Inspection Test Record

M07A Coupling Alignment


SOUTH ACIS

Client: Murphy Sarawak Oil Ltd.

Date: 21-Feb-2013

TagNo:

Description:

System:

Sub System:

SubSubSystem:

Package:

Area:

Location:

Drawing Ref No:


Manufacturer:
SerialNo:
Item
01
02
03
04
05
06
07
08
09
10
11

12
13
14
15
16
17

Model:

Type:

Description
Check vendors instruction, dossier, associated equipment catalogue and test certificate
are provided.
Check equipment for any damage or sign of lack of preservation.
Nameplate is provided and details are correct in accordance with the data sheet.
Check location is correct according to installation drawing and manufacturers instruction.
Obtain manufacturer's figures for coupling alignment and record on Table 1
Confirm pipework is complete and aligned. *W*
Check the condition of all holding down and jacking bolts and ensure all shim material is
stainless steel
Loosen off all pipework to the driven equipment and carry out soft foot check
Check that the spacer, bolts and guards are all preserved, labelled correctly and stored in
warehouse/store.
Check and record the free length of the coupling spacer on sheet 4.
Set the shafts in their correct running position, (paying particular attention to magnetic
centre if applicable), and then record the distance between the coupling hub flange faces
(D.B.F.F.) on sht 4
Confirm radial concentricity of each half coupling is according to specification, ref. Fig. 2
(sheet 2).
Record clock readings on sht 4, section 1 Uncoupled Pipework Loose sheet. *W*
Check axial alignments as per Fig. 3 (sht 2).
Record clock readings on sht 4, section 2 Uncoupled Pipework Loose sheet. *W*
Check radial concentricity as per Fig. 4 (sht 3).
Record clock readings on sheet 4, section 3 Uncoupled Pipework Loose sheet. *W*
Tighten all pipework then repeat items 8 to 10
Record results in appropriate sections of Uncoupled Pipework Tight (sht 5) and confirm
that results comply with manufacturers specifications
If the manufacturer stipulated any special requirements record the results on sheet 6 and
confirm they complied with the manufacturers specifications.

NA

OK

PL

Output /Remarks

Note:
*W* MOC rep. Witness points
___________________________________________________________________________________________________________________

Completed By Construction
Signature:
Print Name:
Date of Signing:
Printed by: Soh, Gerald. 21-Feb-2013 16:36, (ID=28922).

Certified By QA/QC

Accepted By BDEWC COMM.

Inspection Test Record


M07A Coupling Alignment
SOUTH ACIS

Client: Murphy Sarawak Oil Ltd.

Date: 21-Feb-2013

TagNo:

Description:

System:

Sub System:

SubSubSystem:

Package:

Area:

Location:

Drawing Ref No:

Completed By Construction
Signature:
Print Name:
Date of Signing:
Printed by: Soh, Gerald. 21-Feb-2013 16:36, (ID=28922).

Certified By QA/QC

Accepted By BDEWC COMM.

Inspection Test Record


M07A Coupling Alignment
SOUTH ACIS

Client: Murphy Sarawak Oil Ltd.

Date: 21-Feb-2013

TagNo:

Description:

System:

Sub System:

SubSubSystem:

Package:

Area:

Location:

Drawing Ref No:

Completed By Construction
Signature:
Print Name:
Date of Signing:
Printed by: Soh, Gerald. 21-Feb-2013 16:36, (ID=28922).

Certified By QA/QC

Accepted By BDEWC COMM.

Inspection Test Record


M07A Coupling Alignment
SOUTH ACIS

Client: Murphy Sarawak Oil Ltd.

Date: 21-Feb-2013

TagNo:

Description:

System:

Sub System:

SubSubSystem:

Package:

Area:

Location:

Drawing Ref No:

Completed By Construction
Signature:
Print Name:
Date of Signing:
Printed by: Soh, Gerald. 21-Feb-2013 16:36, (ID=28922).

Certified By QA/QC

Accepted By BDEWC COMM.

Inspection Test Record


M07A Coupling Alignment
SOUTH ACIS

Client: Murphy Sarawak Oil Ltd.

Date: 21-Feb-2013

TagNo:

Description:

System:

Sub System:

SubSubSystem:

Package:

Area:

Location:

Drawing Ref No:

Completed By Construction
Signature:
Print Name:
Date of Signing:
Printed by: Soh, Gerald. 21-Feb-2013 16:36, (ID=28922).

Certified By QA/QC

Accepted By BDEWC COMM.

Inspection Test Record


M07A Coupling Alignment
SOUTH ACIS

Client: Murphy Sarawak Oil Ltd.

Date: 21-Feb-2013

TagNo:

Description:

System:

Sub System:

SubSubSystem:

Package:

Area:

Location:

Drawing Ref No:

Completed By Construction
Signature:
Print Name:
Date of Signing:
Printed by: Soh, Gerald. 21-Feb-2013 16:36, (ID=28922).

Certified By QA/QC

Accepted By BDEWC COMM.

Inspection Test Record


M07A Coupling Alignment
SOUTH ACIS

Client: Murphy Sarawak Oil Ltd.

Date: 21-Feb-2013

TagNo:

Description:

System:

Sub System:

SubSubSystem:

Package:

Area:

Location:

Drawing Ref No:

Records of Special Requirements (if any):

_____________________________________________________________________________________________________________________
Remarks:

Completed By Construction
Signature:
Print Name:
Date of Signing:
Printed by: Soh, Gerald. 21-Feb-2013 16:36, (ID=28922).

Certified By QA/QC

Accepted By BDEWC COMM.