Contract Documents

Volume 2 - Bills of Quantities

Syrconsult- Consulting Engineers


Residential Building for
H.H. Sh. Seif Bin Mohammad Al Nahyan
Sector W-1 Plot No.C-10 Abu Dhabi U.A.E.

ITEM

DESCRIPTION

QTY UNIT

RATE
AED

AMOUNT
AED

DIVISION 9 - FINISHES

General

Finishes are measured as the net area in contact with support.


2

No deduction are made for voids of less than 0.25 m .

Rates shall include (but not be limited to) the following:


Surface preparation of and application to any surface of finishes,
backings, raking and angle cutting, work in any width or area,
any location and any height, fair joints of every description,
fair edges, rounded edges, chamfered edges, quirks arises
and the like, beaded edges, molded edges, ends, angles,
intersections and the like, all as required to execute
the works complete.

Total carried to Collection

Division 9 - Finishes

Page 1 / 15

Contract Documents
Volume 2 - Bills of Quantities

Syrconsult- Consulting Engineers


Residential Building for
H.H. Sh. Seif Bin Mohammad Al Nahyan
Sector W-1 Plot No.C-10 Abu Dhabi U.A.E.

ITEM

DESCRIPTION

QTY UNIT

RATE
AED

AMOUNT
AED

DIVISION 9 - FINISHES (ctd)

Section 092400 - Plastering


General
Works are measured net, as per the layout and units of the
Bills of Quantities, no other consideration shall be considered
with regard to any practice or local measurement custom.

Rates shall include (but not be limited to) the following:


Preparation of substrates, embedded items (corner beads, metal lath,
reference spots, stop beads and the like), admixtures and additives
where required, application to any surface indicated as per
required number of coats and tolerances,making good around inserts,
recesses and the like, curing, cutting and patching.
(Mix ratio as per specifications)

Self Levelling Cement Screed

10cm Self Levelling Cement Screed to Floors of MDB's, Transformer,

680

m2

Generator, H.V Room & Services Area.

Internal Plaster Type 1


Dash coat, base coat and finish coat,
Tolerance: 1 mm under a 3 m straight edge, Perfect angles and corners.

To Walls in all floors (Full walls height)

48,037

m2

To Staircases Walls as shown on drawings.

5,620

m2

To Walls in Basements as shown on drawings.

7,135

m2

Total carried to Collection

Division 9 - Finishes

Page 2 / 15

Contract Documents
Volume 2 - Bills of Quantities

Syrconsult- Consulting Engineers


Residential Building for
H.H. Sh. Seif Bin Mohammad Al Nahyan
Sector W-1 Plot No.C-10 Abu Dhabi U.A.E.

ITEM

DESCRIPTION

QTY UNIT

RATE
AED

AMOUNT
AED

DIVISION 9 - FINISHES (ctd)


Section 092400 - Plastering

Internal Plaster Type 2


Dash coat, base coat
Tolerance: 1 mm under a 3 m straight edge,
Perfect angles and corners.
A

5,334

m2

7,058

m2

To ceilings of Elect, Tel., Store, Pump, Generator, Transformer, H.V, MDB, 8,251

m2

To Walls in all floors where Antiseptic, Antifungus Semi Gloss


Finishes are applicable.

To O.T.S Walls as shown on drawings.

Ready Mix Surfacing Compound Plaster:

L.V, Generator, Service, Living, Bedroom, Lift room, MCC,


Chilled Water Pump Room, Filter Room & Boiler Room at Roof Floor.
D

To Ceiling in Basements as shown on drawings.

8,334

m2

To Staircases Ceilngs as shown on drawings

1,398

m2

Accessories

Galvanized metal lath, 200 mm wide bands, to walls,

Item

at intersection of concrete structure and masonry walls.


G

Galvanized angle beads, vertical and horizontal

Item

(Angle beads to be of aluminum in wet areas)

Total carried to Collection

Division 9 - Finishes

Page 3 / 15

Contract Documents
Volume 2 - Bills of Quantities

Syrconsult- Consulting Engineers


Residential Building for
H.H. Sh. Seif Bin Mohammad Al Nahyan
Sector W-1 Plot No.C-10 Abu Dhabi U.A.E.

ITEM

DESCRIPTION

QTY UNIT

RATE
AED

AMOUNT
AED

DIVISION 9 - FINISHES (ctd)

Section 092900 - Gypsum Board Ceilings


Gypsum board ceiling, made of 12 mm thick gypsum boards
mounted on suspended galvanized steel frame fixed to
ceiling by means of adjustable threaded rods, including joints
and connexions treatment with special filler on mesh band,
and all necessary details, such as edging, connexions,
openings and inserts for fixing electrical and A/C fixtures
and the like,as shown on drawings and instructed by Consultant.

12mm thick Decorative Suspended Decorative Gypsum Board with

60

m2

1,676

m2

3,230

m2

1,792

m2

Emulsion Paint as per Detailed Drawings in Building's Main Entrance


including Ready made Access Panels as per specifications.

12mm thick Decorative Suspended Gypsum Board with Emulsion Paint in


Lift Lobby & Lobby.
Ready made Access Panels as per specifications.

12mm thick Gypsum Board Bulk Head with Emulsion Paint as per
specifications in Living/Dining Room.

12mm thick Gypsum Board with Emulsion Paint as per specification in


Flat Entance, Corridor & Dress rooms.

Total carried to Collection

Division 9 - Finishes

Page 4 / 15

Contract Documents
Volume 2 - Bills of Quantities

Syrconsult- Consulting Engineers


Residential Building for
H.H. Sh. Seif Bin Mohammad Al Nahyan
Sector W-1 Plot No.C-10 Abu Dhabi U.A.E.

ITEM

DESCRIPTION

QTY UNIT

RATE
AED

AMOUNT
AED

DIVISION 9 - FINISHES

Section 093013 - Ceramic Tiles

General
Rates include adhesives, backing and bedding compounds
as indicated, application to any surface, coordination with
adjacent works, detailing, jointing, grouting and cleaning. Including
bedding compound, grouting, and all fixing materials and accessories.
CERAMIC TILES TO FLOOR

60x60/40x40 cm Ceramic Tiles-Floor for Retail Area in Ground Floor


PC Rate = AED 60/A.1

Ceramic Tiles to floors as shown on drawings,

99

m2

A.2

Allow for overhead and profit

99

m2

20x20/30x30 cm Ceramic Tiles-Floor for Bathrooms & Toilets:


PC Rate = AED 45/B.1

Ceramic Tiles to floors as shown on drawings,

1,104

m2

B.2

Allow for overhead and profit

1,104

m2

C.1 Ceramic Tiles to floors as shown on drawings,

1,398

m2

C.2 Allow for overhead and profit

1,398

m2

D.1 Ceramic Tiles to floors as shown on drawings,

1,808

m2

D.2 Allow for overhead and profit

1,808

m2

20x20/30x30 cm Ceramic Tiles-Floor for Kitchens & Pantries:


PC Rate = AED 50/-

20x20/30x30 cm Ceramic Tiles-Floor for WC's, Elect, Tel,


Room Service, Storage Area, Laundry, Store, Pump,
Maidroom, Maidbathroom, Garbage Room, Lift room, MCC,
Chilled Water Pump & Filter Room: PC Rate = AED 35/-

Total carried to Collection

Division 9 - Finishes

Page 5 / 15

Contract Documents
Volume 2 - Bills of Quantities

Syrconsult- Consulting Engineers


Residential Building for
H.H. Sh. Seif Bin Mohammad Al Nahyan
Sector W-1 Plot No.C-10 Abu Dhabi U.A.E.

ITEM

DESCRIPTION

QTY UNIT

RATE
AED

AMOUNT
AED

DIVISION 9 - FINISHES

Section 093013 - Ceramic Tiles

5x5/10x10/15x15/20x20 cm Porcelain Tiles to Floor of Health Club:


PC Rate = AED 100/2

A.1

Porcelain Tiles to Floors of Lockers, Showers, etc

131

A.2

Allow for overhead and profit

131

m2

60x60, 40x40 cm Graniti Porcelain Tiles-to Floors of


Lift-Lobby and Offices: PC Rate = AED 80/B.1

Graniti Porcelain Tiles to floors as shown on drawings,

1,955

m2

B.2

Allow for overhead and profit

1,955

m2

C.1 Graniti Porcelain Tiles to floors as shown on drawings,

12,071

m2

C.2 Allow for overhead and profit

12,071

m2

60x60, 40x40 cm Graniti Porcelain Tiles-to Floors of Flat Entrance,


Bedrooms, Corridors, Living/Dining, Dress Rooms, Balconies,
Massage & Reception Area:
PC Rate = AED 70/-

Total carried to Collection

Division 9 - Finishes

Page 6 / 15

Contract Documents
Volume 2 - Bills of Quantities

Syrconsult- Consulting Engineers


Residential Building for
H.H. Sh. Seif Bin Mohammad Al Nahyan
Sector W-1 Plot No.C-10 Abu Dhabi U.A.E.

ITEM

DESCRIPTION

QTY UNIT

RATE
AED

AMOUNT
AED

DIVISION 9 - FINISHES

Section 093013 - Ceramic Tiles

2 x 2 cm Pure Clear Glass Mosaic Tiles to Swimming Pool Floor:


PC Rate = AED 120/2

A.1

Pure Clear Glass Mosaic Tiles to floors as shown on drawings,

67

A.2

Allow for overhead and profit

67

m2

C.1 Ceramic Glazed Tiles as shown on drawings,

7,417

m2

C.2 Allow for overhead and profit

7,417

m2

D.1 Ceramic Glazed Tiles as shown on drawings,

5,920

m2

D.2 Allow for overhead and profit

5,920

m2

CERAMIC TILES TO WALLS

20x20/20x25/20x30/30x30cm Ceramic Glazed Tiles for


Bathrooms & Toilets Walls:

PC Rate = AED 45/-

20x20/20x25/20x30/30x30cm Ceramic Glazed Tiles for


Kitchens & Pantries Walls:

PC Rate = AED 50/-

Total carried to Collection

Division 9 - Finishes

Page 7 / 15

Contract Documents
Volume 2 - Bills of Quantities

Syrconsult- Consulting Engineers


Residential Building for
H.H. Sh. Seif Bin Mohammad Al Nahyan
Sector W-1 Plot No.C-10 Abu Dhabi U.A.E.

ITEM

DESCRIPTION

QTY UNIT

RATE
AED

AMOUNT
AED

DIVISION 9 - FINISHES (ctd)

Section 093013 - Ceramic Tiles

20x20/20x25/20x30/30x30cm Ceramic Glazed Tiles for


Garbage Room, Laundry & Maid Bathroom: PC Rate = AED 30/A.1

Ceramic Glazed Tiles as shown on drawings,

3,989

m2

A.2

Allow for overhead and profit

3,989

m2

5x5/10x10/15x15 cm Porcelain Tiles to Walls of Health Club:


PC Rate = AED 60/B.1

Porcelain Tiles to Walls of Lockers, Showers, etc

559

m2

B.2

Allow for overhead and profit

559

m2

C.1 Graniti Porcelain Tiles to Walls as shown on drawings,

6,148

m2

C.2 Allow for overhead and profit

6,148

m2

D.1 Pure Clear Glass Mosaic Tiles to Walls as shown on drawings,

108

m2

D.2 Allow for overhead and profit

108

m2

60x60, 40x40 cm Graniti Porcelain Tiles-Walls to Lift-Lobby:


PC Rate = AED 80/-

2 x 2 cm Pure Clear Glass Mosaic Tiles to Swimming Pool Walls:


PC Rate = AED 120/-

Total carried to Collection

Division 9 - Finishes

Page 8 / 15

Contract Documents
Volume 2 - Bills of Quantities

Syrconsult- Consulting Engineers


Residential Building for
H.H. Sh. Seif Bin Mohammad Al Nahyan
Sector W-1 Plot No.C-10 Abu Dhabi U.A.E.

ITEM

DESCRIPTION

QTY UNIT

RATE
AED

AMOUNT
AED

DIVISION 9 - FINISHES (ctd)

Skirting
A

80mm high Procelain base to match Flooring

14,175 LM

80mm high Ceramic base to match Flooring

1,828

LM

Wood Skirting

39

LM

Epoxy Paint Skirting

2,171

LM

3,077

m2

108

m2

279

m2

Section 095130 - Metal Ceilings

Suspension System
Aluminium False Ceilings, stove enamelled with polyester paint including
supporting all necessary details, such as inserts for fixing
Electrical and A/C fixtures and the like,
as shown on drawings and instructed by Consultant.

600x600mm Concealed Suspension Aluminium Plain Tiles False


Ceiling in Showers, Laundry, Kitchend, Lockers,
Plunge Pool, Steam, WC's & Corridor.

600x600mm Concealed Suspension Aluminium Perforated


Tiles False Ceiling in Reception, Gymnasium & Massage.

Combination of 300mm wide Aluminium Strip False Ceiling


and 12mm Water Resistant Gypsum Board with Emulsion Paint
in Offices at Mezzanine Floor.

Total carried to Collection

Division 9 - Finishes

Page 9 / 15

Contract Documents
Volume 2 - Bills of Quantities

Syrconsult- Consulting Engineers


Residential Building for
H.H. Sh. Seif Bin Mohammad Al Nahyan
Sector W-1 Plot No.C-10 Abu Dhabi U.A.E.

ITEM

DESCRIPTION

QTY UNIT

RATE
AED

AMOUNT
AED

DIVISION 9 - FINISHES (ctd)


Section 096340 - Stone Flooring

Rates include adhesives, backing and bedding compounds as indicated,


cement mortar (white or ordinary cement as required), application to any
surface, finishing as required, coordination with adjacent works, detailing,
grouting, cleaning. Provide Marble, cut to size as per detailed drawings.
The contractor must submit a sample of each type of marble
and shop drawings for approval.

Natural Marble to Floor, as per detailed drawings:

Flamed Granite Brown Nejran

233

m2

Polished Granite Brown Nejran

25

m2

3cm Thick Marble Tread & 2cm thick Marble Riser, 60x30x2cm

58

m2

159

m2

Thick Marble for Landing of Staircase-1


on Ground Floor, Mezz. Floor & First Floor.

Natural Marble to Walls, as per detailed drawings:

Selected Marble-Walls of Main Entrance, Lounge/Reception & Lift Lobby.

Total carried to Collection

Division 9 - Finishes

Page 10 / 15

Contract Documents
Volume 2 - Bills of Quantities

Syrconsult- Consulting Engineers


Residential Building for
H.H. Sh. Seif Bin Mohammad Al Nahyan
Sector W-1 Plot No.C-10 Abu Dhabi U.A.E.

ITEM

DESCRIPTION

QTY UNIT

RATE
AED

AMOUNT
AED

DIVISION 9 - FINISHES (ctd)

Section 096340 - Stone Flooring

Marble Counter (30 mm Thick)

Top Counter of Baths and Toilets are Granite/Marble


(PC Rate: 600/ Dhs./LM)

Counter

95 x 50cm at Ground Floor in WC

No.

Counter 125 x 50cm at Mezzanine Floor in WC

Nos.

Counter 136 x 50cm at Typical Floor in Bath 01

34

Nos.

Counter 185 x 50cm at Typical Floor in Bath 02

34

Nos.

Counter 146 x 50cm at Typical Floor in Bath 03

34

Nos.

Counter 146 x 50cm at Typical Floor in Bath 04

34

Nos.

Counter 146 x 50cm at Typical Floor in Bath 05

34

Nos.

Counter 150 x 50cm at Typical Floor in Bath 06

34

Nos.

Counter 116 x 50cm at Typical Floor in WC 01

34

Nos.

Counter 116 x 50cm at Typical Floor in WC 02

34

Nos.

Threshold (20 mm Thick)


To thresholds, Carrara/Crema Marfil marble, polished finish in baths,
toilets, kitchens, flats entrances, service rooms, ...etc.
K

10 cm wide,

23

LM

20 cm wide,

714

LM

Total carried to Collection

Division 9 - Finishes

Page 11 / 15

Contract Documents
Volume 2 - Bills of Quantities

Syrconsult- Consulting Engineers


Residential Building for
H.H. Sh. Seif Bin Mohammad Al Nahyan
Sector W-1 Plot No.C-10 Abu Dhabi U.A.E.

ITEM

DESCRIPTION

QTY UNIT

RATE
AED

AMOUNT
AED

DIVISION 9 - FINISHES (ctd)

Section 099100 - Painting

General

Rates include surface preparation as specified. Contractor shall


verify compliance of finishing products in surfaces.
Surface preparation shall be as follows:Rubbing and dusting of
cementitious and wood surfaces, where natural wood is to be
painted knots shall be burned. Shop primed metal surfaces.
Cementitious surfaces to be epoxy painted shall be acid etched
with a 5% muriatic acid solution then washed thoroughly with water.
Apply primer on prepared surfaces, clean and dry, apply putty
fillers to surfaces at a rate to ensure smoothness, uniformity
and complete coverage with pores filled.
Apply paints with brush, roller, spray, or other applicators
according to manufacturer's instructions and to Consultant's indications
Do not paint over dirt , rust , scale , grease, moisture,
and scuffed surfaces. Allow sufficient time between successive
coats to permit proper drying. Paint behind movable equipment same
as adjacent exposed surfaces.

Antiseptic & Antifungus Semi Gloss Paint


A

One coat of Antiseptic, Antifungus semi gloss finish to walls

5,334

m2

7,025

above False Ceiling as per specifications


B

One coat of Antiseptic, Antifungus semi gloss finish to ceiling

above False Ceiling as per specifications

Total carried to Collection

Division 9 - Finishes

Page 12 / 15

Contract Documents
Volume 2 - Bills of Quantities

Syrconsult- Consulting Engineers


Residential Building for
H.H. Sh. Seif Bin Mohammad Al Nahyan
Sector W-1 Plot No.C-10 Abu Dhabi U.A.E.

ITEM

DESCRIPTION

QTY UNIT

RATE
AED

AMOUNT
AED

DIVISION 9 - FINISHES (ctd)

Section 099100 - Painting

Use only one primer behind permanent equipment to be fixed.


Paint backsides of access panels and removable or hinged
covers to match exposed surfaces. Finish doors on tops,
bottoms,and side edges the same as exposed faces.

Apply as many finishing coats needed to obtain a final


homogeneous finished aspect, regardless the number
of coats specified hereunder.

Paint to comply with manufacturer's recommendations to


provide top quality application of commercial quality product.

Emulsion paint on cementitious surfaces

Emulsion paint over cement plaster surface to Walls

48,037

m2

Emulsion paint over compound plaster surface to Ceiling

8,251

m2

Total carried to Collection

Division 9 - Finishes

Page 13 / 15

Contract Documents
Volume 2 - Bills of Quantities

Syrconsult- Consulting Engineers


Residential Building for
H.H. Sh. Seif Bin Mohammad Al Nahyan
Sector W-1 Plot No.C-10 Abu Dhabi U.A.E.

ITEM

DESCRIPTION

QTY UNIT

RATE
AED

AMOUNT
AED

DIVISION 9 - FINISHES (ctd)


Section 099100 - Painting

Full Epoxy Paint

Epoxy Paint on 10cm Self Levelling Cement Screed to Floors of

680

Generator Room, Transformer Room, H.V Room & Services Area

Epoxy Flooring Paint System

Epoxy Flooring Paint System for Staircases as per Specifications

1,399

m2

Epoxy Flooring Paint System for Car Parkings as per Specifications

8,334

m2

Epoxy Flooring Paint System on Screed in Basements . (Color as per


Archtect's choice)

785

m2

Elastomeric Silk Finish , as per Specifications.

To Walls of Car Parking in all Besements

7,135

m2

To Ceilings of Car Parking in all Besements

8,334

m2

12,678

m2

1,398

m2

Acrylic Shield Fine Textured, as per Specification

100% pure Acrylic Shield Fine Textured System to Walls of


Staircases and OTS's

100% pure Acrylic Shield Fine Textured System to Ceilings of Staircases

Total carried to Collection

Division 9 - Finishes

Page 14 / 15

Contract Documents
Volume 2 - Bills of Quantities

Syrconsult- Consulting Engineers


Residential Building for
H.H. Sh. Seif Bin Mohammad Al Nahyan
Sector W-1 Plot No.C-10 Abu Dhabi U.A.E.

ITEM

DESCRIPTION

QTY UNIT

RATE
AED

AMOUNT
AED

DIVISION 9 - FINISHES (ctd)

Collection

Page 1 / 15
Page 2 / 15
Page 3 / 15
Page 4 / 15
Page 5 / 15
Page 6 / 15
Page 7 / 15
Page 8 / 15
Page 9 / 15
Page 10 / 15
Page 11 / 15
Page 12 / 15
Page 13 / 15
Page 14 / 15

Total carried to Summary

Division 9 - Finishes

Page 15 / 15