Reports:
1.
2.

3.
4.

Reports shall include measured data, data sheets, and a comprehensive summary describing
the operation of systems at the time of testing.
Include data sheets for each controller to verify proper operation of the control system, the
system it serves, the service it provides, and its location. For each controller, provide space
for recording its readout, the reading at the controller's sensor(s), plus comments. Provide
space for testing personnel to sign off on each data sheet.
Prepare a preliminary test report. Deficiencies will be evaluated by Engineer to determine
corrective action. Deficiencies shall be corrected and test repeated.
If it is determined that the system is constructed according to the Contract Documents,
Engineer will decide whether modifications required to bring the performance of the system to
the OPR and BoD documents shall be implemented or if tests will be accepted as submitted.
If corrective Work is performed, Engineer will decide if tests shall be repeated and a revised
report submitted.

END OF SECTION 01815


HVAC COMMISSIONING REQUIREMENTS
Volume 2

01815 Page 7 of 7
May 2012

Saraya Aqaba

Specifications

SECTION 01820 - DEMONSTRATION AND TRAINING

PART 1 - GENERAL

1.1

RELATED DOCUMENTS
A.

1.2

Drawings and general provisions of the Contract, including General and Particular Conditions and
other Division 1 Specification Sections, apply to this Section.

SUMMARY
A.

This Section includes administrative and procedural requirements for instructing Employer's and
Operators personnel, including the following:
1.
2.
3.

B.

Related Sections include the following:


1.
2.

1.3

Demonstration of operation of systems, subsystems, and equipment.


Training in operation and maintenance of systems, subsystems, and equipment.
Demonstration and training videotapes.

Division 1 Section "Project Management and Coordination" for requirements for preinstruction conferences.
Divisions 2 through 16 Sections for specific requirements for demonstration and training for
products in those Sections.

SUBMITTALS
A.

Instruction Program: Submit four copies of outline of instructional program for demonstration and
training, including a schedule of proposed dates, times, length of instruction time, and instructors'
names for each training module. Include learning objective and outline for each training module.
1.

At completion of training, submit four complete training manual(s) for Engineers,


Employer's, and Operators use.

B.

Qualification Data: For instructor.

C.

Attendance Record: For each training module, submit list of participants and length of instruction
time.

D.

Evaluations: For each participant and for each training module, submit results and documentation of
performance-based test.

E.

Demonstration and Training Videotapes: Submit four copies within seven days of end of each
training module.
1.

Identification: On each copy, provide an applied label with the following information:
a.
b.
c.
d.
e.
f.
g.

Name of Project.
Name and address of photographer.
Name of Employer.
Name of Engineer.
Name of Contractor.
Date videotape was recorded.
Description of vantage point, indicating location, direction (by compass point), and
elevation or story of construction.

DEMONSTRATION AND TRAINING


Volume 2

01820 1 of 5
May 2012

Saraya Aqaba
2.

1.4

Specifications
Transcript: Prepared on A4 paper, punched and bound in heavy-duty, 3-ring, vinyl-covered
binders. Mark appropriate identification on front and spine of each binder. Include a cover
sheet with same label information as the corresponding videotape. Include name of Project
and date of videotape on each page.

QUALITY ASSURANCE
A.

Facilitator Qualifications: A firm or individual experienced in training or educating maintenance


personnel in a training program similar in content and extent to that indicated for this Project, and
whose work has resulted in training or education with a record of successful learning performance.

B.

Instructor Qualifications: A factory-authorized service representative, complying with requirements


in Division 1 Section "Quality Requirements," experienced in operation and maintenance procedures
and training.

C.

Photographer Qualifications:
construction projects.

D.

Pre-instruction Conference: Conduct conference at Project site to comply with requirements in


Division 1 Section "Project Management and Coordination." Review methods and procedures related
to demonstration and training including, but not limited to, the following:
1.
2.
3.
4.

1.5

A professional photographer who is experienced photographing

Inspect and discuss locations and other facilities required for instruction.
Review and finalize instruction schedule and verify availability of educational materials,
instructors' personnel, audiovisual equipment, and facilities needed to avoid delays.
Review required content of instruction.
For instruction that must occur outside, review weather and forecasted weather conditions and
procedures to follow if conditions are unfavorable.

COORDINATION
A.

Coordinate instruction schedule with Employer's and Operators operations. Adjust schedule as
required to minimize disrupting Employer's and Operators operations.

B.

Coordinate instructors, including providing notification of dates, times, length of instruction time,
and course content.

C.

Coordinate content of training modules with content of approved emergency, operation, and
maintenance manuals. Do not submit instruction program until operation and maintenance data has
been reviewed and approved by Engineer.

PART 2 - PRODUCTS

2.1

INSTRUCTION PROGRAM
A.

Program Structure: Develop an instruction program that includes individual training modules for each
system and equipment not part of a system, as required by individual Specification Sections, and as
follows:
1.
2.
3.
4.
5.
6.
7.
8.

Fire Fighting Pumps and Sprinkler System.


Chilled Water and Hot Water Systems with Primary and Secondary Pumps
Conveying systems
Air Handling Units
Domestic Water Boosters
Electrical service and distribution, including Switchboards, Panelboards, Uninterruptible
Power Supplies and motor controls.
Communication Systems
Fire Alarm System

DEMONSTRATION AND TRAINING


Volume 2

01820 2 of 5
May 2012

Saraya Aqaba
9.
10.
B.

Specifications
Building Management System
Emergency Lighting Source

Training Modules: Develop a learning objective and teaching outline for each module. Include a
description of specific skills and knowledge that participant is expected to master. For each module,
include instruction for the following:
1.

Basis of System Design, Operational Requirements, and Criteria: Include the following:
a.
b.
c.
d.
e.
f.
g.
h.

2.

Documentation: Review the following items in detail:


a.
b.
c.
d.
e.
f.
g.

3.

Startup procedures.
Equipment or system break-in procedures.
Routine and normal operating instructions.
Regulation and control procedures.
Control sequences.
Safety procedures.
Instructions on stopping.
Normal shutdown instructions.
Operating procedures for emergencies.
Operating procedures for system, subsystem, or equipment failure.
Seasonal and weekend operating instructions.
Required sequences for electric or electronic systems.
Special operating instructions and procedures.

Adjustments: Include the following:


a.
b.
c.
d.

6.

Instructions on meaning of warnings, trouble indications, and error messages.


Instructions on stopping.
Shutdown instructions for each type of emergency.
Operating instructions for conditions outside of normal operating limits.
Sequences for electric or electronic systems.
Special operating instructions and procedures.

Operations: Include the following, as applicable:


a.
b.
c.
d.
e.
f.
g.
h.
i.
j.
k.
l.
m.

5.

Emergency manuals.
Operations manuals.
Maintenance manuals.
Project Record Documents.
Identification systems.
Warranties and bonds.
Maintenance service agreements and similar continuing commitments.

Emergencies: Include the following, as applicable:


a.
b.
c.
d.
e.
f.

4.

System, subsystem, and equipment descriptions.


Performance and design criteria if Contractor is delegated design responsibility.
Operating standards.
Regulatory requirements.
Equipment function.
Operating characteristics.
Limiting conditions.
Performance curves.

Alignments.
Checking adjustments.
Noise and vibration adjustments.
Economy and efficiency adjustments.

Troubleshooting: Include the following:

DEMONSTRATION AND TRAINING


Volume 2

01820 3 of 5
May 2012

Saraya Aqaba

Specifications
a.
b.

7.

Maintenance: Include the following:


a.
b.
c.
d.
e.
f.
g.

8.

Diagnostic instructions.
Test and inspection procedures.

Inspection procedures.
Types of cleaning agents to be used and methods of cleaning.
List of cleaning agents and methods of cleaning detrimental to product.
Procedures for routine cleaning
Procedures for preventive maintenance.
Procedures for routine maintenance.
Instruction on use of special tools.

Repairs: Include the following:


a.
b.
c.
d.
e.

Diagnosis instructions.
Repair instructions.
Disassembly; component removal, repair, and replacement; and reassembly
instructions.
Instructions for identifying parts and components.
Review of spare parts needed for operation and maintenance.

PART 3 - EXECUTION

3.1

PREPARATION
A.

Assemble educational materials necessary for instruction, including documentation and training
module. Assemble training modules into a combined training manual.

B.

Set up instructional equipment at instruction location.

3.2

INSTRUCTION
A.

Facilitator: Engage a qualified facilitator to prepare instruction program and training modules, to
coordinate instructors, and to coordinate between Contractor and Engineer, Employer, and Operators
for number of participants, instruction times, and location.

B.

Engage qualified instructors to instruct Employer's and Operators personnel to adjust, operate, and
maintain systems, subsystems, and equipment not part of a system.
1.
2.
3.

C.

Employer will furnish an instructor to describe basis of system design, operational


requirements, criteria, and regulatory requirements.
Employer will furnish an instructor to describe Employer's and Operators operational
philosophy.
Engineer will furnish Contractor with names and positions of participants.

Scheduling: Provide instruction at mutually agreed on times. For equipment that requires seasonal
operation, provide similar instruction at start of each season.
1.

Schedule training with Employer and Operators, through Engineer, with at least seven days'
advance notice.

D.

Evaluation: At conclusion of each training module, assess and document each participant's mastery of
module by use of a demonstration performance-based test.

E.

Cleanup: Collect used and leftover educational materials and give to Engineer. Remove instructional
equipment. Restore systems and equipment to condition existing before initial training use.

DEMONSTRATION AND TRAINING


Volume 2

01820 4 of 5
May 2012

Saraya Aqaba
3.3

Specifications

DEMONSTRATION AND TRAINING VIDEOTAPES


A.

General: Engage a qualified commercial photographer to record demonstration and training


videotapes.
Record each training module separately. Include classroom instructions and
demonstrations, board diagrams, and other visual aids, but not student practice.
1.

At beginning of each training module, record each chart containing learning objective and
lesson outline.

B.

Videotape Format: Provide high-quality VHS color videotape in full-size cassettes.

C.

Recording: Mount camera on tripod before starting recording, unless otherwise necessary to show
area of demonstration and training. Display continuous running time.

D.

Narration: Describe scenes on videotape by audio narration by microphone while videotape is


recorded. Include description of items being viewed. Describe vantage point, indicating location,
direction (by compass point), and elevation or story of construction.

E.

Transcript: Provide a typewritten transcript of the narration. Display images and running time
captured from videotape opposite the corresponding narration segment.

END OF SECTION 01820

DEMONSTRATION AND TRAINING


Volume 2

01820 5 of 5
May 2012