Professional Documents
Culture Documents
Centre, Hyderabad
General Information:
Client: Microsoft India Development Centre
City: Hyderabad
Climate: Hot & Dry
Operational schedule 10 hours, 5 working days in a week
Area of the building: 55,741m (out of which 45,057 m - conditioned area, 10,683 m - nonconditioned area)
Building Design
Orientation
Window
Walls
All blocks - 400mm block with 25mm thick water repellant coating, 50mm thick air gap & 40mm thick
stone cladding
Roof
Building Lighting
Day lighting
Glazed Atrium for the natural daylight (U-Value: 5.7 W/sq m deg K and SC of 0.53)
Abundance of daylight is available in the atrium which is completely day lighted zone and no
artificial lights are
required during the daytime in the atrium
Natural light is available in the circulation areas at the periphery of the building
Lighting system
Daylight controls
the
illuminance levels as required
COP of the water cooled chillers is 6.6 at ARI condition and that of the air cooled ones is 3.23,
which is better than ECBC recommended values of 6.3 and 3.05 respectively
Rated Sqmt/TR 19
Air cooling towers and closed circuit fluid coolers have either two speed motors, pony motors, or
variable speed drives controlling the fans
The table below summarizes the calibrated existing ECBC model case, conventional case generated over
the existing building in hot & dry climate zone.
Building
Lighting
Power
density
Controls
Occupancy sensors
No controls or sensors
Parameters
Building
orientation
Building
Envelope
Building
Chiller
Energy
performance 150
Index
208
The conventional case was run by incorporating low energy solar passive design strategies on the
annual electricity consumption (kWh), electric load (kW) and cooling demand (TR) of the building.
Parameter comparison
Conventional case
Electrical load
Base case
Cooling Load
Base case
EPI
Base case
Parameter comparison
Conventional case
Electrical load
Base case
Cooling Load
Base case
EPI
Base case
Parameter comparison
Conventional case
Electrical load
Base case
Cooling Load
Base case
EPI
Base case
Impact of ECBC, Low energy strategies, and ECBC+low energy strategies on conventional
case for Microsoft building, Hot and Dry climate
The above graph shows the variation in the Electrical load (kW), Coil load (TR) and EPI (energy
performance index) for all the cases.
The below table gives the comparison of the impact of ECBC, Low energy strategies, and ECBC + low
energy strategies on conventional case for Microsoft building for a composite climate.
Parameter
comparison
Electrical
load
Coil Load
EPI
ECBC+Low
energy
strategy
17% less than 35% less than 41% less than
the
the
the
conventional conventional conventional
case
case
case
5% less than
the
conventional
case
Base case
ECBC case
conventional
case
conventional
case
conventional
vase
conventional
case