METHOD STATEMENT FOR

CONSTRUCTION OF PILE
CAP

DATE : 24-OCT15
REV : 01

METHOD OF STATEMENT
CONSTRUCTION OF PILING WORKS

ISSUE DETAILS
REVISION

DETAILS

PAGES

DATE

00

FIRST ISSUE

11

04 July 2015

01

RE-ISSUE 1

08

24 October 2015

JOE P S
PROJECT ENGINEER
PREPARED BY

JAYA KUMAR RAMAN


HSE ENGINEER
HSE REVIEW

SR. PROJECT MANAGER


REVIEWED BY

TABLE OF CONTENTS

1|Page

METHOD STATEMENT FOR


CONSTRUCTION OF PILE
CAP

1.

DATE : 24-OCT15
REV : 01

Purpose
2.

Scope of Work

3.

References:

4.

Preparation

5.

Resources

6.

Equipment

7.

Roles & Responsibility

8. Safety Precautions
9. Control Measures
10.
11.
12.
13.

1.0

Work Methodology
Inspection and Testing
Related Forms
Attachments

Objective
To provide a detailed description for Pilling works methods to ensure that the works are
performed in a safe, professional and controlled manner.

2.0 Scope of Works


This procedure covers Mobilization, Installation of piles, Inserting of Pre-Fabricated reinforcement
steel cages and Concreting of 600 mm Diameter piles.
3.0 References:
3.1 Contract Specification
3.2 All relevant applicable BS, ACI & ASTM codes for various civil works
3.3 Approved drawings
4.0 Preparation

2|Page

METHOD STATEMENT FOR


CONSTRUCTION OF PILE
CAP

DATE : 24-OCT15
REV : 01

Simplex will produce a programme of works such that client is aware of proposed area of works can
advise on logistical constraints imposed by other departments
5.0 Resources
All the materials used in permanent works shall be got approved before using at site.
Subcontractor approval shall be sought, if any subcontracting jobs involved in this scope.
Before starting of the work, it will be ensure that all the shop drawings are approved.
6.0

Equipment
Hydraulic drilling Rig
Skid steer loader
Crawler crane
Vibro Hammer with power pack
Rock Auger & Bucket
Casing pipes
Survey Equipments with necessary accessories
Welding Generator
Other Tools & Tackles
Hand Tools (If any)

7.0 Roles & Responsibilities:


Project Manager

bear overall responsibility for timely and quality execution of works


and ensures the effective use of resources and manpower

Project Engineer

To ensure all operations are in accordance with the relevant Project


contract specifications and this method statement and check the
accuracy of the works done by the site engineers

Site Engineer

To ensure that all earth works are carried out as per the approved shop
drawings. Coordinate with surveyors for accuracy of the work

QQA/QC Engineer

To ensure that the works are carried out as per the specifications.
Necessary tests are to be carried out for conformity and results are to be
provided to the Engineer.
To ensure that the works are carried out in a safe manner. Give necessary
guidelines to the workforce and facilitate safe working condition
To ensure to carry out the work with proper control over labors and
equipments. Coordinate with surveyor for accuracy of the work
To ensure that the work is being carried out accurately as per the approved
shop drawings in coordination with Site Engineers and Foreman

HSE Officer
Foreman
Surveyor

8.0 Safety Precautions:


8.1 Objective
To ensure that all safe practices are adhered to, as per standard operating procedures,
Safety Management Plan and contractual obligations while carrying out installation of Piles.
8.2 H.S.E Requirements:
The following are the H.S.E. requirements for Piling Works:

3|Page

METHOD STATEMENT FOR


CONSTRUCTION OF PILE
CAP

DATE : 24-OCT15
REV : 01

Proper barricades shall be provided for the working area to prevent unauthorized
access.
Warning signs shall be fixed near the excavation.
A signalman shall be deployed where the vision of the heavy equipments is hindering.
All employees shall be provided with safety induction before entering to site.
All vehicles entering the site shall be fit and adhere with safety requirements and preapproved TPC
All operators/ drivers should have current valid TPC.
All personnel shall wear PPEs i.e. safety jacket, safety shoes, helmet etc.
9.0
Control Measures
Ensure all permissions and consents have been obtained

Ensure approval status of QAP

Ensure approval status of this method statement has been received

Ensure approval status of ITP

Ensure maintain a system of records that permit verification of any issued report before and
after work
Ensure all plants are escorted to work site by qualified banksman

Ensure work area is cordoned off

Site briefings will be undertaken to induct all operatives in the detail of his method statement.
All personal attending will sign on the briefing sheet acknowledging they understand the
briefing given.
10.0 Work Methodology
Sequence of Piling Work
Prior to work
Pre-Mobilization Activities
Preliminary Survey
Mobilization and Erection of Plant, Equipments
Installation of Temporary Casing
Drilling/Boring
Installation of Reinforcement Cage with accessories
Pouring of Concrete
Demobilization of Plant & Equipments and Man powers.

10.1 Prior to work


A certificate or permit shall be obtained from the concerned authority, in accordance with all
the requirements of the Client.
Where applicable, temporary or permanent rerouting shall be provided for above ground and
underground services. For this purpose exploration pit shall be made for known underground
services
Internal traffic arrangements will be made in the work site area with the assistance of safety
personnel.
Remove all surface obstructions and unsuitable materials such as debris, rubble, shrubs,
hedges, trees, stumps, and roots and surface shall be levelled
Area shall be verified & cleared from underground services.

Survey the area & spot level readings of OGL recorded.

4|Page

METHOD STATEMENT FOR


CONSTRUCTION OF PILE
CAP

DATE : 24-OCT15
REV : 01

Care shall be taken so that the site clearance does not affect the foundation of existing
adjacent structures (if present).
Suitable temporary accesses shall be provided for all construction activities.

10.2 Pre-Mobilization Activities


The piling shall be carried out from the working platform level or dry levelled excavated
platform level as per suitability of execution. Pile setting out drawings shall be provided by
M/s EMAL and the survey for pile point shall be done by M/s EMAL.
Foundation layout drawing shall indicate working platform level, cut-off level, top of
reinforcement, reinforcement detailing and shall be duly approved by the Engineer / Client.
Approved Drawings shall be used for execution purpose. Pile length and rock socketing shall
also be indicated in the approved pile design.
Access to the work areas shall be kept unobstructed and clear at all the times so that the
work can be inspected by the Engineer/Client as and when required.
10.3 Survey
Pile points shall be established by main Contractor and marked using steel pins as per a preapproved setting-out drawing. Pile points locations and elevations shall be checked as
deemed necessary by the Engineer/Client. Pile shall not deviate 1 % in vertical direction and
shall not deviate more than 75mm in any direction on plan.
Existing underground services location shall be marked on the ground and reference points
shall be established and to be visible
10.4 Mobilization and Erection of Plant, Equipments
Crawler and Rig machine shall be mobilized to the location and erected st site. Third party
inspection will carried out prior to starting the activities
The rig will be positioned at pile point with required boring tool attached to the Kelly. Three
nos of offset pins will be positioned at a 2.0 to 3.0m distance, and at right angles to the pile
positions pin. (This is to ensure that position is not lost when casings are being placed.) They
will be used as reference points.
Verticality of mast shall be checked using controls in the operators cabin before
commencement of drilling operation and as and when deemed fit during drilling operation.
10.5 Installation of Temporary Casing
Depending upon the ground conditions, an initial pre-bore of suitable depth if required shall
be made before installation of temporary casing. Temporary casing of adequate length shall
be available at site. The Temporary Casing length may vary based on the subsurface
conditions.
The casing shall be installed by Vibro hammer or by rotary rig using casing adopter attached
to its rotary with reference to offset pins and spirit level to ensure that the pile shall not
deviate 1 % in vertical direction. Once the casing has achieved the required depth, final
checking will be made on this position. The casing top will generally be kept about 600 mm
above the ground level.

10.6 Drilling by Rig Machine

5|Page

METHOD STATEMENT FOR


CONSTRUCTION OF PILE
CAP

DATE : 24-OCT15
REV : 01

Installation/drilling of pile will be carried out only after the installation of temporary casing
pipes as described in the previous point no. 10.5
For boring through soil strata soil auger/ bucket will be used. As rock is encountered rock
auger/ rock bucket replaces the soil auger/ soil bucket and boring continues till termination
depth.
As soon as rock strata for socketing of piles are met with, the depth will be measured and
the boring through such rock will be continued up to a depth as per the pile design and
approved shop drawings.
At the termination level the pile bottom will be cleaned using cleaning bucket and the final
depth measurement and will be jointly recorded.

Tolerance: No piles shall not deviate more than 1 in 75 in vertical direction and shall not
deviate more than 75mm in plan in any direction.
Disposal of Excavated Material: Disposal of Excavated/Boring materials shall be disposed off
as per the project HSE Plan.
10.7 Reinforcement
Epoxy coated high yield strength deformed bars cages as per drawings shall be prepared in
accordance with a pre-approved shop drawing & BBS. Reinforcements shall be made up into
stiff cages using stiffener rings at suitable intervals, main reinforcement sufficiently well
wired at suitable points to withstand handling without any distortion or damage. They would
be placed in position and be supported away from the sides of the pile shaft by means of
spacer blocks. The steel reinforcement cages of required grade shall be provided by the
main contractor along with concrete cover blocks and PVC sleeves. Steel above cut off level
shall be protected from the concrete/weather by wrapping polythene sheet under the PVC
sleeves.
Normal lap between reinforcement cages will be as per specifications. The main reinforcing
steel would project for a length sufficient to develop bond above the cut off level of the pile
as shown in the approved shop drawings. The clear concrete cover to helical reinforcement
will be as per project specification and suitable approved spacer blocks will be provided at
intervals not exceeding 2m and wired to the helical / rings.
For ultrasonic integrity test on pile purpose, MS ducts will be jointed using welding and tied
together with reinforcement cage
10.8 Pouring of Concrete
Ready mix Concrete of C40 grade will be used for concreting of piles. Concrete of required
grade will be brought to the site by transit mixers. Concreting shall be poured in a single
continuous operation so there will not be any construction/cold joints.

The Record/Data Sheet of Concrete from RMC wherein the details such as name of RMC
supplier, transit mixer number, quantity of concrete received, batching time, concrete arrival
time shall be provided (one copy) to the Consultant/Client. The concrete will be placed in the
pile bore by tremmie method.
Casing position shall be checked and recorded before starting of concrete.
The tremmie pipe should clean and watertight throughout the length and shall not be less
than 150mm dia. for concrete work. The tremmie pipe shall be attached directly to the
concrete pump and is held by crane for lowering and lifting.

6|Page

METHOD STATEMENT FOR


CONSTRUCTION OF PILE
CAP

DATE : 24-OCT15
REV : 01

The tremmie pipe, attached to the concrete pump, will be lowered to the pile bore till toe of
the pile and raised approximately 200mm off the bottom (to allow concrete to flow).
Once sufficient concrete is pumped in, tremmie pipe will be gradually raised ensuring that
the tremmie pipe is always at a minimum of 3.0m into the concrete and a maximum of 6.0m
as per the provisions of ICE Specifications for Piling and Embedded Retaining Walls.
The lifting operation / movement of the tremmie pipe shall be in tandem with the lifting of
boom of the concrete pump. Pumping of concrete will continue until sound concrete is
observed.
The casing shall be withdrawn initially for 1.0 - 2.0m then the hose of the concrete pump
shall be inserted into the casing to complete the balance concreting.
Then, the crane with Vibro Hammer shall move to the pile location and the casing shall be
fully withdrawn.
The crane with casing shall be moved to next pile bore location where an initial pre bore was
done. The casing shall be placed in the pre bore and the above point 11 (Installation of
Temporary Casing) and point no. 15 (Formation of pile) shall be repeated.
Deviation
The permissible Deviation Level/ Tolerances for finished concrete works shall be as per site
requirements/ Specification/ drawings

12.0 Inspection and Testing:


All sampling and testing of concrete will be carried out as per the technical specification and
approved QA/QC Plan in accordance with relevant code provisions.
Before placing the concrete in the pile bore workability of concrete for each batch will be
checked using slump cone.
All pile testing shall be conducted at the frequency specified in Project Specifications. Test
piles will be selected by the Engineer at random and nominated immediately prior to casting.
Low strain Integrity Test shall be carried for 100% of installed piles in compliance with
specifications after 7 days of concreting
Ultrasonic Integrity Test on piles shall be carried out on 10% of Piles. ASTM codes shall be
followed.
Pile Static load test shall be carried on preliminary pile.
13.0 Related Forms:
1. Approved shop drawings.
2. Inspection request.
14.0 Attachments:
Risk Assessment
APPENDIX-A
METHOD STATEMENT- BRIEFING REGISTER
Project: EMIRATES ALUMINIUM SMELTER PROJECT
Date:

Time:

Sheet No:
Delivery by:

7|Page

METHOD STATEMENT FOR


CONSTRUCTION OF PILE
CAP

DATE : 24-OCT15
REV : 01

Induction Type: Task Specific (Detail): Construction of Anode Storage Building


# I have been briefed of the contents of the above method statement, site safety and piling work
requirements. I fully understand all that has been said to me. I have also had the opportunity to raise
any queries relating to the work that is to be carried out.

NO.

NAME (PRINT)

EMPLOYER
(PRINT)

SIGNATURE #

PAYROLL NO

1
2
3
4
5

8|Page